Where an agency's requirements change in a material way
after a solicitation has been issued, the agency must
generally issue an amendment and afford all offerors an
opportunity to compete for its changed requirements.
Murray-Benjamin Elec. Co., L.P., B-400255, Aug. 7, 2008,
2008 CPD ¶ 155 at 3-4. Nonetheless, our Office has
explained that where a solicitation contemplates, for
example, ongoing fluctuations of requirements that do not
constitute material changes, and such fluctuations occur
after a solicitation is issued, an agency need not, in
effect, begin the procurement anew. See Companion Data
Servs., LLC, B-410022, B-410022.2, Oct. 9, 2014, 2014 CPD
¶ 300 at 10.
Here, Occam's protest allegations do not establish that
the agency's actions were improper. With regard to the
alleged change in the RFQ's requirement that an opt-in
statement include the certification, Occam characterizes
Amendment 02 as significantly relaxing the requirement by
indicating that a quotation that failed to include a
formal subcontracting relationship with a [Trusted
Internet Connection] (TIC) compliant provider or
TIC-compliant provider or TICAP "would merely receive a
reduced rating for the technical approach, not be
eliminated from consideration for the award." Protest at
1-2; Protester's Comments at 13. We disagree.
Amendment 02 did not materially change this aspect of the
RFQ. Both before and after it was amended, the
solicitation established that only quotations "with the
highest ratings and with no weaknesses or deficiencies
[would] be eligible for award." See RFQ at 94; AR, Tab 13,
RFQ, Amend. 02, at 94. Amendment 02 did not waive or relax
the requirement to provide certification of the vendor's
formal subcontracting relationship with a TIC-compliant
provider, as Occam suggests, but indicated that a failure
to include this certification would result in a rating
that effectively rendered a quotation unacceptable.
Therefore, while the amendment arguably permitted vendors
to submit a quotation without the certification, the
solicitation provided that if a vendor did so, it would
not be eligible for award. In short, the amendment did not
materially change the terms of the solicitation.
Occam nonetheless argues that it was prejudiced by the
agency's decision to "waive these requirements after the
opt-in date had passed" because Occam was not given an
opportunity to compete under the purportedly less
stringent requirements. Protester's Comments at 1. As
explained above, we find no merit to Occam's premise that
the amendment materially changed the certification
requirement, and therefore find that Occam has not
demonstrated that the amendment resulted in competitive
prejudice. The protester has not demonstrated that the
agency's action in this regard had an effect on Occam's
chance of receiving the award.
We conclude that Occam's allegation that the agency waived
a material requirement when it amended the solicitation is
belied by the record and therefore provides no basis to
sustain the protest. (Occam
Solutions, Inc. B-415422, B-415422.2: Jan 9, 2018)
The protester asserts that although it received amendment
2, it did not receive the revised pricing spreadsheet
attachment, and that “[t]he front page of Amendment 2, did
not explicitly state that there were changes made to the
[pricing spreadsheet] Attachment[] E” such that a new
pricing spreadsheet was required. Comments at 3 (citing
RFQ, amend. 2, attach. E). The protester argues that the
requirement for submission of the revised pricing
spreadsheet is ambiguous because “[n]o place or statement
on the front of Amendment 2 stated that a new Attachment E
was required and had to replace the original Attachment
E.” Id. The agency argues that amendment 2 clearly stated
there were changes to the pricing spreadsheet and that Nu‑Way
failed to acknowledge amendment 2 because its quotation
used the outdated pricing spreadsheet that included
transition pricing which should not have been separately
priced, failed to include pricing for the project manager,
and included incorrect mileage reimbursement. Memorandum
of Law at 4-6.
We find that amendment 2 specifically stated that the
following changes were made to attachment E, the pricing
spreadsheet: added not separately priced language to the
transition contract line item number; added a CLIN for a
project manager for San Diego; and increased the mileage
reimbursement rate for several CLINs. RFQ amend. 2 at 1.
All of these changes were summarized on page one of
amendment 2. See RFQ amend. 2, at 1. Regardless of whether
Nu-Way could download or received the revised pricing
spreadsheet, the protester was on notice that the agency
revised the spreadsheet. As a result, the protester should
have availed itself of every reasonable opportunity to
obtain the attachment. See The Creative Mobility Group,
LLC,B‑410380.2, Dec. 19, 2014, 2014 CPD ¶ 376 at 3
(protest against an agency’s solicitation dissemination is
denied where protester failed to avail itself of every
reasonable opportunity to obtain the solicitation
documents).
Generally, a quotation may be rejected for failure to
acknowledge a material amendment. In determining whether
an amendment is material, we look at the facts of each
case. While no precise rule exists as to whether a change
required by an amendment is more than negligible, an
amendment is material where it imposes legal obligations
on the contractor that were not contained in the original
solicitation or subsequent amendments acknowledged by the
offeror. See MG Mako, Inc., B-404758, April 28, 2011, 2011
CPD ¶ 88 at 2; Skyline ULTD, Inc., B-297800.3, Aug. 22,
2006, 2006 CPD ¶ 128 at 3. An amendment may be
constructively acknowledged where the proposal includes
the material items appearing only in the amendment. Kuhana-Spectrum
Joint Venture, LLC, B-400803, B-400803.2, Jan. 29, 2009,
2009 CPD ¶ 36 at 9-10.
Here, attachment E to amendment 2 imposed new legal
obligations on the contractor that were not contained in
the original solicitation or subsequent amendments.
Attachment E required the contractor to provide the
transition at no cost, a project manager in San Diego, and
an increased mileage reimbursement. Attachment E was
therefore a material amendment to the solicitation. See
RightStar Sys., B-407597, Jan. 16, 2013, 2013 CPD ¶ 35 at
5 (because vendors were required to price specific CLINs,
and those prices were to be evaluated for purposes of
determining the total evaluated price, the prices for
those CLINs were a material solicitation requirement).
When an offeror fails to acknowledge a material amendment,
the offeror’s proposal must be rejected. ECI Def. Group,
B-400177, B‑400177.2, July 25, 2008, 2008 CPD ¶ 141 at 4-5
n.7. In this case, the agency acted reasonably when it
rejected Nu-Way’s proposal because the offer separately
priced its transition CLIN, failed to add pricing for the
CLIN for a project manager for San Diego, and failed to
increase the mileage reimbursement rate for several CLINs.
See also RightStar Sys., supra (an agency may reject a
quotation that omits required pricing). (Nu-Way
Security and Investigative Services, Inc. B-414988.2:
Oct 20, 2017)
Finally, in addition to the matters discussed above, the
protester raised a number of issues for which the agency
requested dismissal, and we agreed with the agency. For
example, the protester argues that the agency’s extension
of the closing date for receipt of initial proposals was
improper because it occurred after the initial closing
date had passed. This assertion fails to state a valid
basis for protest because there is no prohibition against
a procuring agency issuing an amendment to extend the
closing time for receipt of proposals after that time has
passed to accommodate even one offeror, where the
motivation for the extension is enhanced competition. Geo-Seis
Helicopters, Inc., B-299175, B‑299175.2, Mar. 5, 2007,
2007 CPD ¶ 135 at 5. Similarly, the protester contends
that the Social Security Administration failed to follow
Congressional mandates regarding the award of this
contract. We find this argument legally and factually
unsupported. See 4 C.F.R. §§ 21.1(c)(4), 21.1(f). In any
event, this concern is untimely as it relates to the
stated evaluation scheme; protesters are required to raise
challenges to the terms of a solicitation prior to the
stated closing time for the receipt of proposals. 4 C.F.R.
§ 21.2(a)(1). (National
Disability Rights Network, Inc. B-413528: Nov 16,
2016)
The Competition in Contracting Act generally requires
“full and open competition” in government procurements as
obtained through the use of competitive procedures. 41
U.S.C. § 3301. Our Office generally will not review
modifications to contracts, because such matters are
related to contract administration and are beyond the
scope of GAO’s bid protest function. 4 C.F.R. § 21.5(a);
MCI Telecomms. Corp., B‑276659.2, Sept. 29, 1997, 97-2 CPD
¶ 90 at 7. However, the allegation that an agency awarded
a contract with the intent to modify the scope of work
concerns pre-contract award actions in violation of
Federal Acquisition Regulation (FAR) § 15.206(a), which
requires that the solicitation be amended, even after
receipt of proposals, to reflect the agency’s actual
requirements. The appropriate standard in reviewing these
pre-contract actions is not whether the subsequent
modification is within the scope of the original contract,
but whether the changed work could significantly affect
the competitive positions of offerors such that the RFP
should have been amended. NV Servs., B-284119.2, Feb. 25,
2000, 2000 CPD ¶ 64 at 23.
As noted above, the value of the contract has increased,
and that increase was driven by two significant changes in
requirements. First, modifications 3 and 10 changed
service levels from COL 4 to COL 3. AR, Exh. 3, Decl. of
Supervisory Contract Specialist at 2. Second, one of the
buildings under renovation at the time of contract
award--building 174--was returned to use; modification 2
added that building to the contract requirements. Id.
Together, those 3 modifications accounted for $1,821,538
of the $2,233,976.16 increase in contract value for the
base year.
With respect to the change in COL levels, the agency
explains that the level is dictated by the Commander,
Naval Installations Command, and not the specific
shipyard; therefore, the contracting activity had no prior
knowledge that the service level would definitively change
after award. AR at 8-9. Further, the RFP required offerors
to submit fixed prices on both COLs 3 and 4, stated that
the agency would evaluate the aggregate of the COLs 3 and
4 pricing, and reserved for the agency the right to award
at either COL. Id. at 8. In addition, the agency argues
that, based on the prices offered, even if the agency had
evaluated offerors only on COL 3 prices for the
fixed-price portion of the contract, Richen would still
have not been the lowest-priced offeror. See AR, Exh. 3,
Decl. of Supervisory Contract Specialist at 4. With
respect to the addition of the renovated building to the
contract, which also increased the value of the contract,
the agency explains that this and other changes are the
result of ongoing changes in government spaces that result
in both deletion of some services and addition of others.
AR at 7.
Here, the record shows that the solicitation adequately
advised offerors of the potential for the type of changes
that occurred during the course of contract performance
(e.g., change from COL 4 to COL 3), and that in the
context of the type of work at issue here, the
modifications encompass changes which the field of
competitors could reasonably have anticipated. The
protester fails to provide evidence to support its
assertion of any unfair dealing on the part of the agency.
Moreover, the protester asserts that, had it known that
the value of the contract would increase, Richen would
have lowered its rates and made a profit on the greater
volume of work to be performed. Response to Agency Request
for Dismissal, July 28, 2016, at 2. However, we generally
do not view as persuasive generalized arguments that a
protester’s price would have been more competitive under
an increased requirement as amended, NV Servs., supra,
and, absent some evidence in the record to indicate
otherwise, in a case such as this where the value of the
contract has increased, we may assume that the protester’s
price would increase proportionately to the other offerors’
prices. See Central Texas Coll. Sys., B-215172, Feb. 7,
1985, 85-1 CPD ¶ 153 at 6 (finding no evidence of
prejudice where contract increased in value by
approximately 67 percent through modifications, because
there was nothing in the record to suggest that offerors’
prices would have been disparately impacted). Therefore,
the record in this case provides no basis on which to
sustain this protest. NV Servs., supra. (Richen
Management, LLC B-409706.3: Oct 24, 2016)
As a general rule, an offeror's failure to acknowledge a
material amendment renders the proposal unacceptable and
such proposal may not form the basis for award. ECI Def.
Group, B-400177; B-400177.2, July 25, 2008, 2008 CPD ¶
141. While no precise rule exists as to whether a change
required by an amendment is more than negligible, such
that failure to acknowledge the amendment renders the
proposal unacceptable, an amendment is material where it
imposes legal obligations on a party that are different
from those contained in the original solicitation, or if
it would have more than a negligible impact on price,
quantity, quality, or delivery. Id.
To the extent that TTCC argues that some aspects of
amendment 3 (such as question 30) clarified the scope of
work in ways that reduced the contractor’s obligations, or
simply repeated them, we have held that failure to
acknowledge an amendment may be waived where the amendment
imposes insignificant obligations on the offeror, since
acceptance of an offer premised on the requirements in the
original solicitation would not prejudice any other
competitor. See DBI Waste Sys., Inc., B‑400687,
B-400687.2, Jan. 12, 2009, 2009 CPD ¶ 15 at 3-4 (agency
properly waived awardee’s failure to acknowledge amendment
that changed identification of item required by one
contract line where record showed no effective price
difference between the items). However, we need not
address these aspects of amendment 3 because we conclude
that the Air Force correctly concluded that the amendment
also made a material change to the scope of work: that the
10,500 linear feet of new fencing lacked a gravel
barrier/mowing strip.
