With regard to long-term multiple-award contracts,
including GSA schedule contracts, a contracting officer
has the discretion to request recertification of offerors’
small business size status in connection with the issuance
of task orders. 13 C.F.R. § 121.404(a)(1)(i); Enterprise
Information Services, Inc., B‑403028, Sept. 10, 2010, 2010
CPD ¶ 213 at 3-4. In issuing its regulations regarding
small business size determinations under multiple-award
long-term contracts, the Small Business Administration
(SBA) has specifically stated:
Allowing procuring agencies to
request size certifications in connection with
particular orders is consistent with the purposes of the
Small Business Act (procurements meant for small
businesses should be awarded to small businesses) . . .
. The final rule gives contracting officers the
discretion to request size certifications for individual
orders, but does not require them to do so. . . .
71 Fed. Reg. 66434, 66438 (2006).
With regard to the solicitation language a procuring
agency must use to request recertification, the SBA’s
Office of Hearings and Appeals (OHA) has recognized that
it is unnecessary to use the words “certify” or
“recertify.” Rather, the OHA has considered whether the
solicitation was “reasonably understood as a request to
recertify at the task order level.” Size Appeal of:
Metters Industries, Inc., SBA No. SIZ-5456 at 9, 10
(2013). In this regard, the OHA has concluded that SBA’s
primary concern in drafting the applicable regulations was
to ensure that “procurements meant for small business
should be awarded to small businesses,” further noting
that “[i]n light of this objective, the drafters likely
would not have intended that a task order set aside for
small businesses should be awarded to a firm that is
currently large, merely because the recertification
request may have been drafted with less than perfect
clarity.” Id. at 10; cf. Size Appeal of: Reliasource, SBA
No. SIZ-5536 (2014); Size Appeal of: Safety and Ecology
Corp., SBA No. SIZ-5177 (2010) (inclusion of mandatory FAR
clauses is insufficient to constitute a request for
recertification).
Here, in addition to including the FAR clause requiring
offerors to verify that their prior size status
certifications were current, accurate, and complete “as of
the date of this offer,” the agency responded to offerors’
requests that the agency permit reliance on the offerors’
prior certifications under their respective GSA schedule
70 contracts. The agency rejected these requests,
reiterating that “business size will be verified by data
found in SAM when the proposal is submitted.” AR, Tab
2.05, Questions and Answers for DRFP, at 412, 422
(emphasis added). Likewise, in responding to a request to
remove the requirement for offerors to make annual
representations regarding their size status, the agency
expressly referenced the portion of the mandatory FAR
clause quoted above, and stated that the clause “will not
be modified for this solicitation.” AR, Tab 2.05,
Questions and Answers for DRFP, at 422.
On this record, we conclude that the solicitation was
reasonably understood to require recertification at the
time initial task order proposals were submitted.
Accordingly, we reject InuTec’s assertion that the terms
of the initial solicitation did not seek recertification
of its size status at the time it submitted its initial
proposal, and its protest in this regard is denied.
(InuTeq, LLC B-411781: Oct
21, 2015) (pdf)
SES raises multiple
arguments concerning OBXtek’s eligibility to receive the
task order after its changed size status. In this regard,
SES primarily argues that the contracting officer failed
to exercise due diligence with respect to verifying
OBXtek’s status as a small business in view of OBXtek’s
changed size status after the submission of its initial
task order proposal. Protest at 8; SES Response to SBA &
GSA Comments at 9.
Because the protester’s arguments raise legal questions
related to the Small Business Act, and the SBA regulations
implementing it, our Office solicited and obtained the
views of SBA on matters raised in this protest. As a
general rule, our Office will defer to SBA's judgment in
matters such as this, which fall squarely within its
responsibility for administering the Small Business Act.
CMS Info. Servs., Inc., B-290541, Aug. 7, 2002, 2002 CPD ¶
132 at 3 n.6.
SBA explains that an agency’s decision to request--or not
to request--recertification at the task order level is at
the discretion of the contracting officer. The SBA states
that, since OBXtek certified as small at the time the
option on the underlying GWAC was exercised, OBXtek should
be treated as small for the remainder of the Alliant GWAC
or, as relevant here, until the contracting officer
requests recertification in connection with an order. With
respect to the instant RFP, the SBA concludes that the
solicitation did not require offerors to recertify their
small business status. SBA Comments at 6.
Section 19.301-1(b) of the FAR states in relevant part
that “the contracting officer shall accept an offeror’s
representation in a specific bid or proposal that it is a
small business unless (1) another offeror or interested
party challenges the concern’s small business
representation or (2) the contracting officer has a reason
to question the representation. Challenges of and
questions concerning a specific representation shall be
referred to the SBA.” FAR § 19.301-1(b); Reliable
Builders, Inc., B-402652, B-402652.3, June 28, 2010, 2010
CPD ¶ 260 at 6 n.7. Even where a contracting officer’s
research gives reason to question the representation by a
firm that it is a small business, that research is not an
adequate substitute for referral to the SBA. Marcola
Meadows VA LLC, B‑407078.2 et al., June 4, 2013, 2013 CPD
¶ 141 at 9.
Here, even if we were to agree with the protester that the
contracting officer had reason to question OBXtek’s small
business status, SES has identified no basis for our
Office to sustain its protest. The contracting officer
forwarded SES’s size challenge to the SBA, which concluded
that the task order solicitation did not require
recertification of an offeror’s small business status and
that therefore the protest was untimely. Protest, Attach.
E, SBA Size Determination, at 1. In this regard, the SBA
has conclusive authority to determine size status matters
for federal procurements. 4 C.F.R. § 21.5(b)(1); Mark
Dunning Indus., Inc., B‑405417.2, Nov. 19, 2013, 2013 CPD
¶ 267 at 5. Furthermore, an offeror’s size status is
determined at the time that it submitted its proposal, not
at the time that it is issued a task order. See Research &
Dev. Solutions, Inc., B-410581, B‑410581.2, Jan. 14, 2015,
2015 CPD ¶ 38 at 6.[6] While OBXtek’s size status changed
after it submitted its initial proposal, the record
shows--and SES does not disagree--that OBXtek was listed
as small on the date that its proposal was submitted.
(Software Engineering Services
Corporation B-411739: Oct 8, 2015) (pdf)
TrustComm asserts that since MTNGS was
not a small business, it was ineligible for award and the
contract therefore is illegal and should be terminated.
We find the agency determination to continue with
performance under MTNGS’s contract to be unobjectionable.
As an initial matter, we note that consistent with the
FAR, the Coast Guard did not award a contract until more
than 10 business days after furnishing the SBA with a copy
of TrustComm’s size protest. See FAR § 19.302(h)(1).
