On or before the September 9 closing date, bids were
submitted by various offerors, including [CI Filing
Systems, LLC] CFS and its sister corporation, IFS Filing
Systems LLC (IFS). Thereafter, GPO determined that CFS’s
affiliate was the low bidder and, on September 16, issued
a purchase order to IFS. Protest, exh. E, Timeline
for Jacket 386-060, at 5. On October 8, IFS
delivered pre‑production samples of the folders that
included fasteners which IFS described as “Permclip bonded
fastener[s].” Protest, exh. E, Letter from HoganWillig
(Counsel for both IFS and CFS) to GPO Contracting Officer,
Oct. 15, 2014, at 1.
(sections deleted)
On December 10, the contracting
officer issued a final decision terminating IFS’s contract
for default. Agency Report (AR), Feb. 4, 2015, at 2;
Protester’s Comments on Agency Report, Tab 1, Request for
Inspector General Investigation, at 5.
On December 11, the contracting
officer determined that CFS was the next low bidder and,
accordingly, sent CFS an email seeking confirmation that
the bid it previously submitted was still valid. AR, Tab
3, Email from GPO Contracting Officer to CFS’s Chief
Executive Officer (CEO), Dec. 11, 2014. Additionally,
because the contracting officer noted that CFS’s bid was
nearly identical to IFS’s bid, he also asked CFS: “[C]an
you give me information about the fastener that will be
used in the folder?” Id.
(sections deleted)
On December 30, the contracting
officer advised CFS that, based on CFS’s unwillingness to
substantively respond to the contracting officer’s
requests, along with the fact that CFS’s bid was nearly
identical to the bid submitted by IFS (which had led to
termination for default of IFS’s contract), CFS’s bid was
considered nonresponsive to the solicitation requirements
regarding embedded fasteners. AR, Tab 5, Letter from GPO
Contracting Officer to CFS CEO, Dec. 30, 2014. This
protest followed.
(sections deleted)
As discussed above, the contracting
officer had inspected the pre-production samples of the
Permclip fasteners that were submitted by CFS’s sister
corporation before reaching a conclusion that the
fasteners were not embedded in the file folders. Further,
the agency declined to accept a proposed modification of
the contract that would have changed the requirements in
this regard, opting instead to terminate the prior
contract for non-compliance with the solicitation
requirements. Finally, the manufacturer of the fastener,
Permclip, used the term “adhesive” in describing the
fasteners on its website. See Protest, exh. E, Letter from
HoganWillig to GPO, Nov. 10, 2014, at 5. The fact that the
description of the fasteners was subsequently altered to
reflect language more consistent with the terms of the
solicitation does not provide a basis for concluding that
the contracting officer’s determination was unreasonable.
In short, the record reasonably supports the agency’s
determination that CFS’s bid to provide Permclip fasteners
failed to comply with the solicitation requirements for
embedded fasteners--just as IFS’s bid for the same product
had done--and, accordingly, was nonresponsive. Neither the
fact that CFS disagrees, nor the additional information
and arguments that CFS has provided, persuade this Office
that the agency unreasonably determined that the Permclip
fasteners fail to comply with the solicitation requirement
for embedded fasteners. See, e.g., AT&T Corp., B-299542.3,
B-299542.4, Nov. 16, 2007, 2008 CPD ¶ 65 at 19. (CI
Filing Systems, LLC B-411012: Apr 17, 2015). (pdf)
Bidders were informed that performance of the work must
begin within 10 calendar days and be completed within 245
calendar days after receiving notice to proceed. IFB at 1.
The IFB also stated that if funding was available at the
time of award the agency may make award for both Schedule
A and Schedule B at that time; but that if funding for
Schedule B was received after award, the agency had the
right to exercise its option for the Schedule B work not
later than 120 calendar days after the notice to proceed
for Schedule A. Bid Schedule Instructions at 1. In this
regard, the IFB provided that if Schedule B was not part
of the original contract award, but was exercised later,
overall contract performance must still be completed
within 245 calendar days of notice to proceed. IFB at B-8.
(sections deleted)
To be responsive, a bid must show on
its face at the time of bid opening that it is an
unqualified offer to comply with all material requirements
of the solicitation, and that the bidder intends to be
bound by the government’s terms as set forth in the
solicitation. Sundt Corp., B-274203, Nov. 5, 1996, 96-2
CPD ¶ 171 at 2. The performance schedule is a material
requirement. Northwest Pesticide Enterps., Inc., B-235982,
Sept. 28, 1989, 89-2 CPD ¶ 284 at 2. A bid, which takes
exception to a material IFB requirement or is ambiguous
with respect to whether the bid represents an offer to
comply with a material requirement, may not be changed or
clarified after bid opening and must be rejected as
nonresponsive. Marco Equip., Inc.; Scientific Supply Co.,
B-241329, B-241329.2, Jan. 31, 1991, 91-1 CPD ¶ 107 at 3.
This is to ensure that all bidders compete on an equal
basis, with no advantage being given to any bidder over
another, and thus to ensure the integrity of the
competitive bidding system. Id.
Here, the record shows that, at best, the protester’s bid
was ambiguous with respect to whether Valley Quarries had
unequivocally promised to complete contract performance
within the time required. Although it is true that the
calculation of contract administrative costs was for
evaluation purposes only, this calculation was to be based
upon the bidders’ estimated number of days to complete the
contract work. By specifying 280 calendars days for this
calculation, Valley Quarries called into question its
commitment to perform the contract work within 245
calendar days as required. In this regard, the Bid Summary
stated, directly above the space provided for the bidders’
estimated calendar days for calculating the contract
administrative costs, that “[t]he total calendar days
bid to complete all contract work must be greater than or
equal to (≥) 120 and less than or equal to (≤) 245.”
IFB at B-8 (emphasis in original). Although Valley
Quarries argues that it intends to perform the contract
work within 245 calendar days, it is well settled that
when determining the responsiveness of a bid, the
controlling factor is not whether the bidder intends to be
bound, but whether this intention is apparent from the bid
as submitted. Balongas, S.A., B-215153, July 23, 1984,
84-2 CPD ¶ 86 at 2. (Valley
Quarries, Inc., B-409859: Aug 13, 2014) (pdf)
HPC argues that the bid
submitted by BES Design/Build, LLC was nonresponsive, and
should have been rejected because it did not provide a
price for both line item 1 and the alternate line item 2.
Protest at 10. The VA argues that it correctly concluded
that the bid from BES Design/Build, LLC was not defective
because the failure to submit a price for an alternative
line item that the agency does not award does not render a
bid nonresponsive. AR at 5.
This Office recently considered essentially this same
situation, and held that a bidder’s failure to bid on an
alternate item that was not selected for award does not,
in itself, render the bid nonresponsive. Povolny Group,
B-407570, Jan. 9, 2013, 2013 CPD ¶ 26 at 3. Where a
solicitation includes a base bid and alternatives, bids
must be evaluated on the basis of work actually awarded.
See, e.g., Niemela Constr. Co., B-237616, Feb. 7, 1990,
90-1 CPD ¶ 161 at 2. Failure of a bidder to offer a price
for all alternates will constitute a basis for rejection
only if evaluation and award includes the items not bid.
This is true even where the IFB states that failure to bid
on every item will cause rejection of the bid as
nonresponsive. Haskins Co., B-227898, Sept. 21, 1987, 87-2
CPD ¶ 285 at 2.
