The agency
received sealed bids from ten firms, including JCMCS and M&F.
Abstract of Offers. M&F had the lowest bid price of
$20,514,321.50, significantly lower than JCMCS’s bid, which was
the second lowest ($36,374,996). Id. The contracting officer
determined that M&F’s bid was responsive to the IFB and award
was made to M&F. Contracting Officer’s Statement of Facts at 3.
This protest followed.
(sections deleted)
JCMCS next argues that M&F’s bid is so low that the bid must be
unbalanced. This argument, by itself, fails to state a basis for
protest. Unbalanced pricing exists where the prices of one or
more items are significantly overstated, despite an acceptable
total evaluated price (typically achieved through underpricing
one or more of the other line items). ABSG Consulting, Inc.,
B-404863.7, June 26, 2013, 2013 CPD ¶ 185 at 6; General
Dynamics--Ordnance & Tactical Sys., B‑401658, B‑401658.2, Oct.
26, 2009, 2009 CPD ¶ 217 at 5. Low prices, by themselves, are
not improper and do not themselves establish (or create the risk
inherent in) unbalanced pricing. Id.
Despite failing initially to state a valid basis for arguing
that the bid is unbalanced, in an attachment to its comments on
the agency report, JCMCS identifies one line item (out of
several hundred total line items) which it believes M&F
overbid‑‑contract line item 0036AA, for surveying, engineering,
and permitting. JCMCS Comments, Tab 6, Response to M&F’s Unit
Price Schedule at 6. JCMCS bid the item at $1,000. The protester
asserts that M&F’s unit price of $10,000, or $60,000 total at
the solicitation’s estimated quantity of 6, was “way high.” Id.;
compare JCMCS Proposal at 62 with M&F’s Proposal at 62.
We disagree that this information establishes that the bid is
unbalanced. The prior contract for the agency’s concrete
requirement included a unit price of $11,750 for this item,
while the independent government cost estimate (IGCE) was
$23,397.17, both substantially more than M&F’s unit price.
Agency Report, Tab 10, M&F Bid Comparison at 5. Furthermore,
while the protester relies on the typical cost of a survey crew
to arrive at its estimate of a reasonable bid price, the item is
actually for surveying, engineering, and permitting, and thus
encompasses more work, which could account for the discrepancy
between the protester’s calculations and the prior contract
price and the government estimate for the work. In any case, the
value of this one line item is de minimis, and JCMCS has made no
showing that, in view of M&F’s overall $15,860,675 price
advantage, there would be any risk to the government associated
with M&F’s allegedly unbalanced bid, including the allegedly
inflated bid of $10,000 for each of six estimated projects. See
Serco, Inc., B‑406683, B-406683.2, Aug. 3, 2012, 2012 CPD ¶ 216
at 10 (noting that, where an unbalanced offer is received,
agencies are not required to reject it, but should consider the
risk to the government of unreasonably high prices for contract
performance). (JCMCS,
B-409407: Apr 8, 2014) (pdf)
The agency also concluded that 33
line items in W.B.'s bid were 50 percent over the revised IGE,
59 items were 30 percent over the revised IGE, and 54 items were
more than 50 percent under the revised IGE. AR, Tab 3B Price
Comparison, at 1-28. The contracting officer determined that
this analysis provided sufficient evidence to indicate the
presence of unbalanced pricing in W.B.'s bid and that the bid
should be rejected as nonresponsive. AR, Tab 15, Award
Memorandum, at 2. W.B. argues that the rejection of its bid on
this basis did not comply with FAR § 15.404-1(g).
The IFB included the clause at FAR § 52.214-19(d), which
provides in pertinent part:
The Government may reject a bid as
nonresponsive if the prices bid are materially unbalanced
between line items or subline items. A bid is materially
unbalanced when it is based on prices significantly less than
cost for some work and prices which are significantly
overstated in relation to cost for other work, and if there is
a reasonable doubt that the bid will result in the lowest
overall cost to the Government even though it may be the low
evaluated bid, or if it is so unbalanced as to be tantamount
to allowing an advance payment.
