Clarifications/Discussions and Awardee's Past
Performance
SOC also complains that the agency was required to engage
in clarifications or discussions with respect to the
deficiencies in SOC's proposal regarding the PSC license
and key personnel experience issues. We disagree.
As noted above, this task order procurement was conducted
as a competition between [Department of State's Worldwide
Protective Services II] WPS II contract holders and was
subject to the provisions of Federal Acquisition
Regulation (FAR) subpart 16.5, which does not establish
specific requirements for conducting clarifications or
discussions. Technatomy Corp., B-411583, Sept. 4, 2015,
2015 CPD ¶ 282 at 7. The solicitation here stated that the
agency intends to evaluate proposals and award "without
discussions with Offerors, (except clarifications as
described in FAR 15.306(a), if required)." TORFP § M, at
5. Where, as here, however, an agency conducts a task
order competition as a negotiated procurement, our
analysis regarding fairness, will, in large part, reflect
the standards applicable to negotiated procurements.
Technatomy Corp., supra.
Section 15.306 of the FAR describes a range of exchanges
that may take place when an agency decides to conduct
exchanges with offerors during negotiated procurements and
states that clarifications are limited exchanges between
an agency and an offeror that may occur where contract
award without discussions is contemplated. FAR §
15.306(a). An agency may, but is not required to, engage
in clarifications that give offerors an opportunity to
clarify certain aspects of proposals or to resolve minor
or clerical errors. Id. However, clarifications may not be
used to cure proposal deficiencies or material omissions,
materially alter the technical or cost elements of the
proposal, or revise the proposal. Superior Gunite,
B-402392.2, Mar. 29, 2010, 2010 CPD ¶ 83 at 4.
Here, any exchanges between the agency and SOC regarding
the license and key personnel would have concerned the
acceptability of SOC's proposal and would have required
that SOC revise its proposal in some manner to cure the
proposal deficiencies or material omissions. Accordingly,
SOC could not have corrected its proposal through
clarifications.
SOC further asserts that the agency was required to hold
discussions with SOC because its price was so much lower
than the awardee's. An agency need not conduct discussions
with a technically unacceptable offeror. Electronic
Systems USA Inc., B-246110, Feb. 14, 1992, 92-1 CPD ¶ 190.
Further, the solicitation, expressly advised that the
agency contemplated making award without discussions.
TORFP § M at 5. An agency's decision not to initiate
discussions is a matter we generally will not review.
Tribalco, LLC, B-414120, B-414120.2, Feb. 21, 2017, 2017
CPD ¶ 73 at 6. (SOC LLC
B-415460.2, B-415460.3: Jan 8, 2018)
DBSI complains that the agency acted unreasonably by not
seeking clarifications from the firm with regard to its
legally binding teaming agreement. In support of this,
DBSI points to its proposal, which states "Please see the
following pages for a fully executed true and authentic
copy of our legally binding agreement with [DELETED]."
Agency Report (AR), Tab 5, DBSI Proposal, Vol. I-19.
Rather than include the proper agreement, however, DBSI
states that its proposal mistakenly included the
confidentiality agreement. According to DBSI, the agency
should have known that DBSI erroneously included the wrong
agreement, and should have permitted the firm to clarify
its proposal by allowing the firm to substitute the proper
agreement with the mistaken agreement.
FAR § 15.306 describes a spectrum of exchanges that may
take place between a contracting agency and an offeror
during negotiated procurements. Clarifications are limited
exchanges between the agency and offerors that may occur
when contract award without discussions is contemplated;
an agency may, but is not required to, engage in
clarifications that give offerors an opportunity to
clarify certain aspects of proposals or to resolve minor
or clerical errors. FAR § 15.306(a); Satellite Servs.,
Inc., B-295866, B-295866.2, Apr. 20, 2005, 2005 CPD ¶ 84
at 2 n.2. Although agencies have broad discretion as to
whether to seek clarifications from offerors, offerors
have no automatic right to clarifications regarding
proposals, and such communications cannot be used to cure
proposal deficiencies or material omissions, materially
alter the technical or cost elements of the proposal,
and/or otherwise revise the proposal. Alltech Engineering
Corp., B-414002.2, Feb. 6, 2017, 2017 CPD ¶ 49 at 6.
We find no merit to DBSI's contention that the Navy was
required to seek clarifications from the protester with
respect to DBSI's legally binding teaming agreement. As
noted above, an agency is permitted, but not required, to
obtain clarifications from offerors. Furthermore, the RFP
permitted, but did not require, the agency to "waive
informalities and minor irregularities." RFP at 15.
Moreover, to become acceptable, the protester would have
to provide additional, substantive proposal
information--specifically, the legally binding teaming
agreement. Although the protester views its proposal
omission to be minor or clerical, correction of this
discrepancy would have required the agency to conduct
discussions. Highmark Medicare Servs., Inc., et al.,
B-401062.5 et al., Oct. 29, 2010, 2010 CPD ¶ 285 at
11(discussions occur when an agency communicates with an
offeror for the purpose of obtaining information essential
to determine the acceptability of a proposal, or provides
the offeror with an opportunity to revise or modify its
proposal in some material respect); see FAR § 15.306(d);
see also Environmental Quality Mgmt., Inc., B-402247.2,
Mar. 9, 2010, 2010 CPD ¶ 75 at 5.
(Defense Base Services, Inc.
B-414591: Jul 12, 2017)
Awardee’s Low Price
In its initial protest, Pontiac argued that the awardee’s
price was so low that it was either fictitious or evinced
a plan to deceive the Forest Service through a
bait-and-switch scheme. Protest at 12-13. Pontiac based
its argument on a recalculation of the awardee’s price on
a per-acre basis, which it compared to the per-acre price
that the awardee had charged under the incumbent contract.
Id. at 12. By Pontiac’s calculations, the awardee’s price
is almost half the price it charged under the awardee’s
incumbent contract. Id. Pontiac reasons that the awardee
does not intend to perform in the manner required by the
RFP (resulting in an alleged bait-and-switch), or else it
intends to demand price increases from the Forest Service
during performance. Id. at 13.
In our view, these allegations do not state a valid ground
of protest. In the context of a fixed-price contract, a
bidder or offeror, in its business judgment, may properly
decide to submit a price that is extremely low--even below
the cost of performance. Brewer-Taylor Assocs., B-277845,
Oct. 30, 1997, 97-2 CPD ¶ 124 at 4. As a result, we
dismiss this basis of protest.
Communication Regarding Pricing Schedules
During Pontiac’s debriefing, the CO acknowledged that the
evaluation of the awardee’s pricing identified the
potential that the firm had made a mistake,[7] and that
the agency communicated with the firm to obtain
clarification of whether its pricing was correct. Pontiac
contends that the communication constituted discussions,
and that such discussions were improperly unequal because
Pontiac was not provided discussions or an opportunity to
revise its proposal. Protest at 9. The agency contends
that the communication was permissible because it was
limited to clarifying that the agency had properly
interpreted the awardee’s alternate price schedule as
being applicable if both items were awarded to the firm,
and clarifying whether the awardee’s pricing was mistaken.
AR at 5-8. Furthermore, the agency argues, the awardee’s
brief response, which stated that both the prices in its
proposal and the agency’s interpretation of the alternate
pricing schedule were correct, further confirms that the
agency did not conduct discussions. Id. at 7-8.
The FAR describes a spectrum of exchanges that may take
place between a contracting agency and an offeror in a
negotiated procurement. See FAR § 15.306. In that regard,
clarifications involve a limited exchange with an offeror
that gives an opportunity to clarify certain aspects of a
proposal or resolve minor or clerical errors. FAR §
15.306(a). Such communications “shall not be used to cure
proposal deficiencies or material omissions, materially
alter the technical or cost elements of the proposal,
and/or otherwise revise the proposal.” FAR §
15.306(b)(2)-(3). Discussions occur when an agency seeks
information essential to determine the acceptability of a
proposal, or provides the vendor with an opportunity to
revise or modify its proposal in some material respect. In
contrast, where an agency simply seeks confirmation of its
understanding of the proposal, it is merely obtaining a
clarification. PricewaterhouseCoopers Public Sector, LLP,
B-413316.2, B-413316.3, Dec. 27, 2016, 2017 CPD ¶ 12 at
13-14; see FAR § 15.306(d).
The record does not support the protester’s arguments that
the meaning of the awardee’s pricing schedules required
revision to be sufficiently clear, or that the agency’s
communications otherwise permitted the firm to revise its
proposal. Rather, the record reflects that before
communicating with the awardee, the agency concluded that
the awardee’s pricing schedules permitted the award of
either item to the firm under the prices listed on one set
of schedules, or the award of both items combined under
the other set of schedules. When the agency communicated
with the awardee, the contracting officer simply asked for
confirmation of that understanding, and for price
verification, which the awardee then provided in simple
terms. Since the awardee was not permitted to revise its
proposal, the record does not support Pontiac’s claim that
the agency improperly held discussions only with the
awardee. (Pontiac
Flying LLC B-414433, B-414433.2, B-414433.3: Jun 12,
2017)
On August 1, the Department of Justice filed a motion with
the court requesting an advisory opinion from our Office.
The court granted the motion and requested that our Office
issue an advisory opinion regarding the merits of the
protest Paltech filed with our Office. See id. Our opinion
here is issued in response to the court’s request, and is
presented in the same general format as we normally employ
to issue decisions responding to bid protests. As
explained below, our Office finds the protest without
merit, and we would deny this protest.
(Sections deleted)
Paltech also asserts that the agency
unreasonably refused to allow Paltech to submit additional
documentation when the agency requested Paltech to clarify
whether there was information in its proposal
demonstrating performance within five years of the
solicitation’s December 3 closing date. The agency states
that the solicitation did not allow additional submissions
or revisions relating to anything that could affect an
offeror’s score.
It is well-settled that “[a]n agency may, but is not
required to, engage in clarifications that give offerors
an opportunity to clarify certain aspects of proposals or
to resolve minor or clerical errors.” Wolverine Services
LLC, B-409906.3, B-409906.5, Oct. 14, 2014, 2014 CPD ¶ 325
at 6; see also, Savvee Consulting, Inc., B-408623,
B-408623.2, Nov. 8, 2013, 2013 CPD ¶ 265 at 6.
Clarifications cannot be used to cure deficiencies or
material omissions in a proposal or otherwise revise a
proposal. Savvee Consulting, Inc., supra. Providing an
offeror the opportunity to revise its proposal and cure a
deficiency would constitute discussions, not
clarifications, because that would require the submission
of information necessary to make the proposal acceptable.
Id.
The solicitation stated that the agency could allow an
offeror to respond to clarifying questions but that
offerors could not resubmit or revise documents. RFP at
159. Therefore, the agency provided Paltech the
opportunity to clarify whether the proposal contained
verifiable contractual documents demonstrating the
required performance period for the IT Shows subcontract.
Specifically, the agency requested that Paltech provide
the location of the needed information in the verifiable
contractual document that was submitted in its initial
proposal submission and stated that Paltech could not
provide additional documents or explanation. AR, Exh. 6,
Agency Clarification Request, at 1. In response, Paltech
referenced its subcontract agreement with IT Shows. AR,
Exh. 6, Response to Clarification, at 1.
Here, additional documentation was required to demonstrate
that Paltech met the five-year performance period
requirement for the IT Shows subcontract and for Paltech’s
proposal to become acceptable. This information could only
be submitted in the course of discussions. See Savvee
Consulting, Inc., supra. Since the agency did not hold
discussions, it properly did not permit Paltech to provide
additional documentation. In this regard, clarifications
cannot be used to cure deficiencies or material omissions
in a proposal, or to otherwise revise a proposal. Id.
On the record presented to our Office, and in response to
the court’s request for an advisory opinion, we would deny
this protest. (Planning &
Learning Technologies, Inc.-- Advisory Opinion,
B-413156.23: Oct 14, 2016).
CJW Desbuild contends that its failure to submit a signed
copy of its joint venture agreement was “a minor
oversight” and that it was “unreasonable” for the agency
to downgrade its proposal on this basis. Protest at 4. The
protester maintains that it is an “established limited
liability company with its own DUNS number” and that it is
currently “working with NAVFAC on another multiple award
contract,” indicating that “NAVFAC is aware that CJW
Desbuild is an established joint venture.” Id. The
protester also asserts that it “submitted a proposed price
that was over $300,000 lower than the lowest-priced
awardee.” Id. CJW Desbuild further argues that NAVFAC
should have used clarifications to permit it to correct
its failure to provide a signed joint venture agreement.
Id.
We find the protester’s arguments unpersuasive. As
indicated above, the RFP specifically required a “signed
copy of the joint venture agreement” and warned that
failure to submit that agreement would be considered
unacceptable. RFP at 13. Since the requirement for a
signed JV agreement was specifically linked to technical
acceptability, it could not be considered an informality
or minor irregularity, subject to waiver. Further,
regarding the protester’s argument that the agency was
aware of its status as an established joint venture based
on information outside its proposal, the agency was under
no obligation to consider information not submitted as
part of the protester’s proposal to establish the
protester’s status as a joint venture. See ABSG
Consulting, Inc., B-413155.14, Oct. 12, 2016, 2016 CPD ¶
287 at 4-5.
We also conclude that CJW Desbuild’s failure to provide a
signed joint venture agreement here could not have been
remedied through clarifications. The Federal Acquisition
Regulation (FAR) describes a spectrum of exchanges that
may take place between a contracting agency and an offeror
during negotiated procurements. See FAR § 15.306.
Clarifications are limited exchanges between the agency
and offerors that may occur when contract award without
discussions is contemplated; an agency may, but is not
required to, engage in clarifications that give offerors
an opportunity to clarify certain aspects of proposals or
to resolve minor or clerical errors. FAR § 15.306(a);
Satellite Servs., Inc., B-295866, B-295866.2, Apr. 20,
2005, 2005 CPD ¶ 84 at 2 n.2. Clarifications cannot be
used to cure deficiencies or material omissions in a
proposal or otherwise revise a proposal. DataSource, Inc.,
B-412468, Feb. 16, 2016, 2016 CPD ¶ 59 at 4. Since the
protester’s failure to submit a signed JV agreement was a
deficiency that rendered its proposal technically
unacceptable, and clarifications do not envision revisions
to proposals to cure matters of technical unacceptability,
the protester could not have revised its proposal to make
it acceptable via clarifications. See Hi-Tec Sys, Inc.,
B-402590, B-402590.2, June 7, 2010, 2010 CPD ¶ 156 at 4.
Also, as noted above, an agency is permitted, but not
required, to engage in clarifications; thus, even if CJW
Desbuild’s failure to submit a signed JV agreement had
been a minor clerical error, the agency would not have
been required to give it the opportunity to correct it via
clarifications.[2]
The protester further argues that FAR § 15.306 provides
that an agency may communicate with offerors regarding
“[a]mbiguities in the proposal or other concerns (e.g.,
perceived deficiencies, weaknesses, errors, omissions, or
mistakes (see 14.407)).” According to the protester, this
means that the provisions of FAR § 14.407 pertaining to
mistakes are effectively incorporated into FAR § 15.306.