Here, the bid submitted by BES Design/Build, LLC
unequivocally offered to perform the base requirement,
which is what the VA actually awarded.[2] Accordingly the
bid was responsive, and provided a proper basis for the
award of a contract. (Hamilton
Pacific Chamberlain, LLC, B-409208.2: Apr 3, 2014)
(pdf)
C&D argues that RUSH’s bid should have
been rejected because the discrepancies in its bid schedule
represent a non-responsive bid. Protest at 2. More specifically,
C&D argues that RUSH’s original bid did not commit the firm to
complying with Note 9 in performing the east wall fender
installation. Protester’s Comments at 2; Protester Response to
Intervenor’s Reply at 2. In response to an inquiry from our
Office to all parties about the significance of both pages of
RUSH’s schedule referring to the west wall base requirement, C&D
argues that this fact also rendered RUSH’s bid ambiguous and
unacceptable. Protester’s Response to GAO Questions, Feb. 4,
2014, at 2-3.
The Corps and RUSH argue that the agency properly waived the
discrepancies in RUSH’s bid schedule, both because the bid did
not reflect material variations from the IFB requirement, and
because despite the discrepancies in the second page of the bid
schedule, the page included the appropriate lines and
quantities, and thus displayed RUSH’s intention to offer a bid
for each of the option contract line items. Intervenor’s Reply
Brief at 2; Intervenor’s Response to GAO Questions, Feb. 4,
2014, at 2-3; Agency’s Response to GAO Questions, Feb. 4, 2014,
at 2-4.
As explained below, we agree with C&D that RUSH’s bid schedule
differed materially from the terms of the IFB. As a result, the
discrepancies in RUSH’s bid schedule could not be waived;
rather, the contracting officer should have rejected RUSH’s bid
as nonresponsive.
A bid that fails to include a price for every item required by
the IFB generally must be rejected as nonresponsive. HH&K
Builders, B-232140, Oct. 20, 1988, 88-2 CPD ¶ 379 at 2, recon.
denied, B-232140.2, Nov. 30, 1988, 88-2 CPD ¶ 537. This includes
a bidder’s failure to provide a responsive bid for optional
contract line items, which thus renders the entire bid
nonresponsive. Massillon Constr. & Supply, Inc., B‑407931, Mar.
28, 2013, 2013 CPD ¶ 85 at 3. This rule reflects the legal
principle that a bidder who has failed to submit a price for an
item generally cannot be said to be obligated to furnish that
item. United Food Servs., B‑218228.3, Dec. 30, 1985, 85‑2 CPD ¶
727 at 3. Therefore, where a page in a bidder’s schedule does
not clearly indicate that the prices apply to an option that the
IFB requires to be priced, the bid is ambiguous and thus,
nonresponsive. Thompson Metal Fab, Inc., B‑293647, May 4, 2004,
2004 CPD ¶ 109 at 3.
The discrepancies in RUSH’s bid here were not a mere minor
informality. Both pages of RUSH’s bid schedule identified the
scope of work being bid as the west wall; neither identified any
prices as applying to the east wall. The second page of the
schedule, which should have contained prices for the east wall
work identified Note 9 (the west wall fender installation note)
as applicable, rather than Note 6 (which, as revised by
Amendment 5, required the reuse of fender material). As a
result, at the time of bid opening, RUSH had not made a firm
commitment to perform the east wall scope of work at specific
line item prices.
Although the contracting officer identified misnumbering on the
second page of RUSH’s bid schedule, and expressed her view that
such a discrepancy could be waived as a minor informality, she
did not identify the fact that RUSH’s bid also referred only to
the west wall base requirement, and referenced only Note 9 for
fender installation. Since these discrepancies reflected
material differences in the work and the manner of its
performance, they could not be waived--even if the contracting
officer had identified them. In short, the contracting officer
improperly allowed RUSH to correct its nonresponsive bid.
The protest is sustained.
RECOMMENDATION
We recommend that the Corps revoke the waiver of the
discrepancies in RUSH’s bid, reject RUSH’s bid as nonresponsive,
and terminate the contract for the convenience of the
government. We recommend that the Corps identify the next
lowest-priced responsive responsible bidder, and make award to
that firm, if otherwise proper. We also recommend that C&D be
reimbursed the costs of filing and pursuing its protest,
including reasonable attorneys’ fees. Bid Protest Regulations, 4
C.F.R. § 21.8(d)(1) (2013). The protester should submit its
certified claim for such costs, detailing the time expended and
the costs incurred, directly to the contracting agency within 60
days after receipt of this decision. (C&D
Construction, Inc., B-408930.2: Feb 14, 2014) (pdf)
While the IFB
required bidders to submit prices for each CLIN in order to be
eligible for award, IFB at 1, MCSI failed to submit a separate,
lump sum price for the Schedule D CLIN. MCSI, however, asserts
that the agency nevertheless should have found its bid
responsive because it acknowledged IFB amend. 0001 and included
the price for the Schedule D work as part of the testing CLIN
under Schedule A.
We disagree. Rather, we find that the agency properly determined
MCSI’s bid to be nonresponsive because of the failure to submit
a separate bid for the optional Schedule D work. To be
responsive, a bid must constitute an unequivocal offer to
perform the exact thing called for in the solicitation, such
that acceptance of the bid will bind the contractor in
accordance with the material terms and conditions of the
solicitation. Custom Envtl. Serv., Inc., B-234774, May 24, 1989,
89-1 CPD ¶ 501 at 3. While MCSI acknowledged the amendment
providing for Schedule D, the mere acknowledgement of an
amendment, without a specific price, is not sufficient to
constitute a bid for the additional quantity of work since doubt
exists as to the amount of the bid and the bidder’s obligation
to perform the increased work. See J.D. Bertolini Indus., Ltd.,
B-231598, Sept. 14, 1988, 88-2 CPD ¶ 245 at 3; Larry’s Inc.,
B-230822, June 22, 1988, 88-1 CPD ¶ 599 at 2. Further, MCSI’s
post-bid opening explanation that its price was included within
another CLIN under Schedule A is unavailing since nothing in
MCSI’s bid established the likely price for Schedule D. See,
e.g., United Food Servs., Inc., B-218228.2, Dec. 30, 1985, 85-2
CPD ¶ 727 at 3 (correction of omitted price may be allowed where
there is a consistent pattern of pricing within the bid itself
establishing both the error and the intended price). In this
regard, each testing CLIN called for specific work to be
accomplished under the relevant Schedules A, C, and D. IFB, as
amended, § 154 at J-20. MCSI’s mere inclusion of a total price
under Schedule A, with the annotation “Amendment 001,” while
allegedly covering both Schedules A and D testing work, provided
neither an assurance that the firm had agreed to perform the
specific Schedule D requirements nor any indication of the cost
of that work. Furthermore, MCSI’s non-responsive bid cannot be
made responsive by explanations after bid opening since doing so
would effectively allow the bidder to elect whether to accept or
reject the additional work. Larry’s Inc., supra.
MCSI nevertheless asserts that its omitted price is a minor
informality or immaterial defect, and thus that the agency
should waive the omission or allow its correction. Federal
Acquisition Regulation § 14.405; W.B. Constr. and Sons, Inc.,
B-405818, B-405818.2, Jan. 4, 2012, 2012 CPD ¶ 17 at 4. A defect
or variation is immaterial if the effect on price, quantity,
quality, or delivery is negligible when contrasted with the
total cost or scope of the services being acquired. Id. Thus, a
contracting agency may waive the failure to bid on an item as a
minor informality if the item for which the price is omitted is
divisible from the solicitation’s overall requirements, de
minimis as to total cost, and would not affect the competitive
standing of the bidders. W.B. Constr. and Sons, Inc., supra; E.
H. Morrill Co., B-214556, May 3, 1984, 84-1 CPD ¶ 508 at 3.
Here, the record shows that one of the prerequisites for waiver
of the omission is not met inasmuch as the Schedule D work is
not logically divisible. Although priced as an option, the
agency considers the Schedule D intelligent compaction work to
be an essential, integral part of the overall contract, intended
to accelerate project delivery and improve pavement performance,
and which will be ordered as soon as funding becomes available.
