|
New Our Office
examines an agency's evaluation of past performance to ensure
that it was reasonable and consistent with the stated evaluation
criteria and applicable statutes and regulations; however, the
necessary determinations regarding the relative merits of
offerors' proposals are primarily matters within the contracting
agency's discretion. Kay & Assocs., Inc., B-291269, Dec. 11,
2002, 2003 CPD para. 12 at 4. In this regard, our Office will
not question an agency's determinations absent evidence that
those determinations are unreasonable or contrary to the stated
evaluation criteria. Id. A protester's mere disagreement with
the agency's judgment does not establish that an evaluation was
unreasonable. UNICCO Gov't Servs., Inc., B-277658, Nov. 7, 1997,
97-2 CPD para. 134 at 7.
We first note that Dunamis did provide the requisite past
performance references with its proposal. In this regard,
Federal Acquisition Regulation (FAR) sect. 15.305(a)(2)(iii)
directs agencies to take into account past performance
information regarding predecessor companies, key personnel, and
major subcontractors when such information is relevant to an
acquisition. Thus, an agency properly can consider the relevant
experience and past performance history of the individual joint
venture partners of the prime contractor in evaluating the past
performance of a joint venture, so long as doing so is not
expressly prohibited by the RFP. MVM, Inc., B‑290726 et al.,
Sept. 23, 2002, 2002 CPD para. 167 at 4; Network Sec. Techs.,
Inc., B‑290741.2, Nov. 13, 2002, 2002 CPD para. 193 at 9. The
RFP here did not prohibit considering the past performance of
individual joint venture partners in evaluating an offeror's
past performance; indeed, the RFP specifically encouraged
offerors to provide such information and advised that
consideration would be given to the relevant past performance of
the joint venture partners. RFP sect. M at 3. Because at least
three past performance references for the joint venture partners
were provided in Dunamis's proposal and because it provided
sufficient information regarding these referenced contracts on
the forms provided in the RFP, Dunamis satisfied the RFP
requirements. (Advanced
Environmental Solutions, Inc., B-401654, October 27, 2009)
(pdf)
On October 6, HHS
requested dismissal of the protest on the grounds that Divakar’s
claims were factually baseless. After our Office convened a
conference call with the parties, and declined to dismiss the
protest, counsel for HHS offered to provide to Divakar (with
SKY’s agreement) a copy of the experience/past performance
section of SKY’s proposal, and a copy of the corresponding page
of HHS’s evaluation. With this information, HHS sought to
persuade Divakar to withdraw its protest. Instead, Divakar filed
a supplemental protest.
Divakar’s supplemental protest argued that it was improper for
HHS to credit SKY with the experience and past performance of
SKY’s key personnel at times when those individuals had been
employed by other firms, or were assisted by other people, or
when SKY was a subcontractor to another firm. Supplemental
(Supp.) Protest at 2. Divakar also argued that SKY was not
listed in the central contractor registry until 2009, and
therefore could not claim experience before that time. Supp.
Protest at 1, 3, 5. In addition, Divakar argued that SKY’s
proposal failed to include a resume for an administrative
assistant, that HHS had been motivated by bad faith in selecting
SKY over Divakar, and that HHS had provided Divakar with a
defective debriefing.[5] Supplemental (Supp.) Protest at 6-7.
On October 15, HHS filed materials that, in essence, constituted
an agency report. On October 26, Divakar filed comments.
Divakar argues that SKY lacks experience and has no relevant
past performance, because the firm’s references were for work
performed by SKY’s key personnel, rather than by SKY itself as a
business entity, or were for work performed by SKY as a
subcontractor. Divakar argues that HHS therefore was required to
find that SKY lacked relevant past performance, and was required
to give SKY a neutral rating. Divakar Comments at 1. Divakar
argues that if SKY had received a neutral rating for
experience/past performance, the CO would have selected Divakar
as the best value.
Where a solicitation calls for the evaluation of experience and
past performance, we will examine the record to ensure that the
evaluation was reasonable and consistent with the solicitation’s
evaluation criteria and procurement statutes and regulations.
MIL Corp., B-297508, B-297508.2, Jan. 26, 2006, 2006 CPD para.
34 at 10. Nothing in the RFQ prohibited the agency from
evaluating experience/past performance information where the
vendor had been a subcontractor. See George G. Sharp, Inc.,
B‑401077, B-401077.2, Apr. 15, 2009, 2009 CPD para. 87 at 5
(agency properly considered experience gained as a
subcontractor). Likewise, in evaluating a firm’s experience and
past performance, it is proper for an agency to consider the
experience of proposed key personnel. Id. Here, SKY’s quotation
showed that the firm’s proposed key personnel had performed in
key roles on contracts submitted as experience/past performance
references. Therefore the evaluation record supports the
evaluators’ judgments that the experience of SKY’s key personnel
would be brought to bear in the firm’s work for SAMHSA, and that
SKY’s experience/past performance was highly relevant to the
work under the RFQ. In short, the evaluation of SKY’s
experience/past performance was reasonable in our view.
In summary, the contemporaneous evaluation record provides a
reasonable basis for HHS to consider SKY’s experience/past
performance to be uniformly superior. The RFQ specified that
experience/past performance was significantly more important
than cost, and therefore the CO reasonably justified the
selection of SKY’s higher-rated, higher-cost proposal over
Divakar’s. (Divakar
Technologies, Inc., B-402026, December 2, 2009) (pdf)
Health Net contends that TMA’s evaluation of AGHP’s past
performance was fundamentally flawed and that it was not
entitled to a “High Confidence” past performance rating. Among
other things, Health Net argues that it was unreasonable for TMA
to consider contracts performed by entities other than AGHP in
evaluating AGHP’s past performance. Health Net also maintains
that TMA failed to meaningfully consider the limited size of the
prior contracts, as reflected by the relatively small
beneficiary populations covered by the contracts, when it
assigned AGHP the highest past performance rating. We sustain
the protest on these grounds.
Where a solicitation requires the evaluation of offerors’ past
performance, we will examine an agency’s evaluation to ensure
that it was reasonable and consistent with the solicitation’s
evaluation criteria. The MIL Corp., B-297508, B-297508.2, Jan.
26, 2006, 2006 CPD para. 34 at 10; Hanley Indus., Inc.,
B-295318, Feb. 2, 2005, 2005 CPD para. 20 at 4. The critical
question is whether the evaluation was conducted fairly,
reasonably, and in accordance with the solicitation’s evaluation
scheme. Clean Harbors Envtl. Servs., Inc., B-296176.2, Dec. 9,
2005, 2005 CPD para. 222 at 3.
In its proposal, AGHP indicated that it had not had any active
business operations in the past 3 years. AR, Tab 40, at 699. As
a consequence, AGHP did not have any relevant past performance
of its own under the terms of the RFP, which defined relevant
past performance as limited to contracts “concluded within the
last three years.” RFP at 103. This lack of relevant experience
was acknowledged by the PAG. AT, Tab 10, PAG Final Report for
AGHP, at 2.
Lacking relevant past performance of its own, AGHP submitted
past performance information for its “team.” According to AGHP,
this team “brings together AGHP, a wholly owned subsidiary of
Aetna Life Insurance Company; its parent, Aetna Inc.; and their
affiliates (collectively referred to as Aetna) for expertise and
assistance,” as well as its first-tier subcontractor WPS (which
was to be primarily responsible for claims processing). AR, Tab
10, PAG Final Report for AGHP, at 1-2. The PAG and the SSEB
indicate that they based their evaluation of AGHP’s past
performance on the activities of its parent, its affiliates, and
WPS. AR, Tab 8, SSEB Report, at 26; AR, Tab 10, PAG Final Report
for AGHP, at 1-2.
An agency properly may attribute the experience or past
performance of a parent or affiliated company to an offeror
where the firm’s proposal demonstrates that the resources of the
parent or affiliate will affect the performance of the offeror.
Perini/Jones, Joint Venture, B-285906, Nov. 1, 2000, 2002 CPD
para. 68 at 4. The relevant consideration is whether the
resources of the parent or affiliated company--its workforce,
management, facilities or other resources--will be provided or
relied upon for contract performance such that the parent or
affiliate will have meaningful involvement in contract
performance. Ecompex, Inc., B-292865.4 et al., June 18, 2004,
2004 CPD para. 149 at 5.
TMA maintains that it reasonably attributed to AGHP the past
performance information of its parent corporation and affiliated
companies. In this regard, the PAG concluded that “AGHP’s parent
organization is sufficiently involved in the daily operations of
the offeror that the performance record of the parent reflects
the performance of the organization.” AR, Tab 10, PAG Final
Report for AGHP, at 9. In reaching this conclusion, the PAG
noted:
Aetna states AGHP will be subject to the
overall leadership of the Aetna Inc. board of directors. Aetna
states AGHP will be operated as a distinct legal entity under
the direction of its own board of directors with substantial
independent operational flexibility but, as a wholly owned
subsidiary, Aetna’s best practices, innovations, information
technology capabilities and thought leadership are available to
AGHP. Many AGHP staff members will be drawn from other Aetna
operations and AGHP and a variety of Aetna corporate staff
functions will support the AGHP operations, including [Deleted].
AR, Tab 10, PAG Final Report for AGHP, at
1.
The PAG’s findings in this regard mirror the representations
contained in AGHP’s proposal. AR, Tab 40, AGHP Past Performance
Proposal, at 688, 700, 706.
The record reflects that for each of the five contracts
identified by AGHP for the purpose of evaluating its past
performance, AGHP identifies the contract as having been
performed generically by “Aetna.” AR, Tab 40, AGHP Past
Performance Proposal, at 721, 727, 731, 735, and 741. Elsewhere
in its proposal, however, AGHP explains that its ultimate parent
is currently Aetna, Inc., and the term “Aetna” is the brand name
used for one or more of the Aetna group of subsidiary companies,
which include Aetna Life Insurance Company, as well as the
following HMO entities that are licensed or otherwise qualified
to provide health care coverage in the states that comprise the
TRICARE North Region: Aetna Health Inc. (CT), Aetna Health Inc.
(ME), Aetna Health Inc. (NY), Aetna Health Inc. (NJ), Aetna
Health Inc. (PA, IN, KY, MA & OH), Aetna Health Inc. (DE), Aetna
Health Inc. (MD, D.C. & VA), Aetna Health of the Carolinas Inc.
(NC & SC), Aetna Health of Illinois Inc. (IL & IN), and Aetna
Health Inc. (MI). AR, Tab 40, AGHP Past Performance Proposal, at
707.
The flaw with TMA’s analysis originates in the complex network
of corporate entities which comprise the “Aetna brand,” AGHP’s
general references to “Aetna’s” role in performing the
requirements, and the general references to “Aetna” past
performance information. Given the repeated use of the general
reference to “Aetna” throughout AGHP’s proposal, the PAG did not
know the specific roles, if any, the various Aetna entities
would have in performance of the T-3 effort. Nor did the PAG
have any insight regarding which specific Aetna entities had
performed the contracts referenced in AGHP’s past performance
proposal; therefore, the PAG could not know what role, if any,
the entities that had performed the prior contracts would have
in performance of AGHP’s T-3 contract. Given this lack of
information, TMA’s reliance on past performance by “Aetna” in
its assessment of AGHP effectively attributed to AGHP the past
performance of other Aetna corporate entities based on the mere
fact of their corporate affiliation. Absent some more definitive
indications of what entities performed what contracts and what
roles they would have in performing the T-3 effort, there was no
basis for TMA to consider, let alone give credit in the
evaluation for, the “generic” Aetna past performance submitted
with its proposal.[8] See Universal Building Maintenance, Inc.,
B-282456, July 15, 1999, 99-2 CPD para. 32 (sustaining protest
where agency unreasonably based evaluation on past performance
of awardee’s corporate affiliate and parent company). (Health
Net Federal Services, LLC, B-401652.3; B-401652.5, November
4, 2009) (pdf)
AAJV asserts that Chugach's parent and sister companies are not
teamed with or otherwise contractually committed to perform the
awarded contract, and that it therefore was improper for the
agency to consider those firms' past performance and experience
in evaluating Chugach's proposal.
An agency properly may consider the experience or past
performance of an offeror's parent or affiliated companies where
the firm's proposal demonstrates that the resources of the
parent or affiliated company will affect the performance of the
offeror. See, e.g., Perini/Jones, Joint Venture, B-285906, Nov.
1, 2000, 2002 CPD para. 68 at 4; Federal Acquisition Regulation
15.305(a)(2)(iii). We find that this was the case here.
Chugach's proposal stated that its parent company's (Chugach
Alaska Company (CAC)) and several of its sister companies'
resources--including workforce, management, key personnel,
facilities and performance strategies--would be provided and
relied upon for contract performance. Chugach Proposal at B-1.
For example, the proposal stated that Chugach would transition
key personnel from the current COOM contract in Guam performed
by a sister company; had reach-back capability to tap more than
6,000 CAC and affiliate employees worldwide; and would rely on
the expertise of various subject matter experts, including two
named personnel--an individual who had been the project manager
on an affiliate's base operating systems contract on Wake Island
as well as the COOM project manager for the incumbent Guam
contract, and Chugach's own president, who had experience with
Chugach and two of its affiliates on 21 prior contracts. Id. at
2, C-3, C-4. In addition, CAC would provide general and
administrative support, including accounting, human resources,
legal and risk, compliance and regulatory information
technology, project transition, and business development
services. Id. at C-1. CAC representatives would also assist with
interviewing and hiring employees; meeting security
requirements; overseeing safety, quality control, and accounting
setup; purchasing or leasing equipment; and bringing utilities
on line. Id. The fact that these affiliates and personnel are
not contractually bound to perform these services, does not
render the agency's consideration of their experience and past
performance unreasonable. The RFP did not require any such
commitment and, based on Chugach's representations, we think the
agency reasonably concluded that Chugach's proposal demonstrated
that the resources of the parent and affiliated companies would
affect Chugach's performance. Perini/Jones, Joint Venture,
supra. Thus, there was nothing improper in the agency's
consideration of their respective experience and past
performance.
AAJV asserts that, even if it were otherwise permissible for the
agency to consider Chugach's parent's and affiliates' experience
and past performance, the RFP here effectively precluded their
consideration. See Doyon-American Mech., JV; NAJV, LLC,
B‑310003, B-310003.2, Nov. 15, 2007, 2008 CPD para. 50 at 4
(reliance on a third party's experience and past performance is
contingent upon the absence of any solicitation provision
precluding such consideration).
AAJV's assertion is without merit. In Doyon-American, the RFP
clearly restricted past performance and experience information
to "[o]nly those projects for which the Offeror or a primary
teaming partner was the Prime Contractor." Id., 2008 CPD para.
50 at 2-3. In contrast, the RFP here did not provide such direct
guidance; instead, with regard to the past performance factor,
the RFP provided that the "term 'offeror' typically refers to a
single corporation submitting a proposal as a prime contractor,"
and that, in evaluating past performance and experience, the
government's "evaluation will generally focus on the entities
submitting the proposal." RFP sect. L, at 37. While offerors
"typically" were single corporations and the government would
"generally" focus on those entities, nothing in the RFP
prohibited an offeror from submitting--or the agency from
evaluating--information relating to corporate parents and
affiliates. (AMI-ACEPEX, Joint
Venture, B-401560, September 30, 2009) (pdf)
Initially, Ahtna argued that the Army improperly downgraded its
proposal for its lack of experience, even though it had proposed
one of the incumbent CCAD motor pool operators as a
subcontractor. After receiving the agency report, Ahtna refined
its position to argue that while neither firm had relevant prime
contract experience operating a government motor pool--and both
had relied on subcontractors with motor pool experience--Ahtna
was downgraded for its lack of prime contract experience, but
Goldbelt was not. Thus, the protester contends that the agency
treated the offerors unequally by crediting Goldbelt with the
experience of its subcontractor, but not similarly crediting
Ahtna.
