GAO Sanctions,
COFC, Rule 11:
Signing of Pleadings, Motions, and Other Papers; Representations
to Court; Sanctions |
Comptroller General - Key Excerpts |
Abuse of Process
and Suspension
The protest at issue here is very similar to the many
other protests filed by Latvian Connection. In
implementing CICA’s mandate, our Office has devised simple
and flexible procedures that are easy to follow, and have
as a basic principle, elimination of barriers to filing a
protest. By design, our procedures make it easy and
inexpensive for a party to file and pursue a protest where
that party has a legitimate belief that some aspect of a
federal acquisition has been conducted improperly.
However, our Office necessarily reserves an inherent right
to dismiss any protest, and to impose sanctions against a
protester, where a protester’s actions undermine the
integrity and effectiveness of our process. PWC Logistics
Servs. Co. KSC(c), B‑310559, Jan 11, 2008, 2008 CPD ¶ 25
at 12. The inherent right of dispute forums to levy
sanctions in response to abusive litigation practices is
widely recognized and has been characterized by the
Supreme Court as “ancient in origin,” and governed not by
rule or statute, but by the control necessarily vested in
a forum to manage its own affairs. Roadway Express, Inc.
v. Piper et al., 447 U.S. 752, 765 (1980).
As detailed above, Latvian Connection has filed an
exceptionally large number of protests in fiscal year
2016. These filings reflect a larger pattern of vexatious
protesting that dates back several years. As set forth
above, these protests have challenged an array of
acquisitions conducted by a host of contracting agencies
worldwide. In the overwhelming majority of these protests,
the record has demonstrated that Latvian Connection either
was not an interested party to challenge the agency’s
actions, or raised challenges that were legally
insufficient. In other words, Latvian Connection--time and
again--either has failed to demonstrate that it was
capable of, or interested in, performing the solicited
requirements, or that it had a legitimate basis to
question an agency’s actions.
Indeed, despite filing protests challenging hundreds of
federal procurements, there is little or no evidence that
this company has the requisite direct economic interest in
any of these procurements. Publicly available information
provides no evidence that Latvian Connection has
successfully performed even a single government contract,
and there is no evidence in the many cases presented to
our Office to suggest that Latvian Connection engages in
any government business activity whatsoever beyond the
business of filing bid protests.
It has become evident to our Office, and to procuring
activities across the government, that Latvian
Connection’s protests are not filed for the purpose of
allowing the firm to compete on a relatively equal basis
for a requirement that it is capable of, and interested
in, performing. Moreover, the effect of Latvian
Connection’s protests is to hector the acquiring
activities--and our forum--with a stream of protests that
divert our collective time and resources. In the cases
described above, and in the many, many other cases Latvian
Connection has filed, attorneys for procuring agencies
have prepared responses to Latvian Connection’s protests
on the basis that Latvian Connection is not an interested
party to challenge these procurements; that its protests
are procedurally infirm in one way or another; or that
they simply are without merit. Correspondingly, our Office
has expended significant resources to process Latvian
Connection’s filings, review the facts and law, and
respond meaningfully and equitably to Latvian Connection’s
contentions.
The wasted effort related to Latvian Connection’s filings
is highlighted by its latest series of protests (including
the current protest) challenging acquisitions that were
conducted years ago, where performance is complete and
there is no possible remedy available. These protests have
placed a burden on GAO, the agencies whose procurements
have been challenged, and the taxpayers, who ultimately
bear the costs of the government’s protest-related
activities. When presented with evidence, as here, that
Latvian Connection does not hold the umbrella ID/IQ
contract under which the order was issued, or that the
order involves an amount lower than the statutory
threshold for GAO’s task order jurisdiction, Latvian
repeatedly fails to engage with the issues. Instead, the
company simply files a lengthy, often unrelated, harangue
that does not address the threshold issues that must be
answered by any forum as part of its review.
We conclude that the above-described litigation practices
by Latvian Connection constitute an abuse of our process,
and we dismiss the protest on this basis. Although
dismissal for abuse of process or other improper behavior
before our Office should be employed only in the rarest of
cases, it is appropriate here where we find that Latvian
Connection’s abusive litigation practices undermine the
integrity and effectiveness of our process. See PWC
Logistics Servs. Co. KSC(c), supra.
In addition, because of these abusive litigation
practices, and to protect the integrity of our bid protest
forum and provide for the orderly and expedited resolution
of protests, we are suspending Latvian Connection from
protesting to our Office for a period of one year as of
the date of this decision. We are taking this action to
conserve limited government resources that would otherwise
be expended to respond to meritless protests filed by an
entity with no direct economic interest in the outcome (as
required by our statute and regulations). We are also
taking this action because we have seen no evidence that
Latvian Connection is prepared to engage constructively on
the issues raised by the protests it files.
Our forum remains available to protesters with legitimate
concerns regarding the propriety of an agency’s
procurement activities, and we stand ready to entertain
protests from Latvian Connection at the end of this
period--provided those protests raise legitimate concerns
in acquisitions where Latvian Connection has a direct
economic interest in the outcome, and is prepared to
engage substantively on the issues it raises. But we also
conclude that allowing this pattern of abuse to continue
uninterrupted serves no useful purpose.
We do not take these actions lightly. We understand that
we temporarily are foreclosing to Latvian Connection one
avenue of redress that ordinarily would be available to a
concern interested in competing for a federal contract to
contend that the government has taken action that violates
procurement laws and regulations. 31 U.S.C. § 3554.
Nonetheless, on balance, suspending for one year Latvian
Connection’s eligibility to file protests with our Office
may incentivize the firm to focus on pursuing legitimate
grievances in connection with acquisitions for which there
is evidence that Latvian Connection actually is interested
in competing.
Our bid protest process does not provide, and was never
intended to provide, a platform for the complaints of
businesses or individuals that, to all outward
appearances, have no actual interest in, or capability to
perform, the government contracting opportunities to which
they have objected. Nor, as a forum for the expeditious
and inexpensive resolution of bid protests, are we
required to endure baseless and abusive accusations.
By separate letter of today to Latvian Connection, we are
advising the firm, and its principal, that both will be
precluded from filing a protest in our Office for a period
of one year from the date of this decision. As set forth
above, if, at the end of this period, Latvian Connection
wishes to raise concerns that an agency has violated
procurement laws or regulations in an acquisition where
Latvian Connection has a direct economic interest, and
Latvian Connection demonstrates that it is prepared to
engage substantively on the issues it raises, we will
again accept its protests in our forum. (Latvian
Connection LLC B-413442: Aug 18, 2016)
Clearly, there has been a
violation of the protective order here. Although the
partner and the associate explain that certain
circumstances regarding the process of creating redacted
party-unique versions of documents led to the violation,
there is no question, and it is not disputed by any of the
attorneys involved, that protected versions of the
protected comments and the protected response, containing
information proprietary to Anham, were improperly
disclosed to PWC personnel. As noted above, our
Regulations provide for the imposition of appropriate
sanctions in the case of a violation. Consistent with our
Office's practice, any sanctions concerning the
individuals admitted to the protective order here will be
separately considered by our Office subsequent to, and
separate from, the resolution of the protest.
This case, however, involves more than a protective order
violation. Although the protective order itself applies
only to the individuals admitted under it, our bid protest
forum cannot function effectively if the parties before
us--both counsel admitted to a protective order and their
clients who have not been admitted to it--do not treat
protected information appropriately. For that reason, our
Office's concern, when nonpublic information obtained
through our protective order has been improperly released,
goes beyond the individuals admitted to that order. We
view it as self-evident that a participant in our protest
process who was not admitted to a GAO protective order
cannot retain a document, however obtained, if the
document bears a legend clearly identifying it as
protected. In our view, that individual's responsibility,
once he or she sees the protective legend, is to
immediately close the document, advise his or her counsel
admitted to the protective order of the disclosure, and
turn the protected document over to counsel (or destroy
it); retaining the document is improper.