Supplemental Agency Report (SAR) at 2. The agency explains that,
since the intelligent compaction work involves sampling,
testing, and compaction support activities to be performed on a
portion of the road in conjunction with the asphalt laying work,
it would not be practical to have two contractors--one
performing intelligent compaction and the other laying
asphalt--separately accomplish the required work. Second SAR at
1-2; see E. H. Morrill Co., supra (need to have contractor
responsible for additional (omitted) excavation work which
represented material part of overall contract requirements); cf.
Leslie & Elliott Co., B-216676, Feb. 19, 1985, 85-1 CPD ¶ 212 at
3; aff’d Ryan Elec. Co.--Recon., B-218246.2, Apr. 1, 1985, 85-1
CPD ¶ 366 (unpriced, potential work considered divisible where
no need for same contractor to perform it as well as remaining
work). For example, according to the agency, if the asphalt was
not properly compacted, the paving contractor could be required
to remove the asphalt it put down and would not be paid until
the problem was corrected. This in turn could potentially lead
to claims against the agency by the paving contractor. Second
SAR at 1-2.
While MCSI asserts that the agency could easily contract for the
Schedule D intelligent compaction testing with the paving
contractor used by the protester (and apparently other bidders),
the government would not be required to do so. Thus, we see no
basis to question the agency’s determination that the Schedule D
work is not, as a practical matter, divisible from the other
aspects of the contract. Accordingly, MCSI’s failure to include
a price for Schedule D cannot be waived and the agency thus
properly rejected the firm’s bid as nonresponsive. (Massillon
Construction and Supply, Inc., B-407931, Mar 28, 2013)
(pdf)
Povolny complains
that RPreusser’s bid is nonresponsive, because the awardee did
not provide a bid price for the alternate bid item.
Where a solicitation includes a base bid and alternatives, bids
must be evaluated on the basis of work actually awarded. Niemela
Constr. Co., B-237616, Feb. 7, 1990, 90-1 CPD ¶ 161 at 2; The
Haskins Co., B-227898, Sept. 21, 1987, 87-2 CPD ¶ 285 at 2;
recon. denied, Cree Constr. Co., Inc., B-227898.3, Oct. 26,
1987, 87-2 CPD ¶ 394 at 2. As a result, we have held that the
failure of a bidder to provide a price for all alternates
constitutes no basis, sufficient in itself, to require rejection
of the bid. Casson Constr. Co., Inc., B-198746, Oct. 24, 1980,
80-2 CPD ¶ 318 at 5. Failure of a bidder to offer a price for
all alternates will constitute a basis for rejection only if
evaluation and award includes the items not bid, and this is
true even where the IFB states that failure to bid on every item
will cause rejection of the bid as nonresponsive. The Haskins
Co., supra.
Since RPreusser unequivocally offered to perform the work
actually awarded, i.e., the basic bid item, its bid is
responsive and properly may be considered for award. Casson
Constr. Co., Inc., supra.
The protest is denied. (The
Povolny Group, B-407570, Jan 9, 2013) (pdf)
As an initial
matter, 4Granite maintains that the references to the commercial
items clauses in its bid was an “inadvertent error” and, as a
consequence, they should not have been construed as imposing
additional conditions or obligations in conflict with the terms
established by the solicitation. Protest at 2. 4Granite also
argues that the document at issue was not required by the
solicitation, the contracting officer could have overlooked its
contents, and that it should have been permitted to delete the
references to the clauses set forth in the document because any
differences between the referenced clauses and the
solicitation’s clauses are immaterial. For the reasons discussed
below, we find that the agency properly rejected 4Granite’s bid
as nonresponsive.
To be responsive, and considered for award, a bid must contain
an unequivocal offer to perform, without exception, the exact
thing called for in the solicitation so that, upon acceptance,
the contractor will be bound to perform in accordance with all
of the solicitation’s material terms and conditions. Oregon
Electric Constr., Inc. dba Integrated Systems Group, B-294279,
Sept. 27, 2004, 2004 CPD ¶ 188 at 2. If, in its bid, a bidder
imposes conditions or modifies a material solicitation
requirement, limits its liability to the government, or limits
the rights of the government under a resulting contract, then
the bid must be rejected as nonresponsive. Id.; FAR §
14.404-2(d). A bidder’s intention to be bound by the
solicitation requirements must be determined from the bid itself
at the time of bid opening. See Franklin Instrument Co., Inc.,
B-204311, Feb. 8, 1982, 82-1 CPD ¶ 105 at 2.
Here, the contracting officer could not overlook the document
4Granite included in its bid. Any extraneous documents submitted
with a bid must be considered a part of the bid for purposes of
determining the bid’s responsiveness. Washington Printing
Supplies Inc., B-227048, July 10, 1987, 87-2 CPD ¶ 34 at 3. The
face of the document at issue indicates that 4Granite understood
the commercial items clauses as applying to this solicitation.
Specifically, 4Granite represented that the clause at FAR §
52.212-3, Representations and Certification-Commercial Items,
was “applicable to this solicitation,” and referenced the clause
at FAR § 52.212-1, Instructions to Offerors-Commercial Items,
when indicating it was in complete agreement with all terms and
conditions included in this solicitation. These statements,
coupled with 4Granite’s subsequent indication that it had “read
and understood” two particular commercial items clauses and “all
other” FAR and DFAR clauses “incorporated by reference in this
solicitation” rendered its bid, at best, ambiguous as to whether
it was agreeing to the terms and conditions of the commercial
items clauses or to the terms and conditions set forth in the
solicitation.
Moreover, we agree with the agency that the ambiguity created by
4Granite’s references to the commercial items clauses concerned
material terms of the firm’s bid since they implicate matters
such as the contractual terms of the warranty. See Bailey
Controls Co.; The Foxboro Co., B-256189, B-256189.2, May 23,
1994, 94-1 CPD ¶ 320 at 4 (establishing that warranty provisions
are material terms of a contract since they affect the legal
obligations of the contracting parties). In this regard, the
reference in 4Granite’s bid to FAR § 52.212-4, Contract Terms
and Conditions--Commercial Items, invoked the standard
commercial item warranty, which merely provides that a
contractor “warrants and implies that the items delivered
hereunder are merchantable and fit for use for the particular
purpose described in this contract.” In contrast, the warranty
provision set forth in the solicitation, FAR § 52.246-21,
Warranty of Construction, establishes fundamentally different
legal obligations concerning the length of the warranty, the
contractor’s obligation to remedy defects and at whose expense,
the contractor’s obligation to enforce warranties for the
benefit of the government, and the government’s rights in the
event of a contractor’s failure to fulfill its obligations. It
is well settled that where a bidder introduces ambiguity in its
bid regarding material terms, such as the case here, the bid
must be rejected as nonresponsive. Washington Printing Supplies
Inc., supra.
Although 4Granite now maintains that it unintentionally included
this document, and meant to agree to all the terms and
conditions in the solicitation, no such statement of this intent
was attached to the bid at the time of its submission. This
document and its contents were submitted along with the bid and
must be considered part of the bid, as noted above, for purposes
of determining responsiveness. Since only material available at
bid opening may be considered in making a responsiveness
determination, 4Granite’s protest statements concerning its
intent cannot be considered in determining the responsiveness of
its bid. HBH, Inc., B-225126, Feb. 26, 1987, 87-1 CPD ¶ 222 at
2. Bidders bear the primary responsibility for properly
preparing bid documents in such a fashion that the contracting
agency can accept the bid with full confidence that an
enforceable contract, conforming to all the requirements of the
IFB, will result. See The Scotsman Group, Inc., B-245634, Jan.
