New
The protester argues that there was a
clear error on the face of its quotation, and the
contracting officer abused her discretion by not allowing
NDP to correct the mistake. Protest at 1, 4. NDP argues
that, as corrected, its quotation would be the
lowest-priced, technically acceptable quotation, with a
total price of $5,153,229, an amount that is $54,463 less
than Cardinal Health's price, and therefore it should
receive the contract award. Id. Specifically, NDP argues
that the contracting officer should have recognized that
it had erroneously multiplied its intended CLIN 0002 price
for the F18-FDG bulk dose by six (patients/day), further
compounded its mistake by multiplying that price by 1,560
(the quantity), and then multiplying that price by three
(the three-year performance period), thereby incorrectly
inflating its price by $2,274,480. Id. at 3. NDP argues
that the agency should have known there was an error in
the quotation based on the large gap between its price and
Cardinal Health's price, and further reviewed NDP's
quotation to discover that its proposed unit price for
CLIN 0002 was intended to be the same as its proposed unit
price for CLIN 0001. Id.
The agency argues that it was not clear on the face of
NDP's quotation that there was any mistake in its price.
Memorandum of Law (MOL) at 3-5. In the agency's view, NDP
made a complex math error, and therefore the agency was
not obligated to provide NDP an opportunity to clarify its
quotation before award. COS at 2. The agency also argues
that the price difference between NDP, a small business,
and the two other large businesses that submitted
quotations was not large enough to indicate that there was
an error in NDP's quotation. Id. The agency further argues
that the contracting officer had no reason to know there
was a mistake in NDP's proposal because NDP's CLIN 0002
price in response to the RFQ was the same as the CLIN 0002
price NDP submitted in response to the original
solicitation. Id.
As a preliminary matter, where, as here, simplified
acquisition procedures are used, the evaluation procedures
provided for in FAR parts 14 and 15, including the
procedures for the correction of mistakes, are not
mandatory. See FAR § 13.106-2(b); Paraclete Contracts,
B-299883, Sept. 11, 2007, 2007 CPD ¶ 153 at 4. In an
appropriate case, an agency may allow an offeror to
correct a clerical error in a cost or price proposal
through clarifications, as opposed to discussions. Joint
Venture Penauillie Italia S.p.A. et al., B-298865,
B-298865.2, Jan. 3, 2007, 2007 CPD ¶ 7 at 8; see FAR §
15.306(a)(3). However, both the existence of an error and
the intended pricing must be apparent from the face of the
proposal. Battelle Mem'l Inst., B-299533, May 14, 2007,
2007 CPD ¶ 94 at 3; CIGNA Gov't Servs., LLC, B-297915.2,
May 4, 2006, 2006 CPD ¶ 74 at 9.
Here, we agree with the agency that it was not obvious
from the face of NDP's quotation that there was a clerical
mistake that the agency could have allowed NDP to fix with
clarifications. The solicitation required that vendors
provide the pricing for a bulk dose of F18-FDG. The
solicitation explained that the bulk dose was for 6
patients a day, 5 days a week, for 52 weeks a year, which
equals 1,560; 1,560 is the quantity set forth in CLIN
0002. It would not be obvious to the contracting officer,
therefore, that NDP had erroneously multiplied its
intended CLIN 0002 price for the F18-FDG bulk dose by 6
(patients/day) and then multiplied that amount by 1,560
(the quantity).
Moreover, even if the contracting officer had found NDP's
CLIN 0002 price to be so high as to conclude there was a
mistake in the proposal, NDP's intended pricing is not
apparent on the face of the proposal. In this regard, NDP
does not explain why the contracting officer should have
known that NDP intended to propose the same price for a
bulk dose of F18-FDG as a unit dose of F18-FDG. Finally,
as noted, NDP had two opportunities to submit a quotation
in response to the agency's requirement, and twice
submitted a quotation that contained an error. We see no
reason to hold the contracting officer accountable for not
identifying a mistake in the protester's quotation when
the protester itself did not identify the mistake until
after contract award.
Since NDP's intended price for CLIN 0002 was not apparent
from the face of its quotation, correction of the mistake
through clarifications would not have been proper. On this
record, we find the agency's award of the contract to
Cardinal Health reasonable.
The protest is denied. (Nuclear
Diagnostic Products B-416227: Jul 12, 2018)
As noted above, this procurement was
conducted under the simplified procedures for evaluation
of commercial items. Simplified acquisition procedures are
designed, among other things, to reduce administrative
expenses, promote efficiency and economy in contracting,
and avoid unnecessary burdens for agencies and
contractors. FAR § 13.002; 41 U.S.C. § 3305. When using
these procedures, an agency must conduct the procurement
consistent with a concern for fair and equitable
competition and must evaluate proposals in accordance with
the terms of the solicitation. ERIE Strayer Co., B-406131,
Feb. 21, 2012, 2012 CPD ¶ 101 at 4.
Our Office reviews allegations of improper agency actions
in conducting simplified acquisitions to ensure that the
procurements are conducted consistent with a concern for
fair and equitable competition and with the terms of the
solicitation. ERIE Strayer Co., supra; Russell Enters. of
N. Carolina, Inc., B‑292320, July 17, 2003, 2003 CPD ¶ 134
at 3. Although an agency is not required to conduct
discussions under simplified acquisition procedures, where
an agency avails itself of negotiated procurement
procedures, the agency should fairly and reasonably treat
offerors in the conduct of those procedures. ERIE Strayer
Co., supra, at 4.
