As relevant to this protest, bid opening was scheduled for
September 13, at 9:00 a.m., Eastern Standard Time. Agency Report
(AR), Exh. 2, IFB amend. 6 at 1. Williams initially submitted its
bid to the contracting officer at 8:30 a.m. on September 13.
Contracting Officer’s Statement (COS) at 1. However, at
approximately 9:00 a.m., the Williams’ representative asked if he
could change Williams’ bid. Id. The contracting officer, believing
that Williams intended to exchange one envelope for another,
handed the representative the unopened envelope containing the
bid. Id. The Williams’ representative opened the sealed envelope,
wrote something down, and inserted a bid sheet. Id.; Protest at
3-4. Although the representative intended to remove the original
bid sheet, he failed to do so. Protest at 3-4. The representative
returned the bid package to the contracting officer at 9:02 a.m.
COS at 1. At 9:03 a.m. the contracting officer read the four bids
that had been submitted, including Williams’ bid. Id. Williams’
bid package contained two offer forms (standard form (SF) 1442):
one in the amount of $4,929,583; and a second one in the amount of
$4,795,139, which was written next to a crossed out amount of
“$4,7195.” COS at 1-2; AR, Exh. 3, Williams’ Bid Package. The
contracting officer read the Williams’ bid as $4,929,583. COS at
1- 2. Nordstrom Contracting and Consulting Group submitted the
second lowest bid of $5,385,000. Id. Following protests by
Williams and then Nordstrom, the agency rejected Williams’ bid as
late. Williams protests that decision.
DISCUSSION
Williams argues that its bid should be accepted because it is
clear that its original bid was $4,795,139. Protest at 5.
Specifically, according to Williams, the envelope in which its bid
was submitted contained, in addition to the two SF 1442’s, a bid
sheet on which Williams crossed out the initial quote $4,795,139
and hand wrote the amended quote $4,929,583. Id. The protester
argues that when an attempted bid modification (its attempt to
change the bid from $4,795,139 to $4,929,583) is invalid, the
bidder is bound by its initial bid. Id. at 6. Thus, according to
Williams, if its modified bid--$4,929,583--was late, the agency
could accept its original bid--$4,795,139, that was submitted at
8:30 a.m.
The agency argues that when the contracting officer returned the
original sealed bid package to Williams, the agency relinquished
control over the bid. Memorandum of Law (MOL) at 5. The agency
further argues that when Williams returned the bid package to the
contracting officer after 9:00 a.m., Williams’ bid was late and
properly rejected. Id. Finally, the agency states that there was
no bid sheet in the envelope with Williams’ bid, but only the two
SF 1442’s for $4,795,139 and $4,929,583. MOL at 5.
Bidders are responsible for submitting bids, and any modifications
or withdrawals, so as to reach the government office designated in
the invitation for bid by the time specified in the IFB. Federal
Acquisition Regulation (FAR) § 14.304; IFB amend. 2 at 50
(incorporating by reference FAR provision 52.214-7). A bid must be
submitted so that it is received in the office designated in the
IFB not later than the exact time set for the opening of bids.
Weeks Marine, Inc., B-292758, Oct. 16, 2003, 2003 CPD ¶ 183 at 3.
The time a hand-carried bid is considered submitted is determined
by the time the bidder relinquishes control of the bid to the
government. Id.; Chestnut Hill Constr., Inc., B-216891, Apr. 18,
1985, 85-1 CPD ¶ 443 at 3.
Here, Williams took its bid back, and did not relinquish control
of the bid to the government until 9:02 a.m., after the time set
for bid opening. Therefore, the bid was late. Further, although
Williams argues that the agency could accept its original bid of
$4,795,139, which it contends was submitted at 8:30 a.m., we
disagree. Since there were two bids in the Williams’ bid package,
there is no way to determine which bid was the original bid.
Moreover, what Williams alleges is its original
bid--$4,795,139--was in the bid package that Williams submitted to
the contracting officer after the 9:00 a.m. time set for bid
opening and therefore was late. Again, when Williams took its bid
package back, it took the bid that was submitted at 8:30 a.m. out
of the government’s control and when it resubmitted the package at
9:02 a.m., the entire bid package, including both bids, was late.
(Williams Building Company, Inc.