In this connection, FAR § 14.407-1 provides as follows:
After the opening of bids, contracting officers shall
examine all bids for mistakes. In cases of apparent
mistakes and in cases where the contracting officer has
reason to believe that a mistake may have been made, the
contracting officer shall request from the bidder a
verification of the bid, calling attention to the
suspected mistake. If the bidder alleges a mistake, the
matter shall be processed in accordance with this section
14.407. Such actions shall be taken before award.
The protester’s argument is unavailing. The subsection of
FAR § 15.306 cited by the protester--i.e., (b)(3)(i)--pertains
to communications with offerors for purposes of
determining whether a proposal should be included in the
competitive range. Here, the agency did not intend to
establish, nor did it establish, a competitive range.
Thus, the provisions of FAR § 15.306(b)(3)(i) are
inapplicable.
The protest is denied. (CJW
Desbuild JV, LLC B-414219: Mar 17, 2017)
SAIC argues that the agency abused its discretion by
making the award without conducting discussions. Protest
at 7-11; Comments at 2-12; Supp. Comments at 2‑4. Had the
agency conducted discussions, SAIC contends, the firm
could have corrected the deficiencies assessed to its
proposal and addressed other adverse evaluation findings.
Protest at 11-15. SAIC recognizes that our Office
generally does not review an agency’s decision to make
award without conducting discussions. Id. at 7 (citing
Kiewit Louisiana Co., B-403736, Oct. 14, 2010, 2010 CPD ¶
243 at 3). SAIC argues that we nevertheless should
consider its allegation because our practice in this area
rests in part on findings in prior decisions that there
are “no statutory or regulatory criteria specifying when
an agency should or should not initiate discussions.” Id.
(quoting Trace Sys., Inc., B‑404811.4, B‑404811.7, June 2,
2011, 2011 CPD ¶ 116 at 5; ITT Sys. Corp., B‑405865,
B‑405865.2, Jan. 6, 2011, 2012 CPD ¶ 44 at 3 n.3; Kiewit
Louisiana Co., supra). SAIC points out that after these
decisions were issued, the Department of Defense (DoD)
promulgated Defense Federal Acquisition Regulation
Supplement (DFARS) § 215.306(c), which states that “[f]or
acquisitions with an estimated value of $100 million or
more, contracting officers should conduct discussions.”[5]
Protest at 8.
Based on this regulation, and the fact that this is a DoD
procurement valued over $100 million, SAIC argues that our
Office should review the agency’s decision not to conduct
discussions here. SAIC further argues that due to the
complexity and high dollar value of this procurement, the
agency’s decision not to conduct discussions was improper.
Protest at 10; Comments at 4. Finally, SAIC argues that
the policy underlying DFARS § 215.306(c) dictates that
discussions should have been conducted in this
procurement.[6] Protest at 8-9; Comments at 6, 9-10.
We agree with SAIC that DFARS § 215.306(c) provides a
basis for our Office to review the agency’s actions
here.[7] We begin our review by observing that the
operative word in the regulation is “should” and that FAR
§ 2.101 defines the word “should” to mean “an expected
course of action or policy that is to be followed unless
inappropriate for a particular circumstance.” Thus, DFARS
§ 215.306(c) is reasonably read to mean that discussions
are the expected course of action in DoD procurements
valued over $100 million, but that agencies retain the
discretion not to conduct discussions if the particular
circumstances of the procurement dictate that making an
award without discussions is appropriate. From this, we
see the inquiry here to be whether the record shows, given
the particular circumstances of this procurement, that
there was a reasonable basis for the agency’s decision not
to conduct discussions.
In response to SAIC’s protest, the agency points out that
the solicitation cautioned offerors to submit their best
price and technical terms in their initial proposals
because the agency intended to make the award without
discussions, if possible. See Mem. of Law at 4. The agency
argues that this admonition, together with the disparity
in the evaluated technical merit of the proposals, and the
fact that Battelle’s pricing was found to be reasonable,
shows the agency reasonably exercised its discretion under
DFARS § 215.306(c) to forgo discussions. See id. at 9-10.
Under the circumstances here, we agree with the agency.[8]
As discussed above, the solicitation provided for the
evaluation of proposals under the “qualifying criteria”
and three areas--technical/management, past performance,
and price. RFP at 181. The technical/management area was
weighted as significantly more important than the other
two areas, and technical/management area factor 1, vehicle
configuration, was weighted as significantly more
important than the other area 1 factor. Id. As also
discussed above, the solicitation advised that the
assessment of a deficiency under any of the areas or
factors “may cause” a proposal to be excluded from
consideration for award. Id.
After the evaluation, SAIC’s proposal was assigned a
rating of unacceptable under the qualifying criteria, a
rating of marginal under the technical/management area,
and a rating of unacceptable under the vehicle
configuration factor. AR, Tab 8, SSEB Rep., at 25.
Further, SAIC’s proposal was assessed three deficiencies
and five significant weaknesses under the
technical/management area. Id. at 29. In contrast,
Battelle’s proposal was assigned a rating of acceptable
under the qualifying criteria, a rating of good under the
technical/management area, and a rating of good under the
vehicle configuration factor. Id. at 25. Further, no
deficiencies or significant weaknesses were assessed to
Battelle’s proposal. AR, Tab 17, SSEB Rep., App. E, at 2.
Upon reviewing the evaluation findings, the SSAC concluded
that conducting discussions was not warranted based on
Battelle’s superior technical/management proposal, its
substantial confidence past performance rating, and its
reasonable price. See AR, Tab 10, SSAC Comparative
Analysis, at 13-15. The SSA adopted this recommendation.
We previously have found an agency’s decision not to
conduct discussions to be reasonable where the record
showed there were deficiencies in the protester’s
proposal, the awardee’s proposal was evaluated as being
technically superior to the other proposals, and the
awardee’s price was reasonable. See Richard M. Milburn
High Sch., B-277018, Aug. 19, 1997, 97-2 CPD ¶ 53 at 6;
Int’l Data Prods., Corp. et al., B-274654 et al., Dec. 26,
1996, 97-1 CPD ¶ 34 at 10-11; Stabro Labs., Inc.,
B-256921, Aug. 8, 1994, 94-2 CPD ¶ 66 at 2, 5. Although
those cases pre-date DFARS § 215.306(c), we find the
principle applicable here. SAIC’s proposal was assessed a
number of deficiencies under the most heavily-weighted
components of the evaluation, and any one of these
deficiencies provided a basis to eliminate the firm from
the competition under the terms of the solicitation.
Battelle’s proposal, on the other hand, was evaluated as
technically superior under the most heavily weighted
components of the evaluation, and it was seen as offering
“significant benefits to the Government at low risk to
both performance and schedule,” and at a reasonable price.
AR, Tab 11, SSDD, at 4-5. On this record, we view as
reasonable the agency’s decision to exercise the
discretion it is afforded under DFARS § 215.306(d) to
forgo discussions. (Science
Applications International Corporation B-413501,
B-413501.2: Nov 9, 2016)
Sevatec also argues that the agency conducted discussions
with SeKon without furnishing Sevatec a similar
opportunity to address evaluated deficiencies in its
proposal. In this regard, in its technical proposal SeKon
included a diagram which listed, by name and employment
category (e.g., systems engineer, subject matter expert
for cybersecurity), proposed key personnel, members of its
management team, subject matter experts, support staff,
and a reach back team. SeKon Proposal Figure 25. The chart
did not specifically identify whether the personnel were
employees of SeKon or its subcontractor, Deloitte. In its
cost proposal, SeKon listed, as required, proposed
off-site and on-site rates for different labor categories
for both SeKon and Deloitte.
In conducting the cost realism evaluation, the cost
analyst considered whether the employees were SeKon or
Deloitte employees. Supp. AR at 15-16. To confirm her
conclusions in this regard, she requested the contracting
officer to ask SeKon to indicate whether the employees
worked for the prime or subcontractor, the employee’s
skill category, and the applicable on-site and off-site
rates. Id. at 17. The agency specifically advised SeKon
that this was not an opportunity to revise, change or
modify its proposal. Agency Email from Agency to SeKon,
Sept. 18, 2014. SeKon responded with the requested
information. SeKon Response to email, Sept. 18, 2014.
Sevatec asserts that SeKon’s initial proposal did not
indicate how the management team would be divided between
SeKon and Deloitte. According to Sevatec, this amounted to
a material deficiency which the agency allowed SeKon to
correct through discussions. Sevatec asserts that since
the agency held discussions with SeKon, it was obligated
to hold discussions with Sevatek and allow it to correct
the deficiencies in its proposal.
Federal Acquisition Regulation § 15.306 describes a range
of exchanges that may take place between an agency and an
offeror during negotiated procurements. Clarifications are
limited exchanges between an agency and an offeror for the
purpose of clarifying certain aspects of a proposal, and
do not give the offeror the opportunity to revise or
modify its proposal. Discussions, on the other hand, occur
when an agency communicates with an offeror with the
intent to obtain proposal revisions and include
bargaining, give and take, persuasion, and alteration of
assumptions and positions. iGov et al., B-408128.24 et al,
Oct. 31, 2014, 2014 CPD ¶ 329 at 10. When an agency holds
discussions with one offeror it must hold them with all
offerors in the competitive range. Booz Allen Hamilton,
Inc., B‑405993, B-405993.3, Jan. 19, 2012, 2012 CPD ¶ 30
at 10. Communications that do not permit an offeror to
revise or modify its proposal, but rather permit the
offeror to explain what it has already proposed to do, are
clarifications, not discussions. Id.
The agency argues, and we agree, that the information
SeKon provided regarding personnel was the result of
clarifications, not discussions. In this regard, the
agency did not undertake the exchange with the intent of
allowing SeKon to revise its proposal, and, in fact,
specifically advised SeKon that it would not be permitted
to do so. Rather, the agency asked for the information so
that it could confirm the conclusions it reached while
performing its cost evaluation. In this regard, both the
names of the employees and the rates were included in the
proposal, and the agency merely sought to ensure that it
had correctly mapped the cost proposal to the technical
proposal. Further, we note that, contrary to Sevatec’s
allegations, the information was not sought or used to
evaluate SeKon’s technical proposal. Since SeKon was not
permitted to materially revise its proposal, and the
information was not needed to determine that SeKon’s
proposal was acceptable, the communications did not
constitute discussions. (Sevatec,
Inc. B-410665, B-410665.3: Jan 21, 2015) (pdf)
Clarifications are “limited exchanges” that agencies may
use to allow offerors to clarify certain aspects of their
proposals or to resolve minor or clerical mistakes. See
FAR § 15.306(a)(2). Communications that do not permit an
offeror to revise or modify its proposal, but rather
request that the offeror confirm what it has already
committed to do, are clarifications and not discussions.
Highmark Medicare Servs., Inc., et al., B-401062.5 et al.,
Oct. 29, 2010, 2010 CPD ¶ 285 at 11. Discussions, on the
other hand, occur when an agency communicates with an
offeror for the purpose of obtaining information essential
to determine the acceptability of a proposal, or provides
the offeror with an opportunity to revise or modify its
proposal in some material respect. Id.
Here, the express terms of both RFPs indicated that an
offeror’s failure to submit a surety letter would be a
mandatory basis for disqualification. RFP-0316 at 67;
RFP-0317 at 67. This term, in each solicitation, made
submission of a surety letter a material requirement for
each RFP. See The Walsh-Vaughn JV, B-407998.2, B‑407998.4,
May 21, 2013, 2013 CPD ¶ 134 at 7 (failure to provide an
electronic version of a construction schedule, even though
paper copy was submitted, is a deficiency when the
electronic version is required by the RFP). Consequently,
the CO’s e-mails requesting the surety letters constituted
discussions since HPC’s proposals, which did not initially
conform to either solicitation’s requirements, could only
be made acceptable after the protester submitted the
surety letters. That said, we do not agree that the agency
could not remedy its misstep by belatedly recognizing that
its request of the letters would constitute discussions
and by returning the situation to the status quo ante by
electing not to consider the submission provided by HPC.
In certain very limited circumstances, where a
communication is the result of a mistake on the part of a
contracting officer, an agency is not required to consider
the information it requested. The Saxon Corp., B-232694.2
et al., June 13, 1989, 89-1 CPD ¶ 553 at 2-3 (even if
agency asked for and refused to consider information
requested, discussions need not be held where the intent
was to make award on the basis of initial proposals, and
where agency action did not impinge on the integrity of
the competitive system). When an agency intends to make an
award on initial proposals, the integrity of the
competitive system would not be enhanced by requiring that
revisions be solicited and considered from all offerors.
See Rainbow Technology, Inc., B-232589, Jan. 24, 1989,
89-1 CPD ¶ 66 at 4-5; The Saxon Corp., supra.
Here, the terms of the solicitations notified all offerors
that the agency intended to make award on the basis of
initial proposals. The record establishes that the CO’s
communications with the protester were not intended to be
discussions. Moreover, before the VA’s source selection
boards started deliberations, the agency recognized that
by requesting the surety letters the agency would initiate
discussions, and recognized the unintended impact on these
procurements. The record reflects that in order to correct
this error and to ensure that the award would be made on
the basis of initial proposals, as provided by the RFPs,
the agency did not consider HPC’s surety letters and
evaluated the proposals based upon only the initial
submissions. Accordingly, we find that the agency’s
decision to eliminate the protester from the competitions
was reasonable. (Hamilton
Pacific Chamberlain, LLC B-411294, B-411301: Jul 6,
2015) (pdf)
The protester challenges the agency’s evaluation of AMH’s
quotation as technically unacceptable, asserting that it
addressed the agency’s concerns in its response to the agency’s
questions. The agency maintains that AMH’s quotation was
unacceptable for failure to comply with the solicitation
requirements for the required heavy duty bucket, quick coupler,
hydraulic line for the quick coupler, and “maximum extended
warranty.” AR, Tab 16, Contracting Officer’s Statement of Facts.
Regarding the questions asked of AMH concerning both the extent
and cost of the warranty and the hardware to be provided, the
agency asserts that the questions were intended as
clarifications only, not discussions, and therefore did not
provide AMH an opportunity to modify its quotation so as to
render it acceptable. Aff. of Contracting Officer ¶¶ 20-23.
Clearly stated solicitation requirements are considered material
to the needs of the government, and a quotation that fails to
conform to such material terms is technically unacceptable and
may not form the basis for award. 4D Sec. Solutions, Inc.,
B-400351.2, B-400351.3, Dec. 8, 2008, 2009 CPD ¶ 5 at 4.
Further, in the case of a brand name or equal solicitation, the
particular features of a brand name item set forth in a
solicitation are presumed to be material and essential to the
government’s needs. Sourcelinq, LLC--Protest and Costs,
B-405907.2 et al., Jan. 27, 2012, 2012 CPD ¶ 58 at 3. With
respect to a firm offering an equal product, the quotation must
demonstrate that the product conforms to the salient
characteristics listed in the solicitation. Nas/Corp-Telmah,
Inc., B-405893, Jan. 10, 2012, 2012 CPD ¶ 88 at 2; OnSite
Sterilization, LLC, B‑405395, Oct. 25, 2011, 2011 CPD ¶ 228 at
2. If the firm fails to do so, its product is properly rejected
as technically unacceptable. Id.
Here, by AMH’s own admission during its email exchange with the
agency, AMH’s quotation as submitted by the closing time did not
meet at least one of the solicitation requirements, that is, the
requirement that the vendor offer its “maximum extended
warranty.” Instead, AMH offered to provide the required maximum
warranty for an additional $25,000. Evaluation of AMH Quotation,
Email from AMH to Contract Specialist, Sept. 30, 2014.
