When a procuring agency takes corrective action in
response to a protest, our Office may recommend under 4
C.F.R. § 21.8(e) that the agency reimburse the protester
its reasonable protest costs where, based on the
circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a
clearly meritorious protest, thereby causing the protester
to expend unnecessary time and resources to make further
use of the protest process in order to obtain relief.
Pemco Aeroplex, Inc.--Recon. & Costs, B-275587.5,
B-275587.6, Oct. 14, 1997, 97-2 CPD ¶ 102 at 5. A protest
is clearly meritorious when a reasonable agency inquiry
into the protest allegations would show facts disclosing
the absence of a defensible legal position. The Real
Estate Ctr.--Costs, B-274081.7, Mar. 30, 1998, 98-1 CPD ¶
105 at 3. A GAO attorney will inform the parties through
outcome prediction ADR that a protest is likely to be
sustained only if he or she has a high degree of
confidence regarding the outcome; therefore, the
willingness to do so is generally an indication that the
protest is viewed as clearly meritorious, and satisfies
the “clearly meritorious” requirement for the purpose of
recommending reimbursement of protest costs. National
Opinion Research Ctr.--Costs, B-289044.3, Mar. 6, 2002,
2002 CPD ¶ 55 at 3.
In considering whether to recommend the reimbursement of
protest costs, we generally consider all issues concerning
the evaluation of proposals to be intertwined--and thus
not severable--and therefore, generally will recommend
reimbursement of the costs associated with both successful
and unsuccessful challenges to an evaluation. Coulson
Aviation (USA) Inc.; 10 Tanker Air Carrier, LLC--Costs,
B-406920.6, B-406920.7, Aug. 22, 2013, 2013 CPD ¶ 197 at
5. While we have, in appropriate cases, limited our
recommendation where a part of a successful protester’s
costs is allocable to a protest issue that is so clearly
severable as to essentially constitute a separate protest,
see, e.g., BAE Tech. Servs., Inc.--Costs, B-296699.3, Aug.
11, 2006, 2006 CPD ¶ 122 at 3; Interface Flooring Sys.,
Inc.--Claim for Attorneys’ Fees, B-225439.5, July 29,
1987, 87-2 CPD ¶ 106 at 2-3, limiting recovery of protest
costs in all cases to only those issues on which the
protester prevailed would be inconsistent with the broad,
remedial Congressional purpose behind the cost
reimbursement provisions of the Competition in Contracting
Act, 31 U.S.C. § 3554(c)(1)(A). Fluor Energy Tech. Servs.,
LLC--Costs, B‑411466.3, June 7, 2016, 2016 CPD ¶ 160 at 3.
The Corps argues that all issues other than the adequacy
of the source selection decision are not clearly
meritorious and are clearly severable from the concerns
identified in the outcome prediction ADR. We disagree.
First, Auxilio’s challenge to the adequacy of the source
selection decision was not the only clearly meritorious
protest issue. As stated above, the GAO attorney
conducting the ADR predicted that the protest would be
sustained because (1) the source selection decision was
improperly based upon a mechanical comparison of the
offerors’ adjectival ratings; (2) the SSA’s decision to
increase the technical ratings for three offerors,
including one awardee, was unreasonable; and (3) the
agency’s past performance evaluation failed to follow the
RFP evaluation criteria. Each of these issues was clearly
meritorious. Contrary to the agency’s assertion, our ADR
sustain prediction was not limited to the adequacy of the
source selection decision.
With regard to Auxilio’s challenges to the technical
evaluation of proposals--i.e., failure to credit Auxilio’s
proposal with various strengths under the solicitation’s
technical factor, and unequal treatment in the evaluation
of the offerors’ technical factor, including the
evaluation of offerors’ schedules--we consider these
issues to share common factual and legal bases with the
clearly meritorious protest grounds. In this regard, both
the meritorious and non-meritorious issues are intertwined
and interrelated with the agency’s flawed consideration of
the relative merits of proposals and the SSA’s improper
change in technical ratings. See Sevatec, Inc.--Costs,
B‑407880.3, June 27, 2013, 2013 CPD ¶ 163 at 3-4. As such,
we decline to sever the costs of any protest grounds.
(Auxilio FPM JV, LLC--Costs
B-415215.4: Apr 27, 2018)
Clearly Meritorious
The Awardee’s Experience
HESCO argued that JSF (and the other firm named in the
debriefing letter as the awardee) lacked the necessary
experience. Protest at 6-7. Specifically, as noted above,
the solicitation required the offeror to have at least 2
years of experience within the last 5 years manufacturing
earth-filled barriers for the government. RFP at 6. HESCO
argued that it had researched prior contracts of these two
firms and found that neither had at least 2 years’
experience with the government, within the last 5 years,
of manufacturing earth-filled barriers, as required by the
solicitation. Protest at 6-7.
In response, the agency noted that “all of the experience
documented by JSF’s quote concerns delivery of
earth-filled barriers.” Memorandum of Law (MOL) at 10
(citing AR Tabs 7g, JSF Past Performance Proposal, and 7k,
JSF Subcontractor’s Prior Contract). The agency concluded
that “[c]onsequently, to some degree, all that experience
concerns manufacture of those barriers.” Id. The agency
asserted, furthermore, that the awardee’s proposal
indicated that a subcontractor would be performing the
production of the barriers, and that the agency report
contained an ISO 9001-2008 certification for that
subcontractor which “documents that [the subcontractor]
produces barriers, fences, walls, and kits for welded
gabions, among other products.” MOL at 10 (citing AR, Tab
7a, ISO 9001-2008 Certification). That certification,
however, expired in 2015. AR, Tab 7a, ISO 9001-2008
Certification.
The record here shows that the awardee’s experience was
with the delivery of, and not the manufacture of,
earth-filled barriers. See MOL at 10 (noting that “all of
the experience documented by JSF’s quote concerns the
delivery of earth-filled barriers”). The proposed
manufacturing subcontractor possessed an expired required
certification. See AR, Tab 7A, ISO 9001-2008
Certification. The agency was therefore aware of the
awardee’s lack of manufacturing experience, and the agency
should have been aware that the awardee’s manufacturing
subcontractor lacked a current, required ISO
certification. Both of those facts were evident on the
face of the documents produced by the agency to defend
against this allegation. Because the agency lacked a
defensible legal position, we find clearly meritorious the
allegation that the agency’s unreasonably evaluated the
awardee’s experience.
The Awardee’s Past Performance
The protester also argued that the agency’s evaluation of
the awardee’s proposal under past performance was
inconsistent with the terms of the solicitation, given the
awardee’s minimal experience producing earth-filled
barriers. Protest at 7-8. As noted above, the solicitation
required offerors to provide the following documentation
to demonstrate past performance manufacturing earth-filled
barriers that have been delivered within the past 5 years:
company name, contract number, total dollar value,
contract award date, title of contract, description of
project, and period of performance. RFP at 7. The
protester asserted that the agency’s past performance
evaluation was limited to a review of the offeror’s status
in the System for Award Management (SAM). Protest at 8
(citing Protest Exh. A, Agency Debriefing, Oct. 6, 2017
(noting, under past performance, both the protester and
the awardee’s proposals were evaluated as “SAM Check No
Exclusion”)).
In response, the agency explained that the contracting
officer directed the contract specialist to determine
whether JSF had defaulted on any prior contracts or had
any exclusions. Contracting Officer’s Statement (COS) at 4
(citing AR, Tab 8, SAM Report on Awardee). No exclusions
were listed against JSF in SAM. Id. The agency also stated
that it reviewed information JSF provided on the past
performance of an affiliate and its subcontractor. MOL at
9. Further, the agency stated that it reviewed the past
performance information for JSF’s proposed subcontractor
that would be manufacturing the barriers, and concluded
the subcontractor had satisfactory or better performance
in the Past Performance Information Retrieval System. COS
at 4 (citing AR, Tab 11, Award Determination Summary, at
3).
The RFP advised offerors that the past performance
evaluation would be conducted in accordance with FAR
provision 52.212-1, which requires offerors to include
recent and relevant contracts for the same or similar
items. RFP at 8. The only contemporaneous evaluation of
the awardee’s past performance was an “A” notation next to
the prior experience requirement on the technical
evaluation report and a statement on the award memorandum
that the awardee “submitted past performance information.”
See AR, Tab 9i, Technical Evaluation Report; Tab 11, Award
Determination Summary, at 3. Nothing in the evaluation
record suggests that the agency’s past performance
evaluation was consistent with the FAR or solicitation.
Moreover, the record does not support the agency’s
assertion that the awardee provided “detailed information
on the contracts” of its affiliate or subcontractors. MOL
at 13. Rather, the awardee’s proposal failed to include
the information required under the RFP and instead
included the following information in its list of contract
references in the past performance portion of its
proposal: contractor name, program title, dates of
contract/order, customer, and total contract/order value.
See AR, Tab 7g, Awardee’s Past Performance Proposal.
Without the contract number and a brief description of the
work completed, this list of contract references provided
insufficient information on which to evaluate the
awardee’s past performance and determine whether it was
relevant.
The awardee also submitted copies of two delivery orders
awarded to JSF’s proposed manufacturing subcontractor,
which the agency states it used to assess JSF’s past
performance. COS at 3. As noted above, that
subcontractor’s ISO certification for manufacturing had
expired--a factor that should have been known to the
agency--but there is no evidence that the subcontractor’s
lack of a current certification was considered in the
evaluation. Nor is it clear from the face of the delivery
orders that the products delivered were similar to the
brand name or equal barrier being procured here. See AR,
Tab 7j, SPE8E6-15-D-0001, Delivery Order 0005, and AR, Tab
7k, SPE8E6-15-D-0001, Delivery Order 0010. Where, as here,
the awardee’s proposal fails to provide information
sufficient for the agency to conclude that the awardee’s
past performance was acceptable, and the contemporaneous
agency evaluation provides no basis on which to ascertain
the reasonableness of the evaluation, we find that the
agency had no defensible legal position.
Agency Evaluation of Awardee’s Proposed Products
The protester also argued that it reviewed the awardee’s
website and did not find any products that could meet the
salient characteristics of the solicitation. Protest at
9-10. The agency stated that JSF’s proposal included many
documents on product characteristics and that JSF’s
products met the salient characteristics listed in the
solicitation. COS at 5.
The RFP required the offeror to propose RAID or equal and
CART or equal products, both of which could be deployed in
a maximum of 60 seconds. RFP at 5. The awardee’s proposal
did not specify that either of its proposed products could
meet that requirement. Rather, the awardee described both
products as “rapid deployment.” See AR, Tab 16.a-01 REF a,
Awardee Spec Sheet at 1 (noting that the offered products
meet the salient characteristic of deployment in no more
than 60 seconds because they are “[r]apid deployment”
units). Nevertheless, the agency found that both products
offered by the awardee met the solicitation’s deployment
requirements. The awardee’s proposal offered no basis for
this evaluation finding.
In addition, the RFP required offerors to propose a RAID
or equal product that contained “[b]uilt rails inside for
easy deployment.” RFP at 5. The agency’s evaluation found
that the awardee’s proposed RAID or equal product met this
requirement where the proposal specification sheet
described the offered product as “easy to deploy by
pulling open, positioning and filling.” AR, Tab 16.a-01
REF d, Awardee Spec Sheet, at 1 (agency emphasis added to
awardee’s proposal). Again, the awardee’s proposal offered
no basis for this evaluation finding. The agency lacks a
defensible legal position where the awardee’s proposal, on
its face, fails to satisfy the objective solicitation
requirement of built rails inside, and where the agency’s
evaluation nevertheless finds the proposal in conformance
with the RFP’s requirements. This protest allegation also
was clearly meritorious.
The agency argues that the protester’s allegations could
not be clearly meritorious where GAO requested that the
Army respond to the protester’s comments. Opposition to
Request for Costs at 20-22. The agency’s reliance on
additional record development to demonstrate that
allegations were not clearly meritorious is misplaced.
While the decisions of our Office have stated that, as a
general rule, a protest is not clearly meritorious where
further record development was contemplated, the decisions
also explain that where warranted by the record, we will
grant a request for recommendation of the reimbursement of
costs even where further record development was
contemplated. See URS Fed. Servs., Inc.--Costs,
B-406140.4, July 17, 2012, 2012 CPD ¶ 223 at 4 (granting
request for reimbursement of costs where agency took
corrective action after the scheduling of a hearing);
Basic Commerce and Indus., Inc.--Costs, B-401702.3, Feb.
22, 2010, 2010 CPD ¶ 258 at 4 (same); Eagle Home Med.
Corp.--Costs, B-299821.3, Feb. 4, 2008, 2008 CPD ¶ 41 at 4
n.4 (same). Here, as discussed above, the agency had in
its possession documents upon which it relied to defend
against the initial protest allegations, and those
documents did not provide a legally defensible basis for
the agency’s position.
Undue Delay
Finally, here, we find that the agency’s corrective
action, taken after the filing of the agency report, was
unduly delayed. As noted, our Office generally considers
corrective action to be prompt if it is taken before the
due date for the agency report responding to the protest
but not prompt where it is taken after that date. See East
Coast Nuclear Pharmacy--Costs, supra, at 5-6. While the
agency asserts that it promptly took corrective action
before the agency’s supplemental report was due, we find
that a reasonable agency inquiry into the protester’s
initial protest would have led the agency to discover that
it had unreasonably evaluated the awardee’s proposal.
Accordingly, we conclude that the agency unduly delayed
taking corrective action in response to a clearly
meritorious protest. (HESCO
Bastion Ltd.--Costs B-415526.3: Apr 3, 2018)
Herren requests that our Office recommend that the
protester be reimbursed the reasonable costs of filing and
pursuing its initial and supplemental protests. Herren
argues that its protest grounds were clearly meritorious,
particularly its objection to the SSA’s imposition of a
cost risk to Herren’s proposal. Request for Costs at 1.
Herren further maintains that reimbursement of costs is
warranted because the Navy unduly delayed taking its
corrective action.
When a procuring agency takes corrective action in
response to a protest, our Office may recommend
reimbursement of protest costs where, based on the
circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a
clearly meritorious protest, thereby causing the protester
to expend unnecessary time and resources to make further
use of the protest process in order to obtain relief. 4
C.F.R. § 21.8(e); AAR Aircraft Servs.--Costs, B‑291670.6,
May 12, 2003, 2003 CPD ¶ 100 at 6. Thus, as a prerequisite
to our recommending the reimbursement of costs where a
protest has been settled by corrective action, the protest
must not only have been meritorious, but it also must have
been clearly meritorious, i.e., not a close question.
InfraMap Corp.--Costs, B‑405167.3, Mar. 26, 2012, 2012 CPD
¶ 123 at 3. A protest is clearly meritorious where a
reasonable agency inquiry into the protester’s allegations
would reveal facts showing the absence of a defensible
legal position. First Fed. Corp.--Costs, B‑293373.2, Apr.
21, 2004, 2004 CPD ¶ 94 at 2.
We find that reimbursement is not appropriate in this
case. In this regard, we disagree with the protester that
it raised clearly meritorious allegations in its initial
protest. More specifically, while the protester raised
some compelling concerns, particularly with respect to the
agency’s source selection decision, the protester’s
arguments necessitated a substantive response from the
agency for our Office to fully assess the merits of the
protest grounds. That is, in our view, the agency was not
without a defensible legal position. Indeed, because the
allegations raised, and the agency’s responses thereto,
presented a close question that warranted further research
and analysis to determine the merits of the issues
presented, the reimbursement of costs is not warranted.
See InfraMap Corp.--Costs, supra, at 4 (declining to
recommend reimbursement of protest costs where the matter
was a close call that would have required substantial
further analysis of the parties’ positions to determine
which party was correct). (Herren
Associates, Inc.--Costs B-414792.4: Nov 21, 2017)
Under our Bid Protest Regulations, if an agency decides to
take corrective action in response to a protest, our
Office may recommend that the agency pay the protester the
reasonable costs of filing and pursuing the protest,
including attorneys’ fees and consultant and expert
witness fees. 4 C.F.R. § 21.8(e). This does not mean that
costs should be reimbursed in every case in which an
agency decides to take corrective action; rather, a
protester should be reimbursed its costs where an agency
unduly delayed its decision to take corrective action in
the face of a clearly meritorious protest. NxGen Process
Grp. LLC‑‑Costs, B‑406650.2, May 24, 2012, 2012 CPD ¶ 163
at 2.
When an agency takes corrective action on or before the
due date set for receipt of the agency report, our Office
views such action as prompt and will not recommend the
reimbursement of costs. The Sandi–Sterling
Consortium--Costs, B‑296246.2, Sept. 20, 2005, 2005 CPD ¶
173 at 2-3; HSQ Tech.--Costs, B‑276050.2, June 25, 1997,
97‑1 CPD ¶ 228 at 2. As stated above, the Air Force took
corrective action in response to ITC’s protest before
submitting an agency report. Therefore, ITC’s request does
not meet our standard for recommending reimbursement of
protest costs and we agree with the Air Force that ITC is
not entitled to such costs. See NxGen Process Grp.
LLC‑‑Costs, supra; Air Force Opp’n to Req. at 1‑3.
ITC’s myriad arguments to the contrary provide no basis
for recommending reimbursement of protest cost. First,
contrary to ITC’s mistaken belief, it is not entitled to
recover costs for retaining counsel to represent ITC
during the debriefing. A protester’s actions taken prior
to filing its protest with our Office do not establish
that an agency unduly delayed its decision to take
corrective action in the face of a clearly meritorious
protest. See LORS Med. Corp.--Entitlement to Costs,
B‑270269.2, Apr. 2, 1996, 96‑1 CPD ¶ 171 at 2‑3. The
provisions in our Bid Protest Regulations providing for
the possibility of a recommendation that costs be
reimbursed where an agency takes corrective action in
response to a protest with our Office, are not intended to
ensure the fairness of agency‑level processes occurring
prior to the protest filing; rather, those provisions are
intended to ensure fair treatment of protesters who make
substantial investments of time and resources to pursue
clearly meritorious protests in this forum. Dellew Corp.,
B‑410159.4, Feb. 26, 2016, 2016 CPD ¶ 114 at 2, citing
Innovative Logistics Techniques, Inc.--Costs, B-289031.3,
Feb. 4, 2002, 2002 CPD ¶ 34 at 5.
In this respect, even were we to assume that it raised
clearly meritorious protest grounds, ITC would not be
entitled to reimbursement of protest costs here because it
was not required to expend unnecessary costs preparing
comments on a report since none was filed. See Singleton
Enters.‑‑GMT Mech., Joint Venture--Costs, B‑310454.3, Mar.
27, 2008, 2008 CPD ¶ 61 at 3‑4 (denying request for costs,
even though the protester presented a clearly meritorious
protest, where the agency did not unduly delay taking
corrective action since it did not submit an agency report
and the protester was thus not required to expend
unnecessary costs preparing comments on a report); Neal R.
Gross & Co., Inc.--Entitlement to Costs, B‑254033.4, Sept.
30, 1993, 93‑2 CPD ¶ 199 at 4 (denying protest where the
protester conceded that the corrective action was not
unduly delayed and the record shows that the protester was
not required to incur costs other than those associated
with its initial filing). In any event, the Air Force’s
decision to take corrective action does not, as ITC
insists, suggest that the protest was clearly meritorious
or that the agency violated procurement laws or
regulations. As our Office has frequently stated, the mere
fact that an agency decides to take corrective action does
not establish that a protest was clearly meritorious, let
alone that a statute or regulation has clearly been
violated. See SpectrumS4, LLC--Costs, B-408227.4, Aug. 26,
2013, 2013 CPD ¶ 200 at 3; Diligent Consulting,
Inc.--Costs, B‑299556.3, June 26, 2007, 2007 CPD ¶ 125 at
5.
As for ITC’s position that it should be able to recover
the initial costs of preparing and filing the protest,
regardless of whether the Air Force unduly delayed taking
corrective action, we have consistently denied requests
for costs based on such misguided arguments.
Instrumentation Lab. Co.--Req. for Decl. of Entitlement to
Costs, B‑246819.2, June 15, 1992, 92‑1 CPD ¶ 517 at 3. As
we have explained in a number of decisions, such an
approach would result in contracting agencies having to
pay protest costs in a large number of cases and have the
effect of discouraging agencies from taking corrective
action. Id.; LORS Med. Corp.--Entitlement to Costs, supra
(denying request for costs of initial protest filing,
despite the protester’s argument that the agency’s
improper actions “gave rise to the ‘protest process,’
leaving [the protester] no other choice but to incur the
cost of filing a protest in order to vindicate its right
to a proper evaluation and reasonable opportunity for
award.”); Purdy Corp.--Claim for Costs, B‑249067.2, Aug.
13, 1992, 92‑2 CPD ¶ 105 at 2‑3 (denying request for costs
where the protester did not assert that the agency delayed
taking corrective action, but claimed that the agency only
took corrective action as a result of the protest). The
imposition of costs is not intended as an award to
prevailing protesters or as a penalty to the agency, but
rather, is designed to encourage agencies to take prompt
action to correct apparent defects in competitive
procurements. Evergreen Flying Servs., Inc.--Costs,
B‑414238.10, Oct. 2, 2017, 2017 CPD ¶ 299 at 5.
In sum, since the Air Force took prompt corrective action
in response to ITC’s protest and the protest was not
clearly meritorious, ITC has not met the standard required
by our Office for a recommendation to reimburse its
protest costs. (Innovative
Technologies, Inc.--Costs B-415810.3: Mar 12, 2018)
When a procuring agency takes corrective action in
response to a protest, our Office may recommend
reimbursement of protest costs where, based on the
circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a
clearly meritorious protest, thereby causing the protester
to expend unnecessary time and resources to make further
use of the protest process in order to obtain relief. Bid
Protest Regulations, 4 C.F.R. § 21.8(e); AAR Aircraft
Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at
6. Thus, as a prerequisite to our recommending the
reimbursement of costs where a protest has been resolved
by corrective action, not only must the protest have been
meritorious, but it also must have been clearly
meritorious, i.e., not a close question. Overlook Sys.
Techs., Inc.--Costs, B-298099.3, Oct. 5, 2006, 2006 CPD ¶
184 at 6. A protest is "clearly meritorious" where a
reasonable agency inquiry into the protester's allegations
would reveal facts showing the absence of a defensible
legal position. Office Depot, Inc.--Costs, B-408850.2,
Feb. 25, 2014, 2014 CPD ¶ 85 at 5.
Here, we conclude, based on the record before us, that one
protest ground was clearly meritorious, and grant PSI's
request for reimbursement for the costs of filing and
pursuing the one protest ground. For the reasons that
follow, we recommend that the agency reimburse PSI its
reasonable costs for filing and pursuing its allegation
that the SEC's selection decision failed to consider the
underlying technical differences between offerors.
However, we do not recommend the reimbursement of PSI's
costs for filing and pursuing the other allegations.
Clearly Meritorious Protest Ground
PSI contends that its challenge to the SEC's tradeoff
decision was clearly meritorious. Request for
Reimbursement at 8-9. In its supplemental protest, PSI
argued that the SEC's selection decision improperly
focused on the offerors' adjectival ratings rather than on
the advantages and disadvantages of the offerors'
competing quotations. Protester's Comments & Supp. Protest
at 16. The SEC states that PSI's challenge to the award
decision was not clearly meritorious because the selection
official concurred with the technical evaluation report,
which provided detailed comments regarding the quality of
the quotations. SEC Objections to Reimbursement at 11.
Where, as here, a procurement conducted pursuant to FAR
subpart 8.4 provides for award on a "best-value" tradeoff
basis, it is the function of the source selection official
to perform a price/technical tradeoff, that is, to
determine whether one quotation's technical superiority is
worth its higher price. NikSoft Sys. Corp., B-406179, Feb.
29, 2012, 2012 CPD ¶ 104 at 7; InnovaTech, Inc., B-402415,
Apr. 8, 2010, 2010 CPD ¶ 94 at 6. Moreover, under the
minimum documentation requirements of FAR subpart 8.4,
documentation of the source selection rationale may be
limited, but it must be sufficient to show a reasonable
basis for any tradeoffs. FAR § 8.405-3(a)(7)(viii); SRA
Int'l, Inc.; NTT DATA Servs. Fed. Gov't, Inc., B-413220.4
et al., May 19, 2017, 2017 CPD ¶ 173 at 13.
Here, the record shows that although the best-value award
memorandum discusses some of the more outstanding features
in PAE's quotation, see, e.g., AR, Tab 16, Best-Value
Award Memorandum, at 8-9, the award memorandum is devoid
of any consideration of the strengths and significant
strengths in PSI's quotation, as would be appropriate
given PSI's lower price. With respect to PSI's quotation,
the award memorandum simply states, ‟Protection
Strategies' quote provided lower pricing and received an
overall rating of 'Acceptable'. However, Protection
Strategies' technical rating was two categories below PAE
Professional Services' rating (Outstanding)." Id. at 8.
Agencies are required to look behind the adjectival
ratings to consider a qualitative assessment of the
underlying technical differences among competing offers.
In this regard, evaluation ratings, whether numerical,
color, or adjectival, are merely guides for intelligent
decision making, and an agency's source selection decision
must rest upon a qualitative assessment of the underlying
technical differences among competing offers. Tiber Creek
Consulting, Inc., B-411550.4, B-411550.5, Jan. 6, 2016,
2016 CPD ¶ 15 at 6. The best-value memorandum does not
demonstrate that the source selection official performed a
price/technical tradeoff and looked behind the adjectival
ratings to assess the underlying technical differences of
PAE's and PSI's quotations.
The SEC argues that PSI's protest was not clearly
meritorious because the selection official relied on the
technical evaluation report, which provided sufficient
documentation of a tradeoff. SEC Objections to
Reimbursement at 11. Although a comparative assessment
might be made in the underlying documents upon which the
selection decision relies, or in the selection decision
itself, it must be documented and reviewable. M7 Aerospace
LLC, B-411986, B-411986.2, Dec. 1, 2015, 2016 CPD ¶ 100 at
5. Here, the final technical evaluation report contained a
listing of strengths and significant strengths in the
offerors' quotations, but did not contain a comparative
assessment upon which the selection official could rely.
The record contains no evidence of a comparative
assessment. Accordingly, we conclude that this protest
ground was clearly meritorious. (Protection
Strategies, Inc. B-414573.3: Nov 9, 2017)
Herai Alpha argues that it is entitled to reimbursement
because the protest was meritorious, as demonstrated by
the GAO attorney's views expressed during the ADR outcome
prediction conference call.
When a procuring agency takes corrective action in
response to a protest, our Office may recommend that the
agency reimburse the protester its reasonable protest
costs where, based on the circumstances of the case, we
determine that the agency unduly delayed taking corrective
action in the face of a clearly meritorious protest,
thereby causing protesters to expend unnecessary time and
resources to make further use of the protest process in
order to obtain relief. Pemco Aeroplex, Inc.--Recon. &
Costs, B-275587.5, B-275587.6, Oct. 14, 1997, 97-2 CPD ¶
102 at 5. A protest is clearly meritorious when a
reasonable agency inquiry into the protest allegations
would show facts disclosing the absence of a defensible
legal position. The Real Estate Ctr.--Costs, B-274081.7,
Mar. 30, 1998, 98-1 CPD ¶ 105 at 3. A GAO attorney will
inform the parties through outcome prediction ADR that a
protest is likely to be sustained only if he or she has a
high degree of confidence regarding the outcome;
therefore, the willingness to do so is generally an
indication that the protest is viewed as clearly
meritorious, and satisfies the "clearly meritorious"
requirement for the purpose of recommending reimbursement
of protest costs. National Opinion Research Ctr.--Costs,
B-289044.3, Mar. 6, 2002, 2002 CPD ¶ 55 at 3; Inter-Con
Sec. Sys., Inc.; CASS, a Joint Venture--Costs, B-284534.7,
B-284534.8, Mar. 14, 2001, 2001 CPD ¶ 54 at 3. As
discussed above, we explained during ADR that we found
clearly meritorious the protester's complaint that USAID
unreasonably determined that Herai Alpha was not a
responsible business.
With respect to whether the corrective action was taken
promptly, we consider corrective action to be prompt if it
is taken before the due date for the agency report
responding to the protest. However, we generally do not
consider it to be prompt where it is taken after that
date, including following outcome prediction ADR. CACI
Techs., Inc.--Costs, B-407923.3, Aug. 14 2014, 2014 CPD ¶
321 at 5; Burns & Roe Servs., Corp--Costs, B-310828.2,
Apr. 28, 2008, 2008 CPD ¶ 81 at 2 n.2. Here, since the
agency did not take corrective action until after it
submitted its agency report, we find that the agency
unduly delayed taking corrective action in response to
this meritorious protest.
We recommend that USAID reimburse Herai Alpha for the
costs of filing and pursuing its protest challenging the
agency's decision to eliminate Herai Alpha from the
competition as nonresponsible. Herai Alpha should submit
its certified claim, detailing the time spent and costs
incurred, directly to the agency within 60 days of its
receipt of this decision. 4 C.F.R. § 21.8(f)(1).
The request for reimbursement of costs is granted. (Herai
Alpha Construction--Costs B-414558.2: Sep 26, 2017)
AGS requests that the agency reimburse AGS the costs
associated with filing and pursuing its protest. The
protester argues that the agency unduly delayed the
implementation of its proposed corrective action despite
AGS’s clearly meritorious protest. For the reasons
discussed below, we deny the protester’s request.
Our Office may recommend that a protester be reimbursed
the costs of filing and pursuing a protest where the
contracting agency decides to take corrective action in
response to the protest. Bid Protest Regulations, 4 C.F.R.
§ 21.8(e). Such recommendations are generally based upon a
concern that an agency has taken longer than necessary to
initiate corrective action in the face of a clearly
meritorious protest, thereby causing protesters to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. QuanTech,
Inc.--Costs, B-278380.3, June 17, 1998, 98-1 CPD ¶ 165 at
2-3. This basis for the award of costs does not exist in
the instant protest, since the agency initiated corrective
action promptly, i.e., prior to the agency report due
date. See Veda Inc.--Entitlement to Costs, B-265809.2,
July 19, 1996, 96-2 CPD ¶ 27 at 2.
We may also recommend recovery of protest costs, however,
where an agency unduly delays, without adequate and
reasonable explanation, the implementation of the promised
corrective action that led to the dismissal of the earlier
protest. AdaRose Inc.--Protest & Costs, B-299091.2, Jan.