Further, the FAR does not require termination of a
contract based on a subsequent SBA determination that an
awardee is other than small. FAR § 19.302(h)(2); see
Planned Sys. Int’l, Inc., B-292319.7, Feb. 24, 2004, 2004
CPD ¶ 43 at 2-3. In this regard, we generally have not
questioned the propriety of an award made by an agency
before a decision by the SBA on a size protest had been
issued, where the 10 business day period for issuing such
decisions had expired, even where the awardee was later
determined by the SBA to be other than a small business
concern. See, e.g., ALATEC Inc., B-298730, Dec. 4, 2006,
2006 CPD ¶ 191 at 4-5; Planned Sys. Int’l, Inc., supra,
2-3.
We have recognized, however, that even where the
requirements of FAR § 19.302 have been satisfied by the
agency in making an award, termination of the awardee’s
contract may be appropriate where a timely size protest
was filed, there was no appeal of the SBA size ruling that
the awardee was not a small business, and there are no
countervailing circumstances that weighed in favor of
allowing a business concern that is not small to continue
performance. See, e.g., Tiger Enters., Inc., B-292815.3,
B-293439, Jan. 20, 2004, 2004 CPD ¶ 19 at 4; Diagnostic
Imaging Technical Educ. Ctr., Inc., B-257590, Oct. 21,
1994, 94-2 CPD ¶ 148 at 2-3. We have found that under such
circumstances, when there are no countervailing reasons
for preserving an award to a business that is not small,
it would be inconsistent with the integrity of the
procurement system and the intent of the Small Business
Act, 15 U.S.C. §§ 631-657a, for an agency to permit a
business that is ineligible under the terms of the
solicitation to continue contract performance. ALATEC
Inc., supra, at 5.
Here, we agree with the agency that the record
demonstrates the existence of countervailing circumstances
supporting the agency determination to continue MTNGS’s
contract. As an initial matter, we find that the agency
reasonably determined that award to TrustComm would
necessitate repeating the first article testing, resulting
in significant delays and additional costs. See COS at
4-5. Although TrustComm argues that new first article
testing will not be required, it has not shown that the
agency’s assumption is unreasonable.
Further, the record indicates that the delays resulting
from disturbing the award to MTNGS would adversely affect
the Coast Guard’s mission effectiveness. The SBA
determination here was issued almost 9 months after
TrustComm’s size protest, a delay wholly beyond the
control of the Coast Guard. See Alliance Detective &
Security Service, Inc., B-299342, Apr. 13, 2007, 2007 CPD
¶ 56 at 6-7 (“protracted SBA size protest process”
considered in finding “countervailing reasons” not to
disturb award). If the agency were required to terminate
MTNGS’s contract and instead make award to TrustComm,
thereby necessitating new first article testing, this
would add a substantial delay to the Coast Guard’s
satellite connectivity program, which, because of delays
in acquiring the Ku equipment, is already three years
behind schedule. First D&F at 3. The Coast Guard reports
that further delays in this procurement will lead to
“mission effectiveness impacts,” delaying a system that
will provide “substantially better performance,” to meet
the Coast Guard’s “global maritime and law enforcement
efforts.” Id.
In addition, the Coast Guard determined that the agency
would incur significant additional costs if MTNGS’s
contract were terminated. These costs include the loss of
much of the $1 million Ku-Band airtime pre-purchased for
Fiscal Year 2013 (with only the airtime required by the
“prototype” Ku cutters being used). Second D&F,
Memorandum, at 2-3. Also, the agency expects that delaying
Ku-Band implementation would result in significant
increased costs--perhaps up to $15 million per year--for
FBB satellite airtime. Specifically, the record indicates
that the Coast Guard uses FBB as the primary satellite
service for 31 cutters at a service cost of approximately
$4,500 per cutter “per underway day.” According to the
agency, once the cutters have Ku-Band equipment installed,
it will become the primary communications channel and FBB
will be used as a backup only (estimated at 15% of
underway days). Id. at 2. In addition, the agency expected
to incur a $500,000 loss with respect to the replacement
of installed prototype equipment and $350,000 to repeat
EMI/ECM testing. Id. at 2-3. Although TrustComm has
questioned the magnitude of these costs--suggesting for
example that if testing could be accomplished in just 4
months, the costs associated with the continued primary
use of FBB satellite service would be only $5 million or
less, Comments at 12--it has not shown that the agency
unreasonably determined that there would be significant
additional costs if MTNGS’s contract were terminated.
In sum, we conclude that the “countervailing
circumstances” identified by the Coast Guard provide
significant support for its decision to permit MTNGS to
continue contract performance notwithstanding the SBA’s
determination the awardee was not eligible for award under
a procurement conducted as a small business set-aside. See
ALATEC, Inc., supra, at 4-5. (TrustComm,
Inc. B-408456, B-408456.2, Sep 20, 2013) (pdf)
In relevant parts, FAR §
19.302(i) states that:
An appeal from an SBA size
determination may be filed by any concern or other
interested party whose protest of the small business
representation of another concern has been denied by an
SBA Government Contracting Area Director, any concern or
other interested party that has been adversely affected
by a Government Contracting Area Director’s decision, or
the SBA Associate Administrator for the SBA program
involved. . . . The SBA will inform the contracting
officer of its ruling on the appeal. The SBA decision,
if received before award, will apply to the pending
acquisition. SBA rulings received after award shall not
apply to that acquisition.
Trident argues that because
the SBA OHA decision was received before the agency made a
new contract award under the RFP, the OHA decision applies
to the pending acquisition. Trident further asserts that
“[i]f the Navy would now apply the SBA decision to the
current solicitation an award to Trident should be
immediately forthcoming because [Trident] has already
twice been found the successful offeror.” Protest at 3.
Our Office contacted the SBA in connection with this
protest in order to solicit its opinion on the Navy’s
actions in this case. In response, the SBA argued that the
Navy had not violated applicable regulations. According to
the SBA, upon learning that OHA had reversed the area
office determination that Trident was ineligible, the
agency’s “only obligation is to allow Trident to submit an
offer for the current award and evaluate Trident’s
eligibility as of the date of its offer for the current
award.” SBA Opinion, at 4. By taking this action, the SBA
maintains that the Navy has complied with applicable
regulations, and that Trident’s protest should be denied.
We agree with the SBA.
The duties of a contracting agency following a size status
protest determination are set forth in the SBA’s
regulations at 13 C.F.R. § 121.1009 (2012). As relevant
here, the regulations state:
(2) A contracting officer
shall not award a contract to a protested concern that
the Area Office has determined is not an eligible small
business for the procurement in question.
(i) If a contracting officer receives such a
determination after contract award, and no OHA appeal
has been filed, the contracting officer shall terminate
the award.
(ii) If a timely OHA appeal is filed after contract
award, the contracting officer must consider whether
performance can be suspended until an appellate decision
is rendered.
(iii) If OHA affirms the size determination finding the
protested concern ineligible, the contracting officer
shall either terminate the contract or not exercise the
next option.
