After reviewing the bids, the agency determined that all
three were unreasonably high priced, and that it could not
make award on the basis of the bids submitted. In this
connection, the record shows that the agency made its
determination regarding the unreasonableness of the prices
by comparing them to a government estimate prepared by the
agency. The record shows that the government estimate for
the work was $13,927,205. AR, exh. 22, Independent
Government Estimate at 3. In comparison, 4H’s bid was
$18,332,000, and the other two bids were for $19,279,250
and $21,564,150 respectively. AR, exh. 11, Bid Abstract.
Because all three bids exceeded the government estimate by
more than 25 percent, the agency concluded that they were
unreasonably high and that award could not be made to any
of the bidders.
(paragraph deleted)
In response to the protester’s August
8 letter, the agency wrote to 4H on August 15. AR, exh.
15. By that letter, the agency requested that 4H provide
the agency with the complete details of its bid estimate
in accordance with the requirements of the U.S. Army Corps
of Engineers Acquisition Instructions (UAI). The specific
provision of the UAI pertinent to the protest is §
33.103-101, which provides as follows:
If, after bid opening, an apparent
low bidder protests the reasonableness of the Government
estimate, the contracting officer shall provide the
details of the Government estimate to the protester upon
receipt of complete details of the protester’s estimate.
The details of the Government and protester’s estimates
are not to be disclosed to third parties.
In response to the agency’s request,
4H specifically declined to provide its bid estimate
documents. 4H’s counsel stated as follows:
My understanding of UAI [§
]33.103-101 is that the protestor must provide the details
of its bid estimate in order to obtain a copy of the
details of the independent government estimate (“IGE”). 4H
has not requested a copy of the details of the IGE at this
time, so I do not believe it is necessary or required that
4H provide you with the details of its bid estimate.
AR, exh. 16, 4H Letter, Aug. 17,
2016, at 1 (emphasis supplied).
Subsequent to our dismissal of its
earlier protest, 4H filed the instant protest challenging
the agency’s corrective action.
4H argues that the agency’s decision to convert the
acquisition from sealed bidding to negotiated procedures
is unreasonable because the agency’s conclusion that the
prices submitted are unreasonably high is based on a
government estimate that is unrealistically low. The only
basis for the protester’s current challenge to the realism
of the government estimate is its contention that it was
based on a price for diesel fuel that is too low and does
not reflect market realities. The protester maintains
that, if the agency calculated the government estimate
using a reasonable price for diesel fuel, its bid would be
within 125 percent of the government estimate. 4H
therefore maintains that the agency is required to award a
contract to it at its originally-bid price.
We dismiss 4H’s contention relating to the realism of the
government estimate as untimely because the record shows
that 4H failed to diligently pursue the information
underlying this basis of protest. A protester has an
affirmative duty to pursue information providing a basis
for protest, and a protester’s failure to utilize the most
expeditious information gathering approach under the
circumstances constitutes a failure to meet its
obligation. MILVETS Systems Technology, Inc., B‑411721.2,
B-411721.3, Jan. 14, 2016, 2016 CPD ¶ 42 at 8.
The sole basis for 4H’s challenge to the government
estimate as unrealistically low is its contention that the
agency did not use a realistic price for diesel fuel in
calculating the estimate. The record shows that 4H first
learned of the diesel fuel price used by the agency in its
calculations when it received the agency’s September 8
letter denying its agency-level protest. However, as
discussed in detail above, 4H declined to avail itself of
the opportunity presented by the agency to exchange the
basis of its bid estimate for the government estimate, as
expressly contemplated under UAI § 33.103-101.
Had the protester not declined participation in the timely
exchange of bid estimate information with the agency, it
would have had a copy of the government estimate during
August, at the time its agency-level protest was pending.
Additionally, had the protester exchanged its bid estimate
and the government estimate with the agency at that time,
both parties would have had the necessary information to
engage in a frank and detailed discussion regarding the
propriety of their respective estimates.
In the final analysis, the protester failed to
provide--and receive--the information that could have
allowed the parties to resolve their disagreement before
the agency expended resources defending its position.
Moreover, a timely exchange of information also could have
prevented the expenditure of our Office’s time and
resources to resolve a matter that may well have been
easily and expeditiously resolved by the parties without
our involvement. Under the circumstances, we conclude that
4H failed to diligently pursue the information necessary
to file its protest on this basis, and accordingly dismiss
this allegation as untimely. (4H
Construction Corporation B-413558.4: Feb 8, 2017)
Retro argues that it submitted the
lowest bid, and that any error in the IFB does not provide
a compelling reason to cancel the IFB because multiple
bidders correctly inferred that a subcontractor license
would be acceptable, and because Retro, which holds a
license, was and would remain the lowest-priced bidder
under the IFB, both as issued and as the agency proposes
to revise it. Protest at 4.
The Army argues that the circumstances here provide a
compelling basis to cancel the IFB for two reasons. First,
the restrictive terms of the IFB may have prevented
competition by additional bidders that might have
submitted a lower bid than Retro, but were discouraged by
the apparent requirement that the license be in the prime
contractor’s name. AR, at 8-9. The Army argues that the
goal of achieving full and open competition requires an
IFB that does not overstate the agency’s requirements, and
thus the flaw in the IFB constitutes a compelling reason
to cancel the IFB. Id. at 8. Second, the Army also argues
that Retro’s bid was unacceptable because it did not
describe an acceptable approach to performing the work and
contained a pricing error (entering a price for one line
item as “$12,0000” rather than $12,000). Id. at 10-11. The
Army argues that Retro’s bid therefore should have been
rejected, and the impropriety of awarding a contract in
response to an unacceptable bid further justifies the
decision to cancel the IFB--or at least renders Retro not
an interested party to protest the cancelation. Id. at 12.
In response, Retro argues that the alleged defects in its
bid were identified only after it filed this protest,
whereas at the time of award, the defects had been
properly waived as minor informalities or minor mistakes.
Protester’s Comments at 1-2. Retro also argues that the
Army’s main claim, that the allegedly misleading state
license requirement justifies cancelation of the IFB, is
not a valid legal basis to cancel the IFB because an
ambiguous specification is only a basis to cancel an IFB
before award, not after. Id. at 1 (citing Federal
Acquisition Regulation (FAR) § 14.404-1(c)). Retro also
argues that the IFB resulted in full and fair competition,
and it questions the credibility of the Army’s claim that
a revised IFB would result in more competition. Id. at 2.