In this regard, FAR § 15.306 describes a range of
exchanges that may take place when the agency decides to
conduct exchanges with offerors during negotiated
procurements. Clarifications are “limited exchanges”
between an agency and an offeror for the purpose of
eliminating minor uncertainties or irregularities in a
proposal, and do not give an offeror the opportunity to
revise or modify its proposal. FAR § 15.306(a)(2);
American Material Handling, Inc., B-410899, March 12,
2015, 2015 CPD ¶ 106 at 8; ERIE Strayer Co., supra.
Clarifications are not to be used to cure proposal
deficiencies or material omissions, or materially alter
the technical or cost elements of the proposal, or
otherwise revise the proposal. American Material Handling,
Inc., supra; see eMind, B‑289902, May 8, 2002, 2002 CPD ¶
82 at 5. Discussions, on the other hand, occur when an
agency communicates with an offeror for the purpose of
obtaining information essential to determine the
acceptability of a proposal, or provides the offeror with
an opportunity to revise or modify its proposal in some
material respect. Alliant Enter. JV, LLC, B-410352.4, Feb.
25, 2015, 2015 CPD ¶ 82 at 5; see FAR § 15.306(d). As a
general matter, when an agency conducts discussions with
one offeror, it must afford all offerors remaining in the
competition an opportunity to engage in meaningful
discussions. See ERIE Strayer Co., supra; Strategic
Analysis, Inc., B‑292392, B‑292392.2, Sept. 3, 2003, 2003
CPD ¶ 156 at 4. Further, it is the actions of the parties
that determines whether discussions have been held and not
merely the characterization of the communications by the
agency. Priority One Servs., Inc., B‑288836, B‑288836.2,
Dec. 17, 2001, 2002 CPD ¶ 79 at 5.
The Air Force asserts that its communications with the
Mahto were clarifications, not discussions. AR at 5. We
disagree. Mahto was permitted to revise portions of its
quotation that did not comply with the solicitation’s
terms. In this regard, the RFQ did not include any
provision for progress payments, and instead incorporated
FAR § 52.212-4, which provides that: “Payment shall be
made for items accepted by the Government that have been
delivered to the delivery destinations set forth in this
contract.” FAR § 52.212-4(i); RFQ at 3. Mahto’s quotation,
however, instead quoted a schedule of payments under which
payments would be made in four installments at various
contract milestones, [deleted]. AR, Tab 8, Mahto
Quotation, at 16. When the agency communicated with Mahto
about this discrepancy, Mahto altered its quotation,
dropping the requirement for progress payments, and
instead agreed to accept the agency’s proposed “Net 30”
payment terms. AR, Tab 10, Email Exchange Between Mahto
and Agency, at 1.
In addition, although the RFQ required vendors to propose
a fixed price for 16 days of training, setup, and support
on Wake Island, CLIN 0002, RFQ at 8, Mahto’s quotation
stated that the costs associated with its technicians’
work on Wake Island would be “billed separately” on a per
diem basis. AR, Tab 8, Mahto Quotation, at 16. Where, as
here, a solicitation requests proposals on a fixed-price
basis, a price offer that is conditional and not firm
cannot be considered for award. See SunEdison, LLC,
B-298583, B-298583.2, Oct. 30, 2006, 2006 CPD ¶ 168 at 5.
Thus, Mahto’s statement that the costs of transporting
technicians to and from the jobsite would be billed
separately failed to comply with the RFQ’s requirement
that vendors quote fixed prices for that work.
The agency’s communications with the awardee invited a
response from Mahto that was necessary to determine the
acceptability of Mahto’s quotation and, in fact, resulted
in Mahto being permitted to supplement or alter its
quotation. This is quintessentially the nature of
discussions, not clarifications. Kardex Remstar, LLC,
B-409030, Jan. 17, 2014, 2014 CPD ¶ 1 at 4. Accordingly,
we conclude that the Air Force, having conducted
discussions with Mahto, was required to also conduct
discussions with all other vendors in the competition,
including IWI. We sustain the protest on that basis.
(International Waste Industries
B-411338: Jul 7, 2015.) (pdf)
The RFQ was issued by the Army
Expeditionary Contracting Command in Grafenwoehr, Germany
on March 3, 2014, using commercial item and simplified
acquisition procedures contained in Federal Acquisition
Regulation (FAR) parts 12 (commercial items) and 13
(simplified acquisition procedures). Agency Report at 2.
Quotations were due on March 26. The solicitation provided
that quotations could be submitted via facsimile
transmission, hand delivery, or e-mail to the contracting
specialist identified in the solicitation. RFQ at 3.
Latvian protests that the agency has not established a
restricted access electronic bid box in accordance with
Federal Acquisition Regulation (FAR) § 14.401 to receive
bids.
FAR §14.401 requires all bids received before the time set
for bid opening remain in a locked bid box, a safe, or in
a secured, restricted-access electronic bid box. This
provision of the FAR, however, is applicable to
procurements being conducted using FAR part 14 sealed bid
procedures. FAR §14.000. Here, the Army is not conducting
the procurement using FAR part 14 sealed bid procedures to
solicit bids. Rather, the Army is soliciting quotations
using FAR parts 12, and 13. Accordingly, the Army is not
required to establish a bid box.