TTCC does not meaningfully challenge the Air Force’s
explanation of the amount of additional effort needed to
perform the contract services along that fence line. We
have no basis to conclude that the need to supply
approximately 168 hours of additional effort each year
could be considered negligible or insignificant to the
offerors’ pricing. According, the Air Force’s decision to
reject TTCC’s proposal for failure to acknowledge
amendment 3 was reasonable.
The protest is denied. (TTCC,
Inc. B-412874: May 17, 2016) (pdf)
CGI contends that the agency’s price evaluation
methodology, which provided for comparing offerors’ prices
at the maximum order level of 15 units, did not match the
agency’s planned ordering needs as determined by the
agency prior to award. Given this disconnect, the
protester argues that the agency was required to amend the
solicitation’s evaluation scheme to provide a reasonable
basis for comparing offerors’ prices, one which matched
the agency’s ordering needs. CGI further maintains that if
the price analysis had been based on offerors’ NTE unit
prices for quantities of 5 per delivery order, which is
far more in line with the agency’s revised acquisition
strategy, its evaluated price would have been [deleted],
rather than highest, which would clearly have had an
impact on the best value tradeoff decision. The protester
supports its argument with computations, which do indeed
show that when offerors’ prices are evaluated using the
NTE prices for quantities of 5, as opposed to 15, per
delivery order, its total evaluated price is lower than
the total evaluated prices of several other offerors.
Protester’s Comments, Oct. 30, 2014, Encl. 2 and Exh. E.
We agree with the protester.
This case turns on two fundamental principles. One is
that, while it is up to the agency to decide on some
appropriate and reasonable method for evaluating offerors’
prices, an agency may not use an evaluation method that
produces a misleading result. Raymond Express Int’l,
B-409872.2, Nov. 6, 2014, 2014 CPD ¶ 317 at 6; Air Trak
Travel et al., B-292101 et al., June 30, 2003, 2003 CPD ¶
117 at 22. That is, the method chosen must include some
reasonable basis for evaluating or comparing the relative
costs of proposals, so as to establish whether one
offeror’s proposal would be more or less costly than
another’s. Id.
The other is that where an agency’s requirements
materially change after a solicitation has been issued, it
must issue an amendment to notify offerors of the changed
requirements and afford them an opportunity to respond.
Federal Acquisition Regulation (FAR) § 15.206(a);
Murray-Benjamin Elec. Co., L.P., B‑400255, Aug. 7, 2008,
2008 CPD ¶ 155 at 3-4. For example, where an agency’s
estimate for the amount of work to be ordered under an
ID/IQ contract changes significantly, prior to award, the
agency must amend the solicitation and provide offerors an
opportunity to submit revised proposals. See Symetrics
Indus., Inc., B‑274246.3 et al., Aug. 20, 1997, 97-2 CPD ¶
59 at 6. In Symetrics, our Office concluded that the
agency should have amended a solicitation for an ID/IQ
contract because although the solicitation initially
estimated the agency would require 3,755 sequencers, the
agency subsequently learned--prior to award--that the
agency no longer had a requirement for 3,219 of the
sequencers. Id. Similarly, in Northrop Grumman Info.
Tech., Inc., et al., B-295526 et al., Mar. 16, 2005, 2005
CPD ¶ 45 at 13, our Office sustained a protest where the
Department of the Treasury, prior to award, negotiated a
memorandum of understanding with OMB and the General
Services Administration that significantly changed the
approach set forth in the solicitation and the FAR for
determining whether to exercise contract options, making
it significantly less likely that the options, which were
part of the evaluation, would be exercised.
The circumstances here are unusual in that the
meaningfulness of the price evaluation scheme set forth in
the RFP changed between the closing date for receipt of
FPRs and the date of award. That is, the record reflects
that it made perfect sense to evaluate on the basis of
15/each unit pricing when the agency intended to award
three contracts and issue 3-4 delivery orders per year.
Given the agency’s projection that it would acquire
approximately 45-60 units annually in FYs 2014-2017, each
order would necessarily need to be placed at the 15/each
unit level based on the intended number of orders issued.
Evaluating on the basis of 15/each unit pricing no longer
provided a rational basis for comparison, however, when,
during the source selection process, the agency decided to
increase the number of awardees to five, and to alter its
ordering strategy to significantly increase the number of
delivery orders annually, thereby decreasing the number of
units to be acquired per delivery order. Given this
fundamental shift in the agency’s anticipated ordering
plans, it was unreasonable for the agency to proceed with
a price evaluation methodology that was divorced from
these plans. Rather, the appropriate course of action was
for the agency to amend the solicitation in a manner that
would enable it to evaluate, and make a tradeoff decision
based on, the offerors’ relative relevant prices.
The agency defends its actions on the basis that it
followed the terms of the solicitation and that all
offerors competed on an equal basis because the
solicitation did not establish that the agency would, in
fact, place orders at the 15/unit level. Regarding the
latter point, the agency notes that offerors were to
submit prices at each level and should have understood
that orders could be placed at any of the 15 price levels.
The agency’s arguments, however, miss the point. We agree
that the agency followed the terms of the solicitation,
and that the offerors submitted prices on an equal basis.
The problem is that the price evaluation, and resulting
selection decision under which CGI did not receive an
award due to its high price, were based on comparing
prices for quantities of units that the agency now knows
it does not intend to order. We recognize that price
evaluation in the context of an ID/IQ contract may be
representative, and therefore something of a fiction;
nevertheless, the fiction employed must bear some rational
relationship to the agency’s needs. See CW Govt Travel,
Inc.--Recon.; CW Gov’t Travel, Inc., et al., B-295330.2 et
al., July 25, 2005, 2005 CPD ¶ 139 at 4-5. Where the
agency’s intended ordering strategy does not anticipate
placing orders at the 15 unit per order level, we fail to
see how comparing prices at this level, and using such
prices as the basis for a tradeoff decision, can be
understood to be reasonable. As explained above, where the
disconnect between the terms of the solicitation and the
agency’s order needs became apparent prior to award, it
was incumbent on the agency to instead amend the
solicitation to correct the flaw in the solicitation.
(CGI Federal Inc.,
B-410330.2: Dec 10, 2014) (pdf)
With respect to Platinum’s second argument, the Federal
Acquisition Regulation does not prohibit auctions, and
agencies are not otherwise prohibited from taking
corrective action in the form of requesting revised price
proposals, even where the original awardee’s price has
been disclosed. Jackson Contractor Group, Inc.,
B-402348.2, May 10, 2010, 2010 CPD ¶ 154 at 3. Here,
Platinum’s total evaluated price[4] was released in
connection with the original award, while WIT’s total
evaluated price was released in connection with the
subsequent award to it (that is, after an earlier round of
corrective action). Nevertheless, as discussed above, the
Navy has now concluded that the solicitation established
an unjustified (and possibly ambiguous), experience
standard, which has thereby impaired competition.
Deletion of that requirement is within the agency’s
discretion to take corrective action. It is a reasonable
means to remedy a greater harm to the integrity of the
competitive procurement system--especially since only two
proposals have been received--than the risk that the
disclosure of the award prices for both offerors might
place either at a greater disadvantage in the reopened
competition than the other firm. See id. In our view,
since the agency has changed the evaluation criteria upon
which it will make award, it has also properly informed
the offerors of that change and requested final proposal
revisions. In short, none of Platinum’s arguments
demonstrate a valid basis of protest.
WIT’s protest argues that by deleting the corporate
experience factor from the evaluation criteria, the Navy
will fail to obtain a satisfactory contractor. WIT
Opposition to Dismissal at 15-16; WIT Comments at 5. The
Navy responds that it has amended the RFP because the
Navy’s needs do not include requiring the contractor to
have a minimum level of specific corporate experience,
particularly because the agency will also be considering
key personnel experience. WIT Dismissal Request at 7; WIT
Agency Report (AR) at 8.
Generally, our Office will not consider contentions that
specifications should be made more restrictive because our
role in reviewing bid protests is to ensure that the
statutory requirements for full and open competition are
met, not to protect any interest a protester may have in
limiting competition through more restrictive
specifications. Simplix, B-274388, Dec. 6, 1996, 96-2 CPD
¶ 216 at 5-6. WIT’s protest does not include sufficient
information to establish the likelihood that the agency in
this case violated applicable procurement laws or
regulations.
Nevertheless, WIT argues that since our Office has
recognized that agencies have a legitimate interest in
assessing the experience and past performance of
prospective contractors, the Navy must impose the
corporate experience subfactor in order to obtain
minimally acceptable services. WIT Protest at 10-11. The
Navy responds that it made a reasonable determination that
corporate experience performing these same services in a
remote location is not required for the Navy to obtain a
contractor to perform the commercial services at issue
here. WIT AR at 8. Further, the Navy argues, such a
requirement would overly restrict the already-limited
competition. Id. at 10.
An agency has the discretion to determine its needs and
the best way to meet them. USA Fabrics, Inc., B-295737;
B-295737.2, Apr. 19, 2005, 2005 CPD ¶ 82 at 4. This
includes broad discretion in the selection of the
evaluation criteria that will be used in an acquisition,
and so, our Office will not object to the absence or
presence of a particular evaluation criterion (or even the
deletion of one), so long as the criteria used reasonably
relate to the agency's needs in choosing a contractor that
will best serve the government's interests. King Constr.
Co., B-298276, July 17, 2006, 2006 CPD ¶ 110 at 3. Here,
the Navy has provided a reasonable basis for its decision
to delete the corporate experience subfactor and WIT has
given us no reason to question the Navy’s actions. (Platinum
Services, Inc.; WIT Associates, Inc., B-409288.3,
B-409288.4, B-409288.5: Aug 21, 2014) (pdf)
S3 argues that the Army altered its requirements after making
award of the contract to M1. S3 asserts that the change to the
agency’s requirements is substantial, and that it would have
altered its proposed staffing had it known about the agency’s
revised requirements. S3 therefore contends that it was
prejudiced by the agency’s failure to solicit its revised,
actual, requirements once it became aware of those requirements.
The agency responds that the source selection
authority/contracting officer (SSA) was unaware of the change to
the agency’s requirements at the time she made her source
selection and did not learn of the change until several days
later. The agency therefore takes the position that it did not
make award with a view to substantially altering the contract
after award. See Business Computer Applications, Inc.,
B-406230.3, May 16, 2012, 2012 CPD ¶ 159 at 3 n.2 (agency may
not properly award a contract with the intent to materially
alter it after award). In the alternative, the agency argues
that, because this is a requirements contract, there was no
obligation on the part of the government to order the estimated
quantities included in the RFP. The agency therefore reasons
that any reduction in its actual requirement--as compared to the
RFP’s estimates--was contemplated by the type of contract
solicited.
As a general rule, agencies may not properly award a contract on
a basis that is fundamentally different from the basis upon
which the competition for the requirement was conducted. United
Telephone Co. of the Northwest, B-246977, Apr. 20, 1992, 92-1
CPD ¶ 374 at 7-10, aff’d. Dept. of Energy--Recon.; Westinghouse
Hanford Co.—Recon.; United Telephone Co. of the Northwest,
B‑246977.2, et al. July 14, 1992, 92-2 CPD ¶ 20. Where, for
example, there is a significant change in the government’s
quantity requirements, the appropriate course of action is for
the agency to apprise the offerors of its revised requirements,
and afford them an opportunity to submit proposals responsive to
those revised requirements, even where, as here, a source
selection decision has been made. Id.
In addition, the fact that a requirements-type contract is being
used does not relieve the agency of its fundamental obligation
to conduct a competition on the basis of the most accurate or
realistic estimates of the total quantity of goods or services
likely to be ordered. Federal Acquisition Regulation (FAR) §
16.503(a)(1); Hoechst Marion Roussel, Inc., B-279073, May 4,
1998, 98-1 CPD ¶ 127 at 3. This is because, without such
realistic estimated quantities, firms cannot prepare offers that
reflect the agency’s actual, anticipated needs, and
correspondingly, the agency cannot reasonably determine whether
award to one firm versus another will result in the lowest
possible cost to the government. Hoechst Marion Roussel, Inc.,
supra.
Here, the agency has determined that its actual requirements are
significantly different from the requirements that it solicited,
and for which the offerors competed. The record shows that
agency’s original requirements, and its revised requirements,
are as follows:
Airframe |
Original Number of Students |
Original Number of Instructors |
Revised
Number of Students |
Revised
Number of Instructors |
UH-60
(Instructor Pilots) |
72 |
36 |
0 |
0 |
UH-60 A/L
(Maintenance Examiners) |
8 |
4 |
8 |
4 |
UH-60M
(Maintenance Examiners) |
4 |
2 |
4 |
2 |
AH-64D
Instructor Pilots) |
32 |
16 |
22 |
11 |
AH-64D
(Maintenance Examiners) |
4 |
2 |
0 |
0 |
OH-58D
(Instructor Pilots) |
6 |
3 |
0 |
0 |
CH-47F
(Maintenance Examiners) |
0 |
0 |
2 |
1 |
Total |
126 |
63 |
36 |
18 |
RFP at 51; AR, exh. 31, Memorandum from the Commanding Officer
to the Installation Contracting Command.