Based on our review of the record, we agree with
intervenor's counsel and the Army that the actions of the
PWC employees to whom the protected material was disclosed
were inconsistent with, and undermined, the integrity of
our Office's bid protest process. Although a number of
facts remain unclear or are disputed, all parties
acknowledge that PWC's Chief of Contract Administration
and PWC's Vice President/General Counsel each improperly
received from the associate on November 29 the protected
comments and protected response. It is also clear that
these documents bore on each page the notation –PROTECTED
MATERIAL TO BE DISCLOSED ONLY IN ACCORDANCE WITH
GOVERNMENT ACCOUNTABILITY OFFICE PROTECTIVE ORDER,— and
that even a cursory review of the protected comments would
reveal that they contained technical, cost and price
information proprietary to Anham. It is also undisputed
that these documents remained in PWC's Chief of Contract
Administration's e-mail (and thus his possession and
control) until at least December 6, and in PWC's Vice
President/General Counsel's e-mail (and thus his
possession and control) until at least December 8 (the
protected response) and December 13 (the protected
comments), and that at least the protected response was
provided to at least 10 other PWC employees.[9]
Moreover, PWC concedes that its Vice President/General
Counsel forwarded, at a minimum, the protected response to
three other PWC personnel (including PWC's Chief of
Contract Administration), and that at least one of these
individuals (other than PWC's Chief of Contract
Administration) read, to some extent, the protected
response. PWC Submission (Dec. 17, 2007), Tab 5,
Declaration of PWC Vice President/General Counsel, at 3;
Tab 7, Declaration of PWC Executive Regional Director
Middle East, at 4-5. Additionally, it is clear from the
record that PWC's Chief of Contract Administration
forwarded the protected response, at a minimum, to 10
other PWC personnel (including PWC's Vice
President/General Counsel), and that at least 5 of these
individuals read, to some extent, the protected response.
PWC Submission (Dec. 17, 2007), Tab 4, Declaration of
PWC's Chief of Contract Administration, at 5; Tab 12,
Declaration of PWC's Senior Contracts Manager-Iraq, at 3;
Tab 15, Declaration of PWC's Contract Manager, at 3; Tab
18, PWC's Deputy Program Manager, at 3; Tab 19,
Declaration of PWC's Chief Executive Officer and President
International, at 3; Tab 20, Declaration of PWC's Program
Manager, at 3. Additionally, with the exception of the
declaration of PWC's Vice President/General Counsel, there
is no explanation in any of the declarations submitted by
the PWC personnel of why the declarant(s) believed it
permissible to read or even possess (and, in some
instances, forward to other PWC personnel) documents
labeled as protected and subject to the protective order
issued by our Office.
Furthermore, as argued by Anham's counsel and the Army,
other facts as set forth by the partner, the associate,
and certain PWC personnel are internally inconsistent. For
example, as noted previously, the associate represented in
his December 11 explanation (prior to the intervenor's
request for summary dismissal and our Office's request for
a more complete explanation) that PWC's Vice
President/General Counsel and PWC's Chief of Contract
Administration –[r]ead— both the protected comments and
the protected response. However, in his December 17
submission to our Office, the partner asserts that –it
appears that neither— PWC's Vice President/General Counsel
nor PWC's Chief of Contract Administration had –read— the
protected comments. Protester's Submission (Dec. 17, 2007)
at 2, 7. This assertion is apparently based on the
December 17 declaration of PWC's Vice President/General
Counsel, where, in direct contradiction of the previous
representation, he states that he had –deleted— without
reading the e'mail containing the protected comments based
upon his –belief— that the e-mail was a duplicate of the
associate's e'mail that included the protected response as
an attachment. Protester's Submission (Dec. 17, 2007) at
6-7; see Tab 5, Declaration of PWC's Vice
President/General Counsel, at 3. The partner also notes
that, according to PWC's Chief of Contract
Administration's December 17 declaration, that individual
did not open the attachments to the e-mails from the
associate (contradicting the associate's December 11
submission), but reviewed the attachments to the e'mail
that he received from PWC's Vice President/General
Counsel, which assertedly only contained the protected
response, and then forwarded this attachment to the 10 PWC
employees. Protester's Submission (Dec. 17, 2007) at 7;
see Tab 4, Declaration of PWC's Chief of Contract
Administration, at 3-4.
The partner explains the discrepancy between the
associate's December 11 explanation to our Office that
unequivocally stated that both PWC's Vice
President/General Counsel and PWC's Chief of Contract
Administration had –[r]ead— the protected comments, and
the later assertions that neither PWC's Vice
President/General Counsel nor PWC's Chief of Contract
Administration had read or reviewed the protected
comments, by stating that at the time the December 11
explanation was submitted, counsel for PWC, –having had
little ability to interview the two gentlemen, . . .
perhaps too hastily, chose to be conservative and stated
that both recipients had read 'both of the documents.'—
Protester's Submission (Dec. 20, 2007) at 7. The partner
asserts here that after –talking with [PWC's Vice
President/General Counsel and PWC's Chief of Contract
Administration] at length, it became apparent that neither
of them had read the [protected] [c]omments and they so
declared.— Id.
In our view, the partner's explanations do little to
clarify the issue. For example, they do not adequately
explain why the recollections of PWC's Vice
President/General Counsel and PWC's Chief of Contract
Administration, as to what occurred between November 29
and December 5, were less accurate on December 11 than
they were in their declarations of December 17. Nor do we
find the partner's explanation of December 17 persuasive,
given, among other things, the statement in PWC's Chief of
Contract Administration's declaration that he –remember[ed]
the attachments seeming to do an effective job of
responding to the assertions it stated were made by Anham—
(which suggests through the use of the plural
–attachments— that he also read the more detailed
protected comments). PWC Submission (Dec. 17, 2007),
Tab 4, Declaration of PWC's Chief of Contract
Administration, at 4.
Leaving aside the inconsistencies, we can return to the
undisputed facts. Employees at PWC who inappropriately
received the two protected documents retained them for
approximately one week, until counsel directed them to
destroy them. Some of those PWC employees read, to some
extent, at least one of the documents; some of them then
disseminated at least one of the documents to other PWC
employees. While the protester (both the client and
counsel) would have us focus on whether the individuals
admit –reading— or only –scanning— the protected
documents, on how long this action lasted, on whether
anyone remembers the contents of the protected documents,
and on whether only one, rather than both, of the
protected documents were looked at, these are all
irrelevant to the fundamental question of whether the
individuals acted improperly by retaining the documents,
since even a short glance at any page of either document
would ensure that the protected legend was seen.
We turn then to consideration of the request that the
protest be dismissed because of this improper action. We
have recognized that where a protester's actions undermine
the protective order's effectiveness, and thereby the
integrity of our Office's bid protest process, it is
appropriate to consider dismissing the protest to protect
the integrity of that process. We view our authority to
impose dismissal or other sanctions as inherent, as do
courts. Network Sec. Techs., Inc., B'290741.2, Nov. 13,
2002, 2002 CPD para. 193 at 8; see Roadway Express Inc. v.
Piper, 447 U.S. 752, 754 (1980); Reid v. Prentice'Hall,
261 F.2d 700, 701 (6th Cir. 1958) (–[e]very litigant has
the duty to comply with reasonable orders of the court,
and if such compliance is not forthcoming, the court has
the power to apply the penalty of dismissal—).