Latvian has not provided any information which
demonstrates or suggests that the agency is prohibited
from accepting quotations submitted in response to a
procurement conducted under FAR parts 12 and 13 by fax,
hand delivery, or e-mail to the address of a specified
contract specialist. Further, to the extent that Latvian
believes the quotations are not being property secured the
Army notes that only the contracting specialist has access
to his e-mail box, which is secured using a common access
card, the fax machines are in a secure, locked building,
and visitors must be escorted within the building. AR at
3. Accordingly, there is no basis here to find that the
agency is improperly accepting quotations, or failing to
secure them. (Latvian
Connection General Trading and Construction, LLC,
B-409569: May 8, 2014) (pdf)
In its protest, B&S asserts that it timely verified the
information in its quote via email. Protest at 2. In support of
its assertion, the protester submitted an email chain that
includes a message, allegedly sent at 2:54 p.m. (EST) on
September 24, from B&S’s president to the Army contract
specialist in which B&S verifies the requested information about
the firm’s quote. Protest, attach. 1, Email Correspondence, at
3-4.
When using simplified acquisition procedures, agencies must
promote competition “to the maximum extent practicable.” 10
U.S.C. § 2304(g)(3) (2012). In meeting this requirement,
agencies must make reasonable efforts, consistent with
efficiency and economy, to afford all eligible and interested
vendors an opportunity to compete. S.D.M. Supply, Inc.,
B-271492, June 26, 1996, 96-1 CPD ¶ 288 at 4. Agencies have a
fundamental obligation to have procedures in place not only to
receive quotations, but also to reasonably safeguard quotations
received and to give them fair consideration. Id. However, as a
practical matter, even with appropriate procedures in place, an
agency may lose or misplace a bid or quotation, and the
occasional loss of a bid or quotation--even if through the
negligence of the agency--generally does not entitle the bidder
or vendor to relief. Id.; Interstate Diesel Serv., Inc.,
B-244842.2, Sept. 27, 1991, 91-2 CPD ¶ 304 at 2. Indeed, we have
found an agency’s rejection of a quote to be reasonable where a
protester emailed its quote to the agency, but the record showed
that the agency never actually received the emailed submission
prior to the deadline. See Turner Consulting Group, Inc.,
B-400421, Oct. 29, 2008, 2008 CPD ¶ 198 at 4.
The circumstances here do not provide a basis to sustain the
protest. In this regard, the agency contends that it never
received any email verification from B&S, and, consequently, it
considered the quote to have been withdrawn. AR at 6. The record
shows that the agency’s information technology (IT) staff
conducted an email trace of all email messages the agency
received from B&S’s president on September 24. Agency Memorandum
for the Record at 1-2. The results of the agency’s search
confirm that the Army never received the email B&S contends its
president sent to the contract specialist. Id., attach. 6, Email
from IT Staff to Contract Specialist, at 1.
Although the protester has presented evidence that it timely
sent an email verifying information about its quote, there is no
question that the agency did not receive B&S’s email
verification prior to the contract specialist’s deadline.
Moreover, the agency sent the protester multiple emails seeking
a response, and the agency advised the protester in writing and
on the telephone that the agency would consider B&S to have
withdrawn its quote if it failed to provide written answers to
the agency’s questions. Additionally, the record does not show
that B&S took any steps to confirm that its email message was
received.
In short, given that there is no evidence in the record to show
actual timely receipt of B&S’s verification email, we have no
basis to find unreasonable the agency’s decision not to award a
contract to B&S.[3] See Turner Consulting Group, Inc., supra, at
4; Int’l Garment Processors, B-299674, B-299743, B-299746, July
17, 2007, 2007 CPD ¶ 130 at 7 (agency’s rejection of revised
quote was reasonable where protester only demonstrated that
quote was transmitted, but not that it was actually timely
received by the agency); see also Lakeshore Eng’g Serv.,
B-401434, July 24, 2009, 2009 CPD ¶ 155 at 4 (elimination from
competitive range found reasonable where protester did not show
that its proposal was successfully delivered to agency’s email
box prior to submission deadline); Am. Material Handling, Inc.,
B-281556, Feb. 24, 1999, 99-1 CPD ¶ 46 at 3-4 (agency not
required to consider vendor’s quote where agency lost quote due
to agency computer malfunction). (B&S
Transport, Inc., B-407589, Dec 27, 2012) (pdf)
As noted above,
the procurement was conducted under the simplified procedures
for evaluation of commercial items. Simplified acquisition
procedures are designed, among other things, to reduce
administrative expenses, promote efficiency and economy in
contracting, and avoid unnecessary burdens for agencies and
contractors. FAR § 13.002; 41 U.S.C. § 3305 (Supp. IV 2010).
When using these procedures, an agency must conduct the
procurement consistent with a concern for fair and equitable
competition and must evaluate proposals in accordance with the
terms of the solicitation.
Our Office reviews allegations of improper agency actions in
conducting simplified acquisitions to ensure that the
procurements are conducted consistent with a concern for fair
and equitable competition and with the terms of the
solicitation. Russell Enters. of N. Carolina, Inc., B-292320,
July 17, 2003, 2003 CPD ¶ 134 at 3. Although an agency is not
required to conduct discussions under simplified acquisition
procedures, where an agency avails itself of negotiated
procurement procedures, the agency should fairly and reasonably
treat offerors in the conduct of those procedures. See Kathryn
Huddleston and Assocs., Ltd., B-289453, Mar. 11, 2002, 2002 CPD
¶ 57 at 6; Finlen Complex, Inc., B-288280, Oct. 10, 2001, 2001
CPD ¶ 167 at 8-10.