B-415317.3: Apr 12, 2018)
Athena’s leading argument is that because the solicitation
included a statement that bids received after 2:00 p.m. would not
be accepted, and because R&R’s bid (and those of the next two low
bidders) was received in the bid opening room after 2:00 p.m., the
agency simply should have rejected R&R’s bid as late. See Protest
at 2, 9-12; Comments at 1-4; Supp. Comments at 2, 4-5. Athena
explains its position as follows:
Here, where the Solicitation expressly stated that bids received
after 2:00 p.m. would “NOT BE ACCEPTED,” the Agency cannot rescue
itself by relying on the provisions [in the provision at FAR §
52.214-7] regarding consideration of late bids . . . . The express
language of the Solicitation overrode the more liberal FAR
provisions and divested the Contracting Officer of the discretion
she may have had, under other circumstances, to consider a late
bid, regardless of the time it arrived at the installation.
Comments at 4 (quoting IFB at 1). In other words, Athena contends
that the procedures in the provision at FAR § 52.214-7 regarding
the acceptance of late bids were essentially inapplicable to this
procurement. For the reasons discussed below, we see no merit in
this argument.
Where a dispute exists as to the meaning of an IFB’s terms, our
Office resolves the matter by reading the IFB as a whole and in a
manner that gives effect to all the IFB’s provisions. See Nat’l
Servs., Inc., B-400836.2, Mar. 11, 2009, 2009 CPD ¶ 58 at 2; BAE
Sys. San Diego Ship Repair, B-400350, Sept. 22, 2008, 2008 CPD ¶
174 at 3. To be reasonable, an interpretation of the IFB language
must be consistent with the IFB when read as a whole. See Nat’l
Servs., Inc., supra; BAE Sys. San Diego Ship Repair, supra.
Here, the solicitation provided that bid opening would occur in a
given room at 2:00 p.m. and that bids received after 2:00 p.m.
would not be accepted. IFB at 1. However, the solicitation also
incorporated by reference the provision at FAR § 52.214‑7, which
establishes procedures through which an agency may accept a late
bid, including procedures for instances where, as here, a bid was
received at the government installation and was under government
control before the time set for receipt of bids. IFB at 48. While
Athena argues that the first provision “overrides” the second, we
see no basis for that conclusion.
Instead, we find the two provisions to be harmonious, with the
first provision establishing the deadline for the receipt of bids
in the bid opening room, and the second one establishing a limited
set of circumstances under which a late bid could be accepted. We
further find that the record includes acceptable evidence--screen
shots from the agency’s package-intake software--to show that
R&R’s bid was received at the agency installation and was under
agency control before the time set for the receipt of bids. See
AR, Tab 21, R&R Bid Receipt Verification, at 1. Additionally, we
see no basis to question the contracting officer’s determination
that acceptance of R&R’s bid would not unduly delay the
procurement. Accordingly, we see the agency’s acceptance of R&R’s
bid as reasonable. In sum, we deny Athena’s claim that the agency
was somehow required to ignore the solicitation’s inclusion of the
provision at FAR § 52.214-7 and simply reject R&R’s bid as late.
(Athena Construction Group, Inc.
B-413406, B-413406.2: Oct 21, 2016)
Al-Tahouna argues that its highest-priced bid was timely submitted
to DLA, and that the agency unreasonably excluded the protester
from the competition. The protester’s argument relies on two
documents: (1) a copy of the email it asserts was submitted to the
email address set forth in the IFB approximately 6 minutes before
the bid closing time; and (2) a document logging the various
servers the email message passed through after being transmitted,
including the successful receipt at another contractor-controlled
email account that was copied on the transmission to the agency.
For the reasons set forth below, we find no basis to sustain the
protest.
Neither the Competition in Contracting Act of 1984 (CICA) nor the
Federal Acquisition Regulation (FAR) apply to sales of government
property. Where, as here, CICA and the FAR do not apply to
procurements that are otherwise within our jurisdiction, we review
the record to determine if the agency’s actions were reasonable
and consistent with any statutes or regulations that do apply.
See, e.g., Open Spirit, LLC, B-410428, B‑410428.2, Dec. 15, 2014,
2014 CPD ¶ 373 at 6; Great S. Bay Marina, Inc., B‑293649, May 3,
2004, 2004 CPD ¶ 108 at 2-3.