We recognize that dismissal is a severe sanction, and that
it should be employed only in the rarest of cases. Indeed,
we are acutely aware, and it weighs against the dismissal,
of the general public policy favoring a decision on the
merits. Balanced against these factors are a number of
other factors that lead us to conclude that dismissal is
appropriate here. As discussed below, those factors are
the inadequacy of lesser available sanctions, the
protester's (as opposed to its counsel's) responsibility
for what occurred, the gravity of what occurred and the
prejudice to the intervenor and the agency resulting from
it, and the salutary deterrent effect of dismissal on
others who might be tempted to such conduct in the future.
See National Hockey League v. Metropolitan Hockey Club,
Inc., 427 U.S. 639, 643 (1976); Alaska Pulp Corp. v.
United States, 41 Fed. Cl. 611, 614'15 (1998); Griffin &
Dickson v. United States, 16 Cl.Ct. 347, 351 (1989).
A number of –lesser sanctions— considered by the courts,
such as the imposition of fines or costs, are unavailable
to our Office, and other lesser sanctions are, in our
view, inadequate. In particular, the possible –lesser
sanction— of admonishment or other measures aimed at PWC's
outside counsel who are admitted to the protective order
do not address the conduct of the protester itself, which,
as set forth above, we find troubling. Those employees of
the client, not their outside counsel, are responsible for
their conduct, and a sanction directed at counsel does not
reach that conduct. Moreover, the PWC employees had at
least constructive notice, from both our Bid Protest
Regulations and our decision in Network Sec. Techs., Inc.,
supra, that a protester's actions in the context of a
violation of the protective order could result in
dismissal of the protest. Hence, PWC cannot view our
consideration of dismissal for the mishandling of
protected information as unfair or unexpected.
Regarding prejudice, protester's counsel, in arguing that
dismissal is not appropriate, points out that the PWC
employees that submitted declarations that recall
receiving the protected comments and/or the protected
response, state that they have little or no recollection
of the contents of the protected documents, and that a
number of the PWC personnel state in their declarations
that they do not even recall reading to any extent the
protected comments or the protected response. Counsel for
the protester argues that because the PWC personnel cannot
recall the contents of the protected comments and the
protected response, there was little or no harm caused by
the disclosure of the protected documents. Protester's
counsel explains that the PWC personnel did not read the
protected documents because they were either too busy, or
because PWC does not view Anham (the awardee of the
subject procurement, for which PWC was the incumbent
contractor) as a major competitor. PWC Submission (Dec.
20, 2007) at 9. Protester's counsel concludes that,
because in his view Anham has suffered no competitive harm
from the disclosure of the protected comments and
protected response to PWC personnel, it would be
inappropriate to dismiss the protest.
Given the self-serving nature of the declarations relied
on in this argument by counsel, and our agreement with the
Army and intervenor that the declarations and explanations
submitted are both incomplete and inconsistent, we find
them to be of little probative value. Moreover, unlike the
protester's focus on whether the various PWC employees who
received the protected information read it, merely skimmed
it, or forgot what they did read, our analysis of
prejudice should focus more on the nature of the
information provided to those employees and the length of
time that they retained it. As discussed above, the
information included in the protected comments, and to a
lesser extent, the protected response is sensitive and
proprietary to Anham, so that, faced with its undisputed
transmission to PWC employees and their retention of it,
we find that the potential for prejudice to Anham was
significant.
Finally, we return to our concern for protecting the
effectiveness of the protective order process and the
integrity of our bid protest system. Private parties and
agencies whose information, whether proprietary or
source-selection-sensitive, is provided under the aegis of
our protective orders need to have the assurance that our
Office will be vigilant in protecting that information, to
the extent that we are able to do so. Any individual who
might be inclined to show little respect for the
protective order process must know that a lack of due care
in the handling of protected information will not be
tolerated and may lead, in the appropriate circumstances,
to dismissal of a protest. Having considered the entire
record, we conclude that that is the appropriate course
here.
The protest is dismissed. (PWC
Logistics Services Company KSC(c) B-310559: Jan 11,
2008) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
Latvian
Connection LLC B-413442: Aug 18, 2016. |
|
PWC
Logistics Services Company KSC(c) B-310559: Jan 11,
2008 |
|
U.
S. Court of Federal Claims- Key Excerpts |
On May 31, 2016, USSOCOM issued RFI No. H92222-16-GRAP02 in order to gather
information regarding “small businesses’ ability to support [Global Research and
Assessment Program] GRAP while ensuring compliance
with FAR 52.219-14, Limitations on Subcontracting.” AR 1. After reviewing responses from
interested contractors, USSOCOM concluded that “14 respondents were [] capable of supporting
the GRAP requirements [and] the majority of respondents addressed FAR 52.219-14.” Id. at 156.
Satisfied that a small business could perform the GRAP requirements while complying with the
LOS clause, USSOCOM posted Solicitation H9222-17-R-0009 as a small business set-aside
incorporating the LOS clause on November 14, 2016. Id. at 354. Gallup is not a small business,
and thus was ineligible to compete under the Solicitation. Gallup challenged the rationality of
USSOCOM’s set-aside decision specifically arguing that the RFI responses did not indicate that
a small business could satisfy both the GRAP requirements and the LOS clause simultaneously.
Pl.’s Mot. at 1.
Gallup filed this bid protest on December 16, 2016. See Dkt. No. 1. The Government filed
the Administrative Record on January 6, 2017. See Dkt. No. 10. The Administrative Record
contains a key document entitled “Market Analysis (June 24, 2016)” which provides the only
record of USSOCOM’s evaluation of the RFI responses and basis for the small business set-aside
decision. AR, Index at 2, 156-60. First, the Market Analysis contains a “Memorandum for
Record” which includes the following pertinent language:
The GRAP team . . . reviewed the responses and consolidated
comments on the attached matrix, see Enclosure 1. [. . .] Of the 22
responses from small businesses, 14 respondents were determined
capable of supporting the GRAP requirements. While a majority of
responses addressed [the LOS clause], the responses from [three small
businesses] provided the most extensive and detailed information
regarding compliance with the clause. Based on the assessment of
responses received as detailed in the enclosure and with concurrence
from all members of the team, the responses were determined
sufficient and alleviated the government’s concerns. As such, the
GRAP acquisition will be processed as a small business set-aside.
Id. at 156 (emphasis added). The Contracting Officer, Ms. Julia A. DeLoach, signed the
Memorandum for Record. Id. While the document itself contains no date, the Index identifies
June 24, 2016 as the date of creation for the Memorandum of Record. Id., Index at 2. Second,
the Market Analysis contains an undated chart, referenced as “Enclosure 1” in the Memorandum
for Record, which summarizes the USSOCOM evaluation team’s comments on each RFI
response. Id. at 157-60. Importantly, the chart alone does not indicate that “[a] majority of
respondents addressed [the LOS clause].” Id. at 156. Instead, the chart contains a column entitled
“Plan for addressing at least 50%” (seemingly referring to the LOS clause) for which each RFI
response received a “yes” or “no,” with only three small businesses receiving a “yes.” Id. at 157-
60. Thus, the Memorandum for Record is the only consensus documentation of USSOCOM’s
decision to process the GRAP acquisition as a small business set-aside. Pursuant to normal Court
procedures, the Administrative Record also contains a “Certification of Contracting Office”
signed by Ms. DeLoach affirming that “after careful review, the following documents constitute
the record of administrative actions . . . .” Id., Certification following Index (emphasis added).