In this regard, FAR § 15.306 describes a range of exchanges that
may take place when the agency decides to conduct exchanges with
offerors during negotiated procurements. Clarifications are
“limited exchanges” between an agency and an offeror for the
purpose of eliminating minor uncertainties or irregularities in
a proposal, and do not give an offeror the opportunity to revise
or modify its proposal. FAR § 15.306(a)(2); Lockheed Martin
Simulation, Training & Support, B-292836.8 et al., Nov. 24,
2004, 2005 CPD ¶ 27 at 8. Clarifications are not to be used to
cure proposal deficiencies or material omissions, or materially
alter the technical or cost elements of the proposal, or
otherwise revise the proposal. eMind, B-289902, May 8, 2002,
2002 CPD ¶ 82 at 5. Discussions, on the other hand, occur when
an agency communicates with an offeror for the purpose of
obtaining information essential to determine the acceptability
of a proposal, or provides the offeror with an opportunity to
revise or modify its proposal in some material respect. Gulf
Copper Ship Repair, Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶
108 at 6; see FAR § 15.306(d). When an agency conducts
discussions with one offeror, it must conduct discussions with
all other offerors in the competitive range. Gulf Copper Ship
Repair, Inc., supra.
Ultimately, it is the actions of the parties that determine
whether discussions have been held and not the characterization
of the communications by the agency. Id. In situations where
there is a dispute regarding whether communications between an
agency and an offeror constituted discussions, the acid test is
whether an offeror has been afforded an opportunity to revise or
modify its proposal. Id. Communications that do not permit an
offeror to revise or modify its proposal, but rather request
that the offeror confirm what the offeror has already committed
to do in its proposal, are clarifications and not discussions.
Environmental Quality Mgmt., Inc., B-402247.2, Mar. 9, 2010,
2010 CPD ¶ 75 at 7.
As explained below, we disagree with the agency that its
exchange with the awardee involved only clarifications. Prior to
the exchange, the agency viewed the proposal as unacceptable;
after the exchange, the rating was changed to acceptable.
(Note:
The following section that is within
red brackets was taken from the background
section and placed in the discussion section of this
decision because it helps to understand the decision
without referring to the actual decision).
[The contract specialist
conducted what the agency characterized as verbal “clarification[s]”
with RexCon regarding how such “discrepancies” were accounted
for within the proposal submitted. Contract Specialist
Memorandum for Record, July 21, 2011. Following that telephone
call, the agency submitted written questions to RexCon, to
which RexCon replied in writing. Following are those questions
and answers memorializing that verbal exchange:
1. Can the Generator that you proposed run the entire plant
without having to add any additional power?
Yes. Per the proposal, we’ve done an extensive power study
showing the power load of the plant and all equipment. The
power load is 400 [kilowatts (KW)], the proposed generator is
455KW, providing ~12% safety factor.
2. Does your company provide 24 hour 7 days a week
technical support?
Yes. We have field techs on call. Included as well are free
upgrades for a year and 2 free attendees at our annual RC3
training school.
3. Is the moisture compensation you proposed automatic?
Yes. Per page 7 of our proposal: “Includes Automatic computer
batching capability and automatic moisture compensation with a
slump meter readout.”
4. Did you provide safe ladders and/or stairs to access the
requested parts of the plant?
Yes. Per [agency] specifications, Personnel Access to all
plant components (safety Ladders) are included. Access Ladders
will be provided to all plant components as specified.]
In our view, RexCon’s
answers to questions two and four resulted in material revisions
to its proposal. Specifically, the second question concerned the
solicitation’s requirement for a 24 hour a day, 7 day a week
technical hotline direct from the manufacturer for plant
troubleshooting. The agency asked if RexCon provided such
technical support and RexCon replied, “Yes. We have field techs
on call.” Email from RexCon to Agency, July 21, 2011. Through
this exchange, the awardee was permitted to augment its proposal
to address a clear omission regarding a material solicitation
requirement. In response to the fourth question, which concerned
the solicitation requirement for stairs or ladders to access the
plant, the awardee responded that access ladders to all plant
components will be provided. While the agency asserts that it
intended to require personnel access to the entire concrete
plant, the RFQ specified, as noted above, that access must be
provided to only two discrete portions of the plant. The
awardee’s response to the agency’s question references no
portion of RexCon’s proposal, and there is no evidence in the
record that the awardee’s proposal previously met the access
requirement. Because the agency effectively conducted
discussions with RexCon, the Air Force was required to afford
ERIE with an opportunity to address the agency’s concerns with
its proposal through discussions, as well. Gulf Port Ship
Repair, Inc., supra.
Where improper discussions were held, we will resolve any doubts
concerning the prejudicial effect of the agency’s actions in
favor of the protester; a reasonable possibility of prejudice is
a sufficient basis for sustaining the protest. See Ashland Sales
& Serv., Inc., B-255159, Feb. 14, 1994, 94-1 CPD ¶ 108. In other
words, once an impropriety in the conduct of discussions is
found, it must be clear from the record that the protester was
not prejudiced in order to deny the protest. Id.
In brief, on this record, we see a reasonable possibility of
prejudice to the protester. The protester’s proposal was found
unacceptable on four grounds. Two grounds--failure to provide a
generator of sufficient capacity for continuous operation of the
concrete plant and failure to provide plant-wide personnel
access--were issues that the awardee was permitted to address
through discussions. Additionally, the protester omitted from
its proposal a key performance specification, namely, plant
capacity. The record contains the protester’s unrebutted
assertion that, if it were provided the opportunity for
clarifications, its proposal could be amended to accurately
state that its offered plant meets that required performance.
