22 U.S.C. sect. 4852: "United States persons" and "qualified
United States joint venture persons" |
Comptroller
General - Key Excerpts |
Caddell next
argues that Framaco has not built any projects similar in
complexity, type of construction, and value to the three 2009
projects which, as identified above, ranged in value from $85 to
$150 million. As quoted above, subparagraph D of the Security
Act requires that an entity seeking contracts for diplomatic
construction projects over $10 million must have performed
construction services “similar in complexity, type of
construction, and value to the project being bid.” 22 U.S.C.
sect. 4852(c)(2)(D). In addition to having no experience with
projects of this magnitude, Caddell maintains that Framaco has
no experience whatsoever building embassies or working through
the challenges of performing “secure” work.
The agency acknowledges that it initially refused to pre-qualify
Framaco for any of its 2008 projects on the basis that Framaco
could not identify a single project that approached the value of
any of the 2008 projects. After Framaco protested this decision
to our Office, the agency elected not to defend its decision,
and adopted Framaco’s view that an offeror should be permitted
to establish that it has performed similar construction services
by identifying a number of projects it has performed, that, in
total, match or exceed the estimated value of the upcoming
project.
In this regard, in its 2008 submission--which, again, forms the
basis for the 2009 pre‑qualification decision--Framaco
identified the following projects that it contended should be
viewed as similar projects. In addition, it noted that it had
performed these projects for the agency in a joint venture with
two Turkish construction firms.
Name and Location of Project |
Value (US$) |
Interim
Embassy Renovation (Baghdad) |
$
41,656,220 |
500 Man Camp
(Kabul) |
$
14,915,379 |
Cafeteria-Health Center (Kabul) |
$
5,305,646 |
Existing
Office Renovation and Annex Construction (Kabul) |
$
9,994,125 |
Anti-Ram
Perimeter Wall (Mosul and Kirkuk) |
$
4,463,725 |
Geotechnical
Construction Services for NEC Baghdad, Iraq |
$
2,715,074 |
NOX Building
Construction (Bamako) |
$
15,825,748 |
NOX Building
Construction (Accra) |
$
17,749,994 |
Cantonment and
Facilities (Kabul) |
$
9,724,420 |
TOTAL |
$
122,350,332 |
AR, Tab 6, Letter from Framaco to the Agency, Mar. 17, 2008.
As a preliminary matter, we note that the agency report contains
no documentation of any review associated with pre-qualifying
offerors for the 2009 projects. Instead, the agency accepted as
qualified any contractor that was pre-qualified for 2008. AR,
Tab 3, TEP Pre-qualification for 2008 Projects, Feb. 15, 2008.
In our view, the agency’s failure to perform any type of
evaluation contradicts both the letter and spirit of the
Security Act, as well as the sources-sought announcement
published in FedBizOps. At a minimum, the 5-year period of
review anticipated by the Security Act, by definition, changes
each year. It appears from the record that Framaco submitted
only a letter of interest for the 2009 projects. Moreover, while
Framaco indicated in its letter that no changes had occurred in
Framaco’s or [DELETED] (its partner) structure or size status,
Framaco did indicate that it was adding another firm to its
team. Thus, we believe that some type of evaluation was
necessary to ensure that even previously qualified offerors
remained in compliance with the requirements of the Security
Act.
Turning to the analysis that was performed, we do not think the
aggregated list of projects provided by Framaco in its 2008
pre-qualification submission could form the basis for a
reasonable conclusion that Framaco has shown the requisite
experience performing services “similar in complexity, type of
construction and value to the project being bid,” as required by
22 U.S.C. sect. 4852(c)(2)(D). In our view, the Security Act’s
experience requirements anticipate a demonstration that an
offeror has completed at least one construction project of
similar complexity, size, and value as the 2009 embassy
construction projects. As shown above, considering simply the
value of Framaco’s projects, Framaco did not identify a single
completed project that reaches even half the value of the low
end of the estimated range for the Bujumbura construction
project (i.e., a $41.7 million project offered to show a
comparable value for a project estimated between $85 and 105
million); moreover, its largest identified project ($41.7
million) is less than one-third of the estimated value of the
Dakar project ($135 - $150 million). Since Framaco’s experience
consists of contracts of relatively low dollar values compared
to the estimated dollar values of the 2009 projects, we see no
basis for the agency’s conclusion that Framaco has the requisite
experience based on contract values. See Sytronics, Inc.,
B-297346, Dec. 29, 2005, 2006 CPD para. 15; J.A. Farrington
Janitorial Serv., B-296875, Oct. 18, 2005, 2005 CPD para. 187.