A contracting agency must have a compelling reason to
cancel an IFB after bid opening because of the potential
adverse impact on the competitive bidding system of
resoliciting bids after prices have been exposed. FAR §
14.404-1(a)(1). Where a solicitation contains inadequate
or ambiguous specifications, or otherwise does not contain
specifications that reflect the agency’s actual needs,
those circumstances provide a sufficient reason to cancel
the IFB. FAR § 14.404-1(c)(1). Contracting officials have
broad discretion to determine whether a compelling reason
to cancel exists; our Office’s review is limited to
considering the reasonableness of their decision.
Brickwood Contrs., Inc., B-292171, June 3, 2003, 2003 CPD
¶ 120 at 4-5.
Specifications must be sufficiently definite and free from
ambiguity so as to permit competition on an equal basis.
An ambiguity exists if a solicitation requirement is
subject to more than one reasonable interpretation when
read in the context of the solicitation as a whole. Id. In
our view, the contracting officer reasonably determined
that there was a compelling reason to cancel the
solicitation because the IFB included an ambiguous
specification; that is, the IFB here could be reasonably
interpreted as limiting competition only to prime
contractors that held a state asbestos abatement license,
which exceeded the agency’s minimum needs. While Retro
points out that the specification could also be
interpreted as allowing either the prime contractor or the
subcontractor doing the abatement work to possess the
license, the contracting officer reasonably concluded that
the IFB was susceptible to more than one reasonable
interpretation, and thus may have limited competition. The
contracting officer’s judgment that the IFB should be
canceled is thus reasonable. (Retro
Environmental, Inc. B-411457.3: Aug 19, 2015) (pdf)
GLDD argues that the Corps lacks a compelling reason to cancel
the IFB after bid opening, and maintains that the agency did not
meaningfully consider delaying contract award. GLDD complains
that its competitors will seek to undercut its low bid in any
subsequent re‑procurement, and urges the Corps to reinstate the
IFB and permit bidders to extend their bid acceptance periods
pending resolution of the real estate issues.
The Corps asserts that its inability to provide the required
real estate interests, and the indeterminate amount of time that
it will take NJDEP to acquire those interests through the more
time consuming eminent domain process, provide compelling
reasons to cancel the IFB. Moreover, the Corps maintains that
the project performance period will remain unknown for many
months--likely impacting bid prices and the availability of
other offerors to compete for the requirement--which also
provide compelling reasons to cancel the solicitation. AR at 9,
citing, inter alia, Southwest Marine, Inc., B-229596, B-229598,
Jan. 12, 1988, 88-1 CPD ¶ 22. The Corps maintains that when it
issued the IFB, neither the Corps, nor NJDEP, expected the
litigation discussed above, which effectively reversed NJDEP’s
earlier authorization for construction.
A contracting agency must have a compelling reason to cancel an
IFB after bid opening due to the potential adverse impact on the
competitive bidding system of resoliciting after bid prices have
been exposed. FAR § 14.404-1(a)(1); HDL Research Lab, Inc.,
B‑254863.3, May 9, 1994, 94‑1 CPD ¶ 298 at 5. Contracting
officials have broad discretion to determine whether a
compelling reason to cancel exists, and our review is limited to
considering the reasonableness of their decision. Chenega Mgmt.,
LLC, B‑290598, Aug. 8, 2002, 2002 CPD ¶ 143 at 2.
We find the Corps’ decision to cancel the IFB reasonable under
the circumstances described above. The Margate litigation, and
the indeterminate delays that are likely to result from the
required condemnation proceedings, provided compelling reasons
for the Corps to cancel the solicitation. The Corps’ decision is
also consistent with the IFB’s explicit (and emphatic) warning
to potential bidders that there was no guarantee that
outstanding real estate issues would be resolved or that a
contract would be awarded. IFB at 3. Moreover, contrary to the
protester’s assertion, the Corps did in fact consider postponing
the award date and requested that bidders extend their bids for
60 days, as discussed above. Despite its arguments now, GLDD
initially refused to extend its bid for 60 days, and agreed only
to a 30-day extension, which it later extended to 60 days.
While the protester apparently believes that the Corps should
continue to seek an indefinite number of bid extensions, we
believe that the agency acted reasonably here and was not
required to do more. To the extent that GLDD asserts that the
Corps did not consider the risks to bidders of cancelling the
IFB without award, the agency states, and the protester does not
dispute, that the decision to cancel the IFB was taken after
substantial consultation with the project manager, real estate
professionals, legal counsel, and others, who concluded that the
litigation may negatively impact the progress of any awarded
contract. We find no basis to disagree with the agency’s
deliberations or ultimate decision to cancel the solicitation.
(Great Lakes Dredge & Dock Company,
LLC B-411207: Jun 8, 2015) (pdf)
The protester
asserts that the agency did not have a compelling basis to
cancel the solicitation, and that the cancellation was defective
because the agency did not follow proper procedures.
Regarding the protester’s first argument, once bids have been
opened, award must be made to the responsible bidder with the
lowest responsive bid, unless there is a compelling reason to
reject all bids and cancel the IFB. FAR § 14.404-1(a)(1). In
this case, the agency had several compelling reasons for
cancellation. First, the agency determined that funding was not
available for the project. At the time of cancellation, no FY
2013 funds were available to award the contract. Contracting
Officer’s Statement of Relevant Facts at 2. A contracting agency
has the right to cancel a solicitation when sufficient funds are
not available. National Projects, Inc., B-283887, Jan. 19, 2000,
2000 CPD ¶ 16 at 4. Second, the contracting agency determined
that the existing levee meets its needs and, as a consequence,
the government would not receive any benefit if it proceeded
with the project. Cancellation of bids before award but after
bid opening is permitted, when supplies or services being
contracted for are no longer required. FAR § 14.404-1(c)(3).
(Specialized Steel Contractors, Inc.,
B-408022, B-408022.2, May 14, 2013) (pdf)
GLDD argues that
the Corps improperly canceled the IFB because the agency did not
have a compelling reason for its action, as required under the
FAR. In its response to the protest, the Corps identified
several reasons why it believed that cancellation of the August
24 IFB was proper. As relevant here, the agency argues that the
August 24 IFB was ambiguous with regard to the mobilization and
demobilization CLINs, and that this defect could result in the
government paying twice for demobilization services. Agency
Supp. Response (Jan. 15, 2013) at 2; Agency Response to GAO
Interrogatories (Jan. 24, 2013) at 3. Because we conclude that
the defects concerning the mobilization and demobilization CLINs
provide a compelling basis to cancel the solicitation, we do not
address the agency’s other bases for cancellation.
