We need not determine whether CAE’s proposed key personnel
approach was properly found to be unacceptable since, as
set forth below, we agree with the protester’s related
contention that the agency held discussions regarding key
personnel with other offerors, but not with CAE. Our
review of the record indicates that during the evaluation,
the agency contacted the awardee, Jimmy Church, because
its proposed alternate contract manager “was initially
evaluated as unacceptable” by two members of the
evaluation team because it was not clear he had the
required minimum 5 years of experience. AR, Tab 12, SSEB
Report, at 10 (emphasis added). During its conversation
with Jimmy Church, the agency was informed that the
proposed alternate contract manager “had six years
experience and authority working in the capacity as
Alternate Contracting Manager on Federal Contracts for the
company when Jim Church was not available.” Id. As a
result of this conversation, the “SSEB determined that
[the individual proposed] was qualified and acceptable as
the Alternate Contract Manager.” Id. Therefore, the
evaluators concluded that Jimmy Church’s proposal was
“ACCEPTABLE” for Factor B, key personnel, and the overall
proposal was evaluated as “ACCEPTABLE.” Id. (emphasis in
original).
FAR § 15.306 describes a range of exchanges that may take
place when the agency decides to conduct exchanges with
offerors during negotiated acquisitions.[2] Res Rei Dev.,
Inc., B-410466.7, Oct. 16, 2015, 2015 CPD ¶ 320 at 10;
Int’l Waste Indus., B-411338, July 7, 2015, 2015 CPD ¶ 196
at 5; ERIE Strayer Co., B-406131, Feb. 21, 2012, 2012 CPD
¶ 101 at 4; see also RFP at 7-8. Clarifications are
limited exchanges between an agency and an offeror for the
purpose of eliminating minor uncertainties or
irregularities in a proposal, and do not give an offeror
the opportunity to revise or modify its proposal. FAR §
15.306(a)(2); RFP at 8; Int’l Waste Indus., supra; ERIE
Strayer Co., supra. Clarifications are not to be used to
cure proposal deficiencies or material omissions, or
materially alter the technical or cost elements of the
proposal, or otherwise revise the proposal. Res Rei Dev.,
Inc., supra; Int’l Waste Indus., supra.
Discussions, on the other hand, occur when an agency
communicates with an offeror for the purpose of obtaining
information essential to determine the acceptability of a
proposal, or provides the offeror with an opportunity to
revise or modify its proposal in some material respect.
FAR § 15.306(d); RFP at 7-8; Int’l Waste Indus., supra;
Alliant Enter. JV, LLC, B-410352.4, Feb. 25, 2015, 2015
CPD ¶ 82 at 5. As a general matter, when an agency
conducts discussions with one offeror, it must afford all
offerors remaining in the competition an opportunity to
engage in meaningful discussions. Int’l Waste Indus.,
supra; ERIE Strayer Co., supra. Further, it is the actions
of the parties that determine whether discussions have
been held and not merely the characterization of the
communications by the agency. Int’l Waste Indus., supra;
Priority One Servs., Inc., B-288836, B-288836.2, Dec. 17,
2001, 2002 CPD ¶ 79 at 5.
Thus, the agency’s communications with the awardee invited
a response that was necessary to determine the
acceptability of its proposal. This is quintessentially
the nature of discussions, not clarifications. Int’l Waste
Indus., supra, at 6; Kardex Remstar, LLC, B-409030, Jan.
17, 2014, 2014 CPD ¶ 1 at 4. Although the agency argues
that “[n]o revisions were needed for [Jimmy Church] and no
revisions were offered, permitted, or considered by the
SSEB”, Supp. AR at 4, we find this argument unconvincing
since, as the record shows and the agency itself notes,
only after the conversation with Jimmy Church was the
offeror found to be technically acceptable for the
relevant experience factor. AR, Tab 12, SSEB Report, at
10; Supp. AR, at 4.
Likewise, the Army also contacted another offeror because
it found that its proposed quality control manager had “no
credential demonstrated”; there “was no [site safety and
health officer] listed in the Key personnel as required by
the solicitation”; and it was confusing as to which
individual the offeror proposed as the contract manager.
AR, Tab 12, SSEB Report, at 6. Specifically, the proposal
listed two people as a project manager, and indicated that
one of the project managers would be a contract manager
and the other would be a quality control manager. Supp.
AR, Offeror Proposal, at 3-4. The proposal further
indicated that the alternate contract manager was also the
“contract officer”. Id. at 3. As a result, the agency
contacted the offeror “in regard to clarification of the
key personnel and their proposed role on the project,” and
explained that “there was confusion in the roles and
responsibilities of the proposed team identified in the
proposal.” Id. Thus, as with Jimmy Church, the agency
contacted an offeror to obtain information necessary to
determine the acceptability of the proposal under the key
personnel factor. Accordingly, we conclude that the Army,
having conducted discussions with Jimmy Church and another
offeror, was required to also conduct discussions with all
other offerors in the competition, including CAE, and
provide them an opportunity to address deficiencies and
significant weaknesses in their proposals. (Cascadian
American Enterprises B-412208.3 ,B-412208.4: Feb 5,
2016) (pdf)
Finally,
the protester asserts that the agency allowed the awardee
to revise its quotation after discussions were complete,
and that the questions posed to Artel following the
submission of revised quotations constituted unequal
discussions. Supp. Protest at 10. Specifically, the
protester alleges that the agency’s questions provided the
awardee with guidance on which aspects of its revised
quotation could be materially enhanced to increase the
potential for award, and that the agency relied on the
awardee’s responses in finding Artel’s revised quotation
acceptable. Comments at 2, 7-8. In response, the agency
asserts that Artel’s revised quotation was already found
acceptable when the challenged exchanges took place, and
that the agency merely sought clarification of information
already contained in Artel’s revised quotation. The record
supports this assertion.
Under Federal Acquisition Regulation (FAR) § 15.306(d),
discussions are exchanges with offerors after the
establishment of a competitive range. Such exchanges are
supposed to be tailored to each offeror’s unique proposal
or quotation, with the intent of obtaining revisions
through bargaining, give and take, attempts at persuasion,
the alteration of assumptions and positions, and
negotiations. FAR § 15.306(d). In contrast, clarifications
are not used to cure deficiencies or materially alter the
technical or cost elements of a proposal or quotation, but
are limited to enhancing the agency’s understanding and
allowing reasonable interpretation of proposals or
facilitating the agency’s evaluation process. FAR §
15.306(b)(2). Requesting clarifications from one offeror
does not trigger a requirement that the agency seek
clarifications from other offerors. Serco Inc.,
B-406061.1, B-406061.2, Feb. 1, 2012, 2012 CPD ¶ 61.
On this record, including the questions posed to Artel
after the submission of revised quotations as well as
Artel’s responses, we conclude that the agency found
Artel’s revised quotation acceptable prior to its
submission of responses to the agency’s questions.
Additionally, the record shows that the questions were
intended to enhance the agency’s understanding of
information already contained in the quotation. For
example, the questions sought additional information to
clarify the type of satellites and satellite locations
referenced in Artel’s description of its experience in its
quotation. Artel did not further revise its quotation in
response to the agency’s clarification questions or
provide any information that was necessary to make the
quotation acceptable. AR, Tab 7, Artel Response to SSEB
Questions. Accordingly, we do not view these exchanges as
discussions.
The protest is denied. (Hughes
Network Systems, LLC B-409666.5, B-409666.6: Jan 15,
2015) (pdf)
Improper
Exchanges with the Awardee
Next, Staples argues that GSA conducted exchanges that
improperly allowed Office Depot to materially revise its
proposal after the due date for proposals. Protester Supp.
Comments (Oct. 20, 2014) at 13. Staples argues that any
communications between a firm and an agency that results
in that firm changing its proposal constitutes
discussions, and that if GSA held discussions with Office
Depot then it was required to hold discussions with the
other offerors and, at the conclusion, request revised
proposals. Protester Supp. Comments (Oct. 20, 2014) at 14.
GSA responds that Staples was similarly allowed to address
the agency’s concerns with its technical approach after
the due date for proposals. Supp. AR at 7. The agency
states that it allowed all CLIN No. 4 offerors to “clarify
their initial submissions” to address, for example,
noncompliant items in their market baskets and incomplete
subcontracting plans. Id. at 8. Therefore, the agency
argues that its actions in this regard did not prejudice
the protester.