FAR § 14.404-2(g) provides that
"any bid may be rejected if the prices for any line items or
subline items are materially unbalanced (see 15.404-1(g))." FAR
§ 14.404-2(g). FAR § 15.404-1(g)(1) provides that unbalanced
pricing exists when, despite an acceptable total evaluated
price, the price of one or more contract line items is
significantly overstated or understated, as indicated by the
application of cost or price analysis techniques. While
unbalanced pricing may increase risk to the government, agencies
are not required to reject an offer solely because it is
unbalanced. L. W. Matteson, Inc., B-290224, May 28, 2002, 2002
CPD ¶ 89 at 3. Rather, where the contracting officer receives an
unbalanced bid or offer, the contracting officer is required to
consider the risks to the government associated with the
unbalanced pricing in making the award decision, and whether a
contract will result in unreasonably high prices for contract
performance. FAR § 15.404-1(g)(2). An offer properly may be
rejected if the contracting officer determines that the lack of
balance in the bid or offer poses an unacceptable risk to the
government. FAR § 15.404-1(g)(3); L. W. Matteson, Inc., supra at
3. Our Office will review for reasonableness both an agency's
determination as to whether an offeror's prices are unbalanced,
and an agency's determination as to whether an offeror's
unbalanced prices pose an unacceptable risk to the government.
Semont Travel, Inc., B-291179, Nov. 20, 2002, 2002 CPD ¶ 200 at
3; L. W. Matteson, Inc., supra, at 4; Enco Dredging, B-284107,
Feb. 22, 2000, 2000 CPD ¶ 44 at 6.
The record shows that the contracting officer's determination
that W.B.'s bid was unbalanced was reasonable, given the
numerous line items where W.B.'s prices were significantly
higher or lower than the IGE. However, a bid or offer may not be
rejected merely because it is unbalanced. See Citywide Managing
Servs. of Port Washington, Inc., B-281287.12, B-281287.13, Nov.
15, 2000, 2001 CPD ¶ 6 at 7-8. Instead, FAR § 15.404-1(g)(2),
(3) requires that the contracting officer consider the risks
associated with the unbalanced pricing and only reject an
unbalanced bid or offer where it is determined that the lack of
balance posed an unacceptable risk. Id.; see Burney & Burney
Constr. Co., Inc., B-292458.2, Mar. 19, 2004, 2004 CPD ¶ 49 at
2-3 (rejecting unbalanced quotation based upon risk analysis);
Semont Travel, Inc., supra at 3-5 (accepting unbalanced bid
based upon risk analysis); L. W. Matteson, Inc., supra at 4-5
(rejecting unbalanced bid based upon risk analysis).
Here, there is no contemporaneous documentation indicating that
the contracting officer determined that W.B.'s bid was
materially unbalanced in accordance with FAR § 52.214-19(d),[4]
or that this lack of balance posed an unacceptable risk in
accordance with FAR § 15.404-1(g). The only further explanation
of the contracting officer's determination here is provided in
an affidavit provided in response to this protest, where the
contracting officer simply stated that "[t]he number of such
items and the reasonable potential for greater cost of ordering
significantly higher cost items caused me to reasonably doubt
that the Protester's bid would result in the lowest overall cost
to the Government, even though it may have been the lower
evaluated bid." AR, Tab 13, Contracting Officer Affidavit, at 2.
Thus, the record is devoid of any evidence to show that the
contracting officer conducted any type of analysis of the
unbalanced line items to consider the risks to the government
associated with the unbalanced pricing in making the award
decision.
Accordingly, we find unreasonable the agency's rejection of
W.B.'s bid as materially unbalanced because the contracting
officer failed to perform the risk analysis required by FAR §
15.404-1(g).
We sustain the protest. (W.B.