When an agency issues an IFB and opens bids, award must be made
to the bidder who submitted the lowest responsive bid, unless
there if a compelling reason to reject all bids and cancel the
invitation. Federal Acquisition Regulation § 14.404-1(a)(1). The
standard for canceling an IFB after bids have been opened is
different from the standard for canceling a request for
proposals (RFP) after award; an agency need only demonstrate a
reasonable basis to cancel an RFP after award. See Noelke GmbH,
B-278324.2, Feb. 9, 1998, 98-1 CPD ¶ 46 at 3. This different
standard applies because of the potential adverse impact on the
competitive bidding system of cancelation after bid prices have
been exposed at a public bid opening. United Contracting LLC,
B-407417, Jan. 2, 2013, 2013 CPD ¶ ___ at 2. A compelling reason
to cancel a solicitation after bid opening exists where material
solicitation terms are ambiguous or in conflict. P.J. Dick, Inc.
B-259166, B-260333, Mar. 6, 1995, 95-1 CPD ¶ 131 at 4.
The Corps argues that the mobilization and demobilization CLINs
in the August 24 IFB required revision because the solicitation
was ambiguous as to how the successful contractor would be paid
for these services. As discussed above, the August 24 IFB
contained CLIN 0001 for mobilization/demobilization, and CLIN
1001 for demobilization. The August 24 IFB also incorporated the
following DFARS clause, which specified how mobilization and
demobilization costs would be paid:
(a) The Government will pay all costs for the mobilization and
demobilization of all of the Contractor’s plant and equipment
at the contract lump sum price for this item.
(1) Sixty-Five (65%) percent of the lump sum price upon
completion of the contractor’s mobilization at the work
site.
(2) The remaining thirty five (35%) percent upon completion
of demobilization.
DFARS § 252.236-7004; IFB at 39.
The August 24 IFB also provides: “Demobilization will be paid at
the completion of the base year if the option year is not
exercised. If the option year is exercised, demobilization will
be paid upon its completion.” IFB at 53. In contrast, the
revised January 8 IFB contained CLIN 0001 for mobilization and
CLIN 0010 for demobilization in the base year, and CLINs 1001
and 2001 for demobilization in each option year; the January 8
IFB also did not incorporate DFARS § 252.236-7004.
The Corps argues that the August 24 IFB CLINs created an
ambiguity because, for similar dredging contracts, there is
typically one mobilization at the beginning of contract
performance, and one demobilization at either the end of the
base year, or at the end of the option year, if the option is
exercised. Agency Supp. Response (Jan. 15, 2013), at 2. The
agency argues that under the August 24 IFB, the CLIN structure
for mobilization and demobilization created the possibility that
the agency would pay twice for a service provided only once.
Agency Response to GAO Interrogatories (Jan. 24, 2013) at 3.
We agree with the Corps that the August 24 IFB was ambiguous
with regard to the price to be paid for mobilization and
demobilization. Specifically, inclusion of CLIN 0001 for both
mobilization and demobilization in the base year, as well as
CLIN 1001 for demobilization in the option year, creates
uncertainty as to whether the contractor would be paid once, or
twice, for demobilization. In this regard, as discussed above,
DFARS § 252.236-7004 provides that 65 percent of the “lump sum”
for mobilization and demobilization will be paid upon completion
of mobilization, and the remaining 35 percent of that lump sum
amount will be paid upon completion of demobilization. As
applied to the August 24 IFB CLINs, it is not clear whether
“lump sum” means only the price for CLIN 0001 for
mobilization/demobilization in the base year, or the sum of the
prices for CLIN 0001 as well as CLIN 1001 for demobilization in
the option year.
For example, if the term lump is read to mean that the
contractor will be paid the sum of both CLIN 0001 and 1001, and
the agency does not exercise the option year, the agency would
pay for demobilization twice--once for the portion of CLIN 0001
attributable to demobilization and once for demobilization under
CLIN 1001. As another example, if the term lump sum is read to
mean only CLIN 0001, then it is not clear how much the agency
should pay for demobilization if it exercises the option year.
Under DFARS § 252.236-7004(a)(2), the agency is obligated to pay
“[t]he remaining [35 percent]”--however, it is unclear whether
that amount should include only CLIN 1001, or that CLIN plus the
remainder (35 percent) of CLIN 0001.
GLDD contends that the IFB was not ambiguous and would not
result in the government paying twice for demobilization
services. In this regard, the protester states that in its
performance of prior contracts, it was the practice of the
agency to pay 65 percent of the price for the base year
mobilization/demobilization CLIN upon completion of
mobilization, to exercise the option year, and then pay the full
unit price for the demobilization CLIN in the option year.
Protester’s Supp. Comments (Jan. 28, 2013) at 4. Although the
protester contends that the agency could potentially avoid any
confusion or ambiguity concerning payment for mobilization and
demobilization by following this prior practice, there is no
guarantee that the contract here would be performed in the same
manner. Moreover, there is no guarantee that the successful
bidder under the IFB here would not dispute the method for
calculating the method of payment under the contract’s disputes
clause, given the ambiguities discussed above.
In sum, we conclude that the IFB terms governing the amount to
be paid for demobilization are ambiguous and in conflict and,
therefore, provide a compelling reason for cancelling the August
24 IFB. (Great Lakes Dredge &
Dock Company, LLC, B-407502.2, Feb 13, 2013) (pdf)
The IFB, issued
on May 18, 2012, as a total service-disabled veteran-owned small
business (SDVOSB) set-aside, sought bids to replace the roofs on
buildings 2 and 4 at the east campus of the Central Alabama
Veterans Health Care System, Tuskegee, Alabama. The IFB
contained two bid items: (1) “BID ITEM NO. 1” for all the work
to replace the roofs on both buildings, and provide a 20-year
bituminous roof warranty; and (2) “DEDUCTIVE BID ALTERNATIVE #1”
to delete the work for one of the buildings (building 2) and
provide a 15-year bituminous roof warranty, instead of a 20-year
warranty. IFB at 1.
In addition, amendment No. 0003, added “ADDENDUM ITEM UNIT
PRICING,” which stated as a follows:
Contractor to provide unit pricing for rotten, deteriorated or
damaged existing wood components needed and not specified. The
price shall be per board foot of furnished and installed
items. Provide evidence and quantities to the VA.
RFP amend. 3, at 1.
Five bids were received in response to the IFB by the June 18
bid opening. One bidder was determined to be ineligible for
award because it was not an SDVOSB. The remaining bids ranged
from $85,000 to $499,000 for BID ITEM NO. 1; $19,000 to $175,000
for DEDUCTIVE BID ALTERNATIVE #1; and $4.50 per unit to $50 per
unit for the ADDENDUM ITEM UNIT PRICING. Agency Report (AR) at
2.
