JOCH argues that Trevino’s bid
should have been rejected as nonresponsive, since it did not
state the dollar value for item 2/alternate 1 or item
3/alternate 2. Protest at 8. In this regard, the protester
asserts that without “the Contracting Officer’s calculations,
Trevino’s bid was nonresponsive and did not conform to the
solicitation by failing to use the correct bid schedule, and
failing to calculate its own total amounts for the alternate
bids.” Comments and Supp. Protest at 3.
The agency responds that Trevino’s bid was responsive and
provided all of the necessary information to determine Trevino’s
intended bid. AR at 4. Further, the agency asserts that
Trevino’s failure to include total bid amounts for bid items No.
two and three was waivable under Federal Acquisition Regulation
(FAR) § 14.405, regarding minor informalities or irregularities
in bids. AR at 6-8.
The test for responsiveness is whether a bid offers to perform
the exact thing called for in an IFB, so that acceptance of the
bid will bind a bidder to perform in accordance with all of the
terms and conditions of a solicitation without exception. Randy
Sabala; John Button, B-251221, B-251222, Nov. 24, 1992, 92-2 CPD
¶ 379 at 2. Minor informalities and irregularities in bids may
be waived. FAR § 14.405. A minor informality or irregularity is
one that is “merely a matter of form and not of substance,” and
“[i]t also pertains to some immaterial defect in a bid or
variation of a bid from the exact requirements of the invitation
that can be corrected or waived without being prejudicial to
other bidders.” Id. When a bid contains such a minor informality
or irregularity, the FAR requires that the contracting officer
“either shall give the bidder an opportunity to cure any
deficiency resulting from a minor informality or irregularity in
a bid or waive the deficiency, whichever is to the advantage of
the Government.” Id.
Here, we find that Trevino’s bid was responsive to the
solicitation, and that the submission of prices for the work to
be deleted rather than prices for the work remaining after the
deletion was a waivable minor informality. While Trevino did not
follow the exact instructions of the IFB, it nevertheless
provided prices for the work to be deleted in the bid schedule
for each alternate deductive bid item; thus, the amount of
Trevino’s bid for the remaining work could be ascertained by
simply deducting the dollar amount for the deleted work from the
corresponding base bid. Further, Trevino’s intentions were
evident on the face of the bid, and the contract specialist did
not need to alter Trevino’s bid or take into account information
not included on the face of Trevino’s bid schedule. In these
circumstances, we find that the agency properly concluded that
Trevino’s bid was responsive and properly waived Trevino’s
failure to calculate the total bid amounts for items No. 2 and 3
as a minor informality. See De Ralco, Inc., B-281042, Dec. 7,
1998, 98-2 CPD ¶ 138 at 3‑4 (where awardee entered price for
work to be deleted rather than price of work remaining, agency
properly considered this to be a waiveable informality in
accordance with FAR § 14.405). (JOCH
Construction Company B-410980, B-410980.2: Apr 7, 2015)
(pdf)
There is no dispute that W.B.
failed to submit a price for line item 0036 of the IFB's bid
schedule. Line item 0036 requested a unit and extended price to
"remove between 21 to 50 Trees (24 inches but < [less than] 36
inches)." IFB at 8. The estimated quantity for this line item
was 40 trees. Id. This item was part of a series of tree removal
line items (0021-0038), which were described in the IFB as
follows:
These Bid items consist of removal
and disposal of various size tress within the calipers
indicated. Removal and off site disposal of each tree, stump,
all roots larger than 4 inches in diameter, and backfilling of
any holes are all included in this item as incidental to this
work. Payment will be by each tree within the caliper range
indicated.
IFB § 01 02 00, Description of Bid
Items and Drawing Details, at 4.