In our view, Staples’ argument about discussions overlooks
the fact that this procurement anticipated award to the
lowest-priced, technically acceptable offeror. Where
proposals are to be rated acceptable/unacceptable, a
proposal rated “acceptable” cannot be further improved.
Therefore, we have recognized that in such situations, an
agency properly may conduct discussions with only those
offerors whose proposals are unacceptable. Presidio
Networked Solutions, Inc. et al., B-408128.33 et al., Oct.
31, 2014, 2014 CPD ¶ __ at 8; see also Zodiac of North
America, B‑409084 et al., Jan. 17, 2014, 2014 CPD ¶ 79 at
4; Commercial Design Group, Inc., B‑400923.4, Aug. 6,
2009, 2009 CPD ¶ 157 at 3. (Staples
Contract & Commercial, Inc., B-409528.34, B-409528.37:
Dec 3, 2014) (pdf)
The RFP established a two-phase evaluation approach. Under Phase
I, offerors would submit two proposal volumes--one which
provided an equipment list and identified web-based support
capabilities/data and reporting requirements; and a second which
provided contractual documents. The Phase I proposals were to be
evaluated as acceptable or unacceptable. RFP at 19, 96. Only
offerors evaluated as acceptable in Phase I would be invited to
submit Phase II proposals. Id. at 19. The solicitation
stated that the Army did not intend to hold discussions under
Phase I, but reserved the right to engage in discussions and
clarifications, if necessary. Id. Under Phase II, the
agency planned to conduct discussions after establishing a
competitive range. Id. at 238.
(sections deleted)
Presidio and Mercom contend that
the agency’s actions at various points in the procurement
process constituted discussions. As a result, the protesters
contend that the agency conducted discussions with some, but not
all, offerors, resulting in competitive prejudice to the
offerors who did not receive discussions. We will address these
assertions below.
As a general matter, where an agency engages in discussions, it
must afford all offerors remaining in the competition an
opportunity to engage in meaningful discussions. See Lockheed
Martin Simulation, Training & Support, B‑292836.8 et al., Nov.
24, 2004, 2005 CPD ¶ 27 at 8. The FAR requires agencies
conducting discussions with offerors to address, “[a]t a minimum
... deficiencies, significant weaknesses, and adverse past
performance information to which the offeror has not yet had an
opportunity to respond.” FAR § 15.306(d)(3).
The protesters contend that the agency conducted discussions
with some offerors during Phase I of the procurement process,
which allowed certain offerors to improve their Phase I
proposals to the level of acceptable. The protesters argue that
it was improper for the agency to conduct Phase I discussions
with some, but not all, offerors. Alternatively, the protesters
argue that once discussions were opened in Phase I, the agency
was required to conduct discussions regarding Phase I and Phase
II proposals.
The agency does not dispute that it conducted discussions with
offerors during Phase I, but contends that it was not obligated
to conduct discussions with offerors whose Phase I proposals had
already been deemed acceptable, since acceptable was the highest
available rating in Phase I, and since a proposal rated
acceptable could not be further improved. The agency also argues
that its Phase I discussions did not obligate it to conduct
discussions with offerors regarding their Phase II proposals
because the solicitation put offerors on notice that the two
phases would be considered separate for purposes of the
evaluation and the conduct of discussions.
We find nothing objectionable in the agency’s decision to
conduct discussions during Phase I with only those offerors
whose Phase I proposals were deemed unacceptable. The scope and
extent of discussions are a matter of contracting officer
judgment. FAR § 15.306(d)(3); Tritech Field Eng’g, Inc.,
B‑255336.2, Apr. 13, 1994, 94‑1 CPD ¶ 261 at 5. Where proposals
are to be rated acceptable/unacceptable, a proposal rated
“acceptable” cannot be further improved. Therefore, we have
recognized that in such situations, an agency properly may
conduct discussions with only those offerors whose proposals are
unacceptable. See Zodiac of North America, B‑409084 et al., Jan.
17, 2014, 2014 CPD ¶ 79 at 4; Commercial Design Group, Inc.,
B‑400923.4, Aug. 6, 2009, 2009 CPD ¶ 157 at 3. Thus, the agency
was not obligated to conduct Phase I discussions with offerors
whose proposals had already been rated acceptable, since those
proposals could not have been further improved at that point in
the competition.
Further, we disagree with the protesters that the conduct of
discussions during Phase I obligated the agency to conduct
discussions with offerors regarding their Phase II proposals. In
this regard, we note that the solicitation put offerors on
notice that the agency considered the two phases separate and
distinct with regard to discussions. Specifically, the RFP
stated the following:
4.2 Phase I - Acceptable/Unacceptable
* * * * *
The Government does not intend to hold discussions under Phase
I. However, the Government reserves the right to engage in
discussions and clarifications if necessary.
4.3 PHASE II
The Government intends to award contracts after conducting
discussions with offerors in the competitive range under Phase
II. Only those offerors within the competitive range will be
engaged in discussions and be requested to submit a final
proposal revision.
RFP at 237, 238.
Given that offerors were informed that the agency “reserve[d]
the right to engage in discussions” during Phase I, but planned
to conduct discussions during Phase II only after establishment
of the competitive range, we find that the offerors were on
notice that the agency considered the Phases to be separate and
distinct for purposes of conducting discussions. Therefore, we
find nothing improper in the agency’s decision to conduct Phase
I discussions, without engaging all of the offerors in
discussions regarding their Phase II proposals. (Presidio
Networked Solutions, Inc.; Mercom Corporation;
MicroTechnologies, LLC, B-408128.33, B-408128.35,
B-408128.36, B-408128.50: Oct 31, 2014) (pdf)
Turning to the
merits of Metropolitan’s protest, Metropolitan contends that
discussions were unequal because MVM and AllWorld received more
extensive and detailed discussions than the protester. In
conducting exchanges with offerors, agency personnel also may
not “engage in conduct that . . . favors one offeror over
another,” Federal Acquisition Regulation (FAR) § 15.306(e)(1);
in particular, agencies may not engage in what amounts to
disparate treatment of the competing offerors. Front Line
Apparel Group, B-295989, June 1, 2005, 2005 CPD ¶ 116 at 3-4.
Although discussions may not be conducted in a manner that
favors one offeror over another, discussions need not be
identical among offerors; rather, discussions are to be tailored
to each offeror’s proposal. FAR § 15.306(d)(1), (e)(1); see M.
Matt Durand, LLC, B-401793, Nov. 23, 2009, 2009 CPD ¶ 241 at 5.
According to Metropolitan, MVM received more extensive
discussion questions than did Metropolitan because MVM’s
discussion questions included one question regarding MVM’s
technical proposal, whereas none of Metropolitan’s discussion
questions concerned Metropolitan’s technical proposal. Second
Supp. Protest at 16; Metropolitan Comments at 24. The record,
however, reflects that during its initial evaluation of MVM’s
proposal, the SEB identified one weakness under one of the
technical evaluation factors. AR, Tab 7, SEB Final Report,
attach. H. The record also reflects that during its initial
evaluation of Metropolitan’s proposal, the SEB identified no
weaknesses under any of the technical evaluation factors. Id.,
attach. G. The MVM discussion question referenced by
Metropolitan pertains to the sole technical weakness that the
SEB identified for MVM’s proposal. AR, Tab 12, MVM Discussion
Questions, at 3. Given that the agency did not identify any
technical weaknesses for Metropolitan’s proposal, we see no
merit in Metropolitan’s argument that discussions with MVM were
unequal as compared to discussions with Metropolitan. See
Heritage Garden Center, Inc.; S.C. Jones Servs., Inc.,
B-248399.4, Oct. 28, 1992, 92-2 CPD ¶ 290 at 5-6.
Metropolitan also asserts that discussions were unequal because
AllWorld, pursuant to its pre-award debriefing, received a copy
of the SEB’s initial consensus evaluation findings, which
Metropolitan argues provided AllWorld with more detailed
information than was provided to Metropolitan. Supp. Protest at
7; Metropolitan Comments at 19-20 (referencing AR, Tab 17,
AllWorld Pre-Award Debriefing Letter). However, as discussed
above, Metropolitan’s proposal received the highest available
ratings for each evaluation factor and subfactor. AR, Tab 7, SEB
Final Report, at 32-33. Thus, even if Metropolitan, like
AllWorld, had received a copy of the SEB’s consensus evaluation
findings prior the submission of its FPR, Metropolitan cannot
establish that its competitive position would have improved
through discussions. Because Metropolitan cannot establish a
reasonable possibility of prejudice, we will not sustain
Metropolitan’s protest on this basis. See Leisure--Lift, Inc.,
B-291878.3, B-292448.2, Sept. 25, 2003, 2003 CPD ¶ 189 at 10-11;
see also Heritage Garden Center, Inc.; S.C. Jones Servs., Inc.,
supra (no technical discussions necessary where protesters’
proposals received highest available technical ratings and,
thus, there was no opportunity for protesters to improve
ratings).