This change represents a reduction in the agency’s overall
anticipated requirements of more than 70 percent. It also
reflects a significant change in the types of instructors and
maintenance examiners required; of the originally-solicited six
categories of instructors/examiners, the agency has eliminated
three--or half--of all categories, and also has added a new
category not contemplated under the original solicitation. The
record therefore shows that the agency’s current requirements
bear little relationship to the requirements that it solicited,
and for which the offerors competed. It follows that the agency
can have no reasonable assurance, based on the earlier
competition, that award to M1 versus S3 is proper.
In responding to the protest, the Army essentially relies on the
temporal lack of knowledge on the part of its SSA concerning the
agency’s revised requirements. However, the agency’s reliance is
misplaced, since the record shows that the organization as a
whole--and more particularly, the agency’s cognizant commanding
officer--had to have been aware of the Army’s changed
requirements prior to the agency’s revised source selection
decision.
We recognize--and the record reflects--that the SSA was
contemporaneously unaware of the change to the agency’s
requirements at the time she made the agency’s revised source
selection decision. Contracting Officer’s Statement at 11-12;
AR, exh. 33, E-mail to the Contracting Officer, Jan. 31, 2014.
Nonetheless, the record compels the conclusion that the
commanding officer was aware of the change to the agency’s
requirements. As noted, the record includes his instruction to
partially terminate the protester’s predecessor contract, which
was executed on January 27, the same date on which the revised
source selection decision was made. AR, exh. 30. As a practical
matter, however, the agency’s commanding officer likely was
aware that the agency would have a substantially reduced
requirement for contractor-furnished flight instructors and
examiners well before he issued his instruction to partially
terminate S3’s predecessor contract.
As reflected in the change to the agency’s needs, the Army
reduced its requirement by a total of 45 instructors/examiners.
The record shows that these are highly skilled positions. For
example, the RFP requires all of the instructor pilots to be
qualified as instructor pilots for one or more of the airframes
identified in the RFP; have a minimum of five years experience
as an aviator on one or another of the specified airframes; and
to have had their last flight within 24 months of being offered
as a qualified instructor. RFP at 43. The maintenance examiner
qualifications are even more stringent. For example, a
maintenance examiner for an AH-64D helicopter (one of the
maintenance examiner categories now being provided by in-house
personnel) is required to have at least five years of experience
as an aviator; to have had his or her last flight within 12
months of being offered as a qualified examiner; and to have
logged at least 2,000 flight hours, 250 hours as a maintenance
test pilot, and 200 hours as a maintenance examiner. Id.
It simply is not reasonable to suggest that 45 in-house
Department of Defense personnel meeting these stringent
qualifications simply materialized at the agency’s facility
ready and available to go to work on the same day the commanding
officer issued his instruction to partially terminate S3’s
predecessor contract. Under the circumstances, the fact that the
SSA was unaware of the agency’s changed requirements does not
provide a reasonable basis to conclude that the organization was
unaware of its changed requirements. It follows that the agency
was required to revise its solicited requirements and afford the
offerors an opportunity to submit proposals responsive to the
agency’s actual requirements.
The agency also asserts, based on calculations it has performed,
that S3 was not prejudiced by the agency’s failure to solicit
its revised requirements because its price still would not have
been low. The agency’s calculations are based on hourly rates
proposed by the offerors in response to the earlier requirement.
The protester maintains, however, that it would have changed its
proposed staffing profile, as well as proposed personnel had it
known of the agency’s actual requirements. For example, S3
represents that it would have offered [deleted]. Letter of
Protest, Jan. 31, 2014, at 25.
The agency’s calculations provide no basis for our Office to
conclude that the protester was not prejudiced. As correctly
noted by the protester, those calculations are based on
personnel that the offerors may, or may not, have proposed had
the agency advised them of its actual requirements. In addition,
the agency’s revised requirements include one category of
personnel not contemplated by the original solicitation (the
revised requirements include maintenance examiners for the
CH-47F airframe, a category of maintenance examiners not
included under the original RFP, and one which the protester
asserts is particularly difficult to fulfill). Accordingly,
there is no basis for our Office to conclude that the protester
was not prejudiced by the agency’s failure to apprise the
competitors of its actual requirements. Piquette & Howard Elec.
Serv., Inc., B-408435.3, Dec. 16, 2013, 2014 CPD ¶ 8 at 9
(protest sustained where record showed reasonable possibility of
prejudice to protester).
In sum, we conclude that the agency made award of the contract
to M1 based on what ultimately was a significantly different
requirement than the requirement the agency actually solicited.
This was improper because the offerors were not afforded an
opportunity to compete for the agency’s actual requirements, and
there is no basis on the record before us to conclude how the
competition would have ended had the offerors been aware of the
agency’s actual requirements. We therefore sustain S3’s protest
on this basis. (System Studies
& Simulation, Inc., B-409375.2, B-409375.3: May 12, 2014)
(pdf)
It is a fundamental principle of government procurement that
competition must be conducted on an equal basis; that is,
offerors must be treated equally and provided with a common
basis for the preparation of their proposals. Systems Mgmt.,
Inc.; Qualimetrics, Inc., B-287032.3, B-287032.4, Apr. 16, 2001,
2001 CPD ¶ 85 at 8. When, either before or after receipt of
proposals, the government changes or relaxes its requirements,
it must issue an amendment to notify all offerors of the changed
requirements and give them an opportunity to respond. Diebold,
Inc., B-404823, June 2, 2011, 2011 CPD ¶ 117 at 4; Systems
Mgmt., Inc.; Qualimetrics, Inc., supra; see Cardkey Sys.,
B-220660, Feb. 11, 1986, 86-1 CPD ¶ 154 at 2 (If it becomes
apparent that the contract being negotiated differs
significantly from the requirements stated in the RFP, the
contracting agency must amend the RFP or, at the least, advise
offerors of the change during discussions and seek new offers.)
We will sustain a protest where an agency, without issuing a
written amendment, materially alters the solicitation’s
requirements to the protester’s prejudice. See Systems Mgmt.,
Inc.; Qualimetrics, Inc., supra.
Here, the record indicates that the modification of the RFP
clause to the negotiated language materially reduced Amazon’s
obligations from those imposed in the RFP. In this regard, the
RFP clause required the offeror to certify its undertaking to
ensure that “any software” provided will be virus free, while
the modified language covered “only software developed and
provided” by Amazon. This is significant because Amazon’s
proposal contemplated the provision of third party and
open-source software that is not developed by Amazon and thus
would not fall within its modified certification. See, e.g.,
Amazon Proposal at 1-4,1-9 (“rich ecosystem of . . . third-party
security tools”), and at 1-13, 1-23, 1-26, 2-38 (proposed use of
“MySQL” and “Red Hat Enterprise Linux,” an open-source database
and software product, respectively).
During the hearing before our Office, the agency admitted that,
at the time of the post-selection negotiations, it did not
consider the impact of the modified language; it understood that
Amazon was certifying all software and did not realize that the
change might be a restriction on the certification. Tr. at
486-88. Indeed, the contracting officer testified that had the
agency focused more closely on the modification, it would have
taken exception to the revision. Tr. at 502-03. Thus, the
hearing testimony suggested that the new language represented a
material change to the terms of the underlying competition.
Both at the hearing and in briefs filed after the hearing,
however, the agency asserts that this change was not significant
because Amazon is still required to comply with other provisions
of its contract. For example, the agency points out that SRD §
3.13.2 required C2S infrastructure and services to be “assessed
and authorized in accordance with Intelligence Community
Directive (ICD) 503 (reference 3),” which provides for the
agency to incorporate standards, policies, and guidelines issued
by the National Institute of Standards and Technology and the
Committee on National Security Systems (CNSS). Agency Post
Hearing Comments at 20. One aspect of these standards includes
“malicious code protection,” and Amazon’s detailed proposal to
meet these requirements was incorporated into the contract. Tr.
at 470-72; Amazon System Security Plan, Appendix B-91--B-93.
We see no basis in the contemporaneous
record to support a conclusion that the agency made its decision
to allow the modification based on these other provisions of the
solicitation, or on Amazon’s agreement to them. In this
regard, while we consider the entire record in resolving a
protest, including statements and arguments in response to a
protest, in determining whether an agency’s selection decision
is supportable, we accord greater weight to contemporaneous
evaluation and source selection materials than to new judgments
made in response to protest contentions. Boeing Sikorsky
Aircraft Support, B-277263.2, B-277263.3, Sept. 29, 1997, 97-2 CPD ¶ 91 at 15. We accord lesser weight to post hoc arguments or
analyses because we are concerned that judgments made in the
heat of an adversarial process may not represent the fair and
considered judgment of the agency, which is a prerequisite of a
rational evaluation and source selection process. Id. Here,
given the contracting officer’s testimony that, had the agency
focused on the modification requested by Amazon, it would have
taken exception, we find no basis for accepting the agency’s
current assertion that the modification was not material.
In any case, the agency’s current position does not show that
the modification was not material. In this regard, the agency
now contends that the only aspects not covered by Amazon’s
agreement to the certification requirements were (1) the
certification itself, which the agency believes would be
satisfied by Amazon signing its contract; and (2) the
requirement to immediately notify the contracting officer of an
issue with malicious code. Agency Post Hearing Comments at 20.
However, regardless of the agency’s position with respect to the
certification, it is unclear why elimination of Amazon’s
obligation to immediately notify the contracting officer about
malicious code would not represent a change in a material
requirement.
In sum, we find that the agency, without issuing a written
amendment, materially relaxed the solicitation’s requirements
for Amazon without affording the other offerors an opportunity
to propose to the modified requirements. Accordingly, the
protest is sustained on this basis as well.
(IBM-U.S.
Federal, B-407073.3, B-407073.4, B-407073.5, B-407073.6, Jun
6, 2013) (pdf)
Infoshred contends that Amendment 1 is not material because all
of the requirements imposed by Amendment 1 were encompassed or
superseded by Amendment 2, which the firm acknowledged. Comments
at 2. Infoshred further argues that, although it did not
acknowledge Amendment 1, the firm’s quotation nevertheless
committed to comply with the requirements announced in Amendment
1--specifically, the requirement for off-site shredding. Protest
at 4.
Generally, a quotation may be rejected for failure to
acknowledge a material amendment. In determining whether an
amendment is material, we look at the facts of each case. While
no precise rule exists as to whether a change required by an
amendment is more than negligible, an amendment is material
where it imposes legal obligations on the contractor that were
not contained in the original solicitation or subsequent
amendments acknowledged by the offeror. See MG Mako, Inc.,
B-404758, April 28, 2011, 2011 CPD ¶ 88 at 2; Skyline ULTD,
Inc., B-297800.3, Aug. 22, 2006, 2006 CPD ¶ 128 at 3; Navistar
Marine Instrument Corp., B-277143.2, Feb. 13, 1998, 98-1 CPD ¶
53 at 2. We have also held that an amendment may be
constructively acknowledged where the proposal includes the
material items appearing only in the amendment. Kuhana-Spectrum
Joint Venture, LLC, B-400803, B-400803.2, Jan. 29, 2009, 2009
CPD ¶ 36 at 9-10. Further, where a solicitation states that a
quotation may be excluded from consideration for failing to meet
a requirement, as is the case here, offerors are reasonably put
on notice that rejection will not be automatic but instead will
occur only if there is a reasonable basis for such action. See
Macfadden & Assoc. Inc., B-275502, Feb. 27, 1997, 97-1 CPD ¶ 88
at 2-3.
When asked by GAO to identify obligations imposed by Amendment 1
that were not also imposed by Amendment 2, the agency initially
stated that because the protester did not acknowledge Amendment
1, “Infoshred is not bound to perform off-site shredding.” VA
Response to GAO’s Questions, Oct. 1, 2012, at 1. Further, the VA
characterized Amendment 2 as non-substantive. Id. However, in
response to further questions from GAO, the VA acknowledged that
Amendment 2 contained a revised statement of work and also
addressed the requirement for off-site shredding. VA Response to
GAO’s Questions, Oct. 4, 2012. As noted above, Amendment 2
stated that it was “replacing” Amendment 1’s BPA and statement
of work. RFQ amend. 2 at 109.
Here, we find that in light of Amendment 2, which was
acknowledged by Infoshred, Amendment 1 was immaterial. Amendment
2 contained each of the substantive requirements that were
contained in Amendment 1 and included a revised performance work
statement that superseded the one attached to Amendment 1.