13, 1992, 92-1 CPD ¶ 57 at 3. The protester failed to do so
here. (4Granite Inc.,
B-406459, Apr 2, 2012) (pdf)
VCG protests the
VA's rejection of its bid and alternate bid. Specifically, VCG
argues that its bid for the Trane chiller met the requirements
and specifications of the IFB. Comments at 1-2. In the
alternative, VCG argues that the VA should have accepted its
alternate bid for the York chiller as the low bid for the
project. Protest at 2.
The agency argues that the IFB called for a specific "brand name
refrigerant" to be used, and VCG's bid "failed to meet the
criteria" in the IFB. Supp. AR at 1. Additionally, the agency
asserts that the protester's bid and alternate bid "created two
quoted prices" which resulted in the protester's bid being
"contradictory" and nonresponsive. Id. at 1, 5.
To be responsive, a bid must show on its face at the time of bid
opening that it is an unqualified offer to comply with all
material requirements of the solicitation, and that the bidder
intends to be bound by the government's terms as set forth in
the solicitation. Sundt Corp., B-274203, Nov. 5, 1996, 96-2 CPD
¶ 171 at 2. A bidder's intention must be determined at the time
of bid opening from all the bid documents, which include any
extraneous documents submitted with the bid, since such
materials are part of the bid for purposes of determining
responsiveness. M&G Servs., Inc., B-244531, June 27, 1991, 91-1
CPD ¶ 612 at 1-2.
As an initial matter, we first address whether the agency should
have considered VCG's alternate bid for the York chiller. We
conclude that it was reasonable for the VA to reject the
alternate bid. In this regard, the IFB included a FAR clause
stating that the agency would not consider alternate bids unless
the IFB authorized their submission. AR, Tab 17, IFB at 12; see
FAR § 52.214-18. The letter that VCG submitted with its bid
package clearly indicated the firm was submitting an "alternate
bid proposal" of the York model chiller at a higher price.
Protest, encl. 2, VCG Bid Letter, at 1. Since the IFB here did
not authorize the submission of alternate bids, the VA's
decision to reject VCG's alternate bid for the York chiller is
unobjectionable.
Next, we turn to VCG's contention that the VA improperly
rejected its bid for the Trane chiller and the R-123 refrigerant
as not meeting the specifications in the IFB. The record is
remarkably absent of any rationale to support the agency's
arguments in this regard. The contemporaneous record contends
vaguely that cut sheets for the Trane chiller were
"questionable" and that the R-123 refrigerant associated with
the Trane chiller did not meet the specifications of the IFB,
without any explanation of what was questionable or what
specifications were not met. During the development of the
protest, we sought explanation from the agency, and the agency
merely repeated that the bid was "lacking and thus,
nonresponsive" and "failed to meet the criteria established by
the agency in its IFB." Contracting Officer's Statement at 2;
Supp. AR at 1. Despite multiple opportunities, the agency has
not explained why VCG's proposal failed to meet the IFB's
requirements, which of the 384 pages of specifications and
drawings were not met, or what in the 14 pages of documentation
describing the chiller model VCG included in its bid was
questionable. Without support for its conclusions, we cannot
find that the agency acted reasonably in rejecting VCG's bid.
Moreover, to the extent the agency argues that the IFB's
specifications required a particular brand name chiller or
refrigerant, the record does not support that assertion. The
specifications identified three manufacturers that offered
products that "may be" used in the project, but the IFB did not
restrict bidders to these brands exclusively. See AR, Tab 6,
Specifications, at 23 64 00-4. Similarly, the IFB refers both to
the use of HFC-134a refrigerant and R-123 refrigerant, and it
did not restrict bidders to a particular type. We therefore find
the agency's rejection of VCG's bid on the basis that the bid
was not for a specified chiller and refrigerant to be
inconsistent with the solicitation.
We recommend, consistent with this decision, that the VA
reconsider VCG's bid for the Trane chiller to determine if it
satisfies the specifications of the IFB. We further recommend
that the agency reimburse the protester the costs of filing and
pursuing its protest, including reasonable attorneys' fees. 4
C.F.R. § 21.8(d)(1) (2012). The protester's certified claim for
costs, detailing the time spent and the cost incurred, must be
filed to the agency within 60 days after receiving this
decision. 4 C.F.R. § 21.8(f)(1).
The protest is sustained. (Veterans
Contracting Group, Inc., B-405940, Jan 12, 2012) (pdf)
ATR does not
dispute that it failed to provide a price breakdown for
providing mail services to Bryan Tower. However, ATR argues,
citing its letter that stated it would provide mail service to
Bryan Tower, that its bid nonetheless was responsive because its
bid committed it to comply with all the terms and conditions of
the solicitation.
To be considered for award, a bid must comply in all material
respects with the IFB and should be filled out, executed, and
submitted in accordance with the instructions on the invitation.
Federal Acquisition Regulation (FAR) sect. 14.301(a), (d). A
bidder can bind itself to the contents of some amendments merely
by acknowledging receipt of the amendments; however, when a
bidder, despite acknowledging an amendment, otherwise creates
doubt as to its commitment to perform pursuant to the amendment,
its bid must be rejected. Lamb Eng'g & Constr. Co., B-261240,
Aug. 25, 1995, 95-2 CPD para. 87 at 3. If a bidder uses its own
bid form or a letter to submit a bid, the bid may be considered
if (1) the bidder accepts all the terms and conditions of the
invitation and (2) award on the bid would result in a binding
contract with terms and conditions that do not vary from the
terms and conditions of the invitation. FAR sect. 14.301(d).
The record shows that ATR's bid did not conform to the IFB in
two areas. First, although ATR acknowledged amendment 1, the
omission of the pricing for Bryan Tower as provided in the
revised bid schedule created doubt as to whether ATR agreed to
all of the terms of amendment 1. ATR's bid did not identify a
price for providing mail and messenger service to Bryan Tower in
either the bid schedule or in the bid response letter. Also,
although ATR indicated in its bid response letter its intention
to provide mail services to Bryan Tower--e.g., on the first two
pages, the Mail Point Schedules, and the list of Mailroom
Pick-Up and Mail Drop Off Spots--it failed to indicate that it
would comply with all of the terms and conditions of the amended
IFB. Specifically, the protester's bid did not commit to begin
the mail run for Bryan Tower at 1:00 p.m., as required by
amendment 1. Instead, the protester stated that mail runs would
begin at 10 a.m. and 2 p.m., which was the requirement under the
initial IFB for the other locations. IFB amend. 1, at 28; AR,
Tab 8, ATR Bid Response Letter, at 12.
ATR argues that its failure to include a price breakdown for
mail service for Bryan Tower is a minor informality that the
agency should allow it the protester to correct because ATR's
price for this mail service would be only $5,444.40, or 0.0063
percent of its bid. Protest at 2.
A minor informality is one that is merely a matter of form and
not of substance. FAR sect. 14.405. A contracting officer should
waive a defect in a bid as a minor informality if the defect is
immaterial and if waiver will not be prejudicial to other
bidders. TECOM, Inc., B-236929, B-236929.2, May 11, 1990, 90-1
CPD para. 463 at 3. A defect is immaterial if the effect on
price, quantity, quality, or delivery is negligible when
contrasted with the total cost or scope of the services being
acquired. Id. However, where it is apparent that the requirement
is material for reasons other than the effect on price it is not
necessary to determine whether or not the price impact is
negligible. MTC Indus. & Research Carmiel, Ltd., B-227163, Aug.
18, 1987, 87-2 CPD para. 174 at 5.
Here, we find that the requirement for mail service for Bryan
Tower is not immaterial. As noted above, the IFB clearly
identified the accuracy and timeliness of mail pickup and
delivery at each location as being of primary importance--thus
denoting a material requirement of the contract that cannot be
waived. ATR's bid, however, did not commit to the pickup
schedule required for Bryan Tower under amendment 1.