14, 2008, 2008 CPD ¶ 18 at 4. In assessing whether an
agency has unduly delayed the implementation of corrective
action, we do not examine the length of elapsed time in a
vacuum; instead we consider the reasonableness of the
agency’s actions during that time period, the agency’s
explanation for the delay, and whether performance of the
requirement continued during the delay. See Pemco Aeroplex,
Inc.--Recon. & Costs, B-275587.5, B-275587.6, Oct. 14,
1997, 97-2 CPD ¶ 102 at 7-8 (recommending the
reimbursement of costs where the agency provided no
meaningful explanation for its failure to take the first
step in its promised corrective action, and where
performance of the requirement continued during the
four-month delay); Commercial Energies, Inc.--Recon. &
Declaration of Entitlement to Costs, B-243718.2, Dec. 3,
1991, 91-2 CPD ¶ 499 at 6 (recommending the reimbursement
of costs where the agency provided no explanation for
waiting five months to implement its promised corrective
action, while performance was permitted to continue on the
protested contract).
Similarly, we may recommend the recovery of protest costs,
where an agency’s failure to promptly implement its
promised corrective action circumvents the goal of the bid
protest system established by the Competition in
Contracting Act, 31 U.S.C. § 3553 et seq.--that is, the
economic and expeditious resolution of bid protests.
Louisiana Clearwater, Inc.--Recon. & Costs, B-283081.4,
B-283081.5, Apr. 14, 2000, 2000 CPD ¶ 209 at 6; see also
SCB Solutions, Inc.--Recon., B-410450.2, Aug. 12, 2015,
2015 CPD ¶ 255 at 4-5 (granting reconsideration and
recommending the reimbursement of costs where the agency’s
actions resulted in the promised corrective action failing
to remedy the concerns raised in the protest). This is
particularly the case where the delay results in the
protester being put through the expense of subsequently
protesting the same protest issue again. See Envirosolve
LLC, B-294974.4, June 8, 2005, 2005 CPD ¶ 106 at 9
(recommending the reimbursement of costs where the agency
did little to implement its promised corrective action,
effectively requiring the protester to file a second
protest); Chase Supply, Inc.--Costs, B-411849.3, May 17,
2016, 2016 CPD ¶ 134 at 6 (recommending the reimbursement
of costs where the agency’s failure to promptly implement
its promised corrective action resulted in the protester
being forced to pursue the issue again through two
agency-level protests and two protests with our Office).
Here, we conclude that the agency did not unduly delay the
implementation of its promised corrective action. In this
regard, we note that the USDA sent a revised offering
letter to the SBA within nine days of our dismissal of the
underlying protest. Within a week of the SBA telling the
agency that it would not accept the requirement into the
8(a) program, the agency took additional steps in
furtherance of the corrective action. On October 26, an
FSA contracting officer emailed an agency attorney to ask
how the agency could preserve its fiscal year funding if
it decided to procure the requirement through a
competition amongst small businesses rather than as an
8(a) set-aside. Contracting Officer Email to Agency
Counsel, Oct. 25, 2016. The agency attorney replied the
next day, stating that the funds would be available for
100 days and could “only be used in furtherance of
entering into a valid replacement contract for the Na
Ali’i contract.” Email from Agency Attorney to Contracting
Officer, Oct. 26, 2016. The agency attorney further stated
that “[i]f the contracting officer determines that the
8(a) contract was not appropriate, then the FY16 funding
may be used to allow for [a] small business competition
for a replacement contract.” Id.
At this point, however, the FSA contracting staff
incorrectly interpreted the attorney’s email to mean that
the Na Ali’i contract had to remain open for 100 days in
order for the funds to remain available for re-use. See
Agency Resp. to GAO Req. for Supp. Info., Mar. 13, 2017.
Due to this mistaken belief, the FSA contracting staff
kept the Na Ali’i contract open until January 5, 2017.
While the agency’s mistaken interpretation led to an
additional delay of two and a half months before the
agency began the process of terminating the contract
awarded to Na Ali’i, the delay was not the result of any
bad faith on the part of the agency and ultimately did not
substantially affect the implementation of the corrective
action. Indeed, during this time period, the agency kept
the stay in place of Na Ali’i's contract and did not
restart performance of the requirement. These actions are
largely consistent with the agency’s proposed corrective
action, which promised to stay performance of Na Ali’i's
contract, submit a revised letter to the SBA, and, if the
SBA did not approve the requirement into the 8(a) program,
terminate the contract and reassess the agency’s available
procurement options. See Agency Resp. to Objection to
Corrective Action, Sept. 26, 2016, at 2.
AGS additionally argues that the USDA attempted to
circumvent the promised corrective action by procuring the
requirement through a modification of another contract. In
our view, the record does not support this contention. In
this regard, we note that the challenged modification
involved the addition of one mid-level management analyst,
while the Na Ali’i contract involved the provision of an
entire “management consultancy,” consisting of various
management consultants, analysts, and administrative
assistants. Compare B-413912.1 Agency Report, Tab 17,
Contract Modification, at 1 with B-413636.1 Protest, at 8.
Thus, the size and scope of work for the instant
requirement is fundamentally different from the size and
scope of the challenged modification. Moreover, the record
does not contain any indication that the modification was
intended by the agency to circumvent the corrective action
here. (American
Government Services, LLC--Costs B-413636.2: Apr 21,
2017)
Statutory vs Nonstatutory Protests
Boise contends that their protest was filed pursuant to
our statutory jurisdiction, because our Office has
historically taken statutory jurisdiction over “mixed
transactions,” which, like this transaction, involve both
a sale and a procurement of goods or services. Under the
Competition in Contracting Act of 1984 (CICA) and our
Office’s Bid Protest Regulations, we review protests
concerning alleged violations of procurement statutes or
regulations by federal agencies in the award or proposed
award of contracts for procurement of goods and services,
and solicitations leading to such awards. 31 U.S.C. §§
3551, 3552; 4 C.F.R. § 21.1(a) (2009). As a general
matter, sales by a federal agency, such as timber sales,
are not procurements of property or services, and are
therefore not within our Office’s bid protest
jurisdiction. See 31 U.S.C. § 3551(1)(a). We also
recognize, however, that certain transactions can involve
both a sale of government property and a procurement of
goods or services, and we have sometimes exercised
jurisdiction in mixed, or bundled, transaction cases. See,
e.g., Armed Forces Hospitality, LLC, B-298978.2,
B-298978.3, Oct. 1, 2009, 2009 CPD ¶ 192.
It has consistently been our Office’s view that a mixed
transaction, like this one, which includes the delivery of
goods or services of more than de minimis value to the
government, is a procurement within the meaning of CICA.
See Public Commc’ns Servs., Inc., B-400058, B-400058.3,
July 18, 2008, 2009 CPD ¶ 154 at 7. Here, however, the
specific statute authorizing stewardship contracts
provides that the transactions “may, at the discretion of
the Secretary of Agriculture, be considered a contract for
the sale of property under such terms as the Secretary may
prescribe without regard to any other provision of law.”
16 U.S.C. § 6591c(d)(2) (emphasis added). Accordingly, the
question of whether this transaction should be considered
a mixed transaction reviewed pursuant to our statutory
authority under CICA or as a timber sale reviewed pursuant
to our nonstatutory agreement with the Forest Service
hinges on the meaning of the “without regard” provision in
16 U.S.C. § 6591c(d)(2).
In general, the plain meaning of a statute’s provisions
must be read in the context of the broader statutory
scheme, and must be read in a way to give effect to all
provisions of the law. See, e.g., K Mart Corp. v. Cartier,
Inc., 486 U.S. 281, 291 (1988); Mastro Plastics Corp. v.
National Labor Relations Board, 350 U.S. 270, 285 (1956),
quoting United States v. Boisdore’s Heirs, 8 How. 113, 12
L.Ed. 1009 (1850); Lowe v. SEC, 472 U.S. 181, 207 n.53
(1985). In interpreting similar “notwithstanding any other
provision of law” or “without regard to any other
provision of law” provisions, we have considered whether
the provisions of the relevant laws are directly in
conflict when determining if such provisions displace
generally applicable procurement laws. See, e.g., Jacobs
COGEMA, LLC, B-290125.2, B-290125.3, Dec. 18, 2002, 2003
CPD ¶ 16 at 7-10 (similar provision did not displace
generally applicable procurement law to the extent the
requirements of the statutory provision were not actually
inconsistent with generally applicable procurement laws);
Pierce First Medical; Alternative Contracting Enterprises,
LLC--Recon., B-406291.3, B-406291.4, June 13, 2012, 2012
CPD ¶ 182 at 4-5 (similar provision did not supersede
certain generally applicable provisions of law that could
be read in such a way as to give both provisions effect);
c.f., RJO Enterprises, Inc., B-252232, June 9, 1993, 93-1
CPD ¶ 446 at 5-6 (similar provision displaces generally
applicable procurement laws where the application of those
laws would be inconsistent with the plain language of the
provision, and would render it “a nullity”). Likewise,
courts have consistently read similar provisions as
superseding all other laws that are directly inconsistent
with them. See, e.g., Cisneros v. Alpine Ridge Group, 508
U.S. 10, 18 (1993), citing Liberty Maritime Corp. v.
United States, 928 F.2d 413 (D.C. Cir. 1991); Saco River
Cellular, Inc. v. Federal Communications Comm., 133 F.3d
25, 30 (D.C. Cir. 1998); Illinois Nat’l Guard v. Federal
Labor Relations Authority, 854 F.2d 1396, 1403 (D.C. Cir.
1988), quoting New Jersey Air National Guard v. FLRA, 677
F.2d 276, 283 (3d Cir. 1982).
In this case, the provision authorizes the agency to
determine whether or not a stewardship contract is a sale
of property and set its terms without regard to any other
provision of law. 16 U.S.C. § 6591c(d)(2). On its face,
the effect of the “without regard” provision is to
specifically exempt the determination that a given
contract is a sale of property from the statutory
framework governing such a determination. Put another way,
rejecting the agency’s determination that this transaction
was a sale of property in favor of a contrary
determination that CICA applies to this transaction would
have the effect of rendering the “without regard”
provision a nullity. We conclude, therefore, that the
plain language of the statute gives the agency discretion
to determine whether a contract undertaken using this
authority is a sale of property without regard to any
other provision of law, including CICA. We see no other
reasonable interpretation of the broad and unequivocal
language of the “without regard” clause in the statute.
The agency regulations implementing the statute provide
that “[w]hen the value of timber or other forest products
removed through the contract is equal to or exceeds the
total value of the service work items received by the
Forest Service, the activity shall be considered a sale of
property[….]” 36 C.F.R. § 223.301(b)(2). In this case, the
value of the forest products significantly exceeded the
value of the services, and the agency accordingly
determined to solicit the contract as a timber sale.
Agency Response at 3. On these facts, we conclude that
this transaction was properly solicited under the
applicable regulations as a sale of property, which does
not fall within our statutory bid protest jurisdiction,
and that Boise’s protest was therefore a nonstatutory
protest under our Office’s agreement with the Forest
Service to decide protests of timber sales.
Recovery of Costs Following Corrective Action in
Nonstatutory Protest
As its secondary argument, Boise correctly notes that
under our regulations, as written, we are not precluded
from recommending reimbursement of costs pursuant to
section 21.8(e) of our Bid Protest Regulations. As a
general matter, section 21.8(e) authorizes our Office to
recommend the payment of protest costs where the agency
has taken corrective action in response to a protest, as
in this case. See 4 C.F.R. § 21.8(e). Section 21.13(b) of
our regulations, governing nonstatutory protests,
establishes only that the provisions of 4 C.F.R. §
21.8(d), generally authorizing the payment of protest
costs where GAO has determined that the agency has
violated law or regulation, do not apply to nonstatutory
protests. See 4 C.F.R. § 21.13(b). Section 21.13(b) does
not carve out a similar exception with respect to the
recovery of costs under section 21.8(e). Id.
Section 21.8(e), on which the protester relies for the
recovery of its costs, however, provides that our Office
“may” recommend reimbursement of costs, and we have
explained that the decision of whether to award costs is
appropriately based on the circumstances of each case. See
4 C.F.R. § 21.8(e) and Alban Engine Power Systems,
B-247614.2, Apr. 8, 1992, 92-1 CPD ¶ 354 at 2. We have
noted, in another context, that the language of section
21.8(e) does not include a bright line rule concerning
costs and the timing of corrective action, and that there
may be circumstances where the award of costs, even where
corrective action was taken after submission of the agency
report, would not be justified, just as there could be
circumstances where the award of costs would be
appropriate even where corrective action was taken prior
to report submission. See Alban Engine Power Systems,
supra.
It is our view that the inconsistency identified by the
protester is an oversight in our regulatory structure. We
agree with the agency that there is no sound policy reason
to recommend that protesters receive reimbursement of
costs where the agency voluntarily takes corrective
action, but not where we issue a decision on the merits
sustaining the protest. We conclude that it would be
inappropriate to recommend the reimbursement of protest
costs following agency corrective action in response to a
nonstatutory protest, where our Office could not recommend
reimbursement if we had sustained the protest.
The request is denied. (Boise
Cascade Wood Products, LLC B-413987.2: Apr 3, 2017)
In their requests for costs, Technatomy and Octo ask our
Office to recommend that CMS reimburse them for the costs
associated with all of the issues they pursued. In
response, the agency does not dispute that the protesters
should be reimbursed their costs of pursuing their
challenges to the agency’s best value determinations and
the evaluation of Octo’s proposal under the small business
participation factor, but maintains that the protesters’
reimbursement should be limited to these issues.
When a procuring agency takes corrective action in
response to a protest, our Office may recommend under 4
C.F.R. § 21.8(e) that the agency reimburse the protester
its reasonable protest costs where, based on the
circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a
clearly meritorious protest, thereby causing protesters to
expend unnecessary time and resources to make further use
of the protest process in order to obtain relief. Pemco
Aeroplex, Inc.--Recon. & Costs, B-275587.5, B-275587.6,
Oct. 14, 1997, 97-2 CPD ¶ 102 at 5. A protest is clearly
meritorious when a reasonable agency inquiry into the
protest allegations would show facts disclosing the
absence of a defensible legal position. The Real Estate
Ctr.--Costs, B‑274081.7, Mar. 30, 1998, 98-1 CPD ¶ 105 at
3. A GAO attorney will inform the parties through outcome
prediction ADR that a protest is likely to be sustained
only if he or she has a high degree of confidence
regarding the outcome; therefore, the willingness to do so
is generally an indication that the protest is viewed as
clearly meritorious, and satisfies the “clearly
meritorious” requirement for the purpose of recommending
reimbursement of protest costs. National Opinion Research
Ctr.--Costs, B-289044.3, Mar. 6, 2002, 2002 CPD ¶ 55 at 3;
Inter-Con Sec. Sys., Inc.; CASS, a Joint Venture--Costs,
B-284534.7, B-284534.8, Mar. 14, 2001, 2001 CPD ¶ 54 at 3.
As noted above, CMS does not contest the protesters’
requests that we recommend reimbursement of their protest
costs associated with challenging the agency’s best value
determinations, and, in the case of Octo, its challenge to
the agency’s evaluation of its proposal under the small
business participation factor, which were the topics of
the ADR. Accordingly, the remaining question for
resolution by our Office is whether the protesters should
be reimbursed for all of the remaining challenges to the
agency’s evaluation of proposals raised in the protests.
For purposes of determining entitlement to protest costs,
we generally consider all issues concerning the evaluation
of proposals to be intertwined--and thus not
severable--and therefore generally will recommend
reimbursement of the costs associated with both successful
and unsuccessful challenges to an evaluation. Coulson
Aviation (USA) Inc.; 10 Tanker Air Carrier, LLC--Costs,
B-406920.6, B‑406920.7, Aug. 22, 2013, 2013 CPD ¶ 197 at
5. While we have, in appropriate cases, limited the award
of protest costs to successful protesters where a part of
their costs is allocable to a protest issue that is so
clearly severable as to essentially constitute a separate
protest, see, e.g., BAE Tech. Servs., Inc., B-296699.3,
Aug. 11, 2006, 2006 CPD ¶ 122 at 3; Interface Flooring
Sys., Inc.--Claim for Attorneys’ Fees, B-225439.5, July
29, 1987, 87-2 CPD ¶ 106 at 2-3, limiting recovery of
protest costs in all cases to only those issues on which
the protester prevailed would be inconsistent with the
broad, remedial congressional purpose behind the cost
reimbursement provisions of the Competition in Contracting
Act. Fluor Energy Tech. Servs., LLC--Costs, B-411466.3,
June 7, 2016, 2016 CPD ¶ 160 at 3; JV Derichebourg-BMAR &
Assocs., LLC--Costs, B-407562.3, May 3, 2013, 2013 CPD ¶
108 at 3.
CMS argues that the remaining challenges to the agency’s
evaluation of proposals are clearly severable because,
with the exception of Octo’s challenge to the evaluation
of its proposal under the small business participation
evaluation factor, the concerns identified in the outcome
prediction ADR focused on the source selection decision,
and not the evaluation conducted by the lower-level
technical evaluators. We disagree. In our view, these
other issues share common factual and legal bases; both
the meritorious and non-meritorious issues are intertwined
and interrelated with the agency’s flawed consideration of
the relative merits of proposals. See Sevatec,
Inc.--Costs, B-407880.3, June 27, 2013, 2013 CPD ¶ 163 at
3-4.
For example, both Technatomy and Octo argued, among other
grounds, that the agency’s evaluation of their proposals
under the process maturity factor was inconsistent with
the solicitation’s evaluation criteria and disparate with
regard to certain of the awardees. The protesters further
contended that these errors, and related evaluation errors
under the other non-price factors, impacted the
reasonableness of the SSA’s best-value determination by
limiting a reasonable comparative assessment of the
proposals. Essentially, the challenges to the underlying
evaluation and to the SSA’s subsequent comparative
assessment of proposals both relied on the same factual
and legal premises--that the agency had failed to
reasonably consider the merits of the protesters’
proposals. Here the record demonstrates that the
challenges shared a common factual and legal basis, and
therefore we conclude that the underlying technical
challenges were inextricably intertwined with the
meritorious protest grounds challenging the agency’s
best-value determinations. (Technatomy
Corporation; Octo Consulting Group, Inc.--Costs
B-413116.49, B-413116.50: Dec 14, 2016)
When a procuring agency takes corrective action in
response to a protest, our Office may recommend under 4
C.F.R. § 21.8(e) that the agency reimburse the protester
its protest costs where, based on the circumstances of the
case, we determine that the agency unduly delayed taking
corrective action in the face of a clearly meritorious
protest, thereby causing protesters to expend unnecessary
time and resources to make further use of the protest
process in order to obtain relief. Pemco Aeroplex,
Inc.--Recon. and Costs, B-275587.5, B-275587.6, Oct. 14,
1997, 97-2 CPD ¶ 102 at 5. A protest is clearly
meritorious when a reasonable agency inquiry into the
protest allegations would show facts disclosing the
absence of a defensible legal position. The Real Estate
Ctr.--Costs, B-274081.7, Mar. 30, 1998, 98-1 CPD ¶ 105 at
3. A GAO attorney will inform the parties through outcome
prediction ADR that a protest is likely to be sustained
only if he or she has a high degree of confidence
regarding the outcome; therefore, the willingness to do so
is generally an indication that the protest is viewed as
clearly meritorious, and satisfies the “clearly
meritorious” requirement for purposes of recommending
reimbursement of protest costs. National Opinion Research
Center--Costs, B-289044.3, Mar. 6, 2002, 2002 CPD ¶ 55 at
3; Inter-Con Sec. Sys., Inc.; CASS, a Joint
Venture--Costs, B-284534.7, B-284534.8, Mar. 14, 2001,
2001 CPD ¶ 54 at 3.
In response to Fluor’s request, the agency concedes that
the protester should be reimbursed its reasonable protest
costs as they relate to challenges against the agency’s
cost realism evaluation, but asserts that Fluor’s recovery
should be limited to those protest grounds only. In this
regard, the agency states in its response that “DOE
believes the other grounds are discrete and severable and
that it would have prevailed on the other protest grounds,
and therefore protester would not be entitled to recovery
on those allegations.” Agency Response, Aug. 20, 2015, at
1. However, DOE’s response provides no further explanation
or argument in support of its belief that the other
arguments raised in Fluor’s protest are discrete and
severable.
For purposes of determining entitlement to protest costs,
we generally consider all issues concerning the evaluation
of proposals to be intertwined--and thus not
severable--and therefore generally will recommend
reimbursement of the costs associated with both successful
and unsuccessful challenges to an evaluation. Coulson
Aviation (USA) Inc.; 10 Tanker Air Carrier, LLC--Costs,
B-406920.6, B-406920.7, Aug. 22, 2013, 2013 CPD ¶ 197 at
5. While we have, in appropriate cases, limited the award
of protest costs to successful protesters where a part of
their costs is allocable to a protest issue that is so
clearly severable as to essentially constitute a separate
protest, see, e.g., BAE Tech. Servs., Inc.--Costs,
B-296699.3, Aug. 11, 2006, 2006 CPD ¶ 122 at 3; Interface
Flooring Sys., Inc.--Claim for Attorneys’ Fees,
B-225439.5, July 29, 1987, 87-2 CPD ¶ 106 at 2-3, limiting
recovery of protest costs in all cases to only those
issues on which the protester prevailed would be
inconsistent with the broad, remedial congressional
purpose behind the cost reimbursement provisions of CICA.
TRESP Assocs., Inc.--Costs, B-258322.8, Nov. 3, 1998, 98-2
CPD ¶ 108 at 2.
In this case, as noted above, the agency has presented no
argument or evidence to support its contention that
Fluor’s other challenges should be severed from its
clearly meritorious challenges to the agency’s cost
realism evaluation. See Burns and Roe Servs. Corp.--Costs,
B-310828.2, Apr. 28, 2008, 2008 CPD ¶ 81 at 3. Absent such
support, we are unwilling to deviate from the general
premise that a protester is entitled to all costs
associated with both successful and unsuccessful
allegations. Since a reasonable inquiry into Fluor’s
initial protest would have revealed that the protest was
clearly meritorious--where the record showed that the
agency’s cost realism analysis did double-count various
proposed costs--we conclude that the agency unduly delayed
taking corrective action in the face of a clearly
meritorious protest, thereby causing protesters to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief, including the
filing of a supplemental protest expanding upon its
clearly meritorious protest grounds, and comments on the
agency report concerning its initial protest allegations.
In this context, we recommend that Fluor be reimbursed its
reasonable costs incurred with respect to all issues
pursued in its initial protest and supplemental protest.
The request that GAO recommend reimbursement of protest
costs is granted. (Fluor
Energy Technology Services, LLC--Costs B-411466.3: Jun
7, 2016) (pdf)
Under the Competition in Contracting Act of 1984 (CICA)
our Office is authorized to recommend reimbursement of
protest costs only where we find that an agency’s actions
violated a procurement statute or regulation. 31 U.S.C. §
3554(c)(1). Our Bid Protest Regulations further provide
that where the contracting agency decides to take
corrective action in response to a protest, we may
recommend reimbursement of protest costs, including
reasonable attorneys’ fees. 4 C.F.R. § 21.8(e). Our
Regulations do not contemplate a recommendation for
reimbursement of protest costs in every case in which an
agency takes corrective action; rather only where an
agency unduly delays taking corrective action in the face
of a clearly meritorious protest. Information Ventures,
Inc.--Costs, B-294580.2 et al., Dec. 6, 2004, 2004 CPD ¶
244 at 2. Thus, as a prerequisite to our recommending the
reimbursement of costs where a protest has been settled by
corrective action, not only must the protest have been
meritorious, but it also must have been clearly
meritorious, that is, not a close question. PADCO,
Inc.--Costs, B‑289096.3, May 3, 2002, 2002 CPD ¶ 135 at 3.
A protest is clearly meritorious where a reasonable agency
inquiry into the protester’s allegations would reveal
facts showing the absence of a defensible legal position.
Yardney Technical Prods., Inc., B-297648.3, Mar. 28, 2006,
2006 CPD ¶ 65 at 4.
Here, based on the record presented, we cannot conclude
that the agency unduly delayed taking corrective action in
the face of a clearly meritorious protest. In response to
the protester’s request for costs, the agency explains
that it did not take corrective action prior to submitting
its agency report, because our Office in a prior decision,
Jacqueline R. Sims, dba JRS Staffing Servs., supra, denied
JRS’s protest challenging similar issues. It also
correctly points out that it immediately took corrective
action the day after it was advised by the GAO attorney of
its litigation risk. We agree with the agency that its
reading of our prior decision was not unreasonable, and
therefore, provided the BOP with a defensible legal
position.[7]
While the protester asserts that our Office frequently
awards protest costs after conducting ADR with the parties
to a protest, JRS also acknowledges that litigation risk
assessment ADR is different from outcome prediction ADR.
JRS Request for Costs at 5. Furthermore, our Regulations
provide for the reimbursement of protest costs only where
an agency unduly delays taking corrective action in the
face of a clearly meritorious protest. Information
Ventures, Inc.--Costs, supra. While there may be instances
where our Office offers ADR to the parties after
identifying a clearly meritorious protest issue, it does
not follow that ADR is only offered when a protest is
clearly meritorious. In this regard, the offer of ADR--especially
ADR that is limited to an assessment of litigation risk,
or negotiation assistance--does not automatically
translate to the conclusion that the protester should be
awarded costs. Instead the determination of whether to
recommend the reimbursement of costs rests on the factual
and legal posture of each individual protest, which must
be analyzed on a case-by-case basis.
On this record and based on the facts presented here, we
cannot conclude that the agency unduly delayed in taking
corrective action, or that JRS’s protest on this issue was
clearly meritorious. Yardney Technical Prods., Inc., supra
at 4 (the mere fact that an agency decides to take
corrective action does not necessarily establish the
absence of a defensible legal position, or that a statute
or regulation has clearly been violated).
The request that we recommend reimbursement of costs is
denied. (JRS Staffing Services--Costs B-410708.3:
Nov 9, 2015) (pdf)
First, TRAX requests that we recommend that it be
reimbursed the reasonable costs of filing and pursuing its
initial protest, including attorneys’ fees. In this
regard, TRAX asserts that all of its initial protest
allegations were clearly meritorious, and that the Army’s
corrective action was unduly delayed because it took
action filed after the due date for the initial agency
report and after comments and the supplemental protest
were filed. Based upon our review of the record, we find
no basis to recommend reimbursement for TRAX’s initial
protest costs. For illustrative purposes, we discuss a few
of these allegations below.
With regard to the OCI issue raised in TRAX’s initial
protest, TRAX asserted that the awardee either failed to
disclose a potential OCI issue, or that the Army failed to
consider the issue, as required by the RFP. In response to
the protest, the agency provided contemporaneous
documentation demonstrating that the contracting officer
considered the potential OCI issue and concluded that the
risk of a potential OCI was low. AR at 16-22. Although
TRAX disagreed in its comments regarding whether the
contracting officer’s OCI analysis was reasonable, based
on this record, it is clear that the contracting officer
was aware of, and considered, the OCI issue. Thus, we do
not find that the protest was clearly meritorious, or that
the agency lacked a defensible legal position with respect
to TRAX’s OCI allegations since the record demonstrates
that the contracting officer did, in fact, consider the
OCI issue contrary to TRAX’s assertions.[2]
TRAX’s initial protest also raised numerous challenges to
the agency’s evaluation of TRAX’s and the awardee’s
proposals. For example, TRAX asserted that the agency
evaluated the offerors’ staffing levels unequally in the
cost evaluation, arguing that the awardee improperly
deviated from the RFP’s labor hour baseline. Protest at
27‑29. In response, the agency pointed to the provisions
in the RFP that permitted offerors to propose deviations
from the RFP’s labor hour baseline, based on the offeror’s
unique management approach and promised efficiencies, as
long as such efficiencies and management approach are
fully explained and justified in the offeror’s proposal.
See RFP at 102. In addition, the agency provided
documentation of the awardee’s proposed staffing levels,
and the agency’s evaluation thereof. On this record, we
see no basis to conclude that the agency failed to comply
with the RFP’s terms or that the agency evaluated the
proposals unequally, as argued by the protester.
The protester also contends that its supplemental protest
allegations regarding the agency’s exchanges with Jacobs
were so intertwined with its initial protest allegations
regarding the agency’s exchanges with TRAX that
investigation by the Army of TRAX’s initial protest
grounds should have revealed the flaws later identified by
the supplemental protest. TRAX argues that, by waiting
until after the agency report to take corrective action,
the agency unduly delayed taking corrective action with
regard to the supplemental protest grounds. For the
reasons discussed below, we disagree.
With respect to the promptness of the agency’s corrective
action under the circumstances, we review the record to
determine whether the agency took appropriate and timely
steps to investigate and resolve the impropriety. See
Chant Eng’g Co., Inc.--Costs, B-274871.2, Aug. 25, 1997,
97-2 CPD ¶ 58 at 4; Carl Zeiss, Inc.--Costs, B-247207.2,
Oct. 23, 1992, 92-2 CPD ¶ 274 at 4. In general, if an
agency takes corrective action in response to a protest by
the due date for its report in response to the protest, we
consider such action to be prompt and will not recommend
reimbursement of protest costs, even where the protest is
clearly meritorious. See The Sandi‑Sterling
Consortium--Costs, B‑296246.2, Sept. 20, 2005, 2005 CPD ¶
173 at 3; HSQ Tech.--Costs, B-276050.2, June 25, 1997,
97-1 CPD ¶ 228 at 2; see also Metalcraft, Inc.--Costs,
B-402181.3, May 17, 2010, 2010 CPD ¶ 116 at 3 (finding
that the agency promptly took corrective action prior to
the supplemental agency report where the allegations
raised in the supplemental protest were not related to the
initial protest such that the agency’s investigation of
the initial protest should have revealed the asserted
evaluation flaws).
Based on the record, we cannot conclude that the
protester’s supplemental protest allegations were related
to the initial protest such that the agency’s
investigation of the initial protest should have revealed
the asserted flaws in TRAX’s supplemental protest. The
protester points to the following footnote in its initial
protest to support its position that the initial protest
raised concerns regarding the agency’s exchanges with the
awardee: “[T]o the extent the Army engaged in discussions
with Jacobs but not TRAX, that disparate treatment would
constitute unlawfully unequal discussions . . . .” Protest
at 25 n.8. In the absence of the documentation provided in
the agency report, however, this allegation was
speculative, and did not require a response by the agency.