Although Amendment 1 imposed legal obligations on the contractor
that were not contained in the original solicitation--that is,
the requirement for off-site shredding--Amendment 2, which
Infoshred acknowldeged, also contained these requirements and
provided even more detail regarding the requirements. Therefore,
the agency’s rejection of the protester’s quote for failure to
acknowledge Amendment 1 was unreasonable. (Infoshred
LLC, B-407086, Oct 26, 2012) (pdf)
MG Mako contends that amendment 2 is not material because it
merely clarified existing contract performance requirements and
thus did not affect the legal relationship of the parties. The
protester also states that it was the firm's intention to
acknowledge amendment 2 and that it "always understood the fact
that there were two amendments to the solicitation." Protester's
Response to Dismissal Request at 1. However, the protester
states that it inadvertently submitted the incorrect version of
a form, which failed to acknowledge amendment 2. Id.
In determining whether an amendment is material, we look at the
facts of each case. While no precise rule exists as to whether a
change required by an amendment is more than negligible, such
that the failure to acknowledge the amendment renders the
proposal unacceptable, an amendment is material where it imposes
legal obligations on the contractor that were not contained in
the original solicitation. Skyline ULTD, Inc., B-297800.3, Aug.
22, 2006, 2006 CPD para. 128 at 3; Navistar Marine Instrument
Corp., B-277143.2, Feb. 13, 1998, 98-1 CPD para. 53 at 2.
The agency explains, and we agree, that given the complexity of
the electrical work involved in this procurement, the effort to
plan for electrical outages can be complex and convoluted. Thus,
unless the RFP imposed a requirement to coordinate outages with
the local utility, the contractor and the local utility could
schedule their outages independently of each other to maximize
the efficiency of each one's work, which would not minimize the
outages. Fax Confirmation of GAO Conference Call with the
Parties at 1. The requirement added in paragraph A27 of
amendment 2, requiring that the contractor coordinate with the
local utility, recognizes that the project will necessarily
involve some outages by the local utility and some outages by
the contractor. In essence, this provision requires that the
contractor work with the utility company to make those outages
minimal, for example, by rescheduling its outage work to occur
during an outage by the local utility, or requesting the local
utility to reschedule an outage to a time that best suits the
contractor.
Although the protester points to a number of other solicitation
provisions that reference coordination with various entities
prior to or during electrical work, none of these provisions
required that the contractor coordinate with the utility company
to minimize outages. See Protester's Response to GAO's
Questions, March 9, 2011, at 1‑2.
In light of the amendment's addition of contractor obligations
to coordinate with the utility company to minimize electrical
outages, we conclude that the amendment affects the legal
relationship of the parties and therefore is material.
Consequently, the protester's failure to acknowledge it cannot,
as the protester requests, be waived as a minor informality.
Accordingly, we see no basis to object to the agency's rejection
of the proposal for failure to acknowledge amendment 2. (MG
Mako, Inc., B-404758, April 28, 2011) (pdf)
On June 23, the apparent awardee was announced and the offerors
were informed by the agency that any challenges concerning the
small business size status of the apparent awardee must be filed
by June 30. Two offerors, including Ocean, timely challenged the
size status of the apparent awardee. On August 2, the agency
requested that Ocean and the other offerors extend the
acceptance period of their proposals. Agency Report (AR) at 3.
On that same date, Ocean extended the acceptance period of its
proposal to September 30. Id. On September 17, the Small
Business Administration determined that the apparent awardee was
other than small for purposes of this procurement. Id. On
September 24, the agency again requested that Ocean and the
other offerors extend the acceptance period of their proposals
through November 14, and on that same date Ocean again provided
the requested extension. Id. On September 30, the agency
extended the incumbent's contract until February 12, 2011. Id.
On November 8, 2010, the agency again requested the offerors to
extend the acceptance period of their proposals through
Saturday, December 18, and, on that same date the offerors,
including Ocean, provided the requested extension. Id.
On December 10, the agency issued a market survey for the
operation and maintenance of the OSV BOLD. The responses to the
market survey were due on December 20. On Monday, December 13,
the agency again requested the offerors, including Ocean, to
extend the acceptance period of their proposals through February
12, 2011. AR, exh. 3, Email from MSC to Offerors. On that same
date, Ocean sent the following question to the agency:
Can you give us an explanation what the
extension is for? It appears that you are also going out to
the market looking to re-compete this vessel management
contract [without] a small business component? We have put
considerable effort into this proposal as well as the
components of small business vs. large business and
respectfully request some clarification.
AR at 4. On Friday, December 17, Ocean
received the following email from the agency:
This is just a reminder that your offer on
the subject RFP is valid through 18 December 2010. If you wish
to extend your offer please do so by email, stating the exact
date in your email.
Id. On the following Monday, December 20,
Ocean responded to the market survey, and at 10:34 a.m. that
same day, Ocean extended its proposal through February 28, 2011.
AR, exh. 5, Ocean Email Extending Offer. The other offerors
extended their proposals prior to December 18, 2010. AR, exhs. 4
and 5, Emails dated December 13 and 14, 2010, from Offerors
Extending Offers. On December 20, the agency sent the following
email to Ocean:
I received notice of your proposal
extension today. Your proposal was only valid through 18
December 2010. Your offer to extend your proposal was received
on 20 December 2010 and is considered late. Your proposal will
no longer be considered for award.
AR at 5. This protest to our Office
followed.
The record establishes that Ocean's proposal expired because it
did not extend the acceptance period of its proposal by December
18. See Trojan Indus. Inc., B‑220620, Feb. 10, 1986, 86-1 CPD
para. 143 at 5. Nevertheless, Ocean contends that the agency
should allow it to revive its offer because this would neither
prejudice the other offerors nor compromise the integrity of the
competitive process. Protester's Comments at 4.
Where a proposal or bid has expired, we have recognized that an
offeror or bidder may extend its acceptance period and revive
its proposal or bid if doing so would not compromise the
integrity of the competitive bidding system. Id. Circumstances
that compromise the system's integrity are where the bidder
offered an acceptance period shorter than other bidders (if the
solicitation afforded bidders or offerors the option to offer
less than a standard time frame that otherwise would be presumed
to apply), or where the bidder expressly or impliedly refused a
request to extend its bid and later granted an extension as its
own interests dictated; a bidder's or offeror's limitation of
the government's legal ability to accept the bid or proposal in
a manner at variance with the terms offered by other competitors
limits the bidder's or offeror's exposure to marketplace
uncertainties and reduces that bidder's risk. Id.; Camden
Shipping Corp. v. United States, 89 Fed.Cl. 433 (2009).
In this case, Ocean did not decline to extend the acceptance
period for its proposal, which expired on a Saturday, but
extended it on the following Monday morning. We have recognized
in such circumstances that even where other bidders or offerors
had extended their proposals as required, there is no prejudice
to the other bidders or offerors, or to the competitive system,
by allowing the expired bid or proposal to be revived. Trojan
Indus. Inc., supra, at 5-6 (bid which expired on Saturday
revived by bidder's extension of bid period on the following
Monday). Reviving the proposal on the morning of the first
business day following its expiration negates any argument that
Ocean compromised the procurement process by avoiding market
fluctuations to which other offerors were exposed.[2] See id.;
compare Discount Mach. & Equip,, Inc., B‑244392, Oct. 15, 1991,
91-2 CPD para. 334 at 4 (prejudice found and bid revival not
permitted, where the bidder attempted to extend its bid more
than a month after the expiration of the original bid acceptance
period, where the other bidders had timely extended their bids);
MKB Mfg. Corp., B‑208451, Mar. 1, 1983, 83-1 CPD para. 204
(same, where bidder attempted to extend bid 15 days after the
expiration of bid acceptance period).
We recommend that the MSC accept the revival of Ocean's
proposal. We further recommend that the agency reimburse the
protester the costs of filing and pursuing its protest,
including reasonable attorney's fees. 4 C.F.R. sect. 21.8(d)(1)
(2010). The protester's certified claim for costs, detailing the
time spent and the cost incurred, must be filed to the agency
within 60 days after receiving this decision.
The protest is sustained. (Ocean
Services, LLC, B-404690, April 6, 2011) (pdf)
GCE argues that DHS's award to CACI was improper because the
agency knew, prior to award, that its intended approach to the
TASC migration would depart from the assumptions set forth in
the solicitation upon which offerors were required to submit
their proposals. In this regard, GCE argues that the agency's
announced approach for the FEMA migration departs from the
solicitation's assumption that 20 percent of all DHS end-users
would be migrated by the end of the second year of the contract.
Moreover, GCE argues that the agency's approach to the FEMA
migration was inconsistent with the RFP, which contemplated
multiple, simultaneous migrations of DHS component agencies to
TASC.
Where an agency's requirements materially change after a
solicitation has been issued, it must issue an amendment to
notify offerors of the changed requirements and afford them an
opportunity to respond. Federal Acquisition Regulation (FAR)
sect. 15.206(a); Murray-Benjamin Elec. Co., L.P., B-400255, Aug.
7, 2008, 2008 CPD para. 155 at 3-4. Amending the solicitation
provides offerors an opportunity to submit revised proposals on
a common basis that reflects the agency's actual needs. Multimax,
Inc., et al., B-298249.6 et al., Oct. 24, 2006, 2006 CPD para.
165 at 6. Where an agency's estimates for the amount of work to
be ordered under an ID/IQ contract changes significantly, prior
to award, the agency must amend the solicitation and provide
offerors an opportunity to submit revised proposals. Symetrics
Indus., Inc., B‑274246, Aug. 20, 1997, 97-2 CPD para. 59 at 6.
For example, in Symetrics, our Office concluded that the agency
should have amended a solicitation for an ID/IQ contract because
although the solicitation initially estimated the agency would
require 3,755 sequencers, the agency subsequently learned--prior
to award--that the agency no longer had a requirement for 3,219
of the sequencers. Id. Similarly, in Northrop Grumman Info.
Tech., Inc., et al., B-295526 et al., Mar. 16, 2005, 2005 CPD
para. 45 at 13, our Office sustained a protest where the
Department of the Treasury, prior to award, negotiated a
memorandum of understanding with OMB and the General Services
Administration that significantly changed the approach set forth
in the solicitation and the FAR for determining whether to
exercise contract options, making it significantly less likely
that the options, which were part of the evaluation, would be
exercised.
As discussed above, the RFP stated that offerors were required
to propose an integrated financial management, asset management
and acquisition management solution for all DHS component
agencies, and also propose for the transition of those component
agencies to the new solution. RFP attach. J-1, SOO at 1-2;
attach. J-2, TASC Solutions Process Overview, at 5-7. Section L
of the RFP required offerors to base their price proposals on
the assumptions set forth in the implementation plan in RFP
section L, i.e., 20 percent of end-users must be migrated by the
end of base year 2, with an additional 20 percent each year
through the end of option year 1. RFP sect. L.7.2, Tab C.
DHS received and evaluated offerors' proposals, and selected
CACI for award on June 22, 2010. AR, Tab 31, SSD, at 1.
Subsequent to this decision, however, OMB issued guidance that
required agencies to halt ongoing financial services
procurements, and obtain OMB's approval to proceed with those
projects. See AR, Tab 44, OMB Memorandum Re: Immediate Review of
Financial Systems IT Projects (June 28, 2010), at 1. In
accordance with OMB's guidance, DHS selected FEMA to be the
first component agency to be migrated to TASC, with the
understanding that the task order would take 24 months to
complete and that no other DHS agency would be migrated until
FEMA's migration was complete.[8] AR, Tab 53, TASC ESC Minutes
(July 28, 2010), at 3; AR, Tab 62, TASC ESC Minutes (Nov. 18,
2010), Notional Milestone Schedule. Only then did DHS proceed to
award.
GCE argues that DHS's decision to only migrate FEMA--which
represents between 1.5 percent and 2.9 percent of DHS's
end-users--during the first 2 years of contract performance is a
material change to the RFP's assumption that 20 percent of DHS's
end-users should be migrated during that period of time. GCE
contends that the agency required offerors to base their
proposals on the assumptions in RFP section L, but knew, prior
to award, that it would not issue task orders in a manner
consistent with those assumptions.
We agree with GCE that the reduced anticipated scope of work for
the first 2 years of contract performance occasioned by only
migrating FEMA during that period represents a material
departure from the assumptions set forth in the solicitation. In
this regard, the agency acknowledges that the FEMA task order
will require migrating end-users who represent between 1.5
percent and 2.9 percent of all DHS end-users. Agency Response to
GAO Questions (Feb. 14, 2011), at 1-2. Further, the agency
acknowledges that if FEMA is the only agency component migrated
during that period, the 20 percent assumption set forth in the
solicitation would not be met. Id.