ATR also argues, in the alternative, that its bid should have
been understood to have included a fully -priced commitment to
provide mail services to Bryan Tower. In this regard, the
protester argues that the original solicitation required mail
service for two federal buildings, as well as a third "off-site"
location for the Department of Education. Protester's Comments
at 1. Thus, the protester contends, the initial IFB already
required mail services to a third site, and the protester's
failure to provide pricing for the third sub-CLIN, as required
in amendment 1, did not affect the requirement for the
contractor to provide mail services for three locations. We
disagree. The initial IFB clearly referred to two federal
buildings, one of which, the Earle Cabell Federal Building,
contained the Department of Education facility; the initial IFB
did not state that there was a third "off-site" location. The
requirement for mail service to a third location, Bryan Tower,
was first included in amendment 1--which, as discussed above,
required offerors to provide separate sub-CLIN pricing, and
which the protester did not address in its bid.
Furthermore, to the extent that ATR argues that its bid in fact
included pricing for mail and messenger service for Bryan Tower,
we disagree. A bidder's intention must be determined from the
face of the bid itself and evidence submitted after opening to
show a bidder's intent may not be considered. Newfield Constr.,
Inc., B-286912, Feb. 6, 2001, 2001 CPD para. 21 at 4. A
nonresponsive bid cannot be made responsive by explanations
after bid opening. J. D. Bertolini Indus., Ltd., B-231598, Sept.
14, 1988, 88-2 CPD para. 245 at 3.
In sum, ATR's failure to include prices for the sub-CLINs to
provide mail service to Bryan Tower as required by amendment 1,
and its failure to commit to the required schedule, created
doubt as to ATR's intention to fulfill all of the terms and
conditions of the amended IFB. (ATR
Logistic Company LLC, B-402606, June 1, 2010) (pdf)
Blackmon's status
as an SDVOSB concern is not in dispute here. The issue before
our Office is whether Blackmon's bid was nonresponsive because
the firm's ORCA record had expired at the time of bid opening.
Veterans contends that Blackmon's bid is nonresponsive and could
not be made responsive after bid opening when Blackmon updated
its ORCA records.
A responsive bid is one that, if accepted by the government as
submitted, will obligate the contractor to perform the exact
thing called for in the solicitation. See FAR sect. 14.301;
Propper Mfg. Co., Inc.; Columbia Diagnostics, Inc., B‑233321,
B‑233321.2, Jan. 23, 1989, 89-1 CPD para. 58. Responsiveness is
determined at the time of bid opening from the face of the bid
documents. Unless something on the face of the bid, or
specifically a part of it, limits, reduces or modifies the
bidder's obligation to perform in accordance with the terms of
the solicitation, the bid is responsive. Cal-Tex Lumber Co.,
Inc., B-277705, Sept. 24, 1997, 97-2 CPD para. 87 at 3.
With respect to certificates and representations, we examine the
certificate or representation to determine whether it concerns
the bidder's responsiveness (that is, its commitment to provide
the required services) or its responsibility. Generally, we have
found that the failure of a bidder to include completed standard
representations and certifications with its bid does not render
the bid nonresponsive because it does not affect the bidder's
material obligations. See Charter Envtl., Inc., B-297219, Dec.
5, 2005, 2005 CPD para. 213 at 4; see also Nomura Enter.
Inc.--Recon., B-244993.2, B‑245521.2, Oct. 9, 1991, 91-2 CPD
para. 322 at 3.
Here, none of the applicable representations and certifications
in Blackmon's ORCA record reduces or modifies Blackmon's
obligation to perform in accordance with the IFB requirements.
In this regard, we have found that the failure of a bidder under
a small business set-aside to provide a properly executed
certification of small business status with its bid is normally
waivable and the appropriate representation may be made after
bid opening because it pertains only to the bidder's status and
eligibility for award, not to the firm's commitment to provide
the required service.
Cal-Tex Lumber Co., Inc., supra, at 3 n.1. Accordingly, we find
that Blackmon's bid was responsive.
The protest is denied. (Veterans
Construction of South Carolina, LLC, B-401723.2, January 21,
2010) (pdf)
The failure to include with a bid completed standard
representations and certifications does not render the bid
nonresponsive because it does not affect the bidder’s material
obligations. Such a failure therefore may be waived as a minor
bidding irregularity and the information may be furnished after
bid opening. Jettison Contractors, Inc., B-242792, June 5, 1991,
91-1 CPD para. 532 at 2. Similarly, and as conceded by the
protester, the solicitation did not require that bidders be
registered in the CCR prior to bid opening, but rather, required
such registration prior to award. IFB at 117; Federal
Acquisition Regulation sect. 52.204-7(b)(1) (requiring that a
prospective awardee shall be registered in the CCR database
prior to award); see Graves Constr., Inc., B-294032, June 29,
2004, 2004 CPD para. 135 at 3 (protester not prejudiced by the
agency’s failure to verify whether the awardee had registered in
the CCR prior to award). Moreover, the agency advises that
during the course of this protest ECI Northeast has registered
on the CCR. As such, and contrary to the protester’s view, the
agency properly considered ECI Northeast’s bid responsive.
(Charter Environmental, Inc.,
B-297219, December 5, 2005) (pdf)
The agency received 10 technical proposals, seven of which were
found to be technically acceptable. The seven firms submitting
the technically acceptable proposals were thereafter requested
to submit bids. At bid opening, McNeil's was the apparent low
bid. After reviewing McNeil's bid, the agency initially
determined that it was nonresponsive because McNeil had used
tiered pricing in CLIN 0003, 0004, 0005, 0006 and 0009. More
specifically, while the solicitation called for a single unit
price for each CLIN, McNeil's bid included more than one price
for each CLIN, with the price varying depending upon the
quantity ordered (for example, under CLIN 0004, McNeil bid26.93
per hour for the first 400 hours, and $24.03 for all hours in
excess of 400 hours, up to the specified maximum quantity of
15,000 hours). In addition, McNeil's bid sheet showed the
original 66,000 hour maximum quantity for CLIN 0003, rather than
the amended 50,000 hour figure. Finally, for CLIN 0002, McNeil's
bid schedule included the title "team leader" rather than the
term "shift supervisor," as provided for in the solicitation.
Based on these perceived deficiencies, the contracting officer
advised McNeil that its bid had been found nonresponsive. McNeil
protested the agency's decision to our Office. In response to
that protest, the agency advised us that it intended to
reconsider the McNeil bid, and we dismissed McNeil's protest as
academic. (B-295533, Jan. 10, 2005). Thereafter, McNeil and the
agency engaged in several rounds of correspondence. As a result
of that correspondence, McNeil was permitted to substitute the
correct 50,000 hour maximum quantity for CLIN 0003 (replacing
the 66,000 hour figure), to correct minor mathematical errors in
its overtime rates, and to substitute the term "shift
supervisor" for "team leader" in its bid schedule. The seven
technically acceptable bids then were reevaluated, and it was
determined that McNeil's revised bid of12,252,065 was low; SOS's
bid of $13,889,265 was next low. Consequently, the contract was
awarded to McNeil on that date, and this protest followed.
McNeil's bid was responsive. In this regard, the record shows
that McNeil's bid was low under all possible calculations,
including where only the firm's higher hourly rates are applied.
[1] In addition, McNeil's tiered pricing neither expressly nor
implicitly limits the firm's obligation to perform in exact
accordance with the requirements of the solicitation. Rather,
the only effect of McNeil's tiered pricing would be to reduce
the cost of performance as larger quantities are ordered. Under
these circumstances, McNeil's bid's deviation from the pricing
scheme called for by the IFB was immaterial and therefore did
not render its bid nonresponsive. See RR Donnelley, Inc.
