FAR 15.303: Evaluation team, Source Selection Plan |
Comptroller
General - Key Excerpts |
Notwithstanding this representation in the Fluor proposal,
the record shows that the agency’s evaluators and source
selection authority expressed a concern that Fluor would
be unable to recruit the incumbent exempt employees at the
wage rates it had proposed. In this connection, the record
shows that the agency’s technical evaluators questioned
Fluor’s ability to recruit the incumbent exempt staff
based on the wage rates it had proposed, and suggested
that Fluor’s approach could result in employee morale and
retention issues. AR, exh. 23 at BATES 518. The agency’s
cost evaluators echoed these same concerns. AR, exh. 22,
at BATES 428-429. In effect, the evaluators questioned
Fluor’s ability to meet its goal of 95 percent retention
of incumbent employees.
In contrast, the evaluators did not give meaningful
consideration to similar implications of DZSP’s proposed
approach described above, or how it would impact the
firm’s retention of employees, as required by the RFP. In
this connection, the evaluators gave no consideration to
the fact that DZSP expressly proposed to replace its
incumbent staff at a rate of [deleted] percent per year
for each year of the 8-year potential life of this
contract. Given this rate of replacement, DZSP essentially
will replace [deleted] percent of its incumbent exempt
staff during approximately the first [deleted] years of
contract performance, and replace almost [deleted] of the
newly-hired exempt employees during the remaining
[deleted] years of contract performance. The agency
technical evaluators confined their observations to
consideration of whether or not it was realistic for DZSP
to replace its existing, incumbent exempt employees, and
concluded that it was “very realistic” for DZSP to do so
because approximately [deleted] percent of DZSP’s overall
workforce was comprised of an aging population. AR, exh.
23, at BATES 496-497. In addition, the technical
evaluators observed only that DZSP’s claimed 95 percent
retention rate for its exempt employees would “not be
applicable” to future contract periods, but did not
criticize the firm’s proposal for this reason. Id. The
cost evaluators, for their part, did not give
consideration to DZSP’s proposed plan to replace its
exempt workforce, and instead confined their observations
to whether or not DZSP’s proposed rates of compensation
were reasonable and realistic. AR, exh. 22, at BATES
422-423.
In addition to these inconsistencies, the agency’s source
selection authority (SSA) specifically found the DZSP
proposal superior to the Fluor proposal in the area of
employee retention and used that as a discriminator for
making her selection decision. In fact, she apparently was
unaware of DZSPs’ proposed approach of essentially
replacing its exempt workforce more than once over the
life of the contract. The SSA found as follows:
In its July 2016 FPRs [final proposal revision], DZSP
eliminated the Exempt labor rate reduction for each
contract period, and adjusted the Base Year rates for
the [deleted] Exempt employees to the same levels as
current incumbent salaries. DZSP also provided an
explanation of its basis for capturing workforce
turnover in its yearly exempt labor rates. DZSP’s
revised exempt labor rates were compared to Guam fair
market value for Key Personnel, Non-Key managers,
supervisors, and engineers, and determined the rates
reasonable and realistic. Therefore, the concern has
been removed. FFS [Fluor Federal Solutions] also
provided a detailed staffing plan using a Guam BOS [base
operations services], annex specific efficiency factor.
FFS proposed to hire 95% of its workforce from
individuals currently employed by DZSP but at lower
rates than DZSP is currently paying and in some cases,
significantly lower than DZSP’s rates. FFS may have
challenges in meeting this 95% goal due to the proposed
reduced salaries but also indicated FFS has described
effective corporate resourcing as an alternative to
acquiring personnel. While both proposals received
Outstanding ratings for Factor C [staffing and
resources], I conclude DZSP provides slightly more value
because FFS’ initiative to recruit the experienced
incumbent workers at lower salaries imposes some risk of
loss of a portion of that workforce’s experience.
AR, exh. 27, SSA Decision, at BATES 565 (emphasis
supplied).
In sum, the record shows that the agency evaluated the
offerors disparately under the staffing and resources
factor, criticizing Fluor’s proposed approach as possibly
involving a risk that it would not be able to recruit the
incumbent workforce, while at the same time failing to
meaningfully consider whether a similar risk was raised by
DZSP’s proposed approach of repeatedly replacing its
exempt employee workforce over the life of the contract.
In light of these considerations, we sustain Fluor’s
protest. Reevaluation after Multiple Corrective Actions.
(Fluor Federal Solutions, LLC
B-410486.9: Jan 18, 2017)
MILVETS asserts that the agency’s reevaluation is
unreasonable because the evaluation differs from prior
evaluations. MILVETS contends that during the first two
rounds of evaluations, MILVETS’s quotation was evaluated
as highly acceptable under both the technical approach and
the management approach factors, yet the agency’s final
evaluation rated the firm’s quotation as only acceptable
under these factors. MILVETS also notes that the firm was
never evaluated as having any disadvantages prior to the
final round of evaluations. MILVETS argues that since the
PWS has not changed from the prior rounds, and MILVETS’s
technical quotation is virtually identical to its prior
submissions, the changes to the evaluation ratings are
improper. For the reasons explained below, we find nothing
improper with the agency’s evaluations.
The fact that a reevaluation varies from a prior
evaluation does not constitute evidence that the
reevaluation was unreasonable. QuinetiQ North America,
Inc., B‑405163.2 et al., Jan. 25, 2012, 2012 CPD ¶ 53 at
13; Sabre Sys., Inc., B‑402040.2, B‑402040.3, June 1,
2010, 2010 CPD ¶ 128 at 5 n.3. The essence of an agency’s
evaluation is reflected in the evaluation record itself,
not in the adjectival ratings or adjectival
characterizations of proposal features as strengths or
weaknesses. QinetiQ North America, Inc., supra; See
Stateside Assocs., Inc., B‑400670.2, B-400670.3, May 28,
2009, 2009 CPD ¶ 120 at 8.
Here, the record demonstrates that the first two rounds of
evaluations (where MILVETS was rated as highly acceptable)
used the same TEP and the same SSA. Contracting Officer’s
Statement at 1. During the third round of evaluations, the
agency assembled a new TEP and assigned a new SSA to the
procurement, which “had no knowledge of the previous
panel’s evaluation ratings, advantages or disadvantages.”
Id. The new panel rated MILVETS’s quotation as acceptable
under the technical and management factors. AR, Tab 32,
Memorandum of Source Selection Decision, Evaluation
Results. For the fourth and final evaluation, the agency
convened the same panel and SSA as the third round of
evaluation, and this same panel again rated MILVETS’s
quotation as acceptable under these two evaluation
factors.