On March 27, 2017, after the parties completed briefing on their cross-motions for
judgment on the administrative record, the Government filed a Notice of Corrective Action stating
that “[b]ecause broader, more-integrated support services are now needed, USSOCOM has
determined that it is in the United States’ best interests to cancel the current small business setaside
procurement . . . .” Dkt. No. 21, at 1. In addition, the Government notified the Court that
on March 23, 2017 the Government learned the Memorandum for Record “had been prepared on
or about December 15, 2016, i.e., after the agency had proceeded with the procurement as a small
business set-aside and had received [Gallup’s] pre-filling notice regarding its putative protest (the
accompanying chart was created in June 2016).” Id. at 2. The Government further requested that
the Court cancel oral argument on the cross-motions scheduled for March 30, 2017. Id.
In order to “uncover the nature of the inaccuracy present in the administrative record and
determine whether any action should be taken by this Court”, the Court issued an Order retaining
the March 30, 2017 hearing date, and requiring “all those individuals who assisted in the
production of the administrative record” to attend the hearing. Dkt. No. 22, at 1.
At the hearing, the Court questioned Ms. DeLoach while she was under oath. DeLoach,
Tr. 14:22-25:20. Ms. DeLoach testified that she has worked as a Contracting Officer for
“probably 25 plus, maybe 30 years” and currently holds an “unlimited warrant.” Id. at 15:13-14,
15:21. She further testified that she personally compiled the Administrative Record in this case
without any assistance, including choosing the June 24, 2016 date for the Memorandum for
Record in the Index, and signed the Certification of Contracting Office. Id. at 16: 12-18, 21:15-
19; 24:15. Ms. DeLoach confirmed that the chart accompanying the Memorandum for Record
was created on June 24, 2016 and that it accurately represents the contemporaneous comments of
the USSOCOM evaluation team. Id. at 18:18-19:12. When presented with the Memorandum for
Record and asked to explain why she created the document, Ms. DeLoach responded:
[W]hen I received the pre-filing notice about December 13th, I said,
uh-oh, if [Gallup] really file[s], I need to make sure my record [is] in
good shape. […] I realized I had the [chart] with nothing that
consolidated that or nothing that summarized that and I prepared the
[Memorandum for Record] at that time, sir. I now know that [] was a
huge mistake and I am deeply sorry that this has come to this. . . .
[T]he timing was wrong.
Id. at 20:6-18. Ms. DeLoach testified that she prepared the document on December 13th or 14th
of 2016 and no one assisted her.
Id. at 21:7, 27:2-5. Finally, Ms. DeLoach confirmed that the
GRAP acquisition was already “underway” when she created the Memorandum for Record and
thus the memorandum could not have been the basis for the agency’s set-aside decision. Id. at
22:19-25 (demonstrating the misleading nature of the Memorandum for Record’s forward-looking
statement: “As such, the GRAP acquisition will be processed as a small business set-aside.” AR
156).
On March 30, 2017, immediately following the hearing, the Court issued an Order to Show
Cause stating that “the Court contemplates the imposition of sanctions against USSOCOM for
violating Rule 11(b)(3) of this Court” and ordered the Government to “explain[] why the Court
should not require USSOCOM to pay Gallup’s attorney’s fees and costs associated with the
prosecution of this bid protest.” Dkt. No. 23, at 1-2. RCFC 11(b)(3) requires all representations
made to the Court to have proper evidentiary support and RCFC 11(c) provides that “the court
may impose an appropriate sanction on any . . . party that violated [Rule 11(b)]”. Knowingly
providing inaccurate information to the Court is certainly grounds for sanctions under RCFC
11(c). See e.g., Jimenez v. Madison Area Tech. Coll., 321 F.3d 652, 655-57 (7th Cir. 2003)
(upholding sanctions against a party who presented manufactured documents to support
allegations in her complaint); Gonzales v. Trinity Marine Grp., Inc., 117 F.3d 894, 898-99 (5th
Cir. 1997) (holding that a court could issue sanctions for fabrication of evidence under its inherent powers); Pope v. Fed. Express Corp., 974 F.2d 982, 984 (8th Cir. 1992) (upholding sanctions
against a party who produced manufactured documents as an exhibit).
A recent bid protest before this Court, Coastal Environmental Group Inc. v. United States,
presents nearly identical facts to those here and further supports the imposition of sanctions in this
case. 118 Fed. Cl. 15 (2014). In Coastal Environmental Group, an EPA official included a
backdated document in the administrative record in order to “make it appear to anyone who read
the document that she prepared and signed the document ten months earlier than she actually did.”
Id. at 35. The official then “attempted to cure her oversight by preparing . . . a Determination and
Findings document.” Id. Accordingly, Judge Margaret Sweeney of this Court imposed sanctions
under RCFC 11(c) and ordered the agency to pay the plaintiff’s attorney’s fees and costs and a
$1,000.00 fine. Id. at 38. Ms. DeLoach also realized her record was incomplete and attempted to
“cure her oversight” by preparing a Memorandum for Record nearly six months after USSOCOM
made its set-aside decision.
On April 12, 2017, the Court held a telephonic status conference at the request of the parties
during which counsel for the Government indicated (and confirmed in writing the same day) that
the parties had “reached an agreement in principle for USSOCOM to pay Gallup’s attorney fees
and litigation costs . . . as contemplated by the Court’s order.” Dkt. No. 28, at 1. In addition, the
Government noted that USSOCOM will:
issue guidance to its contracting staff emphasizing the importance of
completeness, accuracy, and integrity in preparing records and
accompanying certifications [and] is in the process of planning a
training session . . . that will focus on issues of accuracy and ethics in
preparing and certifying administrative records.
Id. at 1-2. Therefore, the Government does not dispute the appropriateness of sanctions in this
case. Id. at 2. Gallup is “satisfied that these actions, once consummated, will constitute an
adequate remedy for the problems identified with the administrative record . . . .” Dkt. No. 29, at
1. Given this agreement, the formal imposition of sanctions under RCFC 11(c) is unnecessary.
The Government will file a status report on or before May 17, 2017 indicating what progress has
been made towards the payment of Gallup’s attorney’s fees and costs and the implementation of
USSOCOM’s proposed ethics guidance and training session.
Conclusion
The integrity of the administrative record, upon which nearly every bid protest is resolved,
is foundational to a fair and equitable procurement process. While the Government has accepted
responsibility for its misconduct, the importance of preventing a corrupted record cannot be
overstated. The Court encourages USSOCOM to take all reasonable steps to ensure that its
contracting office appreciates the necessity of conducting a well-documented, well-reasoned procurement and producing a meticulous and accurate record for review. The Court will not
tolerate agency deception in the creation of the administrative record. (Gallup,
Inc. v. U. S., No. 16-1656C, April 25, 2017)
3. The Court’s Ruling.
In this case, the Government’s first explanation, as to why RCFC 11(b) sanctions are not
warranted, is that the Government’s August 23, 2016 Response to Plaintiff’s August 11, 2016
Motion For Judgment On The Administrative Record And Cross Motion and the Government’s
September 15, 2016 oral statement “Must Be Viewed As A Whole.” Gov’t Resp. at ii, 10–14. In
support, the Government cites two non-precedential decisions from another jurisdiction and a 1989
text for the proposition that: “the focus of . . . rule [11] is the court paper as a whole, not individual
phrases or sentences construed separately or taken out of context.” Gregory P. Joseph, Sanctions:
The Federal Law of Litigation Abuse § 9(D) at 133–34 (1989); see also Young v. City of Providence
ex. rel Napolitano, 404 F.3d. 33, 41 (1st Cir. 2005) (“The general rule is that statements must be
taken in context, and that related parts of a document must be taken together.” (internal citations
omitted)). None of these sources are helpful to the Government.