Rather, as discussed above, our Office requested that the
agency provide documentation of its clarifications with
the awardee in response to the protester’s allegations
challenging the agency’s technical and cost evaluation of
the awardee’s proposal, not based on the protester’s
allegation regarding discussions. This is the
documentation that prompted TRAX’s supplemental protest
ground regarding the propriety of the agency’s exchanges
with the awardee. Our Office then requested a separate
report in response to the supplemental protest in
recognition of the different nature of the supplemental
protest allegations. Accordingly, because the protester’s
supplemental protest allegations were not related to the
initial protest such that the agency’s investigation of
the initial protest should have revealed the asserted
evaluation flaws, TRAX has not met the standard required
by our Office for a recommendation to reimburse its
protest costs. Metalcraft, Inc.--Costs, supra. (TRAX
International Corporation--Costs B-410441.5: Aug 26,
2015) (pdf)
Where a procuring agency takes corrective action in response to
a protest, we may recommend that it reimburse the protester its
protest costs if we determine that the agency unduly delayed
taking corrective action in the face of a clearly meritorious
protest. See, e.g.,Taylor Consultants, Inc.--Costs, B-400324.3,
Feb. 2, 2009, 2009 CPD ¶ 37 at 3. As a general rule, if an
agency takes corrective action on or before the due date for its
protest report, we regard such action as prompt and decline to
favorably consider a request for cost reimbursement. See, e.g.,
J.A. Jones Mgmt. Servs., Inc., -- Costs, B-284909.4, July 31,
2000, 2000 CPD ¶ 123 at 4.
Here, there is no basis for Palmetto to assert that the agency
delayed taking corrective action. Indeed, Palmetto’s
reimbursement request expressly acknowledges that the action was
taken “[o]nly a week after Palmetto filed its protest,” and
further “agrees that the Agency’s corrective action in response
to the protest renders the substance of the protest ‘academic’
and appropriate for dismissal.” Palmetto Reimbursement Request
at 1-2. Since, as noted above, our Office will recommend
reimbursement of protest costs only where an agency has unduly
delayed taking corrective action, our recommendation of cost
reimbursement is not appropriate here.
The request is denied. (Palmetto
Isotopes, B-410268.2: Jan 5, 2015) (pdf)
When a procuring
agency takes corrective action in response to a protest, our
Office may recommend reimbursement of protest costs where, based
on the circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 4 C.F.R. § 21.8(e)
(2013); AAR Aircraft Servs.--Costs, B-291670.6, May 12, 2003,
2003 CPD ¶ 100 at 6. When an agency takes corrective action
before the due date set for receipt of the agency report, our
Office views such action as prompt and will not recommend the
reimbursement of costs. The Sandi-Sterling Consortium--Costs,
B-296246.2, Sept. 20, 2005, 2005 CPD ¶ 173 at 2-3.
Here, the due date set for the agency report, which consisted of
the consolidated legal memorandum and contracting officer’s
statement, was December 3. On November 30, the agency notified
our Office of its intent to take corrective action. Because the
agency’s corrective action was prompt, we deny the protester’s
request that we recommend costs.
Moreover, we find no basis to conclude that MJLM’s initial
protest grounds were clearly meritorious. As a prerequisite to
our recommending that costs be reimbursed where a protest has
been settled by corrective action, not only must the protest
have been meritorious, but it also must have been clearly
meritorious. Apptis Inc.--Costs, B-402146.3, Mar. 31, 2010, 2010
CPD ¶ 123 at 4; Triple Canopy, Inc.--Costs, B-310566.9,
B-400437.4, Mar. 25, 2009, 2009 CPD ¶ 62 at 3. MJLM’s initial
protest alleged an improper bait and switch of staff, and of the
center director; MJLM alleged the switch was evidenced by the
awardee’s attempt to hire MJLM’s superior incumbent personnel
after award. Protest at 3, 24-25. Generally, however, it is
neither unusual nor inherently improper for an awardee to
recruit and hire personnel previously employed by an incumbent
contractor. Lifecare Mgmt. Partners, B-297078, B-297078.2, Nov.
21, 2005, 2006 CPD ¶ 8 at 6 n.11; see also AT&T Gov’t Solutions,
Inc., B-406926 et al., Oct. 20, 2012, 2013 CPD ¶ 88 at 15 (even
if there was evidence of an intent to switch, allegation of an
impermissible “bait and switch” is not meritorious where there
was no evidence of baiting). Accordingly, we are unable to
conclude that the protest ground was clearly meritorious with
respect to the protester’s claims of a flawed staffing
evaluation. (McConnell, Jones,
Lanier & Murphy LLC--Costs, B-407706.3, May 28, 2013)
(pdf)
Where a procuring
agency takes corrective action in response to a protest, our
Office may recommend under 4 C.F.R. § 21.8(e) (2013) that the
agency reimburse the protester its protest costs where, based on
the circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing protesters to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Pemco Aeroplex,
Inc.--Recon. and Costs, B-275587.5, B-275587.6, Oct. 14, 1997,
97-2 CPD ¶ 102 at 5. A protest is clearly meritorious when a
reasonable agency inquiry into the protest allegations would
show facts disclosing the absence of a defensible legal
position. The Real Estate Ctr.--Costs, B-274081.7, Mar. 30,
1998, 98-1 CPD ¶ 105 at 3. A GAO attorney will inform the
parties through outcome prediction that a protest is likely to
be sustained only if he or she has a high degree of confidence
regarding the outcome; therefore, the willingness to do so is
generally an indication that the protest is viewed as clearly
meritorious, and satisfies the “clearly meritorious” requirement
for purposes of recommending reimbursement of protest costs.
National Opinion Research Center--Costs, B-289044.3, Mar. 6,
2002, 2002 CPD ¶ 55 at 3; Inter-Con Sec. Sys., Inc.; CASS, a
Joint Venture--Costs, B-284534.7, B-284534.8, Mar. 14, 2001,
2001 CPD ¶ 54 at 3.
As noted above, the Navy does not contest the protester’s
request that we recommend reimbursement of its protest costs
associated with the staffing issue, which was the topic of ADR.
Accordingly, the remaining question for resolution by our Office
is whether the protester should be reimbursed for all issues
raised in its protest.
Generally, we consider a successful protester entitled to costs
incurred with respect to all issues pursued, not merely those
upon which it prevails. In our view, limiting recovery of
protest costs in all cases to only those issues on which the
protester prevailed would be inconsistent with the broad,
remedial Congressional purpose behind the cost reimbursement
provisions of the Competition in Contracting Act. AAR Aircraft
Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 9.
Nevertheless, failing to limit the recovery of protest costs in
all instances of partial or limited success by a protester may
result in an unjustified windfall to the protester and cost to
the government. As a consequence, in appropriate cases we have
limited our recommendation for the award of protest costs where
a part of those costs is allocable to an unsuccessful protest
issue that is so clearly severable from the successful issues as
to constitute an essentially separate protest. Focused Mgmt.,
Inc., B-404029.6, Oct. 3, 2011, 2011 CPD ¶ 204 at 4; KAES
Enters., LLC--Protest and Costs, B-402050.4, Feb. 12, 2010, 2010
CPD ¶ 49 at 4. In determining whether protest issues are so
clearly severable as to constitute essentially separate
protests, we consider, among other things, the extent to which
the issues are interrelated or intertwined--i.e., the extent to
which successful and unsuccessful arguments share a common core
set of facts, are based on related legal theories, or are
otherwise not readily severable. See Sodexho Mgmt., Inc.--Costs,
B-289605.3, Aug. 6, 2003, 2003 CPD ¶ 136 at 29.
Here, we regard the protester’s objections to the evaluation of
proposals as interrelated and not readily severable. In this
connection, we generally consider issues concerning the
evaluation of proposals to be intertwined. The Salvation Army
Community Corrections Program--Costs, B-298866.3, Aug. 29, 2007,
2007 CPD ¶ 165 at 7; see also CNA Indus. Eng’g, Inc.--Costs,
B-271034.2. Nov. 20, 1997, 97-2 CPD ¶ 149 at 3. Accordingly, we
recommend that the Navy reimburse the protester for the costs of
pursuing these issues.
We reach the opposite conclusion regarding the procurement
integrity issue. This issue does not share a common core of
relevant facts with--and thus is severable from--the protester’s
other complaints. Moreover, we did not consider the argument
raised by the protester pertaining to an alleged violation of
FAR § 3.104-7 to be clearly meritorious. In our view, the
argument raised involved a close question where the record
indicated that the agency had reviewed the “Workers Committee”
letter, which provided the basis for the Procurement Integrity
Act issues, but the agency did not deem a further investigation
warranted where the author was anonymous and where the
allegations in the letter were unsubstantiated. See Honeywell
Technology Solutions, Inc.--Costs, B-296860.3, Dec. 27, 2005,
2005 CPD ¶ 226 at 4 n.3. Thus, we do not recommend that the
agency reimburse the protester the costs of pursuing the
procurement integrity issue. (JV
Derichebourg-BMAR & Associates, LLC--Costs, B-407562.3, May
3, 2013) (pdf)
URS requests that our Office recommend that the agency reimburse
the protester’s costs of filing and pursuing its protest. URS
argues that the IRS unduly delayed taking corrective action--as
evidenced by its failure to do so until after filing of the
agency report and submission of comments by the protester--and
that its protest was clearly meritorious. The agency opposes
URS’s request, arguing that the protest here was not clearly
meritorious.
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys’ fees, if based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Competition in
Contracting Act of 1984 (CICA), 31 U.S.C. § 3554(c)(1)(A)
(2006); Bid Protest Regulations, 4 C.F.R. § 21.8(e) (2012). A
protest is clearly meritorious where a reasonable agency inquiry
into the protester’s allegations would reveal facts showing the
absence of a defensible legal position. Basic Commerce and
Indus., Inc.--Costs, B-401702.3, Feb. 22, 2010, 2010 CPD ¶ 258
at 4; Information Ventures, Inc.--Costs, B-294567.2, Nov. 16,
2004, 2004 CPD ¶ 234 at 2.
Ordinarily, we do not regard a protest as clearly meritorious
where resolution of the protest required further record
development, such as a hearing, to complete and clarify the
record. See Boston Harbor Dev. Partners, LLC--Costs, B-404614.5,
Feb. 17, 2012, 2012 CPD ¶ 74 at 2-3. However, when corrective
action is taken by an agency after a hearing has been scheduled,
we may still conclude that the protest is clearly meritorious,
where, as here, that conclusion is otherwise established by the
record. See Basic Commerce and Indus., Inc.--Costs, supra; Eagle
Home Med. Corp.--Costs, B-299821.3, Feb. 4, 2008, 2008 CPD ¶ 41
at 5 n.4.
In our view, URS’s protest challenging the adequacy of the IRS’s
evaluation of VSE’s proposal with regard to the use of
subcontractor FJC was clearly meritorious on the record provided
to our Office with the agency report. In this regard, the
agency’s evaluation of VSE’s proposed use of subcontractor FJC
was entirely without support. IRS has not explained, nor is it
otherwise evident from the record, how VSE could be considered
eligible for award when VSE proposed to rely on a subcontractor
(FJC) which VSE itself repeatedly characterized as simply the
new name of a debarred company.
As a general rule, we recommend that a successful protester be
reimbursed protest costs with respect to all issued pursued, not
merely those upon which it prevails. Nevertheless, in
appropriate cases, we have limited our recommendation for the
award of protest costs where a part of those costs is allocable
to one or more unsuccessful protest issues that are so clearly
severable from the successful issues that it essentially
constitutes a separate protest. In determining whether protest
issues are so clearly severable as to essentially constitute
separate protests, we consider, among other things, the extent
to which the issues are interrelated or intertwined--i.e.,
whether the successful and unsuccessful arguments share a common
set of facts, are based on related legal theories, or are
otherwise not readily severable. Core Tech Int’l Corp.--Costs,
B-400047.2, Mar. 11, 2009, 2009 CPD ¶ 59 at 8. We view URS’s
other evaluation challenges--which we find were not clearly
meritorious--as plainly severable from the challenges to the
debarred subcontractor issue because the questions involved
distinct aspects of the record, and were not intertwined
factually or legally. (URS
Federal Services, Inc.--Costs, B-406140.4, Jul 17, 2012)
(pdf)
Where, as here, a procuring agency takes corrective action in
response to a protest, our Office may recommend reimbursement of
protest costs, including reasonable attorneys’ fees, if, based
on the circumstances of the case, we determine the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. §
3554(c)(1)(A); 4 C.F.R. § 21.8(e); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 6. A protest is
clearly meritorious where a reasonable agency inquiry into the
protester’s allegations would reveal facts showing the absence
of a defensible legal position. Yardney Tech. Prods.,
Inc.--Costs, B-297648.3, Mar. 28, 2006, 2006 CPD ¶ 65 at 4.
Additionally, while we consider corrective action to be prompt
if it is taken before the due date for the agency report
responding to the protest, we generally do not consider it to be
prompt where it is taken after that date. AGFA HealthCare
Corp.--Costs, B-400733.6, Apr. 22, 2009, 2009 CPD ¶ 90 at 3-4.
The Air Force does not dispute that Blackstone’s argument that
it failed to evaluate its past performance questionnaires was
clearly meritorious. There is also no dispute that the protest
as initially filed advised the agency that these questionnaires
had been submitted by email and provided evidence from the
firm’s references. The agency did not take prompt corrective
action in response to this protest. As a result, we conclude
that had the agency conducted an adequate search of its email
system prior to filing its report it would have ascertained that
it had, in fact, timely received two past performance
questionnaires for Blackstone as argued by the protester.
As a general rule, we recommend that a successful protester be
reimbursed protest costs with respect to all issues pursued, not
merely those upon which it prevails. AAR Aircraft Servs.--Costs,
supra at 9. Nevertheless, in appropriate cases, we have limited
our recommendation for the award of protest costs where a part
of those costs is allocable to an unsuccessful protest issue
that is so clearly severable from the successful issues that it
essentially constitutes a separate protest. In determining
whether protest issues are so clearly severable as to
essentially constitute separate protests, we consider, among
other things, the extent to which the issues are interrelated or
intertwined--i.e., whether the successful and unsuccessful
arguments share a common set of facts, are based on related
legal theories, or are otherwise not readily severable. Basic
Commerce and Indus., Inc.--Costs, B-401702.3, Feb. 22, 2010,
2010 CPD ¶ 258 at 4.
Here, we do not find that Blackstone’s other arguments were
clearly severable from its argument that the agency failed to
evaluate its past performance questionnaires. All of the
arguments concerned the reasonableness of the agency’s
evaluation of its proposal under the past performance factor,
such that the arguments were interconnected and based on common
factual underpinnings. We agree with Blackstone that its protest
issues were intertwined parts of its basic objection that the
Air Force misevaluated its proposal under the past performance
factor. T Square Logistics Servs. Corp., Inc.--Costs,
B-297790.6, June 7, 2007, 2007 CPD ¶ 108 at 9; see also BAE
Tech. Servs., Inc.--Costs, B-296699.3, Aug. 11, 2006, 2006 CPD ¶
122 at 2. Under the circumstances, we find that all of
Blackstone’s costs incurred in filing and pursuing its protest
are reimbursable.
We therefore recommend that Blackstone be reimbursed its costs
of pursuing its protest. Blackstone should submit its certified
claim, detailing the time spent and costs incurred, directly to
the agency within 60 days of its receipt of this decision. 4
C.F.R. § 21.8(f)(1). (Blackstone
Consulting, Inc., B-405909.2, Jan 31, 2012) (pdf)
The protester requests that our Office recommend that the agency
reimburse NxGen the costs of filing and pursuing its protest.
Under the Competition in Contracting Act of 1984, our Office may
recommend that protest costs be reimbursed only where we find
that an agency’s action violated a procurement statute or
regulation. 31 U.S.C. § 3554(c)(1) (2010). Our Bid Protest
Regulations provide that where the contracting agency decides to
take corrective action in response to a protest, we may
recommend that the protester be reimbursed the costs of filing
and pursuing its protest, including reasonable attorneys’ fees.
4 C.F.R. § 21.8(e) (2012). This does not mean that costs should
be reimbursed in every case in which an agency decides to take
corrective action; rather, a protester should be reimbursed its
costs where an agency unduly delayed its decision to take
corrective action in the face of a clearly meritorious protest.
Griner’s-A-One Pipeline Servs., Inc.-Costs, B-255078.3, July 22,
1994, 94-2 CPD ¶ 41 at 5. When an agency takes corrective action
before the due date set for receipt of the agency report, our
Office views such action as prompt and will not recommend the
reimbursement of costs. The Sandi–Sterling Consortium-Costs,
B-296246.2, Sept. 20, 2005, 2005 CPD ¶ 173 at 2-3. Here, because
the agency corrective action, taken in advance of the agency
report due date, was not unduly delayed, there is no basis to
grant the request for reimbursement of protest costs. (NxGen
Process Group, LLC--Costs, B-406650.2, May 24, 2012) (pdf)
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys’ fees, where, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. § 21.8(e) (2011); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 6. Thus, as a
prerequisite to our recommending that costs be reimbursed where
a protest has been settled by corrective action, not only must
the protest have been meritorious, but it also must have been
clearly meritorious, i.e., not a close question. Apptis
Inc.--Costs, B-402146.3, Mar. 31, 2010, 2010 CPD ¶ 123 at 4. A
protest is clearly meritorious where a reasonable agency inquiry
into the protester’s allegations would reveal facts showing the
absence of a defensible legal position. First Fed. Corp.--Costs,
B-293373.2, Apr. 21, 2004, 2004 CPD ¶ 94 at 2.
Here, we conclude that it is not appropriate to recommend that
Kingdomware recover its protest costs because, even if we
determined that the agency’s corrective action was not prompt,
the protest was not clearly meritorious. Whether the protest was
meritorious was not apparent from the record, which is why GAO
requested additional information and documentation from the VA.
In this regard, the record included both documents consistent
with the agency’s position that the order as awarded in 2010
included an option which was exercised in 2011, and documents
indicating that the original order either never included such an
option or that the option had been deleted at some point. Since
the ultimate resolution of this matter required substantial
further development as indicated, in part, by our Office’s
request for additional information, the protest, in our view,
presented a close question, and therefore was not clearly
meritorious. See Alaska Structures, Inc.--Costs, B-298575.4,
Jan. 22, 2007, 2007 CPD ¶ 15 at 6. (Kingdomware
Technologies--Costs, B-406228.2, May 10, 2012) (pdf)
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest costs
where, based on the circumstances of the case, we determine that
the agency unduly delayed taking corrective action in the face
of a clearly meritorious protest, thereby causing the protester
to expend unnecessary time and resources to make further use of
the protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. § 21.8(e) (2011); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 6. Thus, as a
prerequisite to our recommending that costs be reimbursed where
a protest has been settled by corrective action, not only must
the protest have been meritorious, but it also must have been
clearly meritorious, i.e., not a close question. J.F. Taylor,
Inc.--Entitlement to Costs, B-266039.3, July 5, 1996, 96-2 CPD ¶
5 at 3; Baxter Healthcare Corp.--Entitlement to Costs,
B-259811.3, Oct. 16, 1995, 95-2 CPD ¶ 174 at 4-5; GVC
Cos.--Entitlement to Costs, B-254670.4, May 3, 1994, 94-1 CPD ¶
292 at 3. A protest is “clearly meritorious” where a reasonable
agency inquiry into the protester’s allegations would reveal
facts showing the absence of a defensible legal position. First
Fed. Corp.--Costs, B-293373.2, Apr. 21, 2004, 2004 CPD ¶ 94 at
2.
We find that reimbursement is not appropriate in this case. With
regard to LGS’s supplemental protest, the agency took corrective
action promptly because it acted prior to the deadline for
submitting its supplemental report. When an agency takes
corrective action before the due date set for receipt of the
agency report, our Office views such action as prompt and will
not recommend the reimbursement of costs. The Sandi-Sterling
Consortium--Costs, B-296246.2, Sept. 20, 2005, 2005 CPD ¶ 173 at
2-3. Thus, we have no basis to recommend reimbursement of costs
associated with the supplemental protest.
We also find that the initial protest was not clearly
meritorious. LGS’s initial protest focused on its assertion that
the agency had applied an unstated preference for a specific
technical solution, which impacted both the conduct of
discussions and the best value determination. Even though the
agency’s corrective action provided for reevaluation of the
proposals, the agency does not concede that its original
evaluation was based on a preference for AT&T’s technical
solution; instead, it maintains that its decision to take
corrective action was based on LGS’s supplemental protest, which
specifically challenged the apparent unequal treatment of the
vendors, as reflected in the assignment of strengths to AT&T’s
proposal but not to LGS’s. Response to Cost Request at 2. While
the evaluators assigned strengths to AT&T’s technical solution,
based on our review of the record, it did not appear that the
agency had an unstated preference for that solution. In this
regard, the source selection authority recognized that AT&T’s
solution was not a requirement, but agreed that it was more
compatible with the existing site architecture than LGS’s
solution and would significantly reduce the risk of integration
problems. Price Negotiation Memorandum at 15. We thinks that the
agency’s recognition of technical advantages associated with a
more compatible solution did not constitute an improper unstated
technical preference. Thus, LGS’s protest on that issue was not
clearly meritorious.
The request for costs is denied. (LGS
Innovations LLC, B-405932.3, Apr 26, 2012) (pdf)
SAIC protested
that the agency unreasonably determined that the protester had
an unequal access to information OCI which disqualified it from
participating in the competition; that it failed to treat all
offerors equally in this regard; and that it failed to follow
the requirements of the Federal Acquisition Regulation (FAR). In
response to SAIC's protest, the agency submitted a report to
which SAIC filed comments and a supplemental protest. After the
agency submitted a supplemental report and SAIC submitted its
comments, the cognizant GAO attorney held an alternative dispute
resolution (ADR) conference, in which he engaged in outcome
prediction. He advised the parties that it was not clear from
the record that the agency's determination to exclude SAIC was
reasonable or that the agency had followed applicable
regulations in excluding SAIC. The GAO attorney did not
recommend that SAIC be included in the competition, but
suggested that the agency follow the requirements of FAR sect.
9.506 and document the process and, either revise its
determination and findings (D&F) to ensure its clarity, or
provide SAIC an opportunity to respond to the agency's concerns
in the D&F, clearly documenting whatever approach it ultimately
adopts.
Subsequently, the agency advised our Office that it was electing
to take corrective action. Specifically, the agency intends to
document its compliance with FAR sect. 9.506; amend the RFP as
necessary; prepare a new D&F document for SAIC's review and
comment; a new final D&F if required; and take other corrective
action as deemed appropriate. Air Force Proposed Corrective
Action Letter at 1. We dismissed the protest as academic
(B‑405155, B‑405155.2, Aug. 16, 2011).
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys' fees, if, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. sect.
3554(c)(1)(A) (2006); Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2011); AAR Aircraft Servs.-Costs, B‑291670.6, May 12,
2003, 2003 CPD para. 100 at 6. Our willingness to inform the
parties through outcome prediction ADR that a protest is likely
to be sustained, as we did here, is generally an indication that
the protest is viewed as clearly meritorious, and satisfies the
"clearly meritorious" requirement for purposes of recommending
reimbursement of protest costs. National Opinion Research
Ctr.-Costs, B-289044.3, Mar. 6, 2002, 2002 CPD para. 55 at 3.
Additionally, while we consider corrective action to be prompt
if it is taken before the due date for the agency report
responding to the protest, we generally do not consider it to be
prompt where it is taken after that date. AGFA HealthCare
Corp.--Costs, B-400733.6, Apr. 22, 2009, 2009 CPD para. 90 at
3-4.
Here, the agency acknowledges that it took corrective action in
response to the ADR conference and states that it will consider
a timely claim from SAIC for its reasonable costs, based upon a
recommendation from our Office. Based on the clearly meritorious
nature of the issues, and the agency's undue delay in taking
corrective action, we recommend that SAIC be reimbursed the
costs associated with filing and pursuing its protest, including
reasonable attorneys' fees. SAIC should submit its certified
claim, detailing the time spent and costs incurred, directly to
the agency within 60 days of its receipt of this decision. 4
C.F.R. sect. 21.8(f)(1).
The request is granted. (Science
Applications International Corporation, B-405155.3, October
3, 2011)
When a procuring
agency takes corrective action in response to a protest, our
Office may recommend reimbursement of protest costs if, based on
the circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a clearly
meritorious protest. 4 C.F.R. sect. 21.8(e); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. A protest is
clearly meritorious where a reasonable agency inquiry into the
protest allegations would have shown facts disclosing the
absence of a defensible legal position. Core Tech Int'l
Corp.--Costs, B-400047.2, Mar. 11, 2009, 2009 CPD para. 59 at 6.
Additionally, while we consider corrective action to be prompt
if it is taken before the due date for the agency report
responding to the protest, we generally do not consider it to be
prompt if it is taken after that date. CDIC, Inc.--Costs,
B-277526.2, Aug. 18, 1997, 97-2 CPD para. 52 at 2.
Here, GSA did not take corrective action until after the filing
of its agency report on October 28 and after the subsequent
December 8 ADR conference. Further, our advising the parties
through outcome prediction ADR that the protest was likely to be
sustained on the identified ground was an indication that we
viewed that ground as clearly meritorious. National Opinion
Research Ctr.--Costs, B-289044.3, Mar. 6, 2002, 2002 CPD para.
55 at 3. Accordingly, we do not consider its corrective action
prompt.
Although we therefore recommend that Nationwide be reimbursed
its costs, we do so only with regard to the issue identified as
meritorious during the ADR conference. In this connection, when
appropriate, we will limit our recommendation for reimbursement
of protest costs where we determine that the successful and
unsuccessful protest grounds clearly are severable. See, e.g.,
BAE Tech. Servs., Inc.--Costs, B-296699.3, Aug. 11, 2006, 2006
CPD para. 122 at 3. In making this determination, we consider,
among other things, the extent to which the protest issues are
interrelated or intertwined, e.g., whether the successful and
unsuccessful issues share a common core set of facts, are based
on related legal theories, or are otherwise not readily
severable. See Sodexho Mgmt., Inc.--Costs, B-289605.3, Aug. 6,
2003, 2003 CPD para. 136 at 29.
We conclude that none of the other protest grounds raised in
Nationwide's original and supplemental protests was related to
the successful protest ground and, accordingly, those grounds
are clearly severable. We viewed the successful protest
ground--improper downgrading of the protester's proposal for
lack of a facility security clearance--as meritorious because
the agency's evaluation was based on a factor not set forth in
the solicitation.
In contrast, the other protest grounds were based on different
core sets of facts and were not based on interrelated legal
theories. The first and fourth grounds for protest (inadequate
debriefing and the alleged "pre-marketing" by the awardee) were
not further developed as they failed to state a basis for
protest. The protester's third original protest ground (failure
to consider its lower priced offer) and supplemental protest
ground (failure to evaluate its subcontractor) were evaluation
challenges, but challenged the reasonableness of the agency's
evaluation, not the application of an unstated evaluation
factor. Additionally, as noted, we advised the parties during
the ADR procedure that the supplemental protest ground appeared
meritless, inasmuch as it was not supported by the record.
Accordingly, we find Nationwide's other protest bases severable
from its successful argument, and therefore limit our
recommendation that Nationwide be reimbursed its protest costs
to its single successful issue. (Nationwide
IT Services, Inc. - Costs, B-404160.2, August 8, 2011)
(pdf)
RBS requests that
our Office recommend that the agency reimburse its costs of
filing and pursuing its protests. RBS argues that the Corps
unduly delayed taking corrective action in the face of its
clearly meritorious protest because the Corps' reevaluation was
done "without regard to any protest contentions" and "repeated
most of the mistakes seen in the first protest." RBS Request for
Costs, Mar. 24, 2011, at 2. RBS cites our decision in Holiday
Inn-Laurel--Protest and Request for Costs, B‑270860.3,
B-270860.4, May 20, 1996, 96-1 CPDpara. 259, to support its
request.
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys' fees, if, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. sect.
3554(c)(1)(A) (2006); Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2011); AAR Aircraft Servs.-Costs, B-291670.6, May 12,
2003, 2003 CPD para. 100 at 5. Thus, as a prerequisite to our
recommending the reimbursement of costs where a protest has been
settled by corrective action, not only must the protest have
been meritorious, but it also must have been clearly
meritorious, i.e., not a close question. Apptis Inc.-Costs,
B-402146.3, Mar. 31, 2010, 2010 CPD para. 123 at 4. A protest is
clearly meritorious where a reasonable agency inquiry into the
protester's allegations would reveal facts showing the absence
of a defensible legal position. Yardney Technical Prods.,
Inc.-Costs, B-297648.3, Mar. 28, 2006, 2006 CPD para. 65 at 4.
We have recognized, however, that the mere promise of corrective
action, without reasonably prompt implementation, has the
obvious effect of circumventing the goal of the bid protest
system for the economic and expeditious resolution of bid
protests. See Louisiana Clearwater, Inc.-Recon. and Costs,
B-283081.4, B-283081.5, Apr. 14, 2000, 2000 CPD para. 209 at 6.
Thus, where an agency fails to implement the promised corrective
action, or implements corrective action that fails to address a
clearly meritorious issue raised in an initial protest, such
that the protester is put to the expense of subsequently
protesting the very same procurement deficiency, the agency's
action has precluded the timely, economical resolution of the
protest. Id.
Here, there is no basis to conclude that the agency has unduly
delayed taking corrective action in response to a clearly
meritorious protest. In response to the first protest, the
agency promptly indicated that it would take corrective action.
To the extent that the protester maintains that it is entitled
to reimbursement of its costs for filing the second protest
because the Corps failed to implement its promised corrective
action, the record does not establish that RBS's protests were
clearly meritorious. Even where a protester alleges that an
agency failed to timely implement promised corrective action,
our recommendation that an agency reimburse a protester its
protest costs must be based upon a showing that a procurement
statute or regulation has been violated. See A-Ability Med.
Equip., Inc.‑Costs, B-403256.3, Apr. 4, 2011, 2011 CPD para. 81
at 3 n.3. The mere fact that an agency decides to take
corrective action does not establish that a statute or
regulation clearly has been violated. Contrack Int'l,
Inc.-Costs, B-401871.3, Feb. 17, 2010, 2010 CPD para. 122 at 4.