We find nothing unreasonable with the evaluators reaching
different evaluation conclusions, given that the agency
utilized a new evaluation panel and new SSA following the
second round of evaluations. Our Office has long held that
the mere fact that a reevaluation of proposals after
corrective action varies from the original evaluation does
not constitute evidence that the reevaluation was
unreasonable, since it is implicit that a reevaluation can
result in different findings and conclusions. See Marcola
Meadows VA LLC, B-407078.2 et al., Jun. 4, 2013, 2013 CPD
¶ 141 at 8. In this regard, our Office has recognized that
it is not unusual for different evaluators, or groups of
evaluators, to reach different conclusions and assign
different scores or ratings when evaluating proposals,
since both objective and subjective judgments are
involved. See eAlliant, LLC, B‑407332.6, B‑407332.10, Jan.
14, 2015, 2015 CPD ¶ 229 at 10.
While the protester asserts that it was incumbent upon the
SSA to seek some explanation, or otherwise arrive at an
understanding of the differing ratings and evaluation
findings because the contracting officer (CO) has been
involved with this procurement through each of the four
evaluations, we disagree. Our Office has recognized, that
where the same source selection official reviews
conclusions by different evaluators, it is incumbent upon
an SSA when confronted with differing evaluation results
of essentially the same proposal, submitted by the same
offeror, under the same solicitation, to seek some sort of
explanation, or otherwise arrive at an understanding,
especially where there were significant rating differences
in the respective evaluations. eAlliant, LLC, supra
(sustaining the protest where the SSA was required to
provide some explanation as to why the evaluation results
were materially different from those reached in the prior
evaluations).
Under the circumstances here, however, there is nothing in
the record to indicate that the contracting officer was
either a member of the TEP or otherwise associated with
the evaluation of the quotations after the second round of
evaluations. Accordingly, the protester’s assertion that
the agency was required to explain the differing
evaluation results has no merit. See Domain Name Alliance
Registry, B‑310803.2, Aug. 18, 2008, 2008 CPD ¶ 168 at 11
(denying protest that agency reevaluation and technical
ratings were unreasonable because agency did not explain
why evaluations differed between the initial evaluation
and reevaluation undertaken during corrective action);
Impregilo Edilizia S.p.A., B-292468.4, Nov. 25, 2003, 2003
CPD ¶ 216 at 5 n.5 (while protester may disagree with
technical rating change, its disagreement, absent factual
or legal basis indicating why awardee’s rating was
improper, does not present an adequate basis for protest).
(MILVETS Systems Technology,
Inc. B-409051.7, B-409051.9: Jan 29, 2016) (pdf)
IB primarily argues that the RFP did not state that the
competition was limited to small businesses, or precluded
other than small offerors from receiving award. The
protester notes that although the RFP stated for CLIN No.
1 that “[t]he government has significant preference for
small businesses over other than small businesses,” id. at
3, small business size status was not listed as a go/no-go
factor in the solicitation. Instead, the protester argues,
the RFP provided for a best‑value decision based on
consideration of both price and socio-economic status. In
response to the protest, GSA argues that the RFP, read as
a whole, informed vendors that the best-value proposals
would be from small business contractors. Agency’s Request
for Dismissal (Sept. 16, 2014) at 3-4; Agency’s Supp.
Request for Dismissal (Oct. 2, 2014) at 3-4.
Where a protester and agency disagree over the meaning of
solicitation language, we will resolve the matter by
reading the solicitation as a whole and in a manner that
gives effect to all of its provisions; to be reasonable,
and therefore valid, an interpretation must be consistent
with the solicitation when read as a whole and in a
reasonable manner. Alluviam LLC, B-297280, Dec. 15, 2005,
2005 CPD ¶ 223 at 2; Fox Dev. Corp., B-287118.2, Aug. 3,
2001, 2001 CPD ¶ 140 at 2.
Here, we agree with IB that the solicitation was not
specifically set aside for small businesses, and also
agree that an offeror’s small business status was not
listed as a go/no-go evaluation subfactor. Nonetheless, we
agree with GSA that the RFP specifically advised offerors
of the agency’s intent to award contracts to small
businesses. As discussed above, the solicitation stated
that there would be a “significant preference for small
businesses over other than small businesses” and that
there was a “strong preference for small business
participation for CLINS one, two and three.” RFP, SOW, at
3-4. Moreover, the RFP also advised that “[a]chievement of
socio-economic objectives will be designated as an
evaluation factor,” and further advised that the
application of this evaluation factor “will result in
best-value proposals being those from small business
contractors.” Id. at 38.
Although the RFP did not expressly state that other than
small business offerors were precluded from award, we
cannot ignore the solicitation’s statement that the
evaluation preference for small businesses would “result
in best-value proposals being those from small business
contractors.” Id. We conclude that the agency’s
interpretation of the RFP, as reflected in its award
decision, was consistent with the terms of the
solicitation--which provided for a best‑value award
decision under circumstances where only small business
offerors would be found the best value.
Although we find this solicitation language concerning the
best-value selection criteria somewhat unusual, we think
that offerors were on notice that the agency would apply
the socio-economic preference in a manner that would,
effectively, preclude other than small business offerors
from receiving an award. For this reason, we conclude that
the plain language of the RFP, when read as a whole, and
in a manner that gives effect to all its provisions,
demonstrates that the agency’s award decisions were
reasonable and consistent with the terms of the
solicitation.
The protest is denied. (Industries
for the Blind, Inc. B-409528.35, B-409528.36: Dec 3,
2014) (pdf)
The protester bases these challenges solely on the rating
definitions included in the source selection plan, which was not
provided to offerors as part of the RFP. Id. at 4. The protester
does not contend that the SSEB’s technical evaluation was
otherwise unreasonable.
Source selection plans provide internal agency guidelines and,
as such, do not give outside parties any rights. E.g., Walsh
Investors, LLC, B-407717, B-407717.2, Jan. 28, 2013, 2013 CPD ¶
57 at 8 n.6; Mid Pacific Envtl., B-283309.2, Jan. 10, 2000, 2000
CPD ¶ 40 at 6. It is the evaluation scheme in the RFP, not
internal agency documents, such as the source selection plan, to
which an agency is required to adhere in evaluating proposals
and in making the source selection. All Points Logistics, Inc.,
B‑407273.53, June 10, 2014, 2014 CPD ¶ 174 at 10 n.10;
Meadowgate Techs., LLC, B‑405989, B‑405989.3, Jan. 17, 2012,
2012 CPD ¶ 27 at 6 n.7; Synergetics, Inc., B‑299904, Sept. 14,
2007, 2007 CPD ¶ 168 at 8.
Here, Epsilon’s protest allegation, based entirely on
definitions included in the source selection plan, is without
merit. See Comments/Supp. Protest at 4. The protester has not
argued that the technical evaluation was unreasonable or
inconsistent with the RFP’s evaluation criteria. The protester’s
complaint does not allege that the agency violated any
procurement law or regulation. Instead, Epsilon’s objection is
that the SSEB’s findings under the two technical subfactors were
more consistent with the source selection plan’s definition of
an exceptional rating rather than the very good rating assigned.