In protests involving IFBs subject to FAR part 14, we have found
that bidders are responsible for delivering their bids to the
proper place at the proper time, and late delivery of a bid
generally requires rejection even if it is the lowest (or, in this
case, the highest) bid. See Aquaterra Contracting, Inc., B-400065,
July 14, 2008, 2008 CPD ¶ 138 at 3; Amigo-JT Joint Venture,
B‑292830, Dec. 9, 2003, 2003 CPD ¶ 224 at 4. We have also found
that it is an offeror’s responsibility, when transmitting its bid
or proposal electronically, to ensure the bid’s or proposal’s
timely delivery by transmitting the bid or proposal sufficiently
in advance of the time set for receipt of bids or proposals to
allow for timely receipt by the agency. C2G Ltd. Co., B‑411131,
May 12, 2015, 2015 CPD ¶ 157 at 4.
Here, we find that Al-Tahouna has failed to establish that its bid
was received by DLA prior to the closing time for the receipt of
bids. As stated above, it is an offeror’s responsibility to ensure
that an electronically submitted bid is received by--not just
submitted to--an agency prior to the time set for closing. See
also IFB at 17 (stating that it was the offeror’s responsibility
to confirm receipt of an emailed bid). Al-Tahouna does not argue,
and the record contains no other evidence showing, that the
protester attempted to confirm receipt of its emailed bid. The
only evidence provided by the protester to demonstrate that the
agency received Al-Tahouna’s bid is a copy of the email sent by
the protester 6 minutes before the closing time, and a copy of the
server route for the message reflecting that another Al-Tahouna
controlled email address that was copied on the message
successfully received the email. See Protest (May 7, 2015),
attach. No. 2, Email from Al-Tahouna (Dec. 18, 2014); attach. No.
3, Gmail Server Information (May 6, 2015). Neither of these
documents, however, demonstrates that DLA in fact received the bid
prior to the closing time.
DLA conducted an internal investigation and found no evidence
demonstrating that the agency received the protester’s bid prior
to the IFB’s closing time. See COSF ¶ 13. Furthermore, with regard
to the server data submitted by the contractor, DLA submitted a
declaration by the Microsoft Windows server team lead and senior
Microsoft Exchange email administrator for the agency’s email
support contractor (the DLA email administrator). See DLA Email
Administrator Statement (June 5, 2015). The DLA email
administrator states that he reviewed the server data submitted by
the protester, but that none of the internet protocol addresses
referenced in the document reflect a received message at a DLA
internet protocol. Id. ¶ 5. Rather, the DLA email administrator
explains that the internet protocol addresses in the document only
reflect that the document was successfully transmitted within the
same email environment utilized by the protester. Id. ¶¶ 6‑7. Al-Tahouna
does not specifically dispute the DLA email administrator’s
explanation of the server data.[2] On this record, we find that
the protester has failed to demonstrate that DLA timely received
the bid prior to the IFB’s closing time.
Al-Tahouna also argues that our Office should draw a negative
inference from DLA’s destruction of electronic files, in the
ordinary course of the agency’s business, from the email inbox
used for the receipt of bids. The protester argues that the
agency’s 30-90 day email retention periods are inconsistent with
the requirements of FAR § 4.805. Comments (June 18, 2015) at 1.
That provision of the FAR provides, in relevant part, that
unsuccessful offers, quotations, bids, and proposals relating to
contracts above the simplified acquisition threshold must be
retained at least until the contract is completed. FAR §
4.805(b)(5)(i). Although the FAR is not applicable to this scrap
sale procurement, we find that DLA was nonetheless required to
retain copies of any unsuccessful bids for a reasonable period of
time. Under the circumstances here, it is questionable whether
DLA’s policy of purging the email inbox used to receive bids after
as little as 30 days was reasonable. Had Al-Tahouna provided any
evidence indicating the timely receipt of its bid by the
government, DLA would have borne the risk that it would be unable
to rebut the evidence when the burden would have shifted to the
agency. Cf. Southwest Marine, Inc.; Am. Sys. Eng’g Corp.,
B‑265865.3, B-265865.4, Jan. 23, 1996, 96-1 CPD ¶ 56 at 10
(finding that, in a negotiated procurement, where an agency fails
to retain evaluation materials it bears the risk that there is
inadequate supporting rationale in the record for the source
selection decision), recon. denied, B-265865.5, B-265865.6, June
3, 1996, 96-1 CPD ¶ 261; Hydraudyne Sys. & Eng’g B.V., B-241236,
B-241236.2, Jan. 30, 1991, 91‑1 CPD ¶ 88 at 5 n.4 (finding that,
in a negotiated procurement, the destruction of evaluation
documentation in violation of the FAR’s requirements was
“inappropriate”). In the absence of any such evidence from the
protester showing that its bid was timely received by the agency,
however, we need not resolve this evidentiary matter. (Al-Tahouna
Al-Ahliah General Trading & Contracting Company W.L.L.