Metropolitan contends that discussions were not meaningful with
respect to past performance and price. In a negotiated
procurement where the agency conducts discussions, those
discussions must be meaningful--that is, they must be
sufficiently detailed so as to lead the offeror into the areas
of its proposal requiring amplification or revision. Honeywell
Tech. Solutions, Inc., B-400771, B-400771.2, Jan. 27, 2009, 2009
CPD ¶ 49 at 10; Smiths Detection, Inc., B-298838, B-298838.2,
Dec. 22, 2006, 2007 CPD ¶ 5 at 12.
Metropolitan contends that discussions were not meaningful
because the agency did not give the firm an opportunity to
comment on adverse past performance information. Protest at 19.
As described above, in connection with the evaluation of
Metropolitan’s past performance, the SEB documented that
Metropolitan’s past performance surveys initially included two
relatively low ratings, but that those ratings were determined
to have resulted from a mistake. AR, Tab 7, SEB Final Report, at
36. As also described above, Metropolitan’s proposal received a
rating of low risk under the past performance factor, and low
risk was the highest available rating for the past performance
factor. Id. at 32-33. Finally, notwithstanding a reference to
adverse past performance that appeared in Metropolitan’s written
debriefing, we see nothing in the record to suggest that the
agency considered Metropolitan’s past performance as indicative
of a risk during performance. See id. at 33, 36. Consequently,
this basis of protest is denied.
Metropolitan also argues that discussions were not meaningful
because, after AllWorld’s proposal was included in the
competitive range, the price range of the competitive proposals
changed, and Metropolitan’s pricing was considerably less
competitive. Metropolitan Comments at 9-11. Along the same line,
Metropolitan argues that discussions were not meaningful because
the agency failed to inform the firm that its pricing was high
in relation to MVM’s and AllWorld’s pricing. Id. at 16. These
arguments are untimely because they were raised more than 10
days after Metropolitan’s receipt of the pricing information in
the agency report. Bid Protest Regulations, 4 C.F.R. §
21.2(a)(2). In any event, we see nothing in the record to
suggest that discussions regarding Metropolitan’s pricing were
not meaningful; Metropolitan was advised during discussions that
its overall pricing was high and that its pricing for numerous,
specified labor categories also was high. AR, Tab 11,
Metropolitan Discussion Questions, at 3.
Metropolitan contends that discussions were misleading. In this
regard Metropolitan argues that the agency provided Metropolitan
with guidance during discussions that allegedly limited the
firm’s ability to reduce its pricing, which, in turn, rendered
the firm’s proposal noncompetitive. Protest at 17-18;
Metropolitan Comments at 15-17. Metropolitan acknowledges that
it was informed during discussions that the firm’s overall
pricing was high and that its pricing for numerous labor
categories also was high. Protest at 17. But the firm was
misled, Metropolitan claims, when the agency purportedly
encouraged Metropolitan to increase its linguist compensation
rates. Id. at 18.
An agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency’s concerns, or
misinform the offeror concerning a problem with its proposal or
about the government’s requirements. Academy Facilities
Mgmt.--Advisory Opinion, B-401094.3, May 21, 2009, 2009 CPD ¶139
at 6; Multimax, Inc., et al., B-298249.6 et al., Oct. 24, 2006,
2006 CPD ¶ 165 at 12. In the context of discussions relating to
cost or price, an agency may not coerce or mislead an offeror
during discussions into raising its prices. Academy Facilities
Mgmt.--Advisory Opinion, supra.
Here, we see nothing misleading about the discussions that
occurred. The record reflects that the agency asked
Metropolitan--and MVM and AllWorld--whether the disclosed
linguist compensation rates were the best rates that each firm
could offer its linguists. AR, Tab 11, Metropolitan Discussion
Questions, at 3; AR, Tab 12, MVM Discussion Questions, at 3; AR,
Tab 13, AllWorld Discussion Questions, at 3. This question was
in each case followed by the statement that “[i]n order to
develop and maintain an infrastructure of quality linguists, it
is imperative that linguists be paid commensurate with their
professional status.” E.g., AR, Tab 11, Metropolitan Discussion
Questions, at 3. Contrary to what Metropolitan claims, the
notion that an offeror should consider increasing its personnel
compensation rates is not suggestive that the pricing offered to
the government is competitive where, as here, the agency also
notifies the offeror that its overall pricing is high, and that
the rates offered for numerous specified labor categories are
high. Further, the discussions here did not preclude
Metropolitan from making a business decision to increase its
linguist compensation rates while at the same time decreasing
the rates offered to the government, such that its pricing would
have been more competitive.[5] Metropolitan’s decision not to
take this course does not render the discussions misleading.
This ground of protest is denied.
Finally, Metropolitan asserts that once the agency decided to
include AllWorld’s proposal in the competitive range, the agency
was obligated to reopen discussions with the other competitive
range offerors, and to establish a new, common cut-off date for
the receipt of all offerors’ FPRs. Protest at 11; Metropolitan
Comments at 17-18. The agency responds that AllWorld was
afforded the same number of days to prepare and submit its FPR
as the other offerors. Contracting Officer’s Statement at 8-9.
The agency also responds that reopening discussions and allowing
the original competitive range offerors to submit a second FPR
would have been redundant and would have conferred an unfair
advantage to those offerors. Id. at 8-9.
The FAR requires that when an agency conducts discussions with
one offeror, it must conduct discussions with all offerors whose
proposals are determined to be in the competitive range, and it
must then allow them to submit revised proposals. FAR §§
15.306(d)(1), 15.307(b); WorldTravelService, B-284155.3, Mar.
26, 2001, 2001 CPD ¶ 68 at 5-6. The FAR also requires the
contracting officer to establish a common cut-off date for
receipt of FPRs. FAR § 15.307(b). In the context of discussions,
the FAR specifically prohibits agency conduct that favors one
offeror over another. FAR § 15.306(e)(1); WorldTravelService,
supra.
Although it is true that here, the sequence of events led to
differing cut-off dates for the submission of FPRs, we fail to
see how Metropolitan was prejudiced. All of the competitive
range offerors had the same amount of time to prepare their FPRs
following discussions. Further, notwithstanding the differing
cut-off dates, Metropolitan’s proposal received the highest
available ratings under all of the evaluation factors and
subfactors. Thus, given the circumstances here, the occurrence
of differing cut-off dates for the submission of FPRs does not
provide a basis for our Office to sustain the protest. See Gas
Turbine Corp., B-251265.2, May 24, 1993, 93-1 CPD ¶ 400 at 5-6.
(Metropolitan Interpreters and
Translators, Inc., B-403912.4, B-403912.5, B-403912.6,
B-403912.9, May 31, 2011) (pdf)
Turning to the
merits of the case, discussions occur where a firm is afforded
an opportunity to make material revisions to its quote or
proposal. The Analysis Group, LLC, B-401726, B-401726.2, Nov.
13, 2009, 2009 CPD ¶ 237 at 2. It is axiomatic that, if a
concern makes a revision to its quote or proposal that has the
effect of converting it from one that is unacceptable to one
that is acceptable and eligible for award, the revision is
material and discussions have occurred. Id.
Here, as noted, the record shows that the agency found ASI’s
quote and the third vendor’s quote technically unacceptable as
submitted. AR, exh. 19, Memorandum from Agency’s Program
Manager, Nov. 2, 2011, at 1-2. With respect to ASI’s quote, the
agency explains that there were six major questions that,
without a revision from ASI, rendered its quotation technically
unacceptable. Id.; AR, exh. 16. Similarly, with respect to the
third vendor, the record shows that there were seven questions
relating to the acceptability of its quote that, without a
revision, rendered it technically unacceptable. AR, exh. 19,
Memorandum from Agency’s Program Manager, Nov. 2, 2011, at 2;
AR, exh. 18.