Finally, the protester’s proposal was rated unacceptable for
offering an operating system other than Windows. There is a
reasonable possibility that, with the conduct of discussions,
the protester could satisfy this requirement, as well. (ERIE
Strayer Company, B-406131, Feb 21, 2012) (pdf)
Resource
complains that the agency unreasonably evaluated its technical
quotation because the agency's assigned weaknesses in support of
its determination that Resource's quotation was technically
unacceptable were, in fact, adequately addressed in Resource's
presentation.
Simplified acquisition procedures are designed to, among other
things, reduce administrative costs, promote efficiency and
economy in contracting, and avoid unnecessary burdens for
agencies and contractors. FAR sect. 13.002; Sawtooth Enters.,
Inc., B-281218, Dec. 7, 1998, 98-2 CPD para. 139 at 3. When
using simplified acquisition procedures, an agency must conduct
the procurement consistent with a concern for fair and equitable
competition and must evaluate quotations in accordance with the
terms of the solicitation. In reviewing protests of an allegedly
improper simplified acquisition evaluation, we examine the
record to determine whether the agency met this standard and
executed its discretion reasonably. Computers Universal, Inc.,
B‑297552, Feb. 14, 2006, 2006 CPD para. 42 at 4-5; DOER Marine,
B-295087, Dec. 21, 2004, 2004 CPD para. 252 at 3. Moreover, even
for procurements under simplified acquisition procedures, it is
a fundamental principle of government accountability that an
agency be able to produce a sufficient record to allow for a
meaningful review where its procurement actions are challenged.
See e-LYNXX Corp., B-292761, Dec. 3, 2003, 2003 CPD para. 219 at
8; Checchi and Co. Consulting, Inc., B-285777, Oct. 10, 2001,
2001 CPD para. 132 at 6. In this regard, where an agency fails
to adequately document its actions, it bears the risk that there
may not be adequate supporting rationale in the record for us to
conclude that the agency had a reasonable basis for the source
selection decision. Southwest Marine, Inc.; American Sys. Eng'g
Corp., B-265865.3, B-265865.4, Jan. 23, 1996, 96‑1 CPD para. 56
at 10. Nevertheless, in reviewing an agency's procurement
actions, we do not limit our review to contemporaneous evidence,
but consider, as appropriate, hearing testimony and the parties'
arguments. Id.
Here, while Resource's 1-hour oral presentation was videotaped,
the Q&A session was not. Instead, this session was documented by
hand-written notes taken by acquisition personnel. The contract
specialist used these notes, and her own, to prepare a document
memorializing the session. When Resource asserted that the
contract specialist's account mischaracterized its answers, the
contract specialist permitted Resource to submit its version of
the answers, which with a few edits by the agency, was accepted
as an accurate memorialization of the session. AR, Tab 19f,
Email from Contract Specialist (Nov. 4, 2010). The accepted
revisions provided much more detailed answers to the questions
offered during the Q&A session of the oral presentation, for
example, in the areas of collaboration with federal bureaus and
methods. AR, Tab 19e, Resource's Final Q&A Document.
Because of the events surrounding Resource's Q&A session, this
was an issue at the hearing that our Office conducted on this
protest. At the hearing, a witness from the TEP was asked by the
hearing officer to provide her recollection of Resource's Q&A
session. The hearing officer read several of the questions from
the document memorializing Resource's answers during the Q&A
session to the TEP member, who testified that she had not seen
either the initial or finalized version of the document. Tr. at
30-31, 84. Although the TEP member testified that she was able
to recall some of the questions, she had limited recall of
Resource's answers; to the extent she recalled the answers, her
recollection seemed more consistent with the initial version of
the Q&A document, than with the final document that the agency
agreed more accurately reflected Resource's answers. Tr. at 93,
133, 135-36. Moreover, the initial, less detailed, version of
Resource's responses to the questions posed in the Q&A session
is more consistent with the technical consensus document
concluding that Resource's quotation was technically
unacceptable because it explained that the answers given by
Resource on October 14, particularly in the areas of
collaboration and methods, failed to provide sufficient detail
to convince the technical evaluators that its quotation was
technically acceptable. AR, Tab 21, Consensus of Resource, at
2-3.
Thus, despite receiving hearing testimony and the parties'
post-hearing arguments, we cannot find that the agency's
documentation in regard to Resource's Q&A session is sufficient
to allow us to review the reasonableness of the agency's
judgments. Because the final, mutually agreed-upon version of
the Q&A document addresses some of the weaknesses included in
the TEP's consensus report that supported Resource's
unacceptable rating, this document is at odds with the consensus
evaluation report. In addition, the final Q&A document, which
the agency accepted as an accurate memorialization of the
session, is inconsistent with the testimony of the TEP witness;
at a minimum, the final document provides more robust answers
than the TEP member recalled during her testimony. Compare AR,
Tab 19e, attach., Final Q&A Document for Resource's Oral
Presentation, at 3 with Tr. at 135-136. In view of these
discrepancies, it is unclear whether the TEP members reasonably
understood and considered Resource's answers at the oral
presentation. Accordingly, we cannot find that the agency's
documentation adequately supports its decision. See e-LYNXX
Corp., supra; Checchi and Co. Consulting, Inc., supra. (Resource
Dimensions, LLC, B-404536, February 24, 2011) (pdf)
Frontier argues that its quote was reasonable and that the CO
failed to properly evaluate its quoted price in accordance with
the terms of the RFQ. Frontier also argues that the IGE was
flawed and should not be used as a basis to determine price
reasonableness. The protester further argues that since it was
the only HUBZone small business vendor to submit a quote, the CO
could not evaluate its price by comparing it to the prices
quoted by other small business concerns.