The Corps took corrective action in response to the protests
prior to submitting its reports, and thus we have not been
provided with a record of the agency's evaluation and selection
decision. Further record development would be necessary to
determine whether any of RBS's protest grounds had merit.
Although RBS assumes that its protests have merit based upon the
fact that the agency took corrective action in the face of two
similar protests, the mere fact that the Corps decided to take
corrective action does not establish that the protests were
clearly meritorious. See Contrack Int'l, Inc.-Costs, supra, at
4; Alaska Structures, Inc.-Costs, B‑298575.4, Jan. 22, 2007,
2007 CPD para. 15 at 8.
The request for entitlement to protest costs is denied. (Re-Engineered
Business Solutions, Inc.--Costs, B-404214.4, July 14, 2011)
(pdf)
As a general
rule, we recommend that a successful protester be reimbursed its
incurred costs with respect to all issues pursued, not merely
those upon which it prevails. AAR Aircraft Servs.--Costs,
B‑291670.6, May 12, 2003, 2003 CPD para. 100 at 9. In our view,
limiting recovery of protest costs in all cases to only those
issues on which the protester prevailed would be inconsistent
with the broad, remedial congressional purpose behind the
protest cost reimbursement provisions of the Competition in
Contracting Act of 1984, 31 U.S.C. sect. 3554(c)(1)(a) (2006).
AAR Aircraft Servs.--Costs, supra; TRESP Assocs., Inc.--Costs,
B‑258322.8, Nov. 3, 1998, 98–2 CPD para. 108 at 2. Nevertheless,
failing to limit the recovery of protest costs in all instances
of partial or limited success by a protester may also result in
an unjust cost recovery. Accordingly, in appropriate cases, we
have limited our recommendation for the award of protest costs
where a part of those costs is allocable to an unsuccessful
protest issue that is so clearly severable from the successful
issues as to essentially constitute a separate protest. See,
e.g., BAE Tech. Servs., Inc.--Costs, B‑296699.3, Aug. 11, 2006,
2006 CPD para. 122 at 3; Interface Floorings Sys., Inc.-Claim
for Attorneys' Fees, B‑225439.5, July 29, 1987, 87‑2 CPD para.
106 at 2‑3.
In determining whether protest issues are so clearly severable
as to essentially constitute separate protests, we consider,
among other things, the extent to which the issues are
interrelated or intertwined--i.e., the extent to which
successful and unsuccessful arguments share a common core set of
facts, are based on related legal theories, or are otherwise not
readily severable. See Sodexho Mgmt., Inc.--Costs, B‑289605.3,
Aug. 6, 2003, 2003 CPD para. 136 at 29.
In their requests for costs, KGL and IMG have asked our Office
to recommend that DLA reimburse the costs associated with all
the protest issues they pursued. While DLA concedes that both
protesters should be reimbursed their costs of pursuing the
price realism issue identified by our Office as clearly
meritorious during the ADR session, Response at 2, DLA asserts
that the remaining issues were not clearly meritorious and are
severable from the price realism issue. KGL and IMG maintain
that their remaining issues were intertwined with the price
realism issue and thus, should not be severed.
Even though our outcome prediction ADR was based on the likely
sustain of the price realism issue, in our view, the challenges
to Anham's technical proposal evaluation were intertwined with
and based on a related legal theory to the price realism issue.
In this regard, where, as here, a solicitation expressly
provides for evaluation of an offeror's understanding of the
requirements, based on the realism of proposed prices, the
agency is obliged to conduct a price realism analysis. Health
Net Fed. Servs., LLC, B‑401652.3, B‑401652.5, Nov. 4, 2009, 2009
CPD para. 220 at 19. Typically, this analysis consists of an
individualized approach to analyzing each proposal, including a
review of each offeror's cost elements and technical proposal.
Id. at 20; see Federal Acquisition Regulation sect. 15.404-1(d)
(consideration of "unique methods of performance and materials
described in the offeror's technical proposal"); Hughes STX
Corp., B‑278466, Feb. 2, 1998, 98-1 CPD para. 52 at 8 (protest
sustained where agency failed to consider offeror's technical
approach as part of realism evaluation).
While price realism and technical issues are not always
intertwined, see Basic Commerce and Indus., Inc.--Costs,
B‑401702.3, Feb. 22, 2010, 2010 CPD para. 258 at 4 (cost realism
issue severable from non-cost evaluation issues), here, the
price realism and technical issues are interrelated and not
readily severable. For example, KGL asserted that "Anham's price
does not reflect the costs associated with maintaining readily
accessible warehouse space, a sufficient amount of warehouse
space, separate facilities for pork storage, force protected
warehouse storage, and adequate truck transport," all issues
that it raised in greater detail in its technical challenges.
KGL Protest at 19. IMG asserted that Anham's "unreasonably and
unrealistically low proposed price" was "indicative of
substantial proposal and technical risk," and should have been
evaluated as "technically unacceptable." IMG Protest at 37. It
further argued that "Anham's lower, unrealistic price [could]
only be the result of unrealistic assumptions or
misunderstanding of contract requirements," and that the agency
report "fail[ed] to show that the agency analyzed Anham's
proposal to determine this." IMG Comments on Agency Report at
11. Based on the agency's need to review Anham's technical
proposal as part of its price realism analysis, we conclude that
the price realism and technical issues share a common legal
theory and underlying facts. Thus, KGL's and IMG's protest costs
related to these issues (including the risk evaluation) are
reimbursable.
We reach the opposite conclusion with regard to KGL's and IMG's
protests of DLA's evaluation of Anham's responsibility and past
performance; the protesters' own past performance and technical
evaluations; the conduct of discussions; and the best value
determination. These issues are neither clearly meritorious, nor
are they clearly intertwined with the price realism/Anham
technical evaluation issues. Rather, whether the agency's
evaluations in these areas were reasonable are based on
different legal theories and underlying facts than were relevant
to the successful price realism challenge. Thus, we do not
recommend payment of protest costs associated with these issues.
(KGL Food Services, WLL; Intermarkets
Global--Costs, B-400660.7; B-400660.8, June 20, 2011) (pdf)
Under the
Competition in Contracting Act of 1984 (CICA), our Office may
recommend that protest costs be reimbursed only where we find
that an agency's action violated a procurement statute or
regulation. 31 U.S.C. sect. 3554(c)(1) (2006). Our Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e) (2010), provide that we may
recommend that an agency pay the protester the reasonable costs
of filing and pursuing the protest where the agency decides to
take corrective action in response to the protest. This does not
mean, however, that we will recommend that costs be reimbursed
in every case in which an agency takes action that renders a
protest academic; rather, we will recommend that a protester be
reimbursed its costs only where the record established that (1)
the agency action that rendered the protest academic was taken
in response to the protest, see Takota Corp--Costs, B-299600.2,
Sept. 18, 2007, 2007 CPD para. 171 at 3, and (2) the agency
unduly delayed taking the action in the face of a clearly
meritorious protest. Baine Clark--Costs, B-290675.3, Sept. 23,
2002, 2002 CPD para. 166 at 2. We consider a protest to be
clearly meritorious when a reasonable agency inquiry into the
protester's allegations would show that the agency lacked a
defensible legal position, that is, they did not present close
questions for which there was no defensible legal position.
Triple Canopy, Inc.--Costs, B‑310566.9, B-400437.4, Mar. 25,
2009, 2009 CPD para. 62 at 3-4; SDA Inc.--Costs, B‑298216.2,
Sept. 11, 2006, 2006 CPD para. 133 at 2.
CFS argues that our Office should view its protest as clearly
meritorious because the Army lacked a defensible legal position
to the protest and unduly delayed taking corrective action until
93 days after CFS filed its protest. The Army responds that its
decision to take corrective action was a business decision, not
based on the merits of CFS's protest, and that it presented
persuasive and dispositive defenses to all of CFS's allegations.
The record shows that the agency's corrective action here was in
response to CFS's protest and was taken very late in the protest
process. As to the merits of the protest, we believe that the
agency's actions here, in negotiating revised option prices with
the contractor prior to the exercise of an option while
initiating a competitive procurement for the same services, are
subject to question. However, based on our review, we cannot
conclude that CFS's protest was clearly meritorious.
The protest argument that may have the most merit involves the
protester's assertion that the incentive option exercised was
not an "evaluated" option in accordance with FAR sect. 17.207(f)
and therefore cannot be exercised. That regulation states in
pertinent part:
Before exercising an option, the contracting officer shall
make a written determination for the contract file that
exercise is in accordance with the terms of the option, the
requirements of this section, and [FAR] Part 6. To satisfy
requirements of Part 6 regarding full and open competition,
the option must have been evaluated as part of the initial
competition and be exercisable at an amount specified in or
reasonably determinable from the terms of the basic contract.
FAR sect. 17.207(f). As noted, while the options included in
MDI's contract were specifically evaluated at the time of award,
shortly before the first of the incentive options were exercised
the option prices were increased from those included in the
contract as awarded. While not entirely clear from CFS's
protest, we presume this is the basis for its argument that the
option to be exercised was "unevaluated" and thus could not be
exercised. See Major Contracting Servs, Inc., B-401472, Sept.
14, 2009, 2009 CPD para. 170 at 6, recon. denied, Department of
the Army--Recon., B-401472.2, Dec. 7, 2009, 2009 CPD para. 250
(exercise of option to extend contract that was not evaluated as
part of the initial competition amounts to a contract extension
beyond the scope of the contract and therefore effectively
constitutes a new procurement subject to the competition
requirements of CICA).
We are unaware of any cases that specifically address the
propriety of the agency's actions here. Nor do we decide here
whether the exercise of the first incentive option violated any
procurement statute or regulation. In this regard, it is clear
that revised prices for the incentive options were not
considered in the evaluation of the proposals for award and that
these option prices were negotiated just before the first
incentive option was exercised. On the other hand, the record
demonstrates that these incentive options were evaluated, albeit
at different prices, when the contract was awarded. Moreover, an
agency has the authority to increase option prices pursuant to
the Changes clause of the contract, and to exercise these
options in appropriate circumstances, for example, where the
work requirements have changed from the original contract, so
long as the changes are within the scope of the contract. See
Bulova Techs., Inc., B‑252660, July 15, 1993, 93‑2 CPD para. 23
at 4-6 (options for which prices have been appropriately
increased within the scope of the contract can be exercised in
appropriate circumstances); Gulton Indus., Inc., Engineered
Magnetics Div., B‑203265, July 20,1982, 82-2 CPD para. 59 at
10-13 (same). Under the circumstances, we cannot find that the
protester's argument here was clearly meritorious inasmuch as
this involves a close question for which the agency had a
defensible legal position. See Triple Canopy, Inc.--Costs,
supra.
As to the issuance and cancellation of the RFP, CFS argues that
the Army's ex‑parte negotiations with MDI, even though MDI was a
prospective offeror under the RFP, were improper and thus the
agency could not cancel the RFP. We have found no cases
addressing the propriety of an agency renegotiating an option
price with the contractor prior to its exercise where an RFP has
already been issued for the option period but proposals have not
yet been received. FAR sect. 17.207(d) specifically charges the
contracting officer with the obligation to determine whether the
exercise of the option is the most advantageous method of
fulfilling the government's needs considering both price and
other factors. While this regulation allows for the issuance of
a solicitation to obtain offers that could be used to determine
whether they produce a better price or more advantageous offer
than available in the option, this regulation provides that this
method should not be used if it is anticipated that the existing
option is the best price available or that it is the more
advantageous offer. FAR sect. 17.207(d)(1). Moreover, FAR sect.
17.207(d)(2) provides another acceptable basis to make a
determination as to whether an option should be exercised as
follows: "[a]n informal analysis of prices or an examination of
the market indicates that the option price is better than prices
available in the market or that the option is the more
advantageous offer." We have found a reasonable basis exists to
cancel an RFP rather than to continue with a negotiated
procurement where an agency discovers that it is more
advantageous to exercise an option under an existing contract.
See Astronautics Corp. of Am., B-222414.2, B‑222415.2, Aug. 5,
1986, 86-2 CPD para. 147 at 2-3; cf. National Linen Serv.,
B-257112, B‑257312, Aug. 31, 1994, 94-2 CPD para. 94 at 5
(cancellation of invitation for bids based on potential cost
savings by obtaining laundry services under a proper
modification to an existing contract). Thus, these protest
allegations are not clearly meritorious.
Moreover, CFS has not shown that the exercise of the option was
not the most advantageous method of fulfilling Government's
need, price and other factors considered. See FAR sect.
17.207(c)(3). For example, CFS has not alleged that its offered
price would be lower than the price contained in the incentive
option contained in MDI's contract.
CFS's arguments about the possibility that MDI had knowledge of
information in the market survey, which assisted it in its
negotiations with the Army, and that the Army's actions were
otherwise biased or in bad faith were not clearly meritorious.
In this regard, the Army categorically denied these allegations,
which appear to be based upon pure speculation, and has provided
sworn statements from the affected contracting personnel to
support this denial. Government officials are presumed to act in
good faith, and a protester's claim that contracting officials
were motivated by bias or bad faith must be supported by
convincing proof; our Office will not attribute unfair or
prejudicial motives to procurement officials on the basis of
inference of supposition. Operation Support and Servs.,
B-299660.2, Sept. 24, 2007, 2007 CPD para. 182 at 3.
In sum, we find CFS's protest was not clearly meritorious and
deny its request that we recommend reimbursement of its protest
costs. (The CFS Group,
LLC--Costs, B-403539.3, May 13, 2011) (pdf)
After developing
the record, including obtaining an agency report and comments on
the report, our Office conducted an outcome prediction
alternative dispute resolution (ADR) conference. In the course
of the ADR, the cognizant GAO attorney advised the agency of her
view, based on the record, that the agency had misevaluated
Symvionics' past performance. Specifically, the GAO attorney
stated that the record indicated that in evaluating Symvionics'
past performance, the agency did not consider whether the task
order at issue was relevant as defined by the solicitation, that
is whether it satisfied the minimum contract value and man‑year
requirements and the requirement for management of personnel
performing engineering and either mathematical/statistical
analysis, computer science or information technology support.
The GAO attorney further advised the parties that the protest
likely would be sustained on that ground, with the
recommendation that the agency reevaluate Symvionics' past
performance in accordance with the solicitation. The agency
agreed to take corrective action consistent with the outlined
recommendation. The protester now requests that we recommend
reimbursement of the costs of filing and pursuing their
protests, including reasonable attorneys' fees.
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys' fees, if, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. sect.
3554(c)(1)(A) (2006); Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2010); AAR Aircraft Servs.--Costs, B‑291670.6 , May 12,
2003, 2003 CPD para. 100 at 6.
A protest is clearly meritorious where a reasonable agency
inquiry into the protest allegations would have shown facts
disclosing the absence of a defensible legal position. Core Tech
Int'l Corp.--Costs, B-400047.2, Mar. 11, 2009, 2009 CPD para. 59
at 6.
Here, the Air Force asserts that the RFP indicated that the
agency would evaluate past performance on the basis of previous
efforts and contracts and never indicated that various task
orders would be evaluated as individual or independent efforts.
As an initial matter, we note that our willingness to inform the
parties through outcome prediction ADR that a protest is likely
to be sustained, as we did here, is generally an indication that
the protest is viewed as clearly meritorious, and satisfies the
"clearly meritorious" requirement for purposes of recommending
reimbursement of protest costs. National Opinion Research
Ctr.--Costs, B-289044.3, Mar. 6, 2002, 2002 CPD para. 55 at 3.
Here, our conclusion that the protest likely would be sustained
was not based on any determination that the final rating was to
be assigned at the task order level rather than the contract
level. Rather, the GAO attorney noted that the record indicated
that in evaluating the contract under which the disputed task
order was issued, the agency did not consider the relevance of
the task order effort as defined by the solicitation, including
whether the effort was for management of personnel performing
engineering and either mathematical/statistical analysis,
computer science or information technology support. Regardless
of whether or not the final rating was assigned at the task
order level or the contract level, it was inconsistent with the
solicitation for the agency to base the rating on an effort that
was not evaluated for compliance with the solicitation
definition of relevance. Further, we believe a reasonable
inquiry would have shown facts disclosing the absence of a
defensible legal position.
With regard to whether corrective action is prompt, where, as
here, the merits of the issue were clearly discernable prior to
the agency report, corrective action taken after the agency
report is not prompt. CDIC, Inc.--Costs, B-277526.2, Aug. 18,
1997, 97-2 CPD para. 52 at 2.
We therefore recommend that Symvionics be reimbursed the costs
associated with filing and pursuing its protest on this issue,
including reasonable attorneys' fees. Symvionics should submit
its certified claim, detailing the time spent and costs
incurred, directly to the agency within 60 days of its receipt
of this decision. 4 C.F.R. sect. 21.8(f)(1). (Symvionics,
Inc.--Costs, B-403230.6, May 16, 2011) (pdf)
Greentree
requests that our Office recommend that the agency reimburse its
costs of filing and pursuing its protest of the terms of the
replacement solicitation. When a procuring agency takes
corrective action in response to a protest, our Office may
recommend that the agency reimburse the protester its costs
where, based on the circumstances of the case, we determine that
the agency unduly delayed taking corrective action in the face
of a clearly meritorious protest, thereby causing a protester to
expend unnecessary time and resources to make further use of the
protest process in order to obtain relief. 4 C.F.R. sect.
21.8(e) (2010); AAR Aircraft Servs.--Costs, B-291670.6, May 12,
2003, 2003 CPD para. 100 at 5. A protest is clearly meritorious
where a reasonable agency inquiry into the protest allegations
would have shown facts disclosing the absence of a defensible
legal position. Inter-Con Sec. Sys., Inc.; CASS, a Joint
Venture--Costs, B-284534.7, B-284534.8, Mar. 14, 2001, 2001 CPD
para. 54 at 3. Here, our willingness to inform the parties
through outcome prediction ADR that the protest was likely to be
sustained on the identified ground was an indication that we
view that ground as clearly meritorious for purposes of
recommending reimbursement of protest costs. T Square Logistics
Servs. Corp.--Costs, B-297790.4, Apr. 26, 2006, 2006 CPD para.
78 at 5.
The Army argues that this protest cannot be deemed clearly
meritorious overall because "Greentree was protesting numerous
solicitations under many theories" and "was not successful
overall in its protests and it had the opportunity to submit a
proposal on the revised solicitation." AR at 2. We find neither
merit nor logic in the Army's position. Greentree's unsuccessful
protest of the cancellation of the prior solicitation has no
bearing on the merits of its challenge to the adequacy of the
new solicitation. In this regard, Greentree is requesting
reimbursement of protest costs only with respect to its protest
of the terms of solicitation No. -899F. Moreover, the fact that
Greentree was provided an opportunity to submit a tender in
response to the solicitation also does not address whether
Greentree's protest of the solicitation terms was clearly
meritorious.
The Army also argues that, in concluding that the solicitation
was ambiguous, we failed to recognize the discretion given
transportation officers under the Defense Transportation
Regulation to make a best value decision. We disagree. In the
ADR conference, the GAO attorney advised the parties that we
were likely to sustain the protest and would recommend that the
Army clarify the basis for award. Making the basis for award
clear to vendors in the government's solicitation does not, in
any way, restrict the agency's discretion to make a best value
determination--it simply communicates the agency's intentions.
In short, we find Greentree's protest of the terms of
solicitation No. -899F to be clearly meritorious. As we
indicated in our ADR conference, we agree with Greentree that
solicitation No. -899F was ambiguous and needed to be amended.
The Army also contends that its corrective action was not unduly
delayed, citing AVIATE, L.L.C., B-275058.6, B-275058.7, Apr. 14,
1997, 97-1 CPD para.162. In this regard, the Army argues that in
the context of the procurement under the Defense Transportation
Regulation, there is "no case law directly on point with regard
to the discretion afforded the Transportation Officer in making
a best value determination." AR at 2.
In determining whether an agency's corrective action was unduly
delayed, we review the record to determine whether the agency
took appropriate and timely steps to investigate and resolve the
impropriety. Eagle Home Medical Corp.--Costs, B‑299821.3, Feb.
4, 2008, 2008 CPD para. 41 at 5. We generally do not consider
corrective action to be prompt if it is taken after the due date
for the agency report responding to the protest. Apptis
Inc.--Costs, B-402146.3, Mar. 31, 2010, 2010 CPD para. 123 at 4.
Here, we think the Army unduly delayed taking corrective action
in the face of a clearly meritorious protest. While we agree
that there may be little case law on procurements conducted
under the Defense Transportation Regulation, unlike the
situation we faced in AVIATE, the law is clear with respect to
an agency's obligation to inform competitors in a federal
procurement of the basis for its selection decision. In any
competitive federal procurement, competing firms must be
informed of the basis for selection and how their offers or
tenders will be evaluated. See, e.g., Richard S. Cohen,
B-256017.4, B-256017.5, June 27, 1994, 94-1 CPD para. 382 at 6.
Given that the Army elected to ignore this basic precept,
prepared a report defending its actions, required the protester
to file comments rebutting the agency's report before taking
corrective action, and required our office to convene an ADR
conference before acting, we conclude that the agency's
corrective action was unduly delayed.
We recommend that the Army reimburse the protester its costs of
filing and pursuing the protest of the terms of solicitation No.
-899F, including attorneys' fees. Greentree should submit its
claim for costs, detailing and certifying the time expended and
costs incurred, directly to the Army within 60 days of receipt
of this decision. 4 C.F.R. sect. 21.8(f)(1). (Greentree
Transportation Company, Inc.--Costs, B-403556.4, May 16,
2011) (pdf)
Iron Vine
requests that we recommend that the agency reimburse its costs
of pursuing its initial and supplemental protests. Iron Vine
argues that USAID unduly delayed taking corrective action where
Iron Vine's protest grounds were clearly meritorious. Based on
the record before us, we cannot conclude that Iron Vine's
initial protest grounds were clearly meritorious.
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys' fees, if, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. sect.
3554(c)(1)(A) (2006); Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2010); AAR Aircraft Servs.--Costs, B-291670.6, May 12,
2003, 2003 CPD para. 100 at 5. The mere fact that an agency
decides to take corrective action does not also establish that a
statute or regulation clearly has been violated. Contrack Int'l,
Inc.--Costs, B‑401871.3, Feb. 17, 2010, 2010 CPD para. 122 at 4.
Thus, as a prerequisite to our recommending the reimbursement of
costs where a protest has been settled by corrective action, not
only must the protest have been meritorious, but it also must
have been clearly meritorious, i.e., not a close question.
Apptis Inc.--Costs, B-402146.3, Mar. 31, 2010, 2010 CPD para.
123 at 4. A protest is clearly meritorious where a reasonable
agency inquiry into the protester's allegations would reveal
facts showing the absence of a defensible legal position.
Yardney Technical Prods., Inc.--Costs, B-297648.3, Mar. 28,
2006, 2006 CPD para. 65 at 4.
Here, we find no basis to conclude that Iron Vine's initial
protest grounds were clearly meritorious, which is an essential
prerequisite to its request for costs. See Taylor Consultants,
Inc.--Costs, B-400324.3, Feb. 2, 2009, 2009 CPD para. 37 at 3.
Although Iron Vine argued in its initial protest that USAID
failed to evaluate quotations in accordance with identified
evaluation factors, the agency responded that its evaluated
weaknesses corresponded to PWS tasks and the solicitation
provided for evaluating vendors' approaches to performing PWS
tasks. On this record, we do not find that the protest was
clearly meritorious with respect to whether the agency used
unstated factors in evaluating Iron Vine's quotation.
Iron Vine also argues that its assertion that USAID failed to
document its tradeoff analysis and selection decision was
clearly meritorious. The protester argues, specifically, that
certain requirements of Federal Acquisition Regulation (FAR)
Part 15 were not met here. However, as the agency argues, the
procurement was conducted under FAR Subpart 8.4, not FAR Part
15. For procurements conducted under FAR Subpart 8.4 and
requiring a statement of work, FAR sect. 8.405-2(e) designates
the minimum documentation requirements. USGC Inc., B-400184.2 et
al., Dec. 24, 2008, 2009 CPD para. 9 at 8-9.
We have reviewed the documentation--and the rationale for the
selection decision set forth therein--and we are not prepared to
conclude that the documentation was inadequate. As a result, we
do not find this protest ground to be clearly meritorious.
The request for entitlement to protest costs is denied. (Iron
Vine Security, LLC - Costs, B-403578.3, April 15, 2011)
(pdf)
CCite requests
that we find that the protester should be reimbursed its costs
of filing and pursuing its protests, because the Army has
unreasonably delayed implementing the promised corrective
actions that caused our Office to dismiss its protests as
academic. We disagree.
We have recognized that the reimbursement of protest costs may
be appropriate where an agency does not timely implement the
promised corrective action that led to the dismissal of an
earlier protest. See AdaRose Inc--Protest and Costs, B‑299091.2,
Jan. 14, 2008, 2008 CPD para. 18 at 4; Louisiana Clearwater,
Inc.--Recon. and Costs, B-283081.4, B-283081.5, Apr. 14, 2000,
2000 CPD para. 209 at 6; Commercial Energies, Inc.--Recon. and
Declaration of Entitlement to Costs, B‑243718.2, Dec. 3, 1991,
91-2 CPD para. 499 at 6. Our Office has also found that
months-long delays do not by themselves constitute an undue
delay where an agency reasonably justifies or explains those
delays. See, e.g., J&J/BMAR Joint Venture, LLP--Costs,
B-290316.7, July 22, 2003, 2003 CPD para. 129 at 3 (9-month
delay in the implementation of corrective action was not an
undue delay).
Here, the Army states that following the dismissal of CCite's
protests, in early November 2010, the agency transferred the
procurement to a new contracting office "to provide a fresh
perspective on a problematic procurement." CO's Statement,
B‑402792.5, B-403769.2, at 3. The agency's contract specialist
in the new contracting office began reviewing the requirements
and, on December 17, 2010, drafted a request for proposals (RFP)
for these requirements. AR, B-403769.2, Memorandum of Law, at 5.
Revisions were made to the draft RFP in January 2011. On
February 16, the Army posted a synopsis of its requirements on
the FedBizOpps website, and on February 19, the RFP was posted
on the website as a small business set-aside. The RFP has since
been admended three times. The closing date for receipt of
proposals was March 3.
The record shows that the Army did not unduly delay implementing
its promised corrective action. Instead, from the time the Army
proposed corrective action in October, 2010, until the issuance
of the RFP as a small business set-aside four months later (in
February, 2011), the Army acted as it promised in its corrective
action letter. Accordingly, we find no basis to recommend that
CCite should be reimbursed its costs for filing and pursuing its
protests.
The request is denied. (Computer
Cite--Costs, B-402792.5; B-403769.2, April 14, 2011) (pdf)
A-Ability
requests that we recommend that the agency pay the protest costs
associated with both protests, arguing that the VA's corrective
action in response to the first protest failed to address a
clearly meritorious protest allegation, and that the agency's
failure to take appropriate corrective action required the
protester to file a second protest.
Where a procuring agency takes corrective action in response to
a protest, we may recommend that it reimburse the protester its
protest costs where, based on the circumstances of the case, we
determine that the agency unduly delayed taking corrective
action in the face of a clearly meritorious protest, thereby
causing the protester to expend unnecessary time and resources
to make further use of the protest process in order to obtain
relief. Taylor Consultants, Inc.--Costs, B-400324.3, Feb. 2,
2009, 2009 CPD para. 37 at 3. Generally, when an agency takes
corrective action before the due date for its report, our Office
regards such action as prompt and will not recommend
reimbursement of costs. The Sandi-Sterling Consortium--Costs,
B‑296246.2, Sept. 20, 2005, 2005 CPD para. 173 at 2-3. We have
recognized, however, that the mere promise of corrective action,
without reasonably prompt implementation, has the obvious effect
of circumventing the goal of the bid protest system for the
economic and expeditious resolution of bid protests. See
Louisiana Clearwater, Inc.--Recon. and Costs, B-283081.4,
B-283081.5, Apr. 14, 2000, 2000 CPD para. 209 at 6. Thus, where
an agency fails to implement the promised corrective action, or
implements corrective action that fails to address a clearly
meritorious issue raised in an initial protest, such that the
protester is put to the expense of subsequently protesting the
very same procurement deficiency, the agency's action has
precluded the timely, economical resolution of the protest. Id.
Here, there is no basis to conclude that the agency has unduly
delayed taking corrective action in response to a clearly
meritorious protest. In response to the first protest filed by
A-Ability, the agency promptly indicated that it would take
corrective action. To the extent A-Ability maintains that its
protest costs are justified because the agency has taken
"corrective action" in response to A-Ability's second protest,
A-Ability's argument is misplaced. A-Ability's second protest
was not rendered academic based on the agency's representation
that it would correct the same evaluation issues raised in
A‑Ability's first protest. Rather, the protest was rendered
academic for reasons not directly related to the protest issues
raised by A‑Ability--the agency's decision to cancel and
re-issue the solicitation in order to clarify its requirements
and evaluation criteria. Since A-Ability's second protest was
rendered academic for reasons not directly related to the
protest allegations, there was no corrective action; that is,
there was no indication that the agency recognized the merits of
the protest and was taking action to remedy the impropriety
identified by the protester.[3] See Digital Sys. Group,
Inc.‑‑Entitlement to Costs, B-257835.2, Apr. 3, 1995, 95-1 CPD
para. 173. Accordingly, there is no basis for recommending the
award of costs. (A-Ability Medical
Equipment, Inc.--Costs, B-403256.3, April 4, 2011) (pdf)
Under the Competition in Contracting Act of 1984, our Office
may recommend that protest costs be reimbursed only where we
find that an agency's action violated a procurement statute or
regulation. 31 U.S.C. sect. 3554(c)(1) (2010). Our Bid Protest
Regulations provide that, where the contracting agency decides
to take corrective action in response to a protest, we may
recommend that the protester be reimbursed the costs of filing
and pursuing its protest, including reasonable attorneys' fees.
4 C.F.R. sect. 21.8(e) (2010). This does not mean that costs
should be reimbursed in every case in which an agency decides to
take corrective action; rather, a protester should be reimbursed
its costs where an agency unduly delayed its decision to take
corrective action in the face of a clearly meritorious protest.
Griner's-A-One Pipeline Servs., Inc.--Costs, B-255078.3, July
22, 1994, 94-2 CPD para. 41 at 5.