In response to the agency’s questions, the record shows that
both vendors submitted material revisions to their quotations
that had the effect of rendering their quotations technically
acceptable. AR, exhs. 16, 18. For example, in the case of ASI,
the record shows that, among other things, it submitted a number
of detailed drawings, a resume for its program manager and
details about its proposed training that were absent from its
original quote. AR, exh. 16. Since the information submitted was
necessary for the agency to find ASI’s (and the third vendor’s)
quote technically acceptable, it follows that, in providing the
two firms an opportunity to submit these quotation revisions,
the agency engaged in discussions. The Analysis Group, LLC,
supra at 3.
In contrast, SCI’s responses to the agency’s clarification
questions did not revise its quotation. Instead, the responses
stated that the initial quote was complete, and included a
narrative explanation regarding why its initial quote was
complete, along with verbatim quotes from the original
submission. For example, the agency sent SCI a clarification
request stating that, as understood by the agency, SCI was
offering [deleted]. In response to the agency’s request, SCI
explained that its original quote was complete, and that
[deleted]. SCI then included a verbatim quotation from its
original submission relating to [deleted] to demonstrate that,
in fact, the agency’s understanding was incorrect. AR, exh. 17,
at unnumbered pages 10-11.
The record thus shows that, in the case of ASI and the third
vendor, the agency solicited and obtained material proposal
revisions that ultimately led the agency to find that these two
quotes were technically acceptable; in so doing, the agency
engaged in discussions with these two firms. In contrast, the
agency solicited and obtained only clarifications from SCI, and
SCI, in responding to the agency’s requests, did not make any
revisions to its quotation. In other words, the record shows
that the agency afforded only two of the three competitors an
opportunity to revise their quotes. Under such circumstances, in
order to treat all of the competitors equally, the agency was
obligated to afford the protester an opportunity to revise its
quote as well. The Analysis Group, LLC, supra at 3-4. We
therefore sustain SCI’s protest. (Standard
Communications, Inc., B-406021, Jan 24, 2012) (pdf)
As a final
related matter, Cahaba argues that the exchanges between CMS and
AdvanceMed regarding AdvanceMed's OCI mitigation plan
constituted discussions, which, therefore, should have been held
with Cahaba as well. We disagree.
Where an agency holds exchanges with an offeror regarding the
offeror's plan to mitigate identified conflicts of interest, we
have held that such exchanges do not constitute discussions and,
as a consequence, they do not trigger the requirement to hold
discussions with other offerors. See Overlook Systems
Technologies, Inc., B‑298099.4, B-298099.5, Nov. 28, 2006, 2006
CPD para. 185. Rather, such exchanges are more closely related
to matters concerning the offeror's responsibility. Id. at 20.
In this regard, the FAR states as follows:
The contracting officer shall award the contract to the apparent
successful offeror unless a conflict of interest is determined
to exist that cannot be avoided or mitigated. Before determining
to withhold award based on conflict of interest considerations,
the contracting officer shall notify the contractor, provide the
reasons, therefore, and allow the contractor a reasonable
opportunity to respond.
FAR sect. 9.504(e).
As explained in Overlook, this provision contemplates a review
after evaluations are completed and after an apparent awardee
has been identified--it does not suggest reopening discussions
with all offerors.
Here, after identifying AdvanceMed as the apparently successful
offeror but for concerns regarding unmitigated conflicts, the
agency gave AdvanceMed an opportunity to respond to the concerns
in this regard. CMS's actions, while ultimately flawed, were
consistent with the process outlined in FAR sect. 9.504(e). To
the extent the protester argues that the agency provided
AdvanceMed with additional information regarding the timing of
the agency's issuance of future task orders (specifically, when
it intended to issue task orders for Medicare Parts C and D
work) during its exchanges, which necessitated opening
discussions with all offerors, this information related solely
to the need for and viability of AdvanceMed's amended mitigation
strategy, and did not result in AdvanceMed making any changes to
its proposal in terms of its technical approach or price.[8]
Accordingly, we conclude that CMS's exchanges with AdvanceMed
regarding its OCI plan, did not constitute discussions. (Cahaba
Safeguard Administrators, LLC, B-401842.2, January 25,
2010.) (pdf)
Durand asserts
that the discussions following evaluation of offerors' technical
proposals were unequal, contrary to the requirements of Federal
Acquisition Regulation (FAR) sect. 15.306(a), since the Corps
discussed CRIR deficiencies with three offerors, but failed to
discuss similar issues with Durand. Protester's Comments at 12,
14.
The scope and extent of discussions with offerors in the
competitive range are a matter of the contracting officer's
judgment. FAR sect. 15.306(d)(3); Biospherics, Inc., B‑285065,
July 13, 2000, 2000 CPD para. 118 at 5. Although discussions may
not be conducted in a manner that favors one offeror over
another, FAR sect. 15.306(e)(1); see Chemonics Int'l, Inc.,
B-282555, July 23, 1999, 99-2 CPD para. 61, and offerors must be
given an equal opportunity to revise their proposals,
discussions need not be identical among offerors; rather,
discussions are to be tailored to each offeror's proposal. FAR
sections 15.306(d)(1), (e)(1); WorldTravelService, B‑284155.3,
Mar. 26, 2001, 2001 CPD para. 68 at 5-6.
The discussions here were unobjectionable. While, as noted,
three offerors were advised during discussions that their CRIRs
contained weaknesses and deficiencies, Durand's proposal was
found acceptable with regard to its CRIR, so the agency
determined that there was nothing in that area to discuss with
Durand. AR Tabs 8, 9. Durand does not assert that its CRIR
included information that should have put the Corps on notice of
a problem with its proposed borrow site, and we find nothing in
the record showing that the agency otherwise was or should have
been aware, at the time of discussions, of the problems that
came to light months later. Indeed, as noted above, in providing
the Indian and Mississippi State entities an opportunity to
comment on Durand's proposed borrow site, the EPCB advised that
it did not appear that the site would be problematic. AR Tab 16.
Under these circumstances, where the objections to the proposed
site were unknown by the agency--from Durand's proposal or
otherwise--at the time of discussions, there is no basis for us
to find that the discussions with Durand were unequal or
otherwise deficient. See Metcalf Constr. Co., Inc., B-289100,
Jan. 14, 2002, 2002 CPD para. 31 at 5 (although agency informed
other offerors during discussions that their prices exceeded
applicable budget ceilings, agency was not required to discuss
budget ceilings with protester, whose prices did not exceed
ceilings at time of discussions); KBM Group, Inc., B‑281919,
B-281919.2, May 3, 1999, 99-1 CPD para. 118 at 10 (agency did
not conduct unequal discussions with awardee and protester where
agency conducted technical discussions with awardee, whose
technical proposal was initially evaluated as containing a
number of weaknesses, while conducting no technical discussions
with protester, whose initial proposal was evaluated as
containing no weaknesses). (M.
Matt Durand, LLC, B-401793, November 23, 2009) (pdf)
It is a
fundamental precept of negotiated procurements that discussions,
when conducted, must be meaningful; that is, discussions must
identify deficiencies and significant weaknesses in each
offeror’s proposal that could reasonably be addressed so as to
materially enhance the offeror’s potential for receiving award.
See Federal Acquisition Regulation (FAR) sect. 15.306(d)(3); PAI
Corp., B‑298349, Aug. 18, 2006, 2006 CPD para. 124 at 8; Spherix,
Inc., B‑294572, B‑294572.2, Dec. 1, 2004, 2005 CPD para. 3 at
13. Discussions are to be tailored to each offeror’s proposal.
FAR sect. 15.306(d)(1). An agency fails to conduct meaningful
discussions where it fails to apprise an offeror that its prices
were viewed as unreasonably high. Price Waterhouse, B‑220049,
Jan. 16, 1986, 86-1 CPD para. 54 at 6-7. Further, an agency may
not mislead an offeror--through the framing of a discussion
question or a response to a question--into responding in a
manner that does not address the agency’s concerns; misinform
the offeror concerning a problem with its proposal; or misinform
the offeror about the government's requirements. Metro Mach.
Corp., B‑281872 et al., Apr. 22, 1999, 99-1 CPD para. 101 at 6.