In addition, we think Framaco’s argument that the total value of
its list of smaller value projects equals the value of the 2009
embassy construction projects ignores the fact that combining
the values of a list of projects does not demonstrate the
necessary skills to complete and manage an entire embassy
construction project, as anticipated by the Security Act. See,
e.g., Marathon Constr. Corp., B-284816, May 22, 2000, 2000 CPD
para. 94 at 5-6. The identified projects mostly involved office
or building construction projects; none of them involved the
construction of an embassy (other than an interim renovation for
the embassy in Baghdad). In short, we conclude that the agency
has not provided a reasonable basis for its decision to
pre-qualify Framaco. (Caddell
Construction Company, Inc., B-401596; B-401597; B-401598,
September 21, 2009) (pdf)
Caddell argues that the agency’s approach of adding together 3
years of a company’s business receipts is not what the statute
intended. In fact, Caddell contends that the DOS interpretation
of the statute effectively reads out the term “3 years” because,
under the agency’s interpretation, if only 1 year of business
receipts provided sufficient business volume, and the remaining
2 years did not, the agency could still add together the 3 years
of business receipts and conclude that the offeror met the
requirement in 3 of the 5 years. In answer, the agency argues
that our Office should reject Caddell’s contentions and defer to
its interpretation, as it is the agency charged with
interpreting this statute. In matters concerning the
interpretation of a statute, the first question is whether the
statutory language provides an unambiguous expression of the
intent of Congress. If it does, the matter ends there, for the
unambiguous intent of Congress must be given effect. Chevron
U.S.A. Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837,
842-43 (1984). It is a fundamental canon of statutory
construction that words, unless otherwise defined by the
statute, will be interpreted consistent with their ordinary,
contemporary, common meaning. State of California v. Montrose
Chem. Corp., 104 F.3d 1507, 1519 (9th Cir. 1997); GAO,
Principles of Federal Appropriations Law, vol. 1, at 2-89 (3d
ed. 2004); see Mallard v. United States District Court for the
Southern District of Iowa, 490 U.S. 296, 301 (1989). Here,
the statute contemplates a significant restriction on an
offeror’s eligibility to compete for this type of contract.
Specifically, the statute seeks a showing that an entity must
have “achieved total business volume equal to or greater than
the value of the project being bid in 3 years of the 5-year
period” before the issuance of the solicitation. 22 U.S.C. sect.
4852(c)(2)(E). We think the ordinary and common meaning of these
words is that eligible offerors will have achieved a business
volume equal to or greater than the value of the project in each
of 3 years within the 5-year period. That said, given the
arguments raised by Caddell and State, we necessarily recognize
an element of ambiguity in this provision. When a statute
is silent or ambiguous with respect to the specific issue,
deference to the interpretation of an administering agency is
dependent on the circumstances. Chevron, 467 U.S. at 843-45; see
also United States v. Mead Corp., 533 U.S. 218, 227-38 (2001).
Where an agency interprets an ambiguous provision of the statute
through a process of rulemaking or adjudication, unless the
resulting regulation or ruling is procedurally defective,
arbitrary or capricious in substance, or manifestly contrary to
the statute, the courts will defer to this agency interpretation
(called “Chevron deference”). Mead, 533 U.S. at 227-31; Chevron,
467 U.S. at 843‑44. However, where the agency position reflects
only an informal interpretation, “Chevron deference” is not
warranted. In these cases, deference to an agency’s
interpretation is not mandatory, but rather the weight to be
accorded an agency’s judgment will depend on its relative
expertise, the thoroughness evident in its consideration, the
validity of its reasoning, its consistency with earlier and
later pronouncements, and all those factors which give it power
to persuade, though lacking power to control. Mead, 533 U.S. at
227-31; Skidmore v. Swift & Co., 323 U.S. 134, 140 (1944).