The protester recognizes that, as a general matter, when an
agency takes corrective action before the due date set for
receipt of the agency report, our Office views such action as
prompt and will not recommend the reimbursement of costs, even
where the protest is clearly meritorious. The Sandi-Sterling
Consortium--Costs, B‑296246.2, Sept. 20, 2005, 2005 CPD para.
173 at 2-3. Livanta argues, however, that this general rule
should not apply here given the agency's active defense of the
protest, which included the filing of a request for partial
dismissal and the early submission of documents, which caused
Livanta to incur significant costs that would have been
unnecessary if the agency "had promptly and reasonably
investigated the matter." Request at 2.
With regard to the agency's dismissal request, an agency's
pursuit of a reasonable procedural litigation strategy before
our Office does not constitute undue delay in taking corrective
action. Carlson Wagonlit Travel--Request for Declaration of
Entitlement to Costs, B-266337.3 et al., July 3, 1996, 96-2 CPD
para. 99 at 4. A contracting agency, in defending protests filed
with our Office, should be permitted to vigorously assert
procedural and substantive defenses in good faith without having
to risk the assessment of costs. Id. This is especially true
where, as here, our Office granted the agency's motion for
partial dismissal. See id. There is simply no basis to assert
that the agency's good faith, successful efforts to narrow the
scope of the protest should result in a recommendation that it
pay the protester's costs, where the agency took corrective
action prior to the due date for the agency report.
Moreover, we conclude that the agency's corrective action was
prompt, notwithstanding the fact that the agency produced
relevant documents in advance of the agency report due date, and
thereby may have caused the protester to expend the time and
expense in reviewing these documents. Early document production,
which is something agencies provide voluntarily, facilitates the
efficient resolution of protests since it allows for the early
resolution of issues concerning the scope of the agency's
document production in response to the protest and because it
can lead to the identification of supplemental protest issues
early in the protest process, thereby affording protesters and
our Office greater flexibility in resolving such issues. Given
these considerations, it would not be appropriate to penalize
agencies, by subjecting them to the payment of protest costs,
solely for utilizing this highly useful, but voluntary process.
Thus, we find the agency's corrective action--initiated prior to
the due date for the agency report--to have been prompt and to
not warrant payment of protest costs. (Livanta,
LLC-Costs, B-404215.2, April 5, 2011) (pdf)
By letter dated
October 4, the Army notified our Office of its intent to take
corrective action by terminating the HPS contract and
reexamining its noncompetitive acquisition strategy. We
concluded that the Army's actions rendered Firetrace's protest
of the sole-source contract award to HPS academic and, on
October 7, we dismissed the protest. Firetrace Aerospace, LLC,
B-403193, B-403193.2, Oct. 7, 2010.
Firetrace requests that our Office recommend that the agency
reimburse the protester's costs of filing and pursuing its June
30 protest. Firetrace argues that the Army unduly delayed taking
corrective action--as evidenced by its failure to do so until
after filing of the agency report and submission of comments by
the protester--and that its protest was clearly meritorious. The
agency opposes Firetrace's request, arguing that the protest
here was not clearly meritorious.
Under the Competition in Contracting Act of 1984 (CICA), our
Office may recommend that protest costs be reimbursed where we
find that an agency's action violated a procurement statute or
regulation. 31 U.S.C. sect. 3554(c)(1). Our Bid Protest
Regulations further provide that where the contracting agency
decides to take corrective action in response to a protest, we
may recommend that the protester be reimbursed the costs of
filing and pursuing its protest, including reasonable attorneys'
fees. 4 C.F.R. sect. 21.8(e) (2010).
Our Regulations do not contemplate a recommendation for the
reimbursement of protest costs in every case in which an agency
takes corrective action, but rather only where an agency unduly
delays taking corrective action in the face of a clearly
meritorious protest. Waterfront Techs., Inc.--Costs, B-401948.8,
Sept. 14, 2010, 2010 CPD para. 232 at 3. Thus, as a prerequisite
to our recommending the reimbursement of costs where a protest
has been settled by corrective action, not only must the protest
have been meritorious, but it also must have been clearly
meritorious, i.e., not a close question. Id. A protest is
clearly meritorious where a reasonable agency inquiry into the
protester's allegations would reveal facts showing the absence
of a defensible legal position. Information Ventures,
Inc.--Costs, B‑294567.2, Nov. 16, 2004, 2004 CPD para. 234 at 2.
Here, based on the record presented (including the agency report
and the protester's comments thereto), we cannot conclude that
Firetrace's protest was clearly meritorious. The Army explained,
in response to Firetrace's protest, why an approved source
requirement for the HEMTT FTFS blanket kits was necessary and
not unduly restrictive: "[i]t is beyond cavil that an agency
need not risk injury to personnel or property in order to
conduct a competitive acquisition." AR, July 30, 2010, at 1
(citing Signals & Sys., Inc., B-288107, Sept. 21, 2001, 2001 CPD
para. 168 at 10). Further, the Army argued that while it
restricted the contract to an approved product or source and
utilized a qualification requirement, it provided other
potential sources like Firetrace with a reasonable opportunity
to qualify. As Firetrace was both required to seek qualification
in advance and independent of any specific acquisition, and
contributed to the failure to obtain source approval prior to
award, the Army argued, there was no agency obligation to delay
award to determine if or when Firetrace would become an approved
source. Lastly, the Army asserted that the J&A executed here in
support of the sole-source award to HPS as well as its internal
source approval program regulation met the statutory and
regulatory requirements for establishing a qualification
requirement. Based on the record here, and even resolving doubts
in Firetrace's favor, the issues presented here were indeed
close questions.
The request for a recommendation that the agency reimburse
Firetrace's protest costs is denied. (Firetrace
Aerospace, LLC--Costs, B-403193.4, December 17, 2010) (pdf)
When a procuring
agency takes corrective action in response to a protest, our
Office may recommend reimbursement of protest costs, including
reasonable attorneys' fees, if, based on the circumstances of
the case, we determine that the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest,
thereby causing the protester to expend unnecessary time and
resources to make further use of the protest process in order to
obtain relief. Competition in Contracting Act of 1984 (CICA), 31
U.S.C. sect. 3554(c)(1)(A) (2006); Bid Protest Regulations, 4
C.F.R. sect. 21.8(e). A protest is clearly meritorious where a
reasonable agency inquiry into the protest allegations would
have shown facts disclosing the absence of a defensible legal
position. While we consider corrective action to be prompt if it
is taken before the due date for the agency report responding to
the protest, we generally do not consider it to be prompt where
it is taken after that date. Alsalam Aircraft Co.--Costs,
B‑401298.3, Nov. 5, 2009, 2009 CPD para. 208 at 3.
Ordinarily, we would not regard a protest as clearly meritorious
where resolution of the protest required further record
development, such as a hearing, to complete and clarify the
record. However, when corrective action is taken by an agency
after a hearing has been scheduled, we may still conclude that
the protest is clearly meritorious, where, as here, that
conclusion is otherwise established by the record. Eagle Home
Med. Corp.--Costs, B- 299821.3, Feb. 4, 2008, 2008 CPD para. 41
at 4 n.4.
In our view, BCI's protest challenging the adequacy of the
Navy's cost realism analysis was clearly meritorious on the
record provided to our Office with the agency report. In short,
the record lacked support for the Navy's conclusion that McKean
could perform as it had proposed for the costs provided. Indeed,
as BCI pointed out in its comments on the agency report, the
evaluators' expressed concerns about the realism of McKean's
rates remained unresolved when the Navy selected McKean for
award. Based on our review, we are not persuaded that there is
any meaningful difference between the Navy's explanation of an
error in the "methodology" of the cost realism analysis, and
BCI's challenge.
As a general rule, we recommend that a successful protester be
reimbursed protest costs with respect to all issues pursued, not
merely those upon which it prevails. Nevertheless, in
appropriate cases, we have limited our recommendation for the
award of protest costs where a part of those costs is allocable
to an unsuccessful protest issue that is so clearly severable
from the successful issues that it essentially constitutes a
separate protest. In determining whether protest issues are so
clearly severable as to essentially constitute separate
protests, we consider, among other things, the extent to which
the issues are interrelated or intertwined--i.e., whether the
successful and unsuccessful arguments share a common set of
facts, are based on related legal theories, or are otherwise not
readily severable. Core Tech Int'l Corp.--Costs, B-400047.2,
Mar. 11, 2009, 2009 CPD para. 59 at 8. We view BCI's challenges
to the non-cost evaluation (which it has not shown were clearly
meritorious) as severable from the challenge to the cost realism
analysis because the questions involved distinct aspects of the
record, and were not intertwined factually or legally. (Basic
Commerce and Industries, Inc.--Costs, B-401702.3,February
22, 2010) (pdf)
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest costs
where, based on the circumstances of the case, we determine that
the agency unduly delayed taking corrective action in the face
of a clearly meritorious protest, thereby causing the protester
to expend unnecessary time and resources to make further use of
the protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e) (2010); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. A protest is
"clearly meritorious" where a reasonable agency inquiry into the
protester's allegations would reveal facts showing the absence
of a defensible legal position. First Fed. Corp.--Costs,
B‑293373.2, Apr. 21, 2004, 2004 CPD para. 94 at 2. With respect
to the promptness of the agency's corrective action under the
circumstances, we review the record to determine whether the
agency took appropriate and timely steps to investigate and
resolve the impropriety. See Chant Eng'g Co., Inc.--Costs,
B‑274871.2, Aug. 25, 1997, 97-2 CPD para. 58 at 4; Carl Zeiss,
Inc.--Costs, B-247207.2, Oct. 23, 1992, 92‑2 CPD para. 274 at 4.
While we consider corrective action to be prompt if it is taken
before the due date for the agency report responding to the
protest, we generally do not consider it to be prompt where it
is taken after that date. See CDIC, Inc.--Costs, B-277526.2,
Aug. 18, 1997, 97-2 CPD para. 52 at 2.
The agency opposes the requested recommendation, maintaining
that the issues raised in the initial and first two supplemental
protests were not clearly meritorious, that FSI's third
supplemental protest was the first time FSI challenged the
qualifications of KIRA's key personnel and provided specifics
about the lack of those qualifications, and that its corrective
action thus was prompt, since it was taken prior to its report
in response to the third supplemental protest. Agency Response
at 3; see AGFA HealthCare Corp.--Costs, B‑400733.6, Apr. 22,
2009, 2009 CPD para. 90 at 3-4 (corrective action taken on
supplemental issues considered prompt where initial issues were
not clearly meritorious).
We do not agree with the agency that FSI's challenge to the
qualifications of KIRA's key personnel was first raised in the
third supplemental protest; rather, we find that this argument
was part of FSI's initial protest alleging
misrepresentation/bait and switch. In this regard, in its
initial protest, FSI listed three possible explanations for
KIRA's alleged attempts to replace its proposed assistant
project manager (APM), including the assertion that the APM
failed to meet the PWS requirements. Initial Protest at 14. FSI
also asserted in its original protest that KIRA "wholly failed
to propose all eight (8) key personnel that met the
[solicitation] requirements and who were available and committed
to this contract." Id. at 18. In our view, these allegations
were sufficiently specific that a reasonable investigation by
the agency would have led it to conclude that some--if not
all--of KIRA's proposed key personnel failed to meet the PWS
requirements.
For example, while the solicitation [deleted] required [deleted]
to have completed a [deleted], the resume for KIRA's [deleted]
did not indicate any such [deleted]. Similarly, even though the
[deleted] was required to have a minimum of [deleted] the resume
for KIRA's [deleted] showed less experience. The resumes of
other key personnel (including the [deleted]) also lacked
evidence of required [deleted]. We note that, even though the
TET rated KIRA's proposal satisfactory (defined as "meets all
requirements"), it recognized that KIRA's [deleted], and the SSA
recognized [deleted]. Consensus Technical Factor Ratings at 2-3;
Vendor Selection Report at 5. Having waited until after the
filing of its report and FSI's comments and supplemental
protest, we find that the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest
assertion.
However, we find no undue corrective action delay with regard to
the remainder of FSI's protest grounds, because those issues
were not clearly meritorious. Prior to receipt of the agency
report, we found a number of FSI's initial and supplemental
issues failed to state valid bases of protest.[1] See AGFA
HealthCare Corp.--Costs, supra (dismissed issues are not clearly
meritorious). We do not find the remaining issues--concerning
the evaluation of FSI's proposal--to be clearly meritorious
because further development of the record would have been
required in order for us to determine their merits. In this
regard, the agency provided detailed responses in its report and
we were planning to request a supplemental report addressing
FSI's comments and supplemental issues at the time of the
agency's corrective action.
Our recommendation for reimbursement does not extend beyond
FSI's challenge to the evaluation of the qualifications of
KIRA's key personnel. While, as a general rule, we consider a
successful protester entitled to be reimbursed costs incurred
with respect to all issues pursued, not merely those upon which
it prevails (Burns and Roe Servs. Corp.--Costs, B‑310828.2, Apr.
28, 2008, 2008 CPD para. 81 at 2-3), we nevertheless will limit
a recommendation for reimbursement of costs where we determine
that successful and unsuccessful protest grounds are clearly
severable. See, e.g., BAE Tech. Servs., Inc.--Costs, B‑296699.3,
Aug. 11, 2006, 2006 CPD para. 122 at 3. In making this
determination, we consider, among other things, the extent to
which the claims are interrelated or intertwined, e.g., whether
the successful and unsuccessful claims share a common core set
of facts, are based on related legal theories, or are otherwise
not readily severable. See Sodexho Mgmt., Inc.--Costs,
B‑289605.3, Aug. 6, 2003, 2003 CPD para. 136 at 29. Here, we
conclude that FSI's meritorious issue concerning the evaluation
of KIRA's proposed key personnel is factually unrelated to, and
therefore clearly severable from, the remaining technical
evaluation issues, all of which concern the evaluation of FSI's
own proposal. Accordingly, our recommendation for reimbursement
is limited to FSI's costs related to the key personnel
evaluation issue. (Facility
Services Management, Inc.--Costs, B-402757.5, September 27,
2010) (pdf)
Apptis requests
that we recommend that the agency reimburse its costs of
pursuing its initial and supplemental protests. For the reasons
discussed below, we agree with the Army that reimbursement is
not warranted here because the agency's corrective action was
prompt with regard to the supplemental protest arguments, and
because the initial protest arguments were not clearly
meritorious.
When a procuring agency takes corrective action in response to a
protest, our Office may recommend reimbursement of protest
costs, including reasonable attorneys' fees, if, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 31 U.S.C. sect.
3554(c)(1)(A) (2006); Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2009); AAR Aircraft Servs.--Costs, B-291670.6, May 12,
2003, 2003 CPD para. 100 at 6. The mere fact that an agency
decides to take corrective action does not also establish that a
statute or regulation clearly has been violated. Id. Thus, as a
prerequisite to our recommending the reimbursement of costs
where a protest has been settled by corrective action, not only
must the protest have been meritorious, but it also must have
been clearly meritorious, i.e., not a close question. PADCO,
Inc.--Costs, B-289096.3, May 3, 2002, 2002 CPD para. 135 at 3. A
protest is clearly meritorious where a reasonable agency inquiry
into the protester's allegations would reveal facts showing the
absence of a defensible legal position. Yardney Technical
Prods., Inc., B-297648.3, Mar. 28, 2006, 2006 CPD para. 65 at 4.
Additionally, while we consider corrective action to be prompt
if it is taken before the due date for the agency report
responding to the protest, we generally do not consider it to be
prompt where it is taken after that date. AGFA HealthCare
Corp.--Costs, B-400733.6, Apr. 22, 2009, 2009 CPD para. 90 at
3-4.
We conclude that the Army's corrective action was prompt with
regard to Apptis' supplemental protest arguments. As discussed
above, the protester raised a number of supplemental arguments
on November 27. Because the agency's corrective action took
place prior to the submission of its supplemental agency report
responding to these arguments, such that Apptis did not need to
expend unnecessary time or resources responding to the report,
we view the corrective action as prompt. See AGFA HealthCare
Corp.--Costs, supra.
With regard to the initial protest arguments cited by the
protester in its request for reimbursement, we conclude, as
explained below, that none of them are clearly meritorious. As
discussed above, our Office requested additional information
from the agency in order to further develop the record with
respect to these issues. In our view, the need for such
additional development demonstrates that the protest arguments
were not clearly meritorious. See Alaska Structures, Inc.-Costs,
B-298575.4, Jan. 22, 2007, 2007 CPD para. 15 at 6 (requesting
additional record development by the agency in response to
protester's comments demonstrates that a protest issue is a
"close question," that is, not clearly meritorious).
First, Apptis contends that the Army improperly failed to
consider its proposal in the price-technical tradeoff analysis
for award. As discussed above, however, the agency did not
consider the protester's proposal for award because the
solicitation stated that only offerors whose proposals received
an overall technical score of acceptable or better would be
eligible for award. In light of the protester's overall
technical rating of marginal, we think that the agency's
decision here was consistent with the solicitation and provides
no basis to conclude that this protest ground was clearly
meritorious. Instead, for us to conclude that this ground of the
protest was clearly meritorious, Apptis must demonstrate that
its proposal should have received an overall rating of
acceptable or better. As discussed below, we do not find Apptis'
challenges to the evaluation of its technical proposal--which
received marginal ratings under three of the five evaluation
factors--to be clearly meritorious.
Next, Apptis argues that the Army unreasonably rated its
proposal as marginal under the technical approach factor. The
overall marginal rating for this factor was based on one
weakness and two significant weaknesses regarding the
protester's transition approach, which was one of four
equally-weighted subfactors under the technical approach factor.
AR, Tab 10, ADM, at 7. The agency concluded that these
weaknesses outweighed the single significant strength that
related to its understanding of ITSM and incident and problem
management requirements. Id.
Apptis argues that the weaknesses assessed for its transition
approach were not reasonable. As discussed above, we asked the
agency to provide more information concerning its evaluation of
Apptis' proposed transition. GAO Email, Dec. 2, 2009, at 1.
Because the agency took corrective action before providing this
information, the record is not complete, and provides no basis
to find that this protest argument is clearly meritorious. See
Alaska Structures, Inc.--Costs, supra.
The protester also contends that because the overall factor
rating of marginal was based on weaknesses under a single
subfactor, the agency unreasonably did not accord equal weight
to all of the four subfactors. Our Office has recognized that
where, as here, a solicitation does not disclose the relative
weight of evaluation factors or subfactors in a FAR Part 15
procurement, they should be considered approximately equal in
importance or weight. Bio-Rad Labs., Inc., B-297553, Feb. 15,
2006, 2007 CPD para. 58 at 6. The Army does not dispute that the
subfactors should have been equally weighted, but argues that it
reasonably concluded that the weaknesses regarding transition
outweighed a single strength relating to the first two
subfactors, and that the overall rating of marginal was
reasonable. See AR, Tab 10, ADM, at 7. In our view, the
protester incorrectly assumes that an assessment of weaknesses
under one of four equally-weighted subfactors precludes an
overall rating of marginal. The TOPR stated that a "marginal"
rating reflects a proposal that "does not demonstrate a full
understanding of all the requirements and may pose a risk that
the offeror might fail to perform satisfactorily without
significant Government oversight or participation." TOPR at 9.
We think that, under the evaluation standards announced in the
solicitation, weaknesses relating to an offeror's understanding
of the requirements could have reasonably resulted in an overall
rating of marginal for the technical approach factor--assuming
the agency's assessment of the weaknesses was reasonable.
Next, Apptis argues that the Army failed to identify or give
credit to Apptis for its experience or knowledge of the BOC
requirements for the solicitation. Here also, our Office asked
the agency for additional information regarding its evaluation
of Apptis' proposal. For the reasons discussed above, we think
that the record here was not adequately developed, and thus does
not provide a basis for us to conclude that the initial protest
argument was clearly meritorious.
Finally, Apptis argues that the agency unreasonably evaluated
its proposal under the service desk/ITSM experience factor.
Specifically, the protester contends that although the TOPR
stated that offerors would be evaluated on the basis of either
corporate or proposed staff experience, see TOPR at 6, the
agency assessed weaknesses in the protester's proposal based on
an alleged lack of staff experience, to the disregard of its
demonstrated corporate experience. AR, Tab 10, ADM, at 8. The
protester also contends that the agency unreasonably concluded
that its proposed staff did demonstrate the required experience.
In its response to the protest, the Army acknowledged that
Apptis' proposal demonstrated corporate experience, but argues
that the agency viewed the experience as insufficiently related
to the requirements of the solicitation. CO Statement at 16. As
the protester notes in its comments on the AR, however, the
agency's position is not reflected in the contemporaneous
record; in fact, the protester's corporate experience is not
discussed. See AR, Tab 8, TEP Evaluation, at 5; Tab 10, ADM, at
8.
Although we did not request an additional response from the
agency on this issue, we now view the record as requiring
additional development concerning whether the agency's
evaluation reflects contemporaneous judgments regarding Apptis'
corporate experience, as well as other areas of the agency's
evaluation. For this reason, do not think that this issue meets
our requirement that a protest argument be clearly meritorious,
i.e. not a close question.
The request for entitlement to protest costs is denied. (Apptis
Inc.--Costs, B-402146.3, March 31, 2010) (pdf)
DGR argues that
it should be reimbursed for the costs that it incurred in
preparing its comments on the agency report because the filing
of these comments would have been unnecessary if the agency had
terminated Inuit's contract at the time it was informed that SBA
had determined Inuit to be other than small and thus ineligible
for award in mid-September.
Under the Competition in Contracting Act of 1984, our Office may
recommend that protest costs be reimbursed where we find that
the agency's action violated a procurement statute or
regulation. 31 U.S.C. sect. 3554(c)(1) (2006). Our Bid Protest
Regulations provide that where the contract agency decides to
take corrective action in response to a protest, we may
recommend that the protester be reimbursed the costs of filing
and pursuing its protest, including reasonable attorneys' fees.
4 C.F.R. sect. 21.8(e) (2009). This does not mean that we will
recommend that costs be reimbursed in every case in which an
agency takes action that renders a protest academic; rather, we
will recommend that a protester be reimbursed its costs only
where the record establishes that (1) the agency action that
rendered the protest academic was taken in response to the
protest, and (2) the agency unduly delayed taking the action in
the face of a clearly meritorious protest. RANA Tech.--Costs,
B‑400471.2, Feb. 3, 2009, 2009 CPD para. 38 at 3. (DGR
Associates, Inc.--Costs, B-401791.5, February 16, 2010) (pdf)
When a procuring
agency takes corrective action in response to a protest, our
Office may recommend reimbursement of protest costs, including
reasonable attorneys' fees, if, based on the circumstances of
the case, we determine that the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest,
thereby causing the protester to expend unnecessary time and
resources to make further use of the protest process in order to
obtain relief. Competition in Contracting Act of 1984 (CICA), 31
U.S.C. sect. 3554(c)(1)(A) (2006); Bid Protest Regulations, 4
C.F.R. sect. 21.8(e) (2009); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. We generally
consider corrective action to be prompt if it is taken before
the due date for the agency report responding to the protest,
but not where it is taken after that date. CDIC, Inc.--Costs,
B-277526.2, Aug. 18, 1997, 97-2 CPD para. 52 at 2. A protest is
clearly meritorious where a reasonable agency inquiry into the
protest allegations would have shown facts disclosing the
absence of a defensible legal position. Core Tech Int'l
Corp.--Costs, B-400047.2, Mar. 11, 2009, 2009 CPD para. 59 at 6.
Here, as noted, we found the record showed that the agency had
misevaluated Alion's cost proposal in a manner that was
prejudicial to the protesters, since Alion had deviated
significantly from the proposed costs of the other offerors due
to its significantly lower level of effort. Notwithstanding this
clear evaluation error, the agency elected to defend its
evaluation, which caused the protesters to incur the expense of
continuing to pursue their protests. These are precisely the
expenses our requirement for prompt agency action is intended to
avoid. We therefore recommend that the protesters be reimbursed
the costs associated with filing and pursuing their protests on
this issue, including reasonable attorneys' fees.
As for the protest costs associated with the protesters'
remaining arguments, we did not consider the merits of those
arguments because, as the GAO attorney advised the parties
during the ADR procedure, those assertions would be rendered
academic by the agency's proposed corrective action. Since we
find that those issues are not clearly meritorious on their
face, and since we do not decide academic protests, Dyna-Air
Eng'g Corp., B-278037, Nov. 7, 1997, 97-2 CPD para. 132, there
is no basis for us to recommend reimbursement of the protest
costs related to their pursuit.
The requests are granted as detailed above. (ManTech
Systems Engineering Corporation; TWD & Associates, Inc.,
B-401542.6; B-401542.7, December 22, 2009) (pdf)
Talladega
Machinery & Supply Company, Inc. of Talladega, Alabama, requests
that we recommend that it be reimbursed the costs of filing and
pursuing its protest of the award of a contract to Valley
Machine Company (VMC) under request for proposals (RFP) No.
W911KF-08-R-0010, issued by the Department of the Army for the
abrasive cleaning, light oiling, and painting of combat vehicle
parts; the RFP was issued to augment the agency's in-house
performance of such services at the Anniston Army Depot (ANAD).
We dismissed the protest after the agency notified us that it
was terminating the awardee's contract because of changed
requirements; specifically, the agency reported that, due to
workload reductions, it no longer had a need for the solicited
services. The protester, alleging that its protest was clearly
meritorious and the agency unreasonably delayed taking
corrective action in response to the protest, contends that it
should recover its protest costs.
(sections deleted)
Our Bid
Protest Regulations, 4 C.F.R. sect. 21.8(e) (2009), provide we
may recommend that an agency pay protest costs where the agency
decides to take corrective action in response to the protest.
This does not mean, however, that we will recommend that costs
be reimbursed in every case in which an agency takes action that
renders a protest academic; rather, we will recommend that a
protester be reimbursed its costs only where the record
establishes that (1) the agency action that rendered the protest
academic was taken in response to the protest, see Takota
Corp.--Costs, B‑299600.2, Sept. 18, 2007, 2007 CPD para. 171 at
3, and (2) the agency unduly delayed taking the action in the
face of a clearly meritorious protest. Baine Clark--Costs,
B‑290675.3, Sept. 23, 2002, 2002 CPD para. 166 at 2. We consider
a protest to be clearly meritorious when a reasonable agency
inquiry into the protester's allegations would show that the
agency lacked a defensible legal position. SDA Inc.--Costs,
B‑298216.2, Sept. 11, 2006, 2006 CPD para. 133 at 2.
Talladega argues that the agency's decision to terminate the
award due to the reduced workload should be viewed by our Office
as having been made in response to its protest, arguing in
essence that by challenging the agency's decision to evaluate
surge prices based on only 2 percent of the estimated maximum
quantities, Talladega called into question the agency's
estimates, which led to (or should have led to) the decision to
terminate. We disagree. As noted above, the RFP was issued on
the assumption that the required workload would exceed the
in-house capacity; the actual circumstances as they unfolded
during the protest revealed that the in-house capacity in fact
was sufficient to meet the agency's needs and thus that the
additional contractor support was not required. While Talladega
challenged the evaluation of prices based on only 2 percent of
the estimated maximum surge quantities, we simply fail to see
the required nexus between that contention and the decision to
terminate. At best, we understand Talladega to be arguing that
its protest forced the agency to reconsider its requirements,
which should have revealed that the requirement for contractor
support no longer existed, since the agency apparently had been
experiencing some reduction in workload during the procurement;
however, it was in fact the actual events as they developed
during the pendency of the protest that led to the termination
decision, once it became apparent that the services under the
RFP were not required to meet the agency's actual needs. (Talladega
Machinery & Supply Company, Inc.--Costs, B-401049.3, July 6,
2009) (pdf)
Where an agency
takes corrective action in response to a protest, our Office may
recommend reimbursement of protest costs where, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. A protest is
"clearly meritorious" where a reasonable agency inquiry into the
protester's allegations would reveal facts showing the absence
of a defensible legal position. Overlook Sys. Techs.,
Inc.--Costs, B-298099.3, Oct. 5, 2006, 2006 CPD para. 184 at 6.
With respect to the promptness of the agency's corrective action
under the circumstances, we review the record to determine
whether the agency took appropriate and timely steps to
investigate and resolve the impropriety. See Chant Eng'g Co.,
Inc.--Costs, B-274871.2, Aug. 25, 1997, 97-2 CPD para. 58 at 4;
Carl Zeiss, Inc.--Costs, B-247207.2, Oct. 23, 1992, 92-2 CPD
para. 274 at 4. As a general rule, so long as the agency takes
corrective action by the due date of its protest report, we
consider the action to be prompt. CDIC, Inc.--Costs, B‑277526.2,
Aug. 18, 1997, 97-2 CPD para. 52.
CDG asserts that because several of the resumes in Symtech's
proposal, including the resume of Symtech's proposed CAD
manager, did not meet the RFP's requirements, a reasonable
review of CDG's initial protest should have revealed that the
protest was clearly meritorious. Additionally, CDG argues that
the Coast Guard unduly delayed corrective action by submitting
an agency report defending its evaluation before ultimately
conceding that it "carefully reviewed the proposal submitted by
Symtech Corporation and has determined that their proposal
failed to meet the minimum requirements of the solicitation.'
Discussions Letter, Feb. 2, 2009, at 1.
We agree. The Coast Guard took corrective action in this protest
due to its recognition that some of the resumes supplied by
Symtech did not meet the requirements of the solicitation, but
contends that CDG's initial protest was not clearly meritorious
because the initial allegations concerned only Symtech's
proposed CAD manager, whose resume the Coast Guard continues to
insist "clearly indicates he meets the minimum requirements."
Agency Response to Request for Costs, at 3. Our review of the
record, however, does not support that conclusion. Rather, we
conclude that CDG's initial protest was clearly meritorious and
that, had the agency conducted a reasonable review of the
allegations in CDG's initial protest, it would have discovered
that Symtech's proposed CAD managers resume did not provide a
sufficient basis to conclude that he meets the RFP requirements.
Specifically, the proposed CAD manager's resume did not include
a certificate from an AutoCAD certified training center, and
while the resume did set forth 16 years of general experience,
nothing in that work history demonstrated ArchiCAD training or 6
years of full-time ArchiCAD working experience. In fact, the
only reference to ArchiCAD in the entire resume was the listing
"ArchiCAD 8.0" in a section of the resume stating "software
applications include . . . ."