Id. at 7, 11. As stated above, the source selection plan was not
provided to offerors nor was it incorporated into the
solicitation. Thus, because the source selection plan here is an
internal agency document that does not give rights to outside
parties--contrary to the protester’s suggestions otherwise--this
protest ground is denied. See Park Tower Mgmt. Ltd., B‑295589,
B-295589.2, Mar. 22, 2005, 2005 CPD ¶ 77 at 6 n.5 (denying
challenge based on alleged deficiency in the application of an
agency’s source selection plan because such plans are internal
agency instruction and do not give outside parties any rights).
(Epsilon Systems Solutions, Inc.,
B-409720, B-409720.2: Jul 21, 2014) (pdf)
The agency noted
that the EOHF on VIRGINIA class submarines, which has 10
connectors, is similarly identified by reference number PPD
802-6337554-8.7.1-3, and further concluded that the EOHF on
VIRGINIA class submarines will not fit into the existing hole
cut into the submarine sail to accommodate the EOHF on LOS
ANGELES class submarines (which are the subject of this
procurement). TERP Chair Declaration (July 16, 2008) para. 2.
Accordingly, in the absence of further information provided by
Ultra regarding the size of its “modified hybrid E/O
receptacle,” the agency concluded that Ultra’s proposed
10-connector EOHF would not fit into the existing hole cut into
the submarine to accommodate the EOHF described in the
solicitation, and that Ultra’s proposed approach would likely
require cutting a larger hole. Accordingly the agency assessed a
major weakness to Ultra’s proposal based on its proposed EOHF,
noting that additional engineering efforts would be required due
to “platform integration impacts.” AR, Tab 2, TERP Report, at
36.
In our view, a procuring agency’s technical personnel, who are
most familiar with the government’s requirements, are in the
best position to make judgments regarding the methods for
meeting those requirements, and this Office will not question
those determinations absent a showing that they are
unreasonable. In this regard, we will afford particular
deference to the technical expertise of agency personnel
regarding judgments that involve matters of human life and
safety. E.g., American Airlines Training Corp., B-217421, Sept.
30, 1985, 85-2 CPD para. 356 at 6; Marine Transport Lines, Inc.,
B-224480.5, July 27, 1987, 87-2 CPD para. 91 at 4. Further, an
offeror bears the burden for failing to submit an adequately
written proposal, and a contracting agency is not obligated to
go in search of needed information that the offeror has omitted
or failed to present. E.g. Fluor Daniel, Inc., B-262051,
B-262051.2, Nov. 21, 1995, 95-2 CPD para. 241 at 8.
In its comments responding to the agency report on this matter,
Ultra expresses disagreement with the agency’s conclusions and
asserts that it had no affirmative obligation to show the
dimensions of its “modified hybrid E/O receptacle,” in its
proposal. However, Ultra does not dispute the agency’s
assertions regarding the similarity of its proposed EOHF to the
EOHF on VIRGINIA class submarines, nor does it refute the
agency’s assertion that the 10‑connector EOHF used on VIRGINIA
class submarines will not fit into the existing hole cut to
accommodate the EOHF on the USS Cheyenne, the LOS ANGELES class
submarine on which the ADM is installed.
As noted above, the solicitation specifically directed that, if
an offeror elected to propose a design other than the ADM
design, the offeror “shall explain in their technical proposal
how the design meets the [solicitation requirements].” RFP
amend. 4, at 2. On the record here, as discussed above, we find
no basis to question the agency’s evaluation of weaknesses
flowing from Ultra’s proposed EOHF. Further, we have reviewed
all of the agency’s multiple criticisms of Ultra’s proposal and
find no basis to question any portion of the agency’s technical
evaluation. (Ultra Electronics
Ocean Systems, Inc., B-400219, September 8, 2008) (pdf)
The protesters first complain that the Navy’s evaluators were
not trained, experienced, “operational military personnel” and
that the hearing of these evaluators was not tested before the
product sample tests were conducted. IMLCORP Supp. Protest at 2;
Wattre Protest at 8. The Navy responds that the solicitation did
not require the use of operational military personnel or
identify any other experience requirements for these evaluators
and that, in any event, the SSEB chair is an electrical engineer
with significant experience with acoustic hailing devices. The
Navy also asserts that there was no requirement that the
evaluators’ hearing be tested prior to the product sample
evaluation and that the evaluators reflected the average hearing
that would be expected of actual users of the shipboard devices.
See, e.g., Wattre AR at 10. We find that the protesters’
speculative challenges to the qualifications of the Navy’s
evaluators provide us with no basis to question the agency’s
product sample evaluation. See Philadelphia Produce Mkt.
Wholesalers, LLC, B-298751.5, May 1, 2007, 2007 CPD para. 87 at
5 n.2. Moreover, we have long found that the selection of
individuals to serve as evaluators is a matter within the
discretion of the agency, and, accordingly, we do not review
allegations, such as these, concerning the evaluators’
qualifications or the composition of evaluation panels absent a
showing of possible fraud, conflict of interest, or actual bias
on the part of evaluation officials, none of which have been
alleged or shown here. See Eggs & Bacon, Inc., B-310066, Nov.
20, 2007, 2007 CPD para. 209 at 4; Glatz Aeronautical Corp.,
B‑293968.2, Aug. 10, 2004, 2004 CPD para. 160 at 3 n.1. (IMLCORP
LLC; Wattre Corporation, B-310582; B-310582.2; B-310582.3;
B-310582.4; B-310582.5, January 9, 2008) (pdf)
We have recognized that it is
within the CO's discretion to convene a new evaluation panel
where, for example, the CO, in good faith, determines that such
action is necessary to ensure the fair and impartial evaluation
of proposals, and the record shows that it was not made with the
specific intent of changing a particular offeror's technical
ranking or avoiding an award to that offeror. See Loschky,
Marquardt & Nesholm, B-222606, Sept. 23, 1986, 86-2 CPD para.
336 at 5; Pharmaceutical Sys., Inc., B-221847, May 19, 1986,
86-1 CPD para. 469 at 5. (SOS
Interpreting, Ltd., B-287505, June 12, 2001) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
MILVETS Systems Technology,
Inc. B-409051.7, B-409051.9: Jan 29, 2016 (pdf) |
Fluor Federal Solutions, LLC
B-410486.9: Jan 18, 2017 |
Industries for the Blind, Inc.
B-409528.35, B-409528.36: Dec 3, 2014 (pdf) |
|
Epsilon Systems Solutions, Inc.,
B-409720, B-409720.2: Jul 21, 2014 (pdf) |
|
Ultra Electronics Ocean Systems, Inc.,
B-400219, September 8, 2008 (pdf) |
|
IMLCORP LLC; Wattre Corporation,
B-310582; B-310582.2; B-310582.3; B-310582.4; B-310582.5, January
9, 2008 (pdf) |
|
W
R Systems, Ltd., B-287477; B-287477.3, June 29, 2001 |
|
SOS
Interpreting, Ltd., B-287505, June 12, 2001 |
|
U.