13 C.F.R. § 121.1009(g)(2).
In this case, the Navy properly followed the SBA’s
regulations by terminating Trident’s award, when it
learned that the SBA area office determined that Trident
was ineligible, and Trident had not yet filed an OHA
appeal. Further, because a contract award under the RFP no
longer existed at the time Trident’s OHA appeal was filed,
13 C.F.R. §§ 121.1009(g)(2)(ii) and 121.1009(g)(2)(iii)
had no application in this case. The above regulations,
therefore, did not preclude the agency from proceeding
with a reopened RFP while Trident’s size status appeal was
pending at OHA, and then reinstating Trident in the
ongoing competition once OHA reached its decision.
Moreover, we are not aware of, nor has Trident cited, any
statute or regulation that expressly requires an agency to
reinstate a terminated contract on the basis of an SBA OHA
reversal of a negative size status determination.[2] As
noted above, FAR § 19.302(i), merely provides that “[t]he
SBA [OHA] decision, if received before award, will apply
to the pending acquisition.” Thus, in the absence of any
such regulation, the agency did not err in simply
readmitting Trident to the ongoing procurement and
providing all offerors, including Trident, with an
opportunity to submit revised proposals in response to
solicitation amendments incorporating changed agency
requirements, a new wage determination, and new evaluation
criteria. (Trident^3, LLC,
B-405781.3, Jul 5, 2012) (pdf)
Four offerors, including the protester
and the awardee, submitted proposals. EFS identified
itself as a small business and did not include a small
business subcontracting plan in its proposal. Ultimately,
after conducting discussions with the offerors, receiving
revised proposals, and completing its evaluation, the
agency made award to EFS. Upon learning of the award to
EFS, Accenture filed a size protest with the Small
Business Administration (SBA) challenging the size status
of EFS; Accenture also filed a protest with this Office.
The SBA made a formal size status determination that EFS
was "other than small."[1] Based on the SBA's size
decision, the IRS notified the GAO that it would take
corrective action in response to Accenture's protest,
which we then dismissed. See Accenture Fed. Servs. LLC,
B‑404894, B-404894.2, Apr. 8, 2011.
The IRS's corrective action included canceling the award
to EFS and reevaluating EFS's proposal under the small
business participation factor, knowing that SBA had found
EFS to be other than a small business. Based on this
reevaluation, the agency rated EFS unacceptable under the
small business participation factor since EFS had not
submitted a small business subcontracting plan. The agency
conducted a new best-value determination and made contract
award to Accenture. This protest followed.
EFS argues that the agency improperly evaluated its
proposal as unacceptable under the small business
participation factor for failure to submit the required
small business subcontracting plan. According to EFS,
given "the equities of the present situation"--the fact
that "it believed in good faith that it qualified as a
small business" when it submitted its proposal and that
the requirement for EFS to submit a small business
subcontracting plan only arose as a consequence of the
SBA's post‑award determination that EFS was other than
small--the agency should have reopened discussions and
allowed EFS to revise its proposal to submit a small
business contracting plan. In the alternative, EFS asserts
that its proposal, as initially awarded, included the
relevant subcontracting information, and that the agency
unreasonably evaluated its proposal as unacceptable under
the small business participation factor. Both of the
protester's contentions are without merit.
It is well-settled that once an agency has received final
offers, it is not legally required to reopen discussions
to permit a single offeror to demonstrate the merits of
its proposal. Federal Elec. Corp., B-232704, Jan. 9, 1989,
89-1 CPD para. 18 at 6. The fact that EFS's alleged "good
faith" size status representation in its proposal was
invalidated by a post‑award size status ruling from SBA,
and thereby rendered EFS's proposal unacceptable, is of no
consequence. EFS represented itself as a small business in
its proposal and to the extent this representation
ultimately proved to be legally incorrect, as determined
by SBA, EFS bore the risk associated with the error, not
the agency. As a consequence, the IRS was under no
obligation to reopen discussions in order to provide EFS
with an opportunity to revise its proposal in accordance
with the SBA's size status ruling.
In addition, EFS's contention that its proposal included
the relevant subcontracting information is without merit.
The evaluation of technical proposals is generally a
matter within the agency's discretion, and our Office will
not disturb an agency's judgments regarding the relative
merits of competing proposals absent a showing those
judgments are unreasonable or inconsistent with the RFP's
evaluation criteria. See, e.g., METAG Insaat Ticaret A.S.,
B-401844 , Dec. 4, 2009, 2010 CPD para. 86 at 4.
The record is clear that EFS' proposal did not include a
small business subcontracting plan at Tab A, Volume IV of
its proposal, as required. The protester's assertion that
the relevant information was scattered throughout the
proposal is unpersuasive for two reasons. First, it is an
offeror's responsibility to submit a well‑written
proposal, with adequately detailed information which
clearly demonstrates compliance with the solicitation
requirements and allows a meaningful review by the
procuring agency. See International Med. Corps, B-403688,
Dec. 6, 2010, 2010 CPD para. 292 at 7. Having failed to
submit the small business subcontracting plan, the
protester cannot reasonably require the agency to assemble
the plan itself from various disparate portions of the
proposal. Second, in any event, the record simply does not
support the protester's assertion that the required
information could have been found in its proposal, if the
agency had undertaken the search. We therefore find
nothing unreasonable in the agency's evaluation of the
protester's proposal as unacceptable under the small
business participation factor and thus ineligible for
award. (eTouch Federal
Systems, LLC, B-404894.3, August 15, 2011) (pdf)
ONS21 protests that the agency acted
unlawfully in choosing not to terminate the contract after
it received the SBA OHA decision that Trinity was not a
small business for the procurement under the RFP's NAICS
code 541690.
Since the issue raised, regarding an SBA OHA's reversal of
an SBA area office formal size determination after an
award has been made, concerns a matter of interpretation
involving SBA's regulations, we requested a report on the
protest from SBA. SBA explains that the size protest and
appeal procedures, at 13 C.F.R. sect. 121.1009, have been
set up to allow for quick resolution of size status
protests without unduly delaying procurements. SBA Report
at 2. In this regard, the regulations state that an SBA
area office formal size determination becomes effective
immediately, and a contracting officer may award a
contract based on that determination, 13 C.F.R. sections
121.1009(g)(1), (2). SBA's regulations further instruct
that if an award has been made, and the formal size
determination is, as here, reversed upon appeal by the SBA
OHA, the OHA decision is not to apply to that procurement,
but, instead, is to have prospective effect only, unless
the contracting officer chooses to apply the OHA's
decision to the procurement. 13 C.F.R. sect.
121.1009(g)(3); see Jensco Marine, Inc., B‑278929.7, Feb.