In sum, we conclude that a reasonable inquiry into CDG's initial
protest would have revealed that it was clearly meritorious, as
Symtech's proposed CAD manager's resume was insufficient to
demonstrate the level of experience required by the
solicitation. Thus, by failing to take corrective action before
submitting an agency report to rebut the initial protest, the
Coast Guard unduly delayed corrective action in the face of a
clearly meritorious protest. Accordingly, we recommend that the
Coast Guard reimburse CDG for the reasonable costs of filing and
pursuing its protests of the award to Symtech. CDG should submit
its claim for costs, detailing and certifying the time expended
and costs incurred, directly to the Coast Guard within 60 days
of receipt of this decision. (Commercial
Design Group, Inc.--Costs, B-400923.3, June 10, 2009) (pdf)
CTIC, a large
business, protested the Naval Facilities Engineering Command's (NAVFAC)
award of a contract to DCK Pacific, LLC, under request for
proposals No. N62742‑08‑R‑1307, for design and construction of
replacement, larger-size water lines and related work at the
Naval Base, Guam. CTIC challenged the agency's evaluation of
proposals and conduct of discussions. Subsequently, our Office
conducted "outcome prediction" alternative dispute resolution (ADR),
during which the cognizant GAO attorney stated that it was
likely that CTIC's protest would be sustained based on several
deficiencies in the conduct of the procurement. In this regard,
the GAO attorney advised during the ADR that the agency's
evaluation of past performance and experience/qualifications
appeared unreasonable. NAVFAC thereupon advised our Office that
it intended to undertake corrective action, resulting in GAO
dismissing the protest as academic (B-400047, July 7, 2008).
Subsequently, in our decision Core Tech Int'l Corp.‑‑Costs,
B‑400047.2, Mar. 11, 2009, 2009 CPD para. 59 at 8, we
recommended reimbursement of CTIC's costs of filing and pursuing
its protest. We based our recommendation on our finding that a
reasonable agency inquiry into the protest allegations would
have shown that NAVFAC had failed to reasonably evaluate the
awardee's past performance and experience, and had conducted
disparate, unequal discussions, but the agency unduly delayed
taking corrective action.
Under the Competition in Contracting Act of 1984, as amended,
where the Comptroller General recommends that a successful
protester's costs, including reasonable attorneys' fees, be
reimbursed, those fees are capped at $150 per hour, except where
the protester is a small business concern. However, this hourly
rate may be increased where "the agency determines, based on the
recommendation of the Comptroller General on a case by case
basis, that an increase in the cost of living or a special
factor, such as the limited availability of qualified attorneys
for the proceedings involved, justifies a higher fee." 31 U.S.C.
sect. 3554(c)(2)(B) (2006).
In Sodexho Mgmt., Inc.--Costs, B-289605.3, Aug. 6, 2003, 2003
CPD para. 136 at 37-43, we discussed the section 3554 ceiling on
attorneys' fees and the cost of living adjustment. We found that
the statute contemplates an increase in the specified $150 per
hour rate in order to offset any decrease in the value of the
rate due to increases in the cost of living, Sodexho Mgmt.,
Inc.--Costs, supra, at 41, and that it was proper to determine
the appropriate cost-of-living increase with reference to the
Department of Labor's (DOL) Consumer Price Index (CPI).
Department of the Army; ITT Fed. Servs. Int'l Corp.--Costs,
B-296783.4, B-296783.5, Apr. 26, 2006, 2006 CPD para. 72 at 2.
Since Sodexho, we have found that the justification for an
upward departure from the $150 cap is self-evident if the
claimant asserts that the cost of living has increased, as
measured by DOL's CPI. EBSCO Publishing, Inc.‑‑Costs,
B‑298918.4, May 7, 2007, 2007 CPD para. 90 at 2-3; Department of
State--Costs, B‑295352.5, Aug. 18, 2005, 2005 CPD para.145 at 2;
Department of the Army; ITT Fed. Servs. Int'l Corp.--Costs,
supra, at 2-3. Where the claimant asserts such a claim, and the
contracting agency does not articulate any objection, we will
grant a request for a recommendation in favor of a
cost-of-living adjustment to the fee cap. Department of
State--Costs, supra, at 2.
Here, CTIC and NAVFAC have agreed upon the elements and overall
amount of CTIC's claim for the costs of pursuing the protest and
claim, which are properly reimbursable. The only issue presented
here is whether an enhanced attorney fee rate of $239.74 to
$248.35 per hour (depending on the month of billing) should be
applied to account for increases in the cost of living; if
applied, the parties have agreed upon reimbursement in the
amount of $28,863.77. NAVFAC E‑Mail to GAO, Apr. 16, 2009. In
support of its claim for reimbursement at a higher rate, CTIC
provides a detailed explanation of its calculation of the rates
using DOL's CPI‑‑All Urban Consumers. Use of the "All Urban
Consumers" CPI for a specific area is consistent with our
decision in Sodexho, see Sodexho Mgmt., Inc.--Costs, supra, at
43 n.33, and we have reviewed CTIC’s calculations in support of
the higher requested fees and find that they are properly
supported and reasonable. Since NAVFAC does not object to CTIC's
calculations, we recommend that NAVFAC reimburse CTIC its
attorneys' fees at the claimed higher rate. See Department of
State--Costs, supra, at 2. (Core
Tech International Corporation--Costs, B-400047.3, June 2,
2009) (pdf)
Our Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e) (2008), provide that where
an agency takes corrective action in response to a protest, our
Office may recommend that the agency pay the protester its costs
of filing and pursuing the protest. Information Ventures,
Inc.--Costs, B-294580.2 et al., Dec. 6, 2004, 2004 CPD para. 244
at 2. However, our Regulations do not contemplate a
recommendation for the reimbursement of protest costs in every
case where an agency takes corrective action, but rather only
where an agency unduly delays taking corrective action in the
face of a clearly meritorious protest. Id. Thus, as a
prerequisite to our recommending the reimbursement of costs
where a protest has been resolved by corrective action, not only
must the protest have been meritorious, but it also must have
been clearly meritorious. Overlook Sys. Techs., Inc.--Costs,
B-298099.3, Oct. 5, 2006, 2006 CPD para. 184 at 6. A protest is
"clearly meritorious" where a reasonable agency inquiry into the
protester's allegations would reveal facts showing the absence
of a defensible legal position. Id.
AGFA first asserts that it should be reimbursed its costs based
on the allegation in its initial protest that Philips' proposal
was technically unacceptable due to its failure to "comply with
multiple mandatory technical requirements set forth in the RFP"
related to IHE standards. AGFA contends that this issue was
clearly meritorious, and that the agency unduly delayed taking
corrective action.
While we agree that Philips' proposal's alleged failure to
address certain IHE standards was a serious issue, we do not
agree that the issue was so clearly meritorious as to reveal the
absence of any defensible legal position. The "mandatory [IHE]
technical requirements" referenced in AGFA's initial protest
were elements within the technical requirements section of the
SOW. Of the four "IHE requirements" referenced, two were SOW
provisions stating only that the proposed PACS "should" offer
certain features; the remaining two provisions, while utilizing
the word "shall," did not use the word directly in reference to
IHE standards. Given the imprecise language used in the SOW
provisions referenced by AGFA, we conclude that the issue raised
by AGFA was not clearly meritorious and does not provide a basis
for reimbursement of AGFA's protest costs.
AGFA next argues that it should be reimbursed for its costs
based on the allegation in its first supplemental protest that
Philips improperly offered zero prices for certain line items or
that its price proposal was otherwise incomplete. These
allegations were dismissed by our Office on November 12, for
failure to state a sufficient factual basis. The allegations
themselves demonstrated that AGFA had no knowledge of Philips'
price proposal at the time the protest was filed, and were
grounded entirely in speculation based on the prices of various
elements of AGFA's own price proposal. As they were dismissed by
our Office, these issues were not clearly meritorious and do not
provide a basis for reimbursement.
Finally, AGFA argues that it should be reimbursed for its costs
on the basis of its allegations that Philips' proposal did not
commit to certain staffing requirements, failed to propose a
fixed price, and was materially unbalanced. We disagree. These
allegations were contained in AGFA's second supplemental
protest, which was filed on December 15, after the agency
report. According to our Office's scheduling order for the two
supplemental protests filed by AGFA after receipt of the agency
report, these issues were to be addressed by the agency by
January 5. As the agency advised that it had decided to take
corrective action on January 5, the agency did not unduly delay
corrective action with respect to AGFA's second supplemental
protest. As a general rule, so long as an agency takes
corrective action by the due date of its protest report, as was
the case here, we regard the action as prompt, and will not
consider a request to recommend reimbursement of protest costs.
See CDIC, Inc.-- Costs, B‑277526.2, Aug. 18, 1997, 97-2 CPD para.
52. Accordingly, these issues do not provide a basis for
recommending reimbursement of AGFA's protest costs.
(AGFA HealthCare Corporation--Costs,
B-400733.6, April 22, 2009) (pdf)
Where a procuring
agency takes corrective action in response to a protest, our
Office may recommend reimbursement of protest costs where, based
on the circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e) (2008); AAR Aircraft Servs.
Costs, B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. A
protest is clearly meritorious where a reasonable agency inquiry
into the protest allegations would have shown facts disclosing
the absence of a defensible legal position. AVIATE L.L.C., B
275058.6, B-275058.7, Apr. 14, 1997, 97-1 CPD para. 162 at 16.
With respect to the promptness of the agency's corrective action
under the circumstances, we review the record to determine
whether the agency took appropriate and timely steps to
investigate and resolve the impropriety. See Chant Eng'g Co.,
Inc.‑‑Costs, B‑274871.2, Aug. 25, 1997, 97-2 CPD para. 58 at 4;
Carl Zeiss, Inc.‑‑Costs, B-247207.2, Oct. 23, 1992, 92-2 CPD
para. 274 at 4. While we consider corrective action to be prompt
if it is taken before the due date for the agency report
responding to the protest, we generally do not consider it to be
prompt where it is taken after that date. See CDIC, Inc.‑‑Costs,
B-277526.2, Aug. 18, 1997, 97-2 CPD para. 52 at 2.
Here, according to NAVFAC, "the Agency does not argue that [CTIC]
should be completely deprived of attorney fees." Agency
Response, July 25, 2008, at 4. Rather, the agency asserts that
the initial protest did not include the operative facts that
resulted in the ADR, and, as a result, "was not persuasive and
certainly not 'clearly meritorious.'" Id. at 3-4. The agency
concludes that the award of attorneys' fees therefore should be
"chiefly limited" to the period after submission of the agency
report during which the protester was preparing its comments.
Id.
We find NAVFAC's position unpersuasive. As an initial matter, we
note that our willingness to inform the parties through outcome
prediction ADR that a protest is likely to be sustained, as we
did here as a result of the deficiencies in the technical
evaluation and conduct of discussions, is generally an
indication that the protest is viewed as clearly meritorious,
and satisfies the "clearly meritorious" requirement for purposes
of recommending reimbursement of protest costs. National Opinion
Research Ctr.‑‑Costs, B-289044.3, Mar. 6, 2002, 2002 CPD para.
55 at 3. (As for the remaining protest issues raised by the
protester, none was clearly meritorious.)
Furthermore, we find the agency's corrective action, occurring
only after the agency report and the ADR, to have been unduly
delayed. In this regard, CTIC's initial protest asserted that
NAVFAC had improperly credited DCK Pacific, a recently formed
entity, with the past performance and experience/qualifications
of affiliated companies without consideration of whether there
would be meaningful involvement of those companies in contract
performance. Not only were the determinative facts regarding
this issue apparent on the face of DCK Pacific's proposal, but,
in addition, CTIC's concern in this regard was the same concern
that NAVFAC itself raised during its discussions with DCK
Pacific. In these circumstances, we think it to be beyond any
reasonable dispute that a reasonable agency inquiry into CTIC's
protest allegation would have shown facts disclosing the absence
of a defensible legal position. See AVIATE L.L.C., supra, at 16.
We likewise find the agency's corrective action to be unduly
delayed with respect to CTIC's challenge to the conduct of
discussions regarding relevant contracts. In this regard, CTIC
first asserted in its May 15 comments on the agency report that
the agency had conducted unequal discussions, advising DCK
Pacific, but not CTIC, of informational deficiencies regarding
the nature of prior contracts cited in the proposals, with the
result that several of CTIC's cited contracts were found to be
not relevant. Although it was apparent from the procurement
record that NAVFAC had conducted disparate discussions in this
manner, the agency, in its May 23 response, nevertheless
disputed the assertion that discussions regarding relevant
contracts were unequal or otherwise improper. It was only after
the ADR conducted by GAO more than a month later, that NAVFAC
proposed corrective action. In these circumstances, since
corrective action was proposed only after the agency report
responding to the protest ground, we do not consider the
corrective action to be prompt. See CDIC, Inc.‑‑Costs, supra, at
2.
NAVFAC further asserts that CTIC should not recover protest
costs related to its assertion that CTIC was entitled to a
10-percent HUBZone price evaluation credit. As a general rule,
we consider a successful protester entitled to be reimbursed
costs incurred with respect to all issues pursued, not merely
those upon which it prevails. Burns and Roe Servs. Corp.‑‑Costs,
B-310828.2, Apr. 28, 2008, 2008 CPD para. 81 at 2‑3.
Nevertheless, in appropriate cases, we have limited our
recommendation for the award of protest costs where a part of
those costs is allocable to an unsuccessful protest issue that
is so clearly severable from the successful issues as to
essentially constitute a separate protest. See, e.g., BAE Tech.
Servs., Inc.‑‑Costs, B-296699.3, Aug. 11, 2006, 2006 CPD para.
122 at 3; Interface Floorings Sys., Inc.‑‑Claim for Attorneys'
Fees, B-225439.5, July 29, 1987, 87-2 CPD para. 106 at 2-3. In
determining whether protest issues are so clearly severable as
to essentially constitute separate protests, we consider, among
other things, the extent to which the issues are interrelated or
intertwined‑‑i.e., the successful and unsuccessful arguments
share a common core set of facts, are based on related legal
theories, or are otherwise not readily severable. See Sodexho
Mgmt., Inc.‑‑Costs, B‑289605.3, Aug. 6, 2003, 2003 CPD para. 136
at 29.
Here, CTIC's challenge to the agency's determination that CTIC
was not entitled to a 10-percent HUBZone price evaluation credit
did not involve the same set of core facts as did its clearly
meritorious challenge to the technical evaluation and conduct of
discussions. These protest grounds were also not based on
related legal theories. Accordingly, we recommend that CTIC be
reimbursed the reasonable costs of filing and pursuing its
protest only as related to its challenge to the technical
evaluation and conduct of discussions regarding relevant
contracts. CTIC should submit its certified claim, detailing the
time spent and costs incurred, directly to the agency within 60
days of its receipt of this decision. 4 C.F.R. sect. 21.8(f)(1).
(Core Tech International
Corporation--Costs, B-400047.2, March 11, 2009)
(pdf)
Following the
agency's corrective action, Triple Canopy submitted these
requests for our recommendation that the agency reimburse Triple
Canopy's costs of filing and pursuing the supplemental protests.
Triple Canopy asserts that the agency unduly delayed taking
corrective action and that its supplemental protests were
clearly meritorious. We disagree.
Under the Competition in Contracting Act of 1984 (CICA), our
Office is authorized to recommend reimbursement of protest costs
only where we find that an agency's actions violated a
procurement statute or regulation. 31 U.S.C. sect. 3554(c)(1)
(2000). Our Bid Protest Regulations further provide that where
the contracting agency decides to take corrective action in
response to a protest, we may recommend reimbursement of protest
costs, including reasonable attorneys' fees. 4 C.F.R. sect.
21.8(e). Our Regulations do not contemplate a recommendation for
reimbursement of protest costs in every case in which an agency
takes corrective action, but rather only where an agency unduly
delays taking corrective action in the face of a clearly
meritorious protest. Information Ventures, Inc.--Costs,
B‑294580.2 et al., Dec. 6, 2004, 2004 CPD para. 244 at 2. Thus,
as a prerequisite to our recommending the reimbursement of costs
where a protest has been settled by corrective action, not only
must the protest have been meritorious, but it also must have
been clearly meritorious, that is, not a close question. PADCO,
Inc.--Costs, B‑289096.3, May 3, 2002, 2002 CPD para. 135 at 3. A
protest is clearly meritorious where a reasonable agency inquiry
into the protester's allegations would reveal facts showing the
absence of a defensible legal position. Yardney Technical
Prods., Inc., B-297648.3, Mar. 28, 2006, 2006 CPD para. 65 at 4.
The mere fact that an agency decides to take corrective action
does not necessarily establish the absence of a defensible legal
position, nor that a statute or regulation has clearly been
violated. Id.
Here, based on the record presented, along with the discussions
conducted and clarifications provided during the two GAO
conferences, we cannot conclude that the supplemental protests
were clearly meritorious. Among other things, we agree that the
solicitation was ambiguous regarding the personnel requirements
to which offerors were required to commit. Further, in
responding to the supplemental protests, the agency maintained,
with some basis, that, even accepting the protester's
interpretation of the solicitations' requirements, Sabre's
proposals reflected an intent to comply with those requirements
and that, even increasing Sabre's prices to reflect such intent,
Sabre's proposed prices were still lower than those proposed by
Triple Canopy; thus, the agency argued that there was no
prejudice to Triple Canopy.
In determining whether to recommend cost reimbursement, we need
not definitively resolve whether the protests were meritorious;
rather, we must determine whether they were clearly
meritorious--that is, that they did not present close questions
for which there was no defensible legal position. Based on the
record here, we reject Triple Canopy's assertion that its
protests were clearly meritorious; rather, we acknowledge that,
even resolving doubts in Triple Canopy's favor, the issues
presented were, indeed, close questions.
The request that we recommend reimbursement of costs is denied.
(Triple Canopy, Inc.--Costs,
B-310566.9; B-400437.4, March 25, 2009) (pdf)
Where an agency
takes corrective action in response to a protest, our Office may
recommend reimbursement of protest costs where, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing the protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Bid Protest
Regulations, 4 C.F.R. sect. 21.8(e) (2008); AAR Aircraft Servs.--Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 6. With respect
to the promptness of the agency's corrective action under the
circumstances, we review the record to determine whether the
agency took appropriate and timely steps to investigate and
resolve the impropriety. See Chant Eng'g Co., Inc.--Costs,
B-274871.2, Aug. 25, 1997, 97-2 CPD para. 58 at 4; Carl Zeiss,
Inc.--Costs, B-247207.2, Oct. 23, 1992, 92-2 CPD para. 274 at 4.
We generally do not consider corrective action to be prompt if
it is taken after the due date for the agency report responding
to the protest. See CDIC, Inc.--Costs, B-277526.2, Aug. 18,
1997, 97-2 CPD para. 52 at 2.
Here, the agency argues that Pond should not be reimbursed its
costs because its protest was not clearly meritorious. A clearly
meritorious protest is one that clearly would have been
successful--that is, it must involve a matter over which we have
jurisdiction and be filed by an interested party in a timely
manner and otherwise comply with the requirements of our Bid
Protest Regulations, and the record must establish that the
agency prejudicially violated a procurement statute or
regulation. Georgia Power Co.; Savannah Elec. and Power
Co.--Costs, B-289211.5, B-289211.6, May 2, 2002, 2002 CPD para.
81 at 9. The agency argues that Pond's protest was not clearly
meritorious because Pond was not prejudiced by the ambiguity in
the RFP, since, when subsequently given the opportunity to do
so, Pond failed to provide the Article 134 licenses with its
revised proposal. We disagree.
The question of prejudice in the context of a protest
challenging the terms of a solicitation concerns whether the
alleged defect affects the protester's ability to compete under
the solicitation. See Global Solutions Network, Inc., B-298682,
Nov. 27, 2006, 2006 CPD para. 179 at 3. Prejudice thus is
measured in light of the circumstances while the protest is
pending, not, as the agency argues, by post-protest
developments. Here, at the time the initial protest was filed
and while it was pending, the RFP's failure to clearly state the
agency's requirements with regard to the Italian licensing
requirements prejudiced Pond's ability to prepare an offer on a
common basis with other potential offerors, in response to the
agency's actual needs. The fact that Pond subsequently did not
submit the required licenses, even after the RFP was amended to
clarify the agency’s requirements, is not relevant to
determining the question of prejudice in the context of the
initial protest here.
The agency also argues that the protest was not clearly
meritorious because the Article 134 licenses are required by
Italian law in order for any company to receive award of the
contract, and thus it was not necessary to set out the
requirement in the RFP. Again, we disagree. Our view that the
RFP was defective was not based on an interpretation of the
requirements of Italian law in this area. On the contrary, the
record before us indicated that there were multiple
interpretations of those requirements as they relate to the
specific issue in the protest--whether each member of a joint
venture had to submit an Article 134 license. In our view, the
RFP was defective because it did not clearly express the
requirement (based on the agency's interpretation of Italian
law) that all member companies in a joint venture submit Article
134 licenses as part of the joint venture's initial proposal, or
risk rejection of the proposal. See RFP at 14.
In sum, we conclude that a reasonable inquiry by the agency into
Pond's initial protest would have revealed that the RFP was
unclear regarding the requirements for the Chamber of Commerce
Certificate and Article 134 license and, thus, by failing to act
before the due date for the agency report, the agency unduly
delayed taking corrective action. Accordingly, we recommend that
the agency reimburse Pond for the reasonable costs of filing and
pursuing its initial protest of the terms of the RFP. Pond
should submit its claim for costs, detailing and certifying the
time expended and costs incurred, directly to the Army within 60
days of receipt of this decision. (Pond
Security Group Italia JV--Costs, B-400149.2, March 19, 2009)
(pdf)
The protester
argues that the agency report confirms ICCI's original protest
allegation, namely, "that the Agency's evaluation of ICCI's past
performance was irrational based on the Agency's failure to
consider ICCI's strong record in performing government
construction work of similar size and scope." Request for Costs
at 3. Thus, the protester asserts, the agency unduly delayed
taking corrective action when, in response to the protest, it
produced an agency report instead of taking corrective action.
We disagree.
Under the Competition in Contracting Act of 1984, our Office may
recommend that protest costs be reimbursed where we find that an
agency's action violated a procurement statute or regulation. 31
U.S.C. sect. 3554(c)(1) (2000). Where an agency takes corrective
action in response to a protest, we may recommend that the
protester recover the reasonable costs of filing and pursuing
the protest, where we conclude that the agency unduly delayed
taking corrective action in the face of a clearly meritorious
protest. See 4 C.F.R. sect. 21.8(e) (2008); Georgia Power Co.;
Savannah Elec. and Power Co.--Costs, B-289211.5, B-289211.6, May
2, 2002, 2002 CPD para. 81 at 5. A protest is clearly
meritorious where a reasonable agency inquiry into the protest
allegations would have shown facts disclosing the absence of a
defensible legal position. AVIATE LLC, B-275058.6, B-275058.7,
Apr. 14, 1997, 97-1 CPD para. 162 at 16. As a general rule, so
long as an agency takes corrective action by the due date of its
protest report, we regard the action as prompt, and will not
consider a request to recommend reimbursement of protest costs.
CDIC, Inc.--Costs, B--277526.2, Aug. 18, 1997, 97-2 CPD para.
52. If it is in the protester's comments on the agency report
that the agency is presented for the first time with information
that clearly calls into questions the agency's challenged
determination, and the agency then promptly takes corrective
measures, we will conclude that the agency did not unduly delay
in taking corrective action. LSL Indus., Inc.--Costs,
B-291777.2, Aug. 18, 2003, 2004 CPD para. 99 at 4.
Here, we cannot say that the protester's general allegation that
the agency failed to consider the protester's "strong record" in
performing government construction work was clearly meritorious.
ICCI has not shown that its initial protest on this ground was
clearly meritorious in the sense that it presented a prima facie
case that, without more, demonstrated a valid basis for our
Office to sustain its protest. Career Quest, a Div. of Syllan
Careers, Inc.--Costs, B-293435.5, Apr. 13, 2005, 2005 CPD para.
79 at 3. Rather, in order for us to reach a decision about
ICCI's initial protest allegations, we had to further develop
the record, including a complete agency report and the
protester's comments on the report. Because ICCI's initial
protest did not present what could reasonably be described as
clearly meritorious issues, it follows that there is no basis
for recommending reimbursement of ICCI's protest costs. Id.
Moreover, the agency did not unduly delay taking corrective
action in response to the protester's comments on the agency
report. The promptness of the agency's corrective action is not
measured from the protester's initial protest where the initial
protest did not identify the specific areas where the agency
improperly evaluated the protester's proposal. See Henkels &
McCoy, Inc., B-250875 et al., Feb. 24, 1993, 93-1 CPD para. 174
at 4. As quoted above, the initial protest broadly challenged
the reasonableness of the agency's evaluation of the protester's
past performance without specifically identifying the agency's
failure to consider certain past performance questionnaires and
certain relevancy determinations. It was not until it reviewed
the agency report that ICCI protested, with specificity, the
propriety of its past performance evaluation. We recognize that
ICCI was not able to raise these specific issues before it
received the agency report and reviewed the agency's evaluation.
The fact remains, however, that once ICCI further articulated
its challenge, the agency promptly determined that the
evaluation was flawed and took corrective action. As noted
above, the protester submitted its comments on the agency report
on November 20, and on December 8, 18 days later, the agency
took corrective action. See J.A. Jones Mgmt. Servs.,
Inc.--Costs, B-284909.4, July 31, 2000, 2000 CPD para. 123 at
3-4 (noting that, when the agency responded within 17 days to
the new information offered by the protester, it had not unduly
delayed in taking corrective action). (Intercontinental
Construction Contracting, Inc.--Costs, B-400729.3, March 4,
2009) (pdf)
Under the
Competition in Contracting Act of 1984, our Office may recommend
that protest costs be reimbursed where we find that the agency's
action violated a procurement statute or regulation. 31 U.S.C.
sect. 3554(c)(1) (2000). Our Bid Protest Regulations provide
that where the contracting agency decides to take corrective
action in response to a protest, we may recommend that the
protester be reimbursed the costs of filing and pursuing its
protest, including reasonable attorneys' fees. 4 C.F.R. sect.
21.8(e) (2008). This does not mean that we will recommend that
costs be reimbursed in every case in which an agency takes
action that renders a protest academic; rather, we will
recommend that a protester be reimbursed its costs only where
the record establishes that (1) the agency action that rendered
the protest academic was taken in response to the protest, see
Takota Corp.--Costs, B-299600.2, Sept. 18, 2007, 2007 CPD para.
171 at 3, and (2) the agency unduly delayed taking the action in
the face of a clearly meritorious protest. Baine Clark--Costs,
B-290675.3, Sept. 23, 2002, 2002 CPD para. 166 at 2. We consider
a protest to be clearly meritorious when a reasonable agency
inquiry into the protester's allegations would show that the
agency lacked a defensible legal position. SDA, Inc.--Costs,
B‑298216.2, Sept. 11, 2006, 2006 CPD para. 133 at 2.
Here, it is not clear from the record that the agency decided to
cancel the RFP in response to RANA’s protest. While we recognize
that the contracting officer represented in the agency’s request
for dismissal of the underlying protest that the solicitation
was being cancelled “due to” RANA’s protest, Agency Letter to
GAO, Oct. 15, 2008, at 2, which suggests that there was a link
between the protest and the decision to cancel, the agency
explained in its response to the protester’s request for costs
that it did not decide to cancel in response to RANA’s protest;
rather, the agency maintained that it decided to take this
action “only after learning that the awardee, as well as
offerors next in line for award, were unwilling or unable to
commit to the prices originally offered in their proposals.”
Agency Response to Protester’s Request for Recommendation for
Reimbursement, Nov. 17, 2008, at 2.
Whether the agency decision to cancel was a response to RANA’s
protest is not critical to the outcome of our decision here,
however, because in any event we are not persuaded that RANA’s
protest was clearly meritorious. RANA argues that by submitting
its prices on the price schedule furnished in the RFP and
acknowledging amendment No. 0001, it committed itself to deliver
the items identified in the amendment for the prices that it
entered on the schedule, and that its protest objecting to the
rejection of its proposal as technically unacceptable was thus
clearly meritorious. We disagree. In our view, it was unclear
from RANA’s proposal whether it was offering to furnish the
items described in the price schedule (i.e., the model 3600dn
printer and cartridges) or the items described in the amendment
(i.e., the model cp3505dn printer and cartridges). Faced with an
ambiguity as to what the protester was proposing to furnish (and
thus an ambiguity as to whether it was proposing to furnish
items meeting the requirements of the solicitation, as amended),
we think that the agency’s rejection of RANA’s proposal was
reasonable. See All Bldg. Servs., Inc., B‑293519, Mar. 23, 2004,
2004 CPD para. 73 at 2-3.
The request for a recommendation that the agency reimburse
RANA’s protest costs is denied. (RANA
Technologies--Costs, B-400471.2, February 3, 2009) (pdf)
Under the
Competition in Contracting Act of 1984, our Office may recommend
that protest costs be reimbursed where we find that an agency's
action violated a procurement statute or regulation. 31 U.S.C.
sect. 3554(c)(1) (2000). Where an agency takes corrective action
in response to a protest, we may recommend that the protester
recover the reasonable costs of filing and pursuing the protest,
where we conclude that the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest.
See 4 C.F.R. sect. 21.8(e) (2008); Georgia Power Co.; Savannah
Elec. and Power Co.-Costs, B--289211.5, B--289211.6, May 2,
2002, 2002 CPD sect. 81 at 5. We have recognized that the mere
promise of corrective action, without reasonably prompt
implementation, has the obvious effect of circumventing the goal
of the bid protest system for the economic and expeditious
resolution of bid protests. See Louisiana Clearwater,
Inc.-Recon. and Costs, B‑283081.4, B-283081.5, Apr. 14, 2000,
2000 CPD para. 209 at 6; Pemco Aeroplex, Inc.‑‑Recon. and Costs,
B‑275587.5, B-275587.6, Oct. 14, 1997, 97-2 CPD para. 102 at
7-8. Thus, where an agency fails to implement the promised
corrective action, or implements corrective action that fails to
address a meritorious issue raised in the protest that prompted
the corrective action, such that the protester is put to the
expense of subsequently protesting the very same procurement
deficiency, the agency's action has precluded the timely,
economical resolution of the protest. Louisiana Clearwater,
Inc.-Recon. and Costs, supra.