S. Court of Federal Claims - Key Excerpts |
2. The Expanding Role of SSPs in Judicial Review of Procurements
Historically, the purely internal use of
[Source Selection Plan] SSPs led the Claims Court to conclude that
“when rules and regulations are promulgated for the benefit of the government and no
one else, the other party to a contract cannot complain if such regulations are not
complied with.” C & L Constr. Co. v. United States (C & L), 6 Cl. Ct. 791, 804 (1984)
(citing Perkins v. Lukens Steel Co. (Lukens Steel), 310 U.S. 113, 129, (1940); Hartford
Accident & Indemnity Co. v. United States (Hartford Accident), 130 Ct. Cl. 490, 492-94,
(1955)). The court and the “GAO [have] repeatedly held that [source selection] plans
generally do not give outside parties any rights and, thus, provide no basis for departing
from the requirements of a solicitation….[and thus] it appears the Source Selection Plan
has little, if any, bearing in defining the rights of the parties under the Solicitation.”
Mantech, 49 Fed. Cl. at 67 (internal citations to GAO decisions omitted). The court has
added that “the elements of a source selection plan are not considered to provide
procedural requirements that are binding on a procuring agency.” Huntsville Times Co.
v. United States, 98 Fed. Cl. 100, 107 (2011) (citing Mantech, 49 Fed. Cl. at 67). The
intended use of a SSP as an internal agency resource appears to have influenced the
court’s restrictive interpretation of its legal effect. Manson Constr. Co. v. United States,
79 Fed. Cl. 16, 19 (2007) (“Internal agency documents that are not distributed as part of a
solicitation do not themselves confer rights to potential offerors.”); see also Lincoln
Servs. Ltd. v. United States (Lincoln Services), 230 Ct. Cl. 416, 428-30 (Ct. Cl. 1982)
(noting that an agency’s deviation from its own internal guidance to be arbitrary and
capricious if such deviation results in prejudicial error).
Plaintiff asserts that an agency’s departure from the evaluation criteria and
procedures provided by the SSP “can undermine the rationality of the ultimate source
selection decision.” Pl.’s Supp. Br. 5-6 (citing USfalcon, Inc. v. United States, 92 Fed.
Cl. 436, 452-456 (2010)). Plaintiff asserts that the VA’s departure from the SSP in the
corrective action source selection decision prejudiced Progressive and was arbitrary,
capricious, and contrary to law. Id. at 7.
Relying on a series of cases, defendant argues that the VA’s deviation from the SSP does not furnish a ground for Progressive to protest. See Def.’s Suppl. Br. 2-3
(citing Allied Tech. Group, Inc. v. United States, 94 Fed. Cl. 16, 41 (2010); ManTech, 49
Fed. Cl. at 67; Atlantic Diving Supply, Inc. v. United States, 107 Fed. Cl. 244, 263
(2012)). Defendant claims that “noncompliance with the terms of an SSP cannot serve as
the basis for a bid protest unless the SSP is incorporated into the solicitation.” Id.
As the case law reveals, the court has
looked to prepared SSPs in certain limited circumstances. In Pikes Peak Family Housing, LLC v. United States, 40 Fed. Cl. 673, 678 (1998),
the court found three unexplained inconsistences between the SSP and the procurement.
The inconsistencies included a misapplication of the SSP’s definitions for rating criteria,
a failure to categorize the proposals according to their acceptability, and prolonged delays
in notifying offerors excluded from the competitive range. Id. at 678-79. These
discovered inconsistences prompted the court to allow the AR to be supplemented with
additional documents so that the court could perform its review. Id. at 678.
The court , however, exercises care not to review a SSP as it would a solicitation.
Rather it looks to the SSP to evaluate the rationality of the agency’s departure from its
procurement plan. The court may consider whether the deviations from the SSP are
reasoned departures. USfalcon, Inc., 92 Fed. Cl. at 454 (“Because the SSA relies on the
evaluators working for him to follow source selection plan mandates, departures from the
plan could undermine the rationality of the ultimate source selection decision.”).
When the AR reveals a disparity between the SSP and the solicitation, the court
will examine the record further to find the agency’s expressed rationale for the
divergence or to understand the circumstances that led to the change in the evaluation
criteria or procedures. Such variance is not necessarily indicative of an irrational agency action. As the court observed in USfalcon, Inc., 92 Fed. Cl. at 454, “if no reason is given
for departing from a source selection plan….[the] departure could be due to error and the
resulting ratings [might] be different than the evaluators intended.” While the court noted
that an agency’s failure to follow the SSP could be shown in certain circumstances to
have been irrational, it found in that particular case that the agency had complied with the
evaluation procedures and criteria set forth by the SSP. USfalcon, Inc., 92 Fed. Cl. at
462; but see Fort Carson Support Services v. United States, 71 Fed. Cl. 571, 592-93
(2006) (stating that ‘[u]nless an element of the SSP is expressly waived by an official
with the power to do so, via a valid, articulated reason, the failure to follow that element
is, by its very nature, an arbitrary act.”); United Int'l Investigative Servs. v. United States,
41 Fed. Cl. 312, 314-15 (1998), aff’d, 194 F.3d 1335 (Fed. Cir. 1999) (table) (finding that
the agency’s deviation from the internal procedures “deprived [the] plaintiff of the
opportunity to have its proposal considered fairly and honestly”); Beta Analytics
International, Inc. v. United States, 67 Fed. Cl. 384, 407-408 (2005) (looking to the
procedures set forth in the SSP, the court found that an agency’s departure from those
procedures resulted in unequal treatment of the protestor.) The cases show that the court
has considered deviations from the SSP that cast doubt on either the rationality or the
fairness of the procurement process.
Here, the court relies upon more than the agency’s deviation from the procedures
set forth in the SSP to conclude that it cannot make a finding that the VA’s corrective
action source selection decision was a rational one. The court makes this conclusion
based on the agency’s inability to describe its own evaluation procedures in a clear or
consistent manner.
In this bid protest, the contracting officer offered an affidavit describing evaluation
procedures that differed from those set forth in the corrective action source selection
decision, Compare Suppl. Hurt Decl. ¶ 40 (ECF No. 41), with Tab 9, AR 125, and Tab
59, AR 2370-71, and at oral argument, the VA struggled to explain the difference
between the procedures in the SSP and the procedures followed to make the corrective
action source selection decision. See Hr’g Tr. 23. The corrective action source
selection decision itself made no mention of how the agency
reevaluated the proposal. Nor can the court reconcile the
rationale offered in the corrective action source selection
decision with the contracting officer’s explanation.