The United States Court of Appeals for the First Circuit in Navarro-Ayala v. HernandezColon,
3 F.3d 464 (1st Cir. 1993) reversed a trial court’s decision to impose Rule 11 sanctions for
failing to make a “reasonable inquiry.” Gov’t Resp. at 11. In this case, however, the court made
that inquiry, therefore complying with RCFC 11(c), in the December 5, 2016 Memorandum
Opinion. See 129 Fed. Cl. at 509. In addition, in Navarro-Ayala v. Hernandez-Colon, that federal
appellate court found that the plaintiff’s written motion contained “no significant false statements”
and was “not literally false.” 3 F.3d at 467. In this case, however, the Government’s August 23,
2016 Cross Motion And Response To Level 3’s August 23, 2016 Motion For Judgment On The
Administrative Record affirmatively represented that Verizon would “begin performance on
December 1, 2016.” ECF No. 36 at 25 (emphasis and bold added).
As such, the Government’s
August 23, 2016 Response was a “significant false statement.” Navarro-Ayala, 3 F.3d. at 467.
Nor was the Government’s August 23, 2016 written representation to the court an “isolated factual
error,” as the colloquy between the court and Government’s counsel at the September 15, 2016
oral argument evidences. 9/15/16 TR at 40–43.
Likewise, the Government’s statement of the “Proceedings Before This Court” in its
January 17, 2017 Response, omits any reference to the September 15, 2016 Oral Argument (ECF
No. 62 at 2–6), but instead represents that “[i]t was not until the November 14, 2016 hearing that
the [Government] realized that a misunderstanding had developed between the parties and the
court.” Gov’t Resp. at 6 (citing A27 Bigler Decl. at ¶¶ 4–5). In addition, the Government’s prior
misrepresentation was exacerbated by the Government’s failure to inform the court—at least on
November 1, 2016—that Verizon completed work on the circuit and turned it over to DISA.
11/14/16 TR at 9–10; see also Town of Tiverton, 469 U.S. at 240 (“It is appropriate to remind counsel that they have a ‘continuing duty to inform the Court of any developments that may
conceivably affect the outcome’ of the litigation.” (quoting Fusari, 419 U.S. at 391 (Burger, C.J.,
concurring))).
To place the Government’s conduct in further context, it is important to understand that, in
fiscal 2016 alone, approximately 120 bid protests were filed in the United States Court of Federal
Claims. These cases take precedence over all other cases on the docket, because the complaint
almost always demands issuance of a temporary and/or permanent injunction to prohibit the
Government from performing work under a contract. In addition, as the Government was well
aware, in fiscal 2016, the court operated with 10 active judges, instead of the 16 authorized. But
even not all of those 10 active judges could accept bid protests, because they were in trial or for
other administrative reasons. Therefore, it was not unusual for the judges available to accept bid
protests to be assigned two and sometimes three or more bid protests in a month. It is also
important to understand that the Administrative Record in bid protest cases is not made available
to the plaintiff or the court for at least a week and sometimes longer; briefing usually does not
follow for several additional weeks. Therefore, the court must rely on the Government’s
representation as to the precise status of contract performance to ascertain whether the
circumstances warrant an injunction. If the Government will not voluntarily stay performance, the
court is then faced with the dilemma of having to consider whether to issue an injunction, without
a full record, to preserve plaintiff’s ability potentially to be reconsidered and awarded the contract
at issue. In this case, the court initially decided not to issue an injunction, because of the
Government’s representation that no significant work on the contract would take place before
December 1, 2016. Therefore, the Government’s written and oral representations “taken in
context” and “taken as a whole” were not accurate. See Young, 404 F.3d at 41. The most important
issue at the time of the Government’s written and oral representations was whether a temporary or
permanent injunction was warranted. As the transcript of the September 15, 2016 oral argument
shows—if the only work that Verizon was doing was to “get their subcontracts in place, all their
permits in place, things like that, and make sure they’re ready on December 1st” ( 9/15/16 TR
(Gov’t Counsel) at 41)—then an injunction was not warranted. But, that representation was not
accurate.
The Government’s second explanation as to why sanctions are not warranted, in this case,
is that the “Government’s Factual Contentions Were Accurate And Supported By A Declaration.” Gov’t Resp. at ii, 14–15. Here, the Government relies on the July 15, 2016 unclassified Schmitt
Declaration, that reported: “on 29 June 2016, the [C]ontracting [O]fficer lifted the stop work order
and established new service date for STM–64 as 1 December 2016, based upon Verizon’s lead
time of 150 days to provide service.” 7/15/16 Schmitt Decl. at ¶ 8. The fact that the CO established
a new service date, “as 1 December 2016” is consistent with the Government’s August 23, 2016
Response that Verizon would “begin performance on December 1, 2016,” since some portion of
the 150 days to prepare for performing the March 8, 2016 contract, i.e., testing the circuit, hiring
subcontractors and obtaining permits, would have taken place by December 1, 2016. 9/15/16 TR
at 40–41 (Gov’t Counsel: “[Verizon has] got to set the circuit up and test it . . . They get their
subcontracts in place, all their permits in place, things like that[.]”). If that was true, it was
reasonable for the court to assume that Verizon could not only commence contract performance
on December 1, 2016, but also be able to complete that work in December 2016.
The Government’s third explanation as to why sanctions are not warranted, in this case, is
that the Government’s August 23, 2016 representation that “Verizon would begin performance on
December 1, 2016” was “to make the point that, if the court entered an injunction, the
telecommunications circuit would not be ready by December 1, 2016.” Compare ECF. No. 36 at
25 with Gov’t Resp. at 15. In the court’s judgment, based on all the circumstances and in context,
the Government’s August 23, 2016 representation that “Verizon would begin performance on
December 1, 2016” (ECF No. 36 at 25) was made for the sole purpose of persuading the court not
to enter an injunction, so that Verizon could continue and complete performance of the circuit,
depriving Level 3 of the opportunity to do that work, and receive the [dollar amount] that the
Government now owes Verizon. ECF No. 50 at ¶ 12.
The Government’s fourth and final explanation as to why sanctions are not warranted, in
this case, is that the court was advised on August 1, 2016, that the CO lifted the stop order on June
28, 2016, after the GAO denied Level 3’s protest, and established a “new service date.” ECF No.
62 at 16 (citing 8/1/16 TR at 5). It is true that “[the Government’s] counsel could not be charged
with misrepresenting a fact to the court when the court itself knew the true facts and thus could
not have been misled by the less-than-clear assertions by the party subject to the sanctions order.”
1-10 Industry Associates, LLC, 528 F.3d at 868 (citing Young, 404 F.3d at 41 ). But, in this case,
the Government’s August 1, 2016 statement that the CO lifted the stay order and established a new
service date was followed on August 23, 2016 by a written statement to the contrary—that Verizon
“would begin performance on December 1, 2016” (ECF No. 36 at 25) and repeated at the
September 15, 2016 oral argument, 9/15/16 TR at 40 (Gov’t Counsel: “Verizon, right now, is
preparing to perform on December 1st.”) (emphasis and bold added). Therefore, it was
reasonable for the court to rely on what appeared to be the Government’s change in position,
particularly since the transcript of the subsequent September 15, 2016 oral argument evidences
that the court repeatedly asked the Government’s counsel to define precisely what it meant by the
term “preparing to perform” (9/15/16 TR at 40), and “what [is] Verizon preparing” (9/15/16 TR at
40).