As noted above, the procurement was conducted under simplified
acquisition procedures. Simplified acquisition procedures are
designed to, among other things, reduce administrative expenses,
promote efficiency and economy in contracting, and avoid
unnecessary burdens for agencies and contractors. Federal
Acquisition Regulation (FAR) sect. 13.002. These procedures
provide discretion to COs to use one or more of the evaluation
procedures in FAR Parts 14 and 15. See FAR sect. 13.106-2(b);
Finlen Complex, Inc., B-288280, Oct. 10, 2001, 2001 CPD para.
167 at 8-10. When using these procedures, an agency must conduct
the procurement consistent with a concern for fair and equitable
competition and must evaluate quotations in accordance with the
terms of the solicitation. In reviewing protests of an allegedly
improper simplified acquisition evaluation, we examine the
record to determine whether the agency met this standard and
exercised its discretion reasonably. Russell Enters. of N.
Carolina, Inc., B-292320, July 17, 2003, 2003 CPD para. 134 at
3.
The primary issue here is Frontier’s claim that the CO
improperly used an “unreasonable price” determination to reject
the quote of a HUBZone business concern. As stated above, the
RFQ specifically provided that a BPA would be issued to those
vendors who submitted a technically acceptable quote at a
reasonable price. RFP para. E.2. The RFQ further stated that
price would be evaluated in accordance with the FAR. Id. Under
simplified acquisition procedures price reasonableness is
determined by the CO. FAR sect. 13.106-3(a). The CO may make a
reasonableness determination based on a comparison to an IGE.
FAR sect. 13.106-3(a)(2)(vi). Here, the CO, in accordance with
the FAR, based her price reasonableness decision on an IGE that
was prepared using market research. Frontier’s quote was
significantly higher than the IGE and was therefore determined
to be unreasonably priced. We do not find this determination to
be unreasonable.
The protester also argues that the IGE used here was developed
after an inadequate evaluation of the market for the required
equipment. In calculating the IGE, the agency reports that it
contacted companies in Montana, Idaho and Washington who offered
mobile refrigerated units for rent and the prices from these
firms ranged from $125 through $175 with variations in pricing
schemes depending on length of rental. AR, Tab 2, CO Statement
at 6. The agency also did an internet search to establish a
price range for similar units meeting OSHA (Occupational Safety
and Health Administration) requirements. Finally, the IGE was
established by adding a premium amount to an average of the
market prices to take into consideration the excessive wear and
tear the equipment would experience. Id.
On this record, we have no basis to conclude that the IGE was
not reasonably based or that the market research was inadequate.
If anything, the adequacy of the agency’s market research was
vindicated by the quotes it received from numerous other small
business concerns. Frontier’s argument that the IGE was based on
an inadequate evaluation of the market reflects mere
disagreement with the agency’s assessment and provides no basis
for our Office to sustain a protest. (Frontier
Transportation, Inc., B-400345, September 9, 2008) (pdf)
In reviewing a protest against an agency’s evaluation of
quotations, we examine the record to determine whether the
agency’s judgment was reasonable and consistent with the stated
evaluation criteria and applicable statutes and regulations.
American Artisan Prods., Inc., B-286239, Nov. 29, 2000, 2000 CPD
para. 198 at 2. Here, we think that the agency reasonably
rejected the quotation as unacceptable based on the protester’s
failure to furnish an image demonstrating that the thumbdrive
that it was offering contained an external write-protect switch.
The RFQ required vendors to submit an image of the write-protect
switch, presumably, as noted, to demonstrate the switch’s
compliance with the requirement that it extend above the body of
the drive so as to be operable by finger (i.e., without the use
of a tool). It is the vendor’s responsibility to submit the
information requested by the agency for evaluation purposes, and
a vendor that does not do so runs the risk that its quotation
will be rejected as unacceptable. 3K Office Furniture
Distribution GmbH, B-292911, Dec. 18, 2003, 2003 CPD para. 231
at 4. Here, the only image that the protester furnished to the
contracting officer prior to the technical evaluation on July 13
was the image of the drive incorporating a biometric switch that
it proposed for the top secret drives. Even assuming that
this image satisfied the RFQ requirement for an image of a
finger-operated write-protect switch with regard to the top
secret drives, the fact remains that the protester furnished no
image of the switch that it was proposing for the unclassified
and secret drives. While the protester maintains that it had
previously furnished a color picture of a thumbdrive with an
appropriate switch in response to an earlier RFQ that was
cancelled, the protester made no reference to the previously
submitted image in the quotation that it submitted in response
to the RFQ here; given the lack of any reference to the previous
submission, we do not see how the evaluators should have been
expected to know of its existence and/or the fact that it was an
image of the product that Joint Systems intended to furnish
here. Accordingly, we think that the evaluators reasonably
rejected the protester’s quotation as technically unacceptable
for failing to furnish a picture of a write-protect switch
conforming to the solicitation requirements for the secret and
unclassified drives. (Joint Systems,
Inc., B-298573, October 6, 2006) (pdf)
When using simplified acquisition procedures under FAR Part 13,
an agency must conduct the procurement consistent with a concern
for fair and equitable competition. In reviewing protests
against an allegedly improper simplified award selection, we
examine the record to determine whether the agency met this
standard and exercised its discretion reasonably. Dew Drop
Sprinklers & Landscaping, B‑293963, July 15, 2004, 2004 CPD para.