Although the court may uphold a decision of less than ideal clarity if the agency’s
path may reasonably be discerned, the marked inconsistencies between the evaluation
procedures described in the SSP, the corrective action source selection decision, and in
the contracting officer’s affidavit do not permit the court to follow the agency’s path. Here, the agency appears to have adopted different procedures from those set forth
in the SSP—without explanation as to why or how it did so. Compare Tab 9, AR 125,
with Tab 45, AR 2015-16; Tab 59, AR 2370. Thus the court looks to the SSP, at defendant’s invitation, to evaluate the
rationality of this procurement process. See Avtel Servs., 70 Fed. at 216-17; see Def.’s
Mot. 6-8.
3. The VA Misstated the Evaluation Procedures Set Forth in the SSP in
Its Corrective Action Source Selection Decision
Defendant relies on the SSP to show that the agency contemplated both
establishing a competitive range and holding discussions. Def.’s Mot. 18. Defendant
further relies on the SSP to justify the contracting officer’s position on price analysis.
Def.’s Mot. 8-9; Hr’g Tr. 78 (citing Tab 45, AR 2022-24; Tab 59 AR 2381-85), 108.
But, the VA’s reevaluation of technical capability did not comport with the
evaluation methodology set forth in the SSP. See Tab 9, AR 125. As provided in the
SSP, only past performance, veterans preference, and price (steps two through five),
would receive reevaluation by the agency. Tab 9, AR 125; see Pl.’s Mot. 23-24.
Addressing the agency’s deviation from the SSP, defendant explained that the SSP
contained a typographical error and that “[t]he contracting officer meant to indicate that
the technical capacities, as well as past performance…would be part of that iterative
process.” Hr’g Tr. 23; Def.’s Mot. 5 n.3. But, the Solicitation did not address the
reevaluation of technical capability. Tab 11, AR 214-17.
The contracting officer referenced the SSP in her description of the TET’s
evaluation methods. She stated that “the first step required by each TET member [in
evaluating the revised final proposals] was an evaluation of the technical capability of
each offeror.” Suppl. Hurt Decl. ¶¶ 39-40 (ECF No. 41). This described process differs
from the iterative process described in the SSP—which did not provide for the
reevaluation of technical capability. See Tab 9, AR 125. The additional steps the
contracting officer described were incongruent with the procedures found in the SSP and
with the corrective action source selection decision. Compare Suppl. Hurt Decl. ¶ 40,
with Tab 9, AR 125, and Tab 59, AR 2370.
Progressive asserts that the VA acted in contravention of the SSP by revisiting the
technical capability factor after conducting the initial evaluation. Pl. Mot. 23-24 (citing
Tab 9, AR 125; Tab 45, AR 2015). Essentially, Progressive asks the court to disallow
any deviation from the evaluation criteria and methods set forth in the SSP, in the
agency’s reevaluation of the offerors’ technical capability as part of its corrective action.
See Tab 59, 2376. Defendant maintains the position that VA “did not deviate from the SSP by
reevaluating the technical capability factor after the competitive-range determination.”
Def.’s Supp. Br. 4. The VA explained at oral argument that the disparity between the
evaluation procedures of the SSP and those documented in the corrective action source
selection decision “is . . . an issue of form over substance.” Hr’g Tr. 23. Defendant
points to the sentence in the SSP addressing the possibility of reevaluating technical
capability after the competitive range determination: “In the event that additional
capability information is desired before making a source selection, discussions [might] be
held for those offerors with a realistic chance for award (competitive range).” Def.’s
Suppl. Br. 5 (citing Tab 9, AR 125). Defendant insists that the placement of that sentence
before the instruction that only past performance, veterans preference, and price (steps
two through five) would receive agency reevaluation makes clear that the phrase “[s]teps
two through five” is a typographical error. Def.’s Suppl. Br. 5 (citing Tab 9, AR 125).
Defendant’s explanation for the disparity between the contracting officer’s
characterization of the five-step evaluation process in the corrective action source
selection decision—which was derived purportedly from the SSP—and those described
in the SSP is summary and unsupported. Compare Suppl. Hurt Decl. ¶ 40, with Tab
9, AR 125, and Tab 59, AR 2370. Although the contracting officer states in her supplemental affidavit that the TET’s
first step in reevaluating proposals was to assess the offerors’ technical capability, Suppl.
Hurt Decl. ¶ 40 (ECF No. 41), the first step described in the corrective action source
selection decision was “a determination of the acceptability of each offer by evaluating
the consistency of each Offeror’s promises with the terms and conditions in the RFP.”
Tab 59, AR 2370. The corrective action source selection decision also described
technical capability comprised of: (1) individual evaluations; and (2) “an overall group
consensus on findings leading to a competitive range.” Id. The two-phased process
identified in the corrective action source selection decision does not include a
reevaluation, but instead incudes a fifth procedural step involving “comparisons among
Offerors, [and] trading off expected value against price in order to determine the best
value source selection.” Id.15 Moreover, the corrective action source selection decision
misstated the evaluation procedures of the SSP and failed to set forth the rationale for
reevaluating the proposals. The evaluation procedures that were detailed in the corrective
action source selection decision also differed from what was described in the contracting
officer’s supplemental affidavit. Looking to the SSP to understand how the VA arrived at its corrective action
source selection decision, the court finds the explanation for the disparity between the
evaluation procedures as described in the contracting officer’s affidavit and those found
within the corrective action source selection decision to be wanting. Compare Suppl.
Hurt Decl. ¶ 40 (ECF No. 41), with Tab 9, AR 125, and Tab 59, AR 2370. The agency’s
own inability to describe, with consistency, the evaluation process it used is tellingly
indicative of the lack of clarity in the record as to this aspect of the procurement. Given
the inadequacy of the agency’s explanation, the court cannot make a finding that the
agency acted rationally in its evaluation of the proposals. (Progressive
Industries, Inc. v. U. S. and Irish Oxygen, Co., No.
14-1225C, December 6, 2016)
V. Regulatory Standard for CE Newspaper
Contracting
This procurement is governed by 32 C.F.R. pt. 247 (2010),
“Department of
Defense Newspapers, Magazines and Civilian Enterprise
Publications.”4 It is
important to note that contracting for CE newspapers is not
governed by the
Federal Acquisition Regulation (FAR) or the Defense Federal
Acquisition
Regulation Supplement (DFARS). See 32 C.F.R. pt. 247 App. B(J)(2)
(stating
that “CE contracts are not subject to the FAR or DFARS, because
they do not
involve the expenditure of appropriated funds”). For this
reason, the arguments of
the parties that reference specific FAR provisions, particularly
those that set
standards for communications between offerors and a procuring
authority, are largely unhelpful.6 In general, the government
must “ensure that the [procurement]
process is objective and fair.” 32 C.F.R. pt. 247 App. B(J)(8)(c).