Construction and Sons, Inc., B-405818; B-405818.2, January
4, 2012) (pdf)
The contracting officer here
explains that, while the agency prepared the estimates for each
line item based on historical data and made a good faith effort
to make them accurate, the work under the IFB is subject to many
variables, so the work actually ordered under any line item
could deviate substantially from the estimates. In this regard,
the agency explains, painting is not directly funded but,
rather, is funded under the maintenance budget, and is given low
priority because many other maintenance projects, such as
mechanical repairs, cannot be delayed. Thus, if a large quantity
of priority work arises, less painting than estimated may be
ordered, while, if less priority work is required, more painting
may be ordered. Due to the uncertainty resulting from these
variables, the contracting officer was concerned that Burney’s
bid, with its overstated prices for some line items, could
result in other than the lowest total cost to the government if
the actual quantities for those items exceeded the estimates. In
order to verify her position, the contracting officer calculated
the effect if the ordered quantities under the current contract
ultimately were the same as the quantities actually ordered
under the fiscal year 2003 contract. She determined that, for
several line items, including those overpriced in Burney’s bid,
the amount of work ordered by the Army was significantly higher
than the amount of work estimated, and that the total cost to
the government would be greater than the next low bid if the
same quantities were ordered at Burney’s bid prices for those
items. It was on this basis that the contracting officer
concluded that Burney’s bid should be rejected. The agency’s
actions were unobjectionable. Viewing just two of the overpriced
items in Burney’s bid against the actual fiscal year 2003
requirements, Burney’s total bid increases such that it is no
longer low. Specifically, for line item No. 6 (coverage of wood
trim), Burney’s bid was $7.25, while the government estimate was
$1.91 and the average price of the other bids was $4.19;
multiplying Burney’s item price by the solicitation estimate of
20,000 square yards yielded an extended price of $145,000. In
fiscal year 2003, the agency actually ordered 39,815 square
yards; if the agency ultimately ordered the same quantity under
the current contract, at Burney’s $7.25 bid price the
government’s cost for the line item would increase by
$143,658.75, to $288,658.75. For line item No. 10 (coverage of
metal surfaces), Burney bid $7.25, compared to the government
estimate of $1.59 and the average bid price of $4.70. The IFB
estimate was 3,500 square yards, which yielded an extended bid
price of $25,375 for Burney. However, in fiscal year 2003 the
agency ordered 70,307 square yards of work under line item No.
10; if the same quantity were ordered from Burney under the
current contract, the cost to the government would increase by
$484,350.75, to $509,725.75. Thus, based on the fiscal year 2003
actual requirements for just these two items, Burney’s bid would
increase by $628,009.50, far in excess of Burney’s evaluated
price advantage--$59,778.50--over the second low bidder. The
risk that this would occur provided a reasonable basis for the
agency to reject Burney’s bid. (Burney
& Burney Construction Company, Inc., B-292458.2, March 19,
2004) (pdf)
By including its disposal site preparation costs in its CLIN
0003 price rather than under CLIN 0001, LWM's pricing approach
created the potential that LWM could recover a disproportionate
share of the overall contract price early in the performance
period. Although LWM has expressed its intention to incur
the disposal site preparation costs at the beginning of the
project (asserting that development of the disposal site is a
necessary prerequisite to beginning dredging), neither the IFB
nor its bid obligated it to do so. As a result, the agency
concluded, in the event of early termination of LWM's contract,
the agency would have expended a substantial sum for CLIN 0003
work that had not been performed. Indus. Builders, Inc.,
supra, at 7-8. We think the agency reasonably found
that this was an unacceptable risk to the government; this risk
warranted rejecting LWM's bid as unbalanced.
(L. W. Matteson, Inc., B-290224,
May 28, 2002)
In this regard, we have found
prices to be impermissibly front-loaded only in limited
situations where the front-loaded item prices were many
multiples higher than the value of the work to be performed or
the remaining contract prices. See ACC Constr. Co., Inc.,
B-250688, Feb. 16, 1993, 93-1 CPD para. 142 (line item price of
$4.7 million versus government estimate of $1.8 million); Islip
Transformer & Metal Co., Inc. B-225257, Mar. 23, 1987, 87-1
CPD para. 327 (first article unit prices were $15,000 and the
production unit prices were $408.90); Edgewater Mach. &
Fabricators, Inc., B-219828, Dec. 5, 1985, 85-2 CPD para. 630
(first article prices were $125,000 and the production unit
prices were $301). In each of these cases, the grossly
overpriced items would have resulted in substantial funds--which
significantly exceeded the value received by the
government--being paid to the contractor early in contract
performance. Here, Campbell's bid cannot result in such an
advance payment. (Beldon
Roofing Company, B-283970, January 28, 2000)
Under invitation for bids (IFB)
for construction of water control structure, agency reasonably
rejected bid as unbalanced where bidder failed to allocate the
cost of a cofferdam (a dewatering measure) among related work
items requiring dewatering measures, as provided in the IFB, and
instead included the cost of a cofferdam in its lump-sum line
item price for a relatively minor work requirement for clearing,
grubbing, and snagging of debris on the site, rendering the
bidder's price for that line item many multiples higher than the
government's estimate for the item and the other bids received;
rejection of the bid was proper based upon agency's reasonable
determination that the unbalancing posed an unacceptable risk
that the government would make a substantial payment to the
bidder upon completion of the required clearing, grubbing, and
snagging work, without any assurance that the bidder would have
constructed the cofferdam which was included in its price for
that line item. (Industrial
Builders, Inc., B-283749, December 29, 1999)
|