AMH asserts that its email responses to the agency’s questions,
in which it offered its extended warranty, should have resolved
the agency’s concerns with respect to the warranty. The record,
however, indicates that AMH was not afforded an opportunity to
modify its quotation so as to substitute its extended warranty
for the lesser warranty initially quoted. In this regard,
although an agency is not required to conduct discussions under
simplified acquisition procedures, where an agency avails itself
of negotiated procurement procedures, the agency should fairly
and reasonably treat offerors in the conduct of those
procedures. See ERIE Strayer Co., B-406131, Feb. 21, 2012, 2012
CPD ¶ 101 at 4; Kathryn Huddleston and Assocs., Ltd., B-289453,
Mar. 11, 2002, 2002 CPD ¶ 57 at 6. FAR §15.306 describes a range
of exchanges that may take place when the agency decides to
conduct exchanges with offerors during negotiated procurements.
Clarifications are “limited exchanges” between an agency and an
offeror for the purpose of eliminating minor uncertainties or
irregularities in a proposal, and do not give an offeror the
opportunity to revise or modify its proposal. FAR §
15.306(a)(2); ERIE Strayer Co., supra; Lockheed Martin
Simulation, Training & Support, B-292836.8 et al., Nov. 24,
2004, 2005 CPD ¶ 27 at 8. Clarifications are not to be used to
cure proposal deficiencies or material omissions, or materially
alter the technical or cost elements of the proposal, or
otherwise revise the proposal. eMind, B-289902, May 8, 2002,
2002 CPD ¶ 82 at 5. Discussions, on the other hand, occur when
an agency communicates with an offeror for the purpose of
obtaining information essential to determine the acceptability
of a proposal, or provides the offeror with an opportunity to
revise or modify its proposal in some material respect. Gulf
Copper Ship Repair, Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶
108 at 6; see FAR §15.306(d).
While the contract specialist’s questions to the vendors were
not explicit that the agency intended its inquiries to be
requests for clarifications and not discussions, the contracting
officer states that he asked the contract specialist only to
request clarifications, and that the evaluation was based upon
the quotations as initially submitted by the 10 a.m. closing
time. Aff. of Contracting Officer ¶¶ 10, 18, 19, 21, 22. These
statements are consistent with the contemporaneous evaluation
record, where both technical evaluations of AMH’s quotation
evaluated the quotation as unacceptable for failing to satisfy
material terms of the RFQ. Evaluation of AMH Quotation. Where,
in response to clarification requests, an agency receives
information that seeks to materially modify a proposal or
quotation, we will not consider the communications to be
discussions where the agency does not rely on the modification
in its evaluation. S4, Inc., B-299817, B‑299817.2, Aug. 23,
2007, 2007 CPD ¶ 164 at 7. (American
Material Handling, Inc. B-410899: Mar 12, 2015) (pdf)
L&G complains that Trinity should have been found ineligible for
award, because Trinity’s proposal--prior to corrective
action--allegedly did not contain any commitment to comply with
the RFP’s subcontracting limitation. L&G also argues that the
Air Force’s exchange with Trinity was improper because it went
beyond a mere clarification and constituted discussions by
permitting Trinity to revise a deficient proposal.[7]
Importantly, L&G does not dispute that Trinity’s response here
fully indicates the awardee’s intent to comply with the
subcontracting obligation, as does Trinity’s actual post-award
performance. We have examined the issues raised by the protester
and find they provide no basis on which to sustain the
protest.[8]
Contracting officials in negotiated procurements, such as this,
have broad discretion to take corrective action where the agency
determines that such action is necessary to ensure fair and
impartial competition. The Matthews Group, Inc. t/a TMG Constr.
Corp., B-408003.2, B-408004.2, June 17, 2013, 2013 CPD ¶ 148 at
5. This includes determining the means necessary to remedy the
identified shortcomings. We generally will not object to
corrective action that places all offerors in the same
competitive posture they enjoyed prior to the defect in the
source selection process. National Shower Express, Inc.; Rickaby
Fire Support, B-293970, B-293970.2, July 15, 2004, 2004 CPD ¶
140 at 8. In our view, the corrective action taken here is well
within the broad discretion afforded to contracting agencies in
these circumstances.
Clarifications are “limited exchanges” between an agency and an
offeror for the purpose of clarifying certain aspects of a
proposal, and do not give an offeror the opportunity to revise
or modify its proposal. FAR § 15.306(a)(2); Lockheed Martin
Simulation, Training & Support, B-292836.8 et al., Nov. 24,
2004, 2005 CPD ¶ 27 at 8. Discussions, on the other hand, occur
when an agency communicates with an offeror for the purpose of
obtaining information essential to determine the acceptability
of a proposal, or provides the offeror with an opportunity to
revise or modify its proposal in some material respect. Highmark
Medicare Servs., Inc. et al., B-401062.5 et al., Oct. 29, 2010,
2010 CPD ¶ 285 at 11; see FAR § 15.306(d). In situations where
there is a dispute regarding whether an exchange between an
agency and an offeror constituted discussions, the acid test is
whether an offeror has been afforded an opportunity to revise or
modify its proposal. Id.; Priority One Servs., Inc., B-288836,
B-288836.2, Dec. 17, 2001, 2002 CPD ¶ 79 at 5.
Contrary to L&G assertion, we find that the agency’s exchange
with Trinity here did not constitute discussions. The Air
Force’s June 3 letter to Trinity merely sought verification of
the offeror’s intent to comply with its subcontracting
obligations during performance, and did not provide for the
submission of a revised proposal. Similarly, Trinity’s response
merely explained an aspect of the offeror’s proposal that was
otherwise vague. Quite simply, in light of the ambiguity in
Trinity’s proposal, the Air Force, consistent with its letter
stating its intent to take corrective action in response to
L&G’s prior protest, conducted a limited exchange with the
offeror to clarify the ambiguity. As such, the exchange here
constituted clarifications. See FAR § 15.306(a); LOGMET LLC,
B-405700, Dec. 14, 2011, 2011 CPD ¶ 278 at 3 (agency letter
seeking confirmation of understanding of subcontracting
obligations during performance constituted clarifications).
(L&G Technology Services, Inc.,
B-408080.2: Nov 6, 2013) (pdf)
Kardex protests its technical evaluation, arguing, among other
things, that the VA conducted misleading and non-meaningful
discussions by failing to advise Kardex that its
climate-controlled storage units did not comply with the
specification for totally self-contained cooling systems. See
Protest at 9; Comments at 5.
The VA asserts that its communications with Kardex constituted
clarifications, not discussions, because the agency merely
permitted the protester to explain or clarify its proposed
storage units and explicitly prohibited Kardex from revising its
quotation. AR at 16.
As a preliminary matter, we note that this competition was
limited to FSS vendors. As we have previously noted in our
decisions, the procedures of Federal Acquisition Regulation
(FAR) part 15 governing contracting by negotiation--including
those concerning exchanges with offerors after receipt of
proposals--do not govern competitive procurements under the FSS
program. FAR § 8.404(a); USGC Inc., B-400184.2 et al., Dec. 24,
2008, 2009 CPD ¶ 9 at 3. There is no requirement in FAR subpart
8.4 that an agency conduct discussions with vendors. See USGC
Inc., supra. However, exchanges that do occur with vendors in a
FAR subpart 8.4 procurement, like all other aspects of such a
procurement, must be fair and equitable; our Office has looked
to the standards in FAR part 15 for guidance in making this
determination. A-Tek, Inc., B-404581.3, Aug. 22, 2011, 2011 CPD
¶ 188; USCG Inc., supra.
In this regard, we have looked to FAR part 15 as guidance in
defining clarifications as “limited exchanges” that agencies may
use to allow offerors to clarify certain aspects of their
proposals (or in this case quotations) or to resolve minor or
clerical mistakes. See FAR § 15.306(a)(2); Diversified
Collection Servs., Inc., B-406958.3, B-406958.4, Jan. 8, 2013,
2013 CPD ¶ 23 at 11 (using FAR part 15 definitions of
post-proposal communications, or exchanges, as guidance in FSS
context). Discussions, by contrast, occur when an agency
communicates with an offeror for the purpose of obtaining
information essential to determine the acceptability of a
proposal or quotations, or provides the vendor with an
opportunity to revise or modify its proposal. Diversified
Collection Servs., Inc., supra, at 11-12; see FAR § 15.306(d).
The agency’s characterization of a communication as
clarifications or discussions is not controlling; it is the
actions of the parties that determine whether discussions have
been held and not merely the characterization of the
communications by the agency. See Priority One Servs., Inc.,
B-288836, B-288836.2, Dec. 17, 2001, 2002 CPD ¶ 79 at 5.
Here, the agency’s insistence that the communications it
conducted were clarifications and not discussions is unavailing.
The communications sent by the agency to Kardex invited the firm
to respond to 34 requirements that the firm either “does not
meet” or “does not provide info on,” and requested that the firm
provide pricing discounts. These communications invited
responses from Kardex that were necessary to determine the
acceptability of the firm’s quotation, and in fact resulted in
Kardex being permitted to supplement its quotation. This is
quintessentially the nature of discussions, not clarifications.
Diversified Collection Servs., Inc., supra, at 11-12.
More importantly, we conclude that the nature of the
communications here were fundamentally unfair. Despite the
repeated rounds of discussions with Kardex concerning multiple
requirements that the firm’s quotation did not meet, the agency
never identified the one requirement for which the quotation was
found technically unacceptable--the firm’s failure to provide
totally self-contained units. Under the circumstances here,
where a firm holds discussions with a vendor, those discussions
must be meaningful. See A-Tek, Inc., supra (evaluating whether
discussions were meaningful in FSS competition). Since the
discussions here were not fair, as required in FAR part 8
procurements, we sustain the protest. (Kardex
Remstar, LLC, B-409030, Jan 17, 2014) (pdf)
Discussions
P&H argues that the post-evaluation exchange between the VA and
Monument constituted discussions, and not clarifications. We
agree.
Section 15.306 of the Federal Acquisition Regulation (FAR)
describes a range of exchanges that may take place when an
agency decides to conduct exchanges with offerors during
negotiated procurements. Clarifications are limited exchanges
between an agency and an offeror that may occur where, as here,
contract award without discussions is contemplated. FAR §
15.306(a). An agency may, but is not required to, engage in
clarifications that give offerors an opportunity to clarify
certain aspects of proposals or to resolve minor or clerical
errors. Id. However, clarifications may not be used to cure
proposal deficiencies or material omissions, materially alter
the technical or cost elements of the proposal, or revise the
proposal. Superior Gunite, B-402392.2, Mar. 29, 2010, 2010 CPD ¶
83 at 4. Discussions, on the other hand, occur when an agency
communicates with an offeror for the purpose of obtaining
information essential to determine the acceptability of a
proposal, or provides the offeror with an opportunity to revise
or modify its proposal in some material respect. Gulf Copper
Ship Repair, Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶ 108 at
6; see FAR § 15.306(d). When an agency conducts discussions with
one offeror, it must conduct discussions with all offerors in
the competitive range.[4] Gulf Copper Ship Repair, Inc., supra,
at 6. Finally, at the conclusion of discussions, the agency must
request final proposal revisions. FAR § 15.307(b); Raytheon
Technical Servs. Co., B-404655.4 et al., Oct. 11, 2011, 2011 CPD
¶ 236 at 7.
Ultimately, it is the actions of the parties that determine
whether discussions have been held, not the characterization of
those communications by the agency. Id. In situations where
there is a dispute regarding whether communications between an
agency and an offeror constituted discussions, the acid test is
whether an offeror has been afforded an opportunity to revise or
modify its proposal. Id. Communications that do not permit an
offeror to revise or modify its proposal, but request that the
offeror confirm what the offeror has already committed to do in
its proposal, are clarifications and not discussions.
Environmental Quality Mgmt., Inc., B-402247.2, Mar. 9, 2010,
2010 CPD ¶ 75 at 7.
We find that the exchange with Monument constituted discussions.
The proposal amendment Monument provided in response to the
exchange constituted a material revision to its proposal. The
amendment replaced the sequence of work in Monument’s proposal
with a different sequence, and provided the missing narrative
that was required by the solicitation. Monument’s response did
not, in fact, confirm what it had already committed to do in its
proposal, but committed to doing something else. The materiality
of the revision is underscored by the fact that the source
selection decision relies on it in finding the proposal
technically acceptable. Again, as quoted above, the decision
expressly states that, “[b]ased on the clarification received
from Monument, and . . . a better understanding by the board of
what is required for a proposal to be minimally acceptable, the
board determined Monument . . . to be the lowest priced
technically acceptable proposal . . . .” AR, Tab M, Source
Selection Decision Document, at 2. (Piquette
& Howard Electric Service, Inc., B-408435.3, Dec 16, 2013)
(pdf)
Although IAP does not challenge the Corps’ rejection of its
proposal for exceeding the [task order request for proposals]
TORP’s cost limitation of $30 million, it contends that the
Corps’ questions concerning the protester’s proposed use of the
TA-50 buildings constituted discussions, and that the agency was
therefore required to inform IAP that its proposal was
ineligible for award because its price exceeded the cost
limitation. Specifically, IAP argues that the agency’s questions
required or invited IAP to modify its proposal to either assume
liability for damage to the storage area, and to propose an
alternative plan to using the TA-50 buildings. For the reasons
discussed below, we find no basis to sustain the protest.
IAP’s arguments cite FAR part 15 as the primary support for its
argument that the Corps engaged in inadequate discussions.
Specifically, the protester notes that when an agency engages in
discussions with an offeror, FAR part 15 requires that the
discussions be “meaningful,” that is, sufficiently detailed so
as to lead an offeror into the areas of its proposal requiring
amplification or revision in a manner to materially enhance the
offeror’s potential for receiving the award. See Onsite Health
Inc., B-408032, B-408032.2, May 30, 2013, 2013 CPD ¶ 138 at 7.
FAR part 15 specifically requires that discussions, when held,
must address “at a minimum . . . deficiencies, significant
weaknesses, and adverse past performance information to which
the offeror has not yet had an opportunity to respond.” FAR §
15.306(d)(3).
However, the regulations concerning discussions under FAR part
15, which pertain to negotiated procurement, do not, as a
general rule govern task and delivery order competitions
conducted under FAR part 16, such as the procurement here. See
NCI Info. Sys. Inc., B-405589, Nov. 23, 2011, 2011 CPD ¶ 269 at
6. In this regard, FAR § 16.505 does not establish specific
requirements for discussions in a task order competition;
exchanges in that context, like other aspects of such a
procurement, must be fair and not misleading. CGI Fed. Inc.,
B-403570 et al., Nov. 5, 2010, 2011 CPD ¶ 32 at 9. Nonetheless,
even if FAR part 15 applied here, we conclude that the agency’s
questions did not constitute discussions. In this regard,
communications that do not permit or require an offeror to
revise or modify its proposal, but rather request that the
offeror confirm what the offeror has already committed to do in
its proposal, are clarifications and not discussions. See
Pinnacle Solutions, Inc., B-406998, B-406998.2, Oct 16, 2012,
2012 CPD ¶ 338 at 7; Environmental Quality Mgmt., Inc.,
B-402247.2, Mar. 9, 2010, 2010 CPD ¶ 75 at 7.