In our view, DOS’s interpretation of this statute is not
entitled to “Chevron deference,” as the interpretation arose in
the normal course of a procurement, and is not the result of
either a rulemaking or an adjudication. See, e.g., Intertribal
Bison Cooperative, B-288658, Nov. 30, 2001, 2001 CPD para. 195
at 4. In fact, while the agency suggests it has used this
interpretation before, it has given our Office no examples. In
any event, it has not promulgated this interpretation as part of
its extensive implementing regulations. Nor, as discussed below,
do we think the agency’s interpretation of this statute has the
persuasive weight deserving of deference. Our review leads us to
conclude that Caddell is correct in its argument that the
agency’s interpretation has the effect of rendering meaningless
the statute’s requirement for receipts at this level for 3 years
within the previous 5-year period. We also think the legislative
history of the Diplomatic Security Act does not support the
agency’s interpretation. (Caddell
Construction Company, Inc., B-298949.2, June 15, 2007) (pdf)
(NOTE:
This decision covers various sections of the law and covers them
in detail for this protest. If you work with the
Diplomatic Security and Antiterrorism Act, reading the entire .pdf
file may prove useful.)
In reviewing an agency’s source selection decision, we examine
the supporting record to determine whether the decision was
rational, consistent with the stated evaluation criteria,
consistent with applicable laws and regulations, and adequately
documented. Johnson Controls World Servs., Inc., B-289942, May
24, 2002, 2002 CPD para. 88 at 6; AIU N. Am., Inc., B-283743.2,
Feb. 16, 2000, 2000 CPD para. 39 at 7; Matrix Int’l Logistics,
Inc., B-272388.2, Dec. 9, 1996, 97-2 CPD para. 89 at 5. Where an
agency’s source selection decision is based on conclusions that
appear to be directly contrary to the contemporaneous record,
and where the agency’s evaluation record provides no explanation
regarding the apparent conflict, we cannot conclude that the
decision was reasonable. See AIU N. Am., Inc., supra. As
discussed above, the Security Act, and the agency’s stated
evaluation criteria regarding the procurement at issue here,
limited eligible offerors to “United States persons” or
“qualified United States joint venture persons.” The DOS
regulations implementing the statement of qualifications for the
Security Act provide that:
Organizations that wish to
use the experience or financial resources of any other legally
dependent organization or individual, including parent
companies, subsidiaries, or other related organizations, must
do so by way of a joint venture. A prospective bidder/offeror
may be an individual organization or a firm, a formal joint
venture in which the co-venturers have reduced their
arrangement to writing, or a de facto joint venture where no
formal agreement has been reached, but the offering entity
relies upon the experience of a related U.S. firm that
guarantees performance.
48 C.F.R. sect. 652.236-72.
Here, AICI-SP’s own
prequalification submission expressly stated: “The prospective
offeror . . . is not . . . a joint venture.” AR, Tab 2, AICI-SP
Prequalification Submission at 9. This statement appeared
directly beneath a definition of the term “joint venture,” which
stated the term “refers to a formal or de facto arrangement.”
Further, consistent with AICI-SP’s statement that it was not
seeking qualification on the basis of either a formal or de
facto joint venture, AICI-SP declined to provide any of the
necessary information regarding identification of the “U.S.
person participant” in the joint venture, nor did it identify
“all co-venturers,” as was specifically required. Finally, the
contemporaneous documentation supporting the agency’s summary
conclusion that AICI-SP was eligible to participate in this
procurement on the basis of a de facto joint venture provides no
explanation as to how the agency could reach this conclusion in
light of AICI-SP’s expressly contrary representation. On the
basis of the record here, we are unable to conclude that the
agency’s determination regarding AICI-SP’s eligibility for award
was reasonable. (Caddell Construction
Company, Inc., B-298949, January 10, 2007) (pdf) |
|
Comptroller General - Listing of Decisions |
For the
Government |
For the Protester |
|
Caddell Construction Company, Inc.,
B-401596; B-401597; B-401598, September 21, 2009 (pdf) |
|
Caddell Construction Company, Inc.,
B-298949.2, June 15, 2007 (pdf) |
|
Caddell Construction Company, Inc.,
B-298949, January 10, 2007 (pdf) |
U.
S. Court of Federal Claims |
Key Excerpts |
New
This post-award bid protest comes before the Court on the
parties’ cross-motions for judgment on the Administrative Record
(“AR”). Plaintiff, Caddell Construction Company (“Caddell”),
challenges the Department of State, Bureau of Overseas Building
Operations’ (“DOS”) award of a contract to Framaco
International, Inc. (“Framaco”) for the construction of an
embassy compound at Port Moresby, Papua New Guinea. The
procurement was conducted in two phases: a Phase I
prequalification, and a Phase II technical and price evaluation.