On July 12, the contracting officer cancelled the IFB pursuant
to Federal Acquisition Regulation (FAR) § 14.404-1(c)(4). The
contracting officer determined, based on the significant
variance in prices, that bidders may not have comprehended the
VA’s requirements because ADDENDUM ITEM UNIT PRICING in
amendment 3 failed to include a specific estimate of the
deteriorated or damaged wood components in need of repair, or a
basis for evaluating the costs for this work. Specifically, the
contracting officer decided to issue a new solicitation to
provide: a detailed statement of work; revised specifications;
the estimated square footage of rotten, deteriorated, or damaged
existing wood; the estimated quantities of components needed;
and, a formula by which the bidder would be able to accurately
bid on the work required. AR, exh. 4, Determination and
Findings, at 3.
Because of the potential adverse impact on the competitive
bidding system of cancellation after bid prices have been
exposed, a contracting officer must have a compelling reason to
cancel an IFB after bid opening. FAR § 14.404-1(a)(1). The
contracting officer has the discretion to determine whether the
necessary circumstances exist for canceling a solicitation, and
we will review the decision to ensure that it was reasonable.
Dynamic Corp., B-296366, June 29, 2005, 2005 CPD ¶ 125 at 4. As
a general rule, the need to change inadequate or ambiguous
specifications and to revise them, after the opening of bids, to
express properly the agency’s minimum needs constitutes such a
compelling reason. See FAR § 14.404-1(c)(1), (2); G.H. Harlow
Co., Inc., B-245050 et al., Nov. 20, 1991, 91-2 CPD ¶ 484 at 3.
In addition, FAR § 14.404-1(c)(4) provides that a compelling
basis to cancel exists if the IFB does not provide for
consideration of all factors of cost to the government.
Here, we find the contracting officer’s determination to cancel
the solicitation reasonable because certain material matters
related to the specifications and cost to the government were
not included in the invitation. As noted by the contracting
officer, the record evidences a wide disparity in bid prices,
and we find that without a more accurate formula for pricing the
work, the agency could not accurately compare the bidder’s
prices against each other, or otherwise determine which bid
reflected the lowest price to the government. Thus, any award
under the IFB would be prejudicial to the remaining bidders and
the government. See Dynamic Corp., supra. Although, the
protester raises several arguments as to why the cancellation is
improper, it has not shown that the agency was not reasonably
within its discretion to cancel the IFB. (United
Contracting LLC, B-407417, Jan 2, 2013) (pdf)
A contracting
agency must have a compelling reason to cancel an IFB after bid
opening due to the potential adverse impact on the competitive
bidding system of resoliciting after bid prices have been
exposed. Federal Acquisition Regulation (FAR) sect. 14.404-1(a)
(1); HDL Research Lab, Inc., B-254863.3, May 9, 1994, 94-1 CPD
para. 298 at 5. An IFB may be canceled and all bids rejected
after opening where, consistent with the compelling reason
standard, cancellation is clearly in the public's interest. FAR
sect. 14.404-1(c)(10). An agency's desire to obtain enhanced
competition by materially modifying specifications to make them
less restrictive constitutes a valid reason for canceling an IFB
under this FAR standard. Hroma Corp., B-285053, June 6, 2000,
2000 CPD para. 88 at 4; Diversified Energy Sys.; Essex Elec.
Eng'rs, Inc., B‑245593.3, B-245593.4, Mar. 19, 1992, 92-1 CPD
para. 293 at 3.
Here, in response to Cummins's protest, the agency explains
that, while it requires Onan engines, it has no legitimate need
for the contractor to be a certified Onan distributor. Agency
Report (AR) at 5. In this regard, the agency notes that Fermont
has provided the engines in the past, in a manner that meets its
needs. Id. at 6. This being the case, and since it is clear that
at least one bidder--Fermont, which submitted the lowest
price--would be precluded from competing if the certification
requirement is not removed from the IFB, the agency reasonably
determined that resolicitation would result in enhanced
competition and, accordingly, that cancellation was in the
public's interest. Under these circumstances, there was a
compelling reason to cancel the IFB, and the cancellation
therefore was unobjectionable. See Siemens Power Corp.; Asea
Brown Boveri, Inc., B-257167, B‑257167.2, Aug. 11, 1994, 94-2
CPD para. 160 at 2-3 (cancellation was unobjectionable where
agency determined it had overstated its needs and less
restrictive specifications should result in enhanced competition
and lower costs).
Cummins argues that, because it submitted a responsive bid and
it is a responsible bidder, it will be prejudiced by the
cancellation and resolicitation. However, the fact that Cummins
may be prejudiced does not preclude cancellation where, as we
have found is the case here, there is a compelling reason for
the cancellation. In any case, we note that Cummins will have
the same opportunity as the other bidders to submit a new bid
with knowledge of the other bids submitted. (Cummins
Power Systems, LLC, B-402079.2, January 7, 2010) (pdf)
Sea Box asserts that the agency improperly determined that the
bid prices all were unreasonably high, and challenges the
agency’s determination that it lacked sufficient funds. The
protester asserts that the original estimate of $624,750 was not
based on proper market research and therefore was
unrealistically low. Comments at 2. Sea Box concludes that,
since its bid for non-Chinese-made connexes was low, the agency
should have awarded it a contract instead of canceling the IFB.
Cancellation of a solicitation after bids have been opened and
prices have been exposed is only permitted where a compelling
reason exists to cancel. National Projects, Inc., B‑283887, Jan.
19, 2000, 2000 CPD para. 16 at 4; Federal Acquisition Regulation
(FAR) sect. 14.404-1(a)(1). A contracting agency properly may
cancel a solicitation when sufficient funds are not available,
regardless of any disputes concerning the validity of the
government estimate or the reasonableness of the low responsive
bid price. National Projects, Inc., supra; J. Morris & Assocs.,
Inc., B‑256840, July 27, 1994, 94-2 CPD para. 47 at 2 n.1; Armed
Forces Sports Officials, Inc., B-251409, Mar. 23, 1993, 93-1 CPD
para. 261 at 2-3, recon. denied, B-251409.2, May 24, 1993, 93-1
CPD para. 402.
Here, only two bids--Sea Box’s and one other--offered products
that met the solicitation’s BAA requirements, and by the time
the agency canceled the IFB, Sea Box was unable to supply 238
connexes that were BAA compliant. The agency determined that
both bids exceeded the original budgeted funds and the
additional funds identified by the contracting officer, and the
protester has not shown otherwise. Under these circumstances,
the agency had a compelling reason to reject all bids and cancel
the solicitation.