B-411505: Aug 11, 2015) (pdf)
The IFB was
posted on the Federal Business Opportunities (FedBizOpps)
website on August 15, 2011 as a HUBZone small business
set-aside. The original IFB instructed bidders that bids were
due on September 15, 2011 by 1 p.m. MST at the FHWA Central
Federal Lands Division office in Lakewood, Colorado. Agency
Report (AR), Tab 2, IFB, at A-1. Amendment No. 2 was issued on
September 7 and changed the place for submission of bids to the
FHWA, Arizona Division Office in Phoenix, Arizona. AR, Tab 4,
Amend. No. 2, at A-1. The amendment did not change the time for
receipt of bids.
Five bids were received and accepted. The bids of the protester
and another vendor were received before 12:00 p.m. in Arizona on
September 15. AR, Tab 5, Bid Receipts. The other three bids,
including NAC Construction, the low bidder, were received after
12:00 p.m. but before 1:00 p.m. in Arizona. Id. SBBI submitted
the second low bid. Id. The bid opening summary was posted by
the agency from Lakewood, Colorado on September 19, which stated
the bid opening location as Phoenix, Arizona and the time of bid
opening as "2:00 p.m. (1:00 p.m. Arizona)." AR, Tab 11, Bid
Opening Summary and Contracting Officer's Statement at 3. The
agency states that 2:00 p.m. in the bid opening summary refers
to the time in Lakewood, Colorado. Id. On September 20, SBBI
filed this protest with our Office.
The protester maintains that although the agency changed the
location of the bid opening to Phoenix, Arizona, the agency did
not change the time for submission of bids. The protester argues
that bids were originally required to be submitted by 1:00 p.m.
MST which is actually 12:00 p.m. Arizona time, and that bids
received after 1:00 p.m. Colorado time should be rejected.
Protest at 3.
The agency responds that both Colorado and Arizona are in the
MST time zone, but that Arizona does not observe daylight saving
time. Contracting Officer's Statement at 3. The agency states
that during the months of daylight saving time Arizona is one
hour behind the rest of the MST zone. Id. It is the agency's
position that 1:00 pm MST on the IFB referred to the time in
Arizona where the solicitation designated bids were to be
received, and that all bids were received timely and opened at
the proper time and that NAC was properly declared the apparent
low bidder. Id.
We agree. We have previously held, that under the Uniform Time
Act of 1996, 15 U.S.C. sect. 262 (2006), there is one standard
time for most governmental purposes, including the time
designated for receipt of proposals or opening bids, and that
time is the local time, regardless of whether it is referred to
as standard time or as daylight savings time in the
solicitation. 49 Comp. Gen. 164 (1969) (standard time and
daylight savings time are one and the same for purposes of
designating a bid opening time); Environmental Control Division,
Inc., B-255181, Feb. 16, 1994, 94-1 CPD para. 115 at 4.
Here, all bids were submitted to the FHWA Phoenix, Arizona
office as required by the IFB and all were received prior to the
1:00 p.m. scheduled bid opening. Thus, all the bids were timely
received at the 1:00 p.m. local time for Arizona, the designated
place for receipt of bids. (SBBI,
Inc., B-405754, November 23, 2011) (pdf)
The IFB
incorporated by reference Federal Acquisition Regulation (FAR)
clause 52.214-5, "Submission of Bids," which provides that
facsimile bids would not be considered unless authorized by the
solicitation. Id. at 16. The IFB also instructed potential
offerors to contact the contract specialist in the event of
questions. Id. at 1.