171 at 3. The agency claims that telecommunications services
were necessary to test and demonstrate the operability of the
KVTS, and that it added the $7,000, which was taken from the
same price schedule containing CUI’s $20,000 quotation to make
the system operable, to account for these costs because “[t]he
government also had to identify the cost of telecommunications
within the CUI quotation in order to ensure [that] CUI had
presented a viable proposal of reestablishing operability and
testing of the KVTS,” given that CUI’s quotation did not
specifically indicate that such costs were included. Contracting
Officer’s Supplemental Statement at 3. CUI’s claim that the
costs for necessary telecommunications were included in its
$20,000 lump sum quotation is consistent with its e-mails and
quotation, given that the quotation expressly included the
acquisition of new cell phone lines and testing of the system,
which could not be done without an active telecommunications
service. In addition, CUI’s quotation clearly indicated that the
$7,000 figure used by the agency in the evaluation was not the
total monthly telecommunications charges, but was a proposed
increase to the monthly communications charges under CUI’s
maintenance contract, and that this proposed increase was not
related to CUI’s quotation to make the system operable. Our
review reveals no reasonable basis for the agency to assume that
the $7,000 increase referred to in CUI’s quotation represented
the cost of telecommunications that would be needed to make the
system operable under the purchase order. In any case, the
record evidences that the contracting officer did not ask CUI
whether the costs for necessary telecommunications were included
in its quotation or request CUI to separately price the
telecommunications charges. Instead, when its quotation was
solicited, CUI was asked to provide “a detailed proposal of what
work and costs would be required to reestablish KVTS
operability,” and for a “[p]roposed cost for the overall
effort,” to reestablish the operability of the KVTS. Contracting
Officer’s Supplemental Statement at 2; Agency Supplemental
Report, Tab H, E-mail from Contracting Officer to CUI (Sept. 9,
2006). Before adding this $7,000 charge to CUI’s quotation for
evaluation purposes, the agency, at a minimum, should have
requested CUI to verify whether or not the costs for necessary
telecommunications to accomplish the purchase order work were
included in its $20,000 quotation. In sum, the agency
unreasonably added CUI’s proposed $7,000 increase in its
telecommunications monthly charge in the KVTS maintenance
contract to CUI’s $20,000 quotation without first requesting
that CUI verify whether the necessary telecommunications costs
were already included in its quotation. On this record, CUI’s
$20,000 quotation was the lowest-priced one, and CUI should have
been issued the purchase order, if otherwise appropriate.
Because we are advised by the agency that the performance under
this purchase order has been completed, we recommend that CUI be
reimbursed its quotation preparation costs as well as the
reasonable costs of filing and pursuing the protest. 4 C.F.R.
sect. 21.8(d)(1), (2). CUI should submit its certified claim for
costs, detailing the time expended and costs incurred, directly
to the agency within 60 days of receiving this decision. (Computers
Universal, Inc., B-297552,February 14, 2006)
We find the source selection to be reasonable and in accordance
with the terms of the solicitation. Although Dew Drop asserts
that it was improper for the agency to consider the relative
experience of the two offerors as a discriminator, the RFQ
specifically stated that the agency would evaluate experience,
along with past performance, technical ability to meet the
requirements and price, and make award to the vendor whose
quotation provided the best value after considering these
factors. Further, while Dew Drop challenges the agency's
position that the technical evaluation factors were important,
arguing that the project was only a simple one, we note that the
RFQ did not make price more significant than the technical
factors. On the contrary, the RFQ did not specify the relative
importance of the individual evaluation factors and, in the
absence of any indication in the RFQ of the relative importance
among the individual evaluation factors, they are presumed to be
of equal importance. See Hyperbaric Techs., Inc. , B293047.2;
B-293047.3, Feb.11, 2004, 2004 CPD 87 at 4; Maryland Office
Relocators , B-291092, Nov. 12, 2002, 2002 CPD 198 at 5. Agency
officials have broad discretion in determining the manner and
extent to which they will make use of the technical and cost
evaluation results. Price/technical tradeoffs may be made, and
the extent to which one is sacrificed for the other is governed
by the test of rationality and consistency with the established
factors. See Structural Preservation Sys., Inc. , B-285085, July
14, 2000, 2000 CPD 131 at 7. An agency may properly select a
more highly rated quotation over one offering a lower price
where it has reasonably determined that the technical
superiority outweighs the price difference. See Sawtooth
Enters., Inc. , supra. , at4. As explained above, the
contracting officer determined that TML's non-price advantages
warranted payment of that firm's higher price. Dew Drop has
furnished no basis for our Office to question this
determination. (Dew Drop Sprinklers &
Landscaping, B-293963, July 15, 2004) (pdf)
Here, we find that the contracting officer failed to give any
meaningful consideration to e-LYNXX’s substantially lower
quotation price, given his inability to explain why Noosh’s
superiority was worth the more than 65 percent higher price.