IAP argues that the first question posed by the Corps required
the protester to modify its proposal to accept liability for the
TA-50 buildings it proposed to use for storage of materials. In
this regard, the protester contends that the agency’s question
required the contractor to accept “liability” for the buildings,
and further argues that such an obligation will require the
protester to “compensate third parties for any personal injuries
or property damage stemming from the contractor’s performance of
this task.” Protester’s Comments (Nov. 7, 2013) at 5. The Corps
argues, however, that its question concerning IAP’s proposal to
utilize the TA-50 buildings for storage only confirmed the
protester’s obligation to repair existing facilities under the
terms of the contract. Moreover, the agency contends that the
question did not address the broad scope of liability that the
protester claims was encompassed by this question. We agree with
the agency.
Here, the solicitation required the contractor to take
responsibility for damage during construction that might occur
to existing facilities, including the TA-50 buildings. See SOW
¶¶ 2.13(e), 3.11.B.1.c, 3.11.B.1.d, 3.11.B.2.l, 6.1. For
example, the SOW stated that the “Contractor is to pay utility
bills and repair any damage to the existing site and facilities,
to include out buildings, sidewalks, access roads, and
furnishings. . . . Any damage to Phase I work [including TA-50
buildings] shall be repaired to new condition at the
contractor’s expense.” Id. ¶ 2.1.3(e). The RFP also advised of
the contractor’s obligations regarding newly-constructed
improvements, such as the TA-50 buildings: “There were
improvements made to this facility and site completed under a
previous phase of work. Do not damage newly completed work or
remove new furniture or accessories.” Id. ¶ 6.1; see also AR at
3.
To the extent the protester argues that the agency’s use of the
word “liability” required IAP to assume additional
responsibilities, we disagree. IAP maintains that assuming the
responsibility to repair or replace any damage to existing
facilities or items is not the same as the assumption of
liability--which the protester argues imposes an obligation on
the contractor to compensate third parties for any personal
injuries or property damage stemming from the contractor’s
performance of this task.
The Corps’ question, however, discussed IAP’s proposal to use
the TA-50 buildings for storage of materials, and in this
context asked: “Is the contractor going to take the liability
for that facility if damage occurs?” AR, Tab F, Clarification
Request and Response 1, at 1. Moreover, the protester’s response
clearly discussed its obligations in the context of damage to
the buildings: “Although it is our intention to take precautions
to mitigate possible damage, we will take full responsibility
for the TA-50’s during construction.” Id. We conclude that
neither the agency’s question nor the protester’s response
expressly addressed liability in terms broader than those
anticipated by the SOW, and thus we find no support for the
protester’s argument that the question required the protester to
assume obligations beyond those set forth in the solicitation.
For these reasons, we do not find that the question required or
permitted IAP to revise its proposal, and therefore did not
constitute discussions. See Pinnacle Solutions, Inc., supra.
We also do not find that the Corps engaged in discussions by
asking IAP whether it had an alternate plan to using the TA-50
buildings for storage, in the event the government did not agree
to IAP’s proposal to utilize those buildings. As discussed
above, with regard to the protester’s proposal to use the TA-50
buildings, the agency asked the following: “If the GOVT does not
allow this do they have an alternate plan?” AR, Tab F,
Clarification Request and Response 1, at 1. In response, the
protester stated, “[i]f we are not allowed to utilize the
TA-50’s as storage, then we plan on enclosing two of the covered
training areas for storage.” Id. IAP contends that the question
required the protester to submit an alternative plan to its
proposal to use the TA-50 buildings, and that the protester’s
response was a revision to its proposal that triggered the
agency’s obligation to conduct discussions regarding its
proposed price.
As discussed above, the SOW states that the contractor will be
required to prepare a site plan “indicating the proposed
location and dimensions of any area to be fenced and used by the
Contractor,” and further stated that the plan must “indicate if
the use of a supplemental or other staging area is desired.”
TORP at 190. The agency notes that this SOW provision pertains
to contract performance, and thus neither required offerors to
submit site plans as part of their proposals, nor required
offerors to seek approval for elements of its site plan,
including the use of particular buildings, until after award. AR
at 3; Supp. AR (Nov. 21, 2013) at 4. For this reason, the agency
argues that neither the protester’s proposal to use the TA-50
buildings, nor its response to the agency’s question pertained
to the acceptability of its proposal. In this context, we find
that the agency’s inquiry as to whether the protester had an
alternative plan pertained to a minor uncertainty, that was not
related to the acceptability of the protester’s proposal, and
did not permit or require the protester to modify its proposal
in a manner that constituted discussions. See Pinnacle
Solutions, Inc., supra.
In sum, the record does not show that the agency engaged in
discussions with IAP. We therefore conclude that the Corps
properly rejected IAP’s proposal because its proposed exceeded
the cost limitation. (IAP-Leopardo
Construction, Inc., B-408890, Dec 19, 2013) (pdf)
We also find no
merit to FPM’s argument that it should have been permitted to
correct this omission through clarifications. FAR § 15.306
describes a spectrum of exchanges that may take place between a
contracting agency and an offeror during negotiated
procurements. Clarifications are limited exchanges between the
agency and offerors that may occur when contract award without
discussions is contemplated; an agency may, but is not required
to, engage in clarifications that give offerors an opportunity
to clarify certain aspects of proposals or to resolve minor or
clerical errors. FAR § 15.306(a); Satellite Servs., Inc.,
B-295866, B-295866.2, Apr. 20, 2005, 2005 CPD ¶ 84 at 2 n.2.
By contrast, discussions--which are to occur after establishment
of the competitive range--involve the agency indicating to each
offeror the significant weaknesses, deficiencies, and other
aspects of its proposal that could be altered or explained to
materially enhance the proposal’s potential for award. FAR §
15.306(d)(3). Although agencies have broad discretion as to
whether to seek clarifications from offerors, offerors have no
automatic right to clarifications regarding proposals and such
communications cannot be used to cure proposal deficiencies or
material omissions, materially alter the technical or cost
elements of the proposal, and/or otherwise revise the proposal.
A.G. Cullen Constr., Inc., B-284049.2, Feb. 22, 2000, 2000 CPD ¶
45 at 5-6. FPM’s correction of this omission would require the
protester to revise its proposal, which would constitute
discussions, and not clarifications. (FPM
Remediations, Inc., B-407933.2, Apr 22, 2013) (pdf)
Clarifications
Were Properly Conducted
PSI first asserts that the Army conducted discussions with PSI,
and that those discussions were inadequate. Its argument is
based on PSI’s claim that, despite being labeled as
clarifications, the questions posed by the Army through ENs were
essential to determining the acceptability of PSI’s proposal,
that PSI’s responses materially affected the evaluation of its
proposal, and, therefore, that its responses should be
considered proposal revisions. Protester’s Comments at 2.
Accordingly, PSI maintains that the Army was required to hold
comprehensive discussions with PSI to advise it of all the
significant weaknesses in its proposal, which the firm argues it
could have corrected.
The Army responds that it did not hold discussions but, rather,
limited its communications with both offerors to clarifications.
Thus, the agency argues that it properly did not communicate
with PSI regarding aspects of its proposal that would have
required proposal revisions to correct. In short, the agency
maintains that it conducted only clarifications because it was
proceeding to make award without discussions.
Federal Acquisition Regulation (FAR) § 15.306 describes a range
of exchanges that may take place during negotiated procurements.
In short, an agency is not required to hold discussions, and
thus to allow offerors to submit proposal revisions; rather, it
may properly limit its communications with offerors to
clarifications. Id. Clarifications are defined as "limited
exchanges" between an agency and an offeror for the purpose of
eliminating minor uncertainties or irregularities in a proposal,
and do not give an offeror the opportunity to revise or modify
its proposal. FAR § 15.306(a)(2). Clarifications are not to be
used to cure proposal deficiencies or material omissions, or
materially alter the technical or cost elements of the proposal,
or otherwise revise the proposal. Discussions, on the other
hand, occur when an agency communicates with an offeror for the
purpose of obtaining information essential to determine the
acceptability of a proposal, or provides the offeror with an
opportunity to revise or modify its proposal in some material
respect. FAR § 15.306(d). Accordingly, our Office has confirmed
that where communications do not permit an offeror to revise or
modify its proposal, but rather request that the offeror clarify
and confirm what the offeror has already committed to do, those
communications are clarifications and not discussions. ERIE
Strayer Co., B-406131, Feb. 21, 2012, 2012 CPD ¶ 101 at 4-5.
The record here supports the Army’s position that it sought only
clarifications from the offerors, and then made award based on
the initial proposals as clarified. Notwithstanding PSI’s
arguments, our review of the record shows that the questions
posed to PSI and LSI were indeed clarifications--requests for
each offeror to supply information clarifying the basis for
statements in its proposal, or confirming what the offeror
intended by a statement within its proposal. Thus, for example,
where PSI’s proposal indicated reuse of software code without
making clear from which system the code was being reused or the
status of the development of that code, the Army properly sought
a clarification from PSI. None of the Army’s ENs invited either
firm to revise its proposal. Accordingly, we agree with the Army
that it did not conduct discussions, and we deny PSI’s assertion
that the Army held defective discussions by failing to identify
other weaknesses in PSI’s proposal that could have been
addressed only through proposal revisions. (Pinnacle
Solutions, Inc., B-406998, B-406998.2, Oct 16, 2012) (pdf)
Finally, L-3
contends that the agency acted unreasonably in not conducting
discussions with the offerors. The protester argues that it is
clear from the record that each of the offerors and the agency
lacked a common understanding of the scope of the requirements
of this contract. L-3 believes that the differences in proposed
price prove its contention that there were significant
differences in the offerors’ perceptions of the scope of work.
Comments at 4. Therefore, the protester argues that the agency
should have either amended the RFP to make its expectations
about each project more clear or conducted discussions with the
offerors. Id. at 4-5.
The contracting officer’s discretion in deciding not to hold
discussions is quite broad. Trace Sys., Inc., B-404811.4,
B-404811.7, June 2, 2011, 2011 CPD ¶ 116 at 5. There are no
statutory or regulatory criteria specifying when an agency
should or should not initiate discussions, and there is also no
requirement that an agency document its decision not to initiate
discussions. Id. As a result, an agency’s decision not to
initiate discussion is a matter that we generally will not
review. Booz Allen Hamilton Inc., B-405993, B-405993.2, Jan. 19,
2012, 2012 CPD ¶ 30 at 13.
The agency argues, and we agree, that the RFP, coupled with the
agency’s responses to the 167 questions it had received
regarding the RFP, and the fact that both the protester and the
awardee are incumbents currently performing tasks that are
substantially similar to the tasks required under the RFP at
issue, provided the parties involved here with a common
understanding of the scope of the contract. Further, while the
RFP set out a common scope of work, the proposal instructions
also anticipated that offerors would propose different
approaches to achieving the desired outcomes. Therefore, we find
no basis on which to sustain this protest ground. (L-3
Services, Inc., B-406292, Apr 2, 2012) (pdf)
Post-Final
Proposal Exchanges with Lockheed
Next, CH2M Hill argues that NSF improperly reopened discussions
with Lockheed concerning its cost proposal after the submission
of the final round of proposal revisions. Supp. Protest (Feb.
17, 2012). Specifically, the protester contends that an exchange
between NSF and Lockheed on December 5, 2011, constituted
discussions because it permitted the awardee to revise its cost
proposal. Id. NSF responds that the exchanges with Lockheed
constituted clarifications, rather than discussions. We agree
with the agency.
If an agency holds or reopens discussions with one offeror, it
must hold discussions with all offerors whose proposals are in
the competitive range. Federal Acquisition Regulation (FAR) §
15.306(d)(1); Environmental Quality Mgmt., Inc., B-402247.2,
Mar. 9, 2010, 2010 CPD ¶ 75 at 6. Clarifications, however, are
limited exchanges that agencies may conduct to allow offerors to
clarify certain aspects of their proposals or to resolve minor
or clerical mistakes. FAR §15.306(a)(2); Booz Allen Hamilton,
Inc., B-405993, B-405993.2, Jan. 19, 2012, 2012 CPD ¶ 30 at 12.
An agency may allow an offeror to correct a mistake or clerical
error in a cost proposal through clarifications (as opposed to
discussions); both the existence of the mistake or clerical
error and the amount intended by the offeror must be apparent
from the face of the offer. Joint Venture Penauillie Italia
S.p.A; Cofathec S.p.A; SEB.CO S.a.s; CO.PEL.S.a.s., B-298865,
B-298865.2, Jan. 3, 2007, 2007 CPD ¶ 7 at 8. Requesting
clarification from one offeror does not trigger a requirement
that the agency seek clarification from other offerors. Serco
Inc., B-406061, B-406061.2, Feb. 1, 2012, 2012 CPD ¶ 61.
During discussions, NSF noted that Lockheed’s June 11, 2011,
cost proposal appeared to have a discrepancy between the hours
proposed in attachment L-9, which was to address the labor costs
for the prime contractor, and attachment L-10, which was to
address the combined labor costs for the prime contractor and
its proposed subcontractors. AR, Tab 028-05, Lockheed Discussion
Question (Sept. 14, 2011). In particular, the agency stated that
“[t]he L-9 staffing hours seem to be quite high and do not match
the direct labor dollars proposed.” Id. The agency further noted
that the labor hours listed in attachment L-10 for the base year
appeared to have a mathematical error, and should have been
[deleted], instead of [deleted] hours. Id. In contrast,
attachment L-9, which should have contained only the prime
contractor hours, totaled [deleted] hours--which appeared to be
overstated. Id. NSF requested that Lockheed explain the
discrepancy.
In response, Lockheed confirmed that the agency’s calculation
for attachment L-10 was correct, and should have reflected
[deleted] hours for the prime and subcontractor hours. AR, Tab
028-05, Lockheed Discussion Response, (Sept. 30, 2011). The
awardee stated that the error within attachment L-10 was due to
the omission of certain hours for a subcontractor. Id. With
regard to the discrepancy between attachments L-9 and L-10, the
awardee explained that attachment L-9 had double-counted the
hours for Lockheed Martin Systems Integration (LMSI), resulting
in the overstated amount. Id.
Despite these discussions regarding Lockheed’s double-counting
error, the agency subsequently noted an error in the awardee’s
October 25 revised proposal, which was the final proposal
requested from offerors. The agency sent a letter to Lockheed on
December 2 “seeking clarification to confirm what appears to be
a clear mistake in the total staffing hours assigned to
Attachment L-9 in your Final Proposal Revision.” AR, Tab 028-02,
Letter from Agency to Lockheed (Dec. 2, 2011), at 1.
The agency’s clarification request noted that the September 2011
discussions, cited above, had confirmed that Lockheed had
erroneously double-counted hours for LMSI, resulting in an
overstated labor hour amount for attachment L-9, and therefore a
discrepancy between attachments L-9 and L-10. Id. The agency
stated that its review of Lockheed’s October 25 proposal
identified what the agency believed was “the same inconsistency
between the completed Attachment L-9 and Attachment L-10.” Id.
The agency provided two tables summarizing what the agency
believed was the same double-counting error, resulting in a
discrepancy between what appeared to be the correct number of
hours in attachment L-10, and a higher amount for attachment
L-9. Id. at 2-3. NSF requested that Lockheed confirm that the
proposed amount for attachment L-10 of [deleted] for the base
and option periods was correct. Id. at 3.