DHS argues, however, that the assumptions set forth in section L
should not have been understood by offerors to reflect the
agency's actual requirements for the migration of component
agencies. We disagree. The RFP required offerors to base their
proposals on the assumptions set forth in the implementation
plan in RFP section L, i.e., that 20 percent of end‑users must
be migrated by the end of the second base year, with an
additional 20 percent each year through the end of the first
option year. Offerors were required to use those assumptions in
preparing their BOEs, which were required to "identify the
solution price's limitations and assumptions." RFP sect. L.7.2,
Tab C. The RFP further instructed that the "Solution Price and
BOE shall be consistent with the offeror's proposed [performance
work statement], [contract work breakdown structure] and data
migration plan, and should include labor categories and hours by
[work breakdown structure] element, for the base period and all
option periods." Id.
In support of its position, DHS references language contained in
the RFP pricing templates, which stated that "the assumed
implementation schedule . . . was constructed to provide a
standard for comparison purposes only." RFP attach. J-5, Pricing
Templates-Contract Lifecycle Cost Summary Tab. Similarly, the
agency notes that Q&A No. 89 stated that "[t]he assumptions in
the implementation schedule provide a standard for proposal
evaluation purposes only." RFP amend. 2, Q&A No. 89. The agency
also references a statement contained in both Attachment J-5 and
Q&A No. 89 that the "assumed implementation schedule . . . does
not represent any preference on the part of the government for a
particular implementation schedule." The agency contends that
because the solicitation did not commit the agency to any
particular migration schedule, the approach of migrating only
FEMA and no other DHS agency during the first 2 years of the
contract does not represent a departure from the terms of the
RFP. See AR at 9, 11, 18.
This argument has no merit. While the agency focuses on the
"comparison purposes only" language in Attachment J-5, the
agency also confirmed in this Q&A that "RFP Section L.7.2 – Tab
C provides assumptions for an implementation schedule offerors
must use in proposal preparation." RFP amend. 2, Q&A No. 89
(emphasis added). Thus, the agency clearly advised offerors that
the terms of the competition would be based on those
assumptions.
Moreover, the agency's statement that the assumptions did not
"represent any preference on the part of the government for a
particular implementation schedule" was in provided response to
a question posed by an offeror in Q&A No. 89, "will the
Government disclose what agencies DHS will be focusing on
first?" We think it is reasonably understood that this statement
refers to the order, rather than the pace of migration, i.e.,
the anticipated number of end-users to be migrated. Thus, this
statement provides no support for the agency's argument that the
assumptions in the RFP are immaterial for purposes of
determining whether the agency's requirements changed prior to
award.
Additionally, DHS argues that the 20 percent assumptions in the
RFP were "notional," and were merely intended to provide
offerors with a common basis for submitting proposals. The
agency thus contends that the assumptions set forth in the ID/IQ
contract did not commit the agency to provide any level of
orders above a guaranteed minimum amount. For this reason, the
agency contends, any variance from those assumptions in the
agency's issuance of task orders would not constitute a material
change requiring reopening the competition.
We think that DHS's arguments conflate the agency's discretion
to issue or not issue task orders during contract performance
with its obligation to provide a meaningful basis to compare
offerors' proposals. Although agencies have discretion in the
issuance of orders under an ID/IQ contract, DHS's actions here
relate to a pre-award change in its requirements. As discussed
above, the agency required offerors to submit proposals based on
a specific set of assumptions concerning the pace and volume of
work to be performed. The agency then evaluated those proposals
and selected CACI for award. Subsequent to that evaluation and
award selection--but prior to the actual contract award--the
agency's requirements for the pace and volume of work was
reduced. Specifically, in response to OMB direction, DHS adopted
a migration approach that was expected to take place over the
first 2 years of the contract, and that required migration of a
significantly smaller volume of end users as compared to the RFP
assumptions upon which offerors were required to base their
proposals. Thus, contrary to the agency's arguments, the
material change arose here based on a pre-award change to the
agency's requirements; the material change did not arise from
the agency's exercise of its discretion to issue or not issue a
task order during performance of an ID/IQ contract.
On this record, we think that DHS's proposed approach of
migrating only FEMA over the course of a 24-month period is a
material departure from the assumptions set forth in the RFP,
upon which offerors were required to base their proposals, such
that the agency was required to amend the solicitation and
obtain revised proposals. See Symetrics, supra; Northrop Grumman
Info. Tech., supra.
Moreover, the record evidences that the RFP could be reasonably
read as contemplating that offerors would perform either
multiple, simultaneous migrations of DHS component agencies, or,
alternatively, serial migrations at a rapid pace in order to
meet the assumptions set forth in section L of the RFP. As GCE
notes, the RFP anticipated migrating all DHS component agencies
to an enterprise-wide, integrated system, and offerors were
required to address their "proposed approach for managing
multiple task orders simultaneously." See RFP sect. L.7.1. The
agency also advised that there was no "preference on the part of
the government for a particular implementation schedule," and
that offerors were free to propose migrations as they thought
best. RFP amend. 2, Q&A No. 89. We note, however, that migrating
16 DHS components over the course of 6 years without any
simultaneous migration efforts would require sequential
migrations to be completed, on average, every 4.5 months. We
also note that such a schedule stands in marked contrast to the
24-month schedule for the FEMA migration, which represents only
1.5 percent to 2.9 percent of DHS end-users. Thus, in our view,
the solicitation invited offerors to propose migrations at a
very different pace than DHS now envisions.
In sum, because the solicitation required offerors to submit
proposals based on the assumptions set forth in RFP section L,
because the selection decision relied on the agency's evaluation
of the offerors proposed prices and technical solutions that
were based on those assumptions, and because these assumptions
were no longer valid at the time of award, we think that the
agency's award to CACI was improper. See Symetrics, supra;
Northrop Grumman Info. Tech., supra. Because of the significant
changes to the RFP assumption, the agency was required to amend
the solicitation to reflect the agency's revised requirements,
and provide offerors with an opportunity to submit new
proposals. See Symetrics, supra; Northrop Grumman Info. Tech.,
supra.
We further conclude that GCE was prejudiced by DHS's failure to
amend the solicitation. GCE contends that it would have taken a
different approach to its price and technical approach had it
not been required to assume that 20 percent of all end‑users
would be migrated by year 2 of the contract. GCE's Comments at
22; see GCE Protest, exh. 4, Decl. of GCE Chief Strategy
Officer, at 4-7. Because the work contemplated for the first 2
years is materially different from that indicated by the
assumptions on which offerors were required to prepare their
proposals, we think that there was a reasonable possibility that
GCE was prejudiced because it did not have an opportunity to
revise its proposed technical approach and costs. We sustain
GCE's protest on this basis. (Global
Computer Enterprises, Inc.; Savantage Financial Services, Inc.,
B-404597; B-404597.2; B-404597.3, March 9, 2011) (pdf)
NNSA administers the Nevada Test Site (NTS), a 1,375 square mile
restricted access site in Nevada. The NTS was the site of
numerous explosives tests, including approximately 928
underground and atmospheric nuclear tests. In 1989, DOE
established the Environmental Management Program, which is
responsible for addressing the environmental effects of nuclear
weapons tests at sites across the country, including the NTS.
In 1996, DOE, the Department of Defense, and the state of Nevada
entered into the Federal Facilities Agreement and Consent Order
(FFACO) to identify sites requiring environmental remediation,
including the NTS, and to develop plans and procedures for the
remediation work. As relevant here, the FFACO establishes
procedures for “characterizing” the work required for a
corrective action site (CAS) where evaluation and remediation
services are to be performed. Agency Report (AR), Tab 13, FFACO,
at 7. Under the terms of the FFACO, multiple CASs may be grouped
into a corrective action unit (CAU) based on common conditions
or other features which make treating the CASs as a single unit
appropriate. Id. at 10.
(sections deleted)
Stoller first argues that
NNSA improperly waived or relaxed a material solicitation
requirement in the PWS that required offerors to prepare two
documents for each of three soils sub-project CAUs. As discussed
above, Navarro proposed, and the agency accepted, a technical
approach whereby three soils sub-project CAUs--Johnny Boy, Area
20, and Sedan--were consolidated into a single CAU. As set forth
in greater detail below, this protest ground essentially argues
that the agency accepted a proposal that deviated from the
requirements of the solicitation in such a way that other
competitors, reasonably following the terms of the solicitation,
could not have anticipated was permitted.
It is a fundamental principle of government procurement that
competitions must be conducted on an equal basis, that is,
offerors must be treated equally and be provided with a common
basis for the preparation of their proposals. Continental RPVs,
B-292768.2, B-292768.3, Dec. 11, 2003, 2004 CPD para. 56 at 8.
Contracting officials may not announce in the solicitation that
they will use one evaluation scheme and then follow another
without informing offerors of the changed plan and providing
them an opportunity to submit proposals on that basis. Fintrac,
Inc., B-311462.2, B-311462.3, Oct. 14, 2008, 2008 CPD para. 191
at 6. Our Office will sustain a protest that an agency
improperly waived or relaxed its requirements for the awardee
where the protester establishes a reasonable possibility that it
was prejudiced by the agency’s actions. Datastream Sys., Inc.,
B-291653, Jan. 24, 2003, 2003 CPD para. 30 at 6.
Stoller argues that the solicitation did not reasonably advise
offerors that they could propose, and that NNSA would accept, a
technical approach that consolidated the individual CAUs listed
in the PWS. Instead, Stoller argues that offerors should have
understood the plain language of the PWS to require offerors to
submit technical proposals that addressed the activities as
described in the PWS, i.e., addressed each CAU as stated. The
protester therefore argues that the agency improperly accepted
Navarro's proposal because it did not comply with the
requirement to address the CAUs individually, as listed in the
PWS. Stoller further contends that it was prejudiced by the
agency's actions because it did not have an opportunity to
submit a proposal that involved reorganization or consolidation
of CAUs.
(sections deleted)
In his testimony, the SEB
chair further elaborated that consolidating the three CAUs would
result in cost savings during performance because instead of
preparing three CAIP and three CADD/CR documents, Navarro's plan
anticipated preparing one CAIP and one CADD/CR document for the
consolidated CAU. Tr. at 330:22-331:5. The agency understood
that the consolidation would result in reduced document
preparation efforts, regulatory reviews, and would provide
potential efficiencies in field activities. Id. at 330:3-21,
331:12-334:5. In its evaluation of Navarro's cost proposal, the
agency noted that the proposed staffing and labor hours for the
soils sub-project were realistic because, in part, the work
schedule was accelerated and would be completed 1 year ahead of
schedule. AR, Tab 11, Navarro Cost Realism Evaluation, at 2.
We think Stoller reasonably understood the solicitation to
require offerors to propose technical solutions based on the
CAUs as listed in the PWS. The agency acknowledges that although
the list of CAUs had been updated in FFACO Appendix II prior to
the issuance of the RFP, the PWS requirements reflect an older
version of the appendix. Tr. at 344:10-15. In its proposal,
Stoller stated that it was aware that the list of CAUs in the
PWS was not current, but understood the solicitation to require
offerors to propose the requirements as stated in the PWS:
“While we have based our approach, cost estimate, and proposal
discussions on the PWS and the ‘Description of Work' document
presented on the web site, we know that changes [to Appendix II]
have occurred.”AR, Tab 7A, Stoller Technical Proposal, at 1-8.
In our view, offerors were not reasonably on notice that they
could propose, and the agency would accept, consolidating the
CAUs listed in the PWS. We think the plain language of the PWS
anticipated that each item, as listed, was a separate
requirement. As a result, allowing Navarro to consolidate the
CAUs was a material waiver or relaxation of the
proposal-submission requirements of the solicitation because it
allowed the awardee to propose reduced costs and accelerate its
performance schedule--a feature which the agency recognized as a
significant strength.
During the course of this protest, NNSA and Navarro raised three
primary arguments in support of their view that the PWS
permitted offerors to propose, and the agency to accept, a
technical approach that consolidated individually-listed CAUs.
As discussed below, we find each argument to be without merit.
First, the agency and intervenor argue that the PWS did not
expressly prohibit offerors from consolidating the CAUs. As
discussed above, however, we think the solicitation as written
required offerors to separately address each of the requirements
listed in the PWS. Under these circumstances, we do not think
that offerors should have understood the absence of an explicit
prohibition on consolidating the CAUs to be an authorization to
deviate from the terms of the PWS.
Next, NNSA and Navarro argue that the Q&As issued by the agency
indicate that offerors were allowed to propose consolidation of
the CAUs. After the RFP was issued, the agency published the
following solicitation Q&As on its website:
8. Question: “In the list
of Pertinent Documents, DOE has provided the 2009-2013
schedules. Is DOE dictating that bidders follow the schedule
given, or are bidders free to develop their own approach to
meet the FFACO milestones?”
Response: The FFACO milestones are minimum milestones.
Offerors may propose an approach to meet or accelerate these
milestones consistent with the FFACO approved strategy while
balancing the Offeror’s proposed approach to avoid or minimize
any technical risk.