Here, we find that the Army failed to conduct meaningful
discussions with GTE. The record shows that the Army considered
GTE’s proposed price to be unreasonably high. In this regard,
the contracting officer stated that GTE’s proposed price was
never competitive and, in fact, was “unreasonably high when
compared to past procurements in 2000 and 2005 of the same
services.”[3] Contracting Officer’s Statement at 2. The agency,
however, included GTE’s unreasonably high-priced proposal in the
competitive range and conducted discussions with the firm, but
never informed GTE that the agency viewed GTE’s price to be
noncompetitive and unreasonably high, despite the fact that the
RFP provided for award to the firm with the low priced,
technical acceptable proposal. Instead, as noted above, the Army
sent an identical discussions letter to all the competitive
range offerors, including GTE, and therefore the Army also
failed to tailor its discussions to address areas of concern or
weakness in each of the firm’s proposals, as required by FAR
sect. 15.306(d)(1). (Gas
Turbine Engines, Inc., B-401868.2, December 14, 2009) (pdf)
Ashbury maintains
that the agency failed to engage in adequate discussions with
it. As noted, the agency assigned the Ashbury proposal a
moderate risk rating based on the firm's failure to include
various management plans in its proposal. Noting that the RFP
did not require offerors to include such plans in their
proposals, Ashbury asserts that the agency should have advised
it during discussions that the plans were required. The
protester notes further that the agency raised this specific
concern with Horus.
The agency concedes that the RFP did not require the management
plans and that it raised the matter in discussions with Horus,
but maintains that it was not required to discuss the matter
with Ashbury because the firm's risk rating did not amount to a
weakness assessed against its proposal.
Again, we agree with Ashbury. Ashbury's proposal's moderate risk
rating, and the reasons underlying it, were specifically
referenced in the agency's source selection decision as the sole
technical discriminator for selecting Horus's proposal (rated
low risk). Third Business Clearance Memorandum, Jan. 2, 2009, at
12. There is no indication that the agency ever determined that
this lower rating was considered only a minor matter; indeed, it
was the only evaluated difference in the technical proposals,
and, based on the record, appears to have been a material
concern to the agency. We thus find no merit in the agency's
contention that Ashbury's lower risk rating did not have to be
raised during discussions because it was not a significant
proposal weakness.
In any case, since the RFP did not call for the management plans
in question, it was unreasonable for the agency to downgrade
Ashbury's proposal for failing to include them. The agency
either should have amended the RFP to include a requirement for
the detailed management plans, or informed both firms of the
added requirement during discussions. See Hines/Mortenson,
B-256543.4, Aug. 10, 1994, 94-2 CPD para. 67 at 5. Because the
agency did not amend the solicitation, and downgraded Ashbury's
proposal without otherwise informing it of the requirement
during discussions, we sustain the protest on this ground.
(Ashbury International Group, Inc.,
B-401123; B-401123.2, June 1, 2009) (pdf)
AK-9 challenges
the agency's decision to limit discussions to the KM/PM,1
arguing that this resulted in the discussions being unfair and
not meaningful. We agree.
The exchanges with EODT regarding its KM/PM were undeniably
discussions, given that the agency indicated that this was a
"deficiency" and does not deny that without EODT's modification
to its proposal its proposed KM/PM did not comply with the RFP
requirements. See J.A. Jones/IBC Joint Venture; Black Constr.
Co., B-285627, B‑285627.2, Sept 18, 2000, 2000 CPD ¶ 161 at 5.
When an agency conducts discussions with one offeror, it must
conduct discussions with all other offerors whose proposals have
been found in the competitive range. Federal Acquisition
Regulation (FAR) § 15.306(d)(1); Global Assocs. Ltd., B-271693,
B-271693.2, Aug. 2, 1996, 96-2 CPD ¶ 100 at 4. Moreover,
discussions should be meaningful, equitable, and not misleading.
The Boeing Co., B-311344 et al., June 18, 2008, 2008 CPD ¶ 114
at 49. That is, discussions, at a minimum, must be in sufficient
detail to indicate to each offeror whose proposal remains in the
competitive range deficiencies, significant weaknesses, or
adverse past performance information to which the offeror has
not yet had an opportunity to respond. FAR § 15.306(d)(3). At
the conclusion of discussions, each offeror still in the
competitive range shall be provided an opportunity to submit a
final proposal revision. FAR § 15.307(b). In this regard,
offerors, in response to an agency request that discussions be
opened or reopened, generally may revise any aspect of their
proposals they see fit--including portions of their proposals
which were not the subject of discussions. Partnership for
Response and Recovery, B-298443.4, Dec. 18, 2006, 2007 CPD ¶ 3
at 3.
As noted by the agency, as a general matter, the details of a
corrective action are within the sound discretion and judgment
of the contracting agency. Rockwell Elec. Commerce Corp.,
B-286201.6, Aug. 30, 2001, 2001 CPD ¶ 162 at 4. Moreover, in
appropriate circumstances where the agency has established a
reasonable basis for doing so, our Office has not objected to an
agency's decision to limit discussions under a negotiated
procurement in implementing corrective action in response to a
protest. See Rel-Tek Sys. & Design, Inc.--Modification of
Remedy, B-280463.7, July 1, 1999, 99-2 CPD ¶ 1 at 3.
Here, the agency states that the "discovery of two identical
weaknesses in EODT's and AK-9's proposals prompted the
contracting officer to enter into discussions with both offerors
to address those concerns." AR at 16-17. The agency went on to
state that it did not allow "broader revisions" because EODT's
prices had been disclosed, and the agency did not want to give
one offeror an unfair competitive advantage over another. AR at
20.
We find that the agency's limitation on discussions was
unreasonable and inappropriate. This limitation failed to
account for other significant weaknesses or deficiencies found
in the proposals and thus constituted unequal, not meaningful,
discussions. Specifically, the record indicates that the limited
discussions were primarily to allow EODT to fix its otherwise
unacceptable proposal and did not similarly provide AK-9 with
the opportunity to become more competitive through meaningful
discussions. See Ridoc Enters., Inc./Myers Investigative &
Security Servs., Inc., B-293045.2, July 26, 2004, 2004 CPD ¶ 153
at 3; Rockwell Elec. Commerce Corp., supra, at 4-5.
For example, as quoted in part above, the revised source
selection decision document found that AK‑9's price structure
represented "performance risk" that "ha[d] the potential for
straining [AK-9's] ability to perform the contract in the
[REDACTED] option years" and referenced this as one of the
discriminators in making the source selection decision. AR, Tab
51, Revised Source Selection Decision (Jan. 24, 2009), at 2.
This was not a subject of discussions with AK-9. As noted above,
discussions cannot be meaningful if an offeror is not advised of
the significant weaknesses or deficiencies that must be
addressed in order for its offer to be in line for award. Tiger
Truck, LLC, B-400685, Jan. 14, 2009, 2009 CPD ¶ 19 at 8. In our
view, this issue was a significant weakness or deficiency that
was required to be brought to AK-9's attention during
discussions, so that it could be given the opportunity to submit
a revised proposal.
AK-9 submitted, with its protest, a declaration from the firm's
president that summarized the proposal revisions that AK-9 would
have submitted had it been notified by the agency of an
opportunity to submit final proposal revisions. For instance,
AK-9 states that if discussions had been opened it would have
made a "change in [REDACTED]" that would have made its prices
[REDACTED]. AK-9's president also declared that if discussions
had been opened and revised proposals submitted, AK-9 would have
made numerous changes/improvements in its technical and price
proposals, for example, [REDACTED]. Protest, exh. HH,
Declaration of AK-9 President (Jan. 27, 2009).
In sum, the agency's limitation of discussions here was
inappropriate and resulted in the discussions being unfair and
not meaningful. The disclosure of EODT's contract price alone
does not provide a compelling basis for the failure to provide
for meaningful discussions. The possibility that the contract
may not have been awarded based on the most advantageous
proposal because, for example, discussions are not meaningful,
has a more harmful effect on the integrity of the competitive
procurement system than the fear of an auction; generally the
statutory requirements for competition take priority over any
possible concern regarding auction techniques. RS Info. Sys.,
Inc., B‑287185.2, B-287185.3, May 16, 2001, 2001 CPD ¶ 98 at 4.
Because the discussions were not meaningful, we sustain the
protest. However, before we make our recommendation, we discuss
a number of concerns we have identified in the record that the
agency may wish to address as part of its implementation of our
recommendation.
Specifically, the protester asserts that the agency relied upon
unstated evaluation subfactors that were not consistent with
section M of the RFP. In this regard, as noted above, the agency
separately evaluated 10 categories under the technical
capability factor that were not stated in section M. While it
could be argued that these categories are reasonably
contemplated in the evaluation of the technical capability
factor, see Avogadro Energy Sys., B-244106, Sept. 9, 1991, 91‑2
CPD ¶ 229 at 4, the Competition in Contracting Act of 1984
requires solicitations to include a statement of all significant
factors and significant subfactors that will be considered in
the evaluation, as well as their relative importance. 10 U.S.C.