11, 1999, 99-1 CPD para. 32 at 4. Further, and consistent
with the SBA regulations, Federal Acquisition Regulation
(FAR) sect. 19.302(g)(2) provides that "[i]f an award was
made before the time the contracting officer received
notice of the [size determination] appeal, the contract
shall be presumed to be valid." Accordingly, we conclude
that, under the applicable regulations, since the SBA OHA
decision here was received after award, there was no
requirement for the agency to terminate the award to
Trinity. (ONS21 Security
Services, B-403067, September 16, 2010) (pdf)
In this regard, when issuing its final
rule amending the regulations regarding small business
size determinations under GWACs, multiple-award schedule
contracts, and other long-term contracts, the SBA
specifically stated:
Agencies are increasingly
conducting complex multi-year, multi-million dollar
procurements as competitions for orders under the
[multiple- award schedule] program, where offerors
submit "quotes" that exceed, in terms of volume and
complexity, proposals. Allowing procuring agencies to
request size certifications in connection with
particular orders is consistent with the purposes of the
Small Business Act (procurements meant for small
businesses should be awarded to small businesses) . . .
. The final rule gives contracting officers the
discretion to request size certifications for individual
orders, but does not require them to do so. . . .
71 Fed. Reg. 66434, 66438 (2006).
Here, the 8(a) STARS GWAC
has a total duration, including options, of 7 years. It
therefore meets the definition of a long-term contract to
which the provisions of 13 C.F.R. sect. 121.404(g)(3)
apply. As a result, we conclude that the Air Force
contracting officer has the discretion under the
applicable regulations to request a size re-certification
in connection with the submission of task order proposals.
Our view is consistent with that of SBA, the agency
responsible for administering the Small Business Act (and
whose views we solicited in connection with this
protest).[6] SBA agrees that the contracting agency has
the discretion to request a size re-certification in
connection with submission of task order proposals, and if
a firm cannot certify that it is a small business concern
in response to such a request, the firm is ineligible for
award. SBA Letter to GAO, Aug. 23, 2010, at 3.
In challenging the Air Force's decision to require
re-certification, EIS argues that the decision is
unreasonable because re-certification is not necessary to
achieve the Air Force's stated purpose for requiring
recertification, namely, claiming 8(a) credit for issuance
of the task order. EIS' argument misses the mark. The fact
that a contract holder like EIS that is no longer small
could continue to receive orders under the ID/IQ contract
here, see FAR sect. 19.804-6(c), or that the Air Force
could receive 8(a) credit for issuing such an order, does
not make it unreasonable or an abuse of discretion for the
contracting officer to request a size re-certfication in
connection with the submission of task order proposals.[7]
As explained above, requesting re-certification under
these circumstances is presumptively proper and
reasonable, given that doing so furthers the statutory
goals of the 8(a) program and is permitted by the
applicable regulations.
EIS also argues that the Air Force's decision to request
re-certification of firms' size status as of the time they
submit their task order proposals is improper as it
amounts to retaliation against EIS for the filing of
previous protests.
Government officials are presumed to act in good faith; we
will not attribute unfair or prejudicial motives to
procurement officials on the basis of mere inference or
supposition. Saturn Landscape Plus, Inc., B-297450.3, Apr.
18, 2006, 2006 CPD para. 70 at 3. Where a protester
alleges bad faith, it must provide credible evidence
clearly demonstrating same. TPL, Inc., B-297136.10,
B-297136.11, June 29, 2006, 2006 CPD para. 104 at 21.
EIS has furnished no evidence whatsoever to support its
allegation of retribution; it merely infers bad faith
based on the fact that it filed earlier protests. The
record, however, indicates that the Air Force has had a
longstanding desire to ensure that the ENSA task order
would go to a business concern for which the agency could
properly receive 8(a) credit. Further, the record
indicates that the Air Force held numerous discussions
with various SBA and GSA officials regarding how to ensure
that the task order would in fact be one for which the
contracting agency would properly receive 8(a) credit.
While the protester disagrees with the Air Force's
position here--that task orders issued to business
concerns such as EIS who have graduated from the 8(a)
program and/or are no longer small are not ones for which
the contracting agency may receive 8(a) credit--we
conclude that EIS has presented no evidence that the
agency acted in bad faith. (Enterprise
Information Services, Inc., B-403028, September 10,
2010) (pdf)
We view it as inconsistent with the
integrity of the procurement system and the intent of the
Small Business Act, 15 U.S.C. sections 631-657a (2006),
for an agency to allow a firm to continue performing a
contract where the firm was determined after award to be
other than small, unless there are countervailing reasons
for allowing the award to remain in place. See, e.g.,
ALATEC, Inc., B-298730, Dec. 4, 2006, 2006 CPD para. 191
at 5-6. A key consideration is whether there is another
offeror in line for award who can step in and perform if
the contract is terminated. Compare ALATEC, Inc., supra
(sustaining protest where another offeror was eligible for
award and there were no countervailing reasons to leave in
place award to an other than small business) with Landmark
Constr. Corp., B-281957.3, Oct. 22, 1999, 99-2 CPD para.
75 at 3 (where, in order to meet its ongoing needs, and
with no other offeror eligible to step in and perform the
contract, agency reasonably left in place award to an
other than small business until recompetition was
completed and new contract awarded).
In this case, since all three remaining proposals
(including the protester's) were found unacceptable, there
is no offeror to which award could be made if CWU's
contract were terminated at this juncture. In this regard,
as noted above, Greystones does not challenge the agency's
finding that its proposal was unacceptable, and concurs
that the agency has a legitimate need for uninterrupted
roleplayer services, such that continued performance by
CWU is required to meet the agency's needs. Under these
circumstances, we see no basis to object to the agency's
decision not to terminate CWU's contract. Landmark Constr.
Corp., supra.
The protester's challenge focuses on the method by which
the agency proposes to select a new contractor in place of
CWU. As noted above, the agency plans to not exercise the
option year of the contract and to resolicit with due
diligence in order to make a new contract award. The
protester asserts that the agency instead should reopen
the competition, conduct discussions with the three
offerors whose proposals were evaluated as unacceptable,
and make award to one of those firms. Such a course, the
protester asserts, would lead more quickly to replacing
CWU with a small business eligible under the current
solicitation.
The agency states that it will take approximately 6 months
to conduct a recompetition; we see no basis to conclude
that this reprocurement timetable is unreasonable given
the nature of the procurement here. See id. Moreover,
reopening the original solicitation, instead of conducting
a new competition, would exclude new offerors as well as
CWU. There is no basis for restricting the competition in
this manner, especially given that three of the four
proposals received were found to be technically
unacceptable. Further, we see no basis to conclude that,
in lieu of its plan to conduct a reasonably prompt
recompetition, the agency is required to open discussions
in the hope that one or more of the remaining offerors can
remedy the deficiencies in their proposals such that they
would be eligible for award under the RFP.