Here, however, we find that the agency promptly instituted its
promised corrective action, and thus this is not a situation
where the agency either failed to implement the corrective
action, or unduly delayed the corrective action, such that the
protester was required to file a second protest. In this regard,
the Army, as promised, reviewed its determinations regarding the
SDVOSB set-aside, bundling, and the conflict of interest, and
subsequently documented this review. While the protester
disagrees with the Army's conclusions, this does not demonstrate
that the Army failed to implement its promised corrective
action. Moreover, we find no basis in the record here to
conclude that Taylor's protest grounds were clearly
meritorious. A prerequisite to our recommendation that costs
be reimbursed is that the protest must not only have been
meritorious but must also have been clearly meritorious, i.e.,
not a close question. See New England Radiation Therapy Mgmt. Servs., Inc.--Costs, B‑297397.3, Feb. 2, 2006, 2006 CPD para. 30
at 4 (reimbursement of protests costs not recommended after
agency's corrective action where protest was not clearly
meritorious). Here, further record develop would be required to
determine whether the requirements had changed such that a set
aside was not required (as maintained by the CO), whether the
agency had reasonably decided to have "one point of contact"
such that there was no improper bundling, and whether the agency
had properly addressed the allegation of bias. In short, because
we find that the agency did not unduly delay implementing its
promised corrective action and that Taylor's prior protest
grounds were not clearly meritorious, we conclude that there is
no basis for recommending reimbursement of Taylor's protest
costs. (Taylor Consultants,
Inc.--Costs, B-400324.3, February 2, 2009) (pdf)
Our Office may
recommend that a protester be reimbursed the costs of filing and
pursuing a protest where the contracting agency takes action
which renders a protest academic prior to our issuing a protest
resolving the merits of the protest. Bid Protest Regulations, 4
C.F.R. sect. 21.8(e); Information Ventures, Inc.--Costs,
B-294567.2, Nov. 16, 2004, 2004 CPD para. 234 at 2. Such a
recommendation is generally based upon a concern that an agency
has taken longer than necessary to initiate corrective action in
the face of a clearly meritorious protest, thereby causing the
protester to expend unnecessary time and resources to make
further use of the protest process in order to obtain relief.
Advanced Envtl. Solutions, Inc.--Costs, B-296136.2, June 20,
2005, 2005 CPD para. 121 at 2-3. As a general rule, when an
agency takes corrective action on or before the due date for its
report in response to the protest, we consider the agency’s
actions to have been taken promptly; a protester does not have
to file comments or pursue the protest further when the
corrective action is taken prior to the submission of a report
on the merits of the protest. See Alaska Structures,
Inc.--Costs, B-298156.2, July 17, 2006, 2006 CPD para. 109 at 4.
In our view, a basis for the award of costs does not exist in
this protest, since the Army initiated corrective action on June
18, 10 days prior to the June 28 report due date which, as
mentioned above, is the point at which we will generally
determine that an agency has not acted promptly. Since the
agency’s corrective action has not been shown to have been
unduly delayed, and since we do not recommend the award of
protest costs under the Equal Access to Justice Act, there is no
basis to recommend reimbursement of protest costs. (Coronet
Machinery Corporation--Costs, B-400197.2, November 18, 2008)
(pdf)
Exec requests
that we recommend that the agency reimburse its costs of
pursuing its protest concerning the demolition requirement. GSA
argues that reimbursement is not warranted here because the
original solicitation required all offerors to demolish existing
tenant improvements, and that, notwithstanding the agency's
amendment of the SFO to make the matter more clear, the
protester's argument was without merit. We agree with GSA.
Our Bid Protest Regulations, 4 C.F.R. sect. 21.8(e) (2008),
provide that we may recommend that an agency reimburse a
protester’s costs of pursing a protest where the agency decides
to take corrective action in response to the protest. We will
make such a recommendation, however, only where the agency
unduly delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing a protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. Information
Ventures, Inc.-Costs, B-294567.2, Nov. 16, 2004, 2004 CPD
para. 234 at 2. A protest is clearly meritorious where a
reasonable agency inquiry into the protest allegations would
have shown facts disclosing the absence of a defensible legal
position. AVIATE LLC, B-275058.6, B-275058.7, Apr. 14,
1997, 97-1 CPD para. 162 at 16. As a general rule, so long as an
agency takes corrective action by the due date of its protest
report, we regard the action as prompt, and will not consider a
request to recommend reimbursement of protest costs. CDIC,
Inc.-Entitlement to Costs, B-277526.2, Aug. 18, 1997, 97--2
CPD para. 52.
Here, we think the record shows that Exec's initial argument was
not clearly meritorious. As discussed above, Exec's initial
protest argued that the SFO required only the incumbent lessors
to demolish existing tenant improvements. The SFO set forth
specific provisions that applied only to incumbent lessors,
including the following requirement for demolition of existing
improvements:
The majority of this requirement is currently located at 6116,
6120 and 6130 Executive Boulevard, Rockville, MD (the
"Executive Boulevard Properties"). Modernization of the
Executive Boulevard Properties may be a potential solution for
this procurement. A modernization of the Executive Boulevard
Properties will be required to meet all of the requirements of
this SFO, including the Occupancy Date requirements of Section
1.7. The SFO outlines a level of base building requirements
and tenant improvements that will require all or portions of
the building to be vacant from time to time during
modernization. In addition, existing tenant improvements in
Executive Boulevard Properties must be demolished and replaced
with new tenant improvements in accordance with the
Government's Program of Requirements and approved plans.
SFO sect. 1.20A.
While the original SFO did not specifically state that
non-incumbent offerors were required to demolish existing tenant
improvements, it stated that all offerors were required to
propose their office space as a "building shell." SFO sect. 1.9.
The building shell requirements applicable to all offerors
stated that the proposed office space must have complete base
structures, accessible common areas, and systems such as
heating, ventilation, air conditioning, electrical, and
sprinklers. Id. The SFO required offerors to propose a base
price for the building shell, and provided separately for a
fixed allowance for the construction of new tenant improvements
to meet the government’s requirements. GSA states that this
approach allows the government to evaluate offerors on a common
basis, without having to take existing tenant improvements into
consideration. AR at 9.
Amendment No. 2 added a new section to sect. 1.9, which applied
to all offerors, as follows:
Demolition. All required demolition is at the Lessor's expense
and offers should be priced accordingly. Notwithstanding sect.
1.11(A)(4), any offeror proposing an existing building with
existing tenant improvements must assume that all existing
improvements must be demolished in order to provide for the
Government's new POR.
SFO amend. 2 sect. 1.9(A).
To conclude that the protester's original argument was clearly
meritorious, we would need to agree with the protester that the
solicitation, as originally issued by GSA and challenged by
Exec, was defective. We do not agree.
As discussed above, all offerors were required to propose office
space as a building shell, i.e., empty space with only basic
elements such as utilities and safety systems. GSA concedes that
the SFO did not specifically state that non-incumbents would
need to assume demolition of existing tenant improvements.
However, GSA argues that the solicitation clearly and
necessarily implied that the SFO required demolition of existing
tenant improvements, to the extent that all existing
improvements must be removed so that the office space is reduced
to the status of the required building shell. AR at 9.
We agree with the agency that proposing office space as a
building shell means that an offeror must assume demolition of
all existing improvements. Additionally, although the initial
SFO more explicitly stated this requirement for incumbent
offerors, we do not think the elsewhere-stated, but essentially
duplicative provisions requiring a building shell, excused
non-incumbents from demolishing existing tenant improvements.
Finally, we do not think that GSA's decision to amend the
solicitation demonstrates that the protester's initial argument
was correct, even though we agree that amendment No. 2 more
clearly stated the requirement. As discussed above, we think
that the initial solicitation advised all offerors that existing
tenant improvements required demolition. Therefore, we conclude
that agency's corrective action was not taken in response to a
clearly meritorious protest, and we do not recommend that Exec
be reimbursed its protest costs. (Exec
Plaza, LLC--Costs, B-400107.3, October 24, 2008) (pdf)
Al Qabandi
asserts that reimbursement of its protest costs is warranted
here because all of the issues raised in its initial protest,
other than its claim that the start date in its contract was
inconsistent with the solicitation, were clearly meritorious.
The Army concedes that its report incorrectly stated that there
was no requirement for a price realism analysis. Army Comments,
Jan. 7, 2008, at 4. The agency agrees with the protester that,
under the terms of the solicitation, it was required to conduct
a price realism analysis but failed to do so. Army Comments,
Jan. 7, 2008, at 4-5. In these circumstances, Al Qabandi' s
assertion that the agency had failed to conduct a required price
realism analysis was clearly meritorious. The Army contends,
however, that its corrective action was taken promptly, making
reimbursement of the costs associated with this issue
inappropriate. In this regard, the agency asserts that it was
only after the November 8 agency report had been filed that Al
Qabandi first raised the issue of the Army' s failure to conduct
a price realism analysis.
The Army' s position is incorrect. In its initial, October 9
protest, Al Qabandi asserted that the “award price is not
realistic” since it “apparently does not factor in the increased
cost of beginning performance in a few days.” Al Qabandi
Protest, Oct. 9, 2008, at 6. The agency maintains that this
language does not represent an assertion that the agency failed
to conduct a price realism analysis, but instead “essentially
allege[s] that the Army conducted a flawed, or unrealistic,
analysis because the awardee’s pricing proposal did not reflect
contract performance beginning on October 1, 2007.” Agency
Comments, Jan. 7, 2008, at 8. In our view, however, the
allegation was sufficiently specific that a reasonable
investigation into the assertion would have led the agency to
conclude that, contrary to the agency’s initial position, the
solicitation in fact required a price realism analysis, and that
it improperly failed to perform such an analysis. Accordingly,
we find that the Army unduly delayed taking corrective action in
the face of this clearly meritorious protest assertion. (Al
Qabandi United Company; American General Trading &
Contracting‑‑Costs, B-310600.3; B-310600.4, June 5, 2008.) (pdf)
Where a procuring agency takes corrective action in response to
a protest, our Office may recommend reimbursement of protest
costs where, based on the circumstances of the case, we
determine that the agency unduly delayed taking corrective
action in the face of a clearly meritorious protest, thereby
causing the protester to expend unnecessary time and resources
to make further use of the protest process in order to obtain
relief. Bid Protest Regulations, 4 C.F.R. sect. 21.8(e) (2007);
AAR Aircraft Servs.‑‑Costs, B-291670.6, May 12, 2003, 2003 CPD
para. 100 at 6. A protest is clearly meritorious where a
reasonable agency inquiry into the protest allegations would
have shown facts disclosing the absence of a defensible legal
position. AVIATE L.L.C., B‑275058.6, B-275058.7, Apr. 14, 1997,
97-1 CPD para. 162 at 16. With respect to the promptness of the
agency’s corrective action under the circumstances, we review
the record to determine whether the agency took appropriate and
timely steps to investigate and resolve the impropriety. See
Chant Eng’g Co., Inc.-‑Costs, B‑274871.2, Aug. 25, 1997, 97-2
CPDpara. 58 at 4; Carl Zeiss, Inc.-‑Costs, B-247207.2, Oct. 23,
1992, 92-2 CPD para. 274 at 4. While we consider corrective
action to be prompt if it is taken before the due date for the
agency report responding to the protest, we generally do not
consider it to be prompt where it is taken after that date. See
CDIC, Inc.-‑Costs, B-277526.2, Aug. 18, 1997, 97-2 CPD para. 52
at 2.
Sysorex asserts that reimbursement of its protest costs is
warranted here because, in its view, three issues raised in its
initial protest‑‑‑unequal evaluation of handheld solutions,
misevaluation of cost proposals, and misevaluation of Sysorex’s
proposed network monitoring capabilities‑‑‑were clearly
meritorious, but the agency nevertheless failed to take
corrective action until after the protester had responded to the
agency report.
Interior denies that it unduly delayed taking corrective action
in the face of clearly meritorious protest grounds. According to
Interior, it determined to take corrective action based on
problems in two areas identified by Sysorex. Specifically,
Interior states that Sysorex’s assertion in its October 22
supplemental protest that Perceptics’ handheld solution did not
fully comply with the solicitation requirements “caused the
agency to question both its earlier evaluation of all offerors’
handheld solutions as well as the feasibility of the performance
requirements . . . for the handheld LPRs.” Interior Comments,
Dec. 3, 2007, at 2. In addition, Interior states that Sysorex,
in asserting in its October 22 supplemental protest that
Perceptics’ commercial truck lane did not offer the required 95
percent accuracy read rate, “has identified an area where the
agency may have improperly relaxed a solicitation requirement.”
Id. at 3. Interior concludes that, since it first learned the
basis for corrective action after it filed its agency report
responsive to the initial protest submissions, and it acted
promptly thereafter to take corrective action, there is no basis
for recommending reimbursement of protest costs.
We agree with Sysorex that its initial challenge to the
evaluation of handheld solutions was clearly meritorious. The
agency’s evaluation of proposals was based in significant
measure upon the determination that, while Sysorex’s [REDACTED]
handheld solution “was not well suited to the environment in
which CBP operates” and “compromises officer safety,” Source
Selection Decision at 8, “Perceptics proposed a true handheld
solution, consisting of [REDACTED] that accomplishes all of the
functions of Sysorex’s [REDACTED] ‘handheld’ system.” Agency
Report, Oct. 15, 2007, at 8. However, the solicitation clearly
and unambiguously required that the handheld solution be based
upon a handheld wireless device that is “capable of acting as a
fully functioning LPR system.” SOW sect. C.3.1.5.2. Since
Perceptics’ proposal described its handheld approach as
requiring that [REDACTED], Perceptics FPR at IX-2, it should
have been clear to the agency that the approach was not likely
to meet the SOW requirement that all types of LPR systems,
including the handheld system, be capable of imaging license
plates on vehicles moving at speeds up to 60 miles per hour with
95 percent accuracy.
Interior asserts that it understood that its evaluation “might
have been flawed” only when Sysorex, in its supplemental protest
filed after receipt of a copy of Perceptics’ proposal in the
agency report, pointed out that Perceptics had proposed the
[REDACTED], and asserted that this [REDACTED] could not meet the
requirements of the SOW without additional equipment. Interior
Comments, Dec. 3, 2007, at 2. Again, however, it was clear that
a handheld solution that [REDACTED] was not likely to meet the
SOW requirement that the handheld system, like all other LPR
systems to be furnished under the contract, be capable of
imaging license plates on vehicles moving at speeds up to 60
miles per hour with 95 percent accuracy. In our view, a
reasonable investigation of Sysorex’s claim in its initial
protest filings that all offerors would be required to propose a
suite of equipment similar to Sysorex’s in order to meet the SOW
requirements, should have led the agency to examine the
compliance of Perceptics’ proposed handheld solution; such
examination, reasonably conducted, necessarily would have
indicated the noncompliance of Perceptics’ proposed handheld
solution. Accordingly, we find that Interior unduly delayed
taking corrective action in the face of Sysorex’s clearly
meritorious protest, first raised in its initial protest filings
prior to the agency report, against the evaluation of proposed
handheld solutions. (Sysorex
Federal, Inc.--Costs, B-310273.2, March 27, 2008) (pdf)
Where a contracting agency takes action which renders a protest
academic prior to our issuing a decision resolving the merits of
the protest, our Office may recommend that the protester be
reimbursed the costs of filing and pursuing the protest. Bid
Protest Regulations, 4 C.F.R. sect. 21.8(e) (2007); Information
Ventures, Inc.--Costs, B-294567.2, Nov. 16, 2004, 2004 CPD para.
234 at 2. We will recommend that a protester be reimbursed its
protest costs only where, under the facts and circumstances of a
given case, the agency unduly delayed taking corrective action
in the face of a clearly meritorious protest, thereby causing a
protester to expend unnecessary time and resources to make
further use of the protest process in order to obtain relief.
Advanced Envtl. Solutions, Inc.--Costs, B-296136.2, June 20,
2005, 2005 CPD para. 121 at 2-3. Generally, where an agency
takes corrective action on or before the due date for its report
in response to the protest, we consider the agency’s corrective
measures to have been taken promptly; a protester does not have
to file comments or pursue the protest further when the
corrective action is taken prior to the submission of a report
on the merits of the protest. See Alaska Structures,
Inc.--Costs, B‑298156.2, July 17, 2006, 2006 CPD para. 109 at 4;
The Sandi-Sterling Consortium--Costs, B‑296246.2, Sept. 20,
2005, 2005 CPD para. 173 at 2-3.
In our view, the protester’s request for reimbursement of
protest costs is based on an argument that neither establishes
the meritorious nature of its protest issues (which, in any
event, are unrelated to the basis upon which the agency took
corrective action) nor demonstrates that the agency unduly
delayed taking corrective action. The protester instead
essentially suggests that, since the agency had told it, during
its agency-level protest, that a bond had been submitted by
Alliance, but apparently had not noticed the untimely nature of
the bond, the agency’s subsequent rejection of the Alliance
quotation based on the untimely bond after Tremco filed a
protest with our Office constitutes unduly delayed corrective
action. Tremco generally contends that if the impropriety
regarding the bond had been discovered during the agency-level
protest (even though Tremco did not raise any issue regarding
the bond), and if the Alliance quotation had been rejected
earlier because of the impropriety, Tremco would not have had to
file its protest to our Office, and, as a result, it should be
reimbursed for the costs of doing so. We see no basis to
recommend recovery of protest costs here, since Tremco’s theory
lacks the essential elements necessary to support a
recommendation for reimbursement of protest costs. As an initial
matter, there is no nexus between Tremco’s protest contentions
and the basis for corrective action; Tremco never raised the
timeliness of the awardee’s bond in its protest to our Office.
Thus, Tremco has no basis for reimbursement on that issue. See
Takota Corp.--Costs, B‑299600.2, Sept. 18, 2007, 2007 CPD para.
171 at 3. In any event, with regard to Tremco’s specific protest
allegations, since there was no report submitted by the agency,
there is nothing in the record that supports Tremco’s general
allegation that its protest was meritorious. See Alaska
Structures, Inc.--Costs, B‑298575.4, Jan. 22, 2007, 2007 CPD
para. 15 at 8 n.8. With regard to Tremco’s protest, it is clear
that the agency’s corrective action was not unduly delayed,
since it was communicated to us by the due date for receipt of
the agency report in response to the protest. See The
Sandi-Sterling Consortium--Costs, supra. The record shows that
it was only after further review of the procurement in
preparation of its agency report to our Office in response to
Tremco’s protest that the agency discovered the issue that led
to the prompt corrective action. Since the agency’s corrective
action has not been shown to have been taken in response to
clearly meritorious issues raised by the protester, and,
moreover, was not unduly delayed, there is no basis to recommend
reimbursement of protest costs. (Tremco
Incorporated--Costs, B-310927.2, April 21, 2008) (pdf)
Our Bid Protest Regulations, 4 C.F.R. sect. 21.8(e), provide
that where an agency takes corrective action in response to a
protest, we may recommend that the agency reimburse protest
costs, including attorneys’ fees; however, we will make such a
recommendation only where the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest.
CSL Birmingham Assocs.; IRS Partners-Birmingham--Entitlement to
Costs, B-251931.4, B-251931.5, Aug. 29, 1994, 94-2 CPDpara. 82
at 3. As a general rule, when an agency takes corrective action
by the due date of its protest report, we regard such action as
prompt, and decline a request for recommendation of
reimbursement of protest costs. Alaska Structures, Inc.--Costs,
B-298156.2, July 17, 2006, 2006 CPD para. 109 at 4. Here,
Singleton argues that the need for corrective action under this
IFB should have been apparent as early as November 30, 2007,
when the SBA submitted a statement supporting Singleton’s
earlier protest. However, our decision sustaining Singleton’s
earlier protest (which, as noted, raised a similar issue, but
involved a different solicitation), was only issued later--on
January 10, 2008. Thus, on the day this protest was filed--also
on January 10--there should have been no doubt on the part of
the agency that Singleton’s second protest raising the same
issues present in the earlier VA procurement, presented a
question our Office would view as clearly meritorious. Since we
conclude the protest was clearly meritorious, the only question
remaining is whether the agency’s corrective action (in the face
of this clearly meritorious protest) was unduly delayed. In this
regard, we note that the agency did not submit a report, and 2
days after the date that report was due, advised our Office of
its intent to take corrective action. Since no report was
tendered, the protester was not required to expend unnecessarily
the costs of preparing comments in answer to that report. Cf.
Control Corp.; Control Data Sys., Inc.--Protest & Entitlement to
Costs, B‑251224.2 et al., May 3, 1993, 93-1 CPD para. 353 at 7
(where delay in corrective action required protester to expend
unnecessary effort in preparing comments on agency report,
recommendation of reimbursement of protest costs was
appropriate). Thus Singleton was in no worse a position than it
would have been if the agency had taken corrective action by the
report due date--which, as mentioned above, is the point at
which we will generally determine that an agency has not acted
promptly. Accordingly, we will not conclude that the VA failed
to take prompt corrective action in the face of a clearly
meritorious protest. (Singleton
Enterprises-GMT Mechanical, Joint Venture--Costs,
B-310454.3, March 27, 2008) (pdf)
Where a procuring agency takes corrective action in response
to a protest, our Office may recommend that the agency reimburse
the protester its protest costs, where based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing a protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 4 C.F.R. sect.
21.8(e) (2007); AAR Aircraft Servs.--Costs, B-291670.6, May 12,
2003, 2003 CPD para. 100 at 6. A protest is clearly meritorious
when a reasonable agency inquiry into the protest allegations
would show facts disclosing the absence of a defensible legal
position. AVIATE L.L.C., B‑275058.6, B-275058.7, Apr. 14, 1997,
97-1 CPD para. 162 at 16. In a one-page response to
Eagle’s request for reimbursement, the VA generally disputes
that Eagle’s protest was clearly meritorious or that its
corrective action was unduly delayed. In this regard, the VA
contends that “the brevity of time allotted to the two
contracting officers to take care of their family and personal
needs before departing for a hearing in this protest in
Washington, D.C. made it impossible for either of them to
appear” and that the “loss of the opportunity for a hearing
harmed the VA’s ability to prove it had done its research
properly.” VA’s Response to Eagle’s Request for Reimbursement.
We find that Eagle’s protest was clearly meritorious and that
the VA unduly delayed taking corrective action in the face of
that protest. With respect to the merits of Eagle’s protest, the
contracting officer’s judgment that there were not two or more
small business manufacturers that could satisfy the RFP’s
requirements was unsupported by the contemporaneous record, and
despite repeated requests from our Office, the VA did not
substantively respond to the evidence provided by the protester
and the SBA that, on its face, showed that the VA’s market
research was inadequate. The record also does not support the
VA’s contention now that its inability to produce the
contracting officers for a hearing in Washington, D.C. “harmed”
its ability to defend itself in this protest. In fact, although
the contracting officers were originally requested to attend a
hearing in GAO’s hearing room in Washington, D.C., prior to the
October 10 hearing date we informed the parties that the
contracting officers’ testimony would be taken by telephone and
transcribed by a court reporter.[4] See GAO’s Amended
Confirmation of Hearing, Oct. 5, 2007, at 1. With respect
to the promptness of the agency’s corrective action under the
circumstances, we review the record to determine whether the
agency took appropriate and timely steps to investigate and
resolve the impropriety. See Chant Eng’g Co., Inc.--Costs,
B-274871.2, Aug. 25, 1997, 97-2 CPD para. 58 at 4; Carl Zeiss,
Inc.--Costs, B-247207.2, Oct. 23, 1992, 92-2 CPD para. 274 at 4.
While we consider corrective action to be prompt if it is taken
before the due date for the agency report responding to the
protest, we generally do not consider it to be prompt where it
is taken after that date. See CDIC, Inc.--Costs, B-277526.2,
Aug. 18, 1997, 97‑2 CPD para. 52 at 2. Here, the VA’s proposed
corrective action came not only after the agency filed its
report on the protest but after our repeated requests for
information and that the VA address the protester’s comments and
the SBA’s views that indicated that the contracting officer
erred in concluding that there were no small business
manufacturers that could satisfy the RFP’s requirements. Under
the circumstances, we conclude that the VA’s corrective action
was unduly delayed. We recommend that Eagle be reimbursed
the reasonable costs of filing and pursuing its protest. Eagle
should submit its claim for costs, detailing and certifying the
time expended and costs incurred, directly to the VA within 60
days of receipt of this decision. 4 C.F.R. sect. 21.8(f)(1).
(Eagle Home Medical
Corporation--Costs, B-299821.3, February 4, 2008) (pdf)
In its earlier
protests, B-310398 and B-310398.2, WCC argued that the DEA
conducted an improper sole-source procurement, and wrongly
denied WCC an opportunity to compete for the solicitation
requirements by refusing to test its satellite trackers for
compatibility with the DEA’s tracking system. The agency
produced a report responding to the protest allegations, and
requested that our Office either deny the protests or dismiss
them based on the agency’s argument that WCC was not an
interested party. Our Office convened a conference call during
which the GAO attorney assigned to the protest identified
concerns regarding the agency’s rationale for the sole-source
award, and indicated that the record as produced by the agency
did not support the reasonableness of the sole-source award. The
GAO attorney also requested additional information from the DEA
to supplement its report. Subsequently, however, the DEA advised
our Office that it would take corrective action by terminating
the award to NAL and canceling the solicitation. Because the
agency’s corrective action rendered the protest academic, we
dismissed the protests on November 30, 2007. Where an agency
takes corrective action in response to a protest, our Office may
recommend that a protester be reimbursed the costs of filing and
pursuing that protest. Bid Protest Regulations, 4 C.F.R. sect.
21.8(e) (2007). Such recommendations are generally based upon a
concern that the agency has taken longer than necessary to
initiate corrective action in the face of a clearly meritorious
protest, thereby causing the protester to expend unnecessary
time and resources to make further use of the protest process in
order to obtain relief. See, e.g., AAR Aircraft Servs.-Costs,
B-291670.6, May 12, 2003, 2003 CPD para. 100 at 5. A protest is
clearly meritorious when a reasonable agency inquiry into the
protest allegations would show facts disclosing the absence of a
defensible legal position. The Real Estate Ctr.-Costs,
B-274081.7, Mar. 30, 1998, 98-1 CPD para. 105 at 3. Here, the
DEA states that it “does not contest [WCC’s] request for
reimbursement.” Letter from DEA to GAO, Dec. 18, 2007, at 1. In
the absence of any evidence to show that the DEA’s sole-source
award determination was reasonable, and in view of the agency’s
decision not to contest the request for reimbursement, we
conclude that the protest was clearly meritorious. We also
conclude that the DEA did not take prompt corrective action, as
it did not terminate the award to NAL and cancel the
solicitation until after the agency had produced its report on
the protest, the protester had filed its comments on the report,
and the GAO attorney assigned to the protest had requested
additional information to supplement the record. We recommend
that the agency reimburse WCC its costs of filing and pursuing
its protests. (World Communications
Center, Inc.--Costs, B-310398.4, January 16, 2008) (pdf)
Where an
agency takes corrective action in response to a protest, our
Office may recommend that a protester be reimbursed the costs of
filing and pursuing that protest. 4 C.F.R. sect. 21.8(e)
(2007). However, where, as here, the record reasonably supports
the agency’s cancellation of a protested procurement on the
basis that the solicitation at issue no longer represents the
procuring agency’s actual requirements, we do not view
cancellation as corrective action taken to remedy a meritorious
protest. See PAI Corp., B-244287.5, et al., Nov. 29, 1991, 91-2
CPD para. 508 at 4-5. Accordingly, we will not recommend
reimbursement of protest costs. Id. (RKR
Joint Venture, LLC--Costs, B-299856.2, December 7, 2007)
(pdf)
Where a
contracting agency takes action which renders a protest moot
prior to our issuing a decision resolving the merits of the
protest, our Office may recommend that the protester be
reimbursed the costs of filing and pursuing the protest. Bid
Protest Regulations, 4 C.F.R. sect. 21.8(e) (2007); Information
Ventures, Inc.--Costs, B-294567.2, Nov. 16, 2004, 2004 CPD para.
234 at 2. This imposition of costs is not intended as an award
to prevailing protesters or as a penalty to the agency, but
rather is designed to encourage agencies to take prompt action
to correct apparent defects in competitive procurements. J.A.
Jones Mgmt. Servs., Inc.--Costs, B-284909.4, July 31, 2000, 2000
CPD para. 123 at 3. We will recommend that a protester be
reimbursed its protest costs only where, under the facts and
circumstances of a given case, the agency unduly delayed taking
corrective action in the face of a clearly meritorious protest,
thereby causing a protester to expend unnecessary time and
resources to make further use of the protest process in order to
obtain relief. Advanced Environmental Solutions, Inc.--Costs,
B-296136.2, June 20, 2005, 2005 CPD para. 121 at 2-3. Applying
these standards to the present case, we conclude that it is not
appropriate to recommend that Takota recover its protest costs.
As an initial matter, there was no nexus between the bases of
protest raised by Takota in its protest letter and the basis for
the Coast Guard’s corrective action decision, which was taken in
response to the SBA’s opinion, and we note that the protester
has not shown otherwise. See GPA-Buffer, LP, B-298953.2, Mar.
21, 2007, 2007 CPD para. 53 at 4. Moreover, the Coast Guard took
corrective action no more than 4 days after the SBA’s opinion
was issued and 5 days after filing its agency report with our
Office. Thus, even if we assume that Takota’s initial protest
grounds were clearly meritorious, the agency’s corrective action
was not unduly delayed and is precisely the kind of prompt
agency action that our regulations are designed to encourage.
Since the Coast Guard did not take corrective action in response
to Takota’s protest and Takota’s protest was not sustained,
there is no basis to recommend reimbursement of protest costs.