On December 5, Lockheed advised the agency that it “confirms the
result of the [NSF’s] analysis and concurs with the results
stated in the letter. There is no change to our proposed price.”
AR, Tab 028-03, Letter from Lockheed to Agency (Dec. 5, 2011),
at 1.
In the selection decision, the SSA noted that the exchanges with
Lockheed had taken place, and described them as follows:
NSF sought clarification from Lockheed concerning a clear
mistake in recording in the total staffing hours proposed by
the offeror as set forth in its completed Attachment L-9 as
described in the Contract Officer’s letter dated December 2,
2011. Lockheed confirmed NSF’s analysis of the mistake by
letter dated December 5, 2011.
AR, Tab 19-05, SSD, at 7.
CH2M Hill argues that NSF’s December 2 request to Lockheed
constituted discussions, rather than clarifications, because the
agency had no basis to conclude that Lockheed had made a
mistake, nor any basis to know what the awardee had intended to
propose as its costs. The protester, in essence, argues that the
exchanges between the agency and awardee permitted Lockheed to
revise its proposal by resolving a discrepancy in its proposal
that was not obvious on its face.
As shown above, however, NSF was made aware as a result of
discussions with Lockheed in September 2011 that the awardee had
made an error in its June 11 proposal by double-counting the
proposed hours for LMSI in attachment L-9 of its cost proposal.
The agency subsequently noted what appeared to be the same error
in Lockheed’s October 25 proposal, that is, a double-counting of
LMSI’s hours in attachment L-9, which again resulted in an
apparent discrepancy between attachments L-9 and L-10. AR, Tab
028-02, Letter from Agency to Lockheed (Dec. 2, 2011), at 1. The
agency therefore asked Lockheed to confirm the agency’s
understanding that the double-counting error resulted in an
overstated amount for attachment L-9, and that attachment L-10
showed the correct number of labor hours for the base and option
years; the agency did not, however, provide the awardee an
opportunity to submit a revised cost. On this record, we
conclude that NSF’s exchanges with Lockheed on December 5
constituted a clarification of a mistake, and not discussions.
Additionally, CH2M Hill contends in its February 17 supplemental
protest that there is a discrepancy between the proposed labor
hours for the base year in attachment L-10 of Lockheed’s October
25 proposal and, and what the protester assumes was a different
value in attachment L-10 of Lockheed's September 30 proposal--a
discrepancy that the protester argues indicates that the agency
improperly permitted the awardee to revise its proposed cost. In
this regard, the protester notes that offerors were not
permitted to revise their labor hours in the October 25
proposals, as RFP amendments 17 and 18 limited proposal
revisions to non-labor costs. RFP amend. 17 at 3; amend. 18 at
2.
As discussed above, NSF’s September 14 discussions notice asked
Lockheed to confirm whether the labor for the base period
reflected in attachment L-10 should have been [deleted] hours;
Lockheed confirmed that this was correct. AR, Tab 028-02, Letter
from Agency to Lockheed (Dec. 2, 2011), at 3; Tab 028-03, Letter
from Lockheed to Agency (Dec. 5, 2011), at 1. NSF’s December 2
letter advised Lockheed that the agency had again identified a
variance between the labor hour totals for attachments L-9 and
L-10; a table in this letter stated that Lockheed’s October 25
proposal included [deleted] labor hours for the base period in
attachment L-10. AR, Tab 028-02, Letter from Agency to Lockheed
(Dec. 2, 2011), at 2.
The protester argues that because Lockheed confirmed to NSF on
September 30 that its June 11 proposal should have reflected
[deleted] hours in the attachment L-10 summary, the awardee’s
September 30 proposal likely included the same number of labor
hours. Based on this assumption, and the fact that Lockheed’s
October 25 proposal set forth [deleted] hours for option year
one, CH2M Hill argues that NSF must have permitted Lockheed to
revise its proposed labor costs for option year one to [deleted]
labor hours at some point after September 30.
The record shows, however, that CH2M Hill’s assumption is
incorrect. Although Lockheed’s September 30 response to the
discussion question confirmed that its June 11 proposal should
have reflected a total of [deleted] hours for attachment L-10,
Lockheed also revised those proposed costs in its September 30
proposal to [deleted] hours--as it was permitted to do. Supp. AR
(Feb. 23, 2012), attach. 1, Lockheed Cost Proposal (Sept. 30,
2011). Thus, the revised amount was reflected in Lockheed’s
September 30 proposal, as well as its October 25 cost
proposal--which was the subject of the agency’s December 2
request for clarification. For these reasons, we find no basis
to sustain the protest concerning NSF’s clarifications of
Lockheed’s cost proposal after final proposal revisions were
submitted. (CH2M Hill Antarctic
Support, Inc., B-406325, B-406325.2, B-406325.3, Apr 18,
2012) (pdf)
PN&A also asserts
that by seeking clarifications from CPD, but not from PN&A, DOE
treated offerors disparately in its conduct of oral
presentations. PN&A points out in this regard that the
solicitation stated that the TEP may request clarifications
“[f]ollowing the [oral] presentation,” not a week after the oral
presentation. Protester’s Comments at 18; see RFQ at 3. The
protester also seems to argue that the agency engaged in
discussions rather than clarifications with the other vendors,
which would then require that the agency hold discussions with
all vendors. Protester’s Comments at 19.
Agencies have broad discretion as to whether to seek
clarifications from offerors, and offerors have no automatic
right to clarifications regarding proposals. See A.G. Cullen
Constr., Inc., B-284049.2, Feb. 22, 2000, 2000 CPD ¶ 45 at 5-6.
Here, the agency states that its decision to engage in
clarifications with some vendors but not others was the direct
result of the information or lack of information presented in
the oral presentations. Supplemental Agency Report at 4. Given
that PN&A’s oral presentation was unacceptable, we find the
agency reasonably exercised its discretion in not engaging in
clarifications with that firm, given that PN&A would have had to
materially revise its proposal to be considered acceptable.
We also agree with the agency that the post-oral presentation
communications that it had with CPD were clarifications, not
discussions. Our Office examined, in camera, the documentation
surrounding these communications and find that CPD did not
revise its quotation as a result of these communications.
Instead, CPD’s exchanges with the agency were limited to
providing additional explanation for what it had previously
proposed and thus did not constitute discussions. See Northeast
MEP Servs., Inc., B-285963.9, Mar. 8, 2001, 2001 CPD ¶ 66 at 4.
The fact that these exchanges took place one week after CPD’s
oral presentation is not relevant, given that CPD was not given
the opportunity to change its quotation as a result of these
communications. (PN&A, Inc.,
B-406368, Apr 23, 2012) (pdf)
BAH asserts that
the Navy held discussions with VSE, allowing VSE to revise its
cost proposal during exchanges with DCAA, without providing BAH
a similar opportunity to revise its proposal.
VSE’s cost proposal included its proposed indirect rates and an
explanation for the downward adjustment to its rates from its
historic ones. AR, Tab 15, VSE Proposal, Vol. IV, Supporting
Cost Data, at 41-43. As part of its cost realism evaluation, the
CAP requested that DCAA perform rate verifications of both
offerors’ proposals. In the course of its rate verification
audit, DCAA received additional supporting cost data from VSE
which provided a narrative explanation in support of VSE’s
proposed indirect rates, but did not alter the proposed rates.
Id., Tab 19, VSE Global Indirect Rates, at 1-11. The DCAA
considered VSE’s supplemental submission as part of its rate
verification audit, and subsequently provided it to the CAP
which took the information into account as part of its cost
realism evaluation of VSE’s indirect rates. Id., Tab 3, CAP
Report, at 16.
Contrary to BAH’s position, we find that the agency’s exchanges
with VSE did not constitute discussions. In this regard, FAR §
15.306 describes a range of exchanges that may take place
between an agency and an offeror during negotiated procurements.
Clarifications are “limited exchanges” between an agency and an
offeror for the purpose of clarifying certain aspects of a
proposal, and do not give an offeror the opportunity to revise
or modify its proposal. FAR § 15.306(a)(2); Lockheed Martin
Simulation, Training & Support, B-292836.8 et al., Nov. 24,
2004, 2005 CPD ¶ 27 at 8. Discussions, on the other hand, occur
when a contracting officer communicates with an offeror for the
purpose of obtaining information essential to determine the
acceptability of a proposal, or provides the offeror with an
opportunity to revise or modify its proposal in some material
respect. Highmark Medicare Servs., Inc. et al., B-401062.5 et
al., Oct. 29, 2010, 2010 CPD ¶ 285 at 11; Gulf Copper Ship
Repair, Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶ 108 at 6;
see FAR § 15.306(d). When an agency conducts discussions with
one offeror, it must conduct discussions with all other offerors
whose proposals are in the competitive range. Gulf Copper Ship
Repair, Inc., supra.
In situations where there is a dispute regarding whether
exchanges between an agency and an offeror constituted
discussions, the acid test is whether an offeror has been
afforded an opportunity to revise or modify its proposal. Id.;
Priority One Servs., Inc., B-288836, B-288836.2, Dec. 17, 2001,
2002 CPD ¶ 79 at 5. Communications that do not permit an offeror
to revise or modify its proposal, but rather permit the offeror
to explain or clarify what the offeror has already proposed to
do, are clarifications and not discussions. Allied Tech. Group,
Inc., B-402135, B-402135.2, Jan. 21, 2010, 2010 CPD ¶ 152 at 6;
SRS Tech., B-291618.2, B-291618.3, Feb. 24, 2003, 2003 CPD ¶ 70
at 3 n.4.
We agree with the agency that the supplemental cost information
provided by VSE to DCAA during the audit agency’s rate
verification audit constituted clarifications rather than
discussions. First, the exchange was not undertaken with the
intent of allowing the offeror to revise its proposal. See FAR §
15.306(d); Warden Assocs., Inc., B-291238, Dec. 9, 2002, 2002
CPD ¶ 215 at 3; MG Indus., B-283010.3, Jan. 24, 2000, 2000 CPD ¶
17 at 9. In this regard, we note that the FAR provides for a
contracting agency when conducting a cost proposal analysis to
request audit assistance from DCAA. See FAR § 15.404-2(c)(1). It
is clear from the record that the DCAA audit of VSE was intended
as a means of gathering information for use in the Navy’s cost
evaluation and possible future discussions; it was not initiated
for the purpose of holding discussions with VSE, which are to be
conducted by the contracting officer. See FAR § 15.306(d)(1).
Further, VSE did not revise its proposal so as to cure proposal
deficiencies or material omissions, materially alter the
technical or cost elements of the proposal, or otherwise revise
the proposal to make it acceptable. See eMind, B-289902, May 8,
2002, 2002 CPD ¶ 82 at 5. The acceptability of VSE’s proposal
simply did not turn on the additional information furnished to
DCAA. In sum, VSE’s exchange with DCAA did not involve revising
its proposed indirect cost rates, but rather, was limited to
providing additional explanation for what it had previously
proposed. See Northeast MEP Servs., Inc., B-285963.9, Mar. 8,
2001, 2001 CPD ¶ 66 at 4. In these circumstances, there is no
basis to conclude that DCAA or the Navy improperly conducted
discussions with only one offeror. (Booz
Allen Hamilton, Inc., B-405993,B-405993.2, Jan 19, 2012)
(pdf)
Analytic asserts
that the agency improperly failed to request that Analytic
clarify aspects of the firm’s proposal relating to the evaluated
proposal weaknesses. Protest at 7; Comments at 2-3. Analytic
points out that the solicitation stated that the agency would
consider the “correction potential” of proposals. Protest at 7
n.1 (referencing RFP § M.1.4). According to Analytic, each
proposal weakness was “readily correctable or explainable.”
Protest at 7; see also Comments at 3. The agency responds that
given the magnitude of Analytic’s proposal weaknesses, material
proposal revisions would be required to render the proposal
acceptable, and, therefore, the weaknesses were not properly the
subject of clarifications. Contracting Officer’s Statement at
10; Memorandum of Law at 5.
Clarifications are “limited exchanges” that agencies may use to
allow offerors to clarify certain aspects of their proposals or
to resolve minor or clerical mistakes. Federal Acquisition
Regulation § 15.306(a)(2). Agencies are not required to request
clarifications in the context of an award, such as the one here,
made without discussions. Id. § 15.306(a)(1); Government
Telecomm., Inc., B-299542.2, June 21, 2007, 2007 CPD ¶ 136 at 8;
AIA-Todini-Lotos, B-294337, Oct. 15, 2004, 2004 CPD ¶ 211 at 12.
Analytic’s proposal was deemed unacceptable. Providing Analytic
with an opportunity to correct the weaknesses would constitute
discussions, not clarifications, because it would involve the
submission of information necessary to make the proposal
acceptable. Gemmo-CCC, B-297447.2, July 13, 2006, 2006 CPD ¶ 182
at 5; Lockheed Martin Simulation, Training & Support, B-292836.8
et al., Nov. 24, 2004, 2005 CPD ¶ 27 at 8. (Analytic
Services, Inc., B-405737, Dec 28, 2011) (pdf)
Clearly stated
RFP requirements are considered material to the needs of the
government, and a proposal that fails to conform to material
terms is unacceptable and may not form the basis for award.
National Shower Express, Inc.; Rickaby Fire Support, B-293970,
B-293970.2, July 15, 2004, 2004 CPD para. 140 at 4-5. It is a
fundamental principle in a negotiated procurement that a
proposal that fails to conform to a material solicitation
requirement is unacceptable. See TYBRIN Corp., B-298364.6,
B-298364.7, Mar. 13, 2007, 2007 CPD para. 51 at 5. Here, we
conclude that the objectives set forth in Table 1 were material
requirements of the RFP, and that the agency reasonably
determined that M1 improperly modified an objective in a manner
that did not conform to the terms of the RFP.
Under a performance-based contracting arrangement, such as here,
performance metrics are more than mere proposal evaluation
tools. Rather, the metrics become the standards used to assess
the contractor during performance, and to determine the
application of contractor-proposed performance incentives and
disincentives. Indeed, the objectives, measures, metrics, ALQ,
and incentives/disincentives serve to establish the performance
levels that are required to meet the needs of the agency, as
specified in the SOO, and are critical aspects of the resulting
performance-based contract. In this case, the agency pre‑printed
Table 1 – Performance Metrics with statements of its objectives,
and repeatedly cautioned offerors that these objectives were not
to be revised. Such clearly stated RFP terms, which establish
the obligations of the parties during performance, are
undoubtedly material to the needs of the government; failure to
conform to these terms rendered this proposal unacceptable.
Here, the objective, "[i]ncrease use of small business
subcontractors and teaming partners to bring expert talent and
ingenuity to the varied work under ITS-SB,” was clearly focused
on increasing the use of small business subcontractors and
teaming partners, rather than subcontractors and teaming
partners generally. See COSF, at 18. In contrast, the modified
objective proposed by M1, "[i]ncrease use of subcontractors and
teaming partners to bring expert talent and ingenuity to the
varied work under ITS-SB,” makes no reference to small business,
and thus entirely fails to reflect the import of the agency's
objective.