In sum, we see no basis to challenge the reasonableness of
the agency's decision to leave in place the award to CWU,
given the FLETC's need for continuing roleplayer services
and its plan to award a new contract after holding a
reasonably prompt recompetition. (Greystones
Consulting Group, Inc., B-402835, June 28, 2010)
(pdf)
Five firms
submitted bids in response to the IFB by the September 25
bid opening date. The contracting officer determined that
the two lowest bids were both nonresponsive for reasons
not germane to the protest. Singleton-GMT JV’s bid was
third low. The VA rejected this bid as nonresponsive based
on its review of a copy of a Singleton-GMT JV agreement,
dated August 13, which was not included in the firm’s bid,
but was on file with the agency.[1] Agency Report (AR),
Tab 4, Singleton-GMT JV Agreement (Aug. 13, 2007). The VA
claimed that the Singleton-GMT JV agreement did not comply
with the Small Business Administration’s (SBA) SDVOSBC
regulatory requirement incorporated into this IFB that
every JV agreement to perform a contract set aside for
SDVOSBCs must contain a provision “[d]esignating an
SDVOSBC as the managing venturer of the joint venture, and
an employee of the managing venturer as the project
manager responsible for performance of the SDVO contract.”
13 C.F.R. sect. 125.15(b)(2)(ii) (2007); FAR sect.
52.219-27(d). The VA, therefore, rejected Singleton-GMT
JV’s bid as nonresponsive, and made award to the fourth
low bidder, Affiliated Western, Inc. This protest
followed. At the outset, the agency’s determination that
the bid of Singleton-GMT JV was nonresponsive was clearly
in error. Responsiveness involves whether a bid as
submitted represents an offer to perform, without
exception, the exact thing called for in the solicitation
so that, upon acceptance, the contractor will be bound to
perform in accordance with the IFB’s material terms and
conditions. B-G Mech. Serv., Inc., B-265782, Dec. 27,
1995, 96-1 CPD para. 6 at 2. Responsiveness, thus, is
determined at the time of bid opening from the face of the
bid documents. Id. For such purpose, bid documents include
information submitted with a bid or incorporated into the
bid by reference. Hewlett-Packard Co., B-184515, Jan. 12,
1976, 76-1 CPD para. 18 at 5-6. Here, Singleton-GMT JV’s
bid took no exception to the IFB requirements, and the
August 13 agreement the agency relied on was neither
included, nor incorporated by reference, in the bid.
Moreover, we view the issue of Singleton-GMT JV’s
eligibility as an SDVOSBC to be a matter of status and,
where an agency has a question regarding a bidder’s status
as an SDVOSBC, the SBA, not the procuring agency, is
responsible for determining whether a firm is an eligible
SDVOSBC. In 2003, Congress created, by amending the Small
Business Act, a procurement program for small business
concerns owned and controlled by service-disabled
veterans, that is, SDVOSBCs. Veterans Benefits Act of
2003, Pub. L. No. 108-183, 117 Stat. 2651, 2662 (2003), 15
U.S.C. sect. 657f (Supp. V 2005). The Small Business Act
basically defines an SDVOSBC as a small business concern
that is (1) at least 51 percent owned by one or more
service-disabled veterans, and (2) managed and controlled
by one or more service-disabled veterans, or spouse or
permanent caregiver of a service-disabled veteran with a
permanent and severe disability. 15 U.S.C. sect. 632(q)(2)
(2000). The SBA has issued regulations implementing the
SDVOSBC program, including one establishing criteria
whereby a joint venture that includes a partner that is
not an SDVOSBC, but is otherwise a small business concern,
could qualify as an SDVOSBC. 13 C.F.R. sect. 125.15(b);
see also FAR sect. 19.1403(c). As required by the Small
Business Act, as amended by the Veterans Benefits Act, 15
U.S.C. sections 637(m)(5), 657f(d), the SBA also has
established procedures for interested parties to challenge
a firm’s size or status as a qualified SDVOSBC. 13 C.F.R.
sections 125.24-125.28. Accordingly, we requested the
views of the SBA in this matter. The SBA asserts that
questions concerning SDVOSBC status, including whether an
SDVOSBC joint venture meets the minimum SBA requirements
for such arrangements, are not for resolution by the
procuring agency, but by the SBA. We are required to give
deference to an agency’s reasonable interpretation of its
regulations, and because the SBA is the agency responsible
for promulgating the regulations regarding the SDVOSBC
program, we give its interpretation of its regulations
great weight. Catapult Tech., Ltd., B‑294936, B‑294936.2,
Jan. 13, 2005, 2005 CPD para. 14 at 6. For competitive
set-asides, “[a]ny interested party [to include
contracting officers] may protest the apparent successful
offeror’s SDVOSBC status.” 13 C.F.R. sect.
125.24(b). While the SBA notes that its regulations do not
explicitly address protests concerning the eligibility of
SDVOSBC joint ventures, we agree with the SBA that such
challenges essentially concern the “status” of an SDVOSBC
and that such status challenges are for consideration by
the SBA and not the procuring agency. See PPG-CMS-PSI JV,
B‑298239, B-298239.2, July 19, 2006, 2006 CPD para. 111 at
5.
In addition, FAR sect. 19.307(a) provides, “[f]or
service-disabled veteran-owned small business set-asides,
any interested party [to include contracting officers] may
protest the apparently successful offeror’s [SDVOSBC]
status” and FAR sect. 19.307(h) provides, “[a]ll questions
about service-disabled veteran-owned small business size
or status must be referred to the SBA for resolution.” The
VA focuses on the word “may” in FAR sect. 19.307(a) and
argues that this leaves it to the procuring agency’s
discretion whether to consult the SBA before rejecting the
bid of a JV under an SDVOSBC set‑aside on the basis that
the JV is not compliant with applicable SBA regulations.
This argument is unavailing for two reasons. First, the
“may” language in FAR sect. 19.307(a) is clearly intended
to convey that interested parties (including contracting
officers) have the right, but are obviously not required,
to challenge the apparent winner’s SDVOSBC status. Second,
the VA ignores the mandatory “must” language in FAR sect.
19.307(h), which states that all questions concerning
SDVOSBC status must be referred to the SBA for resolution.
We sustain the protest. Since the VA questions whether
Singleton-GMT JV is an eligible SDVOSBC, we recommend that
the agency forward this matter to the SBA for its
consideration. If the SBA concludes that the protester is
eligible for award as an SDVOSBC, we further recommend
that the VA award the contract to the protester, if
otherwise eligible. We also recommend that the agency
reimburse the protester for the costs of filing and
pursuing its protest. Singleton-GMT JV’s certified claim
for costs, detailing the time expended and costs incurred,
must be submitted to the agency within 60 days of
receiving this decision. 4 C.F.R. sect. 21.8(f)(1) (2007).
(Singleton Enterprises-GMT
Mechanical, A Joint Venture, B-310552, January
10, 2008) (pdf)
Synergetics
asserts that the agency improperly gave Vistronix
evaluation credit for being a small disadvantaged business
(SDB). In the protester’s view, because Vistronix is no
longer an SDB, it was not entitled to represent itself as
one and the agency should have discovered the awardee’s
misrepresented status in its evaluation. The evaluation in
this area was unobjectionable. The RFQ provided that, in
making the best value determination, preference would be
given to small business vendors, with “additional
preference” given to small businesses that were also under
additional socioeconomic preference programs. RFQ sect.
24.4. The RFQ included a form that requested information
from vendors, including their business size status under
their GSA FSS contracts and other socioeconomic programs.
