Defendant and Intervenor argue that
the Competition In Contracting Act (CICA) and the
Federal Acquisition Regulation (FAR) do not apply to this
transaction, and therefore the Air Force
cannot be found to have violated statute or regulation. The
legal issue of whether CICA and the
FAR apply is a thorny one, not necessary to the resolution of
this expedited case. The Court’s
authority to overturn agency action in the bid protest context
is not limited to violations of statute
or regulation. Rather, this Court may set aside a procurement
which lacks a rational basis or results
from a prejudicial violation of procurement procedure. Banknote,
365 F.3d at 1351. The agency’s
failure to follow the terms of its own Solicitation and
selection of an offeror based upon different
requirements than those imposed upon the only other offeror are
quintessential examples of conduct
which lacks a rational basis. See, e.g., LaBarge Prod., Inc. v.
West, 46 F.3d 1547, 1555 (Fed. Cir.
1995) (recognizing “the bastion of federal procurement policy
that all offerors must possess equal
knowledge of the same information in order to have a valid
procurement.”). The agency’s failure
to follow its own selection process embodied in the Solicitation
is also a prejudicial violation of a
procurement procedure established for the benefit of offerors.
Banknote, 365 F.3d at 1351.
This Court’s bid protest jurisdiction is no longer premised on
the theory of the breach of an
implied-in-fact contract. Nonetheless, it has long been held and
is still recognized that the issuanceof a competitive
solicitation which generates responsive offers gives rise to an
implied contract of
fair dealing. Heyer Prods. Co. v. United States, 140 F. Supp.
409, 412 (Ct. Cl. 1956) (“It was an
implied condition of the request for offers that each of them
would be honestly considered, and that
that offer which in the honest opinion of the contracting
officer was most advantageous to the
Government would be accepted. No person would have bid at all if
he had known that ‘the cards
were stacked against him.’”). As the Federal Circuit recognized,
“[t]he government is said to breach
the implied contract if its consideration of offers is found to
be arbitrary and capricious toward the
bidder-claimant.” Southfork Sys., Inc. v. United States, 141
F.3d 1124, 1132 (Fed. Cir. 1998),
(citation omitted). Thus, the Government’s issuance of a
Solicitation and offerors’ submission of
responsive offers created an implied-in-fact contract requiring
fair dealing on the part of the
Government. Moreover, the Solicitation expressly provided that
the Air Force would use “fair”
procedures for the evaluation and selection. AR 6. As such, the
Court has a legal basis to sustain this
protest independent of any statutory or regulatory violations,
so the applicability of CICA and the
FAR is immaterial.
The onerous six-month limitation term, which Actus termed a
“deal breaker,” was eliminated
for Actus by the settlement of Actus’ agency protest, but Hunt
continued to be saddled with it. The
relaxation of this provision would have decreased the risk to
the lender. As a result, Plaintiff and
Actus submitted FPRs based on fundamentally different
assessments of the risk inherent in the
Project. As Hunt’s lender testified, increasing a lender’s risk
exposure had a direct consequence to
a borrower - the risk is passed on to the borrower in the form
of an increase in the financing costs,
either through a higher interest rate or because of the
requirement that credit enhancement, such as
a guarantee, be obtained. Ray Decl. ¶ 12. Risk was an evaluation
consideration. The Solicitation
stated that the standard required for financial proposals would
be met when “[t]he Offeror’s proposal
shows that the financial risk (e.g., default, interest rate,
etc.) to the Project is reasonable. The lower
the risk the more favorable this factor will be evaluated.” AR
86. The pre-selection change to
Condition 23 of the Lease meant that the risk for Plaintiff was
greater than that for Intervenor,
making it impossible for the SSET to apply that evaluation
factor fairly. (Hunt Building Company
Ltd., v. U. S. and Actus Lend Lease, LLC, No. 04-505C, July
21, 2004) (pdf) |