RCFC 11(b) contains four prerequisites, before the court may impose a sanction. See
RCFC 11(b)(1)–(4). In this case, the written and oral statements made by the Government to the
court must be excused under RCFC 11(b)(3) and (4), under an “objective reasonableness
standard.” See 1-10 Industry Assoc’s, 528 F.3d at 869 (“Other courts applying the objective
reasonableness standard have pointed out that the test “is one of reasonableness under the
circumstances.”(quoting White v. Gen. Motors Corp., 908 F.2d 675, 680 (10th Cir. 1990))). This
is so because, RCFC 11(b) provides that a factual contention need not have evidentiary support at
the time it is made, provided that it “will likely have evidentiary support after a reasonable
opportunity for further investigation or discovery.” If this is the standard, than it appears to the
court that this Rule serves no purpose, since any savvy advocate can generate post-conduct
evidence to “paper over” and justify a misrepresentation to the court. Fortunately the United States
Supreme Court may have recognized the potential loopholes in Federal Rule of Procedure 11,
when it held in Chambers v. NASCO, Inc., 501 U.S. 32 (1990), that “where the conduct at issue is
not covered by one of the other sanctioning provisions . . . a federal court [is not] forbidden to
sanction bad-faith conduct by means of the inherent power . . . . [I]f[,] in the informed discretion
of the court, neither the Statute nor the Rules are up to the task, the court may safely rely on its
inherent power.” Id. at 50. In this case, in the court’s judgment, considering the totality of circumstances, and the context of the Government’s statements, this is not a case where there was
a “miscalculation of facts,” as in 1-10 Industry Associates, 528 F.3d at 870, but a breach of the
duty of candor. See Precision Specialty Metals, 315 Fed. Cir. at 1357–58 (“Without regard to
whether [the Government’s counsel’s] misconduct violated Rule 11, the sanction imposed upon
[counsel] would have been sustainable under the inherent power to control and specify the
standards of lawyers before it.”).
IV. CONCLUSION.
For the aforesaid reasons, the court has determined that the Government did not violate RCFC 11(b), but violated the duty of candor to the court. Mr. Douglas Mickle, the direct
supervisor of the Government’s counsel in this case, has appeared before the court in other cases,
where Mr. Mickle’s substantive expertise and professional conduct always has reflected the
highest standard that the court expects from all counsel, most importantly the Government’s
counsel. Some forty-plus years ago, the court, as a GS-12 trial lawyer in the Department of Justice,
was trained to be truthful, direct, and complete in all communications with federal judges. “First
and always,” in the words of my supervising chief. Maybe times have changed. Maybe not. In
any event, the court has determined to rely on Mr. Mickle’s professional judgment as to whether
Robert C. Bigler should receive an adverse report in his annual performance review or other actions
to impress, not only on him, but on other Government lawyers who practice before the United
States Court of Federal Claims and other federal courts, that the duty of candor matters.
(Level 3
Communications, LLC v. U. S. and Verizon Deutschland GmbH,
No. 16-829, March 16, 2017)
This bid protest concerns the Defense Information Systems Agency’s decision to award a
federal contract for construction and maintenance of a Structured, High Availability
Telecommunications Circuit between Wiesbaden, Germany and Arifjan, Kuwait to Verizon
Deutschland GmbH at a price of $38.6 million more than the bid of Level 3 Communications,
LLC, the company that had been performing on the job for several years. Today, the court has
entered an injunction to prohibit any further work from being performed under this contract, but
also ordered the Defense Information Systems Agency (“DISA”) to provide its files in this matter
to the Inspector General of the Department of Defense for further investigation, particularly in
light of the fact that lawyers from the Department of Justice and DISA informed the court, both in
writing and at oral argument, that performance would not commence until December 1, 2016. In
fact, performance began on June 29, 2016 and DISA "accepted" a completed telecommunications
circuit on November 1, 2016—only a few days before the November 8, 2016 election. Although
the court has authority to issue sanctions against the lawyers involved, the Inspector General has
authority to ensure the integrity of the procurement process, and the Senate Armed Services
Committee has oversight responsibility determine whether the American taxpayers are served by
this type of procurement, albeit in support of our military requirements in the Middle East.
(sections
deleted)
On September 15, 2016, the court convened an Oral Argument on the parties’ CrossMotions
For Judgment On The Administrative Record. ECF No. 42 (“9/15/2016 TR”). During
the Oral Argument, the court suggested that Level 3 file an Amended Complaint, since the July
12, 2016 Complaint did not identify which statutes or regulations that DISA violated by granting an award to Verizon. 9/15/2016 TR at 6–7. In addition, the court asked the Government’s counsel
about the status of the contract, and the Government represented that Verizon was preparing to
perform on December 1, 2016:
[THE COURT]: So tell me what’s happening right now. Verizon has the contract.
What are they doing?
[THE GOVERNMENT]: No, I know, Your Honor. Verizon, right now, is preparing
to perform on December 1st.
9/15/2016 TR at 40 (emphasis added).
On September 29, 2016, Level 3 filed an Amended Complaint. ECF No. 43.
On November 9, 2016, the court’s law clerk sent an e-mail to the parties to inquire whether
Verizon still intended to commence performance on December 1, 2016. ECF No. 52.
On
November 10, 2016, the Government responded that: “Verizon was able to complete the circuit
ahead of schedule and the Government accepted the circuit and began using the circuit on
November 1, 2016.” ECF No. 52.
On November 14, 2016, the court convened a hearing to confirm the current status of the
contract. ECF No. 48 (“11/14/16 TR”). During the hearing the Government represented that DISA
had accepted a complete circuit from Verizon on November 1, 2016. 11/14/16 TR at 4. The
Government confirmed that it failed to inform either the court or Level 3 that performance
commenced prior to December 1, 2016. 11/14/16 TR at 9.
In response, on that same day, the court issued a Memorandum Opinion And Temporary
Restraining Order, prohibiting DISA from allowing Verizon to continue performing under the
contract. See Level 3 Communications, LLC v. United States, No. 16-829, 2016 WL 6694969, at
*3 (Fed. Cl. Nov. 14, 2016).
On November 18, 2016, the Government filed a sealed status report to update the court
about the work that Verizon performed to date and the amount that has been paid or is due to
Verizon. ECF No. 50. In an attached declaration, the CO stated that Verizon began the
“provisioning process to install the circuit per the contract,” on June 29, 2016, after GAO issued
its ruling, and that Verizon completed work on the circuit on November 1, 2016. ECF No 50-1 at
¶¶ 5–6. In addition, the CO stated that, under Verizon’s offer, the set up process carried a $ […]
“non-recurring cost,” that would be billed to DISA. ECF No. 50-1 at ¶ 13. Since DISA accepted
the circuit on November 1, 2016, the court was informed that Verizon apparently was also owed
$ […] for one month of service. ECF No 50-1 at ¶ 13.
On November 21, 2016 the Government submitted an additional status report, confirming
that contract “performance” commenced on June 29, 2016. ECF No. 51 at 7.
(sections deleted)
On or before January 3, 2017, the Government is advised to show cause why the
Government’s written and oral representations to the court that performance of the contract with Verizon would not commence until December 1, 2016 does not violate RCFC 11(b).
In addition, the court hereby orders the Defense Information Systems Agency promptly to
provide all pleadings, the Administrative Record, and all Memorandum Opinion and Orders in this
case to the Inspector General of the Department of Defense for investigation into why the
Contracting Officer awarded the contract at issue to Verizon at a price of $38.6
million more than the incumbent contractor and proceeded to
commence performance contrary to written and oral
representations to the court – and prior to the November 8, 2016
election.