RFQ sect. 24.6. No other representations or certifications
were required. RFQ Question Responses No. 9. Even though
Vistronix is not currently certified as an SDB, it was in
the SDB program at the time its FSS contract was awarded,
and its completed quotation form identified itself as a
“small disadvantaged business, minority owned.” Vistronix
Quotation at 00324. In conducting the evaluation, the
agency relied on this information after verifying the
awardee’s SDB status in its FSS contract. Contracting
Officer’s Supplemental Statement para. 7. Since the RFQ
did not require any new or additional recertification or
representation apart from that contained in the vendors’
underlying FSS contracts, and Vistronix accurately
reported its SDB status from its FSS contract, there is no
basis to conclude that the awardee misrepresented its SDB
status. Likewise, in view of the RFQ’s limited SDB
representation requirements, the agency reasonably relied
upon Vistronix’s representation and gave the firm the
additional preference in the evaluation. (We note that the
agency’s approach here is consistent with Federal
Acquisition Regulation (FAR) sect. 19.301-1(b), which
requires agencies to accept a vendor’s small business
representation absent a challenge by another vendor, or
where the contracting officer has a reason to question the
representation, and FAR sect. 8.405-5, which provides that
ordering activities should rely on small business
representations made by schedule contractors at the
contract level). (Synergetics,
Inc., B-299904, September 14, 2007) (pdf)
Termination of even an otherwise properly awarded contract
is appropriate, where a timely size protest was filed, the
SBA ruled that the awardee was not a small business and
that ruling was not appealed, and there were no
countervailing circumstances that weighed in favor of
allowing a business concern that is not small to continue
performance. ALATEC Inc., B‑298730, Dec. 4, 2006, 2006 CPD
para. 191 at 5. In the absence of countervailing reasons,
we view it as inconsistent with the integrity of the Small
Business Act, 15 U.S.C. sections 631-657a (2000), for an
agency to permit a large business, which was ineligible
under the terms of the solicitation, to continue contract
performance. Id. In this case, the contract awards were
not proper when they were made.
FAR sect. 19.302(h)(1) provides:
After receiving a [size]
protest involving an offeror being considered for award,
the contracting officer shall not award the contract
until (i) the SBA has made a size determination or (ii)
10 business days have expired since SBA’s receipt of a
protest, whichever comes first; however, award shall not
be withheld when the contracting officer determines in
writing that an award must be made to protect the public
interest.
DHS awarded these contracts
before it referred the pre-award Alliance and American
Sentry size protests to the SBA for its determination,
without a written determination from the contracting
officer that the award was made to protect the public
interest. While the SBA and OHA ultimately determined that
these protests were procedurally defective, the
disposition of the protests does not excuse DHS’s failure
to follow FAR sect. 19.302(h)(1). In this regard, the
record shows that DHS never raised any questions
concerning the procedural validity of these size status
protests when referring the protests to the SBA. Even
though DHS stayed performance under these contracts, this
was only done after the initial adverse SBA size
determination in order to allow C&D to appeal this
determination. Moreover, the record shows that C&D has
been conclusively determined by the SBA to be other than
small for these procurements and has not contested this
determination. In light of DHS’s failure to comply
with the applicable FAR provision with regard to delaying
award of the contracts, the issue to be considered here is
whether there were countervailing circumstances that
weighed in favor of allowing a business concern that is
not small to continue performance. We first note that when
DHS lifted the stay of performance on November 27 in
response to the OHA decision, actual contract performance
was not scheduled to begin for more than 3 months, on
March 1, 2007. The SBA almost immediately (on November 28)
apprised DHS of its protest of C&D’s size status. As
stated above, under the applicable regulations, the SBA
size determination based on the SBA protest is applicable
to this procurement. C&D never challenged in its appeal to
the OHA the merits of the SBA’s well-documented
determination on October 13 that C&D was other than small
because of certain affiliations, the OHA only vacated the
size determination on technical grounds, and there was no
evidence in the record that indicated that C&D’s small
business self-certification was otherwise proper. Under
these circumstances, we think the facts weigh against
allowing a large business to perform these contracts. On
the other hand, because of the transition period under
these contracts, C&D has incurred substantial performance
costs. While we have considered, but do not always accept,
termination costs as an adequate countervailing reason to
allow an award to a large business to stand, see, e.g.,
Hydroid LLC, supra, at 4; Tiger Enters, Inc., B-292815.3,
B-293439, Jan. 20, 2004, 2004 CPD para. 19 at 4-5, we find
that the substantial costs incurred here, together with
the protracted SBA size protest process, provide
sufficient countervailing reasons not to disturb the base
period award to C&D, even though it is a large business
for purposes of these procurements. However, there are no
countervailing reasons that justify allowing the potential
exercise of the four yearly options available under these
contracts. While C&D asserts that it now qualifies as a
small business under the revised NAICS code size standard,
to allow this contract to continue for the full 5-year
term under these circumstances would, in our view, be
inconsistent with the integrity of the procurement system
and the Small Business Act, inasmuch as C&D was not
eligible for award under the terms of these RFPs. See
ALATEC Inc., supra, at 6. (Alliance
Detective & Security Service, Inc., B-299342, April
13, 2007) (pdf)
Under the SBA’s regulations, “[a] timely filed protest
applies to the procurement in question, even though a
contracting officer awarded the contract prior to receipt
of the protest.” 13 C.F.R. sect. 121.1004(c).
Nevertheless, we generally have not questioned the
propriety of an award made by an agency before a decision
by the SBA on a size protest had been issued, where the 10
business day period for issuing such decisions had
expired, even where the awardee was determined by the SBA
to be other than a small business concern. See, e.g.,
Planned Sys. Int’l, Inc., B‑282319.7, Feb. 24, 2004, 2004
CPD para. 43 at 2-3; Systems Research and Applications
Corp.; Infotec Dev., Inc., B-270708 et al., Apr. 15, 1996,
96‑1 CPD para. 186, at 6-8. However, we have recognized
that in certain circumstances, even where the requirements
of FAR sect. 19.302 have been satisfied by the agency in
making an award, termination of the awardee’s contract is
appropriate, where a timely size protest was filed, there
was no appeal of the SBA size ruling that the awardee was
not a small business, and there were no countervailing
circumstances that weighed in favor of allowing a business
concern that is not small to continue performance. See,
e.g., Tiger Enters., Inc., B-292815.3, B-293439, Jan. 20,
2004, 2004 CPD para. 19 at 4; Adams Indus. Servs., Inc.,
B-280186, Aug. 28, 1998, 98-2 CPD para. 56 at 4;
Diagnostic Imaging Technical Educ. Ctr., Inc., B-257590,
Oct. 21, 1994, 94-2 CPD para. 148 at 2-3; American
Mobilephone Paging, Inc., B-238027, Apr. 5, 1990, 90‑1 CPD
para. 366 at 3. We found that under such circumstances,
when there are no countervailing reasons for preserving an
award to a business that is not small, it would be
inconsistent with the integrity of the procurement system
and the intent of the Small Business Act, 15 U.S.C.
sections 631‑657a (2000), for an agency to permit a
business that is ineligible under the terms of the
solicitation to continue contract performance. In
this case, a timely size protest was filed. In addition,
during the course of this protest, the OHA has affirmed
the SBA size determination, which, therefore, “remains in
full force and effect” with respect to this procurement.