Our conclusion is not changed by Sea Box’s observation that the
IFB allowed the agency to make multiple awards, meaning that
award could be made for less than the entire requirement, and
that the agency therefore could have purchased a quantity of
connexes from Sea Box up to the available funding. Comments at
3-4. While the IFB allowed the agency to make multiple awards,
it did not require the agency to do so. The management of an
agency’s funds generally depends on the agency’s judgment
concerning which projects and activities shall receive increased
or reduced funding. National Projects, Inc., supra at 5; Armed
Forces Sports Officials, Inc., supra, at 2. Thus, the failure to
make award to Sea Box for a reduced quantity was not improper.
(Sea Box, Inc., B-400198, August
25, 2008) (pdf)
With regard to
the cancellation of the IFB, a contracting agency must have a
compelling reason to cancel an IFB after bid opening because of
the potential adverse impact on the competitive bidding system
of resolicitation after bid prices have been exposed. Federal
Acquisition Regulation (FAR) sect. 14.404-1(a)(1); HDL Research
Lab, Inc., B-254863.3, May 9, 1994, 94-1 CPD para. 298 at 5.
Where a solicitation contains inadequate or ambiguous
specifications, or otherwise does not contain specifications
that reflect the agency’s actual needs, the agency has
sufficient reason to cancel. FAR sect. 14.404-1(c)(1); Days Inn
Marina, B-254913, Jan. 18, 1994, 94-1 CPD para. 23 at 2.
Contracting officials have broad discretion to determine whether
a compelling reason to cancel exists, and our review is limited
to considering the reasonableness of their decision. Chenega
Mgmt., LLC, B-290598, Aug. 8, 2002, 2002 CPD para. 143 at 2.
USAID first contends that its decision to cancel BOQ B was
reasonable because the specifications for Class 300 gate valves
were ambiguous with regard to whether NRS or RS gate valves were
required. USAID states that the omission of language specifying
NRS valves likely arose because the shortcomings of RS valves in
buried applications appeared self-evident to USAID’s engineers
and outside technical staff. AR, Tab 3, Memorandum, at 5. Thus,
to these engineers, specifying that the project was for buried
water lines meant that only NRS valves were suitable. USAID
therefore argues that the specifications were ambiguous because
its engineers interpreted the specification language to mean
that only NRS valves would work, while to Corcel, the
specification of a buried application did not eliminate RS
valves from consideration.
Specifications must be sufficiently definite and free from
ambiguity so as to permit competition on an equal basis. Hebco,
Inc., B-228394, Dec. 8, 1987, 87-2 CPD para. 565 at 2-3. An
ambiguity exists if a solicitation requirement is subject to
more than one reasonable interpretation when read in the context
of the solicitation as a whole. Phil Howry Co., B-245892, Feb.
3, 1992, 92-1 CPD para. 137 at 2-3. Based on our examination of
the record here, we do not agree with the agency that the
specifications were ambiguous in the context of the solicitation
as a whole. Rather, as explained below, we conclude that
Corcel’s interpretation of the solicitation, as written, was the
only reasonable interpretation.
The specification requirements for Class 300 gate valves, as
relevant here, were limited to the statement that the valves
must be suitable for buried service. However, the specification
document attached to the BOQ also contained requirements for
other types of valves, and in a specification for lower pressure
valves, the specification document explicitly required that the
valves be “[s]uitable for buried service with non-rising stem.”
AR, Tab 5, at 5 (emphasis added). By clearly requiring NRS
valves in a specification for lower pressure buried gate valves,
but not clearly requiring NRS valves for the Class 300 gate
valve requirement, the solicitation suggested that any type of
Class 300 gate valves suitable for buried service would be
acceptable. Furthermore, the specifications listed “Velan” as an
approved manufacturer of the required Class 300 valves. As
pointed out by Corcel, Velan does not manufacture a Class 300
NRS gate valve, although it does manufacture a Class 300 RS gate
valve. Comments at 4. The agency does not dispute this fact.
Under these circumstances, we think that Corcel’s interpretation
of the specifications, that the valves needed only to be
suitable for buried use and were not required to be NRS, is the
only reasonable interpretation. Therefore, we conclude that
there was no ambiguity in the specifications that would justify
cancellation of BOQ B of the IFB.
USAID next contends that its decision to cancel BOQ B was
reasonable because, if Corcel’s interpretation of the
solicitation was the only reasonable reading, then the
specifications failed to meet the agency’s needs for the
intended project. We agree.
An IFB may be canceled after bid opening, and all bids rejected,
where an award under the IFB would not serve the government’s
actual needs, Eastern Technical Enter., Inc., B-281319,
B-281320, Jan. 22, 1999, 99-1 CPD para. 17 at 2, and our Office
will defer to the agency and to the technical expertise of its
engineering personnel in defining the government’s needs. Corbin
Superior Composites, Inc., B-242394, Apr. 19, 1991, 91-1 CPD
para. 389 at 5; Kings Point Mfg. Co., Inc., B-210757, Sept. 19,
1983, 83-2 CPD para. 342 at 3. Accordingly, we will question
that determination only where it is shown to have no reasonable
basis.
Although Corcel has zealously advocated the technical merits of
its customized RS valves, we conclude from the record that an
award under BOQ B of the IFB would not have met the agency’s
needs, and that the cancellation of BOQ B of the IFB was
therefore reasonable. Based on our review of the record, and
specifically of the statements of the contracting officer, the
USAID engineer, the PWA, and the independent engineering firms
consulted by USAID, it is clear that all parties to the approval
of the solicitation understood the specifications to require NRS
gate valves. These parties understood NRS gate valves to be
necessary to the project due to their perceptions of the
inherent shortcomings of RS valves in buried applications and
their understanding of the PWA’s technical standards, and
clearly did not anticipate that a bidder would offer RS valves
customized for buried applications. According to the agency,
standard off-the-shelf RS valves are not suitable for buried
applications due to several concerns. First among these is that
the threaded stem of a RS valve is at least partially outside
the valve body itself, and if buried, would be directly exposed
to dirt and debris that would jam and corrode the mechanism.
Engineer’s Statement of Facts, at 4. Second, RS valves have more
maintenance issues as they require periodic lubrication, which
would be impossible in the case of a buried valve. Id. Third,
due to their rising mechanism, RS valves are greater in height
than NRS valves, which imposes restrictions on their use,
especially where pipelines are to be buried in roads.