§ 2305(a)(2)(A) (2006), as implemented by FAR § 15.304(d). The
categories here would seem to be significant subfactors, even
though they are not specifically labeled as such, and they were
not disclosed in the solicitation, nor was their relative weight
disclosed. The agency may wish to amend the RFP to address this.
The protester also asserts that the solicitation limited past
performance references to five contracts, but that the agency
considered far more than five contracts in evaluating EODT's
past performance. The agency responds by stating, among other
things, that the letter requesting past performance information
from the offerors in the competitive range (quoted above) put no
limit on contract references. However, as noted by the
protester, this letter also expressly referenced sections L and
M of the RFP, which contained the five contract limitation. AR,
Tab 20, Reevaluation Notice-Contractor Past Performance (Sept.
14, 2008). This is another matter that the agency may wish to
address in implementing corrective action.
Finally, the protester asserts that the agency did not properly
account for EODT's allegedly adverse performance under the
previously awarded CWD contract, which had been protested by
AK-9 before the services were obtained from AK-9 on a
sole‑source basis. The record shows that as part of the
corrective action addressing past performance the agency
questioned EODT regarding adverse performance under this
contract. In its evaluation documentation, the agency states
that EODT responded, "We were forwarded a Stop Work order,
therefore, could not perform." The agency evaluators concluded,
"The committee considers the concern adequately addressed as the
Stop Work order would naturally have precluded contractor
performance," and did not negatively consider this past
performance in its evaluation of EODT. AR, Tab, 24, Past
Performance Re-evaluation Report (Oct. 3, 2008), at 6. However,
in an earlier agency report on the EODT protest of the
noncompetitive award to AK-9 (and in pleadings filed with the
Court of Federal Claims), the agency referenced various
instances of [REDACTED] in justifying the sole source award to
AK-9. E.g., Protest, exh. O, Agency Report (B‑311349.2), at
9-10. Based on our review of the record the agency has not
reconciled its conflicting positions regarding EODT's past
performance on this contract. (American
K-9 Detection Services, Inc., B-400464.6, May 5, 2009) (pdf)
----------------------
1.
kennel master/project manager
IBTCI argues that the agency held disparate discussions with it
and QED because it pointed out weaknesses or deficiencies to QED
that were in its proposal during the second round of
discussions, but did not similarly point out any weaknesses or
deficiencies to IBTCI.
We find that the discussions were not objectionable. Following
the first round of discussions, although the scores of both the
awardee (62.69) and the protester (57.14) remained relatively
low, the agency considered both proposals technically acceptable
for award. Negotiation Memorandum at 10. This being the case,
the agency was under no obligation to revisit the issues that
had already been addressed when it reopened discussions. See
Professional Perf. Dev. Group, B-279561.2 et al., supra. At 5
n.3 (when agency reopens discussions it is not required to
advise offerors of continuing concerns in areas that have
already been subject of adequate discussions).
In its January 28 letter to QED, the agency asked four questions
related to two cost issues. The first three questions concerned
a new negotiated indirect cost rate agreement (NICRA) that had
not been finalized when QED submitted its revised proposal.
Discussion Letter, January 28, 2008. Since these questions
concerned changed circumstances unique to QED’s proposal--QED’s
new NICRA--and were tailored to those unique concerns, raising
these questions did not trigger any obligation on the agency’s
part to ask IBTCI similar questions, or to reiterate questions
raised with the protester during the initial discussions. FAR
sect. 15.306(d)(1); see also The H.J. Osterfeld Co., B-257630,
Oct. 24, 1994, 94-2 CPD para. 150 at 5 (agency should tailor
discussions based on specific deficiencies or weaknesses in each
offeror’s proposal).
The fourth question raised with QED, which stated that “Your
proposed U.S. fixed daily rates appear high at the Junior Level.
Please address this issue,” reiterated a concern raised by the
agency during initial discussions. Discussion Letters, September
18, 2007 and January 28, 2008. However, while an agency may not
have continuing discussions with only one offeror regarding a
certain concern where it has the same concern with other
proposals, The Boeing Co., B‑311344 et al., June 18, 2008, 2008
CPD para. 114, an agency properly may reiterate a cost concern
with one offeror--where that concern applies only to that
offeror, and the agency has no remaining concerns for the other
offeror. Portfolio Disposition Mgmt. Group, LLC,supra, at 2.
(International Business & Technical
Consultants, Inc., B-310424.2; B-310424.3; B-310424.4,
September 23, 2008) (pdf)
It is the actions
of the parties that determine whether discussions have been held
and not merely the characterization of the exchanges by the
agency. Gulf Copper Ship Repair, Inc., B-293706.5, Sept. 10,
2004, 2005 CPD para. 108 at 6. In this regard, we have found
that the acid test for deciding whether an agency has engaged in
discussions is whether the agency has provided an opportunity
for proposals to be revised or modified. See, e.g., Priority One
Servs., Inc., B-288836, B-288836.2, Dec. 17, 2001. Here,
the record shows that the majority of the small business
subcontracting plans submitted by the offerors were found to be
unacceptable by the agency, and that, as a result of the
agency’s exchanges on this subject with the 10 highest rated
offerors (including the awardees), those firms revised their
proposals, such that the proposals became acceptable. It is true
that in each of the cases cited by DISA we found that exchanges
concerning an offeror’s small business subcontracting plan were
not discussions because those plans were only evaluated as part
of the agency’s responsibility determination. See, e.g., General
Dynamics-Ordnance & Tactical Sys., Inc., supra, at 10 (“A
request for, or providing of, information that relates to
offeror responsibility, rather than proposal evaluation, does
not constitute discussions and thus does not trigger the
requirement to hold discussions with other competitive range
offerors. ”) (footnote omitted). However, in each of these
cases, unlike the RFP at issue here, the solicitation did not
include a technical evaluation factor under which the
comparative merits of offerors’ small business subcontracting
plans would be considered to determine which proposal
represented the best value to the government and thus entitled
to award. Thus, under the circumstances of each of these cases,
the assessment of offerors’ small business subcontracting plans
could only be done as part of the agency’s responsibility
determination. In contrast, the RFP here provided for a
comparative assessment of the offerors’ small business
subcontracting plans as part of the agency’s technical
evaluation to determine which proposal represented the best
value to the government.8 See RFP amend. 12, sect.
M.5.2.a.(2)(ii)(6) (“For large businesses, the Government will
evaluate the feasibility and comprehensiveness of the Offeror’s
planned approach to meeting the established subcontracting goals
of . . . .”). In accordance with this evaluation scheme, the
agency’s TMAT performed a comparative evaluation of the offerors’
proposed small business subcontracting plans that were provided
as part of the offerors’ technical/management approach
proposals, assigning strengths and weaknesses for each proposal.
See, e.g., AR, Tab 881, SSAC Evaluation Report, app. 4,
Technical/Management Approach Factor Evaluation, at 103 (SRA’s
proposal was evaluated as exceeding the small business
subcontracting plan requirements, with a number of strengths,
including that the firm had committed to exceeding the small
business goal); see also id. at 189, 212 ([Deleted]’s and [Deleted]’s
proposals were evaluated as exceeding the small business
subcontracting plan requirements, with a number of strengths and
no weaknesses). In contrast, [Deleted]’s proposed small business
subcontracting plan was evaluated as failing to satisfy the
solicitation requirements and a number of weaknesses were
assigned, including that the proposal did not adequately address
how the firm would meet small business goals. Id. at 279. The
SSA, in her selection decision, specifically recognized the
relative strengths and weaknesses assessed in the offerors’
proposed small business subcontracting plans. See, e.g., AR, Tab
894x, Source Selection Decision, at 15 (“[Deleted] has committed
to exceeding goals for [small businesses and other small
business entities identified in the RFP for which goals were
identified]”), and at 20 (“CSC did not provide details on how
they were going to meet or exceed small business goals”).
DISA also contends that these exchanges do not constitute
discussions because they relate only to the small business
subcontracting plan that was submitted as part of the general
contract information proposal and not to the plan that was
submitted as part of the technical/management approach proposal.
DISA and the intervenors argue that the solicitation informed
offerors that the small business subcontracting plans submitted
with the firms’ general contract information proposals would not
be considered in the agency’s technical evaluation, and that the
RFP informed offerors that the agency would not conduct
discussions with regard to the small business subcontracting
plans. See RFP amend. 12, sect. L.3.c. DISA also states in this
regard that offerors’ revisions to their small business
subcontracting plans were not provided to the agency’s TMAT and
therefore did not affect the firms’ technical/management
approach factor evaluations. See Agency Legal Memorandum at 15.