This failure to reflect the agency's objective is even more
clear when one considers M1's proposed measure, metric and ALQ
for objective 1.c. As its measure for objective 1.c, M1 proposed
an "[i]ncrease in the amount of work shared with M1 partners.”
As its metric, M1 proposed "total M1 direct labor performed by
subcontractors compared to the total direct labor.” Finally, as
its ALQ, M1 proposed "base period minimum [DELETED]% [Option]
Period minimum [DELETED]%.” Proposal, Volume 1, at 21-22.
Our review of M1's proposal leads us to conclude that none of
these performance metrics conform to the agency's objective of
increasing the use of small businesses. Turning to M1's
subcontractor participation goals, M1 proposed to subcontract a
minimum of [DELETED] percent of the work under the contract,
consisting of [DELETED] percent to small business
subcontractors, and [DELETED] percent to large business
subcontractors. Id., Volume 4, Section 2, at 3. Thus, M1's
performance metrics for Objective 1.c, along with its omission
of the phrase "small business” from the objective itself, would
enable M1 to meet objective 1.c by subcontracting [DELETED]
percent of the work under the contract to a combination of small
businesses or large businesses. More importantly, in the option
years, the proposed metric would allow M1 to meet its increased
target of [DELETED] percent subcontracting by expanding
subcontracting solely to large businesses, which clearly fails
to meet the agency's actual objective of increasing the use of
small business subcontractors, as set forth in the SOO, and in
Table 1.
M1 next argues that despite any failure to meet the requirements
of the RFP under objective 1.c, it should not have received a
deficiency because it agreed to meet the agency's subcontracting
objectives elsewhere in its technical proposal. For example, M1
correctly stated the agency's objective under entry 1.d of Table
1, "[e]ffectively use small business to assure achievement of
subcontracting targets allowing mentorship of small business.”
Id., Volume 1, at 22. M1's commitment to meet the agency's
intended objective under 1.d of Table 1, however, relates to its
proposed minimum small business subcontracting target. This is
fundamentally different from the import of objective 1.c of
Table 1, which related to increasing small business usage over
the life of the contract. Given the inherent difference, there
is no basis to conclude that the agency's evaluation was
unreasonable.
Finally, M1 asserts that the agency was required to allow M1 the
opportunity to correct its error through clarifications.
Clarifications are limited exchanges between the agency and
offerors that may occur where, as here, contract award without
discussions is contemplated. FAR sect. 15.306(a). An agency may,
but is not required to, engage in clarifications that give
offerors an opportunity to clarify certain aspects of proposals
or to resolve minor or clerical errors. Id. However,
clarifications may not be used to cure proposal deficiencies or
material omissions, materially alter the technical or cost
elements of the proposal, or revise the proposal. Superior
Gunite, B-402392.2, Mar. 29, 2010, 2010 CPD para. 83 at 4.
Because the omission of the phrase "small business” was both a
material omission and a deficiency, the error was not subject to
correction via clarifications. (Mission1st
Group, Inc., B-404811.3; B-404811.6, June 2, 2011) (pdf)
The protester
also contends that, prior to excluding its proposal from the
competitive range, the agency should have sought clarifications
from IMC. The agency responds that the significant weaknesses
and deficiencies in IMC's proposal could not be resolved by
clarifications. See AR at 16-20. Moreover, the agency contends
that it was under no obligation to seek clarifications, in any
event.
FAR sect. 15.306 describes a spectrum of exchanges that may take
place between a contracting agency and an offeror during
negotiated procurements. Clarifications are limited exchanges
between the agency and offerors that may occur when contract
award without discussions is contemplated; an agency may, but is
not required to, engage in clarifications that give offerors an
opportunity to clarify certain aspects of proposals or to
resolve minor or clerical errors. FAR sect. 15.306(a); Satellite
Servs., Inc., B‑295866; B‑295866.2, Apr. 20, 2005, 2005 CPD para.
84 at 2 n. 2. By contrast, discussions--which are to occur after
establishment of the competitive range--involve the agency
indicating to each offeror the significant weaknesses,
deficiencies, and other aspects of its proposal that could be
altered or explained to materially enhance the proposal's
potential for award. FAR sect. 15.306(d)(3).
Where, as here, the agency establishes a competitive range to
conduct discussions, the agency may conduct communications with
an offeror to facilitate the agency's understanding and
evaluation of the offeror's proposal or for the purpose of
exploring whether a proposal should be included in the
competitive range. See FAR sect. 15.306(b)(2). Such
communications, however, cannot "be used to cure proposal
deficiencies or material omissions, materially alter the
technical or cost elements of the proposal, and/or otherwise
revise the proposal." Id.; Battelle Mem'l Inst., B‑299533, May
14, 2007, 2007 CPD para. 94 at 4.
We agree with AID that the agency was not required to seek
clarifications from, or otherwise have communications with IMC,
prior to the establishment of the competitive range. See JBlanco
Enter., Inc., B‑402905, Aug. 05, 2010, 2010 CPD para. 186 at 4,
n.4. Moreover, the significant weaknesses and deficiencies in
IMC's proposal could not properly be the subject of either
clarifications or communications before the establishment of the
competitive range, as this would require material revisions to
IMC's proposal. (International
Medical Corps, B-403688, December 6, 2010) (pdf)
The RFP advised
that the agency would make award on a "best value" basis
considering price and several non-price considerations. The RFP
did not indicate whether the agency intended to conduct
discussions. Keiwit's proposal was assigned a marginal rating
under the technical approach/key personnel evaluation factor for
failure to include certain demolition work. Protest at 3. The
agency proceeded to make award to Boh Bros. on the basis of
initial proposals, without discussions, at a price higher than
Keiwit's.
An agency's intent with regard to discussions is required to be
expressed in the solicitation. Specifically, under the
Competition in Contracting Act (CICA), 10 U.S.C. sect.
2305(a)(2)(A)(ii)(I) (2006), solicitations in negotiated
acquisitions are required to include:
either a statement that the proposals are intended to be
evaluated with, and award made after, discussions with the
offerors, or a statement that the proposals are intended to be
evaluated, and award made, without discussions with the
offerors (other than discussions conducted for the purpose of
minor clarification) unless discussions are determined to be
necessary.
This provision is implemented by Federal Acquisition Regulation
(FAR) sect. 15.209(a), which requires RFPs to include the clause
at FAR sect. 52.215-1(f)(4) if the agency intends to make award
without discussions, or the clause at FAR sect. 52.215-1
alternate 1, if the agency intends to make award after
discussions.
Keiwit asserts that, since the RFP failed to include either of
the above clauses, and the RFP was otherwise silent as to
whether discussions would be conducted, the agency was required
to conduct discussions by default. Keiwit claims that its
omission of the demolition work was a minor error that it easily
could have remedied through discussions, and that the cost of
the demolition work would be lower than the price difference
between its and Boh Bros.' proposals.
First, contrary to Keiwit's position, there is no basis for
finding that the agency was required to conduct discussions
given the RFP's silence on the point. In this regard, Keiwit
cites no statutory or regulatory provision--and we are aware of
none--establishing such a default rule.
Further, in the absence of either of the specified clauses, the
RFP was patently ambiguous as to whether discussions were
contemplated. Under our Bid Protest Regulations, 4 C.F.R. sect.
21.2(a)(1) (2010), protests based on improprieties apparent on
the face of a solicitation must be filed prior to the deadline
for submitting proposals. Here, it was apparent that the RFP did
not include one of the two alternate clauses required to be
included in an RFP to advise offerors of the agency's intention
regarding discussions; as a result, it was unclear whether the
agency would conduct discussions. This being the case, any
question regarding the agency's obligation to conduct
discussions--including Keiwit's assertion that discussions were
required--had to be raised, if at all, prior to the closing time
for receipt of initial proposals. Carter Indus., Inc., B-270702,
Feb. 15, 1996, 96-1 para. 99 at 3-4. Since Keiwit did not
protest prior to the closing time, its assertion that the agency
was required to engage in discussions is untimely, and will not
be considered. (Kiewit Louisiana
Company, B-403736, October 14, 2010) (pdf)
Allied argues
that DOJ improperly conducted discussions only with MGS by
allowing it to submit responses to two questions posed by the
agency. As explained below, we conclude that the exchanges at
issue here did not constitute discussions.
The solicitation, as originally issued, set forth 24 CLINs for
which vendors' quotations were to provide prices: CLIN 0001 was
for transition costs to the new system; CLINs 0002–0023 were for
ARS services for various ranges of DOJ employees potentially
covered by the system; and CLIN 0024 was the "monthly transition
price," if services were needed by the agency for a period of up
to 6 months at the end of the BPA. The agency subsequently
amended the RFQ to clarify that, in terms of pricing CLIN 0024,
vendors' prices would be determined based on the employee range
CLIN being utilized at the end of BPA performance (i.e., the
monthly cost for the transition period would be one-twelfth of
the annual cost of the CLIN the agency was then utilizing). RFQ
amend. 1, at 4. The quotation preparation instructions also
informed vendors that "[a]ll CLINs shall be proposed as firm
fixed prices." RFQ Instructions, at 5. While the SOW required
vendors to provide monthly transition services if needed by the
government, id., the quotation preparation instructions did not
require that vendors' price quotations expressly acknowledge or
agree to perform CLIN 0024.
MGS' price quotation contained the RFQ's price quotation
instruction language, and included prices for CLINs 0001–0023
for the base period and each option period. With regard to CLIN
0024 (Monthly Transition), MGS' quotation stated, "n/a." MGS'
price quotation also contained various narrative comments,
including statements that "CLINs 1 through 23 are proposed as
firm fixed prices," and "[p]ricing does not include Organization
and Change Management, Expunge/Delete Services, as well as
establishment of Dedicated Environments, which will need to be
separately scoped and priced." AR, Tab 14, MGS Price Quotation,
at 3-4.
Following receipt of quotations, the DOJ contracting officer
sent MGS an email asking whether the vendor would allow the
government to extend the contract, if awarded to MGS, on a
monthly basis at a cost of one-twelfth the appropriate CLIN as
stated in the RFQ (as called for by CLIN 0024). Also, with
regard to the comment in MGS' quotation stating that "[p]ricing
does not include Organization and Change Management,
Expunge/Delete Services, as well as establishment of Dedicated
Environments, which will need to be separately scoped and
priced," the agency asked the vendor to "explain what these
services are and if [MGS] is stating it will need to perform
these services to meet the Government's requirement." AR, Tab 5,
MGS Clarifications, at 1.
In its reply, MGS affirmed that it would allow the agency to
extend the contract, if awarded to MGS, on a monthly basis at a
cost of one-twelfth the appropriate CLIN as stated in the RFQ.
Additionally, in response to the second question, MGS stated
that the pricing for all services required by the RFQ was
included in its submitted price quotation, and that "[n]either
Organization and Change Management, nor Expunge/ Delete
Services, nor Dedicated Environments will be required to fulfill
the Government's requirements." Id. at 3.
As discussed above, the RFQ established the agency's intent to
issue a BPA without the use of discussions. Federal Acquisition
Regulation (FAR) sect. 15.306 describes a spectrum of exchanges
that may take place between an agency and offeror during
negotiated procurements. Clarifications are "limited exchanges"
between the agency and offerors that may allow offerors to
clarify certain aspects of proposals or to resolve minor or
clerical errors. FAR sect. 15.306(a)(2). Discussions, on the
other hand, occur when an agency indicates to an offeror
significant weaknesses, deficiencies, and other aspects of its
proposal that could be altered or explained to enhance the
proposal's potential for award. FAR sect. 15.306(d)(3); IPlus,
Inc., B-298020, B-298020.2, June 5, 2006, 2006 CPD para. 90 at
3. The "acid test" for deciding whether discussions have been
held is whether it can be said that an offeror was provided the
opportunity to modify or revise its proposal. Colson Servs.
Corp., B-310971 et al., Mar. 21, 2008, 2008 CPD para. 85 at 13;
Computer Scis. Corp., et al., B-298494.2 et al., May 10, 2007,
2007 CPD para. 103 at 9-10. In our view, the agency's exchange
with MGS here did not constitute discussions.
With regard to CLIN 0024, vendors were not required to submit a
price; rather, the RFQ established how the pricing for CLIN 0024
would be determined (i.e., the monthly transition price would be
one-twelfth of the annual cost of the CLIN that the agency was
utilizing at the time the CLIN was ordered). Further, the RFQ
instructions did not require that vendors' price quotations
expressly acknowledge or agree to perform CLIN 0024. We find
that it was proper for DOJ to allow MGS to address the missing
confirmation regarding the application of CLIN 0024 through a
clarification. See S4, Inc., B-299817, B-299817.2, Aug. 23,
2007, 2007 CPD para. 164 at 7 (agency request for affirmation or
confirmation that offeror would perform a duty already
encompassed by the solicitation was a clarification); Kuhana-Spectrum
Joint Venture, LLC, B-400803, B-400803.2, Jan. 29, 2009, 2009
CPD para. 36 at 10 (offeror's missing affirmation of its
representations and certifications correctable through a
clarification). Moreover, as MGS' quotation stated that its
prices for CLINs 0001-0023 were all fixed prices, and the
pricing for CLIN 0024 was to be mechanically derived from the
vendor's other CLINs, we find no merit in Allied's argument that
MGS had not agreed to a firm-fixed price for CLIN 0024.
Similarly, we conclude that the exchange between DOJ and MGS
regarding the quotation's reference to Organization and Change
Management, Expunge/Delete Services, and Dedicated Environments
was a clarification and not discussions. The contracting officer
contacted MGS for explanation regarding a specific comment in
MGS' price quotation. MGS responded that the submitted prices
covered all ARS services required by the RFQ, and that while its
price quotation did not include Organization and Change
Management, Expunge/Delete Services, and Dedicated Environments,
neither were such services required to fulfill the RFQ's stated
requirements. In our view, as the contracting officer merely
sought to clarify MGS' price quotation, and MGS was not given an
opportunity to materially change its price quotation, the
exchanges constituted a permissible clarification. See IPlus,
Inc., supra; Park Tower Mgmt. Ltd., B-295589, B-295589.2, Mar.
22, 2005, 2005 CPD para. 77 at 7. (Allied
Technology Group, Inc., B-402135; B-402135.2, January
21, 2010) (pdf)
TAG asserts that
the agency improperly conducted discussions with SAIC without
similarly affording it an opportunity to revise its quotation.
According to the protester, this was prejudicial because the
agency identified a number of significant weaknesses in its
quotation that it could have addressed in discussions.
Generally, discussions occur where a firm is afforded an
opportunity to make a material revision to its proposal or
quotation. Global Analytic Info. Tech. Servs., Inc., B‑298840.2,
Feb. 6, 2007, 2007 CPD para. 57 at 5.
Although the agency purportedly made award on the basis of
initial quotations, without engaging in discussions with either
party, the record shows that, subsequent to the submission of
quotations and the oral presentations, the agency and SAIC had
an exchange concerning the following indemnification provision
included in SAIC’s quotation relating to performing contract
activities in a high-threat environment:
Customer agrees to save and hold harmless SAIC and its
directors, officers, agents, employees and subcontractors
(collectively, ‘SAIC’) from and against any demands, claims,
suits, legal or administrative proceedings, damages, losses,
costs, expenses, actions or causes of actions, and liabilities
(including reasonable attorney’s fees) (‘Damages’) that are
asserted against or incurred by SAIC which arise out of,
directly or indirectly, or relate in any way to any act or
omission by SAIC, during the performance of services under
this contract. SAIC agrees to promptly notify Customer of any
claim for Damages against SAIC that is covered by this
provision.