One day before bid opening, Heath contacted the contract
specialist to ask whether the bid could be submitted by email or
facsimile transmission. Agency Report, Tab 2, Emails between
Heath and the VA. The contract specialist informed Heath that
the firm could transmit its bid by facsimile transmission to the
attention of the contracting officer and identified a telephone
number for a facsimile machine. Id. Heath transmitted its bid by
facsimile to the identified telephone number on the bid opening
date. Contracting Officer's Statement of Facts at 1. The
contracting officer, who states that she was unaware of the
contract specialist's communication with Heath until after bid
opening, rejected Heath's bid because facsimile bids were not
authorized by the IFB. Id. This protest followed.
Heath argues that the VA should accept its bid because the
contract specialist gave Heath permission to submit its bid by
facsimile, and it would have submitted its bid by courier if not
misled by the contract specialist.
A bid sent by facsimile must be rejected unless permitted by the
solicitation. FAR sect. 14.301(c); see GROH GmbH, B-291980, Mar.
26, 2003, 2003 CPD para. 53 at 2; PBM Constr., Inc., B-271344,
May 8, 1996, 96-1 CPD para. 216 at 2. Moreover, information that
is necessary to submit bids, or the lack of which would be
prejudicial to an uninformed bidder, should be provided to all
prospective bidders in the form of an amendment to the IFB. FAR
sect. 14.308(c). We have found that information concerning the
availability of facsimile transmissions is procurement
information that must be provided to all bidders since facsimile
transmission confers a potential competitive advantage of
permitting more time for bid preparation. PBM Constr., Inc.,
supra, at 2 n.2.
Here, while the record shows that the protester contacted the
very person the agency designated for receipt of questions on
the face of the solicitation--and received a response via email
from that individual--the law and precedent support the VA's
decision to reject this bid. The IFB did not authorize the
submission of bids by facsimile. In addition, Heath could not
rely upon the communication from the contract specialist, who
lacked the authority to amend the solicitation. Although Heath
asserts that it obtained no competitive advantage and in fact
was disadvantaged by faxing its bid, we have long held that the
potential for competitive advantage is sufficient to require an
agency to reject a faxed proposal when the solicitation did not
authorize facsimile transmission.
Finally, although this result is consistent with our prior
decisions, we think that procuring agencies should ensure that
the personnel designated on the face of solicitation documents
to respond to prospective bidders' questions provide accurate
information concerning a solicitation. (Heath
Construction, Inc., B-403417, September 1, 2010) (pdf)
The protester
argues that there is no proof that the agency had in its
possession the CMEC bid prior to the bid opening. It maintains
that the Federal Express tracking document simply shows that
"something" was delivered on March 3 and that there is no
evidence of a bid document with an agency date stamp proving
receipt.
As a general rule, bidders are responsible for delivering their
bids to the proper place at the proper time. United Teleplex,
B-237160.2, Feb. 2, 1990, 90-1 CPD para. 146 at 2. Where as
here, a bid is delivered by a commercial carrier, the bid is
regarded as hand-carried. Watson Agency, Inc., B-241072, Dec.
19, 1990, 90-2 CPD para. 506 at 2. A late hand-carried bid may
be considered for award, however, where improper government
action was the paramount cause of its late delivery and
consideration of the late bid would not compromise the integrity
of the competitive bid system. Id.
Contrary to the protester's assertion, neither procurement
regulations nor decisions of our Office require that timely
receipt of hand-carried bids be proved only by a time/date stamp
or other documentary evidence maintained by the government
installation. Santa Cruz Constr., Inc., B-226773, July 2, l987,
87-2 CPD para. 7 at 2. Where, as here, the issue is whether a
hand-carried bid was timely received by the agency, all relevant
evidence, including commercial carrier records and statements
made by government personnel, may be considered. Id.; Power
Connector, Inc., B‑256362, June 15, 1994, 94-1 CPD para. 369 at
2.
The evidence cited by the agency shows that CMEC's original bid
was timely received by the agency. For example, the Federal
Express tracking sheet submitted by the agency and CMEC shows
that an agency employee signed for the original bid package at
10:51 a.m. on March 3. The record also evidences that CMEC acted
in a manner reasonably calculated to ensure the delivery of the
bid to the contracting officer before bid opening, and it was
the agency's actions that were the paramount cause for the
contracting officer not having the original bid at bid opening.