Corcel’s customized valves claim to address the major
shortcomings of RS valves in buried uses by equipping the
standard RS valve with custom stem enclosures, sealed
lubrication housings, and a separately manufactured valve box.
However, these customizations do not allay all of the agency’s
concerns about the use of RS valves in buried applications, and
introduce some additional concerns. For example, the agency
remains concerned about the lubrication needs of RS stem valves,
and how those needs would be met once the valves were buried.
Agency Technical Supplement, at 3. In response, Corcel has
referred to its manufacturer’s catalog sheet on “adapto-gear
actuators” which are “fully enclosed light weight, maintenance
free, bevel gear units for valves that require gearing to
facilitate operation.” Comments, at 8; Corcel Supplementary
Response, at 4. Corcel highlights the assurance that these parts
are “maintenance free.” However, this claim relates to the
adapto-gear actuator, an accessory item, and not the RS valves
themselves. See Comments, Tab 12. It is unclear that such an
accessory, for valves that require gearing, would be suitable or
necessary for the valves required under the BOQ. Protest, Tab 3,
at 1. Furthermore, the agency is reasonably concerned that these
customizations and accessories may themselves add an unnecessary
maintenance burden on the PWA, and that the addition of such
customizations and accessories will further exacerbate the
height drawback inherent to RS valves. Agency Technical
Supplement, at 3. Finally, despite Corcel’s customizations,
Corcel is still offering RS valves, which the agency is
reasonably concerned will not be acceptable to the PWA.
Contracting Officer’s Statement of Facts, at 4; Engineer’s
Statement of Facts, Tab D.
In light of the foregoing concerns and the clear statement of
the PWA that only NRS valves are acceptable, we think that the
USAID engineering personnel had a reasonable basis to conclude
that NRS valves were necessary to meet the agency’s needs for
this project. On that basis, and also considering the clear
consensus that a requirement for NRS valves had been intended in
pre-solicitation planning, we conclude that the agency had a
compelling reason to cancel the BOQ B portion of the IFB.
(Corcel Corporation, B-311332;
B-311332.2, June 13, 2008) (pdf)
Although DRG did not submit the lowest bid, the contracting
officer selected DRG for contract award on the basis that it had
submitted the “best responsive bid” and that DRG’s price was
“fair and reasonable.” Id. The contracting officer explained
that her decision that DRG had submitted the “best” bid
reflected her assessment of “the general quality of [DRG’s]
submitted written materials pertaining to [the] solicitation,
accomplishing the scope of work, qualifications, [and]
experience,” along with the fact that DRG’s bid included a cost
breakout identifying the “cost of staff, equipment, supplies and
other needs for this project.” Id. The contracting officer
further noted that the bid submitted by Upper Mohawk, the lowest
priced bidder, “did not contain information about judgment fund
expertise or the staff’s qualifications or experience and no
cost[] break out was submitted.” Id. A contract was awarded to
DRG on August 31. In October, Upper Mohawk filed an agency-level
protest complaining that award to DRG was improper for various
reasons, including the fact that DRG had not submitted the
lowest bid and was not an SDVOSB. AR, Tab 14, Upper Mohawk
Agency-level Protest. Thereafter, the agency concluded that
award to DRG had been improper and, on November 6, terminated
DRG’s contract for the convenience of the government. The agency
plans on resoliciting the requirement after correcting material
errors in the solicitation. On November 9, DRG filed an
agency-level protest; prior to receipt of the agency’s response
to that protest, DRG filed this protest with our Office on
November 22. DRG complains that termination of its contract was
improper for various reasons, including that the agency’s
inclusion of the solicitation clause establishing the
procurement as an SDVOSB set-aside was “inadvertent” and--while
not disputing the fact that it failed to submit the lowest
bid--maintains that termination of its contract 2 months after
award was “arbitrary and capricious.” Contracting agencies
have broad discretion to take corrective action where they
determine that such action is necessary to ensure a fair and
impartial competition. Where the agency has a reasonable concern
that there were material errors in a procurement, it is well
within the agency’s discretion to correct those errors. Alfa
Consult S.A., B-298288, B-298164.2, Aug. 3, 2006, 2006 CPD para.
127 at 2; Patriot Contract Servs., LLC, B-278276.11 et al.,
Sept. 22, 1998, 98-2 CPD para. 77 at 4. Specifically, an agency
may resolicit previously competed requirements where the record
shows the agency’s decision to take this action is made in good
faith. Federal Sec. Sys. Inc., B-281745, Apr. 29, 1999, 99-1 CPD
para. 86 at 5. Here, nothing in the record suggests that
the agency’s corrective action was unreasonable, or that the
agency acted other than in good faith. Specifically, the
contracting officer acknowledges that the solicitation “should
not have contained the language” regarding award to the “best”
bid or, alternatively, that the solicitation should have been
issued as a request for proposals pursuant to the negotiated
procurement procedures of FAR Part 15. Further, there can be no
dispute that the contracting officer’s selection of DRG’s bid
was improperly made on the basis of unstated evaluation factors.
Finally, there is no dispute that DRG is not an SDVOSB and
therefore is not eligible for award under the SDVOSB set-aside.
On this record, we have no basis to question the reasonableness
of the agency’s corrective action to revise the solicitation to
correct errors which led to the improper award to DRG and to
allow all interested parties to compete. (Delaware
Resource Group of Oklahoma, LLC, B-299165, February 26,
2007) (pdf)
The PPR states that an IFB may be cancelled after bid opening
where cancellation is “clearly in the best interest of the
government.” PPR, Chap., XII, sect. 2.1(b). Here, the
contracting officer had two principal reasons for concluding
that the cancellation was in the government’s best interest: the
agency failed to publish the solicitation on FedBizOpps; and the
agency failed to solicit two incumbents. As explained below, we
think the contracting officer’s decision to cancel the
solicitation and, in the resolicitation, to adhere more closely
to the policy guidance in the PPR, was reasonable. The PPR
provides that contracting officers “shall promote and provide
for competition to the maximum extent practicable.” PPR, Chap.
VIII, sect. 3.4(a). Under the PPR, the term “maximum extent
practicable” is defined to mean that “all responsible sources
are permitted to complete.” Id. sect. 3.3. In this case, it
clearly was reasonable for the contracting officer to conclude
that the failure to publish the IFB on FedBizOpps may have
impeded all responsible sources from competing. Compounding that
failure, two incumbent contractors were not sent the IFB, also
contrary to the policy in the PPR to include previously
successful bidders on the bidders list. PPR, Chap. X, sect.