While W.B.'s bid omitted the price for line item 0036, it
provided prices for all other of the tree removal line items as
follows:
For 10 trees or less:
Line Item |
Size of tree |
Estimated Quantity |
Unit Price |
Extended Price |
0021 |
6
inches |
10 |
$165 |
$1,650 |
0022 |
6 to
<12 |
10 |
$185.90 |
$1,859 |
0023 |
12 to
<24 |
10 |
$330 |
$3,300 |
0024 |
24 to
<36 |
10 |
$715 |
$7,150 |
For 11 to 20 trees:
Line Item |
Size of tree |
Estimated Quantity |
Unit Price |
Extended Price |
0027 |
6
inches |
40 |
$165 |
$6,600 |
0028 |
6 to
<12 |
40 |
$165 |
$6,600 |
0029 |
12 to
<24 |
40 |
$198 |
$7,920 |
0030 |
24 to
<36 |
40 |
$275 |
$11,000 |
For 21 to 50 trees:
Line Item |
Size of tree |
Estimated Quantity |
Unit Price |
Extended Price |
0033 |
6
inches |
40 |
$110 |
$4,400 |
0034 |
6 to
<12 |
40 |
$132 |
$5,280 |
0035 |
12 to
<24 |
40 |
$165 |
$6,600 |
0036 |
24 to
<36 |
40 |
— |
— |
AR, Tab 4, W.B. Bid, at 7-8.
The agency rejected W.B.'s bid as nonresponsive in part because
it failed to provide a price for line item 0036, and thus, the
bid did not obligate W.B. to provide this item. The agency
stated that this omission affected the price and the bidder's
overall obligations under the contract and could not be waived
as a minor informality. AR, Tab 9, Agency Letter Rejecting
W.B.'s Bid (Sept. 26, 2011). The protester asserts that this
omission was immaterial and was required to be waived as a minor
informality. We find that the agency unreasonably determined
that that W.B.'s bid was nonresponsive. We also find that W.B.'s
omission of line item 0036 could properly be waived as a minor
informality.
To be responsive a bid must constitute an unequivocal offer to
perform the exact thing called for in the solicitation such that
acceptance of the bid will bind the contractor in accordance
with the material terms and conditions of the solicitation.
Custom Envtl. Serv., Inc., B-234774, May 24, 1989, 89-1 CPD ¶
501 at 3. Because the failure to include a price for an item
evidences a bidder's intent not to be bound to perform the item,
as a general rule, a bid must be rejected as non-responsive if
the bid, as submitted, does not include a price for every item
requested by the IFB. Spectrum Leasing Corp., B-216615, Feb. 19,
1985, 85-1 CPD ¶ 211 at 3.
However, where the omission pertains to some immaterial defect
in or variation of a bid from the exact requirements of the IFB,
it can be corrected or waived where it is not prejudicial to
other bidders. FAR § 14.405. A defect or variation is immaterial
if the effect on price, quantity, quality, or delivery is
negligible when contrasted with the total cost or scope of the
services being acquired. Id. Thus, a contracting agency may
waive the failure to bid on an item as a minor informality if
the item for which the price is omitted is divisible from the
solicitation's overall requirements, de minimis as to total
cost, and would not affect the competitive standing of the
bidders. Giberson Plumbing & Excavating, Inc., B-245798, Dec.
27, 1991, 91-2 CPD ¶ 589 at 2-3; TECOM, Inc., B-236929.2, May
11, 1990, 90-1 CPD ¶ 463 at 3-4; Custom Envtl. Serv., Inc.,
supra at 3-4; Leslie & Elliott Co., B-216676, Feb. 19, 1985,
85-1 CPD ¶ 212 at 3.
We first note that line item 0036 is divisible from the overall
ID/IQ contract requirement because the work to be accomplished
under the ID/IQ contract will be ordered through the issuance of
individual task orders. Because the agency was not obligated to
order any of indefinite-quantity work, this line item cannot be
reasonably said to be an essential or integral part of the
overall contract. See TECOM, Inc., supra; cf. HH&K Builders,
B-232140, Oct. 20, 1988, 88-2 CPD ¶ 379 at 3. (omission of a
price for a material requirement, which is not divisible from
the remainder of the solicitation, cannot be waived as minor
informality.)
Moreover, the price for line item 0036 is de minimis as to the
total cost and would not affect the competitive standing of the
bidders. In this regard, the estimate in the revised IGE for
line item 0036 was $187 per tree with an extended price of
$7,480. AR, Tab 8, Revised IGE, at 2. This amount represents
less than .07 percent of the IGE for the total contract cost of
$10,304,987.10.
In addition, it is evident from W.B.'s bid pricing W.B. priced
its tree removal services in an economy of scale fashion, that
is, its unit prices per tree were lower as the total quantities
of trees became higher. Thus, it would be logical to assume that
W.B.'s bid for the removal of 21 to 50 trees would be lower than
its bid for 11 to 20 trees. However, even assuming that W.B.
would have priced line item 0036 at the same price as for
removal of 11 to 20 of the same-sized trees (line item 0030),
that is, $275, the maximum total price for this line item would
be $11,000, which is .12 percent of W.B.'s overall bid price of
$8,984,611.70.