B-294395, Sep. 15, 2004, 2004 CPD paragraph 199 (bid based on
two different shipping weights rather than the single weight
called for by IFB is responsive where bid would be low applying
either of the two weights, and deviation did not operate to
qualify bidder's obligation to perform in accordance with IFB
requirements).
SOS argues that McNeil's bid was nonresponsive because it was
based on an incorrect maximum number of hours for CLIN 0003.
However, a bid based on a larger quantity than is required by
the solicitation is nevertheless responsive, so long as it is
not conditioned on the government's award of a quantity larger
than that called for under the solicitation, and the
solicitation does not preclude award of a quantity smaller than
the maximum quantity specified. Charles V. Clark Co., Inc,
B-196712, Mar. 12, 1980, 80-1 CPD paragraph 194 at 2-3. Here, as
noted, this is an IDIQ contract under which the government is
obligated to order only the minimum guaranteed quantities, but
may order additional quantities, up to the maximum specified in
the solicitation. Thus, the agency is obligated to purchase the
1,000 hour minimum quantity under CLIN 0003, but may elect to
purchase a larger quantity up to the specified maximum of 50,000
hours. As McNeil's bid did not condition its obligation to
perform on the government's ordering the erroneous maximum
quantity (66,000 hours), it follows that the agency could order
any quantity up to the correct lower maximum of 50,000 hours
without changing McNeil's performance obligation, and would not
be obligated to order the additional 16,000 hours specified in
McNeil's bid. McNeil's bid's inclusion of the incorrect maximum
quantity for CLIN 0003 therefore was immaterial and did not
render the bid nonresponsive. (SOS
International, Ltd., B-295533.2; B-295533.3, July 1, 2005) (pdf)
Generally, where a bidder does not submit its price on a revised
bid schedule listing an increased requirement, but instead
submits its bid on the original schedule, the mere
acknowledgment of the amendment containing the revised bid
schedule is not sufficient to bind a bidder to provide the
increased quantity because it is not clear that the bidder has
committed itself to provide the additional quantity for the
price set forth in the bid. See Harvey Honore Constr. Co., Inc.
, B-262071.2, Jan. 31, 1996, 96-1 CPD 30 at 3 (bid was found
nonresponsive where bidder acknowledged amendment but submitted
its bid on original bid schedule instead of revised schedule
provided by an amendment which increased the estimated quantity
of dirt to be excavated under construction contract).
Application of that rule leads us to the conclusion that the
agency properly found the protester's bid to be nonresponsive.
Here, the protester submitted a bid for a quantity of 218 lineal
feet of pipes, rather than for 394 lineal feet required by the
revised bid schedule. Since it is not clear from the bid whether
the protester intended to be committed to the amendment's larger
quantity or the original schedule's lesser quantity, we can only
conclude that, on its face, McKinley's bid does not provide a
firm commitment to what the IFB, as amended, envisioned as the
required work and, therefore, the bid properly was rejected as
nonresponsive. To the extent McKinley contends that its unit
price for line item No. 16 represents its unit price for the
increased quantity, a nonresponsive bid cannot be made
responsive by explanation after bid opening. Environmental
Health Research & Testing, Inc. , B246601, Mar. 10, 1992, 92-1
CPD 274 at 2. Allowing McKinley to explain its bid after bid
opening would, in effect, give McKinley the advantage of
electing to accept or reject the contract by choosing whether to
make its bid responsive. Id. Such a situation obviously would
have an adverse impact on the integrity of the bidding process.
(McKinley Construction & Excavating,
B-295547, March 3, 2005) (pdf)
Federal Acquisition Regulation 14.402-1 requires the public
opening of unclassified bids. Our Office has interpreted the
requirement for a public opening to mean that the bid must
publicly disclose the essential nature and type of products
offered and those elements of the bid that relate to price,
quantity, and delivery terms, since the purpose of publicly
opening bids is to protect both the public interest and the
bidders from any form of fraud, favoritism, or partiality, and
to leave no room for suspicion. VACAR Battery Mfg. Co., Inc. ,
B-223244.2, June 30, 1986, 86-2 CPD 21. Therefore, we have held
that restricting the disclosure of a bid renders it
nonresponsive. Id. Given that Spotless's hand-delivered, written
SF 1449 and bid schedule properly were accepted by the agency as
explained above, and expressly provided that the documents were
not to be disclosed publicly, the agency correctly rejected
Spotless's bid as nonresponsive. (Spotless
Janitorial Services, Inc., B-295620, February 18, 2005) (pdf)
Here, although the protester acknowledged receipt of amendment
No. 3, its bid cover letter offered a materially different
performance period than was required under the amendment. As the
agency points out, Integrated's cover letter is based on a
subjective, indefinite standard--"substantial completion" of
unidentified work. As a result, the cover letter limits the
agency's right under amendment No. 3 to require the contractor
to operate the plant until final acceptance of the base item.
The cover letter thus qualifies a performance term of the
amended IFB, materially affecting the rights and obligations of
the contractor and agency. Accordingly, the agency properly
rejected the bid as nonresponsive. To be responsive and
considered for award, a bid must contain an unequivocal offer to
perform, without exception, the exact thing called for in the
solicitation, so that, upon acceptance, the contractor will be
bound to perform in accordance with all of the IFB's material
terms and conditions. If in its bid (including its bid cover
letter), a bidder conditions or modifies a material solicitation
requirement (such as a performance period), limits its liability
to the government, or limits the rights of the government under
a resulting contract, then the bid must be rejected as
nonresponsive. See Tel-Instrument Elecs. Corp. , B291309,
B-291309.2, Nov. 20, 2002, 2002 CPD 203 at2-3; Interstate Constr.,
Inc. , B281465, Feb. 10, 1999, 99-1 CPD 31 at 2; Balantine's
South Bay Caterers, Inc. , B250223, Jan. 13, 1993, 93-1 CPD 39
at 3-4. Further, a bid that is nonresponsive on its face may not
be made into a responsive bid through post-bid-opening
clarifications, and mistake-in-bid procedures may not be used to
render the bid responsive. See National Office World, Inc. ,
B-224120, Sept. 5, 1986, 86-2 CPD 270 at 2. (Oregon
Electric Construction, Inc. dba Integrated Systems Group,
B-294279, September 27, 2004) (pdf)
The IFB requested bids to print, bind and otherwise prepare
3,994,000 copies of IRS pamphlet 1040A-1 (80 pages) and
2,947,000 copies of IRS pamphlet 1040A-2 (90pages). The IFB
provided that price would be evaluated by adding together the
extended prices bid for the specified tasks and transportation
charges. The IFB required bidders to provide a "Guaranteed
maximum weight of package (to 000.1pound) _____," which the
agency used to compute the transportation charges. Donnelley bid
2,174,543 to perform the work and listed the guaranteed maximum
weight of its package as .375 pounds. Using this weight, GPO
computed Donnelley's transportation charges as $976,284.17,
resulting in a total evaluated bid of $3,150,827.17. Banta bid
$2,235,227.94 to perform the work and included two guaranteed
maximum weights in its bid--.3142 pounds for 1040-A1 and .3633
pounds for 1040-A2. GPO used both weights in computing the
transportation charges for Banta's pamphlets as $745,752.85,
which resulted in a total evaluated bid price of $2,980,980.79.
The agency made award to Banta as the low bidder. Donnelley
protests that Banta's bid should have been rejected as
nonresponsive for including different guaranteed maximum weights
for the two pamphlets instead of the single weight called for by
the IFB. The test for responsiveness is whether a bid offers to
perform the exact thing called for in an IFB, so that acceptance
of the bid will bind a bidder to perform in accordance with all
of the terms and conditions of a solicitation without exception.