1.1(b)(2). Under these circumstances, it was reasonable for the
contracting officer to conclude that cancellation would serve
the public’s interest in maximizing competition. Kertzman
Contracting, Inc.; Centigrade, Inc.—Entitlement to Costs, supra.
In support of their position that the cancellation lacked a
compelling basis, the protesters argue first that the grounds
cited by the contracting officer reflect GPO policy, not
regulations, and that the agency actions not taken were
optional, not required. We recognize that some provisions of the
PPR describe the procedures to be used in mandatory language,
while other provisions are expressed in terms of a policy to be
followed. These differences in terminology in the PPR are not
dispositive of the propriety of the decision to cancel, however;
rather, it is clear that, as discussed above, the PPR directs
contracting officers to promote and provide for maximum
competition that offers the opportunity for all responsible
sources to compete. As discussed above, the record shows that
the cancellation here was consistent with that responsibility.
The protesters also argue that one of the incumbent contractors
not solicited originally failed to take advantage of the
opportunity to obtain a copy of the solicitation through a bid
subscription service, and that its failure to do so, rather than
the agency’s failure to solicit the firm, was the principal
reason that the incumbent did not receive a copy of the IFB.
This argument does not support the conclusion that the
cancellation was improper. The central issue here is whether the
agency’s failure to publicize the solicitation and to include
two incumbents on the bidders list justifies cancellation of the
solicitation in furtherance of the government’s interest in
maximizing competition. As explained above, we conclude that it
does. We therefore see no basis to question the contracting
officer’s decision to cancel the IFB. (Goodway
Graphics of Virginia, Inc.; NPC, Inc.; P.A. Hutchison Co.,
B-297789, March 21, 2006) (pdf)
After reviewing the bids, the contracting officer decided that
it was appropriate to cancel the IFB for three reasons.
-
First, it was not clear whether bidders were obligated to
enter bids for all the unit price items in the attachment. As
quoted above, the agency, in response to a bidder's question
on this issue, stated that bidders could offer different unit
prices if they deemed them "applicable." In contrast, Section
10 of the SF stated that bidders were to "furnish all
labor, material, equipment and supervision for the demolition,
abatement and chilled water by-pass" for the building.
(Emphasis added.) In fact, three of the eight bidders,
including the protestor, did not enter unit prices for all the
types of materials specified. The contracting officer
determined that the price evaluation method called for by the
IFB, which added all of the unit prices to arrive at a grand
total, did not adequately account for those bids which did not
include unit prices for all material types, and therefore
provided those bidders a possible price advantage.
-
Second, the estimated quantity of work for some types of
abatement services was substantially overstated due to the way
in which the attachment was laid out. For example, the
estimated quantity of work for each of the three types of pipe
insulation abatement was given as 100, for a total of 300 for
all three types, although the actual estimated quantity was
100 for the three types combined. Similar overstatements
occurred throughout the attachment. Although each of the
bidders was using the same incorrect information, the
contracting officer reasoned that the overstated quantities
may have produced inaccurate pricing, because bidders' unit
pricing would presumably be lower for larger quantities of
work.
-
Finally, the attachment was intended to request pricing
information for abatement services at various locations within
the building, and the form contained blank spaces for three
types of removal which were up to the bidder to define. For
example, as set out above, under the category "pipe
insulation," the attachment asked bidders to "identify [three]
types of material or removal method[s] having different unit
costs." Some bidders responded by bidding on different
diameter pipes, while others selected different asbestos
containment methods. Even bidders who chose to bid on three
different pipe diameters did not all choose the same ones.
Consequently, the individual unit prices varied significantly
among the bidders. For instance, the average low bid for the
three types under pipe insulation was $3.10, and the average
high bid was $16.83, a difference of over 400 percent. See
Protest, Exhibit B. Because GSA had not defined the unit
items, but rather left their definition to bidders'
discretion, the contracting officer determined that the unit
prices provided by each bidder could not reasonably be
compared to one another.
We find that the GSA properly
canceled the IFB here because it contained numerous ambiguities,
as a result of which bidders did not prepare their bids based on
a common understanding of the agency's requirements, and prices
could not be compared on an equal basis. The ambiguities misled
bidders as to the requirement to enter prices for all the unit
price items listed, producing lower total bids for the three
bidders who did not bid on each of the unit prices. Further,
even if every bidder had entered prices for each unit price
item, because, in completing the attachment, the IFB left to the
bidders' discretion the nature of the work that each bid, the
resulting total price for the unit work provided by each of the
bidders did not afford the agency a basis on which to accurately
compare the bid prices. In addition, as explained above, the way
in which the estimated quantities were listed in the attachment
was misleading and resulted in a substantial overstatement of
the estimates, which in turn likely materially affected the
bidders' prices. The record thus shows that the lack of clarity
in the attachment resulted in bidders competing on an unequal
basis, such that any award based on this IFB would be
prejudicial to the remaining bidders and the government. This
provides the agency with a compelling reason to cancel the IFB.
Neals Janitorial Serv. , B-276625, July 3, 1997, 97-2 CPD
paragraph 6 at 5. (Dynamic Corporation,
B-296366, June 29, 2005) (pdf)
A contracting agency has the right to cancel a solicitation when
sufficient funds are not available regardless of any disputes
concerning the validity of the IGE, National Projects, Inc.,
B-283887, Jan. 19, 2000, 2000 CPD ¶ 16 at 4; J. Morris &
Assocs., Inc., B-256840, July 27, 1994, 94-2 CPD ¶ 47 at 2 n.1,
as agencies cannot create obligations that exceed available
funds. Further, the VA is precluded by law from obligating or
expending funds in excess of $4 million total for any medical
facility project without express Congressional approval. See 38
U.S.C. §§ 8101 et seq. (2000). Since the VA previously had
obligated $366,228 for the design aspect of the project here,
the contracting officer could not have made contract award to
First Enterprise after the withdrawal of Ace's bid, even if it
had sought to obtain additional funds. Accordingly, the VA's
decision to cancel the IFB after determining that all bids not
withdrawn exceeded available funding was proper. (First
Enterprise, B-292967, January 7, 2004) (pdf)
A contracting agency must have a compelling reason to cancel an
IFB after bid opening because of the potential adverse impact on
the competitive bidding system of resolicitation after bid
prices have been exposed. FAR § 14.404-1(a)(1); HDL Research
Lab, Inc., B-254863.3, May 9, 1994, 94-1 CPD ¶ 298 at 5. Where a
solicitation contains inadequate or ambiguous specifications, or
otherwise does not contain specifications that reflect the
agency's actual needs, the agency has sufficient reason to
cancel. FAR § 14.404-1(c)(1); Days Inn Marina, B-254913, Jan.