In that regard, the court
also intends to forward the public record in this case to the
Senate Armed Services Committee for such oversight as it deems
appropriate.
Level 3
Communications, LLC v. U. S. and Verizon Deutschland GmbH,
No. 16-829 December 5, 2016
The court has concluded that Ms. Nero and Ms. Thomas acted in bad faith when they
prepared a Determination and Findings document, and subsequently included that document in
the supplemental administrative record, with the knowledge that the document was backdated
and contained inaccurate information, and with the further knowledge that the supplemental
administrative record would be used in proceedings in the Court of Federal Claims. The court
has also concluded that Ms. Thomas acted in bad faith by representing in her certification of the
supplemental administrative record that she carefully reviewed the record and that the record
constituted the record of the actions taken by the EPA that were relevant to plaintiff’s protest,
because she acknowledged that she did not review the record and because the record contained
an inaccurate, backdated document.
The bad faith conduct of Ms. Nero and Ms. Thomas caused plaintiff’s counsel, defense
counsel, and the court to question the integrity of the administrative record compiled by the EPA.
Given that one document was created ten months after the fact for the purposes of litigation,
could it be that other documents were similarly created for the purposes of litigation? Does the
false certification of one part of the administrative record call into question the authenticity of the
certification of the rest of the administrative record? The resulting investigation into these
questions, and the subsequent efforts to address and resolve the issues raised by that investigation, required the expenditure of significant resources–both time and money–by counsel
and the court. These were resources that could have been devoted to addressing the merits of the
protest or devoted to work on matters unrelated to this protest. In sum, there is no question that
the actions of Ms. Nero and Ms. Thomas had significant adverse consequences in this protest.
As previously stated, RCFC 11(c)(4) provides that sanctions are meant to deter future
misconduct. Deterrence is particularly important in this case due to the presumption that federal
government contracting officials perform their duties in good faith. See Am-Pro Protective
Agency, Inc. v. United States, 281 F.3d 1234, 1239 (Fed. Cir. 2002) (holding that a contractor
was unable to “overcome the strong presumption that government contract officials exercise their
duties in good faith”); accord U.S. Postal Serv. v. Gregory, 534 U.S. 1, 10 (2001) (noting that “a
presumption of regularity attaches to the actions of Government agencies”); Schism v. United
States, 316 F.3d 1259, 1302 (Fed. Cir. 2002) (en banc) (“This presumption of regularity is the
supposition that public officers perform their duties correctly, fairly, in good faith, and in
accordance with law and governing regulations, and is valid and binding unless ‘well-nigh
irrefragable proof rebuts or overcomes it.’” (citation omitted) (quoting Alaska Airlines, Inc. v.
Johnson, 8 F.3d 791, 795 (Fed. Cir. 1993))). That presumption is overcome when contracting
officials take actions similar to those taken by Ms. Nero and Ms. Thomas in this case, i.e.,
preparing a backdated, inaccurate document; including that document in the supplemental
administrative record; and then certifying the integrity of the record. One of the court’s goals in
sanctioning the bad faith conduct of the contracting officer and her supervisor in this case is to
deter further similar misconduct by contracting officials.
Based on the severity of Ms. Nero’s and Ms. Thomas’s misconduct, the court concludes
that under RCFC 11(c)(4), the EPA should reimburse plaintiff for the reasonable attorney’s fees
and expenses it incurred to address that conduct, beginning on March 6, 2014, the date that Mr.
Wolak advised plaintiff’s counsel that there might be an issue with the Determination and
Findings document, and ending on June 12, 2014, the date that plaintiff filed its brief regarding
the court’s inherent power to impose sanctions.11 In addition, due to the resources expended by
the court in addressing the issues raised by the inaccurate, backdated document and false
certification that defendant filed with the court, the court concludes that, as permitted by RCFC
11(c)(4), the EPA should pay a monetary penalty to the court of $1,000. These sanctions are the
least severe sanctions that would deter further similar misconduct by Ms. Nero, Ms. Thomas,
other EPA personnel, and other contracting officials. (Coastal Environmental Group, Inc. v. U. S., No. 13-71C, August 25,
2014) (pdf).
This case is before the Court on a Motion by bid
protest Intervenor Rowe Contracting Services, Inc. (“Rowe”) for Rule 11 sanctions against the Plaintiff,
The Ravens Group, Inc. (“Ravens”), and its attorney, . . . .
(Sections deleted)
III. Discussion
Rowe’s Motion presents two justifications for
sanctioning Ravens. It charges Ravens with making unverified and baseless accusations of improper conduct
against Rowe and its President, Scott Rowe. The Motion also asserts that many of Ravens’
legal arguments were so deficient as to be frivolous and thus subject to Rule 11
sanctions.
A. The Rule 11 Legal Standard
Rule 11 of the Rules of the United States Court of Federal Claims (“RCFC”) is
patterned after Rule 11 of the Federal Rules of Civil Procedure. Judin v. United
States, 110 F.3d 780, 784 (Fed. Cir. 1997). The Federal Circuit has held that its
rulings under Rule 11 of the Federal Rules are applicable to RCFC 11. Id. The Rule requires
that every pleading filed by a party be signed by the party’s attorney. RCFC 11(a)
(“Every pleading, motion, and other paper shall be signed by or for the attorney of
record in the signing attorney’s own individual name . . . . ”). The attorney’s signature acts
as a certification that the pleading is well-grounded in fact, has a basis in law,
and is not filed for an improper purpose. View Eng'g, Inc. v. Robotic Vision Sys., 208 F.3d 981,
984 (Fed. Cir. 2000); see also RCFC 11(b).
Rule 11 is aimed at curbing baseless filings by parties that burden the courts
and cause needless expense and delay. See Cooter & Gell v. Hartmarx Corp., 496 U.S.
384, 397-98 (1990). The Advisory Committee Notes to the 1993 amendments to the
Rule are instructive on this point: “The [R]ule [] require[s] litigants to ‘stop
and think’
before initially making legal or factual contentions.” Fed. R. Civ. P. 11 (Notes
of Advisory Committee on 1993 Amendments). The Rule therefore requires that parties
make a reasonable inquiry of the applicable law and underlying facts to ensure
that claims brought before the court are not frivolous. Persyn v. United States, 35
Fed. Cl. 708, 712 (1996). The reasonableness of a party’s pre-filing inquiry is measured
by an objective standard. See id. A party’s good faith belief in the merits of
an argument is not sufficient to avoid sanction. See Bus. Guides, Inc. v. Chromatic Commc’ns.
Enters., Inc., 498 U.S. 533, 548-49 (1991).
Rule 11 authorizes the court to sanction an attorney for failure to comply with
its requirements. Fed. R. Civ. P. 11(c); RCFC 11(c). The court may sanction the
attorney to the extent sufficient to deter the repetition of such conduct. Fed. R. Civ.
P. 11(c)(2); RCFC 11(c)(2). The sanction may consist of, or include, nonmonetary directives,
an order to pay a penalty to the court, or an order directing payment to the movant
of reasonable attorneys’ fees and other expenses incurred as a direct result of the
Rule 11 violation. Fed. R. Civ. P. 11(c)(2); RCFC 11(c)(2).
Count II
We believe that this language provides a legal basis for the argument set forth
in
Ravens’ Complaint. Although Ravens’ interpretation of this FAR clause may be
strained, Rule 11 does not require that the legal contentions set forth in a
pleading are
correct, only that they have some basis in existing law. See Saladino v. United
States,
63 Fed. Cl. 754, 757 (2005) (“A legal argument that ultimately is incorrect . .
. does not
necessarily equate to one that is not warranted by existing law or by a
‘nonfrivolous
argument for its extension.’”) (quoting RCFC 11(b)(2)).