With respect to Phase I, Plaintiff claims that DOS unlawfully
prequalified Framaco under the Omnibus Diplomatic Security and
Antiterrorism Act of 1986 (“the Security Act”) because Framaco
had not demonstrated that it was a “United States person” as
required under the Security Act. With respect to Phase II,
Plaintiff claims that DOS erred in finding Framaco’s proposal
technically acceptable because Framaco had not demonstrated that
it met the staffing and subcontracting requirements of the
Solicitation. Plaintiff requests that the Court declare the
award unlawful, order DOS to terminate Framaco’s contract, and
award the contract to Caddell.
(sections deleted)
Whether DOS’
Decision to Pre-Qualify Framaco was Arbitrary, Capricious, or
Contrary to Law
Caddell argues
that DOS acted arbitrarily and capriciously by prequalifying
Framaco under the Security Act because Framaco lacked the
requisite technical and financial resources to perform the
contract. To prequalify under Phase I, an offeror had to meet
the Security Act’s requirement that the offeror qualify as a
“United States person,” that is, the offeror had to demonstrate
“the existing technical and financial resources in the United
States to perform the contract.” 22 U.S.C. § 4852(c)(2)(G).
DOS’ regulations
implementing this Section of the Security Act provide:
7. Section
402(c)(2)(G): “The term ‘United States person’ means a person
which has the existing technical and financial resources in
the United States to perform this contract.”
Definitions for
purposes of Section 402 determinations of eligibility—
Existing
technical and financial resources means the capability of the
prospective bidder/offeror to mobilize adequate staffing and
monetary arrangements from within the United States sufficient
to perform the contract. Adequate staffing levels may be
demonstrated by presenting the resumes of current United
States citizens and resident aliens with skills and expertise
necessary for the work in which the prospective bidder/offeror
is interested or some other indication of available United
States citizen or permanent legal resident human resources.
Demonstration of adequate financial resources must be issued
by entities that are subject to the jurisdiction of United
States courts and have agents located within the United States
for acceptance of service of process.
48 C.F.R. §
652.236-72(d).
Caddell argues
that DOS could not reasonably have found that Framaco met the
technical and financial resources requirement of the Security
Act because Framaco’s offer of [***] United States employees and
a [***] million line of credit were insufficient to perform this
$95 million construction project.
DOS’
Determination That Framaco Had Existing Financial Resources In
The United States to Perform This Contract
Caddell argues
that DOS did not reasonably evaluate Framaco’s financial
resources for purposes of the Phase I prequalification because
Framaco did not provide sufficient evidence of “existing
financial resources.” Caddell argues that Framaco’s evidence of
access to financial resources - - the May 28, 2015 letter from
its bank - - only provides a [***] million line of credit to
perform a $95 million contract. Caddell argues that this bank
letter fails to establish Framaco’s current credit limit or to
explain how much of Framaco’s credit is currently encumbered on
other projects. However, as Defendant and Framaco argue, nothing
in the Notice of Solicitation required Framaco to demonstrate
any particular level of financial resources or to submit any
particular type of documentation, and DOS knew that Framaco
could fund its future work using progress payments.
The agency has
considerable discretion in assessing an offeror’s financial
wherewithal to perform. In an analogous context where an agency,
in determining an offeror’s responsibility, assesses whether an
offeror would have adequate financial resources to perform a
contract, courts have recognized that these type of financial
calls are quintessential business judgments, not appropriate for
second-guessing. E.g., Commc’n Constr. Servs., Inc. v. United
States, 116 Fed. Cl. 233, 272-73 (2014) (“CCS”). As this Court
explained in CCS:
In Bender
Shipbuilding, the Federal Circuit affirmed a financial
responsibility determination where the Army awarded a contract
to a bidder that had recently filed for bankruptcy under
Chapter 11. The contracting officer in Bender Shipbuilding
acknowledged the seriousness of the company’s financial
situation but awarded it the contract, based in part on a
guarantee of performance by the offeror’s parent company and
the availability of progress payments under the contract. In
upholding the decision, the Federal Circuit noted the “wide
discretion” that contracting officers have in making
responsibility determinations and acknowledged that the
awardee and its parent had financial problems, but did not
disturb the contracting officer’s determination that the
awardee was financially responsible.