See 13 C.F.R. sect. 121.1009(g)(1). Thus, there is no
possibility that the SBA’s ruling on this matter will
change. On this record, we also find no plausible
countervailing circumstances that weigh in favor of
allowing a business concern that is not small to begin
performance under this suspended contract, and certainly
none for allowing that firm to perform for what could be 5
years, which could occur if all options are exercised
under the small business set‑aside. In this regard,
contract performance remains stayed and the SBA OHA has
conclusively resolved the size determination with respect
to this procurement. Moreover, the SBA determination that
TAG was not an eligible small business was issued on
August 18--the date that the SBA indicated it planned to
issue its decision--which was only 2 days after the Army
made award to TAG, and the agency received the SBA
determination at least a month prior to the commencement
of scheduled performance of the awarded contract. Finally,
despite having been afforded the opportunity to comment on
the SBA’s comments and the SBA OHA size determination,
which indicated that its ruling was applicable to this
award and that the contract should be terminated, the Army
has not advanced any countervailing reasons for why
preserving the award with TAG at this juncture would be
appropriate, save that the Army complied with FAR sect.
19.302(h)(1). We, therefore, conclude that the Army should
have terminated TAG’s contract when it received the SBA
OHA decision affirming that TAG was not a small business
concern. Not to terminate the contract under these
circumstances was inconsistent with the integrity of the
procurement system and the Small Business Act, inasmuch as
TAG was not eligible for award under the terms of the RFP
that required award to a small business. See Diagnostic
Imaging Technical Educ. Ctr., Inc., supra, at 2-3. (ALATEC
Inc., B-298730, December 4, 2006) (pdf)
Here, the protests challenging TSS’s size status were
forwarded to SBA on December 21, and TSS acknowledges that
SBA contacted it for information regarding its size status
on December 22. Protester Response to Dismissal Request at
3. This being the case, the Navy was permitted to make an
award to Quantell after January 9, that is, 10 business
days later. Since the agency made award to Quantell on
March 16, which is more than 50 business days after the
size protests were received by SBA, the award was
permissible under the applicable regulations. FAR sect.
19.302(h)(1); Planned Sys. Int’l, Inc., B-292319.7, Feb.
24, 2004, 2004 CPD para. 43 at 2. In accordance with FAR
sect. 19.302(i), the OHA ruling received by the agency
after award did not apply to the protested acquisition.
See also 13 C.F.R. sect. 121.1009(g)(3) (OHA decision
received after award does not apply to the current
procurement). Since the award was made in accordance with
the FAR and SBA regulations, and since OHA’s decision on
appeal did not apply to the procurement, the agency was
not required to terminate Quantell’s contract in favor of
an award to TSS.
In comments filed in response to a request by our
Office, SBA posits that OHA’s remanding of the first
regional office determination (finding TSS other than
small) in effect vacated that decision; it goes on to
reason that, since the agency made award to Quantell on
March 16, prior to SBA’s March 20 final determination that
TSS was other than small, the award was improper. SBA
concludes that, since there was no proper award in place
at the time TSS filed its appeal, OHA’s appeal decision
applied to this procurement, and the agency, therefore, is
required to terminate Quantell’s contract and make award
to TSS. See FAR sect. 19.302(i). We do not agree with
SBA’s position. The SBA’s regulations state that an OHA
decision received after award does not apply to the
procurement and will have future effect. 13 C.F.R. sect.
121.1009(g)(3). Furthermore, the regulations do not in any
way suggest that OHA’s decision to remand the regional
office determination, made subsequent to the award to
Quantell, has any bearing on the propriety of the award.
SBA’s position ignores the fact that, as discussed above,
the award to Quantell was made more than 10 days after the
size protests were received and, therefore, was permitted
under the explicit terms of the FAR, whether or not a
final size determination had been issued at the time of
award.
TSS similarly maintains that there was no valid award to
Quantell, citing FAR sect. 19.302(g)(2), which provides
that an award to another offeror will only be “presumed to
be valid” if it is made before the contracting officer
receives notice that the originally intended awardee had
appealed a negative size status decision. According to TSS,
since the Navy made award to Quantell after it received
notice of TSS’s appeal of the first negative size status
determination (the one that thereafter was remanded by OHA),
the award to Quantell is not presumed valid. Again,
however, this argument ignores the fact that the agency
was permitted to proceed with the award to Quantrell
because more than 10 days had passed since the size
protests were received by SBA. While the intended effect
of the “presumed to be valid” language in FAR sect.
19.302(g)(2) is not clear, there is no indication that it
should be read as negating the clear language in FAR sect.
19.302(h)(1). TSS argues that, under FAR sect.
19.302(h)(3), the procuring agency is obligated to notify
SBA if it is making award before a size determination is
received; TSS maintains that the Navy failed to do so and
that the award to Quantell, therefore, was invalid. While
the record does not indicate that the Navy specifically
advised SBA that it planned to make award to Quantell
before it received the size status determination, the Navy
reports that it in fact contacted SBA before making the
award and, on March 14, was told by SBA that it was
finalizing its second determination that TSS was not small
and that the Navy should proceed with the award. Agency
Comments on SBA Response at 5-6. (Technical
Support Services, B-298527, October 12, 2006) (pdf)
As noted above, under FAR sect. 15.503(a)(2), in
procurements that have been set aside for small
businesses, the contracting agency is required to inform
each unsuccessful offeror, in writing, of the identity of
the apparent successful offeror prior to making award. The
purpose for this pre-award notice is to allow unsuccessful
offerors the opportunity to have SBA review the
prospective awardee’s size status before award. Science
Sys. and Applications, Inc., B-236477, Dec. 15, 1989, 89-2
CPD para. 558 at 3. The FAR provides that a contracting
officer may not make an award after receiving a size
protest until (1) SBA has made a size determination, (2)
10 business days have expired since SBA’s receipt of the
size protest, or (3) where the contracting officer
determines in writing that an award must be made to
protect the “public interest.” See FAR sect. 19.302(h)(1).