18, 1994, 94-1 CPD ¶ 23 at 2. Contracting officials have broad
discretion to determine whether a compelling reason to cancel
exists, and our review is limited to considering the
reasonableness of their decision. Chenega Mgmt., LLC, B-290598,
Aug. 8, 2002, 2002 CPD ¶ 143 at 2. Our review of the record here
shows that the FHWA reasonably concluded that it had a
compelling reason to cancel the solicitation because it both
included ambiguous specifications and failed to reflect the
agency's actual needs. (Brickwood
Contractors, Inc., B-292171, June 3, 2003) (pdf)
Here, we find that the Army reasonably concluded that it had a
compelling reason to cancel the IFB after bid opening. The IFB
contained conflicting terms with respect to the contract
performance period, which is a material solicitation
requirement. See The Ryan Co., B-275304, Feb. 6, 1997, 97-1 CPD
¶ 62 at 3 n.1. The bid schedule stated that the performance
period would expire January 31, 2003 (which was only 3 months
after the October 23 bid opening date), but the IFB stated in
other clauses that the period of performance would be 12 months
from the date of award. The IFB also incorporated by reference
the standard “Order of Precedence--Sealed Bidding” clause, FAR §
52-214-29, which provides that solicitation inconsistency are to
be resolved by giving precedence in the following order: (1) bid
schedule; (2) representations and instructions; (3) contract
clauses; (4) other documents, exhibits and attachments; and (5)
specifications. Application of the Order of Precedence clause
indicates that, as argued by the Army, any contract awarded
under the IFB would have expired on January 31, 2003. (Paragon Van Lines,
Inc, B-291820.2; B-291913, April 8, 2003)
We conclude that MARAD reasonably
determined that the bunkering requirement could not be met as it
intended--by barge, within a 4-hour transit time to the layberth-and,
therefore, that the agency had a compelling reason to cancel the
IFB. See Champion Structure Co., B?198863, Oct. 17, 1980,
80-2 CPD ¶ 291 at 2 (cancellation proper where award would
result in a contract impossible to perform). (Chenega
Management, LLC, B-290598, August 8, 2002) (pdf)
Where prior to issuing a
solicitation on an unrestricted basis, an agency fails to
investigate whether the conditions requisite to a set-aside
under the JWOD Act or for a category of small business may be
expected, cancellation is clearly in the public interest if the
agency subsequently determines that the solicitation should have
been set aside. Ryon, Inc., B-256752.2, Oct. 27, 1994, 94-2 CPD
para. 163 at 4 (cancellation even after bid opening was proper
where agency erroneously determined initially not to set
procurement aside for small business). (Diversified
Management Group, A Joint Venture, B-288443.2, October 12,
2001)
Upon learning that the IFB should
have incorporated FAR sect. 52.219-14, requiring the contractor
to perform at least 15 percent of the cost of the contract with
its own employees, rather than FAR sect. 52.236-1 as completed
by the Corps, requiring the contractor to perform 60 percent of
the total amount of work with its own organization, the
contracting officer determined that the IFB should be canceled.
Here, the record shows that at
least one potential bidder was dissuaded from submitting a bid
in response to the solicitation by the requirement that the
contractor perform at least 60 percent of the work with its own
organization, [3] and we think that the agency could reasonably
have surmised that other prospective bidders were likewise
dissuaded, given that more than 50 contractors requested plans
and specifications for the solicitation, but only 3 submitted
bids. Agency Report, Apr. 21, 2000, at 7. Under such
circumstances, we think that the agency reasonably determined
that resolicitation would result in enhanced competition and,
accordingly, that cancellation was in the public's interest.
(Hroma
Corporation, B-285053, June 6, 2000)
Even if the government estimate
is adjusted upward to $3.9 million or $4.3 million as asserted
by the protester, Overstreet's bid is still 18 percent to 8.6
percent higher than the government estimate. Since a contracting
officer may reject a bid as unreasonably priced when the bid
exceeds the government estimate by as little at 7.2 percent, we
see no basis to object to the contracting officer's
determination of price unreasonableness. See Atkinson Dredging
Co. Inc.--Recon., supra, at 2; Building Maintenance Specialists,
Inc., B-186441, Sept. 10, 1976, 76-2 CPD para. 233 at 4. (Overstreet
Electric Company, Inc., B-284691, May 12, 2000)
A contracting agency has the
right to cancel a solicitation when sufficient funds are not
available, regardless of any disputes concerning the validity of
the IGE or the reasonableness of the low responsive bid price.
J. Morris & Assocs., Inc., B-256840, July 27, 1994, 94-2 CPD
para. 47 at 2 n.1; Armed Forces Sports Officials, Inc.,
B-251409, Mar. 23, 1993, 93-1 CPD para. 261 at 2-3, recon.
denied, B-251409.2, May 24, 1993, 93-1 CPD para. 402. We
therefore conclude that the agency had a compelling reason to
reject all bids and to cancel the solicitation. (National
Projects, Inc., B-283887, January 19, 2000)
We have long held that, where a
solicitation's quantity estimates are found to be erroneous, it
is generally improper for the contracting agency to reevaluate
existing bids based on corrected estimates that are
substantially different from those that formed the basis of the
bidders' competition. See, e.g., Edward B. Friel, Inc.,
B-183381, Sept. 22, 1975, 75-2 CPD para. 164 at 10. Here, the
error in the quantity estimate for item No. 35 is so large that
there is no way to predict the impact that correcting it may
have on the prices bid for that or other items being procured.
Accordingly, instead of making an award in these circumstances,
the agency should have resolicited the procurement on the basis
of its best estimate of its actual requirements. While we
recognize the potential adverse impact on the competitive
bidding system of resoliciting after prices have been exposed,
here a compelling reason for doing so exists, since the IFB
substantially overstates the anticipated needs of the
government. See Deere & Co., B-241413.2, Mar. 1, 1991, 91-1
CPD para. 231 at 2. (Mallinckrodt
Inc., B-282902, September 10, 1999)
The agency canceled the IFB only
after it determined that both Poerio's and Massaro's varying
interpretations of the IFB's pricing terms were reasonable.
Since we have determined that Massaro's interpretation was not
reasonable, and that the IFB was not ambiguous, we conclude that
the VA did not have a compelling reason to cancel the IFB after
bids had been exposed. (Massaro
Company; Poerio Inc., B-280772.2; B-280772.3, December 4,
1998)
|