(sections deleted)
With respect to Goldbelt's evaluation, the
panel chair explained that the three evaluated strengths
attributed to "[b]oth [Goldbelt] and ICI," were intended to
reflect the strengths of the two firms together, as a team. Tr.
at 41-42. When cross-examined on whether each of the three
strengths was equally valid if applied to Goldbelt alone
(exclusive of ICI), he acknowledged that Goldbelt's experience
did not include operation of a motor pool as a prime contractor.
Tr. at 42. Nonetheless, the evaluation panel chair maintained
that Goldbelt's Dahlgren contract for supply services operations
was "remarkably similar" to the operation of the CCAD motor
pool. Tr. at 61. He explained that this conclusion was based on
Goldbelt's representations, in its proposal, that it was
required to dispatch and maintain its own vehicles, and that the
Dahlgren contract also involved licensing forklift operators.
Tr. at 23-24. Although Goldbelt's proposal did not describe how
many vehicles or forklift operators were managed at Dahlgren,
the chair of the evaluation panel acknowledged that the
evaluators had not sought more information from either Goldbelt
or the Navy--the agency for whom Goldbelt performed the Dahlgren
contract. Tr. at 63, 68-69, 88.
With respect to Ahtna's evaluation, the panel chair testified
that he had viewed Ahtna separately from its subcontractor, All
Star. Tr. at 50. When asked to characterize the meaning of the
weakness assessed to Ahtna, he testified that Ahtna's lack of
experience in operating a motor pool was "extremely significant"
to the evaluation because "[i]f the prime contractor doesn't
have that experience, that is a significant risk." Tr. at 93.
During the hearing we also heard the testimony of the CO, who
explained that the difference in Goldbelt's and Ahtna's
evaluation under the motor pool experience subfactor was a
significant factor in her award decision. Tr. at 148. She also
testified that she concurred in the evaluators' judgment that
Goldbelt's experience on its Dahlgren contract was relevant to
the CCAD scope of work. Tr. at 149‑50. In addition, the CO
testified that all three of Goldbelt's past performance
contracts--including those for maintenance and repair of
research laboratory equipment, and for shipping and related
services--were "very relevant" to the services here. Tr. at
151-52. In contrast, she testified that, in her view, Ahtna's
four prior contracts were "not very relevant." Tr. at 152-54,
160-61.
In assessing the evaluation here, we note first that the Federal
Acquisition Regulation (FAR) sect. 15.305(a)(2)(iii) directs
agencies to take into account past performance information
regarding subcontractors that will perform major or critical
aspects of the requirement. On the other hand, the significance
of, and the weight to be assigned to, a subcontractor's past
performance is a matter of contracting agency discretion. See
Loral Sys. Co., B-270755, Apr. 17, 1996, 96-1 CPD para. 241 at
5; see also Strategic Res., Inc., B-287398, B-287398.2, June 18,
2001, 2001 CPD para. 131 at 5-6. The weight to be assigned a
prime contractor's past performance--or lack thereof--is also a
matter of contracting agency discretion. Alpha Data Corp.,
B-291423, Dec. 20, 2002, 2003 CPD para. 18 at 4-5.
Nevertheless, while an agency may reasonably emphasize one
firm's lack of a particular type of relevant experience, it
cannot then ignore another firm's similar lack of experience.
E.g., U.S. Prop. Mgmt. Serv. Corp., B‑278727, Mar. 6, 1998, 98‑1
CPD para. 88 at 6 (protest sustained where agency emphasized
protester's lack of corporate experience, but disregarded
similar lack of experience for the awardee by substituting
experience of the awardee's key personnel).
In our view, the record here demonstrates that the Army did not
treat these offerors equally under the motor pool experience
subfactor within the past performance evaluation factor. Rather,
the agency combined the experience of Goldbelt and its
subcontractor, ICI, for purposes of that evaluation, and, in
certain respects, assessed strengths for both companies that are
based on the subcontractor's (ICI's) experience.[5] In contrast,
when the Army evaluated Ahtna, the agency focused separately on
Ahtna's lack of motor pool experience, without similarly
considering its subcontractor, All Star (the incumbent
subcontractor for the CCAD motor pool), even though the record
shows that the evaluators viewed the experience of ICI and All
Star as essentially equal. Tr. at 21-22, 30, 46-48. There is no
reasonable basis for this disparate treatment in the record.
To the extent that the agency's evaluation was based on its
conclusion that Goldbelt's Dahlgren contract was "remarkably
similar," Tr. at 61, to the operation of the CCAD motor pool, we
find that conclusion lacked significant support in the record.
Instead, the record indicates that Goldbelt's Dahlgren contract
involved--according to the description in Goldbelt's
proposal--providing 8.5 of 16.5 full time equivalent workers,
primarily for managing supply operations, not for providing
motor pool services to the Navy. AR, Tab E, Goldbelt Proposal,
vol. II, at 16. There appears to be a significant difference in
the apparent scope of the effort at Dahlgren and the work here,
which, as described above, involves over 390 vehicles, and
numerous other activities, including training and licensing
2,000 to 3,000 vehicle operators. RFP at 24; Tr. at 23, 88.
(Ahtna Support and Training Services,
LLC, B-400947.2, May 15, 2009) (pdf)
The SSA also considered that PlanetSpace’s subcontractors were
responsible for most of the technical aspects of the proposal
and that PlanetSpace itself had no relevant experience managing
a contract with this level of complexity in a fixed-price
environment, while OSC’s proposal was assigned a significant
strength because of its utilization of existing processes and
tools to manage fixed-price spacecraft development, operations
and repetitive production contracts, OSC’s subcontracting team
had a much smaller role in contract performance, and OSC had
extensive in-house expertise in specific areas of the CRS
requirements. The SSA concluded that, accordingly, he “had much
higher confidence” in OSC’s ability to provide resupply services
on a fixed-price basis, id., and that OSC’s proposal “was
superior due to the serious Management risks inherent in the
PlanetSpace proposal.” SSD at 17. Indeed, while recognizing
PlanetSpace’s lower price, the SSA stated that he “could not
conduct [a] ‘typical’ trade-off analysis since I believed there
was a low likelihood PlanetSpace could successfully perform the
contract.” Id. The SSA concluded that SpaceX’s and OSC’s
proposals represented the best value to the government.
(Sections deleted)
TEAMING APPROACH
Subcontractor Performance
PlanetSpace asserts that the evaluation of its teaming approach
was unreasonable and/or otherwise improper. As an initial
matter, the protester contends that the consideration given to
past performance in the SSD was inconsistent with the RFP, which
provided that offerors without a record of relevant past
performance or for which information on past performance is not
available “will not be evaluated favorably or unfavorably on
past performance.” RFP amend. 3, sect. VII. PlanetSpace asserts
that, notwithstanding this provision, the agency evaluated its
proposal unfavorably based on a finding that it lacked relevant
past performance.
The record does not support PlanetSpace’s assertion. As
discussed above, in considering the SEB’s assessment of
significant strengths based on the past performance of
PlanetSpace’s subcontractors/team members, the SSA simply
disagreed with the SEB’s finding of a significant strength.
Again, the SSA concluded that the finding was “offset by
PlanetSpace’s lack of experience in development, production and
operation of large, complex space systems,” and that the
subcontractors’ past performance should not be “discriminators
for selection when almost all of the technical expertise
appeared to reside at the subcontractor level.” SSD at 11-12.
Thus, the SSA determined only that the protester’s record of
past performance should not be considered as a discriminator; he
did not downgrade the proposal overall under the past
performance factor. (PlanetSpace,
Inc., B-401016; B-401016.2, April 22, 2009) (pdf)
Next, with respect to the evaluation of the awardee’s experience
and past performance, Aegis complains that the Corps
misevaluated GSG-IS by allowing it to substitute the experience
and past performance of GSG-IS’s subcontractors, because GSG-IS
itself is a recently-formed entity and therefore had neither
past performance nor experience. Aegis also argues that GSG‑IS
should not have received credit for the experience and past
performance of [DELETED] in analyzing intelligence and running a
national operations center.[8] Aegis argues that since [DELETED]
cannot obtain a facility security clearance, it cannot have any
role in performing intelligence or national operations center
functions, and thus its experience and past performance in those
areas should have been excluded as irrelevant.
The Corps argues that where, as here, an offeror’s performance
relies significantly on a team member or subcontractor, an
agency may consider that firm’s experience and past performance.
Since GSG-IS’s team members, including [DELETED], will perform
significant shares of the contract, the Corps argues that it was
proper to consider the experience and past performance
references of those firms. The Corps disputes the foundation of
Aegis’s argument--that an offeror’s experience and past
performance are only relevant if the offeror itself is
performing the corresponding services under the pending
contract.
Our Office affords agencies discretion in the evaluation of past
performance. Family Entm’t Servs., Inc., B-291997.4, June 10,
2004, 2004 CPD para. 128 at 5. The record here reflects that the
Corps considered the experience and past performance cited by
GSG-IS to show that it was familiar with providing similar
services in Afghanistan, and that it had shown an excellent
record of performance. Although Aegis argues that the experience
of [DELETED] cannot be considered relevant since that firm lacks
a security clearance, we believe the Corps had discretion to
rely on that experience and past performance in evaluating GSG-IS,
since [DELETED] is providing material services under the
contract. In particular, GSG-IS described [DELETED]’s role as
providing “security, logistics, and operations support.” GSG-IS
Proposal, Mar. 18, 2008, vol. I at 1. In our view the agency
reasonably rated GSG-IS excellent under the experience and past
performance factors. (Aegis
Defence Services Limited, B-400093.4; B-400093.5, October
16, 2008) (pdf)
Licenses and permits
The RFP’s performance work statement (PWS) required the
successful contractor to pick-up, transport, and treat and/or
dispose of medical waste in accordance with all applicable
county, Florida state, and federal (Environmental Protection
Agency and Department of Transportation) laws, policies and
guidelines, as well as VA infectious medical waste requirements.
PWS sect. D.1.2. The contractor was also required to “maintain
all necessary medical waste permits and licenses for the
disposal and treatment of such waste.” Id.
AES asserts that NEIE is not technically capable of performing
the contract because it does not meet the RFP’s license
requirements. Specifically, it maintains that NEIE is not a
Florida corporation and lacks a Florida Department of Health
permit to provide biomedical waste transportation and disposal
services. In AES’s view, NEIE cannot “maintain” the necessary
licenses and permits because it must rely on its subcontractor,
Healthcare Waste Solutions of Florida, LLC (HWS), to handle the
waste.
This argument is without merit. The RFP did not require any
specific license or permit as a precondition to receiving award
but, rather, only required that the contractor maintain all
necessary permits and licenses and that it perform the work in
accordance with applicable laws. Whether an offeror,
prospectively, was capable of meeting this performance
requirement was a matter of the firm’s responsibility. See
SourceLink Ohio, LLC, B-299258, Mar. 12, 2007, 2007 CPD para. 50
at 4. The RFP provided for offerors to submit copies of their
permits and licenses with their proposals, presumably for
purposes of enabling the agency to determine offerors’
responsibility in this area. NEIE responded to the requirement
by submitting copies of HWS’s Florida biomedical waste licenses
and permits. There was nothing improper or unreasonable in the
agency’s accepting and considering this information, since there
is nothing improper in an offeror’s meeting licensing
requirements through a subcontractor. See The Ensign-Bickford
Co., B-274904.4, Feb. 12, 1997, 97‑1 CPD para. 69 at 4 (agency’s
allowing offeror to rely on licensed subcontractor and its plan
for waste management tasks was reasonable). We conclude that the
agency reasonably relied on HWS’s information in finding that
NEIE was a responsible offeror.
Experience
AES asserts that NEIE began business in August 2007, just 2
months before the closing date. In the protester’s view, NEIE
lacks relevant experience and it was unreasonable for the agency
to rely on the experience of NEIE’s “sister” company, NEIE, Inc.
Protest at 2.
AES’s assertions are without merit. The RFP required offerors to
provide a description of their applicable experience in the area
of biomedical waste services, but did not specify any amount of
experience or restrict the source of the experience. RFP para.
5.1.2. An agency properly may consider the experience of a
predecessor firm or of the corporation’s principal officers that
was obtained prior to its incorporation date. Trailboss Enters.,
Inc., B‑297742, Mar. 20, 2006, 2006 CPD para. 64 at 4; R.J.
Crowley, Inc., B-229559, Mar. 2, 1988, 88-1 CPD para. 220 at 6.
NEIE Medical Waste Services, LLC was formed when its predecessor
(“sister”) company, NEIE, Inc., divided its business lines and
transferred all of its medical waste contracts to the new
company. AR at 4. As relevant to the RFP here, the newly formed
company shares the same contract management staff, processes,
experience, and support as its predecessor. Id. In evaluating
NEIE’s technical capability (including experience) as excellent,
the agency reviewed information about NEIE, Inc., including its
successful performance of three current, similarly scoped VA
contracts for removal and disposal of medical waste. NEIE
Proposal at 5; AR, Tab 13. Since the agency could properly
consider the experience of NEIE’s predecessor, there was nothing
unreasonable in the agency’s evaluation. (Advant-EDGE
Solutions, Inc., B-400367.2, November 12, 2008) (pdf)
We agree with the protester that the contracting officer’s
explanation of his evaluation, in response to the protest, does
not entirely track the contemporaneous record. For example, the
protester is correct that there is nothing in the
contemporaneous record supporting the contracting officer’s
claim that he did not consider Ahntech-San Diego’s PTR contract
in evaluating Ahntech-Korea’s experience because Ahntech-San
Diego is not a Korean company. In fact, as discussed above, the
record shows that the contracting officer did consider Ahntech‑San
Diego’s PTR contract; he concluded that the proposal information
concerning this contract was too “general in nature” to allow
the contracting officer to find that Ahntech‑Korea met the
3-year experience requirement. However, notwithstanding the
agency’s unsupported statements in response to the protest, it
is clear from the contemporaneous record that it reasonably
found that Ahntech‑Korea did not meet the 3-year experience
requirement.
(See
Ahntech-Korea Company, Ltd.,
B-400145.2, August 18, 2008 sections for discussion of "3-year
experience")
Regarding Ahntech-San Diego’s PTR contract, an agency properly
may attribute the experience or past performance of a parent or
affiliated company to an offeror only where the firm’s proposal
demonstrates that the resources of the parent or affiliated
company will affect the performance of the offeror. Perini/Jones
Joint Venture, B‑285906, Nov. 1, 2000, 2000 CPD para. 68 at 4.
The relevant consideration is whether the resources of the
parent or affiliated company--its workforce, management,
facilities, or other resources--will be provided or relied upon,
such that the parent or affiliate will have meaningful
involvement in contract performance. Id. at 5.
Although the record shows that the agency did consider the PTR
contract in the evaluation (finding that the proposal
information concerning this contract was too “general in
nature”), since Ahntech-San Diego was not an offeror, it would
be appropriate for the agency to impute that entity’s experience
to Ahntech-Korea only if Ahntech-Korea’s proposal committed
Ahntech-San Diego’s resources to performance of the contract. We
find that the proposal did not commit Ahntech-San Diego’s
resources. There is nothing in Ahntech-Korea’s proposal that
purports to offer the workforce, management, facilities or other
resources of Ahntech-San Diego for performance of the contract.