In this regard, CMEC's bid package was properly addressed to the
contracting officer and delivered to the address stated in the
IFB, and CMEC confirmed with the contracting officer that its
bid had been timely received. The contracting officer, however,
failed to pick up the original bid at the proper location prior
to bid opening.
The contracting officer states that at 2:50 p.m. on March 3,
after he had read the bids at the bid opening, he noticed CMEC's
original bid. The contracting officer then verified that the bid
was received prior to bid opening. We further note that, since
CMEC's bid was delivered to the VA well prior to the bid
opening, and it remained in the VA's possession until it was
opened, acceptance of the bid does not compromise the integrity
of the bidding system. Kelton Contracting, Inc., B-262255, Dec.
12, 1995, 95-2 CPD para. 254 at 3. Moreover, there is no
question that CMEC's bid modification was timely received by the
agency. (Stephen Lucas
Construction, LLC, B-402654, June 9, 2010) (pdf)
As a general rule, bidders are responsible for delivering their
bids to the proper place at the proper time, and late delivery
of a bid generally requires its rejection even if it is the
lowest bid. J.C.N. Constr. Co., Inc., B-270068,
B-270068.2, Feb. 6, 1996, 96-1 CPD para. 42 at 3; Aztec Dev.
Co., B-256905, July 28, 1994, 94-2 CPD para. 48 at 3. A bid
is late if it does not arrive at the office designated in the
solicitation by the time specified, Federal Acquisition
Regulation sect. 14.304(b)(1); Aztec Dev. Co., supra.,
and, normally, receipt at other places, such as a post office
box or the agency’s mailroom, is insufficient. Biones Constr.
& Equipment Co., Inc., B-279575, June 29, 1998, 98-1 CPD
para. 175 at 4-5. In this regard, bidders must allow a
reasonable time for bids to be delivered from the designated
point of receipt (such as in this case, a post office box) to
the bid opening room which is the ultimate destination for bid
opening. See Bay Shipbuilding Corp., B-240301, Oct. 30,
1990, 91-1 CPD para. 161 at 3, n.1. Our review of the record
shows that although the protester’s bid was received at the
agency’s mailroom, an intermediate stop for delivery of the
package, approximately 4 hours prior to bid opening, there is no
evidence that the bid was received by the contracting division
before the 2 p.m. bid opening. Further, the contracting
specialist to whom bids were to be addressed and who conducted
the bid opening did not receive the protester’s bid package
until approximately 2 hours after bid opening. Accordingly, we
find reasonable the agency’s determination that the bid was
late.
While a late hand-carried bid may be considered if it is
determined that the late receipt was due primarily to government
mishandling after receipt at the government installation, a late
bid should not be accepted if the bidder significantly
contributed to the late receipt by not acting reasonably in
fulfilling its own responsibility to submit its bid in a timely
manner. Comspace Corp., B-281067, Nov. 30, 1998, 98-2 CPD
para. 122 at 2. Where, as here, a bidder fails to record on its
bid’s sealed envelope required information as to the
solicitation number it is responding to, and the deadline for
its receipt, and, moreover, as here, also fails to address its
bid submission to the required point of contact at the address
provided in the IFB for bid submission, the bidder is usually
primarily responsible for any delay in its delivery. Boines
Constr. & Equipment Co., Inc., supra. In this case, the
protester failed to address its bid to the appropriate
individual, and failed to mark its bid package envelope in any
way to indicate that it contained time-sensitive bid
information, which caused the package to be sorted for standard
delivery to the contracting division, rather than under the
mailroom’s accelerated procedures for delivery of bid documents.
We agree with the agency that the firm here failed to do what it
reasonably could and should have done to ensure proper delivery,
and its failure to take the available steps to ensure timely
delivery was the paramount cause of the bid’s late receipt.