More specifically, we question whether the contracting officer
had a sufficient basis to perform a rational price/technical
tradeoff where he testified that the open posting requirement
was a key consideration in his analysis but that he did not
understand the requirement or obtain any advice concerning it
from anyone that did. We fail to see how the contracting officer
can assign value for something he admittedly does not understand
and for which he did not seek any advice, and we sustain e-LYNXX’s
protest on this basis. (e-LYNXX
Corporation, B-292761, December 3, 2003) (pdf)
Under the circumstances, we find that the USDA's decisions to
rate Houston's quotation unacceptable under the weight and
balance factor and to not conduct discussions with that firm
were reasonable and not unfair. The RFQ informed offerors that
award would be made without discussions, RFQ § E.1(g), and it
does not appear from the record that the exchanges afforded
Commander an opportunity to revise its quotation. Given that
Houston failed to provide the required weight and balance sheet,
which rendered its quotation unacceptable under this factor, the
agency did not have to engage in discussions with Houston to
enable it to remedy this deficiency. CDS Network Sys., Inc.,
B‑281200, Dec. 21, 1998, 98-2 CPD ¶ 154 at 3. (Houston
Air, Inc., B-292382, August 25, 2003) (pdf)
We recognize that the agency may have reasonably desired, and
certainly could have required, that technical proposals include
a detailed plan, as well as evidence of the vendors'
understanding of the requirements and their qualifications and
experience. That would be altogether appropriate and within the
agency's discretion. Stating such desires and requirements is
the purpose of evaluation criteria in a solicitation, and it is
to provide transparency in our federal procurement process and
fairness for those competing for federal contracts that, as
explained above, agencies are required by procurement law to set
out in the solicitation the evaluation criteria, and then to
follow them. Here, the RFQ did not put vendors on notice of any
of the requirements that the agency has now identified. In our
view, it would be unfair for the agency, after the fact, to
evaluate technical proposals based on criteria that the agency
was required to identify before vendors submitted those
proposals. See FAR §§ 13.106-1(a)(2), 13.106‑2(a)(2). We
therefore sustain the protest. (SKJ
& Associates, Inc., B-291533, January
13, 2003) (pdf) (text
version)
Where an agency is not required to hold discussions or otherwise
communicate with vendors regarding past performance information,
as is the case where simplified acquisition procedures are
employed, see FAR § 13.106-2(b)(2), and the contracting officer
has no reason to question the validity of the past performance
information, we think that she can reasonably rely on the
information furnished without seeking to verify it or permitting
the protester an opportunity to rebut it. Lynwood Mach. &
Eng'g, Inc., B-285696, Sept. 18, 2000, 2001 CPD ¶ 113 at
7. Moreover, we note that an agency's past performance
evaluation may be based on a reasonable perception of inadequate
prior performance, even where the protester disputes the
agency's interpretation of the underlying facts. Quality
Fabricators, Inc., B-271431, B-271431.3, June 25, 1996, 96-2 CPD
¶ 22 at 7. Thus, we conclude the agency's actions were
unobjectionable. (John
Blood, B-290593, August 26, 2002)
Although
an agency is not required to establish a competitive range or
conduct discussions under simplified acquisition procedures, we
think that where an agency avails itself of these negotiated
procurement procedures, the agency should fairly and reasonably
treat quoters in establishing the competitive range and
conducting discussions. See Finlen Complex, Inc., B-288280, Oct.
10, 2001, 2001 CPD para. 167 at 8-10.
In sum, we find
unreasonable the Corps's competitive range determination that
included only Act II's quote. In making this judgment, the Corps
apparently mistakenly believed that Act II's quote satisfied all
the solicitation requirements and was acceptable. Instead, the
record shows that two firms' quotes suffered from similar
informational weaknesses that were susceptible of correction
through discussions. We sustain KHA's protest because the Corps
failed to treat the two firms fairly and equally with respect to
conducting discussions. (Kathryn
Huddleston and Associates, Ltd., B-289453, March 11, 2002)
Where an agency is not required to
hold discussions or to otherwise communicate with vendors
regarding past performance information, as is the case here
where simplified acquisition procedures were employed, see FAR
sect. 13.106-2(b)(2), and where the evaluators and selection
official have no reason to question the validity of the past
performance information, they can reasonably rely on the
information furnished without seeking to verify it or permitting
the protester an opportunity to rebut it. See A.G. Cullen Constr.,
Inc., B-284049.2, Feb. 22, 2000, 2000 CPD para. 45 at 5. (Ocean
Technical Services, Inc., B-288659, November 27, 2001)
In our view, it was inappropriate
for the agency, on the one hand, to request quotes from the
vendors for equipment for six locations and to issue a delivery
order based on the prices for all six locations, and, on the
other hand, for price evaluation purposes, to consider prices
for only five locations. Procuring agencies do not have the
discretion to announce one evaluation scheme and then follow
another in the actual evaluation. Technical Support Servs.,
Inc., B-279665, B-279665.2, July 8, 1998, 98-2 CPD para. 26 at
3. The record shows that, had the agency compared the quotes
based on the prices proposed for all six locations, as requested
by the agency, then the protester's quote would have been low.
Nonetheless, based on the record here, the selection of the
Solvetech system is unobjectionable. The agency solicited quotes
orally, which is allowed under FAR sect.13.106-1(c), and while
vendors were told that price would be the predominant
consideration in the selection decision, vendors were also
advised that other factors, such as life-cycle costs,
standardization and ease of data extraction would also be
considered. Telephone Hearing, Jan. 21, 2000. After evaluating
price and technical considerations, the agency reasonably
determined that the Solvetech system represented the better
value. (AudioCARE
Systems, B-283985, January 31, 2000)
Even under simplified
acquisition procedures, award decision is not reasonable where
the record does not provide any documentation or explanation
which supports the price/technical tradeoff, and the award
determination appears to be based entirely on a comparison of
total technical point scores without consideration of
protester's lower technically scored, but low priced proposal.
(Universal
Building Maintenance, Inc., B-282456, July 15, 1999) |