The protester points to proposal language that it believes was
sufficient to commit Ahntech-San Diego’s resources. However, the
cited language consists of only general statements regarding
guidance, instruction, and support. For example, the proposal
states that “[s]ince Ahntech‑Korea’s inception, the parent
company has provided support mentoring, and training to develop
the subsidiary’s management structure to one that focuses
heavily on the needs of the customer and how the company can
satisfy them,” Ahntech-Korea Proposal, at 1, and that
“[c]orporate experience comes from the dual experiences of
Ahntech-Korea, combined with those of the parent company,
Ahntech-San Diego. In the parent role, Ahntech-San Diego
provides guidance, instruction, and support to each contract
performed by Ahntech-Korea and as such Ahntech-Korea benefits
heavily from the experiences gained by the parent company over
years of performance on Government contracts.” Id. at 3. While
these statements perhaps are sufficient to indicate that there
is a business relationship between the two entities, there is
nothing in the language--or elsewhere in the proposal--that
actually commits any of Ahntech‑San Diego’s resources to
performance of the contract. This being the case, the
contracting officer could not properly consider Ahntech-San
Diego’s experience in its evaluation of Ahntech-Korea.
Since the agency reasonably determined that the KTRAC contract
did not satisfy the 3-year experience requirement, and since the
agency could not properly consider Ahntech-San Diego’s
experience in the evaluation, it is clear that the protester did
not meet the 3-year experience requirement. It follows that the
contracting officer’s conclusion that Ahntech‑Korea’s proposal
was technically unacceptable was unobjectionable. The
protester’s other arguments--regarding, for example, the absence
of any RFP requirement that warranted rejecting the protester’s
proposal on the basis that the protester is not a Korean
company--are irrelevant, since they have no bearing on the
propriety of the agency’s rejection of the proposal as
unacceptable under the experience requirement. (Ahntech-Korea
Company, Ltd., B-400145.2, August 18, 2008) (pdf)
LM proposed to design and fabricate the BAMS Mariner, a modified
version of its proposed subcontractor General Atomics
Aeronautical Systems’ (GA-ASI) Predator B aircraft (flown by the
U. S. Air Force), with such modifications as a 22-foot extension
of the wingspan, [REDACTED]. The BAMS Mariner, with a gross
takeoff weight of 12,528 pounds (approximately 2,000 pounds
greater than the existing model), was to be powered by a single
engine with a turboprop propeller. Based upon an evaluated
ingress speed of [REDACTED] knots and an egress speed of
[REDACTED] knots, NAVAIR assessed that for a station
approximately 2,000 miles from its operating base, each BAMS
Mariner would be on station [REDACTED] hours, while the
evaluated ETOS of a 4‑aircraft orbit was 84.6 percent. NG
proposed to design and fabricate the BAMS Global Hawk (RQ‑4N), a
modified version of its RQ-4B Global Hawk B (flown by the U.S.
Air Force), with such modifications as [REDACTED]. The BAMS
Global Hawk, with a gross takeoff weight of 32,250 pounds, was
to be powered by a single turbofan (jet) engine. Based upon an
evaluated ingress speed of [REDACTED] knots and an egress speed
of [REDACTED] knots, each BAMS Global Hawk would be on station
[REDACTED] hours, while the evaluated ETOS of the proposed
3‑aircraft orbit was 96.2 percent. Boeing proposed to design an
unmanned version of the [REDACTED]. The Boeing [REDACTED], with
a gross takeoff weight of [REDACTED] pounds, was to be powered
by [REDACTED]. Based upon an evaluated ingress speed of
[REDACTED] knots and an egress speed of [REDACTED] knots, each
Boeing [REDACTED] would be on station [REDACTED] hours, while
the evaluated ETOS of the proposed [REDACTED]-aircraft orbit was
92.8 percent.
(sections deleted)
LM principally challenges NAVAIR’s evaluation of its own and
NG’s past performance. In this regard, the RFP provided that the
government would
evaluate the offeror’s, and (if applicable), its principal
subcontractors’ and critical team members’ demonstrated past
performance in delivering quality products and in meeting
technical, cost and schedule requirements on similar programs
for SDD, Production, and Operations and Support. The currency
and relevance of the information, source of the information,
context of the data, and general trends in contractor’s
performance will be considered. Problems not addressed by the
offeror will be considered to still exist. However,
consideration for discounting problems may be given when those
problems are addressed through demonstrated systemic
improvement. RFP sect. M.II.B.
In furtherance of the past performance evaluation, offerors were
required to identify contracts “whose performance is within five
years from the RFP release and contain efforts similar to those
efforts, e.g., tasks, contract type, location, contract dollar
value, etc., required by this solicitation.” RFP sect. L.3.1.
The information provided “should be related to similar programs
in the same division, or cost centers in which the Offeror
proposes to perform this effort,” and correspond to the
descriptions of the offeror’s experience under the experience
factor. Id. The experience section of the RFP, in turn, required
that the experience “be relative to proposed roles and
responsibilities of the Offeror/Subcontractor in this
solicitation,” and identified several tasks considered relevant,
including “[p]erforming SDD tasks such as design, integration,
fabrication, and test of a system similar in scope to the BAMS
UAS,” “[p]erforming logistics tasks for major military weapons
systems similar in scope to the BAMS UAS,” and “[p]roduction and
manufacturing of a system similar in scope to the BAMS UAS.” RFP
sect. L.4.0.
For each relevant contract, offerors were required to describe
performance in meeting technical and quality requirements,
meeting schedule requirements, controlling cost, and managing
the contracted effort (e.g., program management, cooperation
with customer, subcontract management). RFP sect. L.3.4.2. In
addition, and of particular importance here, offerors were
required, “[f]or each past performance problem identified, [to]
describe the status of the systemic improvement efforts and,
where applicable, demonstrate the impact that the systemic
improvement effort had on resolving the problem such that it
would not reoccur.” RFP sect. L.3.1. Further, in addition to
“[i]dentify[ing] those systemic improvement actions taken to
resolve past problems,” offerors were required to “[p]rovide the
records of such results and indicate where they are documented,
preferably in Government record systems. Describe the
techniques, elements, and tools used to correct problems on the
contract and, if applicable, how these techniques, elements, and
tools will be used during this program.” RFP sect. L.3.4.3.
Finally, offerors were cautioned that “[t]he Government does not
assume the duty to search for data to cure the problems it finds
in the information provided by the Offeror. The burden of
providing thorough and complete past performance information
remains with the Offeror.” RFP sect. L.3.1.
(section deleted)
LM asserts that NAVAIR’s
evaluation of LM’s, GA-ASI’s, and NG’s past performance was
inconsistent with the solicitation and otherwise unreasonable in
numerous respects.
(section deleted)
Past Performance of LM Team
(emphasis added)
Although the SSEB noted that inadequate staffing and a shortfall
in technical skills had adversely impacted LM’s ability to
execute a somewhat relevant (the Po Sheng) SDD contract to
upgrade the command control system for Taiwanese F-16 fighter
aircraft, the panel generally acknowledged that LM had
demonstrated “high quality technical performance” on five of six
relevant contracts. SSEB at 52. In contrast, however, GA-ASI’s
contract performance was a matter of great concern to the
agency. Specifically, while recognizing that GA-ASI had
demonstrated a willingness and ability to respond on short
notice to evolving Global War on Terror (GWOT) warfighter
requirements, the SSEB found that GA-ASI’s performance
demonstrated: inadequate staffing, resulting in performance
problems on SDD contracts for the MQ‑9 Reaper (a
second-generation, Predator B model) and the MQ‑1C Extended
Range/Multipurpose (ER/MP) UAS (a second-generation Predator
model); unfavorable schedule performance on four of seven
relevant GA-ASI contracts, including very relevant contracts for
the MQ-9 Reaper, UAS ground control stations, MQ-1C ER/MP,
I-GNAT Extended Range UAS (a version of the Predator with some
differences for the Army), and MQ-1 baseline Predator; poor
performance in meeting technical quality requirements on three
of seven GA-ASI contracts, including contracts for the MQ-9
Reaper, MQ-1C ER/MP, and I‑GNAT Extended Range UAS; and workload
exceeded the firm’s capacity on five of seven GA-ASI contracts,
including contracts for the MQ-9 Reaper, UAS ground control
stations, MQ-1C ER/MP, I-GNAT Extended Range UAS, and MQ‑1/MQ-9
maintenance support. In summary, the SSEB found the overall
performance of GA-ASI on its very relevant contracts for the
MQ-9 Reaper (most delivery orders), UAS ground control stations,
MQ-1C ER/MP, and I-GNAT Extended Range UAS to be marginal. SSEB
at 36-38, 52‑62.
Based upon the above past performance problems, the SSEB
determined that there was substantial doubt that LM would
successfully perform the required effort, and that an overall
high risk rating therefore was warranted. According to the SSEB:
The Lockheed Martin team
delivers a high quality, technical product and both Lockheed
Martin and GA-ASI are motivated to meet the warfighter’s
requirements. Lockheed Martin, as the prime contractor
however, will be substantially challenged to ensure that GA-ASI
will remain on schedule. The proposal includes a prominent
role for GA‑ASI including aircraft design, UA manufacture,
flight test, logistics, training support, communications
subsystem and MCS aircraft control segment which represents
approximately 50% of the proposed effort. There is, therefore,
significant risk to the BAMS UAS program if GA‑ASI’s future
performance trend reflects identified past performance
difficulties in managing increasing workload, a possibility
which the [Past Performance Evaluation Team] assesses as
likely to occur.
Lockheed Martin and GA-ASI have recent past performance
histories of being unable to resolve staffing issues resulting
in adverse cost and schedule performance. Furthermore, there
are documented concerns regarding the amount of work that GA‑ASI
has taken on and the slow pace of implementing processes and
process improvements that increased workloads and
responsibilities require. Systemic improvement initiatives
have been identified or are in work in several areas of
concern; however, these efforts are not yet demonstrated to
determine their effectiveness at lowering risk.
SSEB at 62.
LM disputes both the agency’s evaluation of its performance
under several of the individual contracts and the determination
that there was little demonstrated systemic improvement.
(1) MQ-9 Reaper/GCS
GA-ASI’s ongoing Air Force contract No. F33657-02-G-4035
included very relevant (according to both LM and NAVAIR)
delivery orders for interim contract capability, SDD and
production of the MQ-9 Reaper (again, a second-generation
Predator B model), and for the pre-production and production of
UAS ground control stations (GCS). NAVAIR received three
Contractor Performance Assessment Reports (CPAR) for these
contract efforts, the most recent completed on April 23, 2007
for the period from January 1 to December 31, 2006, with earlier
CPARS for the periods October 1, 2004 to December 31, 2005 and
September 18, 2002 to September 30, 2004. (NAVAIR had
unsuccessfully requested updated 2007 performance information on
contract No. 4035. NAVAIR E-mail to Air Force Point of Contact
as suggested by Air Force Program Manager (as listed in LM Past
Performance Proposal at 3-6), Nov. 28, 2007; Tr. at 2183-84.)
LM challenges the overall marginal rating for GA-ASI’s
performance under this contract on the basis that this overall
rating was inconsistent with the category ratings in the latest
2006 Air Force CPAR of very good for technical, satisfactory for
management, and marginal for schedule and cost control. However,
while recognizing that GA-ASI “does an excellent job responding
to quick reaction and rapidly evolving warfighter requirements
in support of the Global War on Terror,” the 2006 CPAR
nevertheless expressed significant reservations as to GA-ASI’s
performance in several areas:
Systems engineering was rated
satisfactory overall but remains an area of concern for the
program. The company has not been able to develop a sufficient
systems engineering staff to keep pace with the numerous other
contracted efforts.
While satisfactory overall, [software engineering] is an area
of concern for the program. Although the company continues to
increase its software engineering staff, there continues to be
limited software engineering resources to complete all
contracted work. . . . The contractor needs to continue to
increase their engineering staff in order to meet contracted
commitments in parallel.
Several projects under this [Basic Ordering Agreement] have
suffered from schedule delays, to include the MQ-9 ICC and
MQ-9 SDD efforts. The schedule variances for these efforts are
-20% and -44.9% respectively as of Dec. 06. While [GA-ASI] has
committed to expanding the workforce, the contractor has
insufficient resources to execute the contracted work on
schedule in several key areas. The resulting schedule delays
directly impact the fielding of combat capability.
CPAR, Contract No. 4035, 2006
Period. The 2004/2005 CPAR for contract No. 4035 included
similar criticisms of GA-ASI’s performance, as well as marginal
schedule and cost control ratings. Given the above continuing
staffing and resources shortfalls, which resulted in “schedule
delays directly impact[ing] the fielding of combat capability,”
CPAR, Contract No. 4035, 2006 Period, and the repeated marginal
schedule and cost control ratings in the most recent CPARs, we
find no basis to question NAVAIR’s evaluation of GA-ASI’s
overall performance under contract No. 4035.
LM further challenges NAVAIR’s assessment that systemic
improvement by GA-ASI on contract No. 4035 (as well as under
other contracts) had not been demonstrated. In this regard, LM
generally acknowledged in its December 4, 2007 discussions
response with respect to a number of GA-ASI contracts (including
the MQ-9 Reaper, MQ-1C ER/MP, and I-GNAT Extended Range UAS),
that “the fundamental cause for GA-ASI Past Performance issues
was availability of trained staff to meet the demand for our
products and services”; that GA-ASI’s workload had exceeded its
capacity; that there had been “management task saturation”; and
that there was a “valid CPAR comment” regarding (overly)
“[c]entralized management structure.” LM Evaluation Notice (EN)
Response, Dec. 4, 2007, LM-PP-003, -008, -009, -010, 011.
However, LM maintained then, id., and asserts in its protest,
that GA-ASI has undertaken such systemic improvements as
increasing engineering and trained staff, hiring mid-level and
senior program managers, and restructuring the decision-making
process. According to the protester, the evaluation failed to
acknowledge these systemic improvements.
The agency’s evaluation in this area was reasonable. Although LM
has suggested that the RFP did not require that there be
documented results of any systemic improvements, and that merely
hiring additional staff should be accepted as effective systemic
improvement, as noted above, the RFP in fact required the
offeror to “identify those systemic improvement actions taken to
resolve past problems, . . . demonstrate the extent to which it
will benefit the instant contract,” and “[p]rovide the records
of such results and indicate where they are documented,
preferably in Government record systems.” RFP L.3.4.3.
Accordingly, in ascertaining whether there had been systemic
improvement in correcting prior performance deficiencies and
problems, the agency properly looked to see whether the record
“demonstrate[d] the impact of the systemic improvement,”
including whether there were any results of the claimed systemic
improvement measures “in a record or documentation to show that
action resulted in a tangible improvement to that program,” such
that there was “independent verification [of] tangible
improvement.” Tr. at 778-80.