Since there has been no showing of government mishandling of the
bid package, the bid was properly rejected as late. (Aquaterra
Contracting, Inc., B-400065, July 14, 2008) (pdf)
We find nothing objectionable in the agency’s rejection of
Amigo’s second bid modification. The modification was plainly
late, since it did not reach the designated location for receipt
of bids prior to bid opening. To the extent that the protester
believes that government mishandling was the cause of the
modification’s being late or that Amigo did all it could
reasonably be expected to do to ensure timely delivery, see
Weeks Marine, Inc., supra, we believe that the record
establishes that the protester’s belief is unsupported. As
indicated, by the protester’s own account, the modification was
sent by facsimile at 1:51 p.m. and the transmission took 7.51
minutes to reach the agency’s facsimile machine, thereby
allowing one minute for agency personnel to retrieve, process,
and deliver this modification to the bid opening room. The
record shows that at the time the contract specialist was
notified that it was time to conduct the bid opening, the second
bid modification was not printed in its entirety--page 3 of the
four pages (containing the second page of the bid schedule) was
still printing. This being the case, it was primarily (if not
entirely) the protester’s tardy beginning of the transmission
that caused the failure of the modification to reach the bid
opening room on time. Nothing in the record suggests mishandling
of the modification by the government. Finally, the protester
alleges that the government was legally required to consider the
bid modification, since it was received in the memory of the
agency’s facsimile machine before 2 p.m. and was therefore
effectively in the Corps’s control before bid opening. We
disagree. At least in the circumstances of this case--where the
solicitation clearly placed the risk of facsimile transmission
problems on bidders and yet Amigo nonetheless began transmitting
its second bid modification within the final few minutes before
the start of bid opening--we do not believe that receipt in the
facsimile machine’s memory (assuming, arguendo, that the
modification was in the machine’s memory before bid opening)
qualifies as “under the Government’s control” prior to the time
for receipt of bids as contemplated by the clause at FAR §
52.214-7 so as to require the agency to consider the protester’s
late bid modification. (Amigo-JT Joint
Venture, B-292830, December 9, 2003) (pdf)
When evaluating the acceptability of a late bid outside the
strict confines of the late bid regulations, we are guided by
the general principle that where a bidder has done all it could
and should to fulfill its responsibility, it should not suffer
if the bid is untimely because the government failed in its own
responsibility, so long as acceptance of the bid would not cast
doubt on the integrity of the bidding process. See Palomar
Grading & Paving, Inc., B-274885, Jan. 10, 1997, 97-1 CPD ¶ 16
at 3-4. Accordingly, we have found late bids acceptable where
the government’s affirmative misdirection—such as erroneous
solicitation instructions--was the paramount cause of a bidder’s
untimely delivery of its bid since an agency has an affirmative
duty to establish procedures for the timely receipt of bids. See
id.; Select, Inc., B-245820.2, Jan. 3, 1992, 92-1 CPD ¶ 22 at 4.
In this case, the IFB listed the wrong room for delivery of
bids. This error, which was attributable solely to the
government, directly resulted in Great Lakes submitting its bid
1 minute late. Had the government provided for the receipt of
bids in the room identified in the IFB, there is no doubt that
Great Lakes’ bid would have been timely; the record clearly
demonstrates that Great Lakes was at the room designated for
receipt of bids approximately 5 minutes in advance of the time
set for bid opening. But, because Great Lakes was required to
make its way from the designated bid opening room to the actual
bid opening room, the government effectively caused Great Lakes’
bid to be received late. As a consequence, the misdirection by
the agency was the paramount cause of Great Lakes’ untimely
submission of its bid. As a final matter, it does not appear
that accepting Great Lakes’ bid compromised the integrity of the
procurement. When addressing this issue, the operative question
is whether the late bidder gained an unfair competitive
advantage over other bidders as a result of having submitted its
bid late. See Brazos Roofing, Inc., B-275113, Jan. 23, 1997,
97-1 CPD ¶ 43 at 5. In this regard, the protester emphasizes the
fact that the agency did not receive Great Lakes’ bid until
after approximately three of the protester’s 18 bid line items
had been disclosed. According to the protester, this provided
Great Lakes with the opportunity to decide not to furnish the
bid after bid opening. The protester’s concern, however, is
tempered by the fact that the position in which Great Lakes was
placed resulted from the actions of Corps personnel and was not
by its own design or choosing. Moreover, there is nothing in the
record to suggest that Mr. Inglis, who delivered Great Lakes’
bid, actually heard the prices when they were read. Mr. Inglis
had only a few minutes to go from the the 19th floor to the
actual bid opening room on the 18th floor; when he arrived,
Corps personnel noted that he appeared hurried and out of
breath. Agency personnel also indicated that they did not see
anyone outside the bid opening room when the contracting officer
called time. Under these circumstances, Mr. Inglis’ statement in
his declaration that he did not hear any prices being read prior
to handing Great Lakes’ bid to the agency, seems credible. (Weeks
Marine, Inc., B-292758, October 16, 2003) (pdf)
GPEA contends that the agency has not adequately shown that its
bid was received late. GPEA challenges the agency's reliance on
the log maintained by the security guards because the guards are
not government employees. In our view, the log is acceptable
evidence of the time of receipt. It is undisputed that the log
is a record maintained by the security guards in the regular
course of monitoring the loading dock for the agency, and there
is no reason to challenge its authenticity or reliability. The
fact that the log is compiled by security guards who are
contract employees rather than government employees does not
preclude reliance on the log. See J. L. Malone & Assocs.,
B-290282, July 2, 2002, 2002 CPD ¶ 116 at 5.