SAIC Written Price Quotation, Tab E, Assumptions and other
Administrative Data, sect. 5.12.6. The record shows that the
agency contacted SAIC in connection with this provision, AR, exh.
19, at 15, and that, in response, SAIC removed the indemnity
provision from its quotation. AR, exh. 18. The agency asserts
that its exchange with SAIC was merely a clarification of the
quotation, and therefore did not trigger the requirement for it
to hold discussions with TAG.
An open-ended indemnification clause such as this cannot legally
be included in a government contract because it would subject
the government to unknown liability; as a result, it creates a
potential violation of the Antideficiency Act, 31 U.S.C. sect.
1341 (2006). Assumption by Gov’t of Contractor Liability to
Third Persons--Recon., B-201072, May 12, 1983, 83-1 CPD para.
501 at 6. Thus, the inclusion of the indemnification provision
in SAIC’s quotation rendered the quotation as submitted
ineligible for selection. By affording SAIC an opportunity to
remove the indemnification clause from its quotation, the agency
essentially allowed SAIC to make its unacceptable quotation
acceptable. This unquestionably constituted a material revision
to the quotation and, therefore, discussions. Since discussions
with SAIC occurred, the agency was obliged to afford TAG a
similar opportunity to participate in discussions. Global
Analytic Info. Tech. Services., Inc., supra.
The agency also asserts that, even if the exchange resulted in a
modification of SAIC’s quotation, this was unobjectionable
because, in the context of an RFQ that does not include a late
submission provision (the case here), agencies are free to
accept late modifications to quotations. This argument is
without merit. While the agency is correct that there is an
exception to the general rule against acceptance of a late
submission in the context of an RFQ that does not include a late
submission provision, see KPMG Consulting, LLP, B-290716,
B-290716.2, Sept. 23, 2002, 2002 CPD para. 196 at 11-12, the
exception only applies where the agency’s acceptance of such a
late submission would not be prejudicial to any other
competitor. Id. Allowing one firm an opportunity to revise its
quotation without also allowing the other firms in the
competition a similar opportunity--that is, unequal
treatment--is precisely the prejudice to which the standard
refers. Compare Payne Constr., B-291629, Feb. 4, 2003, 2003 CPD
para. 46 at 6 (other competitors were not prejudiced by agency’s
acceptance of late submission from protester because they had
been afforded an opportunity to revise their quotations). Thus,
while the agency indeed was permitted to accept a late
modification from SAIC, it was required to provide equal
treatment to the protester by providing it an opportunity to
revise its quotation. Because the agency did not do so, we
sustain the protest on this ground. (The
Analysis Group, LLC, B-401726; B-401726.2, November 13,
2009) (pdf)
As described
earlier, in a supplemental protest, filed timely after Kuhana-Spectrum
received additional documents with the agency report, the firm
argues that the Navy conducted discussions with Chesapeake to
allow it to correct omissions in its proposal. Kuhana-Spectrum
argues that once the Navy communicated with Chesapeake (and
allowed it to remedy a problem with its proposal), the Navy was
required to hold discussions with Kuhana-Spectrum also, to allow
it to improve its proposal. Supp. Protest at 2.
The Navy responds, first, that it properly concluded that the
omissions in Chesapeake’s proposal were either immaterial, or
could be corrected via clarifications. Specifically, the Navy
argues that Chesapeake constructively acknowledged each of the
material amendments to the RFP, and that a failure to
acknowledge the non-material amendments was properly waived.
Specifically, in its supplemental agency report, the Navy
explains that amendments 1, 3, 4, 6, and 7 were not material
because they dealt with administrative details of the
procurement process, such as extensions of the proposal due
date, or they merely provided background information to the
offerors. Supp. AR at 6-7. The Navy explains that, in its view,
amendments 2 and 5 were material, however, and therefore had to
be acknowledged.
Specifically, the Navy explains that amendment 2 changed the
healthcare specialties identified in several of the lots for the
initial 8-month period. However, Chesapeake’s proposal included
pricing for the revised lots set forth in amendment 2. As a
result, the Navy concluded that Chesapeake constructively
acknowledged amendment 2 by using the revised lots in its
proposal. Supp. AR at 7. Similarly, the Navy explains that
amendment 5 added two new MTF locations to the contract
requirements. Chesapeake’s proposal included a discussion of the
firm’s approach to staffing both of the new locations, and
therefore the Navy concluded that the firm had constructively
acknowledged that amendment as well. Id. Finally, with respect
to Chesapeake’s failure to complete DFARS sect. 252.247-7022,
the Navy concluded that the provision should not have been
included in the RFP, and Chesapeake’s error in failing to
respond to it was properly waived. Id. at 8.
The Navy further argues that after concluding that Chesapeake
had constructively acknowledged each of the material amendments
to the RFP, and after concluding that the provision at DFARS
sect. 252.247-7022 should not have been included in the RFP, the
agency only needed to confirm that Chesapeake’s online
representations and certifications were valid. It was this
confirmation that the Navy concluded could be accomplished
through clarifications. Since the Navy states that its
communications with Chesapeake were merely a clarification, the
agency argues that it was not required to open discussions with
Kuhana-Spectrum. Supp. AR at 14.
We agree with the Navy on both issues. First, we think that the
Navy reasonably concluded that Chesapeake’s proposal
constructively acknowledged both of the material amendments to
the RFP. As a general rule, an offeror’s failure to acknowledge
a material amendment renders the proposal unacceptable, and such
proposals may not form the basis for award. However, an
amendment may be constructively acknowledged where the proposal
includes the material items appearing only in the amendment.
See, e.g., Language Servs. Assocs., Inc., B‑297392, Jan. 17,
2006, 2006 CPD para. 20 at 6 (quotation constructively
acknowledged amendment to RFQ).
Second, we agree with the Navy that it was proper to allow
Chesapeake to correct the missing affirmation of its ORCA
entries through a clarification. Offerors may be given the
opportunity to clarify certain aspects of proposals without
holding discussions. FAR sect. 15.306(a). Specifically, an
agency may allow an offeror to correct missing representations
and certifications through clarifications, and does not hold
discussions by doing so. Doty Bros. Equip. Co., B‑274634, Dec.
19, 1996, 96‑2 CPD para. 234 at 2 n.1 (protest sustained where
agency improperly rejected proposal based on failure to
acknowledge immaterial amendment and failure to complete
standard representations and certifications). Accordingly, the
Navy did not hold discussions with Chesapeake, and was not
required to hold discussions with Kuhana-Spectrum. (Kuhana-Spectrum
Joint Venture, LLC, B-400803; B-400803.2, January 29, 2009)
(pdf)
The protester argues that the agency’s request for clarification
of the basis for the offerors’ rebate amounts constituted
discussions because this information was necessary to determine
their proposed prices, and that the SBA’s initiation of
discussions in one area obligated the agency to conduct
discussions regarding all significant weaknesses in offerors’
proposals. As previously noted, the contracting officer
asked both offerors to clarify whether their rebate amounts were
on a monthly or an annual basis, but did not otherwise
communicate with them regarding the content of their proposals.
The contracting officer sought clarification of the basis for
the rebate amounts after being advised by the chairperson of the
technical evaluation team that since the RFP included language
providing that “[t]he rebate will be made to SBA monthly,” RFP
at 3, the rebate amounts entered by the offerors on their price
schedules should be considered monthly amounts. The contracting
officer apparently questioned whether the two offerors had
indeed interpreted the RFP in this manner. Section 15.306
of the FAR describes a spectrum of exchanges that may take place
between an agency and an offeror during negotiated procurements.
Clarifications are “limited exchanges” between the agency and
offerors that may allow offerors to clarify certain aspects of
proposals or to resolve minor or clerical errors. FAR sect.
15.306(a)(2). Discussions, on the other hand, occur when an
agency indicates to an offeror significant weaknesses,
deficiencies, and other aspects of its proposal that could be
altered or explained to enhance materially the proposal’s
potential for award. FAR sect. 15.306(d)(3); IPlus, Inc.,
B-298020, B‑298020.2, June 5, 2006, 2006 CPD para. 90 at 3. The
“acid test” for deciding whether discussions have been held is
whether it can be said that an offeror was provided the
opportunity to modify or revise its proposal Computer Sciences
Corp. et al., B-298494.2 et al., May 10, 2007, 2007 CPD para.
103 at 9.
In our view, the exchanges here did not constitute discussions
because neither offeror was given the opportunity to revise its
proposal; rather, each was merely given the opportunity to
clarify the basis on which it had understood the RFP to be
requesting pricing. Regarding the protester’s argument that
either offeror could have revised its proposal by “offer[ing] a
response that was a change from the originally submitted
approach,” Protester’s Comments, Jan. 25, 2008, at 4 n.3, this
is essentially an argument that either offeror could have
revised its price by misrepresenting the basis for its original
pricing--that is, by representing that its rebate amounts had
been offered on an annual basis when it had in fact intended
them to be on a monthly basis (or vice-versa). Presumably, the
protester is not arguing that it would have engaged in such a
misrepresentation, and, in any event, we do not think that the
opportunity to increase or decrease a price 12-fold, which is
the only revision that could have been achieved through such a
misrepresentation, represents a meaningful opportunity to revise
pricing.
(Colson Services Corporation,
B-310971; B-310971.2; B-310971.3, March 21, 2008) (pdf)
Silynx asserts that the agency unreasonably failed to conduct
discussions. The protester maintains that, because the agency’s
initial technical evaluation was flawed, it had no reasonable
basis to distinguish between the proposals for purposes of
making a best value determination. Silynx claims that our
decision in The Jonathan Corp; Metro Mach. Corp., B-251698.3,
B‑251698.4, May 17, 1993, 93‑2 CPD para. 174 at 13-15, aff’d,
Moon Eng’g Co.--Recon., B‑251698.6, Oct. 19, 1993, 93‑2 CPD para.
233 at 3-4, requires agencies to hold discussions where there is
no reasonable basis to distinguish between proposals. The agency
was not required to conduct discussions here. The RFP
incorporated Federal Acquisition Regulation (FAR) sect.
52.212-1, which expressly advised offerors of the agency’s
intent to make award without discussions. Further, the
circumstances here are distinguishable from those in Jonathan.
In that case, there was no clear basis to distinguish among the
cost proposals due to the degree to which they varied from the
government estimate, and our finding was that the agency had
failed to conduct a reasonable cost evaluation; in effect, we
found, the agency could not determine from the initial
evaluation which proposal offered the lowest overall cost to the
government. Here, in contrast, the agency had a clear basis for
distinguishing between the proposals--the acceptability of
Nacre’s proposal and the unacceptability of Silynx’s. Therefore,
the Jonathan rationale is inapplicable here, and the agency’s
decision not to conduct discussions was legally unobjectionable
in these circumstances. (Silynx
Communications, Inc., B-310667; B-310667.2, January 23,
2008) (pdf)
CTC essentially argues that it submitted an acceptable
subcontracting plan, and contends, in the alternative, that even
its plan was unacceptable, the agency was required to advise CTC
of the problems with the plan and provide the company an
opportunity to revise it. Here, as explained above, the RFP
required offerors to submit a detailed subcontracting plan, and
listed “subcontracting plan” as one of four equally-rated
technical evaluation factors. The RFP specifically stated that
subcontracting plans would be evaluated to determine the extent
to which offerors identify and commit to subcontracting with
small businesses, the realism of the plan, the prior performance
of the offeror in complying with subcontracting requirements,
and the extent of participation of subcontractors in terms of
the value of the total acquisition and the ability to meet
mandated goals. At the conclusion of this review, CTC’s
subcontracting plan was determined to be unacceptable because
CTC failed to provide the requested information. CTC in its
protest submissions does not argue that its plan was responsive
to the RFP requirements, but rather, CTC argues that its
subcontracting plan was identical to the plan it submitted in
response to a previous solicitation and that the agency was
required by the Federal Acquisition Regulation (FAR) 19.702 to
allow CTC to clarify its subcontracting plan. We do not
agree. The record here shows that CTC submitted an inadequate
subcontracting plan in that it was not responsive to the
specific requirements of the RFP. Since the solicitation advised
offerors that the agency intended to make award without
discussions, the protester could not presume that it would have
a chance to correct deficiencies and weaknesses through
discussions. The burden was on CTC to submit an initial
proposal, complete with a subcontracting plan that adequately
demonstrated its merits, and the protester ran the risk of
rejection by failing to do so. DRT Assocs., Inc., B-237070, Jan.
11, 1990, 90-1 CPD para. 47 at 2. There is no basis in this
record for concluding that the decision to award without
discussions was improper, or that the rejection of CTC’s
subcontracting plan was unreasonable. (Central
Texas College, B-309947, October 12, 2007) (pdf)
The solicitation expressly provided that the agency intended to
make award without discussions and the agency did in fact make
award without holding discussions. FAR sect. 15.306(a)(2), which
addresses clarifications and award without discussions, states
in relevant part that where an award will be made without
conducting discussions, “offerors may be given the opportunity
to clarify certain aspects of proposals . . . or to resolve
minor or clerical errors.” Pursuant to this provision, an agency
has broad discretion to decide whether to engage in
clarifications with an offeror. INDUS contends that the agency
acted unreasonably by not allowing it to correct this aspect of
its proposal through clarifications since it had allowed other
offerors to clarify certain aspects of their price proposals. An
agency, however, generally has the discretion to decline to seek
clarifications from an offeror, even where the agency has
engaged in clarifications with other offerors. See General
Dynamics--Ordnance & Tactical Sys., B-295987, B-295987.2, May
20, 2005, 2005 CPD para. 114 at 9 n.4; Landoll Corp., B-291381
et al., Dec. 23, 2002, 2003 CPD para. 40 at 8. While we
recognize that there may be a rare situation where it would be
unfair to request clarification from one offeror but not from
another, the mere fact that an agency requests clarification
from one offeror and not another, does not constitute unfair
treatment. General Dynamics--Ordnance & Tactical Sys., supra;
see also, FAR sect. 1.102-2(c)(3) (providing that “[a]ll
contractors and prospective contractors shall be treated fairly
and impartially but need not be treated the same”). As a
consequence, INDUS has not established that the agency acted
improperly or in contravention of the FAR by not seeking to
clarify the acceptance period of INDUS’s proposals. As a final
matter, INDUS contends that GSA acted unfairly by not affording
it the opportunity to extend the acceptance periods of its
proposals as it had done for other offerors. This argument,
however, is misplaced. GSA only sought extensions from those
offerors whose proposals had been found to comply with the RFP’s
requirements, including the provision regarding the minimum
acceptance period. As noted above, INDUS’s proposals were
excluded from the competition under the terms of the RFP for
failing to offer the minimum acceptance period. Since its
proposals already had failed the agency’s initial “acceptability
review,” and, as a result, had been excluded from the
competition as noncompliant, GSA did not engage in unequal
treatment of offerors by inviting only those offerors with
compliant proposals, and not INDUS, to extend the acceptance
period of their proposals. In sum, given the explicit language
in the RFP establishing a required minimum acceptance period of
350 days, and in the absence of a timely challenge to this
provision, we have no basis to object to the agency’s rejection
of protester’s proposals given the language in its cover letters
limiting the acceptance period of its proposals to 180 days.