Considering that the price of line item 0036 in comparison to
the overall contract cost is much less than 1 percent, W.B.'s
omission of the line item pricing for item 0036 is clearly de
minimis as to the total cost. Furthermore, the competitive
standing of the bidders would also not be affected because
Tanner's total price is $306,408.80 greater than W.B.'s.
Accordingly, the agency's rejection of W.B.'s bid as
nonresponsive, because it did not include a price for line item
0036, was improper. (W.B.
Construction and Sons, Inc., B-405818; B-405818.2, January
4, 2012) (pdf)
Cedar Electric protested to the agency, and following the VA’s
denial of the protest, protested to our Office. Cedar Electric
primarily argues that Amendment 8 is a material amendment that
cannot be waived, and that Seawolf’s bid should have been
rejected. In particular, Cedar Electric contends that the
Schedule for Finishes constitutes a significant design change
that imposes new legal obligations and increases the cost of
performance. The agency responds that Amendment 8 is not
material because the Schedule for Finishes was referenced in
Amendment 5, which Seawolf acknowledged. In the alternative, the
agency argues that the price impact of Amendment 8 is not
significant in relation to the value of the total project and
therefore is not material.
A bidder’s failure to acknowledge a material amendment to an IFB
renders the bid nonresponsive, since absent such an
acknowledgment the government’s acceptance of the bid would not
legally obligate the bidder to meet the government’s needs as
identified in the amendment. Federal Constr., Inc., B-279638,
B-279638.2, July 2, 1998, 98-2 CPD para. 65 at 2. An amendment
is material if it would have more than a negligible impact on
price, quantity, quality, or delivery. FAR sect. 14.405(d)(2).
Moreover, our Office has held that an amendment is not material
where it does not impose any legal obligations on the bidder
different from those imposed by the original solicitation--for
example, where it merely clarifies an existing requirement or is
a matter of form--or has a negligible impact on the relative
standing of the bidders. Kalex Constr. & Dev., Inc., B-278076.2,
Jan. 20, 1998, 98‑1 CPD para. 25 at 2. A bidder’s failure to
acknowledge an amendment that is not material is waivable as a
minor informality. FAR sect. 14.405; Overstreet Elec. Co., Inc.,
B-283830, B-283830.2, Dec. 30, 1999, 2000 CPD para. 8 at 7. No
precise rule exists to determine whether a change required by an
amendment is more than negligible; that determination is based
on the facts of each case. K Services, B-238744, June 13, 1990,
90-1 CPD para. 556 at 2, citing DeRalco, Inc., B‑233996, Mar.
29, 1989, 89-1 CPD para. 327.
We find that Amendment 8 is not a material amendment because the
inclusion of the Schedule for Finishes in Amendment 8 does not
constitute a change in the legal obligations of the bidders to
meet the government’s requirements. The references to the
Schedule for Finishes in Amendment 5 put bidders on notice that
the Schedule for Finishes existed as a contract requirement
which they were obligated to fulfill. The Schedule for Finishes
was included in the list of attachments to Amendment 5, even
through the agency neglected to provide the actual schedule at
that time. Amendment 5 required the contractor to submit for
approval all samples required by the Schedule for Finishes in
quadruplicate. Moreover, several of the specifications attached
to Amendment 5 specifically stated that “color, pattern, and
texture” performance requirements were specified in the Schedule
for Finishes. All of these references, combined, clearly
indicate that Amendment 5 created a legal obligation for
contractors to perform in accordance with the Schedule for
Finishes, even though the schedule was not attached to the
amendment. See B‑173563, Nov. 12, 1971, 51 Comp. Gen. 293
(1971). Because Amendment 8 was not a material amendment, VA
acted appropriately in waiving Seawolf’s failure to acknowledge
the amendment. (Cedar Electric,
Inc., B-402284.2, March 19, 2010) (pdf)
Conduit’s failure to calculate its overtime rates correctly
constituted a minor informality. Overtime rates were not
included in the calculation of the bid prices for purposes of
determining the low bidder, so it is not clear--and the
protester has not explained--how any other bidder could have
been prejudiced by Conduit’s miscalculation. Second, nothing in
Conduit’s miscalculation alters the obligation established in
its bid to perform the exact thing called for under the IFB;
Conduit is legally obligated to perform the contract, including
overtime, in exact accordance with the terms of the
solicitation. Third, the record shows that Conduit’s bid
will result in the lowest price to the government even given the
miscalculation. In this regard, the difference between Conduit’s
bid (as recalculated by the agency to account for the change in
the wage rate determination) and ALC’s bid is $7,217,450. The
error in Conduit’s calculation of its overtime rates amounts to
$1.86 per hour of overtime ($1.87 in the case of one line item).