(Takota Corporation--Costs,
B-299600.2, September 18, 2007) (pdf)
We find that reimbursement is not appropriate in this case
since, even if we agreed with Yardney that the agency’s
corrective action was not prompt, the protest was not clearly
meritorious. In its original protest, Yardney asserted that the
evaluation of Quallion’s proposal as superior was flawed, that
Quallion enjoyed an unfair competitive advantage, as evidenced
by the program manager’s trip to Japan with the firm, and that
the program manager unduly influenced the evaluation panel in
favor of Quallion. The Air Force asserts that its response
(detailed above) constitutes a defensible legal position with
regard to the evaluation and unfair advantage issues based in
part on the pre-existing business relationship between the
awardee and the Japanese firm. Which party’s position is correct
is not apparent from the record as it stands. Rather, in order
to reach a decision on the matter, we would have required, at a
minimum (as was our intention prior to being notified of the
corrective action), a supplemental report from the agency and
comments on that report by Yardney. Following this further
development of the record, we would have had to conduct
substantial further analysis of the parties’ positions. In such
cases, we do not consider the protest grounds to be clearly
meritorious. New England Radiation Therapy Mgmt, Servs.,
Inc.--Costs, B‑297397.3, Feb. 2, 2006, 2006 CPD para. 30 at 4;
LENS, JV--Costs, B-295952.4, Dec. 12, 2005, 2006 CPD para. 9 at
5; East Penn Mfg. Co., Inc.--Costs, B-291503.4, Apr. 10, 2003,
2003 CPD para. 83 at 2-3 (protest not clearly meritorious where
decision would have required further steps to complete and
clarify the record). We therefore decline to recommend
reimbursement of Yardney’s protest costs. Yardney also asserts
that it is entitled to reimbursement of its proposal preparation
costs. In this regard, Yardney argues that its initial proposal
was “wasted” work because the new solicitation--which was
expected to identify technology transfer as the preferred
solution--represents a solution different from the one it
originally proposed, thus requiring it to completely rewrite its
proposal. Request for Reimbursement at 5. Where we have
sustained a protest, we may recommend reimbursement of proposal
preparation costs when changed circumstances render a
previously-submitted proposal no longer relevant. See COBRO
Corp., B-287578.2, Oct. 15, 2001, 2001 CPD para. 181 at 8-9.
However, our Regulations do not provide for recovery of such
costs where an agency has taken corrective action. See 4 C.F.R.
sect. 21.8(e); Mapp Building Servs.--Costs, B-289160.2, Mar. 13,
2002, 2002 CPD para. 60 at 2. Moreover, we generally will not
recommend payment of proposal costs where, as here, the
protester will have the opportunity to compete for the
requirement under a reopened competition. Moon Eng’g Co.,
Inc.--Request for Declaration of Entitlement to Costs,
B-247053.6, Aug. 27, 1992, 92-2 CPD para. 129 at 7 n.7. (Yardney
Technical Products, Inc.--Costs, B-297648.3, March 28, 2006)
(pdf)
Under the Competition in Contracting Act of 1984, our Office may
recommend that protest costs be reimbursed only where we find
that an agency’s action violated a procurement statute or
regulation. 31 U.S.C. sect. 3554(c)(1) (2000). Our Bid Protest
Regulations provide that where the contracting agency decides to
take corrective action in response to a protest, we may
recommend that the protester be reimbursed the costs of filing
and pursuing its protest, including reasonable attorneys’ fees.
4 C.F.R. sect. 21.8(e) (2005). This does not mean that costs
should be reimbursed in every case in which an agency decides to
take corrective action; rather, a protester should be reimbursed
its costs where an agency unduly delayed its decision to take
corrective action in the face of a clearly meritorious protest.
Griner’s-A-One Pipeline Servs., Inc.--Entitlement to Costs,
B-255078.3, July 22, 1994, 94-2 CPD para. 41. Thus, as a
prerequisite to our recommending that costs be reimbursed where
a protest has been settled by corrective action, not only must
the protest have been meritorious, but it also must have been
clearly meritorious, i.e., not a close question. J.F. Taylor,
Inc.--Entitlement to Costs, B-266039.3, July 5, 1996, 96-2 CPD
para.5 at 3; Baxter Healthcare Corp.--Entitlement to Costs,
B-259811.3, Oct. 16, 1995, 95-2 CPE para.174 at 4‑5; GVC
Cos.--Entitlement to Costs, B-254670.4, May 3, 1994, 94-1 CPD
para. 292 at 3. A protest is “clearly meritorious” when a
reasonable agency inquiry into the protester’s allegations would
show facts disclosing the absence of a defensible legal
position. Department of the Army--Recon., B-270860.5, July 18,
1996, 96-2 CPD para. 23 at 3. The mere fact that an agency
decides to take corrective action does not establish that a
statute or regulation clearly has been violated. Spar Applied
Sys.--Declaration of Entitlement, B-276030.2, Sept. 12, 1997,
97-2 CPD para. 70 at 5. Here, we conclude that it is not
appropriate to recommend that NERT recover its protest costs
because, even if the corrective action was in response to NERT’s
original protest, as NERT alleges, that protest was not clearly
meritorious. In its original protest, NERT asserted that either
ROA’s price failed to account for the number of treatments
required by the RFP or, in the alternative, the solicitation
requirements were ambiguous. The agency denied that the
solicitation was ambiguous and asserted that ROA’s price was in
accordance with the RFP’s price schedule. Which party’s position
is correct is not apparent from the record, which is why GAO
informed the parties that a hearing was likely going to be
necessary to complete and clarify the record. See LENS,
JV--Costs, B-295952.4, Dec. 12, 2005, 2005 CPD para. __ at 5
(protest was not clearly meritorious where resolution of the
protest required further record development such as a hearing to
complete and clarify the record). The fact that NERT asserts
that the agency’s corrective action, filed after submission of
the agency report, was in response to its original protest does
not entitle it to its costs where, as here, that protest was not
clearly meritorious. See East Penn Mfg. Co., Inc.--Costs,
B-291503.4, Apr. 10, 2003, 2003 CPD para. 83 at 2-3; J.F.
Taylor, Inc.--Costs, B‑266039.3, July 5, 1996, 96-2 CPD para. 5
at 3. (New England Radiation Therapy
Management Services, Inc.--Costs, B-297397.3, February 2,
2006) (pdf)
Where, as here, a procuring agency takes corrective action in
response to a protest, our Office may recommend that the agency
reimburse the protester its protest costs where, based on the
circumstances of the case, we determine that the agency unduly
delayed taking corrective action in the face of a clearly
meritorious protest, thereby causing a protester to expend
unnecessary time and resources to make further use of the
protest process in order to obtain relief. 4 C.F.R. sect.
21.8(e) (2005); Pemco Aeroplex, Inc.--Recon. and Costs,
B-275587.5, B-275587.6, Oct. 14, 1997, 97-2 CPD para.102 at 5. A
protest is clearly meritorious when a reasonable agency inquiry
into the protest allegations would show facts disclosing the
absence of a defensible legal position. AVIATE L.L.C.,
B‑275058.6, B-275058.7, Apr. 14, 1997, 97-1 CPD para. 162 at 16.
For a protest to be clearly meritorious, the issue involved must
not be a close question. J.F. Taylor, Inc.‑-Entitlement to
Costs, B-266039.3, July 5, 1996, 96-2 CPD para. 5 at 3. Rather,
the record must establish that the agency prejudicially violated
a procurement statute or regulation. Georgia Power Co.; Savannah
Elec. and Power Co.--Costs, B-289211.5, B‑289211.6, May 2, 2002,
2002 CPD para. 81 at 5. The mere fact that an agency decides to
take corrective action does not establish that a statute or
regulation clearly has been violated. East Penn Mfg. Co.,
Inc.--Costs, B-291503.4, Apr. 10, 2003, 2003 CPD para. 83 at 3.
Here, the record does not establish that LENS’s protest was
clearly meritorious. Even were we to accept all of the
protester’s arguments concerning the agency’s should-cost
estimate and the adequacy of the solicitation, the record does
not show a reasonable possibility that LENS was prejudiced,
given the significant difference between the agency’s
should-cost estimate for government operation and maintenance of
the electric utility and LENS’s proposed price.[1] See First
Fed. Corp.--Costs, B-293373.2, Apr. 21, 2004, 2004 CPD para. 94
at 3 (protest not clearly meritorious where there was no
competitive prejudice to the protester, even where agency took
corrective action in response to protest). Here, as our Office
repeatedly informed the parties during the protest, the record
does not show the cost impact on either the agency’s should-cost
estimate or the protester’s proposed price; in fact, this was
one of the reasons our Office informed the parties during the
protest that a hearing might be necessary to resolve this
protest. See Spar Applied Sys.--Declaration of Entitlement,
B-276030.2, Sept. 12, 1997, 97-2 CPD para. 70 at 5 (a protest
was not clearly meritorious where resolution of the protest
required substantial further record development such as
conducting a hearing to complete and clarify the record).
Without further record development in this case, we are unable
to determine that there is any reasonable possibility that LENS
was prejudiced, even assuming, arguendo, that the agency’s
conduct of the acquisition was deficient. (LENS,
JV--Costs, B-295952.4, December 12, 2005) (pdf)
In general, if an agency takes corrective action in response to
a protest by the due date for its report in response to the
protest, we consider such action to be prompt and will not
recommend reimbursement of protest costs. Id.; HSQ Tech.--Costs,
B‑276050.2, June 25, 1997, 97-1 CPD para. 228 at 2. This is the
case even where the report due date was extended; in such
circumstances, although the corrective action may have been
somewhat delayed relative to the original report date, we do not
consider this to be an undue delay, since it did not result in
the protester’s being put to the time and expense of filing
comments in response to the report. TRS Research and Transport
Planning and Servs., Inc.--Costs, supra. Here, the agency
proposed corrective action prior to the extended report due
date, and neither its report nor the protester’s comments were
filed. Thus, SSC was not required to expend additional time or
resources preparing report comments, and the purpose of section
21.8(e) of our Regulations has been served. Under these
circumstances, we consider the corrective action to be prompt;
it follows that there is no basis for recommending reimbursement
of SSC’s protest costs. In any case, we cannot say that SSC’s
protest was clearly meritorious. We consider a protest to be
clearly meritorious when the agency lacked a defensible legal
position; that is, that the protest does not involve a close
question. Information Ventures, Inc-- Costs, supra, at 2. The
mere fact that an agency decided to take corrective action does
not establish that a statute or regulation was violated. Id.
Here, deciding the merits of SSC’s protest would have required
development of the protest record--including a complete agency
report and the protester’s comments on the report--and we would
have had to conduct substantial further legal analysis. This
being the case, we have no basis to find that SSC’s protest was
clearly meritorious. Career Quest, a division of Syllan Careers,
Inc.--Costs, B-293435.5, Apr. 13, 2005, 2005 CPD para. 79 at 3.
(The Sandi-Sterling Consortium--Costs,
B-296246.2, September 20, 2005) (pdf)
The Army’s
failure to investigate the substantive grounds of this protest,
its failure to produce documents when required, and its failure
to take prompt corrective action in the face of a clearly
meritorious protest, frustrated the intent of the Competition in
Contracting Act of 1984, 31 U.S.C. sections 3551-3556 (2000),
amended by the Ronald W. Reagan National Defense Authorization
Act for FY 2005, Pub. L. No. 108-375, Section 326, 118 Stat.
1811 (2004), by impeding the economic and expeditious resolution
of this protest. LB&M Assocs., Inc.--Entitlement to Costs,
B-256053.4, Oct. 12, 1994, 94‑2 CPD para. 135 at 5. Accordingly,
we recommend that the protester be reimbursed the reasonable
costs of filing and pursuing its protests including the cost of
pursuing this request, and including the cost of attorneys’
fees. 4 C.F.R. sect. 21.8(d). The protester should submit its
certified claim, detailing the time expended and costs incurred,
directly to the contracting agency within 60 days of receiving
this decision. 4 C.F.R. sect. 21.8(f)(1). (Johnson
Controls World Services, Inc.--Costs, B-295529.4, August 19,
2005) (pdf)
Envirosolve requests that we recommend the reimbursement of its
protest costs, including reasonable attorneys fees. Our Bid
Protest Regulations provide that where a contracting agency
decides to take corrective action in response to a protest, we
may recommend that the agency pay the protester the costs of
filing and pursuing the protest, including reasonable attorneys
fees. 4 C.F.R. 21.8(e) (2004). We will make such a
recommendation where, based on the circumstances of the case, we
determine that the agency unduly delayed taking corrective
action in the face of a clearly meritorious protest. A protest
is clearly meritorious when a reasonable inquiry into the
protesters allegations would show facts disclosing the absence
of a defensible legal position ( i.e. , not a close question).
As a general rule, so long as an agency takes corrective action
in response to a protest by the due date of its protest report,
we regard such action as prompt and decline to consider
favorably a request to recommend reimbursement of protest costs.
Our rule is intended to prevent inordinate delay in
investigating the merits of a protest and taking corrective
action once an error is evident, so that a protester will not
incur unnecessary effort and expense in pursuing its remedies
before our Office. PADCO, Inc.--Costs , B-289096.3, May 3, 2002,
2002 CPD 135 at 3-4. (Envirosolve--Costs,
B-294420.3, February 17, 2005) (pdf)
In requesting reimbursement of its protest costs, the protester
asks us to create an exception to our existing rule regarding
reimbursement in cases where the agency takes prompt corrective
action. The protester argues that, since it filed numerous
protests, and since the agency canceled many of the
procurements, our Office should infer a "recurrent pattern" of
improper issuance of sole-source acquisitions, warranting
recovery of protest costs. In this regard, our rule limiting
recovery of protest costs to those cases where agency corrective
action is unduly delayed was intended not as an award to
prevailing protesters or as a penalty to agencies, but rather to
encourage agencies to take prompt action where warranted, and
thereby save protesters from expending additional costs in
pursuing their protests. See Wall Comonoy Corp.--Entitlement to
Costs , B-257183.3, Nov. 16, 1994, 94-2 CPD 189 at 2. That is
precisely what HHS did here, and we see no reason to consider
abandoning that principle to allow recovery despite the fact
that corrective action was promptly taken. Moreover, the
protester's argument derives from its assumption that the series
of corrective action decisions by HHS indicates an underlying
procurement impropriety. We do not have a basis to draw that
same conclusion based on the record here. Information Ventures
has not established, and the record otherwise does not show,
that any of the nine protests in fact was meritorious; the
agency maintains that the corrective action was not based on any
determination that the protests had merit; and, as noted above,
because the corrective action was taken so early in development
of the protests, no agency responses on the merits were
prepared. Without a basis to find the protests clearly
meritorious, we have no ground to recommend reimbursement of
costs. (Information Ventures,
Inc.--Costs, B-294580.2, B-294586.2, B-294617.2, B-294632.2,
B-294706.2, B-294707.2, B-294741.2, B-294760.2, B-294762.2 ,
December 6, 2004) (pdf)
Where an agency decides to take corrective action in response to
a protest, we may recommend that the agency pay protest costs,
including attorneys' fees. Bid Protest Regulations, 4 C.F.R.
21.8(e) (2004). We will make such a recommendation only where
the agency unduly delayed taking corrective action in the face
of a clearly meritorious protest. CSL Birmingham Assocs.; IRS
Partners Birmingham--Costs , B251931.4, B251931.5, Aug. 29,
1994, 942 CPD 82 at 3. As a general rule, so long as an agency
takes corrective action by the due date for its protest report,
we regard the action as prompt. CDIC, Inc.--Entitlement to Costs
, B277526.2, Aug.18, 1997, 972 CPD 52. Here, DHS canceled the
solicitations in question and notified our Office of its intent
to reinstate SCG's contract award prior to the due date for the
agency's report. In view of this prompt corrective action, which
obviated the need for SCG to incur additional costs, we have no
basis for recommending reimbursement of costs. Id. (Security
Consultants Group, Inc.--Costs, B-293344.6, November 4,
2004) (pdf)
Here, the agency's notice of corrective action stated that the
agency was taking corrective action in response to supplemental
protest issues, and specifically identified two supplemental
protest issuesfailure to acknowledge a material amendment and
violation of the prohibition against facsimile submissions.
Williamson first raised these protest grounds on April19, and
within 10 days the agency announced its corrective action, well
before May 3, the due date for the agency report on the
supplemental protests. Since the agency did not submit a report
on these supplemental protest issues, the protester did not
expend unnecessary time and resources to make further use of the
protest process in order to obtain relief on these issues. See
J.A. Jones Mgmt. Servs., Inc.Costs , B284909.4, July 31, 2000,
2000 CPD 123 at 4 n.2 (corrective action taken before due date
for agency report on supplemental protest is prompt). (Williamson
County Ambulance Service, Inc. Costs, B-293811.4, September
16, 2004) (pdf)
Our Office may recommend that an agency reimburse a protester
its protest costs where, based on the circumstances of the case,
we determine that the agency unduly delayed taking corrective
action in the face of a clearly meritorious protest, thereby
causing the protester to expend unnecessary time and resources
to make further use of the protest process in order to obtain
relief. 4 C.F.R. 21.8(e) (2004); Shindong-A Express Tour Co.,
Ltd.Costs , B-292459.3, Mar. 25, 2004, 2004 CPD75 at 5. However,
where the agency action that rendered a protest academic does
not constitute corrective action in response to the protest, our
Office will not recommend reimbursement of protest costs.
Bionetics Corp.--Entitlement to Costs , B-270323.3, Aug. 16,
1996, 96-2 CPD 70 at 5; H. Watt & Scott Gen. Contractors,
Inc.--Request for Declaration of Entitlement to Costs ,
B-257776.3, Apr. 6, 1995, 95-1CPD 183 at 2-3; Loral Fairchild
Corp.--Entitlement to Costs , B-251209.2, May12, 1993, 93-1 CPD
378 at 2. Here, the agency continued to defend against the
protest after the contracts had expired. The administrative
contracting officer states that as a result of an administrative
lapse by the procuring activity, a request to exercise options
under either contract was not submitted to him until April 30,
the day on which the contracts expired. The contracting officer
explains that he did not have sufficient time to obtain the
necessary contractor consent and legal review prior to the time
the contracts expired and, therefore, he allowed the contracts
to expire. The contracting officer further states that he did
not consider the pending protests when he allowed the contracts
to expire, and that he did not notify agency legal counsel at
the time that the contracts had expired. There is nothing in the
record that calls into question the contracting officer's
statement that the expiration of the contracts was the result of
an administrative lapse rather than corrective action in
response to REMSA's protest. Indeed, the fact that the agency
continued to defend against the protest after the expiration of
the contracts supports the agency's position that it did not
take corrective action in response to the protest. Since the
agency did not take corrective action in response to REMSA's
protest, and REMSA's protest was not sustained, there is no
basis for recommending that the agency reimburse REMSA its
protest costs. (REMSA, Inc.--Costs,
B-293771.2, September 3, 2004) (pdf)
The fact the agency ultimately came to the position, as a result
of the new information presented by the protester, that bags
with an anti-reflux chamber would not meet its needs may have
justified the VA’s taking corrective action, but it does not
establish that selection of such bags initially was unlawful. We
conclude that the agency did not unduly delay its decision to
take corrective action in the face of a clearly meritorious
protest. (LSL Industries,
Inc.--Costs, B-291777.2, August 18, 2003) (pdf)
Where a proposal deviates from a specification by a
negligible amount, the agency may waive the requirement,
so long as it did not prejudice other vendors. Gulf Copper
Ship Repair, Inc., B-292431, Aug. 27, 2003, 2003 CPD ¶ 155
at 4 (deviation of 1 inch water depth specification
properly waived by agency); Magnaflux Corp., B-211914,
Dec. 20, 1983, 84-1 CPD ¶ 4 at 3-4 (agency permitted to
waive deviation from specification which was minor and did
not result in prejudice); Champion Road Mach. Int’l Corp.,
B-200678, July 13, 1981, 81-2 CPD ¶ 27 at 4 (deviation of
two horsepower is minor and should have been waived by
agency where price, quantity, quality, and delivery were
not affected). In our view, since the approximately
one-half mile deviation from the 25-mile requirement
appears minor on its face and, according to SSA, did not
diminish the purpose of the restriction, it could
reasonably be viewed by SSA as negligible. The deviation
therefore was waivable, so long as First Federal, the only
other vendor in the competition, was not prejudiced. There
is no evidence of competitive prejudice. In this regard,
while First Federal asserts that the waiver gave ISC an
“unfair competitive advantage,” (Protest at 9), it does
not show how it would have altered its proposal to improve
its competitive standing had it been given an opportunity
to respond to the relaxed requirement. See Copper Ship
Repair, Inc., supra. For example, it does not assert that
knowledge of the relaxation would have affected its price
or the location of its proposed facility. Given the
absence of any evidence of prejudice to First Federal, we
conclude that the agency had a defensible legal position
and, thus, that the protest was not clearly meritorious.
It follows that there is no basis to recommend
reimbursement of protest costs in this case. (First
Federal Corporation--Costs, B-293373.2, April 21,
2004) (pdf)
As a general rule, we consider a successful protester
should be reimbursed the costs incurred with respect to
all issues pursued, not merely those upon which it
prevails. Price Waterhouse--Claim for Costs, B-254492.3,
July 20, 1995, 95-2 CPD ¶ 38 at 3; Data Based Decisions,
Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2 CPD
¶ 538 at 4. While we have limited the award of protest
costs to successful protesters where a part of their costs
is allocable to a protest issue that is so clearly
severable as to essentially constitute a separate protest,
see, e.g., Interface Flooring Sys. Inc.--Claim for
Attorneys' Fees, B-225439.5, July 29, 1987, 87-2 CPD ¶ 106
at 2-3, limiting recovery of protest costs in all cases to
only those issues on which the protester prevailed would
be inconsistent with the broad, remedial congressional
purpose behind the cost reimbursement provisions of CICA.
TRESP Assocs., Inc.--Costs, B‑258322.8, Nov. 3, 1998, 98-2
CPD ¶ 108 at 2. Here, we conclude that the issues
raised are intertwined parts of AAR's basic objection that
the Marshals Service misevaluated proposals. Furthermore,
we do not find that the record established that there were
clearly severable issues upon which AAR would not have
prevailed. Accordingly, we see no reason why AAR's
recovery of protest costs should be limited to a
particular issue. (AAR Aircraft
Services--Costs, B-291670.6, May 12, 2003)
(pdf)
In sum, because KENROB's challenges to its own
evaluation and to the prices proposed by other vendors are
either untimely or without merit, and, as a result, KENROB
is not an interested party to challenge the evaluation of
Zen, we cannot conclude that any of the protest grounds
raised by KENROB are clearly meritorious. Georgia
Power Co.; Savannah Elec. and Power Co.--Costs,
supra. Accordingly, we have no basis upon which to
recommend that KENROB recover its protest costs. (KENROB
& Associates, Inc.--Costs, B-291573.7, April 25, 2003)
In our view, a reasonable agency inquiry into these
allegations would have disclosed the absence of a
defensible legal position and, by unduly delaying
corrective action, the agency caused the protester to
expend unnecessary time and resources to make further use
of the protest process to obtain relief. Georgia Power
Co.; Savannah Elec. and Power Co.--Costs, supra, at 6. The
Army correctly notes that this Office will consider
post-protest explanations that are credible and consistent
with the contemporaneous documentation in rendering a
decision, and that the Army might have prevailed in the
protest as a result of the hearing. See, e.g., Jason
Assocs. Corp., B-278689 et al., Mar. 2, 1998, 98-1 CPD ¶
67 at 6-7. Here, however, the Army provided written
post-protest information that was inconsistent with and
had little or no nexus to the contemporaneous record, yet
opted to forgo the hearing which might have permitted it
to prevail in the protest. That being the case, the record
before us stands as inadequately documented and
insufficiently supportive of the source selection
decision. (Martin
Electronics, Inc.--Costs, B-291732.2, April 22, 2003)
(pdf)
Our Bid Protest Regulations provide that where the contracting agency decides to take corrective action in response to a protest, we may recommend that the protester be reimbursed the costs of filing and pursuing its protest, including reasonable attorneys' fees. 4 C.F.R. § 21.8(e) (2002). This does not mean that costs should be reimbursed in every case in which an agency decides to take corrective action; rather, a protester should be reimbursed its costs only where an agency unduly delayed its decision to take corrective action in the face of a clearly meritorious protest. Griner's-A-One Pipeline Servs., Inc.--Entitlement to Costs, B-255078.3, July 22, 1994, 94-2 CPD ¶ 41 at 5; LB&M Assocs., Inc.,-- Entitlement to Costs, B-256053.4, Oct. 12, 1994, 94-2 CPD ¶ 135 at 4. Thus, as a prerequisite to our recommending that costs be reimbursed where a protest has been settled by corrective action, not only must the protest have been meritorious, but it also must have been clearly meritorious, i.e., not a close question. Georgia Power Co.; Savannah Elec. and Power Co.--Costs, B-289211.5, B-289211.6, May 2, 2002, 2002 CPD ¶ 81 at 5. A protest is “clearly meritorious” where the record plainly establishes that the agency prejudicially violated a procurement statute or regulation. Tri-Ark Indus., Inc.--Declaration of Entitlement, B-274450.2, Oct. 14, 1997, 97-2 CPD ¶ 101 at 3.
(Baine
Clark--Costs, B-290675.3, September 23, 2002)
Where a procuring agency takes corrective action in response to a protest, our Office
may recommend that the agency reimburse the protester its protest costs where,
based on the circumstances of the case, we determine that the agency
unduly delayed taking corrective action in the face of a clearly meritorious protest, thereby
causing a protester to expend unnecessary time and resources to make further use of
the protest process in order to obtain relief. Pemco
Aeroplex, Inc.--Recon. and Costs, B-275587.5, B-275587.6, Oct. 14, 1997, 97-2 CPD ¶102 at 5. A protest is clearly
meritorious when a reasonable agency inquiry into the protest allegations would
show facts disclosing the absence of a defensible legal position. AVIATE
L.L.C., B-275058.6, B-275058.7, Apr. 14, 1997, 97-1 CPD ¶ 162 at 16. For a protest to
be clearly meritorious, the issue involved must not be a close question. J.F. Taylor,
Inc.--Entitlement to Costs, B-266039.3, July 5, 1996, 96-2 CPD ¶ 5 at 3. Rather, the
record must establish that the agency prejudicially violated a
procurement statute or regulation. Tri-Ark Indus., Inc.--Declaration of Entitlement, B-274450.2, Oct. 14, 1997,
97-2 CPD ¶ 101 at 3. (Georgia
Power Company; Savannah Electric and Power
Company--Costs, B-289211.5, B-289211.6, May 2,
2002) (pdf)
When an
agency takes corrective action prior to our issuing a
decision on the merits, we may recommend that the
protester recover the reasonable costs of filing and
pursuing the protest. 4 C.F.R. sect. 21.8(e) (2001).
Under this provision, we will recommend recovery of
protest costs where, based on the circumstances of the
case, we conclude that the agency unduly delayed taking
corrective action in the face of a clearly meritorious
protest. Griner's-A-One Pipeline Servs.,
Inc.--Entitlement to Costs, B-255078.3, July 22, 1994,
94-2 CPD para. 41 at 5. For a protest to be clearly
meritorious, the issue involved must not be a close
question. J.F. Taylor, Inc.--Entitlement to Costs,
B-266039.3, July 5, 1996, 96-2 CPD para. 5 at 3. Rather,
the record must establish that the agency prejudicially
violated a procurement statute or regulation. Millar
Elevator Serv. Co.--Costs, B-281334.3, Aug. 23, 1999,
99-2 CPD para. 46 at 2. The fact that an agency decides
to take corrective action does not establish that a
statute or regulation clearly has been violated. J.F.
Taylor, Inc.--Entitlement to Costs, supra. (Sun
Chemical Corporation--Costs, B-288466.4, December 7,
2001)
Our Office may recommend
that a protester be reimbursed the costs of filing and
pursuing a protest where the contracting agency decides
to take corrective action in response to the protest. 4
C.F.R. sect. 21.8(e) (2001). Such recommendations are
generally based upon a concern that an agency has taken
longer than necessary to initiate corrective action in
the face of a clearly meritorious protest, thereby
causing protesters to expend unnecessary time and
resources to make further use of the protest process in
order to obtain relief. QuanTech, Inc.--Costs,
B-278380.3, June 17, 1998, 98-1 CPD para. 165 at 2-3.
The reimbursement of protest costs may also be
appropriate where an agency does not timely implement
the promised corrective action that prompted the
dismissal of a meritorious protest. Louisiana
Clearwater, Inc.--Recon. and Costs, B-283081.4,
B-283081.5, Apr. 14, 2000, 2000 CPD para. 209 at 6.
Where an agency implements corrective action that fails
to address a meritorious issue raised in the protest
that prompted the corrective action, such that the
protester is put to the expense of subsequently
protesting the very same procurement deficiency, the
agency action, even though promptly proposed, has
precluded the timely, economical resolution of the
protest. Id. Here, we have no basis to recommend that
NTMI recover the costs it incurred in filing its prior
protests because, even if the prior protests were
meritorious, USDA did timely implement the promised
corrective action that prompted the dismissal of the
protests. (New
Technology Management, Inc., B-287714.2; B-287714.3;
B-287714.4, December 4, 2001)
With respect to DOS's
concern with their authority to reimburse protesters for
the costs of filing and pursuing protests at GAO in the
absence of a recommendation from our Office, the Federal
Acquisition Streamlining Act of 1994, sect. 1066, 41
U.S.C. sect. 253b(l) (Supp. IV 1998), provides that if,
in connection with a protest, the head of an executive
agency determines that a solicitation, proposed award,
or award does not comply with the requirements of law or
regulation, the agency head may pay the costs described
within section 3554(c)(1) of title 31 of the United
States Code (protest costs and proposal preparation
costs) within the limits stated in section 3554(c)(2).
(Inter-Con
Security Systems, Inc.; CASS, a Joint Venture--Costs,
B-284534.7; B-284534.8, March 14, 2001) (pdf)
Regarding the other
prong of our analysis, the question of the promptness of
the agency's corrective action, we generally do not
consider corrective action to be prompt where it is
taken after the due date for the agency report. See CDIC,
Inc.--Entitlement to Costs, B-277526.2, Aug. 18, 1997,
97-2 CPD para. 52 at 2. GSA did not propose corrective
action until May 8, well after the agency had submitted
its report and the protester had incurred the time and
expense necessary to respond to that report. Under these
circumstances, we do not consider the corrective action
to have been prompt. Tri-Ark Indus., Inc.--Declaration
of Entitlement, B-274450.2, Oct. 14, 1997, 97-2 CPD para.
101 at 4-5. Accordingly, we recommend that Millar be
reimbursed its protest costs. Millar should submit its
claim for such costs, detailing and certifying the time
expended and costs incurred, directly to the agency
within 60 days of receipt of this decision. Bid Protest
Regulations, 4 C.F.R. sect. 21.8(f)(1) (2000). (Millar
Elevator Service Company--Costs, B-284870.3, August
3, 2000) (pdf)
|