The [Letter Request for Proposal] LRFP in this procurement references not the applicable
regulation, but
Department of Defense Instruction (DODI) 5120.4 (dated June 16,
1997), a
document which largely replicates the standards and information
contained in 32
C.F.R. pt. 247. The governing regulation and DODI 5120.4 each
include an
attached sample source selection plan and a sample evaluation
scoring sheet, which
are similar if not identical in content. Compare 32 C.F.R. pt.
247 App. B Atts. 1-2
with DODI 5120.4 Enc. 4 Atts. 1-2. The parties disagree as to
whether the
numerical scoring system set forth in the sample source
selection plan and scoring
sheet is required by the regulation, or is simply provided as an
example. The court
agrees with defendant and TVP that the numerical scoring system
offered as an
example by the regulation provides guidance to the Army, but
does not impose
this, or any other, numerical scoring system as a requirement
for this procurement.
VI. The Source Selection Plan Contained Two
Conflicting Sets of
Evaluation Criteria, Conflicting Weighting Schemes, and Was Not
Approved in Accordance with the Governing Regulation
According to the introduction to the
[Source Selection Plan] SSP,
this document “describe[d] the
organization, responsibilities, evaluation process, and
instructions to the evaluation
committee for the competitive award of a civilian printer for
the civilian enterprise
(CE) installation newspaper, hereinafter referred to as the
Redstone Rocket.” AR
Tab 4 at 3. The purpose of the SSP was to “to ensure an
impartial; equitable, and thorough evaluation of proposals;
ensure that the technical
evaluation findings provide for the selection of the offer most
advantageous to the
Government; and document all aspects of the evaluation and
decision process.” Id.
According to the governing regulation, the [evaluation
committee] EC must follow the SSP, because the
SSP “serve[s] as a guide for the personnel involved and ensure[s]
a fair and
objective process and a successful outcome.” 32 C.F.R. pt. 247
App. B(J)(8)(b)-
(9).
(sections deleted)
In the end, this analysis of the
differences between Evaluation Criteria Set A
and Evaluation Criteria Set B is disturbing. The evaluation
team, the EC, was
given two very different sets of evaluation criteria, and it is
difficult to imagine
how such an evaluation process could reconcile the conflicting
descriptions of the
evaluation criteria and apply these evaluation criteria with any
degree of
uniformity or accuracy. Indeed, proceeding with an internally
inconsistent source
selection plan appears to the court to be an irrational
enterprise, not a rational one.
It is also disturbing to note that the EC relied heavily on the
descriptions of subfactors
of criteria found in Set B, when Set B differed so significantly
from the
descriptions of evaluation criteria sub-factors advertised in
the LRFP. See CACI
Field Servs., Inc. v. United States, 13 Cl. Ct. 718, 728 (1987)
(noting that if the
government “utilized the evaluation criteria listed in the SSP
rather than the RFP,
and if the SSP evaluation factors were significantly different
from the RFP
evaluation factors (in terms of content and/or relative
importance), then [the
protestor] would be entitled to relief assuming that it was
prejudiced by such
actions.”), aff’d, 854 F.2d 464 (Fed. Cir. 1988). The court now
turns to another
flaw in the rating procedures set forth in the SSP.
B. Differing Weighting Schemes
As stated in the background section of this
opinion, the weighting scheme in
the LRFP informed offerors that Technical Capability and
Services Offered were
approximately equal in weight, Past Performance had
approximately half the
weight of Technical Capability or Services Offered, and
Management Approach
had less weight than Past Performance. AR Tab 5 at 3. The SSP
has three
weighting pronouncements, all of them distinguishable from the
weighting scheme
announced in the LRFP. First, in what appears to be the
weighting scheme to be
applied to Evaluation Criteria Set A,9 the SSP states that:
Technical and Production Capability and
Services and Items Offered are approximately equal in
importance. Technical and Production Capability and
Services and
Items Offered are each approximately twice as important
as Past Performance. Past Performance is approximately
twice as important as Management Approach.
AR Tab 4 at 7. Aside from a slight
difference in describing the weight of the
Management Approach rating, this pronouncement is roughly
consistent with the
LRFP.
Next, however, within the text of the
Services Offered evaluation criteria,
Set A announces that the sub-factors announced in Services
Offered (version Set
A) are “listed in order of relative importance.” Id. at 8. The
same sub-factors in
the LRFP are not similarly designated, AR Tab 5 at 2, and many
offerors with
experience in FAR-governed procurements would assume that the
listed Services
Offered sub-factors were equal in importance, see, e.g., Bean
Stuyvesant, L.L.C. v.
United States, 48 Fed. Cl. 303, 321 (2000) (“In the absence of a
statement of the
relative importance of the factors or subfactors, [the FAR
instructs that] each factor
or subfactor must be weighed equally.” (citing Isratex, Inc. v.
United States, 25 Cl.
Ct. 223, 229 (1992))). Finally, Set B contains an assignment of
weight to the four
evaluation factors, so that the percent weighting is as follows:
Technical
Capability (40%); Services Offered (30%); Past Performance
(20%), and
Management Approach (10%). AR Tab 4 at 11-13. The court notes
that most
mathematicians would dispute that 40% is approximately equal to
30%, and finds
that Set B’s weighting scheme varies significantly from the
weighting scheme set
forth in the LRFP.
Having thus discovered that the SSP
contains weighting schemes that differ
from the scheme presented in the LRFP, the court cannot
immediately determine
the gravity of this error. The court found no evidence of
mathematical scoring in
the administrative record, and defendant’s counsel agreed that
there is no evidence
before the court that “numerical scoring” was utilized by the
Army in this
procurement. Oral Arg. Tr. at 53. Nor has the court found any
evidence that the
EC or the SSA adhered to, or even applied, the weighting scheme
presented to offerors in the LRFP. To the extent that the two
competing proposals for this CE
newspaper contract each had a substantial chance of award, as
discussed below, the
court finds the absence of any evidence of the application of
the weighting scheme
set forth in the LRFP troubling.
(sections deleted)
VII. Evaluation Errors Committed by the
Evaluation Committee
In addition to the creation of a flawed SSP, the failure to get
the SSP
approved before offers were received on August 12, 2010, and the
failure to
document any weighting of the evaluation criteria ratings, this
court has found
significant errors in every area of the consensus evaluation
produced by the EC.
The court turns first to Technical Capability, one of the two
most important
evaluation criteria.
(sections deleted)
IX. Significantly Flawed Award Decision
and Prejudice to the Protestor
The court has closely examined this
procurement and found (1) procedural
errors in establishing the SSP; (2) a confusing and internally
inconsistent SSP; (3)
ratings that were based on evaluation criteria different from
those stated in the
LRFP; (4) ratings that were irrational or were in violation of
the governing
regulation; and (5) a failure to apply the weighting scheme for
evaluation criteria
set forth in the LRFP. These errors are significant, and the
court finds that the
decision to award this contract to TVP was “‘arbitrary,
capricious, an abuse of
discretion, or otherwise not in accordance with law.’” Banknote,
365 F.3d at 1350-
51 (quoting Advanced Data Concepts, 216 F.3d at 1057-58). The
SSA’s award
decision, although rational, in the main, as to the different
ratings assigned to
Huntsville and TVP in Management Approach and Services Offered,
was arbitrary
and capricious in the remainder of its assessment of proposals.