Here, ICE violated the pre-award notice regulation, thus
precluding Spectrum from being able to file a size status
protest until after award and denying SBA the opportunity
to issue its size determination before award. Under
similar circumstances where the agency failed to give the
required pre-award notice, we have sustained protests and
recommended the termination of contracts awarded to the
concerns that were determined to be large businesses. See,
e.g., Tiger Enters., Inc., B-292815.3, B-293439, Jan. 20,
2004, 2004 CPD para. 19 at 4-5; Science Sys. &
Applications, Inc., supra, at 6. ICE nevertheless argues
that termination of Ahuska’s contract is not appropriate
despite SBA’s determination that Ahuska is not a small
business concern for this procurement. ICE first points
out that the FAR allows the contracting officer to make
award pending SBA’s size determination after 10 business
days have expired since SBA’s receipt of the size protest,
see FAR sect. 19.302(h)(1), and that, here, SBA took 14
business days to issue its size determination. ICE
suggests that SBA’s failure to issue its size
determination within 10 business days excuses the agency’s
failure to provide the pre-award notice. We disagree. As
we have noted in prior decisions, we are unwilling to
speculate whether SBA would not have provided its formal
determination within 10 business days of receipt had ICE
complied with the pre-award notice requirement. See
Science Sys. & Applications, Inc., supra, at 4. Rather, we
think it is more reasonable to assume--given that the
10-day period for SBA’s size decisions is premised upon
agency compliance with the pre-award notice
requirement--that SBA would have issued its size
determination within the 10-day period had the agency been
delaying award pending SBA’s determination. Id.; see also
Eagle Marketing Group, B-242527, May 13, 1991, 91-1 CPD
para. 459 at 3. Accordingly, we do not find that SBA’s
failure to issue its size determination within 10 business
days excuses ICE’s failure to provide pre-award notice and
to stay award pending SBA’s decision. (Spectrum
Security Services, Inc., B-297320.2; B-297320.3,
December 29, 2005) (pdf)
PSI’s timely protest of AMTI’s size status was received
in the appropriate office at SBA on August 28. Thus,
according to its own regulations, if possible, SBA was to
render a decision on the size protest within 10 business
days thereafter, that is, by September 12; SBA’s
subsequent request to NSF that this time be extended 10
days moved the due date for SBA’s decision to September
24. SBA did not issue the size determination by the
September 24 due date. Indeed, SBA did not issue its
decision until November 6. This was inconsistent with
SBA’s regulations; there is no indication--and SBA does
not assert--that it was not possible to issue the
determination by September 24. NSF did not make award
until more than 1 month after the size determination due
date, on October 31, the day after our decision on PSI’s
protest was issued and the stay of award was lifted. Under
these circumstances, since NSF delayed the award as
required by the FAR, and SBA had not issued the size
status determination as of the award date, the award to
AMTI was proper and the delivery order need not be
canceled. See Systems Research and Applications Corp.;
Infotec Dev., Inc., B-270708 et al., Apr. 15, 1996, 96-1
CPD ¶ 186 at 6; Priscidon Enters., Inc., B-230035, Mar.
18, 1988, 88-1 CPD ¶ 290 at 2. (Planned
Systems International, Inc., B-292319.7, February 24,
2004) (pdf)
We previously have found, in circumstances such as
these, where a timely size protest has been filed, there
is no appeal of the SBA’s size ruling, and there are no
countervailing circumstances that would weigh in favor of
allowing the large business concern to continue
performance, that termination of the awardee’s contract is
appropriate. Adams Indus. Servs., Inc., B-280186, Aug, 28,
1998, 98‑2 CPD ¶ 56; Diagnostic Imaging Tech. Educ. Ctr.,
Inc., B-257590, Oct. 21, 1994, 94-2 CPD ¶ 148 at 2-3. In
the absence of countervailing reasons, we view it as
inconsistent with the integrity of the Small Business Act,
15 U.S.C. §§ 631-657a, for an agency to permit a large
business, which was ineligible under the terms of the
solicitation, to continue performance. Adams Indus. Servs.,
Inc., supra. The record shows that in the present
circumstances, all of these conditions are met. First,
although Tiger filed its size status protest after award,
it could not have done otherwise because simplified
acquisition procedure acquisitions do not require the
agency to issue a pre-award notice to unsuccessful
vendors, and none was issued here. See Federal Acquisition
Regulation (FAR) § 13.106-3(c). Because the size protest
was filed within 5 days of Tiger receiving notice from the
USMC of the awards to Tarheel, Tiger’s protest was timely
under SBA’s size status regulations. 13 C.F.R. §
121.1004(a)(2). Moreover, a contracting officer’s size
protest is always timely. 13 C.F.R. § 121.1004(b). Second,
according to SBA, Tarheel has not appealed the SBA’s size
determination. Third, there are no countervailing reasons
that would justify allowing Tarheel to perform these
contracts until September 30, 2004. The J&A, prepared by
the agency based on urgency, does not discuss why an
11-month base period of the award was required. As noted
by Tiger and SBA, an urgency justification cannot support
the procurement of more than a minimum quantity or time
period needed to satisfy the immediate urgent
requirement.[4] See Signals & Sys., Inc., B-288107, Sept.
21, 2001, 2001 CPD ¶ 168 at 12; Tri-Ex Tower Corp.,
B-239628, Sept. 17, 1990, 90-2 CPD ¶ 221 at 5. While the
USMC states that termination of the contracts is
impractical due to the substantial performance of the
contracts, it has not explained why that should be the
case, given the apparent availability of other sources for
these relatively mundane services, such as the two other
vendors (including Tiger), who responded to the RFQ. We
also note that, pending a competition conducted under full
and open competition, the interim requirement for the
services can be quickly satisfied from small businesses,
as is evidenced by the expeditious matter in which the
competition under this RFQ was conducted. (Tiger
Enterprises, Inc., B-292815.3; B-293439, January 20,
2004) (pdf)
We conclude that, in light of the purpose of the Act and
the absence of any specific statutory or regulatory
prohibition, there is nothing objectionable in an
agency's requiring that FSS vendors responding to a task
order RFQ be small as of the date quotations are due,
instead of relying on the original FSS
self-certification, which may not reflect a vendor's
current small business status. (CMS
Information Services, Inc., B-290541, August 7,
2002) (pdf)
Contracting
agency's reliance on information in the Small Business
Administration's (SBA) PRO-Net database to determine
that the protester, which certified itself in its bid as
an eligible HUBZone small business concern, was not
small and thus was not eligible for a HUBZone evaluation
preference was improper because such questions must be
referred to the SBA under applicable regulations where
the agency does not believe it can or should accept the
bidder's self-certification. (AMI
Construction, B-286351, December 27, 2000)
While FAR sec. 19.302(j)
treats size status protests received after award of a
contract as having no applicability to that contract,
SBA's regulations, which we view as controlling in this
area, provide that "[a] timely filed protest
applies to the procurement in question even though a
contracting officer awarded the contract prior to
receipt of the protest." 13 C.F.R. sec.
121.1004(c). Moreover, in the absence of countervailing
reasons, we view it as inconsistent with the integrity
of the competitive procurement system and the intent of
the Small Business Act, 15 U.S.C. sec. 631-657a (1994),
for an agency to permit a large business, which was
ineligible under the terms of the RFQ, to continue to
perform. Diagnostic Imaging Tech. Educ. Ctr., Inc.,
supra. (Adams
Industrial Services, Inc., B-280186, August 28,
1998) |