Fire Sec. Sys. Inc. , B259076, Mar. 2, 1995, 95-1 CPD 124 at 3.
Here, the agency requested the guaranteed maximum weight to
establish the maximum amount that could be reimbursed to the
contractor for transportation costs, which amount was to be
added to the bids for evaluation purposes. Banta's inclusion of
a second, lesser, weight for the 1040-A1 pamphlets did not
reduce or otherwise affect Banta's performance obligations, and
therefore did not affect the responsiveness of Banta's bid.
While a bid also must be rejected as nonresponsive if it is
ambiguous regarding the actual price the government would be
obligated to pay upon acceptance of the bid, Murray Serv. Co.
t/a EMD Mech. Specialists , B-274866, Dec. 9, 1996, 962CPD 220
at 2, that clearly is not the situation here. Banta's properly
evaluated bid price--that is, its price based on a single
guaranteed weight--can be calculated using the greater of the
two weights provided in Banta's bid. GPO has performed this
calculation and reports--and Donnelley has not refuted--that
Banta's bid remains low when transportation costs are calculated
in this way. Thus, Banta's evaluated bid price was clear and its
bid, therefore, responsive. (RR
Donnelley, Inc., B-294395, September 15, 2004) (pdf)
Where an IFB provides that award will be made to the low
aggregate bidder, a bid that fails to include a price for every
item required by the IFB generally must be rejected as
nonresponsive. HH&K Builders, B-232140, Oct. 20, 1988, 88‑2 CPD
¶ 379 at 2, recon. denied, B-232140.2, Nov. 30, 1988, 88-2 CPD ¶
537. This rule reflects the legal principle that a bidder who
has failed to submit a price for an item generally cannot be
said to be obligated to furnish that item. United Food Servs.,
B-218228.3, Dec. 30, 1985, 85-2 CPD ¶ 727 at 3. Apart from
whatever other defects may arise out of Thompson’s failure to
revise the numbers and the option descriptions to conform to the
schedule, we agree with the contracting officer that there was
no clear indication within Thompson’s bid that Thompson priced
approximately half of the option CLINs (those on the second page
of options B, C, and D). This created doubt as to whether
Thompson intended to furnish the services on those CLINs, and
thus rendered its bid nonresponsive. See Jorgensen Forge Corp.,
B-255426, Feb. 28, 1994, 94‑1 CPD ¶ 157 at 2 (bidder’s use of
“n/a” on bid created doubt whether bidder intended to furnish
item, rendering bid nonresponsive). The Corps therefore properly
rejected Thompson’s bid as nonresponsive. (Thompson
Metal Fab, Inc., B-293647, May 4, 2004) (pdf)
With
regard to the completeness of Petticoat's bid, the agency
printout clearly shows that all three pages were included with
the bid. The confusion was caused, it appears, by the
computer's reading the last two faxed pages as a single page.
The agency explains that, since only two pages were shown as
having been received when it initially read the bid, it did not
bother to scroll down further after seeing that the second page
was not the bid schedule--this would have revealed the attached
third page. COS ¶ g.2.b. Instead, the agency
assumed at that point that no bid schedule page was received.
The agency's mere failure to read the entire bid is not a basis
for finding that the bid was not timely received. We find
the documentary evidence, together with the agency's
explanation, clear evidence that Petticoat's bid was received
prior to bid opening, and was complete. Mitchell has
provided no evidence that shows otherwise. Accordingly,
there is no basis for questioning the award. (Mitchell Roofing & Contracting,
B-290462, June 25, 2002 )
A requirement for the submission of the permits necessary for performance at a
particular site relates to how the contract requirements will be met, rather than to
the performance requirements themselves; such a requirement thus pertains to
bidder responsibility. VA Venture; St. Anthony Med. Ctr, Inc., B-222622, B-222622.2,
Sept. 12, 1986, 86-2 CPD ¶ 289 at 5. A bidder need not demonstrate compliance with
solicitation requirements pertaining to its responsibility, that is, its ability
to perform as promised, in order to have its bid determined responsive. Moreover, the fact that
the IFB called for submission of a permit showing that the proposed disposal site
was “legal to operate” as of the bid opening date does not convert the permit
requirement into a matter of bid responsiveness. The terms of a solicitation cannot
convert a matter of responsibility into one of responsiveness. Integrated Prot. Sys.,
Inc., B-254457.2, B-254457.3, Jan. 19, 1994, 94-1 CPD ¶ 24 at 3; Norfolk Dredging Co.,
B-229572.2, Jan. 22, 1988, 88-1 CPD ¶ 62 at 3. (Great
Lakes Dredge & Dock Company, B-290158, June 17, 2002 (pdf))
Where invitation for
bids (IFB) expressly required option period prices to be
determined solely by application of IFB's economic price
adjustment clause, bid was properly rejected as nonresponsive
for offering different option year prices, since the economic
price adjustment clause is a material term of the IFB and any
bid taking exception to it materially affects the legal rights
of the bidder and the government. (First
American Engineered Solutions, B-289051, December 20, 2001)
Where, however, a
bidder agrees to hold its bid open for the minimum bid
acceptance period required by the solicitation and complies with
each agency request for an extension of its bid acceptance
period, the bidder has obtained no advantage over the other
bidders and the integrity of the bidding system is not
compromised if the bidder is subsequently permitted to revive an
expired bid. See Carnes Constr., Inc., B-241778,
Feb. 26, 1991, 91-1 CPD ¶ 215 at 3.
Here, Jackson agreed
to hold its bid open for the 30-day period originally requested
by the agency. It then extended its bid acceptance period
without the agency's having requested it, and confirmed, when
requested by the agency to do so, that its bid would remain open
until October 16. Thus, the record in no way suggests that
Jackson endeavored to obtain an advantage over other bidders by
offering less than the requested bid acceptance period.
Furthermore, Jackson was not required to extend its bid
acceptance period through the pendency of its protest because a
party's active participation in a bid protest, without a formal
extension of its bid acceptance period, tolls that period until
the protest is resolved. See S. J. Groves & Sons
Co., B-207172, Nov. 9, 1982, 82-2 CPD ¶ 423 at 2. (Consultants
Ltd., B-286688.2, May 16, 2001)
Forest Service
properly rejected bid for timber sale as nonresponsive where
protester failed to include a price for one of the several line
items being sold; in the absence of a price for the item, the
agency reasonably concluded that there was doubt regarding
whether the protester had offered to perform that aspect of the
requirement. (New
Shawmut Timber Company, B-286881, February 26, 2001)
As a general rule, where, as here, an IFB provides that award will be made to the low
aggregate bidder, a bid that fails to include a price for every item required by the IFB
must be rejected as nonresponsive. HH&K Builders, B-232140, Oct. 20, 1988, 88-2
CPD ¶ 379 at 2, recon. denied, B-232140.2, Nov. 30, 1988, 88-2 CPD ¶ 537. This rule
reflects the legal principle that a bidder who has failed to submit a price for an item
generally cannot be said to be obligated to furnish that item. United Food
Servs.,B-218228.3, Dec. 30, 1985, 85-2 CPD ¶ 727 at 3. We have held that the omission of a price for a certain line item may be corrected in
the rare circumstance where the price for the omitted item can be determined from
the initial bid submitted based upon the difference between the total bid price and
the sum of the line item prices present on the face of the bid. See, e.g., MKB
Constructors, Joint Venture, B-250413, Jan. 15, 1993, 93-1 CPD ¶ 50 at 2-3, recon.
denied, B-250413.2, June 8, 1993, 93-1 CPD ¶ 441. These cases apply the strict
criteria required for correction of mistakes. See Federal Acquisition Regulation
§ 14.407-3(a). That is, the omitted price could be corrected only because the bid, as
submitted, indicated that an error had been made, the exact nature of the error, and
the intended price for the bid item. MKB Constructors, Joint Venture, supra.