(INDUS Technology, Inc.,
B-297800.13, June 25, 2007) (pdf)
Finally, SSI contends that the agency improperly decided not to
conduct discussions with offerors. SSI asserts that, had
discussions been conducted SSI could have addressed the various
weaknesses in its proposal. Where, as here, an RFP
provides for award on the basis of initial proposals without
discussions, an agency may make award without discussions,
unless discussions are determined to be necessary. FAR sect.
15.306(a)(e). While discussions are necessary where the
solicitation provides for award on a best value basis and the
source selection official is unable to determine without further
information which proposal represents the best value to the
government, an agency may dispense with discussions where there
is a reasonable basis to conclude that the proposal of the
intended awardee represents the best overall value. Facilities
Mgmt. Co., Inc., B-259731.2, May 23, 1995, 95-1 CPD para. 274 at
8. The contracting officer has broad discretion in deciding
whether to hold discussions, which our Office will review only
to ensure that it was reasonably based on the particular
circumstances of the procurement. Incident Catering Servs., LLC,
B-296435.2 et al., Sept. 7, 2005, 2005 CPD para. 193. Here, as
discussed above, the agency had a reasonable basis for
evaluating proposals, for performing a meaningfully comparison
of the those proposals, and for making a determination regarding
which proposal offered the best value to the government. See
Sierra Military Health Servs., Inc.; Aetna Gov’t Health Plans,
B‑292780 et al., Dec. 5, 2003, 2004 CPD para. 55 at 6-7 n.5. The
decision not to conduct discussions was reasonable under the
circumstances. (Synectic Solutions,
Inc., B-299086, February 7, 2007) (pdf)
The protester argues that it is clear from the record that the
agency in fact conducted discussions with Offeror A, and that,
as a consequence, the agency had an obligation to conduct
discussions with all offerors. Bannum cites as evidence that the
agency conducted discussions with Offeror A the fact that in its
April 4 memorandum to the contracting officer, the evaluation
board identified a deficiency in Offeror A’s technical proposal,
while in its evaluation report of late May, the board stated
that Offeror A’s proposal had no deficiencies. According to the
protester, the only explanation for the elimination of the
deficiency is that the agency gave Offeror A the opportunity to
cure it through discussions. The agency denies that it conducted
discussions with Offeror A. According to the agency, the reason
that the item was not mentioned as a deficiency in the second
evaluation report was that subsequent to the April 4 memorandum,
the evaluators decided that it was not actually a deficiency.
The agency further argues that even assuming that it had
conducted discussions with Offeror A, the protester suffered no
prejudice as a result because award was not ultimately made to
Offeror A. In its comments on the agency report, Bannum does not
rebut the agency’s assertion that it did not conduct discussions
with Offeror A. Instead, Bannum disputes the agency’s finding
that Offeror A’s proposal did not have a deficiency and the
agency’s position that Bannum was not prejudiced as a result of
the elimination of the alleged deficiency. Both of these
arguments are wholly unpersuasive. First, since Offeror A was
not in line for award in any event, any deficiency in its
proposal which would have resulted in lowering its rating would
have had no effect on the ranking of the offerors. Second,
Bannum argues that it was prejudiced by the agency’s failure to
recognize the deficiency in Offeror A’s proposal because the
agency would not have elected to award on the basis of initial
proposals if it had not thought that it had two technically
acceptable proposals (i.e., those of Dismas and Offeror A) to
trade off against one another in a best value determination.
This theory is simply too speculative to warrant questioning the
agency’s actions here. (Bannum, Inc.,
B-298281.2, October 16, 2006) (pdf)
FAR sect. 15.306 describes a spectrum of exchanges that may take
place between an agency and an offeror during negotiated
procurements. Clarifications are “limited exchanges” between the
agency and offerors that may allow offerors to clarify certain
aspects of proposals or to resolve minor or clerical errors. FAR
sect. 15.306(a)(2). Discussions, on the other hand, occur when
an agency indicates to an offeror significant weaknesses,
deficiencies, and other aspects of its proposal that could be
altered or explained to enhance materially the proposal’s
potential for award. FAR sect. 15.306(d)(3). When an agency
conducts discussions with one offeror, it must conduct
discussions with all other offerors in the competitive range.
FAR sect. 15.305(d)(1). The “acid test” for deciding whether
discussions have been held is whether it can be said that an
offeror was provided the opportunity to revise or modify its
proposal. Park Tower Mgmt. Ltd., B-295589, B-295589.2, Mar. 22,
2005, 2005 CPD para. 77 at 7; Priority One Servs., Inc.,
B-288836, B-288836.2, Dec. 17, 2001, 2002 CDP para. 79 at 5. The
substance of Washington’s proposal regarding the coarse ground
beef requirement, i.e. shelf life from pack, price, and
delivery, remained unchanged. Instead, the agency suspected, and
Washington confirmed, that the term “case ready” had been
misapplied to the proposal item describing Washington’s
commitment to meet the requirements for “coarse” ground beef.
These exchanges were clarifications and not discussions, as they
were “limited exchanges” that resolved a minor or clerical
error. Washington was not given an opportunity to materially
change its proposal because it was clear that the terms and
details of the proposal for coarse ground beef did not change,
but rather the label applied to those terms and details was
corrected. Because all of the evidence in the proposal as
submitted indicated that this was a mistaken label, we conclude
that the agency reasonably inquired and received clarification
from Washington. (National Beef
Packing Company, B-296534, September 1, 2005) (pdf)
Eight offerors, including CMR/Anese and ICGM, submitted
proposals, which were evaluated by a technical evaluation board.
CMR/Anese's proposal, at an offered price of €7.5 million,
was rated marginal overall based on satisfactory ratings under
the experience and past performance factors and a marginal
rating under the schedule factor. ICGM's proposal, at an offered
price of €7.9
million, was rated as good-plus overall. The agency determined
that ICGM's proposal represented the best value and awarded it
the contract without conducting discussions. At its debriefing,
CMR/Anese learned that its marginal schedule rating was based on
the agency's (erroneous) finding that its North Ramp schedule
exceeded the allowed schedule by 5 days. When CMR/Anese showed
the agency that, in fact, its North Ramp schedule was fully
compliant with the RFP, the agency acknowledged its mistake and
suspended the debriefing to reevaluate the protester's proposed
schedule. Protest at 4. Upon further review, the agency
recognized that it was CMR/Anese's schedule for the Zulu Pad
that exceeded the completion date. Specifically, based on the
RFP-required assumptions of a start date of September 15, 2004,
the 360 days allotted for performance would expire on September
10, 2005. Although CMR/Anese proposed to perform the work in 324
days, a shorter period than the 360 days allowed by the RFP, its
CPM schedule showed a start date of October 26, 2004 and a
completion date of September 15, 2005, that is, 5 days beyond
the assumed completion date. Based on this review, the Navy
notified CMR/Anese that its proposal rating remained at
marginal. The protester maintains that this evaluation
conclusion was unreasonable. Noting that its Zulu Pad schedule
had been designated a strength in the evaluation, CMR/Anese
asserts that, once the Navy identified the completion date
problem and evaluated the proposal as marginal, it was required
to open negotiations with the firm. In this regard, the
protester states that the perceived problem could have been
easily corrected by adjusting the start date for the Zulu Pad.
This argument is without merit. There generally is no obligation
that a contracting agency conduct discussions where, as here,
the RFP specifically instructs offerors of the agency's intent
to award a contract on the basis of initial proposals. FAR
15.306(a)(3); Colmek Sys. Eng'g. , B291931.2, July 9, 2003, 2003
CPD 123 at 7. The contracting officer's discretion in deciding
not to hold discussions is quite broad. Our Office will review
the exercise of such discretion only to ensure that it was
reasonably based on the particular circumstances of the
procurement. Colmek Sys. Eng'g , supra . We find no
circumstances that call into question the agency's decision not
to engage in discussions here. Contrary to the protester's
assertions, the fact that it may have erroneously entered the
wrong start date in its CPM schedule does not give rise to an
obligation on the agency's part to hold discussions where
discussions are not otherwise necessary. See Omega World Travel,
Inc ., B-283218, Oct. 22, 1999, 2002 CPD 5 at 6. (Cooperativa
Maratori Riuniti-Anese, B-294747, October 15, 2004) (pdf)
As mentioned in the previous section, the RFP here clearly
advised that the agency intended to make award, if possible, on
the basis of initial proposals. RFP amend. 5, at 53. The RFPs
definition of marginal also advised that it meant that a
proposal so rated may be correctable only with a significant
re-write of the proposal. Id. at 51. In addition, the SSA here
expressly determined that DynCorps marginal proposal was
ineligible for award as written due to its significant shortfall
in proposed staffing. Put simply, since we find that the Army
reasonably concluded that the proposal could not be accepted as
written, there was no requirement to consider it further. Tomco
Sys., Inc. , B-275551 et al. , Mar. 13, 1997, 97-1 CPD 130 at
4-5. (DynCorp International LLC,
B-294232; B-294232.2, September 13, 2004) (pdf)
The contracting officer has broad discretion whether to open
discussions. Colmek Sys. Eng’g, B-291931.2, July 9, 2002, 2003
CPD ¶ 123 at 7. Here, the RFP stated that the agency did not
intend to open discussions, and the questions issued to AHNTECH
were labeled “Clarification Request” and, rather than identify
and seek correction of deficiencies or weaknesses, sought
clarification of the firm’s proposal. As such, the clarification
requests did not constitute discussions. By proposing additional
personnel to meet the SOW requirements, AHNTECH, not the agency,
disregarded the scope of the clarification process. The firm’s
unilateral decision to modify its proposal could not and did not
transform the agency’s clarifications into discussions. (AHNTECH,
Inc., B-293582, April 13, 2004) (pdf)
Although it is true that the RFP informed offerors that they
would be informed of the test results, the solicitation also
provided that “[t]he purpose of the test and evaluation is NOT
to reveal deficiencies or significant weaknesses for possible
remediation through discussions,” and that “[n]o part of a
Contractor's proposal will be changed as a result.” RFP at
41-42. As the agency explains, test results were to be provided
to offerors for the sole purpose of ensuring that the boats were
being operated properly during testing.[2] Contracting Officer's
Statement at 3. Given the RFP's warning that remediation would
not be permitted, we find no basis to question the agency's
decision not to conduct discussions with SeaArk or to permit the
firm to redesign its boat or to otherwise remedy the weaknesses
identified in testing. (SeaArk Marine, Inc.,
B-292195, May 28, 2003) (pdf)
Clarifications are "limited exchanges" between the government
and offerors that may occur when award without discussions is
contemplated. Federal Acquisition Regulation (FAR) §
15.306(a)(1). Such exchanges may allow offerors to clarify
certain aspects of proposals or to resolve minor clerical
errors. FAR §
15.306(a)(2). In contrast to discussions, requesting
clarification from one offeror does not trigger a requirement
that the agency seek clarification from other offerors.
See Priority One Servs., Inc., B-288836, B-288836.2, Dec. 17,
2001, 2002 CPD ¶ 79 at 5; Global Assocs. Ltd., B-271693;
B-271693.2, Aug. 2, 1996, 96-2 CPD ¶ 100 at 4. While we
recognize that a situation might arise in which it would be
unfair to request clarification from one offeror but not from
another, here, given that Landoll has failed to explain, and we
cannot see, how the protester's competitive position would have
been affected if the agency had sought clarification from
Landoll, we find no merit to this aspect of Landoll's protest.
(Landoll
Corporation, B-291381; B-291381.2; B-291381.3, December 23,
2002) (pdf) (txt
version)
In other words, a clarification may not be used to furnish information required to determine the technical acceptability of a proposal. The course descriptions here, regardless of when written, were required to determine the acceptability of eMind’s proposal; accordingly, they cannot properly be termed clarifications. Moreover, to the extent that the protester is suggesting that the availability of the course descriptions on its website was sufficient to place the agency on notice of them, agencies may evaluate proposals only on the basis of the information presented in them. Microcosm, Inc., B-277326 et al., Sept. 30, 1997, 97-2 CPD ¶ 133 at 6-7. The record shows that eMind did not incorporate or otherwise reference information from its website in its proposal.
(eMind, B-289902, May 8, 2002) (pdf))
Discussions occur when the government communicates with an offeror for the
purpose of obtaining information essential to determine the acceptability of a
proposal or provides the offeror with an opportunity to revise or modify its
proposal. In contrast, clarifications are merely inquiries for the purpose
of eliminating minor uncertainties or irregularities in a proposal and do not
give an offeror the opportunity to revise or modify its proposal.
Here, the communications in question clearly constituted discussions. The
agency found that certain proposed personnel were “unacceptable” and
required SoBran to replace these personnel. In addition, the agency found
that SoBran may not be able to retain personnel in certain “key positions”
at the proposed salaries and requested SoBran to address this concern, which
SoBran did by raising the salary levels of these positions. A variety of
other concerns about the technical and cost proposal were raised and SoBran
amended its technical and cost proposal to address these concerns, including
raising its proposed cost by $156,992. (Priority One Services, Inc. B-288836; B-288836.2,
December 17, 2001)
Here, we find that NASA reasonably
exercised its discretion to make award on the basis of initial
proposals, as provided for by the RFP. It is true that the
agency found that LB&B understated its proposed costs and
our review found a number of errors in the agency's cost realism
evaluation of LB&B's proposal; we also found, however, that
the firms' relative cost standing was unaffected by NASA's and
our probable cost adjustments. Under the circumstances, the
agency had no reasonable doubt as to which offer represented the
best value to the government and could make award on initial
proposals. See Southwest Marine, Inc.; American Sys. Eng'g
Corp., B-265865.3, B-265865.4, Jan. 23, 1996, 96-1 CPD para. 56
at 19-20. (NV
Services, B-284119.2, February 25, 2000)
There is no requirement that the
agency hold discussions where the solicitation advises offerors
of the possibility of award without discussions. FAR sect.
15.306(a)(3); Kahn Instruments, Inc., B-277973, Dec. 15, 1997,
98-1 CPD para. 11 at 8. In such circumstances, the burden is on
the offeror to submit an initial proposal containing sufficient
information to demonstrate its merits, and an offeror failing to
do so runs the risk of having its proposal rejected. Kahn
Instruments, Inc., supra. Moreover, an agency is not precluded
from awarding on an initial proposal basis merely because an
unacceptable lower offer could be made acceptable through
discussions. Integration Techs. Group, Inc., B-274288.5, June
13, 1997, 97-1 CPD para. 214 at 6. (Century
Elevator Inc., B-283822, December 20, 1999)
We find no circumstances here that call into question the agency's decision not to engage in discussions. Contrary to the protester's assertions, the fact that its proposal may have contained a mistake does not give rise to an obligation on the agency's part to hold discussions where discussions are not otherwise necessary. Since the agency had properly determined both that Sato had submitted an initial proposal that was technically acceptable and that its offered low price was fair and reasonable, there is no basis for us to object to the Air Force's determination to make award without discussions. Cornet, Inc.; Datacomm Management Servs., Inc., B-270330, B-270330.2, Feb. 28, 1996, 96-1 CPD ¶ 189 at 7.
(Omega
World Travel, Inc., B-283218, October 22, 1999) |