Given the solicitation requirement that any improvements in
contract performance be documented, the agency reasonably
determined that overall systemic improvement by GA-ASI on
contract No. 4035 had not been shown. In this regard, as noted
above, notwithstanding the agency’s November 2007 request to the
Air Force for updated contract performance information, an
updated CPAR or other updated past information had not been
furnished by the Air Force. Further, while LM furnished its own
updated Earned Value Management System (EVMS) data on contract
No. 4035 in a December 6, 2007 discussions response, that data
did not clearly establish that overall demonstrated systemic
improvement on the contract had occurred. LM reported that the
cumulative Schedule Performance Index (SPI) (ratio of work
performed to the initial planned schedule, with an SPI of less
than 1.0 indicating that work is not being completed as planned
and the program may be behind schedule if the incomplete work is
on the critical path) on the three ground control system
delivery orders as of October 2007 was only 76.6 percent, 88.8
percent, and 91.9 percent, all below the 95‑percent level at
which performance began to be a matter of some concern to the
agency. LM also reported that the cumulative Cost Performance
Index (CPI) (ratio of work performed to actual costs for work
performed, with a CPI of less than 1.0 being unfavorable because
the work is being performed less efficiently than planned) on
one of the orders likewise was below the 95-percent level (93.1
percent). LM Response to EN LM-PP-015, Dec. 6, 2007; Tr. at
1084-92; GAO Cost Assessment Guide, GAO-07-1134SP, at 226.[1] As
for the four MQ-9 Reaper delivery orders, LM reported that one
had been completed in December 2006 at a cumulative CPI of 92.4
percent, one of the remaining three orders was below the
95‑percent CPI level in October 2007 (at 91.3 percent), and the
third order had been rebaselined in October 2007 (and the index
thus was reset to 1.0). LM also reported that one of the orders
was below the 95‑percent level for SPI in October 2007 (at 83.7
percent), while a second had been rebaselined in October 2007
after having an SPI of 55.2 percent in June 2007. We conclude
that the agency reasonably determined that there was no
documentation of systemic improvement on contract No. 4035.
(2) MQ-1C ER/MP
Both NAVAIR and LM considered ongoing Army contract No.
W58RGZ-05-C-0069, for the MQ-1C Extended Range/Multipurpose
(ER/MP) UAS (a second-generation Predator model using the basic
structure of the Predator aircraft with the Predator B avionics
suite), to be very relevant to LM’s proposed BAMS Predator-based
Mariner UAS. LM Past Performance Proposal at 3-9, 3-51. NAVAIR
received for this contract: four past performance questionnaire
(PPQ) responses, including December 10, 2007 and April 2007
responses from the Army Procuring Contracting Officer (PCO), an
April 2007 response from the Army Product Manager, and a
February 26, 2007 response from the Defense Contract Management
Agency (DCMA) Administrative Contracting Officer (ACO); and a
number of LM discussion responses that referred to the contract
(as well as a number of other contracts).
LM challenges the overall marginal rating for GA-ASI’s
performance under this contract, primarily on the basis that
this rating was inconsistent with the input from the DCMA ACO
and LM’s discussion responses.
We find that the agency reasonably rated GA-ASI’s performance
under contract No. 0069 only marginal. In this regard, the most
recent detailed information received by NAVAIR for this contract
was the Army PCO’s December 10, 2007 PPQ response in which he
rated GA-ASI’s performance as marginal for technical/quality
performance, schedule, cost performance, and program management.
According to the Army PCO, while the agency was “confident the
company can and will deliver a quality aircraft system,”
nevertheless, “as the program continues, and [GA‑ASI] takes on
additional contracts, we are concerned about [GA-ASI’s] ability
to successfully manage and deliver products to all customers on
time and within cost.” Army PCO PPQ Response, Contract No. 0069,
Dec. 10, 2007. The Army PCO specifically reported the following
performance problems on the MQ-1C ER/MP contract:
[GA-ASI has not met contracted .
. . delivery schedules.
[GA-ASI] continues to struggle as the Systems Integrator.
[GA-ASI] has resisted hiring adequate engineering and
technical staff to address all of the tasks they are currently
contracted to perform.
The common theme within the delivery/schedule problems appears
to relate back to the acceptance of contractual commitments
which are physically beyond production capacity.
A major contributor is [that GA-ASI’s] senior management
continues to obligate the company without fully reviewing and
understanding the current workload and commitments.
Management task saturation coupled with [GA-ASI’s] highly
centralized management structure both contribute towards the
delays with the integration testing and coordination efforts .
. . .
The engineering staff appears to be technically [competent],
but in most cases are not empowered at the appropriate levels
to make the necessary decisions to push the task forward in a
timely manner to maintain schedule.
[GA-ASI] has made limited corrective actions and usually not
without Government PMO insistence.
Army PCO PPQ Response, Contract
No. 0069, Dec. 10, 2007. Furthermore, the April 2007 PPQs
completed for Contract No. 0069 by the Army PCO and the Army
Product Manager appeared to indicate that GA-ASI’s performance
problems had been continuing for some time, with references to
GA-ASI “continu[ing] to struggle in identifying and executing
system engineering and system integration tasks required to
facilitate final integration of the subsystems,” and having
“struggled in the area of staffing at adequate levels to
properly resource the program schedule.” Army PCO PPQ Response,
Contract No. 0069, Apr. 2007; Army Product Manager PPQ Response
Contract No. 0069, Apr. 2007.
LM asserts that the overall marginal rating for GA-ASI’s
performance on contract No. 0069, for the MQ-1C ER/MP, did not
reasonably account for the February 26, 2007 PPQ response
completed by the DCMA which reported that GA-ASI’s
technical/quality and schedule performance was exceptional, its
cost performance was very good, and its management performance
was very good to exceptional.
We find LM’s position unpersuasive. As an initial matter, we
agree with the agency that the DCMA ACO furnished little detail
in support of his very favorable performance ratings, and that
the detail that was furnished appears in some measure
inconsistent with the high ratings. In this regard, for example,
while the DCMA ACO rated GA-ASI’s cost performance as very good
and its schedule performance as exceptional, the DCMA ACO
reported cumulative, unfavorable EVMS ratings of 0.84 for CPI
and 0.91 for SPI as of January 2007. Although the DCMA ACO
stated that government-directed changes were the cause of
schedule and cost issues, he also acknowledged that $18 million
of a predicted $37 million cost overrun was believed to be the
result of “cost growth within the contract scope,” as distinct
from “scope growth,” and he referred to the fact that
“[c]orrective actions are on-going,” including continued hiring
by GA-ASI, thus seemingly implying that there was some
contractor responsibility for performance problems. Tr. at
1784-93. In any case, the DCMA ACO’s response was furnished in
February 2007, while the more detailed responses by the Army PCO
and Army Product Manager represented more recent assessments
based on the contract performance as of April and December 2007.
We note in this regard that the PPQs completed in April 2007 by
the Army PCO and Army Product Manager both rated GA-ASI’s
performance as marginal to satisfactory for technical/quality
and schedule performance, and satisfactory for cost and
management performance, thus suggesting both that GA-ASI’s
performance had deteriorated since the DCMA ACO’s assessment in
February and continued to deteriorate up to the time of the
marginal performance reported by the Army PCO in December 2007.
Army PCO PPQ Response, Contract No. 0069, Apr. 2007; Army
Product Manager PPQ Response, Contract No. 0069, Apr. 2007.
Moreover, to the extent that the differences in assessment of
GA-ASI’s performance represented a difference of opinion, as
distinct from a mere change over time in the quality of
performance, we consider it significant that it was the views of
the Army PCO and Army Product Manager, rather than those of the
DCMA ACO, that were broadly consistent with the reports in the
Air Force CPARs on GA-ASI’s performance on the MQ-9 Reaper/GCS
delivery orders, that is, the reports of continuing GA-ASI
staffing and resources shortfalls resulting in schedule delays.
In summary, based on the recent, detailed information concerning
GA-ASI’s performance problems on contract No. 0069, which
information was consistent with reports of staffing and resource
shortfalls resulting in schedule delays on other contracts,
NAVAIR reasonably rated GA-ASI’s performance on this contract as
no better than marginal.
LM asserts that, in any case, NAVAIR failed to account for
systemic improvement by GA-ASI, such as increased staffing. As
noted above, however, the RFP required a showing of documented
improvements in contract performance as a result of any claimed
systemic improvement measures. RFP sect. L.3.4.3. While GA-ASI
has apparently continued to increase its workforce, again, an
increase in workforce by itself, without a documented
improvement in contract performance, did not meet the
solicitation standard for showing systemic improvement. Here,
not only did the PPQ responses seem to suggest deteriorating
performance on contract No. 0069 through December 2007, but, in
addition, recent EVMS data furnished by LM during discussions
was not favorable. In this regard, in its December 6, 2007
discussion response to EN LM‑PP-015, LM indicated that the MQ-1C
contract had been rebaselined after performance resulted in
increasingly unfavorable EVMS numbers at the beginning of
2007‑‑with a decline in the CPI from 83.8 percent in January to
80.3 percent in April and a similar SPI decline from 90.9
percent to 87.1 percent‑‑but then, after the rebaselining was
reflected in the EVMS data in September 2007 with fresh
100-percent CPI and SPI ratings, the numbers again began to
decline, falling to 98.4 percent and 98.2 percent, respectively,
in October 2007. LM Response to EN LM‑PP-015, Dec. 6, 2007. In
these circumstances, we find that NAVAIR reasonably concluded
that the information known to the agency did not support a
finding of systemic improvement on contract No. 0069.
(3) I-GNAT Extended Range UAS
Both NAVAIR and LM considered Army contract No.
DAAH01-03-C-0124, ending in December 2007, for the I-GNAT
Extended Range (ER) UAS (an Army version of the Predator), to be
very relevant to LM’s proposed BAMS Predator-based Mariner UAS.
LM Past Performance Proposal at 3-9, 3-70. NAVAIR received three
PPQ responses for this contract: a May 31, 2007 response from
the Army Deputy Product Director, Unmanned Aerial Systems
Program Management Office; an April 18, 2007 response from the
Army PCO (who was also the Program Manager (PM) for this program
(according to LM, LM Past Performance Proposal at 3-7), and the
PCO for the MQ-1C ER/MP contract); and an April 2007
“coordinated” response from the DCMA ACO (who also was the ACO
for the MQ-1C ER/MP contract) and the DCMA Program Integrator,
which was subsequently updated by the DCMA ACO on May 24, 2007.
In addition, NAVAIR received several LM discussion responses
that referred to the contract (among a number of other
contracts).
LM challenges the overall marginal rating for GA-ASI’s
performance under this contract, primarily on the basis that it
fails to account for the DCMA input. In this regard, the record
reflects what appears to be an irreconcilable difference between
the Army and DCMA evaluations of GA-ASI’s performance. On the
one hand, the Army Deputy Product Manager and the Army PCO/PM
agreed on marginal ratings for technical/quality, schedule, cost
and management performance based on concerns that GA‑ASI had
“consistently failed to meet contractual delivery dates for the
spares and Ground Data Terminals and [was] beginning to show
moderate slippage on delivery dates for Air Vehicles and Ground
Control Stations”; had demonstrated resistance to hiring
adequate personnel; had overly centralized management structure
that contributed to program delays; had difficulty in managing
its subcontractors; and ultimately was “agreeing to contractual
commitments which are beyond its production capacity.” PPQ
Response, Contract No. 0124, May 31, 2007, Army Deputy Product
Director; PPQ Response, Contract No. 0124, Apr. 18, 2007, Army
PCO/PM. On the other hand, the coordinated response from the
DCMA ACO and DCMA Program Integrator offered the summary
conclusion that there had been exceptional technical/quality,
schedule, cost and management performance, with “generally”
on-time performance or, as of May 2007, “on schedule” aircraft
deliveries and “[n]o major slippage on the production schedule.”
PPQ Response, Contract No. 0124, Apr. 2007, DCMA ACO; E-mail
from NAVAIR to DCMA ACO, May 24, 2008.
We find that NAVAIR’s evaluation of GA-ASI’s performance on
contract No. 0124 was reasonable. Confronted with materially
differing ratings from the Army and DCMA representatives as of
May 2007, the agency unsuccessfully sought updates from both
entities on November 28, 2007, E-mail to Army Deputy Product
Manager, Army PCO/PM, and DCMA ACO, Nov. 28, 2007, and also
raised the negative past performance information from the Army
with LM in a series of ENs in October 2007. Of particular
significance in this latter regard were LM’s October 12
responses to EN LM-PP-009 and EN LM-PP-11, in which LM did not
specifically refute the reports that GA-ASI had failed to meet a
number of contractual delivery dates, but essentially maintained
that it was simply “being responsive to the customer’s
aggressive requests” and that any performance difficulties were
beyond its control. LM Response to EN LM-PP-009, Oct. 12, 2007.
Given that the record before NAVAIR included negative
performance appraisals from responsible officials of the Army,
that is, the customer agency; the Army evaluations were
consistent with those on several other Army and Air Force
Predator-related contracts; the Army evaluations were more
detailed than the general praise from the DCMA ACO; the DCMA
ACO’s use of such language as “generally” on-time or “[n]o major
slippage” suggests that there were some schedule slippages,
which would appear to be inconsistent with the DCMA ACO’s
exceptional ratings; and the fact that, when questioned by
NAVAIR in this regard, LM did not refute the reports that GA-ASI
had failed to meet a number of the contractual delivery dates,
we find that NAVAIR reasonably rated GA-ASI’s performance on
this contract as marginal.
In summary, we find that LM’s challenges to the evaluation of
its team’s past performance provide no basis for questioning the
agency’s determination that the LM team‑‑in particular, GA-ASI‑‑had
a recent past performance history of being unable to resolve
staffing and resource issues, which resulted in adverse cost and
schedule performance. We further find no basis for questioning
the agency’s determination that, notwithstanding such systemic
improvement measures as hiring additional staff, LM did not
establish documented improvements in contract performance as a
result of the systemic improvement measures; these efforts
therefore did not furnish a basis for reducing the risk
associated with the LM team’s unfavorable past performance.
(Lockheed Martin MS2 Tactical Systems,
B-400135; B-400135.2, August 8, 2008) (pdf)
While McGoldrick
contends that the VA unreasonably considered SPD’s
subcontractor’s experience, it is well-established that in
evaluating the past performance of a new business, an agency may
consider the experience of the firm’s proposed subcontractors,
unless it is prohibited from doing so by the terms of the
solicitation, since such experience could be reasonably
predictive of the offeror’s performance under the contract. See
Cleveland Telecomms. Corp., B-257294, Sept. 19, 1994, 94‑2 CPD
para. 105; Commercial Bldg. Serv., Inc., B‑237865.2, B-237865.3,
May 16, 1990, 90-1 CPD para. 473 at 4. To the extent the
protester contends that the agency failed to confirm the
subcontractor’s role in performance of the work and whether that
firm’s experience is relevant to the RFP’s requirements, the
agency reports, and our review of the record confirms, that the
awardee’s major subcontractor is an experienced construction
firm with relevant and recent successful performance of
substantially similar renovation work at another VA medical
facility and will have substantial responsibility for the
performance of the work here. Under these circumstances, the
agency reasonably considered the subcontractor’s experience in
evaluating the awardee’s past performance. (McGoldrick
Construction Services Corporation, B-310340.3; B-310340.4,
May 16, 2008) (pdf)
Within the qualifications factor, the solicitation established
the following subfactors, listed in descending order of
importance: construction experience, past performance, design
experience, and execution plan. With regard to the most
important evaluation subfactor, construction experience, the
solicitation provided that proposals would be evaluated “based
on projects . . . similar in nature, scope, and complexity to
the project types identified in this solicitation,” and provided
that the agency’s evaluation would be based on the offerors’
submission of no more than three past projects for each type of
experience required. RFP at 20, 1888. The solicitation further
directed as follows:
Only those projects for which the Offeror or a primary teaming
partner was the Prime Contractor should be submitted. The
projects selected should clearly demonstrate the construction
capabilities of the Offeror on projects that are similar in
scope and magnitude to the work required in this RFP.
RFP at 19.
On or before the April 13, 2007 closing date, proposals were
submitted by six firms qualified to compete for the 8(a)
set-aside contracts, including AIS, BDBS, CGS, Doyon, and NAJV.
Thereafter, the proposals were evaluated by the agency. There is
no dispute that, in responding to the solicitation requirement
to submit prior projects reflecting the required experience, the
awardees submitted projects that had been performed by the
parent corporations and/or other subsidiaries of the parent
corporations, and that the agency relied on performance of those
projects in performing its evaluation. See Agency Report, Sept.