30. Question: “In the PWS, Section 3, Specific Requirements, a
certain number of milestones have been defined. In particular,
the milestones dictate the approach to be taken (CAIP, CADD or
CADD/CR) for all the Projects. Can we use our own approach for
the milestones that are not FFACO milestones? We respectfully
suggest that allowing the bidders to bring their own approach
would provide the government with a better understanding of
the value that the bidders bring. So, we suggest that for the
CAUs where a firm FFACO milestone is not fixed yet, the
government uses as milestones the closure of the CAU by a
given date and give the bidders flexibility on the approach to
be taken.
Response: See response to Question 8.
Id., RFP-Related Q&As, Apr.
2, 2008, at 4, 9-10 (emphasis added).
The agency and intervenor
argue that the phrase “may propose an approach to meet or
accelerate these milestones consistent with the FFACO approved
strategy” implies that offerors could propose any approach that
was consistent with the FFACO--including consolidation of CAUs
listed in Appendix II. As discussed above, the record shows that
the agency has the discretion to reorganize CAUs listed under
Appendix II of the FFACO. The Q&As cited above, however, clearly
address accelerating the schedule for completing the various
milestones for the activities listed in the PWS, and do not
mention consolidation or reorganization of the CAUs. We do not
think that the phrase “consistent with the FFACO approved
strategy” reasonably advised offerors that they could also
propose to consolidate the CAUs listed in the PWS, especially
where the agency, and not the contractor, would have to
determine whether such consolidation or reorganization was
appropriate.
Finally, NNSA and Navarro argue that the PWS specifically
permitted offerors to propose consolidation of the CAUs listed
in the PWS. PWS sect. 3.1.1.8 states that “[t]he contractor
shall provide planning and management services for the
identification, grouping, and prioritization of CASs and CAUs.”
The agency and intervenor contend that this section advised
offerors that they were permitted during contract performance to
propose reorganization or consolidation of any CAUs listed in
Appendix II. We disagree.
This PWS section merely addresses the support services that the
contractor must provide during contract performance--it does not
clearly state, as the agency and intervenor suggest, that
offerors are permitted to propose an alternative CAU
organization from that listed in the PWS. Put differently, we do
not think that the PWS requirement to provide “planning and
management services for the identification, grouping, and
prioritizing of CASs and CAUs” during contract performance
reasonably advised offerors that they could propose to
consolidate the CAUs in their proposals as part of their
technical approach.
In sum, we think that offerors were not reasonably on notice
that the agency would accept a proposal that consolidates the
CAUs listed in the PWS. Accordingly, we conclude that NNSA
improperly waived or relaxed the requirements of the PWS in its
evaluation of Navarro's proposal. We also conclude that Stoller
was prejudiced here because, but for the agency's improper
action, Stoller would have had a substantial chance of receiving
an award. See McDonald-Bradley, B-270126, Feb. 8, 1996, 96-1 CPD
para. 54 at 3; Statistica, Inc. v. Christopher, 102 F.3d 1577,
1581 (Fed. Cir. 1996). (The S.M.
Stoller Corporation, B-400937; B-400937.3; B-400937.4, March
25, 2009) (pdf)
As indicated above, on September 26, VA amended CLIN 09 of the
RFP, changing the phrase "4 CU YD compactor" to "4 CY
CONTAINER." AR exh. 2 at 1. DBI maintains that the record shows
that WMI did not acknowledge the amendment, that its offer thus
should have been rejected, and that the requirement should be
resolicited. VA advises that the contracting officer
determined that the amendment was not material, and therefore
waived the failure to acknowledge the amendment as a "minor
informality." Id. The protester does not agree that the
amendment was immaterial.
We find the waiver unobjectionable. In determining whether an
amendment is material, we look at the facts of each case. While
no precise rule exists as to whether a change required by an
amendment is more than negligible, such that failure to
acknowledge the amendment renders the proposal unacceptable, an
amendment is material where it imposes legal obligations on a
party that are different from those contained in the original
solicitation, or if it would have more than a negligible impact
on price, quantity, quality, or delivery. See Skyline ULTD,
Inc., B-297800.3, Aug. 22, 2006, 2006 CPD para. 128 at 3. The
mere fact that requirements have been changed by an amendment,
however, does not render the amendment material. Doty Bros.
Equip. Co., B-274634, Dec. 19, 1996, 96-2 CPD para. 234 at 3-5.
DBI asserts that the amendment was material because "a
compactor, including its wiring and installation, is far more
expensive than a mere container." Comments at 12. However, it
appears from the record that there is no effective price
difference between the two items. VA reports that all of the offerors submitted the same price for the compactor and the
container CLINs, ASR exh. 1, and also has furnished an invoice
indicating that DBI charges an identical rate for compactors and
containers under its current contract. ASR exh. 3. We also note
that the unacknowledged amendment related to only 1 of 35 CLINs.
These considerations indicate that the change was not
significant, and DBI has presented no evidence showing
otherwise. Under these circumstances, we conclude that the
amendment was not material and that the agency properly waived
WMI's failure to acknowledge it. See, e.g., Lumus Constr., Inc.,
B-287480, June 25, 2001, 2001 CPD para. 108 at 3 (even where
amendment arguably introduced new obligations in solicitation,
any price difference attributable to amendment was negligible
and amendment was not material); Microform, Inc.; Gov't Printing
Office--Recon., B‑231411.2, B‑231411.3, Dec. 13, 1988, 88-2 CPD
para. 587 at 2 (amendment decreasing estimated quantity not
material where no evidence that change would have had more than
trivial effect on prices).
(DBI
Waste Systems, Inc., B-400687; B-400687.2, January 12, 2009)
(pdf)
Even if Hart's protest were to be considered timely, it fails to
state a valid basis for consideration. In this regard, Hart's
protest to our Office asserts that the agency "issued a
defective solicitation"; complains that, by failing to identify
the facility clearance requirement until 6 weeks after the
solicitation was first issued, the agency misled potential
offerors and/or failed to engage in adequate advance planning;
and seeks recovery of the costs Hart incurred in preparing its
proposal. Protest, Nov. 17, 2008.
Procuring agencies have an obligation to draft solicitations
that reflect their actual needs. Federal Acquisition Regulation
(FAR) sect. 15.203(a). Further, this obligation is ongoing, and
a solicitation must be amended where, as initially issued, it
fails to reflect the agency's actual requirements. FAR sect.
15.206(a); Global Solutions Network, Inc., B‑298682.2, Dec. 10,
2007, 2007 CPD para. 223 at 3.
Here, nothing in Hart's protest suggests that the solicitation's
inclusion of a facility clearance requirement is inconsistent
with the agency's actual needs, or is otherwise contrary to
applicable law or regulation. Accordingly, there is no basis for
this Office to conclude that inclusion of this requirement
rendered the solicitation "defective." Indeed, Hart's protest is
based almost exclusively on the premise that the agency acted
improperly in failing to identify the facility clearance
requirement at an earlier point in the procurement
process--specifically, before Hart had incurred proposal
preparation costs.
Although agencies are obligated to engage in reasonable advance
planning prior to conducting procurements, our Office has
recognized that the specific activities associated with this
requirement may vary from procurement to procurement, and that
the obligation does not constitute a requirement that
procurement planning be perfect, that is, completely error-free.
See, e.g., New Breed Leasing Corp., B-274201, B‑274202, Nov. 26,
1996, 96-2 CPD para. 202 at 6; Sprint Communciations Co., LP,
B‑262003.2, Jan. 25, 1996, 96-1 CPD para. 24 at 9. Further, we
have noted that not every flaw or irregularity in a given
procurement process entitles an offeror to recover the expenses
incurred in submitting a proposal. See, e.g., New Breed Leasing
Corp.--Recon., B-274201.2, B-274202.2, Apr. 7, 1998, 98-1 CPD
para. 97 at 2; I.E. Levick and Assocs., B‑218294.2, Apr. 12,
1985, 85-1 CPD para. 424 at 2.
Here, even if Hart's protest were timely filed, and even if we
were to accept Hart's proposition that the agency should have
responded more clearly to questions regarding the facility
clearance requirement at an earlier point in the procurement
process, in these circumstances, we do not view the 6-week delay
in identifying this requirement as a valid basis for protest.
(Hart Security Limited,
B-400796.2, December 16, 2008) (pdf)
MBE argues that UNICOR was required to amend the RFP and request
revised proposals, rather than making an award based on prices
calculated for the larger quantity of cable. MBE also argues
that it was competitively prejudiced by the error because, if
the competition had been reopened, MBE would have offered a
lower price.
UNICOR responds that the offerors' total prices can be
recalculated with certainty, using the quantities in the RFP,
and that under this approach also, Allied proposed a lower total
evaluated price than MBE. CO Statement at 4. UNICOR also argues
that the difference in quantity was not significant enough to
affect the offered prices.
MBE does not dispute that Allied's prices were lower under both
calculations, but argues that it was prejudiced by the erroneous
estimate because between the deadline for submission of offers
(June 2) and award (June 4), the prices of copper and crude oil
in commodities markets dropped. MBE argues that since copper is
a raw material used in producing the cable, and oil is a
component of the cost of delivery, if UNICOR had reopened the
competition on June 4 to revise the quantities, MBE could have
submitted a lower price than Allied. Protester's Comments at 2.
Generally, where an agency's requirements change after a
solicitation has been issued, it must issue an amendment to
notify offerors of the changed requirements and afford them an
opportunity to respond. FAR sect. 15.206(a). The object of the
requirement is to avoid award decisions not based on the
agency's most current view of its minimum needs. One
circumstance requiring the issuance of an amendment is a
significant change in the government’s estimate of the quantity
it expects to order. Symetrics Indus., Inc., B-274246.3 et al.,
Aug. 20, 1997, 97-2 CPD para. 59 at 6. In the context of a
requirements contract, we have held that a change in the
estimated quantity must be shown to have more than a trivial
effect on the prices offered. See Microform, Inc.; Government
Printing Office--Recons., B-231411.2; B-231411.3, Dec. 13, 1988,
88-2 CPD para. 587 at 2 (amendment decreasing estimated quantity
in requirements contract was not material where there was no
evidence that the change would have had more than a trivial
effect on prices). Consistent with this, our Office will not
sustain a protest unless the protester demonstrates a reasonable
possibility that it was prejudiced by the agency’s actions, that
is, unless the protester demonstrates that, but for the agency's
actions, it would have had a substantial chance of receiving the
award. McDonald‑Bradley, B‑270126, Feb. 8, 1996, 96‑1 CPD para.
54 at 3; see Statistica, Inc. v. Christopher, 102 F.3d 1577,
1581 (Fed. Cir. 1996).
Here, MBE does not attempt to quantify how much the decrease in
the cost of copper would influence the cost of producing the
cable, nor how much the decrease in the cost of crude oil would
affect the cost of delivery. Nor has MBE shown that it was
uniquely-positioned among the competitors to benefit from the
fortuitous short-term movement of the commodities markets that
it has identified. Moreover, MBE has offered no explanation of
how these issues are at all related to the small change in the
estimated maximum quantity for one of the locations. Taken
together, MBE has not shown that it was competitively prejudiced
by UNICOR's evaluation of proposals using a slightly greater
quantity than the maximum estimate stated in the RFP in the
context of a requirements contract. (Murray-Benjamin
Electric Company, L.P., B-400255, August 7, 2008) (pdf)
ECI protests the agency's determination that its proposal was
unacceptable. Specifically, the protester argues that its
proposal did in fact comply with the solicitation’s delivery
schedule and represented the best value to the government based
on its more favorable pricing. Protest, May 20, 2008, at 2-4.
Additionally, ECI protests that DSCR employed unstated
evaluation criteria in its evaluation of offerors’ proposals.
Protest, June 30, 2008, at 2-4.
The agency argues that ECI's protest should be dismissed because
ECI is not an interested party. The agency contends that ECI
failed to timely acknowledge amendment No. 0005, a material
amendment to the solicitation. Because ECI did not have a valid
(i.e., timely submitted) proposal before the agency for
consideration and thus is ineligible for award even if it
prevails in its protest, DSCR argues, ECI is not an interested
party to pursue its protest. Agency Dismissal Request, June 11,
2008, at 1-4.
ECI argues that its protest should not be dismissed on these
grounds. The protester does not dispute that it failed to
acknowledge and return amendment No. 0005 by the specified date.
Rather, ECI argues that its late submission of amendment No.
0005 did not automatically mandate rejection of its proposal but
instead made such action only discretionary on the agency’s part
(and DSCR apparently elected to further consider ECI’s
proposal). In support thereof, ECI points to the language of
Standard Form (SF) 30, Amendment of Solicitation/Modification of
Contract, which states in relevant part that “[f]ailure of your
acknowledgement to be received at the place designated for the
receipt of offers prior to the hour and date specified may
result in rejection of your offer.”