We do not agree that the solicitation provided that offerors’
small business subcontracting plans (and more specifically their
promises to satisfy or exceed the small business subcontracting
goals) would not be evaluated by the agency in its consideration
of the firms’ proposals under the technical/management approach
factor. Rather, as noted above, the RFP specifically stated that
the firms’ promises to satisfy the solicitation’s mandatory
subcontracting goals would be considered under this factor.9 See
RFP amend. 12, sect. M.5.2.a.(2)(ii)(6). In fact, these promises
were specifically considered by the TMAT, the SSAC, and the SSA
in their consideration of the relative merits of the firms’
technical/management approach proposals. See, e.g., AR, Tab
894x, Source Selection Decision, at 15, where the SSA recognized
that SAIC had committed to exceeding the small business
subcontracting goals. In conclusion, we find that the
agency’s exchanges with the offerors, which allowed a majority
of the highest rated offerors to revise their proposals in a
material way, were not clarifications but were discussions. As
noted above, when an agency conducts discussions with one
offeror, it must conduct discussions with all other offerors
whose proposals are in the competitive range, and those
discussions must be meaningful; that is, the discussions must
identify deficiencies and significant weaknesses in each
offeror’s proposal. See Spherix, Inc., supra, at 13-14. Here,
the record establishes that the protesters were prejudiced,
because, although the agency conducted discussions with CSC,
NGIT, and IBM concerning their subcontracting plans, the
discussions with the protesters were not meaningful, given that
there were a number of significant weaknesses identified in each
of the protesters’ proposals, and considered by the SSA in her
selection decision, which the protesters were never given an
opportunity to address, but which could have been altered or
explained to materially enhance the proposals’ potential for
award. See, e.g., AR, Tab 894x, Source Selection Decision, at
19-21, 24, and 27-28 (identifying numerous weaknesses in the
protesters’ proposals).
Computer Sciences Corporation; Unisys Corporation; Northrop
Grumman Information Technology, Inc.; IBM Business Consulting
Services--Federal, B-298494.2; B-298494.3; B-298494.4;
B-298494.5; B-298494.6; B-298494.7; B-298494.8; B-298494.9;
B-298494.10; B-298494.11; B-298494.12; B-298494.13; B-298494.14,
May 10, 2007. (pdf)
In our view, the
corrective action here is well within the broad discretion
afforded to contracting agencies in these circumstances. As
described above, during the course of defending the previous
protest, it came to the agency’s attention that there were
various errors in this procurement that warranted reopening
discussions; as indicated above, the agency is not required to
limit the scope of discussions in such circumstances. To the
extent that PaRR argues that because offerors were informed of
its low price, rescinding the original award and reopening the
competition will foster an auction and put PaRR at a competitive
disadvantage, we have previously noted that the Federal
Acquisition Regulation does not prohibit auctions, and agencies
are not otherwise prohibited from taking corrective action in
the form of requesting revised price proposals where the
original awardee’s price has been disclosed. In this regard, we
have repeatedly observed that the possibility that the contract
may not have been awarded based on a fair determination of the
most advantageous proposal has a more harmful effect on the
integrity of the competitive procurement system than does the
possibility that the original awardee will be at a disadvantage
in the reopened competition. PCA Aerospace, Inc., B-293042.3,
Feb. 17, 2004, 2004 CPD para. 65 at 4. Moreover, as described
above, significant new requirements of HSPD-12 that have been
added to the solicitation will require revised technical
proposals and prices. Under the circumstances, the agency can
choose not to limit discussions and revised proposals. (Partnership
for Response and Recovery, B-298443.4, December 18, 2006) (pdf)
GIV first protests that it was improper for CDC to seek
additional information from McKesson regarding its information
technology system security plans, thereby permitting McKesson to
revise its initially unacceptable responses. Specifically, GIV
argues that CDC’s March 7 inquiry to McKesson constituted
prohibited discussions. CDC responds that nothing prohibited
exchanges with McKesson in this regard. We agree that CDC’s
exchanges with McKesson seeking additional information about its
security systems constituted discussions, rather than
clarifications, because CDC needed this information to conclude
that McKesson’s proposal was acceptable. See Nu‑Way, Inc.,
B-296435.5, B-296435.10, Sept. 28, 2005, 2005 CPD para. 195 at
7. However, GIV was not competitively prejudiced by these
discussions. As noted, GIV was similarly provided discussions
and an opportunity to revise its proposal prior to CDC’s final
competitive range determination. GIV places significant emphasis
on the RFP provision that “proposals that do not pass this first
level of screening will not be further considered in the Source
Selection process.” RFP amend. 5, at 22. To the extent that GIV
is reading this provision as precluding CDC from conducting
discussions with offerors in connection with the “pre-screening”
process, GIV has failed to identify a persuasive rationale for
its interpretation. Accordingly, we decline to sustain its
protest of the agency’s determination that McKesson ultimately
met the go/no-go security plan requirements. (General
Injectables & Vaccines, Inc., B-298590; B-298590.2;
B-298590.3, November 15, 2006) (pdf)
Communications between a procuring agency and an offeror that
permit the offeror to materially revise or modify its proposal
generally constitute discussions. FAR sect. 15.306(d); Lockheed
Martin Simulation, Training & Support, B-292836.8 et al., Nov.
4, 2004, 2005 CPD para. 27; 4th Dimension Software, Inc.;
Computer Assocs. Int’l, Inc., B‑251936, B-251936.2, May 13,
1993, 93-1 CPD para. 420. In this regard, communications that
permit an offeror to correct a mistake constitute discussions
unless the mistake is minor and both the existence of the
mistake and what was actually intended are clearly apparent from
the face of the proposal. Matrix Int’l Logistics, Inc.,
B-272388, B-272388.2, Dec. 9, 1996, 97-2 CPD para. 89; Stacor
Corp., B‑231095, July 5, 1988, 88-2 CPD para. 9. If an agency
does conduct discussions with one offeror, it must conduct
discussions with all competitive range offerors, and provide all
such offerors an opportunity to submit revised proposals. KPMG
Peat Marwick, LLP, B‑259479, May 9, 1995, 95-2 CPD para. 13;
Paramax Sys. Corp., B-253098.4 et al., Oct. 27, 1993, 93-2 CPD
para. 282. Here, it is clear the agency conducted discussions
with Palmetto following submission of FRPs. As discussed above,
the agency’s FRP specifically provided that the LOE templates
were a required part of the offerors’ cost/price proposals. AR,
Tab 37, FRP Request (Nov. 30, 2005), at 2-3. With regard to the
materiality of the error in the LOE template, Palmetto itself
characterizes its FRP submission as reflecting a “gross[]
overstate[ment]” of its intended level of effort, and the
agency’s contemporaneous documents establish that the agency
relied on Palmetto’s post‑FRP revisions regarding the proposed
level of effort in making the contracting officer’s and SSB’s
award recommendations, and the SSA’s source selection decision.
AR, Tab 41, at 21; Tab 45, at 6, 16. Finally, as acknowledged by
the BEP chair during the GAO hearing, the agency could not
discern Palmetto’s intent with regard to the final proposed
level of effort from the face of Palmetto’s FRP without the
additional post-FRP submissions. On this record alone, it is
clear the post-FRP communications constituted discussions. In
addition, Palmetto’s post-FRP submission of various other
changes to its cost/price proposal support the conclusion that
discussions were conducted. With regard to Palmetto’s December
13 e-mail referencing “Revised DMAC Schedules,” and including
the table listing various errors in its FRP, it is clear that
neither the existence of the errors identified in that table,
nor what Palmetto’s actual intentions were with regard to the
errors, was apparent from the face of Palmetto’s FRP.
Specifically, it is clear that Palmetto’s proposed rate of
[deleted] for the “[deleted] cost pool,” was not an obvious
error apparent from the face of Palmetto’s proposal, nor was
there any way for the agency to determine that the rate “should
have been” [deleted]. Similarly, since Palmetto testified that
the errata table itself contains an error, there can be no
suggestion that the face of Palmetto’s FRP clearly established
what Palmetto intended in this regard. On this record, we reject
the agency’s and Palmetto’s assertions that the post-FRP
communications, during which the agency permitted Palmetto to
make significant revisions to its proposal, should be considered
as merely minor corrections. Rather, the communications clearly
constituted discussions concerning material aspects of
Palmetto’s proposal, which triggered the agency’s obligation to
give CIGNA a similar opportunity to revise its proposal. (CIGNA
Government Services, B-297915.2, LLC, May 4, 2006) (pdf)
Here, the agency conducted discussions with FLAG in the areas of
past performance and surge and sustainment, after which it rated
the firm's proposal [deleted] in both areas. Had the agency done
nothing further, we would have no basis to object to its
actions, since agencies are not required to afford offerors
multiple rounds of discussions in areas that have been the
subject of prior discussions where the agency's concerns remain
unresolved. Portfolio Mgmt. Disposition Group , B-293105.7, Nov.