11, 2007, at 2-6. Based on the agency’s evaluation, including
its consideration of the prior projects performed by the
parent/affiliate corporations, each of the awardees’ proposals
was rated [deleted] with regard to qualifications; in contrast,
each of the protester’s proposals was rated [deleted].
Contracting Officer’s Statement, Sept. 11, 2007, at 6. Each of
the awardees’ proposed prices was higher than each of the
protesters’ proposed prices. Id. On July 27, the agency selected
AIS, BDBS, and CGS for award. These protests followed.
DISCUSSION
Doyon and NAJV each protest that, pursuant to the provisions of
this solicitation, it was improper for the agency to consider
the experience of the awardees’ parents/affiliates in making the
source selection decision. We agree. It is well-settled that an
agency may consider the experience or past performance of an
offeror’s parent or affiliated company under certain
circumstances. See, e.g., Perini/Jones, Joint Venture, B-285906,
Nov. 1, 2000, 2002 CPD para. 68 at 4. However, our Office has
consistently recognized that reliance on a third party’s
experience, even if otherwise permissible, is contingent upon
the absence of any solicitation provision precluding such
consideration. See, e.g., Hot Shot Express, Inc., B-290482, Aug.
2, 2002, 2002 CPD para. 139 at 3; Physician Corp. of Am.,
B-270698 et al., Apr. 10, 1996, 96-1 CPD para. 198 at 13; Tutor-Saliba
Corp, Perini Corp., Buckley & Co., Inc. and O & G Indus. Inc., A
Joint Venture, B-255756, Mar. 29, 1994, 94-1 CPD para. 223 at 5;
Fluor Daniel, Inc., B‑262051, B-262051.2, Nov. 21, 1995, 95‑2
CPD para. 241 at 12. Here, as noted above, the solicitation
provided that the agency’s evaluation would be based on the
offerors’ submission of no more than three projects for each
type of experience required; that the projects submitted should
demonstrate the capabilities of the offeror; and that only
projects for which the offeror or a primary teaming partner was
the prime contractor should be submitted. With regard to the
identity of the offerors, none of the parent/affiliate
corporations on which the agency relied for its assessment of
the awardees’ experience would appear to qualify as “offerors”
for this 8(a) set-aside procurement. Further, while each of the
awardees’ proposals identified various subcontractors or teaming
partners that would perform under the contract, the
parent/affiliate corporations were not identified as such.
Nonetheless, the record shows that the awardees submitted prior
projects performed by parent/affiliate corporations other than
the 8(a) offerors themselves, and that the agency relied on
those projects in evaluating the awardee’s experience; both
actions were inconsistent with the provisions of this
solicitation. (Doyon-American
Mechanical, JV; NAJV, LLC, B-310003; B-310003.2, November
15, 2007) (pdf)
Two members of
the evaluation team recognized Daylight’s operations manager as
the president of Associated Arborists, Inc., and noted that
Daylight’s address and telephone number were the same as that
listed for Associated Arborists on prior Forest Service
contracts. Agency Report (AR), Memorandum of Law, at 5-6.
Consequently, the evaluation team assumed that Daylight and
Associated Arborists were successor and predecessor companies,
and rated Daylight’s past performance based on their personal
experience with Associated Arborists. CO Statement at 1.
Daylight received a neutral rating in the past performance
evaluation factor based on instances of poor performance by
Associated Arborists, but received a satisfactory rating
overall, indicating that it adequately met the requirements of
the evaluation factors. AR, Tab 3, CO’s Decision Letter, at 1,
2. The Forest Service awarded the contract to Woolery
Timber Management, and Daylight filed an agency-level protest.
AR, Tab 3, Daylight Protest, Sept. 27, 2007, at 1. In response
to the protest, the Forest Service contacted some of the
references listed in Daylight’s proposal. AR, Tab 1, Memorandum
of Law, at 4. Two of the references stated that they were
unfamiliar with the work of Daylight, but recognized the name of
Daylight’s operations manager in connection with Associated
Arborists and provided past performance information with regard
to Associated Arborists. Id. at 6. Subsequently, the Forest
Service denied Daylight’s protest. AR, Tab 3, CO’s Decision
Letter, at 4.
Daylight filed a protest challenging its past performance
evaluation with this office, arguing only that the evaluation
was flawed because it and Associated Arborists are not the same
company. Protest at 1. The Forest Service argues that, by
listing references in its proposal that pertain to contracts
performed by Associated Arborists, Daylight itself apparently
considered the past performance of Associated Arborists relevant
to the performance of Daylight, and therefore the Forest Service
reasonably considered Associated Arborists’ performance. AR, Tab
1, Memorandum of Law, at 6. In our view, the evaluation
team reasonably included the past performance information of
Associated Arborists in its assessment of Daylight’s past
performance. The use of the same address and telephone number
for both companies, combined with the same person representing
the companies, strongly suggest that the two companies are, if
not predecessor and successor companies, then at least close
affiliates, and therefore, the past performance of Associated
Arborists could appropriately be considered in evaluating
Daylight’s proposal. As proof that Daylight and Associated
Arborists are not the same company, Daylight merely asserts that
it has been awarded contracts by the Forest Service since 2005.
However, it has provided no explanation as to how the two
companies shared the same address and telephone number while
remaining separate entities. Moreover, the Federal
Acquisition Regulation (FAR) directs agencies to take into
account past performance information of predecessor companies,
key personnel who have relevant experience or subcontractors
when such information is relevant to an acquisition. FAR sect.
15.305(a)(2)(iii). Daylight’s operations manager had also been
president of Associated Arborists. Therefore, the experience of
Associated Arborists under his leadership is relevant to the
performance of Daylight. See, e.g., United Coatings, B-291978.2,
July 7, 2003, 2003 CPD para. 146 at 6-7 (past performance of a
new company based on the experience key individuals gained
through prior employment with another, affiliated company is
relevant). Finally, the fact, undisputed by Daylight, that it
included contacts for work performed by Associated Arborists in
its references reinforces the conclusion that consideration of
Associated Arborists’ past performance in evaluating Daylight’s
proposal was appropriate. To the extent that Daylight
argues that the Forest Service improperly waited until after
Daylight filed an agency-level protest before contacting its
references, relying instead on the personal experiences of the
evaluation team with regard to the performance of Associated
Arborists, we find that the agency’s actions were not improper.
With regard to the evaluation team relying on its own knowledge,
we have held that an evaluator’s personal knowledge of an
offeror may be properly considered in a past performance
evaluation. Omega World Travel, Inc., B-271262, July 25, 1996,
96-2 CPD para. 44 at 4. Here, the evaluation team provided
documentation from prior contracts with Associated Arborists
that support the personal knowledge. In light of our conclusion
that it was reasonable to attribute Associated Arborists’ past
performance to Daylight, the Forest Service properly relied on
the personal experiences of the evaluation team with Associated
Arborists. With regard to the Forest Service contacting
Daylights references after the agency-level protest was filed,
we do not find it improper, and note that those
Daylight-provided references confirmed Daylight’s affiliation
with Associated Arborists. (Daylight
Tree Service & Equipment, LLC, B-310808, January 29, 2008) (pdf)
Contrary to the protester’s position, the RFP required more than
written evidence of an agreement to enter into a subcontract;
the RFP language quoted above clearly provided that any
subcontracting agreements on which an offeror relied to
establish the required experience had to be “final” at the time
of proposal submission. The letter from the consultant provided
by SeBS failed to furnish any detail whatsoever regarding the
services to be delivered, stating only that the consultant would
provide “professional services” to SeBS in support of the
contract “after discussion and mutual agreement on a defined set
of services to be delivered” by the consultant. Similarly, the
letter left open the price terms of any agreement, stating that
the consultant’s “rates and fees will be negotiated once the
contract has been awarded.” Further, as noted above, the version
of the letter furnished by the protester to the agency did not
contain a signature by an SeBS representative; thus, there was
no evidence that the two parties had in fact entered into an
agreement. Given the general nature of the letter and its lack
of specificity regarding basic terms, we think that the agency
reasonably concluded that SeBS failed to demonstrate that it had
a final subcontracting agreement in place to establish the
required NGD experience that SeBS itself was missing, as
required by the RFP. (Strategic
e-Business Solutions, Inc., B-310210, November 8, 2007) (pdf)
Synergetics’ assertion that its quotation should have been found
significantly superior to Vistronix’s is not supported by the
record. The RFQ provided that under the past performance factor,
evaluation of both a vendor’s technical experience and technical
accomplishment would be based on consideration of all available
and relevant facts and circumstances concerning projects that
were the same as or similar to the work described in the SOW.
RFQ sect. 24.2. In evaluating Synergetics’s quotation, the TEB
noted that the firm was a current incumbent subcontractor with
NRCS, with extensive working knowledge of agency programs,
requirements, and relevant computing environments, and with a
record of success. Agency Report (AR), Tab 11, at 00354. In
evaluating Vistronix’s past performance, the TEB noted that the
Vistronix team had been a USDA prime contractor since 1999, with
some large dollar value contracts; had experience in core NRCS
technologies; had proposed key personnel and technical experts
with significant technical knowledge and experience; and had
received excellence awards from other federal and state agencies
in similar work. AR, Tab 10, at 00346. Thus, although
Synergetics’s quotation received “additional consideration” for
its incumbent past performance, the TEB also found that
Vistronix’s past performance was “strong” based on these
considerations. TEB Report at 00569. (Synergetics,
Inc., B-299904, September 14, 2007) (pdf)
The protester
argues that the agency should not have considered it a weakness
that only two of the contracts that it submitted were for the
joint venture itself (as opposed to the large business partner).
DMSJV acknowledges that our Office has held that in evaluating
past performance, an agency may appropriately consider the
experience of the individual members of a joint venture and, at
the same time, consider the lack of experience of the joint
venture, see, e.g., Transventures Int’l, Inc., B-292788, Nov. 4,
2003, 2003 CPD para. 195 at 7; ITT Federal Servs. Int’l Corp.,
B‑283307, B-283307.2, Nov. 3, 1999, 99-2 CPD para. 76 at 14, but
urges us to reconsider these decisions. We see no basis for
departing from our precedent. Since it is the joint venture that
will be performing the work here, we see no reason that the
agency could not properly have considered the extent of its
experience in its evaluation. (Data
Management Services Joint Venture, B-299702; B-299702.2,
July 24, 2007) (pdf)
In this regard, an agency’s past performance evaluation may be
based on a reasonable perception of inadequate prior
performance, regardless of whether the contractor disputes the
agency’s interpretation of the underlying facts, Ready Transp.,
Inc., B-285283.3, B-285283.4, May 8, 2001, 2001 CPD para. 90 at
5, and the protester’s mere disagreement with the agency’s
judgment is not sufficient to establish that the agency acted
unreasonably. Birdwell Bros. Painting & Refinishing, B-285035,
July 5, 2000, 2000 CPD para. 129 at 5. Here, our review of the
record establishes that the agency’s evaluation of Womack’s past
performance was reasonable and consistent with the RFP’s
evaluation terms. As an initial matter, Womack argues that in
evaluating its past performance, the Air Force unreasonably
failed to consider other positive indications of its past
performance. However, the information was not considered because
it was included only in Womack’s protest, not in Womack’s
proposal. In any event, much of the information provided by
Womack in its protest was not eligible for consideration since
it either was beyond the 3-year window of consideration or not
relevant; further, in some instances, the information reflects
“marginal” ratings for Womack’s performance and, thus, actually
supports the agency’s rating. CO Statement at 10‑12.
Womack also challenges the validity of the underlying adverse
past performance information which led to its rating of “little
confidence”; Womack essentially denies the accuracy of the
allegations. However, with respect to the information concerning
A-1 Service’s performance of the Robins AFB warehouse addition
contract, Womack did not dispute the accuracy of the information
when the Air Force raised the issues with Womack during
discussions. Rather, Womack simply noted that A-1 Service was
not a member of its proposed team, thereby suggesting that the
information was not relevant to the agency’s evaluation of its
proposal. Upon further investigation, however, the Air Force
determined that A-1 Service’s performance should be attributed
to Womack given the close affiliation and the overlapping key
personnel between A-1 Service, Womack, and its teaming partner,
A-1 Mechanical/Electrical. Womack has not disputed the
reasonableness of the agency’s determination in this regard; in
fact, the firm corroborates the agency’s conclusions regarding
affiliation and relationship of the companies in its protest
submissions. Since the allegations were not rebutted by Womack,
we conclude that the agency reasonably considered these
allegations as accurate in evaluating Womack’s past performance.
Womack did challenge the validity of the adverse information
regarding its performance of the VSU contract in its response to
the discussion questions raised by the Air Force. Given the
conflicting views, the Air Force conducted an interview with
another individual to obtain yet another assessment of Womack’s
performance, which in the agency’s view corroborated the
negative evaluation of Womack’s performance and the conclusion
that the customer would not award Womack another contract.
Womack argues that the interview information does not support
the initial negative assessments of A-1 Service’s performance,
nor does it support the conclusion that the customer would not
award Womack another contract. While the interview information
may not support every detail of the initial evaluation, which
the agency received, the overall tenor of the information does
support the assessment of Womack’s performance as “marginal.” In
this regard, the interview contact noted paperwork,
communication, and performance problems under the contract. In
addition, the contact specifically indicated that the customer
had implemented changes to its contractor prequalification
process so that it would not repeat the experience it had with
Womack, reasonably leading the agency to conclude that the
customer was not satisfied with Womack’s performance and would
not do business with the firm again. Thus, notwithstanding
Womack’s contentions to the contrary, we believe the record
shows that the agency acted reasonably in its assessment of
Womack’s performance of the VSU contract. (J.
Womack Enterprises, Inc., B-299344, April 4, 2007) (pdf)
In challenging the agency’s decision not to attribute the past
performance information of CSPS’ parent company, Chenega,
Frontier points to numerous sections of CSPS’ proposal
referencing the experience and capabilities of Chenega. Frontier
also highlights the fact that the relevant experience of CSPS’
key employees involved work they had performed on behalf of
Chenega, as well as the fact that CSPS intended to rely on a
personnel database maintained by Chenega for recruiting
purposes. When taken together, Frontier contends that CSPS’
proposal shows that Chenega will maintain a significant role in
performing the required guard and security services contract.
CSPS’ proposal, however, clearly identified Chenega’s role under
the contract as limited to providing support type functions,
i.e., accounting, invoicing, payroll, and quality control
certification, and clearly explained that CSPS and Wackenhut
personnel were to manage and perform all of the required guard
and security services. CSPS Proposal at 39. Based on these clear
and unequivocal representations in CSPS’s proposal, the Navy
reasonably determined that Chenega would not have a meaningful
role in performing the primary services required by the agency
and therefore acted properly in not attributing to CSPC the
experience or past performance history of its parent
corporation. (Frontier Systems
Integrators, LLC, B-298872.3, February 28, 2007) (pdf)
The past performance of proposed subcontractors may properly be
considered in evaluating the past performance of an offeror
where the solicitation does not expressly prohibit its
consideration. Federal Acquisition Regulation (FAR) sect.