We find that ECI failed to timely acknowledge a material
amendment and, as a result, is not an interested party to
challenge the agency's evaluation of proposals. As a general
rule, an offeror’s failure to acknowledge a material amendment
renders the proposal unacceptable and such proposal may not form
the basis for award. Sterling Servs., Inc., B-291625,
B-291626, Jan. 14, 2003, 2003 CPD para. 26 at 3;
International Filter Mfg. Corp., B-235049, June 21, 1989,
89-1 CPD para. 586 at 3. In determining whether an amendment is
material, we look at the facts of each case. While no precise
rule exists as to whether a change required by an amendment is
more than negligible, such that failure to acknowledge the
amendment renders the proposal unacceptable, an amendment is
material where it imposes legal obligations on a party that are
different from those contained in the original solicitation, or
if it would have more than a negligible impact on price,
quantity, quality, or delivery. See Skyline ULTD, Inc.,
B-297800.3, Aug. 22, 2006 CPD para. 128 at 3; Navistar Marine
Instrument Corp., B-277143.2, Feb. 13, 1998, 98-1 CPD para.
53 at 2.
Here, amendment No. 0005 significantly altered the guaranteed
minimum quantity for the base year. Instead of a guaranteed
minimum quantity of 63 assemblies as contained in the original
RFP, the amendment changed the minimum quantity that DSCR was
required to purchase to 250 assemblies, in comparison to the
unchanged estimated quantity of 252 units. As expressed in
percentage terms, amendment No. 0005 changed the RFP’s
guaranteed minimum quantity for the base year from 25 percent
(63 / 252 = .25) to 99 percent (250 / 252 = .99) of the
estimated quantity. While the evaluation of proposals remained
based on offerors' prices for the estimated quantities, offerors
were able to, and did, propose different (i.e., tiered) pricing
based on the number of units that the agency actually purchased.
For example, ECI’s base year price for the guaranteed minimum
quantity of 63 assemblies was $[DELETED] each, while its base
year price for the estimated quantity of 252 assemblies was
$[DELETED] each, a $[DELETED] difference per unit. AR, Tab 9,
ECI Email to DSCR, Mar. 14, 2008, at 3. That ECI did not
actually modify its proposed pricing as a result of amendment
No. 0005 does not alter the fact that DSCR’s legal obligation as
a result of such amendment was significantly greater than that
contained in the original solicitation, and had the potential
for more than a negligible impact on offerors’ prices. See
Christolow Fire Prot. Sys., B-286585, Jan. 12, 2001, 2001 CPD
para. 13 at 3-4. Accordingly, the amendment was material in
nature. (ECI Defense Group,
B-400177; B-400177.2, July 25, 2008) (pdf)
During the course of the procurement, the agency twice extended
the deadline for FPRs in order that Presidential's FPR could be
considered. In this regard, initial FPR's were due on March 22,
2006, at 2 p.m. EST, but Presidential's FPR was not received
until 2:33 p.m. At 2:36 p.m., the contracting officer extended
the deadline to March 23 at 11 a.m. A second round of FPR's was
due August 15 at 2 p.m., and Presidential’s FPR was received at
2:30 p.m. At 2:29 p.m., after becoming aware that Presidential
would miss the deadline, the contracting officer issued an
amendment changing the deadline to 4 p.m. Geo‑Seis argues that
extending the closing times was improper and that MSC instead
should have rejected the FPRs and eliminated Presidential from
the competition. This argument is without merit. The
record shows that the agency's motivation in extending the
deadlines was to enhance competition by keeping Presidential's
proposal in the competition. There is no prohibition against a
procuring agency issuing an amendment to extend the closing time
for receipt of proposals after that time has passed in order to
accommodate even one offeror, where the motivation for the
extension is enhanced competition. Varicon Int'l, Inc.; MVM,
Inc., B-255808, B‑255808.2, Apr. 6, 1994, 94-1 CPD para. 240 at
4. Geo-Seis attempts to distinguish our prior decisions from the
case here on the facts. However, we find that the essential
facts from our prior cases are present here--the agency issued
an amendment extending the closing time after the expiration of
the original closing time in order to keep an offeror in the
competition, and thereby enhance competition. Again, extending
the closing time for this purpose is unobjectionable. See
Institute for Advanced Safety Studies--Recon., B-221330.2, July
25, 1986, 86‑2 CPD para. 110 at 2 (it was not improper for
agency to issue an amendment extending the closing time 3 days
after expiration of the original closing time); Fort Biscuit
Co., B-247319, May 12, 1992, 92-1 CPD para. 440 at 4 (it was not
improper for agency to extend closing time to permit one of four
offerors more time to submit its best and final offer). (Geo-Seis
Helicopters, Inc., B-299175; B-299175.2, March 5, 2007) (pdf)
Note:
This Court of Federal Claims ruled differently.
See Geo-Seis Helicopters., v. U. S. and
Presidential Airways, Inc., No. 07-155C, July 13, 2007,
below.
DRS complains that this relaxation of the fuel efficiency
requirements is inconsistent with section 317 of the National
Defense Authorization Act (NDAA) for Fiscal Year 2002, 10 U.S.C.
sect. 2865, note (Supp. II 2002), Federal Acquisition Regulation
(FAR) sect. 11.101, and Executive Order (E.O.) No. 13,423, 72
Fed. Reg. 3919 (Jan. 24, 2007). According to the protester, the
relaxation of the efficiency standards is inconsistent with
these authorities, all of which require agencies to acquire
energy efficient products "to the maximum extent practicable."
The protester maintains that the agency's relaxation of the fuel
efficiency requirements here is especially unreasonable because
it has been working to design its generators to meet the
earlier, more stringent, requirements for the past 2 years. In
any event, there is no indication in the NDAA (or the E.O. or
the FAR) that the energy efficiency requirements were intended
to override the requirement for full and open competition
articulated in the Competition in Contracting Act (CICA), 10
U.S.C. sect. 2302 et seq. (2000), or otherwise to take
precedence over an agency's other legitimate needs. Rather,
agencies are required to meet the efficiency requirement only
"to the maximum extent practicable." Here, the agency determined
that neither DRS nor Onan can meet the original fuel efficiency
requirements, and that the requirement therefore had to be
relaxed in order for the competition to proceed. There is
nothing in the NDAA to suggest that relaxing a fuel efficiency
requirement for this reason is impermissible. Moreover, even if
the evidence is as the protester claims, we think the agency
nevertheless could properly relax the requirement in order to
ensure that there would be more than a single potential source;
again, there is nothing in the NDAA providing that agencies must
apply stringent fuel efficiency standards at the expense of
competition. In this regard, where, as here, an agency
determines that a relaxed specification will both meet its needs
and afford enhanced competition for the goods or services being
acquired, we will not object to the relaxation. See Virginia
Elec. and Power Co; Baltimore Gas & Elec. Co., B‑285209,
B-285209.2, Aug. 2, 2000, 2000 CPD para. 134 at 7-8 (the role of
our Office in reviewing bid protests is to ensure that the
statutory requirements for full and open competition are met,
not to protect any interest a protester may have in more
restrictive specifications). Thus, even if, as the protester
alleges, its generator design is able to meet the earlier, more
stringent fuel efficiency requirements, the agency’s decision to
relax the specification in order to include Onan in the
competition is unobjectionable. (Engineered
Electric Company d/b/a DRS Fermont, B-295126.4, June 14,
2007) (pdf)
Here, the protester contends that amendment No. 6 is not
material because it merely clarified existing contract
performance requirements and thus did not affect the legal
relationship of the parties. Specifically, the protester asserts
that, despite its failure to acknowledge the amendment, it would
be obliged to monitor foreign travel danger area status changes,
since its proposal generally offers to review policies affecting
contract performance. We disagree. As the agency points out,
prior to issuance of amendment No. 6, there was no specific
requirement in the RFP obligating the contractor to
affirmatively monitor foreign travel danger status changes and
to promptly coordinate any such change with the contracting
agency. Since there was no such requirement in the RFP,
Skyline’s offer to generally review policies regarding contract
peformance does not constitute an agreement to the specific
obligations imposed by amendment No. 6. Consequently, we cannot
agree with the protester that amendment No. 6 did no more than
clarify existing obligations of the contractor. In light of the
amendment’s addition of contractor obligations to monitor and
coordinate action regarding changes in foreign travel danger
area status, and the agency’s additional rights derived from
those requirements, we conclude that the amendment affects the
legal relationship of the parties and therefore is material. See
Federal Constr., Inc., B-279638, B‑279638.2, July 2, 1998, 98-2
CPD para. 5 at 4-5. Consequently, the protester’s failure to
acknowledge it cannot, as Skyline requests, be waived as a minor
informality. See T&S Maint. Servs., B-278598, Feb. 18, 1998,
98‑1 CPD para. 54 at 2-3. Accordingly, we see no basis to object
to the agency’s rejection of the proposal for failure to
acknowledge amendment No. 6. (Skyline
ULTD, Inc., B-297800.3, August 22, 2006) (pdf)
Space-Lok principally questions the agency’s use of the 210-day
delivery requirement as a basis for issuing the purchase order
to UFC, asserting that the 210-day requirement was not stated in
the solicitation and, in any case, did not represent the
agency’s needs, as evidenced by the agency’s delays in
evaluating the quotations and issuing the purchase order. In
this latter regard, the protester stated a 150-day delivery in
its initial quotation and contends that, had the agency timely
evaluated the initial quotations, it would have been issued the
purchase order. Although the protester is correct that the
210-day delivery requirement was not stated in the solicitation,
it was set forth in the August 10 synopsis issued following the
change from the original simplified acquisition. Information
disseminated during the course of a procurement that is in
writing, signed by the contracting officer and provided to all
vendors, meets all the essential elements of an amendment
and--even where not designated as an amendment--is sufficient to
operate as such. Linguistic Sys., Inc., B-296221, June 1, 2005,
2005 CPD para. 104 at 2. The August 10 synopsis met this
standard, since it was issued in writing and posted and
available to all vendors on the Federal Business Opportunities
website. The synopsis thus became part of the solicitation, and
it follows that the information in the synopsis was sufficient
to establish, and to put Space-Lok on notice of, the 210-day
delivery requirement. Id. (Space-Lok,
Inc., B-297516, January 25, 2006) (pdf)
Based on the record before us, we agree with the protester that
MGT’s proposal failed to address material solicitation
requirements and, as a consequence, did not provide a proper
basis for award. In this connection, any proposal that fails to
conform to material terms and conditions of an RFP should be
considered unacceptable and may not form the basis for an award.
SWR, Inc., B-284075, B‑284075.2, Feb. 16, 2000, 2000 CPD para.
43 at 3. While MGT’s proposal contained more information than
Wiltex’s, it still did not address a number of the RFP’s
material requirements, including the requirement for proof of
ability to furnish 24-hour on-site warranty service within 2
hours of notice and the requirement for a guarantee from the
manufacturer that replacement parts would be available for a
minimum of 10 years from the date of installation.[2] The
contracting officer acknowledges that the awardee’s proposal did
not address the latter requirement. With regard to the former
requirement, the contracting officer argues that MGT
demonstrated its ability to respond to service calls within the
required timeframe by including in its proposal literature from
Powerex, the manufacturer of its proposed air compressor system,
that stated as follows:
Powerex also has over 200 trained and authorized service
centers in the U.S. These local distributors have parts and
service available normally 24 hours a day 7 days per week.
Since there is no indication in MGT’s proposal that either it or
its installer is a Powerex authorized service center, we are not
persuaded by the contracting officer’s argument. Moreover, MGT
did not otherwise address the requirement. We also think that
the evaluators unreasonably determined that MGT had demonstrated
acceptable experience. As previously noted, the RFP instructed
offerors “to describe the past experience of the company in
providing maintenance on the equipment specified in this
solicitation within the past three (3) years.” While MGT’s
proposal described the company’s experience in selling air
processing systems and the experience of its installer in
installing them, MGT’s proposal furnished no description of
experience on the part of either in providing maintenance on the
systems once installed. Despite MGT’s failure to furnish
evidence of the type of experience specifically required by the
RFP, the technical evaluators rated its proposal as acceptable
under the experience evaluation factor. This, we think, was
unreasonable. In sum, because we conclude that the VA could not
reasonably have determined MGT’s proposal, as submitted, to be
technically acceptable, MGT’s proposal could not form the basis
for award. Further, while both Wiltex and MGT submitted
technically unacceptable offers, the agency essentially
overlooked the deficiencies in MGT’s proposal while rejecting
Wiltex’s proposal for similar deficiencies. This disparate
treatment was inconsistent with the agency’s duty to treat
offerors equally, and thus was improper. See Infrared Tech.