We further note that Ravens’ attorney dropped this contention at oral argument.
Rather than insist that exercise of the options was the functional equivalent of
a “best
value” contract award, Ravens’ attorney argued instead that his client relied on
exercise
of the options as evidence that award of the contract was no longer in
contention. See
Opinion at 11. We ultimately dismissed Count II for failure to state a claim
upon which
relief could be granted because Ravens’ attorney was unable to demonstrate how
this
alleged “reliance” altered his client’s circumstances or what prejudice it
suffered. Id. (p. 16)
Count IV
We rejected Ravens’ argument as not being persuasive. Opinion at 12.
However, the fact that Ravens’ claim was dismissed on the merits does not mean
sanctions are warranted. See Fed. R. Civ. P. 11 (Notes of Advisory Committee on
1993 Amendments) (“The certification is that there is (or likely will be)
‘evidentiary
support’ for the allegation, not that the party will prevail with respect to its
contention
regarding the fact . . . . [The rendering of] summary judgment . . . against a
party does
not necessarily mean . . . that [the party] had no evidentiary support for its
position.”).
As set forth in the Complaint, Count IV was poorly crafted and based on weak
facts, but
was not frivolous. Cf. Saladino, 63 Fed. Cl. at 757-58 (finding that the theory
presented
by the plaintiff was frivolous and “wholly without merit” because the theory had
been
discredited when another judge of the Court of Federal Claims ruled against the
plaintiff
in a separate, previously filed case and because binding precedent applicable to
his
claims had warned litigants that “pressing such claims would be sanctionable”).
(p. 18)
We decline to impose sanctions on Ravens or its attorney. In doing so, we do not
express our approval of Ravens’ performance in this Court. To the contrary, we
note our
frustration with Ravens’ inability to present its arguments logically. In the
future, this
Court will not tolerate the presentation of claims by Ravens or its attorney
that are clearly
outside the Court’s jurisdiction or which lack a firm factual or legal basis.
(The Ravens Group, Inc., v. U. S. and Rowe
Contracting Services, Inc., No. 07-243C, Filed October 31, 2007) (pdf) |
|
U.
S. Court of Federal Claims - Listing of Decisions |
For
the Government |
For
the Protester |
The Ravens Group, Inc., v. U. S. and Rowe Contracting
Services, Inc., No. 07-243C, Filed October 31, 2007 (pdf) |
Gallup, Inc. v. U. S., No.
16-1656C, April 25, 2017 |
|
Level 3
Communications, LLC v. U. S. and Verizon Deutschland GmbH,
No. 16-829, March 16, 2017 |
|
Level 3 Communications, LLC v. U. S.
and Verizon Deutschland GmbH, No. 16-829 December 5, 2016 |
|
Coastal Environmental Group, Inc. v. U. S., No. 13-71C, August 25,
2014 (pdf). |
U. S. Court of Appeals for the Federal Circuit - Key Excerpts |
New On appeal, the government contends, on behalf of itself
and Mr. Bigler, that the Court of Federal Claims
abused its discretion in using its inherent authority to
impose sanctions. The government argues that this is so
because the court did not make the required finding of
fraud or bad faith against either the government or Mr.
Bigler and because, in any event, there is no support in
the record for such a finding. The government also argues
that the court deprived both it and Mr. Bigler of due
process because the order to show cause stated that the
court was contemplating Rule 11 sanctions, but did not
mention the possible use of its inherent authority, and did
not mention that the imposition of sanctions was contemplated
against Mr. Bigler individually. See Corrected
Appellants Br. 14–16. For the following reasons, we hold
that the record in this case does not support the imposition
of sanctions. The Court of Federal Claims therefore
erred in sanctioning the government and Mr. Bigler. In view of our disposition of the case, it is not necessary for
us to address the government’s due process argument.
Central to the issue before us are the telephone status
conference held on August 1, 2016, the government’s filing
of August 23, 2016, and the hearing convened on September
15, 2016. As seen, on August 1, the parties explained
to the court that Verizon was working on Phase 1 of the
contract, doing what it had to do in order to be able to
begin performance of Phase 2 on December 1, 2016.
Thereafter, in its August 23 filing, the government represented
that Verizon’s circuit would not be operational
until December 1. And subsequently, at the September
15 hearing, the focus of the court’s discussion with Mr.
Bigler was on the question of what Verizon had been
doing since August 1. Mr. Bigler informed the court that
Verizon was “preparing to perform,” by which he meant
that Verizon was in the process of setting up the circuit
and testing it to make sure that it worked, so that Phase
2 contract performance could begin on December 1.
Thereafter, upon learning that Verizon had in fact
completed its Phase 1 work early and had commenced
Phase 2 performance on November 1 without notice from
the government to the court or Level 3, the court, on
November 14, expressed its displeasure with the government
and Mr. Bigler. It stated that it had been the
court’s “impression” at the conclusion of the proceedings
on September 15 that all that would happen until the
court decided the cross-motions was Verizon’s continuing
Phase 1 work. The court stated at the November 14
proceedings that, under these circumstances, it believed
that it had been misled by the government and Mr.
Bigler. The order to show cause followed. As seen, the
focus of the order to show cause was upon “the
[g]overnment’s written and oral representations that
performance of the contract with Verizon would not
commence until December 1.” App. 51.
The concern expressed by the court on November 14 is
understandable. The government should have informed
Level 3 and the court that Verizon had completed the
Phase 1 work early and that Phase 2 performance was
about to begin. Nevertheless, we do not believe that the
record reveals a sufficient basis for finding “the conscious
doing of wrong because of dishonest purpose or moral
obliquity” that is required in order to support the imposition
of sanctions under the court’s inherent authority.
We say this for several reasons. As to Phase 1 work,
Mr. Bigler, as well as Level 3 itself, expressly indicated,
correctly, that “performance” of that part of the contract
was in fact under way. As to Phase 2, Mr. Bigler did
make a representation—that Phase 2 would not begin
before December 1—that turned out in retrospect to be
incorrect. But nothing in the record suggests that, when
Mr. Bigler made the statements he did on August 1,
August 23, and September 15, he believed they were not
correct or he was attempting to deceive the court. And
there is no basis in the several colloquies with the court,
which were not entirely clear as to exactly what contract
“performance” was being discussed in particular passages,
for finding any clear agreement by the parties and the
court as to what was to happen if the time came for a
transition from Phase 1 to Phase 2. Moreover, the August
1 colloquy indicated agreement by the government and
Level 3 that, even if Phase 2 were to begin, Level 3 would
still anticipate a full 60 month service period were it to
win the bid protest and then be awarded the contract in
place of Verizon. In short, based upon the record before
us, we are unable to conclude that the government,
through Mr. Bigler, could be found to have knowingly and intentionally made
misrepresentations to the court as to when Phase 2 contract performance would
start or to have acted with a dishonest purpose or other bad faith in failing to
update the information on November 1.
CONCLUSION
For the foregoing reasons, the Sanctions Order is reversed.
(Level 3
Communications, LLC v. U. S. and Verizon Deutschland GmbH,
Robert C. Bigler, 2017-1924, 2017-2068, January 30, 2018)
|
|
U. S. Court of Appeals for the Federal Circuit - Listing of
Decisions |
For
the Government |
For
the Protester |
New
Level 3
Communications, LLC v. U. S. and Verizon Deutschland GmbH,
Robert C. Bigler, 2017-1924, 2017-2068, January 30,
2018 |
|
|
|
|
|