15.305(a)(2)(iii); Roca Mgmt. Educ. & Training, Inc., B-293067,
Jan. 15, 2004, 2004 CPD para. 28 at 5. In its evaluation, the
agency gave the awardees credit for their subcontractors’
favorable past performance in determining their performance was
low risk. Contrary to the protester’s argument, the RFP did not
suggest that prime contractor past performance would necessarily
be given greater weight than relevant past performance by
subcontractors. Our in camera review of the record shows that
the awardees’ past performance evaluations are documented, give
appropriate weight to subcontractor past performance and support
the low risk ratings. (Indtai
Inc., B-298432.3, January 17, 2007)
(pdf)
KIC argues that the agency unreasonably concluded that its
proposal was technically unacceptable because KIC elected to
meet the solicitation’s experience requirement with the
experience of a properly-committed subcontractor. KIC contends
that the solicitation allowed offerors to meet the experience
requirement with committed key employees or subcontractors, and
that its proposal did so in a manner consistent with the
solicitation’s instructions. HUD does not argue--nor does the
record suggest--that KIC’s proposed subcontractor fails to meet
the experience requirement, or that KIC failed to provide a
valid letter of commitment from the subcontractor. Rather, HUD
explains that the evaluation panel found the proposal
unacceptable under the experience portion of the experience and
past performance factor because KIC “relied completely on a
subcontractor for the work performance and work experience,” AR,
Memorandum of Law, at 2, and “because the proposal did not
indicate in any fashion that the offeror or any of its own staff
had any experience whatsoever in the area of lead evaluation
services.” AR, Contracting Officer’s (CO) Statement, at 5. HUD
also argues that KIC’s proposal should have been rated
unacceptable under the management plan factor, although the
contemporaneous evaluation concluded the proposal was acceptable
in this area. Id. Specifically, the CO states that he now thinks
that KIC’s “proposal (1) indicated no management role for itself
in this effort, (2) identified no key personnel staff from [KIC],
and (3) did not demonstrate how it would manage subcontractors .
. . .” Id. at 9. In our view, HUD’s evaluation strayed from the
RFP’s stated evaluation scheme. As indicated above, the RFP
expressly provided that “[t]he Offeror and/or its proposed key
personnel and/or proposed subcontractors must have performed the
same or similar services as required by the solicitation over
approximately the last three years.” RFP at M-2. Despite HUD’s
attempt to argue that the term “and/or” immediately following
the term “Offeror” permits other entities (key personnel or
proposed subcontractors) to contribute to an offeror’s showing
of experience, but not substitute for it entirely, that is not
the commonly understood meaning of the term “and/or.” Rather,
the term “and/or” as used in this context indicates that the
experience requirement can be met jointly (X and Y together meet
the requirement) or by one of the named entities (either X meets
the requirement, or Y meets the requirement). Accordingly, KIC’s
proposed approach of meeting the experience requirement with its
properly-committed subcontractor was consistent with evaluation
scheme; HUD’s finding that the proposal was technically
unacceptable in this regard was not. As noted above, in the
agency report, HUD also argues that the CO now views KIC’s
proposal as unacceptable under the third evaluation factor,
management plan. (During the contemporaneous evaluation, KIC’s
proposal was rated acceptable under the management plan factor.)
Generally, we accord little weight to agency efforts to defend,
in the face of a bid protest, a prior source selection through
the submission of new analyses, because such reevaluations and
redeterminations prepared in the heat of the adversarial process
may not represent the fair and considered judgment of the
agency. Boeing Sikorsky Aircraft Support, B-277263.2,
B-277263.3, Sept. 29, 1997, 97-2 CPD para. 91 at 15. In
addition, we note that the management plan factor in section M
of the RFP was focused entirely on whether an offeror’s proposal
indicated sufficient awareness of the 6-day turnaround for
inspections required by the solicitation. As mentioned above,
the contemporaneous evaluation materials indicate that HUD’s
evaluators thought the proposal met this requirement, and based
on our review of the record here, we see no basis to question
that conclusion. (KIC Development,
LLC, B-297425.2, January 26, 2006) (pdf)
The predicate to Aerosol's arguments is its view that the agency
improperly considered the past performance history of IH&T's
employees and/or corporate partners. We disagree. Generally, an
agency properly may attribute the experience or past performance
of a parent or affiliated company to an offeror where the firm's
proposal demonstrates that the resources of the parent or
affiliated company will affect the performance of the offeror.
Universal Bldg. Maint., Inc. , B-282456, July 15, 1999, 99-2 CPD
Paragraph 32 at 6; Phillips Nat'l., Inc. , B-253875, Nov. 1,
1993, 93-2 CPD Paragraph 252 at 6 (rejecting protester's
argument that only the "actual awardee" was entitled to list
prior contract for purpose of past performance). The relevant
consideration is whether the resources of the parent or
affiliated company--its workforce, management, facilities or
other resources--will be provided or relied upon for contract
performance, such that the parent or affiliate will have
meaningful involvement in contract performance. NAHB Research
Ctr., Inc. , B-278876.2, May 4, 1998, 98-1 CPD Paragraph 150 at
4-5. Here, the record shows that the agency recognized that IH&T
had no experience of its own but the evaluators considered the
past performance history of the awardee's three partners--M.A.
Cecil & Associates, Inc. (Cecil), Comar Associates, Inc. (Comar),
and All American Environmental Services, Inc.(All American). AR
exh. 6, TEC Rating Sheets, Questionnaires, and Notes. In this
regard, IH&T's proposal stated that it is a Limited Liability
Corporation (LLC) that was created to combine the experience,
abilities and strength of three companies that have long
histories of providing industrial hygiene, safety and
environmental services to the Department of Defense. For more
than twenty years, the Partners of IH&T provided these services
as independent companies, often in joint ventures with each
other. Recently, the Presidents of each company combined forces,
incorporating the staff and resources of each company to form IH&T,
LLC to provide the manpower, expertise and strength that will be
required for engagements of this size and scope. While the
corporate structure and name reflect the creation of a new
entity, the managing partners and staff are the same highly
qualified professionals who have provided industrial hygiene,
safety and environmental services . . . AR exh. 4, IH&T's
Proposal, at 3-1. IH&T's proposal provided elsewhere that the
"organizational structure of IH&T allows [the firm] to have a
senior partner dedicated to each area of task responsibility for
this program." Id. In addition, IH&T's proposal specifically
indicated that all of its past performance contracts are
"multi-year contracts awarded to the companies owned by the
three partners of IH&T." AR exh. 4, IH&T's Proposal, at 1-5. The
consideration of the three partners' past performance here was
consistent with the Federal Acquisition Regulation (FAR), which
specifically permits agencies "to take into account past
performance information regarding predecessor companies, [or]
key personnel, who have relevant experience, or subcontractors
that will perform major or critical aspects of the requirement."
FAR Section 15.305(a)(2)(iii). In addition, the fact that IH&T
has no past performance history of its own need not have
resulted in a lower past performance and higher risk rating, as
contended by AMA. As noted above, the awardee's proposal
unequivocally provides that each of the three partners, as well
as their personnel and resources, would be involved in the
performance of the contract. Thus, the proposal did provide a
basis for the agency to consider the experience of the firm's
three partners--Cecil, Comar, and All American--in evaluating
the past performance of IH&T. Battelle Mem'l Inst., B-278673,
Feb. 27, 1998, 98-1 CPD Paragraph 107 at 22. Moreover, the
record makes clear that Cecil, Comar, and All American each have
a long history of performing industrial hygiene, safety, and
environmental services, and AMA does not question these
companies' record of successful past performance in this regard,
which the agency, based on references received by the
evaluators, evaluated as consistently positive. Accordingly, on
the basis of the record here, we find no basis to question the
agency's evaluation of IH&T's proposal under the past
performance evaluation factor. (Aerosol
Monitoring & Analysis, Inc., B-296197, June 30, 2005) (pdf0
ELE's protest that the agency erroneously evaluated the
awardees' experience is based primarily on its belief that none
of the awardees has the required relevant experience to justify
their receiving a rating equal to or greater than ELE's rating.
However, the record shows that AMES, JWK, and VWI all have
significant experience providing operation and maintenance
services at medical facilities, both as prime contractors and
subcontractors. AR, Tab 3, Source Selection Evaluation Board
Report, at 25, 82 and 106. While the protester is correct that
Ginn and QSI have limited operation and maintenance experience
as prime contractors, the record shows that both of these
offerors proposed a team member with highly relevant experience
with medical facilities. For example, the SSA specifically
recognized that Ginn's primary weakness in medical operation and
maintenance experience was offset by its proposal to team with
an experienced subcontractor with highly relevant medical
operation and maintenance experience. AR, Tab 4, Source
Selection Decision, at 5. Similarly, while QSI had limited
direct experience with medical operation and maintenance
services, the record shows that QSI included in its proposal
evidence of a formal DoD/SBA Mentor-Protg Program agreement with
an experienced contractor, and the SSA determined that this
teaming arrangement "significantly enhanced" QSI's ratings. Id.
at 6. ELE asserts that the agency's consideration of proposed
subcontractor experience for Ginn and QSI was improper. Here, as
described above, the RFP clearly placed offerors on notice that
they could propose subcontractors and that at least with respect
to past performance, the RFP specifically stated that a
subcontractor's prior projects would be evaluated. RFP B, 14. In
this connection, an agency may consider an offeror's
subcontractor's capabilities and experience under relevant
evaluation factors where, as here, the RFP allows for the use of
subcontractors and does not prohibit the consideration of a
subcontractor's experience in the evaluation of proposals. FMC
Corp. , B-252941, July 29, 1993, 93-2 CPD 71 at 2. Thus, in our
view, the agency's evaluation of the offerors' subcontractors
was not objectionable under the RFP. (Erica
Lane Enterprises, Inc., B-295068, January 19, 2005) (pdf)
The Air Force maintains that its evaluation of the program
managers experience was proper. According to the program
managers resume, prior to his retirement from the Navy as a
Captain, he had served as the Executive Officer for a Naval
Medical Clinic from June 2001 through May 2004 and as a Navy
Family Advocacy Coordinator from March 1999 to June 2001. In
evaluating the program managers experience, the agency indicates
that, despite the statements in the awardees proposal, its
technical evaluators were familiar with the positions held by
FAP personnel among the different services and were aware that
by virtue of his Executive Officer position the program manager
proposed by RehabPlus had the desired experience. In addition,
the agency notes that the proposed program managers experience
was well known throughout the Navy and the Department of
Defense. The agency also highlights the fact that two other
offerors proposed the same program manager and demonstrated that
he met the desired experience under the management subfactor. As
a final matter, the proposed program manager submitted a
declaration in response to the protest, which details his
experience and establishes that he met the desired experience
for the management subfactor. Based on this record, we conclude
that the agencys evaluation of the awardees program manager was
reasonable. (The OMO Group, Inc.,
B-294328, October 19, 2004) (pdf)
Based on the record, we think that the agency's evaluation was
reasonable. First, to the extent that ATL argues that risk, in
and of itself, was an undisclosed evaluation criterion, we note
that agencies may always consider a proposal's risk to
successful performance where that risk is intrinsic to the
stated evaluation factors. Ridoc Enter., Inc. , B-202962.4, July
6, 2004, 2004 CPD __ at 7; Davies Rail & Mech. Works, Inc. ,
B-278260.2, Feb. 25, 1998, 98-1 CPD 134 at 10. Next, although an
agency may consider the separate qualifications of individual
partners in evaluating a joint ventures experience or past
performance, there is no converse requirement that an agency
disregard a lack of experience or past performance by the joint
venture. Transventures Intl, Inc. , B-292788, Nov. 4, 2003, 2003
CPD 195 at 7; Global Engg & Constr. Joint Venture , B-275999 et
al. , Oct. 6, 1997, 97-2 CPD 125 at 9; MR&S/AME, An MSC Joint
Venture , B-250313, B-250313.2, Mar. 19, 1993, 93-1 CPD 245 at
9. Further, we do not think that the RFPs statement that joint
ventures whose partners had prior experience working together
would receive more weight, or any other language in the RFP, in
any way prohibited the agency from reasonably considering that a
joint venture whose partners lacked prior work experience
together might pose a risk to successful performance. The SSB
risk assessments here were well within the agency's discretion,
as they reasonably related to the stated evaluation factor of
organizational experience, which required offerors to
demonstrate the degree to which an offeror has completed recent
new construction projects that are similar in scope,
construction features, monetary value and complexity, and also
to the stated evaluation factor of organizational past
performance, which required offerors to demonstrate that the
offeror has managed projects submitted under Factor 1 [that are
relevant based on the criteria of] new construction projects
physically completed within the past five years, have somewhat
similar construction features, and are somewhat similar in
dollar value and complexity. RFP amend. 2, 202, at 1.2, Factors
1 and 2. (AIA-Todini-Lotos,
B-294337, October 15, 2004) (pdf)
Command protests the agency's past/present performance
evaluation, essentially arguing that, based on the prior
experience of Command's proposed project manager, the agency was
required to rate Command's past/present performance as
exceptional/high confidence. We disagree. Here, the agency
evaluated Command's past/present performance as
satisfactory/confidence because Command had not performed any
contracts that constituted relevant past performance; that is,
Command's prior contracts were relatively small, and the scope
of activities previously performed was more limited than the
broad range of activities required under this solicitation. As
noted above, the RFP contained clear definitions regarding
relevant past/present performance, and also advised offerors
that, in evaluating past/present performance the agency would
consider the risks and strengths identified in the past and
present performance record of each offeror. The agency's
procurement record amply supports the agency's concern that
Command, the corporate offeror, had not, performed any contracts
of sufficient size or scope to qualify as relevant past
performance. Although Command's proposal of an experienced
project manager reduced the agency's assessment of risk flowing
from Command's limited corporate experience, we find nothing
unreasonable in the agency's assessment of only a
satisfactory/confidence rating. Accordingly, Command's assertion
that the experience of one individual, its proposed project
manager, mandated a rating of exceptional/high confidence is
without merit. (Command Enterprises,
Inc., B-293754, June 7, 2004) (pdf)
Ridocs argument that the experience of its individual managers
demonstrates its ability to manage this contract is based on its
belief that the agency must impute to Ridoc, as an organization,
the experience of its proposed managers. We have held, however,
that while an agency may properly consider the experience of key
personnel in evaluating an entitys corporate experience, Rice
Servs., Ltd. , B284997.5, Mar. 12, 2002, 2002 CPD 59 at 5,
absent a solicitation provision mandating such consideration,
there is no legal requirement that it do so. Id. In any event,
we note that the information submitted regarding the experience
of the various managers was general in nature, lacking
specificity and detail. For example, Ridocs vice president was
described as having a background in management of both
manufacturing and service businesses. He oversees a commercial
security contract and is familiar with the requirements and has
participated fully in the preparation of this proposal. [He] has
27 years management experience in local government and
commercial activities. Ridoc Quotation at 7. The agency could
reasonably view such general summaries as lacking the detail
required to assess the firms management capability. Accordingly,
we conclude that the corporate experience/management capability
evaluation was reasonable and consistent with the RFQ. (Ridoc
Enterprise, Inc., B-292962.4, July 6, 2004) (pdf)
Our
reading of the materials submitted with the agency report
provides no support for HSG’s contention that the Army’s
evaluation has been rendered invalid by the change in SGM’s
ownership. For example, the record shows only that the corporate
shares of SGM changed hands. AR, Tab 3, at 2. In addition, the
new owners have indicated that the entity formerly known as SGM
remains intact, has the same location and offices, and intends
to honor its prior commitments. Id. In our view, this situation
is analogous to those where an agency properly credits an
offeror with the favorable past performance experience of key
employees who gained their experience working elsewhere. See MCR
Eng’g Co., Inc., B-287164, B-287164.2, Apr. 26, 2001, 2001 CPD ¶
82 at 7. In fact, unlike in MCR, there is no suggestion that any
of the strengths of the entity formerly known as SGM are other
than fully intact and available. Put simply, there is nothing in
this record that suggests that the licenses and permits, the
specialized personnel, the information conveyed during the oral
presentation, or the administrative resources offered by SGM
have been rendered unavailable, or in any way changed by this
transaction. (Consortium HSG
Technischer Service GmbH and GeBe Gebäude- und,
B-292699.6, June 24, 2004) (pdf)
IMC next complains that TLD “misrepresented” the status of one
of its proposed key personnel, and that TLD’s proposal should
have been downgraded under the technical/management subfactor
for failing to submit a resume for that individual. In this
regard, the record shows that both IMC’s and TLD’s proposals
offered the same individual to perform as key personnel. In
short, IMC asserts that, because the individual at issue was
committed to IMC as its project manger, he could not also be
committed to TLD. We disagree. As with past performance, we
review challenges to an agency’s technical evaluation only to
determine whether the agency acted reasonably and in accord with
the solicitation’s evaluation criteria and applicable
procurement statutes and regulations. PharmChem, Inc.,
B-291725.3 et al., July 22, 2003, 2003 CPD ¶ 148 at 3. Here, the
record shows that TLD unambiguously disclosed to the agency that
TLD could not provide the proposed job superintendent’s resume
because of that individual’s commitment to its current employer,
IMC. AR, Tab 7, TLD’s Initial Proposal, at 156. Nonetheless,
TLD’s proposal included a letter of intent, signed by the
individual in question, stating that “based on the successful
bid [of TLD under this solicitation],” this individual “will
assume [the] position as job superintendent.” Id at 162. The
record further shows that the Army recognized that TLD’s
proposed job superintendent was currently managing the grounds
maintenance work for IMC and that he had also been proposed as
IMC’s project manager. AR, Tab 9, TLD’s Overall
Technical/Management Rating, at 1-2; Tab 8, IMC’s Overall
Technical/Management Rating, at 1. On this record, there is no
merit to IMC’s assertion that TLD’s proposal misrepresented the
individual’s status. (Family
Entertainment Services, Inc., d/b/a/ IMC, B-291997.4, June
10, 2004) (pdf)
Where an agency is evaluating the experience and past
performance of a joint venture, there is nothing improper in the
agency considering the specific experience and past performance
of the entity that would actually perform the work so long as
doing so is not expressly prohibited by the RFP. Base Techs.,
Inc., B-293061.2, B-293061.3, Jan. 28, 2004, 2004 CPD ¶ 31 at
10. Moreover, the SBA regulations governing the mentor-protégé
program do not provide otherwise, see 13 C.F.R. § 124.520, and
we find no other basis for precluding the agency from
considering the experience and past performance of both partners
in such an arrangement. Urban-Meridian Joint Venture, B-287168;
B-287168.2, May 7, 2001, 2001 CPD ¶ 91 at 3. It is undisputed
that the RFP does not indicate how joint venture proposals would
be evaluated. However, the record shows that, consistent with
the terms of the RFP, the agency evaluators determined that it
was important to consider the experience and past performance of
the individual joint venture partners since each would perform
major or critical aspects of the solicited requirements. Such a
determination should, in our view, be considered a matter of
contracting agency discretion, and the protester has not shown
that the agency abused its discretion in this regard. The fact
that the protester disagrees with the agency does not establish
that the evaluation approach was unreasonable. The Paintworks,
Inc., B-292982, B-292982.2, Dec. 23, 2003, 2003 CPD ¶ 234 at 3.