AR, exh. 10, Letter from Conduit to Agency, June 6, 2006,
attach. 1. Applying this hourly difference, even if every
estimated hour under the IFB for SCA employees were priced as an
overtime hour (a virtual impossibility, since overtime is
defined in the IFB as work in excess of 40 hours per week), the
additional cost of Conduit’s performance would be less than the
difference between the two bids. We conclude that Conduit’s
miscalculation was a waivable minor informality that did not
affect the responsiveness of the bid. (AllWorld
Language Consultants, Inc., B-298831, December 14, 2006) (pdf)
The
solicitation called for sealed bids offering to purchase various
species of government-owned timber. Minimum acceptable rates
were set forth for each species. For white oak sawtimber, the
minimum acceptable rate was set at $33.22 per unit with an
estimated quantity of 71 ccf (hundred cubic feet). Bids were
opened on September 12, 2006, and Squires was the high bidder
with an overall bid of $184,051.68. Winslow-Bateman Forestry was
the second high bidder at $123,968.31. The agency noted,
however, that Squires had bid only $26.09 per unit for the white
oak sawtimber portion of the sale. Since this bid was below the
minimum acceptable rate, the contracting officer rejected
Squires’ bid as nonresponsive and made award to Winslow-Bateman.
Squires claims that it intended to bid the required minimum for
all species, and that its bid on the white oak sawtimber was the
result of an arithmetic error in calculating its price which it
should be permitted to correct.
Although, as a general rule, a bid must be rejected as
nonresponsive where it does not strictly conform to the
solicitation’s terms and conditions, this rule does not apply to
deviations which are immaterial or matters of form rather than
substance. We have held that where the discrepancy between the
minimum advertised rate for a particular species of timber and
the rate actually bid is clearly “negligible,” the discrepancy
may be viewed as a minor informality and the pricing defect may
be corrected. Building By Thrift, Inc., B-215036, June 28, 1984,
84-1 CPD para. 691; W-1 Forest Prods., Inc., B-204168.2, Feb.
17, 1982, 82-1 CPD para. 138. In this case, we conclude that the
discrepancy between Squires’ bid of $26.09 per unit of white oak
sawtimber and the specified minimum of $33.22 per unit (a
difference of $7.13 per unit) is negligible. Squires’ bid would
have been $506.23[1] higher (for a total bid of $184,557.91) had
Squires bid the minimum rate for white oak--a discrepancy
resulting in a 0.275 percent increase in Squires’ total bid.
Moreover, since Squires was the high bidder by more than
$60,000, and the $506.23 adjustment to Squires’ bid is an upward
adjustment, making Squires’ price even more favorable to the
government, there is no possibility that any other bidder would
be prejudiced or that the integrity of the procurement process
would be undermined by adjusting Squires’ bid. Accordingly, we
conclude that Squires’ bid is responsive, that the $506.23
pricing defect can be corrected as a minor informality, and that
Squires should therefore receive the award if otherwise
eligible. (Squires Timber
Company, B-298859, December 1, 2006) (pdf)
Additionally,
while the bid evidences that Thompson at some point changed its
prices to $8.01 and $7.01 without initialing the changes, our
Office has consistently held that a bidder's failure to initial
changes is a matter of form that may be waived by the agency as
a minor informality, where, as here, there is no doubt as to
intended bid. Stone Forest Indus., Inc., B-246123, Feb. 7, 1992,
92-1 CPD P: 161 at 1-2; Jordan Contracting Co.; Griffin Constr.
Co., Inc., B-186836, Sept. 16, 1976, 76‑2 CPD P: 250
at 2. (Delta
Timber Company, B-290710, September 6, 2002) (pdf)
|