Corp.--Recon., B-255709.2, Sept. 14, 1995, 95-2 CPD para. 132 at
4-5. (Wiltex Inc., B-297234.2;
B-297234.3, December 27, 2005) (pdf)
It is a fundamental principle of government procurement that
competition must be conducted on an equal basis, that is,
offerors must be treated equally and be provided with a common
basis for the preparation of their proposals. Continental RPVs,
B-292768.2, B-292768.3, Dec. 11, 2003, 2004 CPD para. 56 at 8;
Systems Mgmt., Inc.; Qualimetrics, Inc., B-287032.3, B-287032.4,
Apr. 16, 2001, 2001 CPD para. 85 at 8. Our Office will sustain a
protest that an agency improperly relaxed its requirements for
the awardee where the protester establishes a reasonable
possibility that it was prejudiced by the agency’s actions.
Datastream Sys., Inc. B-291653, Jan. 24, 2003, 2003 CPD para. 30
at 6. We find that the Army did not improperly relax the
solicitation requirements for the benefit of Wright. We find
Lifecare’s argument that the agency improperly relaxed material
solicitation requirements for the awardee to be without merit.
First, as the protester itself acknowledges, the solicitation
did not require that the successful offeror have all of its
employees on hand prior to contract award, Lifecare’s Comments,
Oct. 3, 2005, at 5; rather, the RFP requirements mandated only
that the awardee have sufficient accredited medical coding
personnel to begin performance by the contract start date.
Second, the record reflects that the agency had a valid reason
for altering the August 15 contract start date, namely, delays
in the contract award process. As set forth above, given that it
was required to reevaluate offerors’ clarified prices and
resolve Lifecare’s agency-level protest, the Army did not make
its final award decision until August 18 and did not issue a
contract to Wright until August 19. In light thereof, we fail to
see, and the protester fails to explain, how Wright or any other
offeror could have begun contract performance on August 15.
Moreover, notwithstanding the agency’s statement that the start
date would be “on or about” September 1, the actual contract
start date was August 22, the first business day after the Army
issued the contract to Wright--a fact which Lifecare ignores. In
sum, we find that there was a reasonable basis for the agency’s
decision to extend the start date for commencement of contract
performance; it was not done to improperly relax the
requirements for the awardee. See Military Waste Mgmt., Inc.,
B-240769.3, Feb. 7, 1991, 91-1 CPD para. 135 at 3. Lifecare, the
incumbent contractor, cannot protest the solicitation, delay the
agency’s ability to award a contract, and then reasonably argue
that any alteration of the planned contract start date
constitutes a relaxation of the requirements in favor of the new
awardee. (Lifecare Management Partners,
B-297078; B-297078.2, November 21, 2005) (pdf)
It is a fundamental principle of government procurement that
competition must be conducted on an equal basis, that is,
offerors must be treated equally and be provided with a common
basis for the preparation of their proposals. Systems Mgmt.,
Inc.; Qualimetrics, Inc. , B-287032.3, B-287032.4, Apr. 16,
2001, 2001 CPD 85 at 8. When, either before or after receipt of
proposals, the government changes or relaxes its requirements,
it must issue an amendment to notify all offerors of the changed
requirements and give them an opportunity to respond. Federal
Acquisition Regulation (FAR) 15.206(a). If time is of the
essence, however, the contracting officer may make an oral
notice of the amendment. FAR 15.206(f). While the contracting
officer must then document the file and formalize the notice
with an amendment, id. , where the agency has adequately advised
the offerors of its changed requirements, the failure to
formally amend the solicitation is not significant. Ram Enters.,
Inc. , B-221924, June 24, 1986, 86-1 CPD 581 at 3. Here,
although AVL Books asserts generally that the agency's telephone
inquiry did not adequately communicate that online claims
processing was an agency requirement, we find its assertion
unpersuasive. As noted above, AVL Books was one of three firms
that the contracting officer questioned about its online claims
processing capabilities. Both of the other two firms understood
the question to mean that online claims processing capability
was now an evaluation factor. Both firms, apparently of their
own accord, followed up the telephone call from the contracting
officer with a written confirmation to the contracting officer
of their ability to provide that additional contract service.
Under these circumstances, we conclude that the telephone call
from the contracting officer and the medical librarian was
adequate notice to all offerors that online claims processing
capability had been added as a requirement to the solicitation.
(AVL Books.Com, Inc., B-295780,
March 28, 2005) (pdf)
On December 2, the day before the award to AT&T, the Chief
Information Officer for Treasury (Treasury CIO), the
Commissioner of the General Services Administration's (GSA)
Federal Technology Service (FTS), the Administrator of the
Office of Management and Budget's (OMB) Office of Federal
Procurement Policy (OFPP), and the Administrator of OMB's Office
of Electronic Government (E-Government) signed a memorandum of
understanding (MOU) regarding the possible migration of
Treasury's TCE requirements to the forthcoming GSA FTS-Networx
telecommunications services contract at the expiration of the
3-year TCE base period. The protesters assert that the MOU
represented a fundamental and material change in the manner in
which the determination whether to exercise the options would be
made, and that it was unreasonable to require offerors to
prepare their proposals without disclosing this information. We
agree with the protesters. Here, the MOU significantly changed
the approach to determining whether to exercise the TCE options
in ways that, in total, made it significantly less likely that
the TCE options would be exercised. In fact, in light of all of
the information in the record indicating that all of the other
government entities that would be involved in the option
exercise decision believed that Treasury's requirement should
transition to the GSA Networx contract, it appears that the MOU
made it more likely that the options would not be exercised than
that they would. This represented a material change to the basis
upon which offerors prepared their proposals. Treasury thus was
required to advise offerors of the new approach to determining
whether to exercise the TCE options and provide them an
opportunity to submit revised proposals on a common basis that
reflects the agency's actual needs. Accordingly, we sustain the
protest on this basis. (Northrop
Grumman Information Technology, Inc.; Broadwing, B-295526;
B-295526.2; B-295526.3; B-295526.4; B-295526.5; B-295526.6;,
March 16, 2005) (pdf)
While, as the protester asserts, there may be little difference
between the maintenance to be performed on the printers already
covered by the requirement and that required for the additional
printers, the agency's actions were proper based on the
significant change in its quantity requirements. As noted above,
under the original RFP, offerors submitted proposals to maintain
an estimated 2,557 computers and 3,148 printers. The amended RFP
added an estimated 2,439 impact printers, an increase of
approximately 77 percent in the number of printers, and a more
than 40 percent increase in the total equipment to be
maintained. Quantity estimates in a solicitation establish the
general framework for the governments anticipated purchases
under the contract, and thus provide the basis for offerors to
determine their pricing. Consequently, when an agency knows that
there is a serious discrepancy between a solicitation estimate
and actual anticipated needs, it should not make award on the
basis of the stated estimate but, rather, should revise the
solicitation to provide offerors with the most accurate
information available. United Tel. Co. of the Northwest , supra
, at 9, quoting N.V. Philips Gloellampenfabriken , B-207485.3,
May 3, 1983, 83-1 CPD 467 at 12. Given the significant change in
the quantities of equipment to be maintained under the contract,
amending the solicitation and seeking revised proposals on that
basis was reasonable. The addition of Guam as a performance site
further supports the agency's actions. While there is only a
limited amount of equipment on Guam--a midrange computer and two
printers--the remote location and 18-hour response time for
maintenance would appear to be potentially significant factors
that each offeror is entitled to take into consideration in
calculating its pricing. (Digital
Technologies, Inc., B-291657.3, November 18, 2004) (pdf)
The RFP referred to the Archives II parking lot as an area that
must be maintained by the contractor, even though it was
incomplete when proposals were submitted. RFP at 1.3, 35, 38,
60. The RFP also noted that shuttle service provided by the
contractor to off-site parking could be deleted in the base
year. RFP at 146. With regard to the Archives I building,
prospective offerors had access to the building drawings,
including the planned renovations, and were provided detailed
information on major systems in both the pre- and
post-renovation configurations. RFP, amend. 02; AR at 8. In
addition, when an offeror questioned whether the RFP would be
amended to phase in service at Archives I, the agency answered
that offerors were "to propose 100% service on day one of the
contract," with adjustments to be negotiated upon award. RFP
amend.04. CESI acknowledges that the future construction and
renovations were identified in the RFP, but maintains that
offerors were required to speculate as to the costs. However,
while some degree of speculation obviously was necessary, CESI
has not shown that completion of the work on the Archives I
building and the parking lot resulted in material changes to the
assumptions on which offerors were to base their original
proposals. Thus, since the original proposals were to be based
on the ultimate completion of the work in question, the agency
could reasonably conclude that there was no need to allow
offerors to revise this aspect of their proposals. (Consolidated
Engineering Services, Inc., B-293864.2, October 25, 2004) (pdf)
Because AMFUEL was clearly put on notice during discussions that
its proposed delivery schedules were unacceptable, and because
the agency informed AMFUEL, also during discussions, of what
delivery schedules the agency would find acceptable, we think
that formal amendments to the same effect were not necessary.
See Avitech, Inc., B-214749, Sept. 17, 1984, 84-2 CPD ¶ 297 at
2-3. While AMFUEL characterizes the delivery schedules
identified by the agency during discussions as merely
negotiating positions, the discussions letters clearly advised
that the specified delivery schedules were minimum requirements.
It simply was not reasonable for AMFUEL to assume that it could
submit what it characterized as counter-offers, which again did
not comply with the delivery schedules that the agency clearly
identified as acceptable, without risking that its proposals
would be regarded as unacceptable. Delivery is a material term
of a solicitation and award generally cannot be made on the
basis of a proposal that takes exception to a required delivery
schedule. Logitek, Inc., B-238773, July 6, 1990, 90-2 CPD ¶ 16
at 3-4, recon. denied, B-238773.2, Nov. 19, 1990, 90-2 CPD ¶
401. Because AMFUEL's revised proposals failed to include
delivery schedules that satisfied the government's minimum
requirements, the agency properly found AMFUEL's proposals
unacceptable. (American Fuel Cell &
Coated Fabrics Company, B-293001; B-293020, January 12,
2004) (pdf)
With regard to the water purification systems, the record shows
that award was made to Phenix for a purification system not
including a first step based on water distillation or reverse
osmosis despite the fact that all vendors were notified, via
e-mail requests for clarification, that such a step was
required. To the extent that Phenix believes that compliance
with the requirement was not necessary because it was not
formally made a part of the solicitation through amendment,
where a contracting officer advises all vendors of a
solicitation requirement in writing, the essential elements of
an amendment are present whether or not the communication is
designated as a formal amendment. Realty Ventures/Idaho,
B-226167, May 18, 1987, 87-1 CPD ¶ 523 at 4; see also Federal
Elec. Int'l, Inc., B-232295.2, Dec. 21, 1988, 88-2 CPD ¶ 610 at
10 (furnishing of copy of written question and response places
offeror on notice of government requirements even though they
are not reflected in formal amendment). (Phenix
Research Products, B-292184.2, August 8, 2003) (pdf)
While an ID/IQ contract does give the government flexibility
when it cannot determine its needs above a minimum quantity in
advance of contracting, the use of such a contract does not
excuse the government from actually identifying its needs. Where
an agency's requirements change after a solicitation has been
issued--even after the submission of best and final offers and
up until the time of award--it is required to issue an amendment
to notify offerors of the changed requirements and afford them
an opportunity to respond. Federal Acquisition Regulation (FAR)
§ 15.206(a); NV Servs., B‑284119.2, Feb. 25, 2000, 2000 CPD ¶ 64
at 17; Symetrics Indus., Inc., B-274246.3 et al., Aug. 20, 1997,
97-2 CPD ¶ 59 at 6. This requirement ensures that award
decisions are based on the agency's most current view of its
needs, Symetrics Indus., Inc., supra, and that proposals will be
prepared on a common basis that reflects the agency's actual
needs. Dairy Maid Dairy, Inc., B‑251758.3 et al., May 24, 1993,
93-1 CPD ¶ 404 at 7-9. As noted above, the record shows that the
agency's funding philosophy concerning box drain repair had
changed prior to issuance of the RFP, and that it was aware
after issuance of the RFP that, if funding could be obtained, it
would order the work under the contract awarded under the RFP.
Under these circumstances, the quantity changes should have been
communicated to all offerors through an RFP amendment. This is
particularly the case under the circumstances here, since
Pembroke had been made aware of the increased box drain
quantities through the agency's attempt to include that work
under its prior contract. Although Pembroke perhaps could not be
certain that the additional work ultimately would be funded,
Taylor should have been furnished with equivalent information,
so that it would have had the same opportunity Pembroke had to
factor this risk into its prices. It is undisputed by the agency
that the quantity changes at issue were significant. (M.K. Taylor, Jr.
Contractors, Inc., B-291730.2, April 23, 2003) (pdf) |