With respect to the protester’s specific allegation that the
agency based the consensus evaluation ratings for the joint
venture by simply averaging the individual joint venture
partners’ ratings, the record reflects otherwise. As explained
previously, the JACO/MCC consensus ratings were the product of
an SSEB meeting at which the evaluators discussed their
assessments in order to develop a consensus rating for each
factor. Contracting Officer’s Statement of Facts at 2-3. The
record further shows that the SSEB reviewed and analyzed the
joint venture agreement and the SSEB chairman prepared a table
listing the individual partners’ and the joint venture’s
responsibilities under the contract. For example, while the
joint venture would provide [DELETED], MCC would review
[DELETED] and JACO would direct [DELETED]. Similarly, while the
joint venture would provide [DELETED], MCC would establish
[DELETED] procedures subject to JACO’s approval. The SSEB also
noted that under the joint venture agreement, JACO was
[DELETED]. AR exh. 8, Revised SSEB Evaluation, at 15; AR exh.
30, JACO/MCC Joint Venture Agreement, at 2. The protester argues
that the agency’s conclusion that the individual joint venture
partners’ responsibilities under this contract would be 50/50
impermissibly ignored the clear weight of responsibility that
resided with the mentor partner. Protester’s Comments at 3, Mar.
26, 2004. Given the respective roles of the partners as
identified by the SSEB from the joint venture agreement, we have
no basis to question the SSEB’s conclusion that both joint
venture partners’ experience and past performance should be
evaluated and given equal weight. (JACO
& MCC Joint Venture, LLP, B-293354.2, May 18, 2004) (pdf)
The agency does not dispute the protester’s assertion that the
agency failed to consider its key personnel under the corporate
experience factor. Rather, the agency maintains that it was not
required to consider Ashe’s management personnel when evaluating
Ashe’s corporate experience as an entity. 14 The record
reflects, however, that the agency considered Kira’s “key
personnel” when it evaluated Kira’s corporate experience. For
example, in the final SSB report, which was approved by the SSA,
the SSB changed the “marginal” rating it had assigned to Kira’s
corporate experience in prior evaluations to an “acceptable”
rating, stating that Kira’s “key personnel” warranted the rating
and offset performance risks. See AR, exh. 16, supra, at 2-3.
Moreover, the TEB report, which was prepared after the first
round of discussions, explains that Kira’s lack of similar
experience for the [deleted] work required under the RFP was
“offset by the experience of Key Personnel.” AR, exh. 11, TEB
Report, Kira Synopsis, at 1. Finally, the chairman of the SSB
stated in a declaration prepared in response to Ashe’s protest
that Kira’s final acceptable rating for corporate experience was
warranted based, in part, on Kira’s “key personnel.” AR, exh.
18, Decl. of SSB Chairman, at 3. Given the clear indication in
the record that the agency considered Kira’s key personnel under
the corporate experience factor, it was unfair for the agency
not to consider Ashe’s key management personnel under the same
factor. This disparate treatment rendered the agency’s
evaluation of corporate experience unreasonable. Lockheed Martin
Info. Sys., B-292836 et al., Dec. 18, 2003, 2003 CPD ¶ 230 at
11-12. (Ashe Facility Services,
Inc., B-292218.3; B-292218.4, March 31, 2004) (pdf)
Where an RFP requires the evaluation of offerors’ past
performance, an agency has the discretion to determine the scope
of the offerors’ performance histories to be considered,
provided all proposals are evaluated on the same basis and
consistent with the RFP’s requirements. Honolulu Shipyard, Inc.,
B-291760, Feb. 11, 2003, 2003 CPD ¶ 47 at 4. The performance
history of one or more of the individual joint venture partners
may be considered in evaluating the past performance of the
entire joint venture, so long as doing so is not expressly
prohibited by the RFP. Northrop Grumman Tech. Servs., Inc.;
Raytheon Tech. Servs. Co., B-291506 et al., Jan. 14, 2003, 2003
CPD ¶ 25 at 30. Here, the RFP did not preclude consideration of
a joint venture partner’s past performance in lieu of
performance by the joint venture entity, or require
consideration of all of the partners’ past performance, but
instead contemplated that the agency would evaluate relevant
contracts and subcontracts that are similar in nature to the
requirements of the RFP. In its proposal, LAJV identified
several prior contracts from only one of its partners, LifeCare,
who was proposed to provide investigation experts and analysts,
to include all of the senior project management and supervisory
team and senior data retrieval specialists, and corporate
resources for specialized investigation research training and
Microsoft product training. The proposal explained that
LifeCare’s “core competencies include legal counsel, forensic
accounting, auditing, assessments and reviews, investigations,
data analysis, data mining, case management, and centralized
operations center management.” AR, Tab 8, LAJV Proposal, § 1.3.
Given that the description of LifeCare’s efforts encompassed
most of the services required under the RFP, we find that the
agency could properly consider LifeCare’s performance history to
be reasonably predictive of the performance of the joint venture
as a whole. See Northrop Grumman Tech. Servs., Inc., supra, at
30-31. (Base Technologies, Inc.,
B-293061.2; B-293061.3, January 28, 2004) (pdf)
The record here shows that in evaluating MMF's past/present
performance, the agency gave MMF credit for Spray Systems'
substantial experience in manufacturing and providing paint
booths, for which Spray Systems received ratings of very good
and exceptional from each of its references.[2] The experience
of a proposed subcontractor properly may be considered in
determining whether an offeror meets experience or past
performance requirements where the solicitation does not
expressly prohibit its consideration. See Federal Acquisition
Regulation § 15.305(a)(2)(iii); Rolf Jensen & Assocs., Inc.,
supra, at 6. Given the absence of any prohibition in the RFP on
consideration of a subcontractor's relevant experience, and in
view of Spray Systems' positive references, it was reasonable
for the agency to favorably consider Spray Systems' experience
in evaluating the awardee's ability to perform the RFP's
requirements. (The Paintworks, Inc.,
B-292982; B-292982.2, December 23, 2003) (pdf)
The record
shows that the agency in fact considered all of Career Quest’s
and [deleted]’s experience in the evaluation, and that it
assigned strengths to Career Quest based on its association with
its subcontractor, and that firm’s experience with a similar
operation and continuity of service. AR, Tab 12, at 6. However,
as discussed above, Career Quest was downgraded due to the lack
of its own similar experience. In this regard, the RFP
specifically warned joint arrangement offerors (such as Career
Quest) that their proposals must clearly demonstrate that the
section 8(a) prime contractor had sufficient experience and
resources of its own, and was not relying solely on the
subcontractor to provide the expertise and/or resources. RFP
Addendum H at H‑1(b)(12)(b). Since Career Quest, the proposed
prime contractor, failed to provide information establishing
that it possessed similar experience, as discussed above, we
have no basis for questioning the agency’s determination that
Career Quest was unacceptable under the experience factor, and
its decision to eliminate Career Quest’s proposal from the
competitive range. (Career Quest, Inc.,
B-292865; B-292865.2, December 10, 2003) (pdf)
The evaluation here was reasonable. First, while the record
shows that the agency indeed was aware that Delco held its
supplier responsible for the late deliveries, the agency had no
information--and the record contains none--definitively showing
that Delco's position regarding the cause of the delinquencies
was the correct one. Rather, the agency was aware that the
delivery problems may be due to other problems Delco was having;
the agency states--without purporting to adjudicate any
dispute--that it had “information from more than one source that
problems [with Delco] did exist and were related to a history of
late payments for materials by the protester to its
subcontractor.” AR at 13. The agency also was aware that, as
noted above, it had been necessary for it to provide webbing to
Delco to “optimize” delivery under another recent contract. As
indicated above, an agency's evaluation properly may be based on
its reasonable perception of inadequate prior performance,
whether or not the offeror disputes the agency's interpretation
of the facts. The agency's perception of Delco's performance
problems clearly was reasonable, since it had no information
establishing that the information it had been presented was
incorrect, and there had been no formal adjudication of the
matter in Delco's favor. Contrary to Delco's assertion, we find
nothing unreasonable in the agency's considering the information
furnished by the supplier; the mere fact that Delco disputed it
did not render it invalid or any less reliable than the
information Delco had furnished. In any case, Delco's attempt to
absolve itself of all responsibility for the delayed deliveries
is unavailing; as the agency point out, a prime contractor under
a government contract is normally responsible for the
performance of its subcontractors. ViaSat, Inc., B‑291152,
B‑291152.2, Nov. 26, 2002, 2002 CPD ¶ 211 at 8; Neal R. Gross &
Co., Inc., B-275066, Jan. 17, 1997, 97-1 CPD ¶ 30 at 4. Delco
has not established that a different rule should apply here.
(Delco Industrial Textile Corporation,
B-292324, August 8, 2003) (pdf)
Gentex also contends that Scott should not have been credited
with SAIC's past performance experience. We disagree. As a
general rule, subcontractor and team member performance may be
considered in assessing past performance. Battelle Mem'l Inst.,
B-278673, Feb. 27, 1998, 98-1 CPD ¶ 107 at 22; Phillips Nat'l,
Inc., B-253875, Nov. 1, 1993, 93-2 CPD ¶ 252 at 6 (rejecting
protester's argument that only the "actual awardee" was entitled
to list prior contract for purpose of past performance). The
consideration of both the team members' past performance here
was consistent with the RFP, which specifically required
consideration of the PDRR "team effort" (which includes both
Scott and SAIC) and prototype quality (which reflects the work
of both Scott and SAIC). RFP § M, at 6. In
addition, Scott's lack of prime contractor experience under the
PDRR contract need not have resulted in a lower past performance
and higher risk rating, as contended by Gentex. As Scott's
proposal states, "SAIC was the logical lead for an effort that
was primarily [research & development] and involved extensive
integration with aircraft and [life support equipment]. . . .
Scott is the logical prime contractor for the SDD and Production
phases, where final development for manufacturing and production
are the primary emphasis." Scott Proposal, vol. I, Executive
Summary, at 1. Based on our review, we think the agency
reasonably considered the PDRR team's experience in finding that
Scott's past performance was satisfactory. (Gentex
Corporation--Western Operations, B-291793; B-291793.2;
B-291793.3, March 25, 2003) (txt
version)
Here,
the record establishes that DFAS performed its own research
regarding the status of BOA and Bank of America, N.A. (USA),
concluding that, although both companies were wholly-owned
subsidiaries of Bank of America Corporation, they are, in fact,
separate legal entities. AR, Tab Y, Evaluation Summary, Tab Y-4.
The agency further determined that the two entities have
substantially different workforces, management, and facilities.
Id. Finally, based on these considerations, along with the fact
that DFAS has been responsible for administering both the travel
card contract and the OMBP contract and has interfaced with
different legal and managerial entities for the two contracts in
the past, the agency concluded that Bank of America, N.A. (USA)
would not be involved in performing the OMBP contract and that
it would be inappropriate to consider performance of the travel
card contract in connection with the evaluation of BOA's past
performance for the OMBP contract. On this record, we have no
basis to question the reasonableness of the agency's
determination. (National
City Bank of Indiana, B-287608.3, August 7, 2002) (pdf)
Federal Acquisition Regulation
(FAR) § 15.305(a)(2)(iii) directs agencies to take into
account past performance information regarding predecessor
companies, key personnel, and major subcontractors when such
information is relevant to an acquisition. Thus, the
agency properly can consider the relevant experience and past
performance history of the individual joint venture partners in
evaluating the past performance of the joint venture, so long as
doing so is not expressly prohibited by the RFP. See
Rolf Jensen & Assocs., Inc., B-289475.2, B-289475.3,
July 1, 2002, 2002 CPD ¶___ at 6; Dynamic Isolation Sys.,
Inc., B-247047, Apr. 28, 1992, 92-1 CPD ¶ 399 at 7 n.7.
Here, not only did the RFP not prohibit considering the
experience/past performance of the individual joint venture
partners in the evaluation, as noted above, it specifically
encouraged (RFP at 3-4) offerors to provide such information.
The record shows that BNCI/AKAL's
proposals contained the required financial information regarding
both individual joint venturers. Agency Report, Tab 14,
BNCI/AKAL Proposal § C. Contrary to MVM's contentions,
the separate qualifications and financial capability of each of
the legal entities in a joint venture properly can be considered
in evaluating the qualifications of the joint venture. See
Beneco Enters., Inc., B-239543.3, June 7, 1991, 91-1
CPD ¶ 545 at 6‑7. Our review confirms
that the agency considered, and could reasonably conclude from,
the information submitted in BNCI/AKAL's proposal that the joint
venture could complete the requirements of the contracts.