12, 2004, 2005 CPD paragraph __ at 2. However, as FLAG alleges,
the agency afforded two of the competitive range offerors
additional discussions in areas that had previously been
discussed with those firms, but did not extend the same
opportunity to FLAG. Specifically, the record shows that the
agency provided AC Fabricated initial discussion questions in
the areas of [deleted], but the firm apparently did not submit a
timely reply to the agency's initial questions. Consequently,
the agency afforded AC Fabricators a second opportunity to
revise its proposal in these areas. AR, exh. 16. This second
round of discussions resulted in AC Fabricators' proposal being
upgraded from [deleted] to [deleted] under the [deleted]
criterion, which in turn resulted in the firm's overall rating
being upgraded from [deleted] to [deleted]. AR, exh. 13, at
9-10; AR, exh. 37, at 23. With regard to Tullahoma, the record
shows that the agency initially discussed [deleted] with the
firm, and then afforded it a second opportunity to provide
additional information in the area of [deleted]. AR, exh. 17.
While the additional information did not result in a change in
the firm's adjectival rating under the [deleted] criterion, the
record shows that it did result in the agency's source selection
official distinguishing Tullahoma's proposal from FLAG's under
that criterion; Tullahoma's proposal ultimately was rated
[deleted] to FLAG's based, in part, on the additional
information submitted by Tullahoma during the second round of
discussions. AR, exh. 43, at 44. In view of the foregoing
considerations, we find that the agency's actions amounted to
disparate treatment of the competing offerors. Since there is no
way to determine how FLAG's proposal would have been evaluated
had the firm been afforded additional discussions in the areas
of [deleted], we further find that FLAG was prejudiced by the
disparate treatment. We sustain FLAG's protest on this basis. (Front
Line Apparel Group, B-295989, June 1, 2005) (pdf)
We sustain the protest on the basis that the agency's action in
engaging in discussions only with Anteon was improper, and
improperly favored Anteon over Gulf Copper. We recommend that
the agency reopen discussions with all offerors whose proposals
are within the competitive range, obtain revised proposals,
evaluate the revised proposals in a manner consistent with the
solicitation requirements, and make a new source selection
decision. In the event that the Navy determines that an offeror
or offerors other than Anteon and Southwest have submitted the
best value proposals, the agency should terminate the contract(s)
of the offeror(s) no longer in line for award. We also recommend
that the agency reimburse the protester its cost of pursuing
this protest, including reasonable attorney's fees. 4 C.F.R
Section21.8(d) (2004). The protester should submit its certified
claim for costs, detailing the time expended and the costs
incurred, directly to the contracting agency within 60 days of
receipt of this decision. 4 C.F.R. Section 21.6(f)(1). (Gulf
Copper Ship Repair, Inc., B-293706.5, September 10, 2004)
(pdf)
This argument is without merit. DIY never received discussion
questions simply because, as discussed above, DIYs proposal was
not included in the competitive range. The purpose of a
competitive range determination is to select those offerors with
which the agency will hold written or oral discussions.
PeopleWorks, Inc. , B257296, Sept. 2, 1994, 94-2CPD 89 at 3.
Contracting agencies are not required to retain a proposal in
the competitive range where the proposal is not among the most
highly rated or where the agency otherwise reasonably concludes
that the proposal has no realistic prospect of being selected
for award. Federal Acquisition Regulation 15.306(c)(1); Americom
Govt Servs., Inc. , B292242, Aug. 1, 2003, 2003 CPD 163 at 3.
Once an offerors proposal has been excluded from the competitive
range, the agency has no obligation to conduct discussions with
the offeror. SOS Interpreting, Ltd. , B-287505, June 12, 2001,
2001 CPD 104 at 12. Since DIYs proposal was not in the
competitive range, DIY was not entitled to discussions; there
thus is no basis for concluding that the agency accorded DIY
unequal treatment, or otherwise acted improperly. (DIY,
Inc., B-293105.9, December 20, 2004) (pdf)
The Federal Acquisition Regulation (FAR) provides that, when an
agency conducts discussions with one offeror, it must conduct
discussions with all offerors whose proposals are determined to
be in the competitive range, and it must then allow them to
submit revised proposals. FAR 15.306(d)(1), 15.307(b); World
Travel Serv. , B284155.3, Mar. 26, 2001, 2001 CPD 68 at 5-6. The
EPA's corrective action here--a complete reevaluation of
proposals by a new TEP--led to a determination that all three
offerors' proposals should have been included in the competitive
range. If the agency had not conducted further discussions with
any offeror, the agency's corrective action might have been
adequate. As explained above, however, the agency, based on the
earlier determination that Eagle's proposal was the only one in
the competition range, had conducted an additional round of
discussions solely with that firm. Once the agency decided to
revise the competitive range determination by including two more
proposals, the fact that the additional round of discussions had
been limited to Eagle had to be addressed as part of the
agency's corrective action. Specifically, after the EPA
determined that the proposals of Ridoc and Offeror A should have
been included in the competitive range, the agency's failure to
conduct another round of discussions with those firms and to
afford them the same opportunity to submit a second revised
proposal as had been afforded to Eagle was inconsistent with the
government's obligation to give all offerors whose proposals
were in the competitive range the same opportunity to learn
about the government's concerns regarding their proposals and to
revise those proposals. See Rockwell Elec. Commerce Corp. ,
B-286201.6, Aug. 30, 2001, 2001 CPD 162 at 5. (Ridoc
Enterprises, Inc./Myers Investigative & Security Services, Inc.,
B-293045.2, July 26, 2004) (PDF)
Warden asserts that its quote was
included in the competitive range--as evidenced by its receipt
of the two RFQ amendments--and that it therefore was entitled to
meaningful discussions before submitting its revised quote.
Federal Acquisition Regulation (FAR) § 15.306(c). Warden's
assertions are without merit and are based on a misunderstanding
of the circumstances of this procurement. Contrary to Warden's
expressed understanding, its quote was not included in a
"competitive range" either before or after the amendments were
issued. Rather, as discussed above, both its initial and
revised quotes were evaluated as unacceptable. Agency Report
(AR), exh. 12, at 3, 5. Where a quote is eliminated from the
competition as unacceptable, the vendor is not entitled to
discussions. See Drytech, Inc., B‑246276.2, Apr.
28, 1992, 92‑1 CPD ¶ 398 at 7‑8. The agency provided the
amendments to Warden despite the unacceptability of its original
quote only after determining that the amendments made
significant revisions to the RFQ; the agency concluded that
Warden should be given the opportunity to respond to the
agency's actual requirements. Providing this opportunity
did not reverse the prior evaluation and place Warden's
unacceptable proposal in a competitive range for discussion
purposes; rather, it merely returned the procurement to the
quotation submission/evaluation stage. Accordingly, Warden was
not entitled to discussions based on the agency's actions.
(Warden
Associates, Inc., B-291238, December 9, 2002.) (pdf)
Since discussions were reopened
with MCI to advise MCI of the defect in its proposal, and MCI
was permitted to revise its proposal, SSA was required to
conduct discussions with all offerors whose proposals had been
found in the competitive range and allow those offerors to
submit proposal revisions. (Rockwell
Electronic Commerce Corporation, B-286201.6, August 30,
2001)
Similarly, if discussions are
reopened with one offeror after receipt of final revised
proposals, they must be reopened with all offerors in the
competitive range. Patriot Contract Servs., LLC et al., B-278276
et al., Sept. 22, 1998, 98-2 CPD para. 77 at 5 n.3. Discussions
occur when an offeror is given the opportunity to revise or
modify its proposal, or when information requested from and
provided by an offeror is essential for determining the
acceptability of its proposal. FAR sect. 15.306(d); J. A. Jones/
IBC Joint Venture; Black Constr. Co., B-285627.2, Sept. 18,
2000, 2000 CPD para. 161 at 5. (International
Resources Group, B-286663, January 31, 2001)
|