(Newfield
Construction, Inc., B-286912, February 6, 2001)
Evidence required to show the
authority of an individual signing a bid may be presented after
bid opening. FMS Corp., B-228201, Sept. 30, 1987, 87-2 CPD para.
318 at 1; Cambridge Marine Indus., Inc., B-202965, Dec. 31,
1981, 81-2 CPD para. 517 at 2. The sufficiency of the evidence
presented is largely a factual question to be resolved by the
contracting agency after consideration of all the materials
presented. Alpha Q, Inc., B-234403.2, Oct. 31, 1989, 89-2 CPD
para. 401 at 2. In Alpha Q, Inc., supra, the low bid
received bore the "signature" of the president of the
firm followed by three initials in parenthesis. Because of this,
the agency requested information from the firm "concerning
the legal effectiveness of the signature." Id. at 2. The
firm explained in an affidavit that the bid, at the direction of
the president, had actually been signed by an employee of a
prospective subcontractor of the firm. The agency determined
that the explanation "was sufficient evidence to establish
the signing individual's authority to execute the bid and bind
[the firm]." Id. at 3. Our Office, in considering a protest
challenging the responsiveness of the bid and propriety of the
agency's actions, found that the agency had properly requested
the information, that its factual determinations based upon the
information received were reasonable, and that the agency had
properly found the bid responsive. Our decisions in this
area recognize an obligation on the part of an agency that has
questions regarding the authority of the individuals whose
signatures appear on a bid to raise these questions with the
bidder. See, e.g., Cambridge Marine Indus., Inc., supra. Here,
we agree with the contracting officer that the differing
appearance of the signatures on G & J's bid raised certain
concerns, such as who actually signed the bid or whether there
may have been a forgery. However, the concerns raised, rather
than requiring the rejection of G & J's bid, obligated the
contracting officer to seek an explanation from G & J, and
this was in essence done through the above-noted exchange of
letters between the contracting officer and G & J. The
contracting officer, however, then erred in ultimately
concluding that she could not consider G & J's
post-bid-opening explanation. Rather, the contracting officer
was obligated to consider G & J's explanation in resolving
her concerns. See id. (G
& J Small Construction, Inc., B-286716, February 5,
2001)
A bid that is based upon the
incorrect premise that only three full-time and two part-time
positions were required under a solicitation for services where
the invitation for bids clearly requires five full-time
positions may not be corrected. (Aquila
Fitness Consulting Systems, Ltd., B-286488, January 17,
2001)
In particular, a bid such as
D.B.I.'s, which uses lump sum prices rather than separate prices
as called for under a bid schedule which contains lines for
separate pricing entries is responsive where there is no
ambiguity as to the bidder's legal obligation to perform as
required by the solicitation. Inland Serv. Corp., supra, at 3. A
lump-sum bid submitted in place of a line-item bid is responsive
where it merely reflects a firm's agreement to perform the
contract work for a single lump-sum price. Mike Johnson, Inc.,
supra, at 3. This kind of "irregular" price entry
renders the bid unacceptable only where it results in benefits
to the bidder which were not extended to all bidders by the IFB.
If the irregularity is prejudicial to other bidders, then the
bid should be rejected as nonresponsive. Valix Fed. Partnership
I, B-250686, Feb. 1, 1993, 93-1 CPD para. 84 at 4. Here, D.B.I.
acknowledged all amendments and submitted its prices on the
revised bid schedule. Its pricing entries clearly bound it to
perform all the work required by the solicitation, since
D.B.I.'s bid specifically noted that its flat rate per haul
included disposal charges. D.B.I.'s pricing in this respect is
functionally equivalent to the entry of "NSP"
("not separately priced") or "N/C" ("no
charge") notations, which we have found express the
bidder's affirmative intent to obligate itself to provide the
item at no charge to the government and therefore do not provide
a basis to reject a bid. Kasco Fuel Maintenance Corp., B-274131,
Nov. 22, 1996, 96-2 CPD para. 197 at 4. D.B.I.'s bid entries for
the hauling and disposal charges simply combine the two sub-CLIN
requirements and indicate that the disposal charge sub-CLIN is
not separately priced but is included in the price for the
hauling charge sub-CLIN. Thus, contrary to VA's assertion,
D.B.I.'s pricing format does not, by itself, require the
rejection of the bid as nonresponsive for failure to comply with
a material IFB requirement. (D.B.I.
Waste Systems, Inc., B-285049, July 10, 2000)
Protester's bid is responsive,
despite a discrepancy in the name of the bidder as identified on
the bid and the name of the principal identified in the required
bid bond, where reasonably available extrinsic evidence in
existence at the time of bid opening establishes that the bidder
and principal are the same entity, such that there is no doubt
that the surety will be liable under the bond to the government
on the bidder's behalf. (Harris
Excavating, B-284820, June 12, 2000)
The record here
sufficiently identifies Heavenly Ham as the same legal entity as
Knox-Ham Enterprises, so that the bid submitted by Heavenly Ham
at 9307 Kingston Pike, Knoxville, Tennessee, would legally bind
Knox-Ham Enterprises. The information on the CCR, as well as the
business tax licenses, business tax returns, food service
inspection report, articles of organization, and certificate of
existence--evidence which existed and was publicly available at
the time of bid opening--show that Heavenly Ham with the address
of 9307 Kingston Pike in Knoxville is the trade name for
Knox-Ham Enterprises, a North Carolina LLC, and does not exist
as a separate legal entity. (Specialized
Contract Services, Inc., B-283451, October 21, 1999)
Delivery terms are a material
requirement and thus a bid that takes exception to the stated
delivery terms is nonresponsive and must be rejected. Copley
Int?l Trading Partners; Western States Elec., Inc., B-248751,
B-248751.3, Sept. 10, 1992, 92-2 CPD para. 167 at 3. Further, a
bid which is nonresponsive on its face may not be made into a
responsive bid by post-bid opening clarifications or
corrections. Lathan Constr. Corp., B-250487, Feb. 5, 1993, 93-1
CPD para. 107 at 3-4. (Valley
Forge Flag Company, Inc., B-283130, September 22, 1999)
We recognize that the amended bid
schedule, by creating a box with a dollar sign in the box on the
line identifying the overall CLIN, suggests that a price should
be included in that box for the CLIN overall (in addition to the
prices for the sub-CLINs). In our view, however, no possible
prejudice arose to the protester, and we therefore conclude that
there is no basis to challenge EPA's considering bids which
failed to write a price in the box on the CLIN line. (American
Analytical & Technical Services, Inc., B-282277.2, July
16, 1999)
Here, the effect of
the conditions attached to Ellicott's bid was that the bid was
premised on modifying material requirements of the IFB. In this
regard, it is not disputed that the requirements for a
particular grade of forged steel and for approval of flame
cutting are material, since they relate to the quality of the
project. While the protester notes that the IFB provided for
acceptance of alternate material or flame cutting, the cited
provisions pertain to contract performance by the successful
contractor and cannot be relied upon by bidders to condition
their bids, as Ellicott appeared to do here, on receiving
approval of material other than that required by the IFB.
(Ellicott
Engineering, Inc., B-282382, June 23, 1999)
As discussed in detail below,
since the Kinley bid qualification conditions performance by the
firm on the agency taking steps to clean the tanks and render
them "gas free," the bid imposes additional
obligations on the agency not contemplated by the IFB which
limit the government's rights, as well as the contractor's
liability under the contract. The bid therefore must be rejected
as nonresponsive. (Interstate
Construction, Inc., B-281465, February 10, 1999)
|