These errors are
too significant to disregard as harmless or de minimis errors.
(sections deleted)
XI. Nature of the Permanent Injunction
When the injunctive relief factors are
weighed together, the court concludes
that a permanent injunction must issue. The award of Contract
No. W9124P-10-RA001
must be set aside. The court has considered a variety of
solutions to the
hardships faced by Huntsville, TVP and the Army in the wake of a
permanent
injunction. In the court’s view, the injunction must be timed to
take effect on May
23, 2011. This timing should allow for an orderly transition and
a fair opportunity
to compete for the remaining six months of the first year of
contract performance
(and the follow-on option years) improperly awarded to TVP, if
the Army chooses
to award a new contract for the publication of the Redstone
Rocket.
The court does not set any restrictions on the Army’s options
for the
re-solicitation of proposals, or for the re-evaluation of
proposals received under
Letter Request for Proposals W9124P-10-R-A005. The court notes,
however, that
a related protest would be reviewed under the standards
referenced in this opinion.
The Clerk’s Office will assign a related protest to the
undersigned. (The Huntsville
Times Co. Inc. v. U. S. and Tennessee Valley Printing Co., Inc.,
No. 10-812C, March 31, 2011) (pdf)
C. The Relevance of Source Selection Plans
to Court Review
As the ratings used in the technical evaluation of each
offeror’s proposal, and their
definitions, were provided in the SSEP rather than the
Solicitation,21 a consideration of the
relevance of a source selection plan to our Court’s review is in
order. As the government notes,
see Def.’s Br. at 33-34, our Court has acknowledged the
long-standing rule of the GAO that
source selection “plans generally do not give outside parties
any rights.” ManTech Telecomms.
& Info. Sys. Corp. v. United States, 49 Fed. Cl. 57, 67 (2001).
The rule traces back to a decision
in which the GAO analogized such plans to directives and other
internal agency regulations, and
found that failure to comply with such an “internal instruction”
was no “basis for questioning the
validity of [an] award since an internal agency guideline does
not have the force and effect of
law.” Robert E. Derecktor of R.I., Inc., 84-1 CPD ¶ 40, 1984 WL
43785, at *4 (Comp. Gen. Feb.
2, 1984).
Thus, unlike the treatment of a statute, the prejudicial
violation of a source selection plan
is not, per se, a ground for a protest. Since the agency is free
to change or waive its internal
policies, under the GAO approach “agencies are permitted to
deviate from their stated evaluation
plans so long as the agency’s evaluation is reasonable.” Textron
Marine Sys., 91-2 CPD ¶ 162,
1991 U.S. Comp. Gen. LEXIS 967, at *9 n.3 (Comp. Gen. Aug. 19,
1991). On the other hand,
adherence to a source selection plan may result in an
unreasonable procurement decision and
thus a protest that is sustained -- for instance, when an
evaluation methodology blurs all technical
distinctions and effectively makes a lesser important price
factor decisive. See Trijicon, Inc., 71
Comp. Gen. 41, 91-2 CPD ¶ 375, 1991 U.S. Comp. Gen. LEXIS 1245,
at *10-12 (1991); see also
The MIL Corp., 2005 CPD ¶ 29, 2004 U.S. Comp. Gen. LEXIS 283, at
*9-11 (Comp. Gen. Dec.
30, 2004) (finding evaluation unreasonable when an unfavorable
rating was given to an offeror
for a past performance subfactor concerning which the offeror
had no relevant information). To
the GAO, what is relevant is what an agency actually did in its
evaluation, not what it may have
intended to do -- unless the intention was expressed in the
Solicitation itself. See Frank E. Basil, Inc., 69 Comp. Gen.
472, 90-1 CPD ¶ 492, 1990 U.S. Comp. Gen. LEXIS 518, at *5-6
(1990)
(holding that “agencies do not have the discretion to announce
in a solicitation that one
evaluation plan will be used and then follow another in the
actual evaluation,” unless offerors are
informed and given the “opportunity to structure their proposals
with the new evaluation scheme
in mind”).
This Court has developed a refinement of
the GAO approach, which recognizes that the
act of choosing an evaluation methodology is itself a
discretionary decision in the evaluation
process, and which takes stock of the natural and logical
consequences of this act. See, e.g., Fort
Carson, 71 Fed. Cl. at 592-93; Beta Analytics, 67 Fed. Cl. at
399, 407. The FAR does not
require that agencies use any particular rating method, see 48
C.F.R. § 15.305(a), or disclose
rating methods in the solicitation, except for the “approach for
evaluating past performance.” 48
C.F.R. §§ 15.304(d), 15.305(a)(2)(ii). No law or regulation
appears to prevent an agency’s
changing from one undisclosed rating method to another, and in
that respect a source selection
plan is similar to general guidelines or internal policies which
are adopted by an agency. But
source selection plans differ from these other internal policies
in a significant respect -- as,
presumably, when an agency adopts a source selection plan for a
particular procurement, its
officials are employing their expertise to select a rating
methodology they believe will best meet
the agency’s needs that are the subject of the specific
solicitation.
In a negotiated procurement under the FAR,
the SSA, acting on behalf of the agency
head, is ultimately responsible for the evaluation and the best
value decision. 48 C.F.R.
§§ 15.303(b), 15.308. He must assemble an “evaluation team”
which is “tailored for the
particular acquisition” and possesses the “expertise to ensure a
comprehensive evaluation of
offers.” 48 C.F.R. § 15.303(b)(1). He must ensure that the
agency is consistent in the
information requested of offerors, and that “proposals are
evaluated based solely on the factors
and subfactors contained in the solicitation.” 48 C.F.R. §
15.303(b)(3)-(4). And although “the
SSA may use reports and analyses prepared by others, the source
selection decision shall
represent the SSA’s independent judgment.” 48 C.F.R. § 15.308.
On this last point, nothing
prevents the SSA from basing his judgment upon the evaluations
and ratings of others, and
indeed the provision cited expressly allows the SSA’s decision
to be based on “business
judgments and tradeoffs made or relied on by the SSA.” Id.
(emphasis added).
Since the SSA is responsible for the source
selection decision, and will want to efficiently
make use of the talents and expertise of the evaluation team,
the contents of a source selection
plan guiding his subordinates would naturally be his concern.
For Department of Defense
procurements, including those of the military departments, the
Defense Federal Acquisition
Regulation Supplement (“DFARS”) requires that for “high-dollar
value” and certain other
acquisitions, the SSA “shall approve a source selection plan
before the solicitation is issued.” 48
C.F.R. § 215.303(b)(2).22 A mandatory procedure, see 48 C.F.R.§
202.101 (definition for “Procedures, Guidance, and Information”
(“PGI”)), requires that this source selection plan
include “[a] description of the evaluation process, including
specific procedures and techniques
to be used in evaluating proposals.” PGI § 215.303(b)(2)(C)(3).