(MVM,
Inc., B-290726; B-290726.2; B-290727; B-290727.2, September
23, 2002) (pdf)
In determining whether one
company's performance should be attributed to another, the
agency must consider not simply whether the companies are
affiliated, but also the nature and extent of the relationship
between the two--in particular, whether the proposal
demonstrates that the workforce, management, facilities, or
other resources of the affiliate may affect contract performance
by the offeror. Perini/Jones, Joint Venture, B-285906, Nov. 1,
2000, 2002 CPD ¶ 68 at 4-5; ST Aerospace Engines Pte. Ltd., B-275725,
Mar. 19, 1997, 97-1 CPD ¶ 161 at 3. Here, the record shows that
Penauille did not propose to use its corporate affiliate to
perform the present contract. Although the agency now states
that two high-level management personnel are shared by the two
affiliates, Penauille's proposal did not commit either person to
performance under the present contract. Thus, the proposal did
not provide any basis for the agency to consider the experience
of Penauille's affiliate in evaluating the past performance of
Penauille. See ST Aerospace Engines Pte. Ltd., supra at 3-4
(shared top level management is not sufficient basis to credit a
firm with an affiliated entity's past performance experience
where the proposal does not show that these personnel would be
involved in contract performance). It is also notable that
the agency did not offer this argument until late in the protest
process. It clearly was not part of the evaluation upon which
the award was based; rather it is a reevaluation of the proposal
conducted in the heat of an adversarial process. As such, it may
not represent the fair and considered judgment of the agency,
which is a prerequisite of a rational evaluation and source
selection process. We thus find it inappropriate to accord any
significant weight to the agency's position. See Tennier Indus.,
Inc., B-286706.2, B-286706.3, Mar. 14, 2001, 2002 CPD ¶ 75 at 5
n.4; Boeing Sikorsky Aircraft Support, B-277263.2, B-277263.3,
Sept. 29, 1997, 97-2 CPD ¶ 91 at 15. Once the Paris contracts
are removed from consideration, the record does not support a
finding that Penauille's contracts exceeded the scope or
complexity of the RFP requirements.
(Gemmo
Impianti SpA, B-290427, August 9, 2002) (pdf)
Viewing
the protest as a whole, we understand Hot Shot's essential
argument to be that, lacking a DOT motor carrier identification
number of its own, CSS could not be "regularly established
in business to provide transport services"--as required by
the solicitation--and could not have past performance of its
own. This argument is without merit. An agency properly may
attribute the experience or past performance of a parent or
affiliated company to an offeror where the firm's proposal
demonstrates that the resources of the parent or affiliated
company will affect the performance of the offeror. Universal
Bldg. Maint., Inc., B-282456, July 15, 1999, 99-2 CPD ¶ 32 at
6. The relevant consideration is whether the resources of the
parent or affiliated company--its workforce, management,
facilities or other resources--will be provided or relied upon,
such that the parent or affiliate will have meaningful
involvement in contract performance. Perini/Jones, Joint
Venture, B-285906, Nov. 1, 2000, 2002 CPD ¶ 68 at 4-5; NAHB
Research Ctr., Inc., B-278876.2, May 4, 1998, 98-1 CPD ¶ 150 at
4-5. Further, where, as here, no provision in the solicitation
precludes offerors from relying on the resources of their
corporate parent or affiliated companies in performing the
contract, and an offeror represents in its proposal that
resources of a related company will be committed to the
contract, the agency properly may consider those resources in
evaluating the proposal. See Physician Corp. of Am., B-270698 et
al., Apr. 10, 1996, 96-1 CPD ¶ 198 at 13. The record here
indicates that the resources of CSS's parent and affiliated
companies will have meaningful involvement in contract
performance. CSS's proposal indicated that CSS is part of a
family of wholly-owned subsidiaries and closely-held affiliates
with interlocking officers and boards of directors, which
provide a variety of services to the federal government, and the
parent of which was Crown Management Services, Inc. According to
the proposal, although the Crown companies operate as
independent cost centers, they report to the corporate office in
Pensacola, Florida, from which they receive corporate resources
and support as required. CSS Past Performance Proposal at
2. (Hot
Shot Express, Inc. , B-290482, August 2, 2002) (pdf)
In this regard, an agency may reasonably attribute to an offeror the performance of
firms that are members of the offeror’s proposed team where the team members are
to be involved in the contract effort. Wackenhut Servs., Inc., B-276012.2, Sept. 1,
1998, 98-2 CPD ¶ 75 at 6. As discussed above, the agency recognized that RLM did
not have its own experience in providing emergency room physician services.
However, to perform this contract, RLM teamed with RGB, which did have
experience similar to that required by the RFQ, that is, experience in providing
physicians and other medical personnel to the government. Since the RFQ did not
prohibit teaming arrangements, we believe the agency reasonably determined to
evaluate and credit RLM with the similar experience of RGB, RLM’s team member
for performance of the RFQ requirements. Other than expressing disagreement with
this aspect of the agency’s evaluation, Godwin has provided no meaningful basis for
our Office to question the reasonableness of the agency’s evaluation of RLM’s offer
in the area of experience. (Godwin
Corporation, B-290291, June 17, 2002 (pdf))
TyeCom asserts that it was entitled
to an exceptional rating under this evaluation factor based on
the past performance of its company president, and that DOE
improperly failed to credit this experience. TyeCom cites FAR
15.305(a)(2)(iii) as requiring that "the evaluation take
into account past performance information regarding predecessor
companies, key personnel who have relevant experience, or
subcontractors that will perform major or critical aspects of
the requirement when such information is relevant to the instant
acquisition.* Protest at 6. While, in fact, the FAR language
cited by the protester is precatory rather than mandatory, the
simple and undisputed answer is that for purposes of evaluation
as key persons under section L-14 of the RFP, the solicitation
designated only the program manager and assistant program
manager. AR.3 at 6. TyeCom's company president was not proposed
to fill either position and therefore does not fall within the
purview of the key person requirement. The agency also correctly
points out that while, in appropriate circumstances, an agency
properly may consider the experience of supervisory personnel in
evaluating the experience of a new business, there is no legal
requirement for an agency to attribute employee experience to
the contractor as an entity. Hard Bodies, Inc., B-279543, June
23, 1998, 98-1 CPD ¶ 172 at 4. Accordingly, the agency was
under no obligation to credit TyeCom as a corporate entity with
the individual experience or past performance of the company's
president; TyeCom's protest allegation is misplaced as to both
fact and law. (TyeCom,
Inc., B-287321.3; B-287321.4, April 29, 2002) (pdf)
We think that the agency's
decision not to attribute the past performance of MCS's
subcontractor to MCS in rating its past performance was
reasonable. The key consideration in determining whether a
subcontractor's past performance should be considered is whether
the experience is reasonably predictive of the offeror's
performance under the contract. Strategic Res., Inc., B-287398,
B-287398.2, June 18, 2001, 2001 CPD para. 131. As indicated, the
RFP stated that the "organization itself will be evaluated
with respect to the Offeror's past experience." RFP at 36.
Based on our review of the record, we conclude that the agency
reasonably determined that MCS's subcontractor, which was to
supply [DELETED] of the [DELETED] full-time employees, was not a
major or critical subcontractor, and thus did not attribute the
experience of this subcontractor to MCS; MCS's contesting of
this point constitutes mere disagreement which does not render
the agency's judgment in this regard unreasonable. Strategic
Res., Inc., supra; Oceanometrics, Inc., B-278647.2, June 9,
1998, 98-1 CPD para. 159 at 5. (MCS
of Tampa, Inc., B-288271.5, February 8, 2002)
While agencies may consider the
prior relevant experience of subcontractors, in the absence of a
solicitation provision to the contrary, there is no broad
requirement that they do so. North State Res., Inc., B-282140,
June 7, 1999, 99-2 CPD para. 60 at 7. (Systems
Management, Inc.; Qualimetrics, Inc., B-287032.5;
B-287032.6, November 19, 2001)
Al
Hamra argues that Al Musairie cannot be a successor to Baddah
& Musairie because that firm still exists as a legal entity.
However, as noted, the key consideration in this area is whether
the experience evaluated reasonably can be considered predictive
of the offeror's performance under the contract. Since Al
Musairie has acquired the resources Baddah & Musairie used
in performing the cited contracts, thus affording some
additional confidence in the likelihood of successful
performance by Al Musairie under the contemplated contract, we
see nothing unreasonable in the agency's considering Baddah
& Musairie's experience in the evaluation, whether or not
Baddah & Musairie remains in existence. (Al
Hamra Kuwait Company, B-288970, December 26, 2001)
The
contract specialist and the contracting officer discussed the
fact that IIUSA is a new company with no corporate experience
and decided that it would be appropriate to evaluate the key
personnel capabilities for IIUSA rather than the company. The
record shows that IIUSA's chief executive officer and two of its
instructors, both of whom were also proposed for management
positions and were previously employed by DRA under its prior
contract for these services, all received excellent ratings from
their references, and that these ratings formed the basis for
the firm's excellent-low risk rating. Since the relevance of the
experience of key personnel experience in an acquisition for
training is self-evident, the Army properly considered such
experience in evaluating IIUSA's proposal for past performance.
(DRA
Software Training, B-289128; B-289128.2, December 13, 2001)
While Lynwood did propose to hire
experienced former SAF personnel, including a former SAF
employee to serve as the project manager, the agency simply
concluded that this employee experience was not equivalent to
SAF's demonstrated relevant corporate experience. In any case,
it did not provide any evidence (such as letters of intent or
commitment) showing that these employees would accept employment
with Lynwood. Under these circumstances, the agency was not
required to credit Lynwood with the employees' experience. See
Urban-Meridian Joint Venture, B-287168, B-287168.2, May 7, 2001,
2001 CPD para. 91 at 3; SWR Inc., B-286044.2, B-286044.3, Nov.
1, 2000, 2000 CPD para. 174 at 2-3. (Lynwood Machine & Engineering,
Inc., B-287652, August 2, 2001)
In determining whether one
company's performance should be attributed to another, the
agency must consider not simply whether the two companies are
affiliated, but the nature and extent of the relationship
between the two--in particular, whether the workforce,
management, facilities, or other resources of one may affect
contract performance by the other. ST Aerospace Engines Pte.
Ltd., B-275725, Mar. 19, 1997, 97-1 CPD para. 161 at 3. In this
regard, it is appropriate to consider an affiliate's performance
record where it will be involved in the contract effort, Fluor
Daniel, Inc., B-262051, B-262051.2, Nov. 21, 1995, 95-2 CPD para.
241 at 12, or where it shares management with the offeror.
Morris Knudsen Corp., B-280261, Sept. 9, 1998, 98-2 CPD para. 63
at 4-5. (Strategic Resources,
Inc., B-287398; B-287398.2, June 18, 2001)
As for Urban-Meridian's
intention to hire the incumbent employees, the firm's proposal
did not include any information demonstrating that these
employees would accept employment with Urban-Meridian. For
example, Urban-Meridian did not submit letters of interest or
intent from the employees, and did not provide an explanation of
how it planned to recruit them; indeed, Urban did not even
indicate that it had contacted the employees. Under these
circumstances, GSA's failure to credit Urban with the experience
of these potential employees was not unreasonable. (Urban-Meridian Joint
Venture, B-287168; B-287168.2, May 7, 2001)
However, agencies properly may
consider an offeror's subcontractor's experience under relevant
evaluation factors where, as here, the RFP allows for the use of
subcontractors to perform the contract, and does not prohibit
consideration of subcontractor experience in the evaluation of
proposals. Premier Cleaning Sys., Inc., B-249179.2, Nov. 2,
1992, 92-2 CPD para. 298 at 4; Commercial Bldg. Serv., Inc.,
B-237865.3, May 16, 1990, 90-1 CPD para. 473 at 6. (Myers Investigative and Security Services,
Inc., B-286971.2; B-286971.3, April 2, 2001)
Protest that agency misevaluated
technical proposals is sustained where record shows that agency
improperly gave awardee evaluation credit for corporate
experience of an affiliated company that was not proposed to
perform the contract. (Perini/Jones,
Joint Venture, B-285906, November 1, 2000)
Agency reasonably assigned a
favorable past performance rating to awardee's proposal based
primarily on the experience of one key individual where
solicitation specifically stated that in assessing past
performance, the agency would consider the experience of key
personnel; that individual has extensive, relevant experience;
and, as corporate vice president and project manager, that
individual will have substantial involvement in managing and
overseeing performance of the contract. (SDS International, B-285822; B-285822.2, September 29, 2000)
An offeror may not propose to
use specific personnel that it does not expect to use during
contract performance; doing so would have an adverse effect on
the integrity of the competitive procurement system and
generally provide a basis for proposal rejection. CBIS Fed.
Inc., B-245844.2, Mar. 27, 1992, 92-1 CPD para. 308 at 5. The
elements of such a "bait and switch" rendering a
contract award improper, are as follows: (1) the awardee
represented in its proposal that it would rely on certain
specified personnel in performing the services; (2) the agency
relied on this representation in evaluating the proposal; and
(3) it was foreseeable that the individuals named in the
proposal would not be available to perform the contract work.
Ann Riley & Assocs., Ltd.--Recon., B-271741.3, Mar. 10,
1997, 97-1 CPD para. 122 at 2-3. (Airwork
Limited-Vinnell Corporation (A Joint Venture), B-285247; B-285247.2, August 8, 2000)
Agency's determination that the
awardee's past performance, based on the experience of one of
the awardee's proposed key personnel, was equal to the
extensive, successful past performance of the protester, was
unreasonable and inconsistent with the solicitation's evaluation
scheme. (Beneco Enterprises,
Inc., B-283512.3, July 10, 2000)
In evaluating the protester's
experience and past performance, an agency was not required to
impute to the protester the totality of its proposed mentor's
experience and past performance, where the mentor was not
proposed to play a major role in the performance of the
contract. (BioGenesis Pacific,
Inc., B-283738, December 14, 1999)
We have sustained protests where
the awardee failed to disclose material changes in personnel
availability which occurred after proposals were submitted, but
before award. See, e.g., Mantech Field Eng'g Corp., B-245886.4,
Mar. 27, 1992, 92-1 CPD para. 309 at 5; CBIS Fed. Inc.,
B-245844.2, Mar. 27, 1992, 92-1 CPD para. 308 at 5-6. Here, the
record shows that Camber agreed to sell the division which it
stated would perform significant TSA work and to transfer the
employees of that division to the acquiring company. Camber did
not notify the Air Force of the sale agreement. (Dual,
Incorporated, B-280719, November 12, 1998)
Agency improperly downgraded
protester's proposal relative to awardee's based on awardee's
more detailed description of proposed elevator maintenance
subcontractor's experience; since protester and awardee proposed
same subcontractor, they should have received same score for
subcontractor's experience. (Consolidated Engineering Services,
Inc, B-279565.2; B-279565.3, June 26, 1998)
As explained above, we conclude
that Dynacs misrepresented the level of commitment it received
from its key personnel, which, together with the agency's
erroneous conclusion that the proposal offered "signed
commitments," led to a material misevaluation of Dynacs's
proposal under the key personnel subfactor within the mission
suitability evaluation factor. We also conclude that the
misevaluation of the key personnel portion of Dynacs's proposal
had a ripple effect in other areas of the mission suitability
evaluation as well. (Aerospace
Design & Fabrication, Inc., B-278896.2; B-278896.3;
B-278896.4; B-278896.5, May 4, 1998) |