GPEA itself submitted a copy of a “customer cartage manifest”
from Airborne Express that purports to show that the bid package
was delivered to the loading dock at 11:49 a.m. on bid opening
day.2 Commercial carrier records, standing alone, however, do
not serve to establish the time of delivery to the agency, since
they are not evidence of receipt maintained or confirmed by the
agency. Valenzuela Eng'g, Inc., B-280984, Dec. 16, 1998, 98-2
CPD ¶ 145 at 3. In any event, to the extent that GPEA relies on
the Airborne Express document to establish that its bid was not
in fact late, receipt of a bid at a mailroom or other receiving
area does not constitute receipt at the office specified in the
IFB. Inland Marine Indus., supra. Thus, even assuming that GPEA
had established that the bid was received at the loading dock
before the closing time--which it has not--the bid nevertheless
properly would be considered late, since there is no evidence
showing receipt of the bid in the specified office by the time
set for receipt of bids in the IFB. (General Power
Engineering Associates, Inc., B-292170, May 28, 2003)
(pdf)
Although the contracting officer
was the official designated in the prospectus as the recipient
of mailed bids, the contracting officer was not present at his
desk or in his office prior to bid opening, and did not return
to his office prior to bid opening to determine whether any last
minute bids had been received. The bid opening official did
check the mailroom and the mail clerk's desk prior to bid
opening, but she too failed to check the contracting officer's
desk. This failure by the cognizant officials to check the desk
of the official designated for receipt of bids constituted
mishandling. (Carroll
Gene Brewer, B-285484, August 22, 2000)
In short, there is no acceptable
evidence which establishes that Cal Marine's bid was received at
the installation prior to bid opening, as required under the
test set forth in Pershield, Inc., supra, at 3, and it follows
that if timely receipt cannot be established by acceptable
evidence, then the second requirement of Pershield--i.e., that
the bid was in the government's sole custody from prior to bid
opening until discovered--is also not met. In this case, the
location of Cal Marine's bid at any time prior to its discovery
on January 14 remains unaccounted for. Accordingly, the bid
cannot be properly considered, Chelsea Clock Co., Inc.,
B-251348.2, May 24, 1993, 93-1 CPD para. 401 at 4, and the
protest is sustained. (Pacific
Tank Cleaning Services, Inc., B-279111.2, July 1, 1998)
However, a late bid should not
be accepted if the bidder significantly contributed to the late
receipt by not acting reasonably in fulfilling its
responsibility for ensuring delivery to the designated place for
receipt by the proper time. Aztec Dev. Co., supra, at 3; John
Holtman and Sons, Inc., B-246062, Feb. 13, 1992, 92-1 CPD para.
187 at 2; J.E. Steigerwald Co., Inc., supra, at 5. Where the
bidder fails to record required information as to the
solicitation number, deadline for receipt and ultimate
destination on the outside envelope provided by the commercial
carrier, the bidder is usually primarily responsible for any
delay in delivery. See Systems for Bus., B-224409, Aug. 6, 1986,
86-2 CPD para. 164 at 3-4. Here, Pierce's failure to mark its
commercial carrier-provided envelope as required by FAR sec.
52.214-5 was the paramount reason for the delay resulting from
the mailroom's "misrouting" of its bid. (Boines
Construction & Equipment Co., Inc., B-279575, June 29,
1998) |