Thus, at least where procedures
similar to the Defense Department’s are followed, the source
selection plan is drawn up before
any proposals are seen by evaluators, and is expressly approved
by the SSA.23 The evaluation
procedures and techniques embodied in these plans may vary, of
course, given the particular
needs being addressed in a procurement, and could employ
detailed and objective rules, on the
one hand, or more subjective and deferential standards, on the
other. But the important point for
our purposes is that once the SSA approves a particular source
selection plan, he should expect,
unless informed to the contrary, that it has been followed.
Thus, mandatory instructions that
evaluators “must” and “shall” rate proposals a certain way are
fixed among the foundational
assumptions of the SSA.
Because the SSA relies on the evaluators
working for him to follow source selection plan
mandates, departures from the plan could undermine the
rationality of the ultimate source
selection decision. He might believe, for instance, that a
certain rating was produced by one
formula, when in fact another formula was used by evaluators,
creating a disconnect between his
decision and the underlying facts. Now, it could be the case
that the formula used was better
adapted to the needs of the agency than the original one
selected -- but it is also possible that the
change in formula was an unintended error or, perhaps worse,
reflected a (conscious or
unconscious) reaction to the actual features and qualities
presented by a particular proposal.
Thus, the failure of evaluators to follow the specific
procedures and techniques mandated by a
source selection plan, to the prejudice of a protester, could be
evidence of an erroneous or biased
evaluation. See Fort Carson, 71 Fed. Cl. at 592-93. Any such
suspicions could be dispelled by
records showing that the departure from the plan was consciously
chosen prior to the viewing of
proposals, or articulating a rational reason for the departure.
Although an agency may have wide
discretion in selecting the procedures and techniques to be used
in an evaluation, provided these
have some possible relation to the relevant factors and
subfactors, when its evaluators choose to
depart from these after being exposed to offerors’ proposals,
the integrity of the process would
demand that some reason be documented. And to ensure that there
is no disconnect between the
SSA’s decision and its underlying assumptions, the choice to
depart must have been made known
to him so that it may receive at least implied approval.
There are, of course, many good reasons why
a source selection plan may be changed
midstream, and documentation of these is but a minor burden. The
record in this case provides
one example of this, as the SSEP was changed to eliminate a
consideration from the ratings
definitions for the SBPP factor because this consideration was
not contained in the Factor
elements described in the Solicitation. AR at 10447-48. This
change was memorialized in a
contemporaneous memorandum from the CO, id., and resulted in a
revised SSEP, AR at 10449-
98, that was expressly approved by the SSA. See AR at 10450. In
other circumstances, the
evaluators may conclude that the plan’s definitions are too
rigid or otherwise not well-suited for
the factors they are judging. But if no reason is given for
departing from a source selection plan
(or the departure is not highlighted to allow the SSA to
articulate a reason), a departure could be
due to error and the resulting ratings may be different than the
evaluators intended. Or, in
extreme (and, the Court hopes, rare) cases, the departure could
have been intended to benefit a
particular offeror.24 Particularly when the SSA bases his
ultimate decision not on the proposals
themselves but on briefings in which the ratings are presented
as the inputs for his calculus, an
unjustified departure from a source selection plan may rob this
ultimate decision of its rational
basis.
Source selection plans could be relevant to
court review for other reasons. The regularity
presumed by an SSA may also be presumed by the court. Thus, if
the source selection plan
required a certain event to take place, such as a consensus
meeting, the presumption of regularity
will support that event’s occurrence, absent other record
evidence. Cf. Beta Analytics, 67 Fed.
Cl. at 397 (finding no presumption because there was no plan
requirement) (citing Tecom, Inc. v.
United States, 66 Fed. Cl. 736, 769-70 (2005)). Under this
presumption, “predicate acts that
were required of public officials could be presumed upon proof
of their natural results.” Tecom,
66 Fed. Cl. at 769. The presumption can apply to substantive
matters, such as the inference that
a particular finding was made to support a rating, see Beta
Analytics, 67 Fed. Cl. at 400, or to
procedural matters -- for instance when a plan articulates the
circumstances under which fewer
than all proposals would get a second review. Cf. id. at 407
(finding no plan provision justifying>
a reevaluation for just one offeror). In the latter case, a
decision that at first glance might appear
to treat offerors unequally would instead be seen as the fair
application of a preexisting rule
(under which not every offeror qualified for the particular
treatment).
A source selection plan may also be the
source of a restriction on evaluators, foreclosing
certain actions. Thus, an action that might initially appear to
be fair procedurally, such as a rescoring
of all proposals, could be the ground for a successful protest
when such reevaluations are
specifically forbidden by the source selection plan. But in the
absence of such a restriction --
even if the reevaluation resulted in a change in ordering or
ranking of offerors -- the action would not be objectionable, so
long as the offerors were given equal treatment. See Fort
Carson,
71 Fed. Cl. at 599.
And, of course, when a source selection
plan is the source of the ratings definitions that
are followed in the course of evaluating offerors, it figures
prominently in court review of a
procurement decision. This review “entails identifying the
judgments made by the relevant
officials and verifying that the relevant information was
considered, the relevant factors were
employed, and a satisfactory explanation was articulated.” Id.
at 592 (citing Overton Park, 401
U.S. at 416 and Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43). A
procurement decision’s
explanation necessarily includes the ratings assigned to
proposals. When a rating, given its
definition, cannot be squared with an actual proposal, the
decision to assign that rating is
arbitrary. But since courts are not to second guess
discretionary determinations that are technical
and subjective in nature, see E.W. Bliss, 77 F.3d at 449, the
less objective the rating criteria
happen to be, the harder it is for a protester to establish that
a rating decision was arbitrary. See
Beta Analytics, 67 Fed. Cl. at 399.
With these various ways in which a source
selection plan may be relevant to court review,
it is little wonder that the source selection plan is identified
in our rules as among the “relevant
core documents” of the administrative record which may be
produced early to expedite a case.
RCFC App. C, ¶ 22(b). (USfalcon,
Inc., v. U. S., No. 09-602c, May 21, 2010) (pdf) |
|
U.
S. Court of Federal Claims - Listing of Decisions
|
For
the Government |
For
the Protester |
USfalcon, Inc., v. U. S., No.
09-602c, May 21, 2010 (pdf) |
Progressive Industries, Inc. v. U. S.
and Irish Oxygen, Co., No. 14-1225C, December 6, 2016 |
|
The Huntsville
Times Co. Inc. v. U. S. and Tennessee Valley Printing Co., Inc.,
No. 10-812C, March 31, 2011 (pdf) |
|
|