116 Fed. Cl. at
273 (citing Bender Shipbuilding & Repair Co. v. United States,
297 F.3d 1358, 1360, 1362-63 (Fed. Cir. 2002)). In CCS, this
Court upheld a contracting officer’s determination that an
offeror with significant debt was financially responsible, since
the firm was performing “per its agreed loan terms” and the bank
“was comfortable with [the firm’s] ability to meet its
obligations.” 116 Fed. Cl. at 272.
In the instant
case, Framaco has access to [***] million in credit from its
United States bank, as well as access to surety credit from a
United States company, ability to obtain bonding, and the
ability to receive progress payments if awarded the contract - -
a far cry from bankruptcy or significant debt. As such, it was
reasonable for DOS to prequalify Framaco on the basis that it
had existing financial resources in the United States to perform
the contract.
DOS’
Determination That Framaco Had Existing Technical Resources In
The United States To Perform This Contract
Caddell argues
that DOS could not reasonably find that Framaco had adequate
technical resources because Framaco has [***] full-time
employees in the United States. Caddell states, “[U]nder no
reasonable interpretation [of the Security Act] can [***] full
time employees be deemed sufficient for Framaco to perform this
$95 million contract.”15 Pl.’s Mot. for J. on the AR 25. In its
reply, Defendant argues, “Caddell offers no support for its
conclusion that [***] full-time staff members [were] not enough
to manage this project.” Def.’s Reply 3-4. Defendant attempts to
turn the tables by requiring a protestor to demonstrate how an
unexplained agency action was unresaonable. Caddell’s so-called
“conclusion” is not being challenged here. DOS’ determination
that [***] full-time United States employees met the Phase I
Security Act requirement is at issue. Yet DOS offered no
explanation of why it reached this determination, effectively
making the agency action unreviewable on the record as it
stands.
In response to
Certification 6(b) (certifying the number of the offeror’s total
employees and United States citizen employees) in its initial
prequalification submission, Framaco informed DOS that it
employed [***] United States citizens in the United States.
DOS evaluated
Framaco’s response as follows:
All [***] listed
principal management positions are occupied by U.S. citizens.
Framaco fails to identify its total number of permanent,
full-time employees, while saying that [***] are U.S.
citizens.
AR 114.
DOS requested
additional information from Framaco, and Framaco submitted its
revised prequalification submission, confirming that it had
[***] full-time employees in the United States. AR 141.1. DOS’
only response was to note “Corrected Certification 6(b).” AR
142. The record contains no Contracting Officer decision on
prequalification - - there is not even a statement in the record
by the Contracting Officer approving or accepting L/BA’s
recommendation. There is no explanation of why DOS determined
that Framaco met the existing technical resources requirement.
Defendant cannot
prevail in an APA review action merely by harping on Plaintiff
having the burden of proof, without pointing to some rationale
the agency articulated in support of its determination. While
Plaintiff has the burden of proving the agency’s conduct was
arbitrary and capricious, the agency has a legal responsibility
in making administrative decisions in the first place - - the
fundamental requirement of articulating a reason for the
decision or choice it made.
The law is clear
that the agency “must examine the relevant data and articulate a
satisfactory explanation for its action including a ‘rational
connection between the facts found and the choice made.’” Motor
Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins.
Co., 463 U.S. 29, 43 (1983) (quoting Burlington Truck Lines v.
United States, 371 U.S. 156, 168 (1962)). As the Supreme Court
has explained:
If the
administrative action is to be tested by the basis upon which
it purports to rest, that basis must be set forth with such
clarity as to be understandable. It will not do for a court to
be compelled to guess at the theory underlying the agency’s
action; nor can a court be expected to chisel that which must
be precise from what the agency has left vague and indecisive.
In other words, “We must know what a decision means before the
duty becomes ours to say whether it is right or wrong.”
Sec. & Exch.
Comm’n v. Chenery Corp., 332 U.S. 194, 196-97 (1947) (quoting
United States v. Chi., M., St. P. & P.R. Co., 294 U.S. 499, 511
(1935)). The Court “cannot supply a basis for agency action that
the agency has not itself provided.” Balestra v. United States,
803 F.3d 1363, 1373 (Fed. Cir. 2015).
Because DOS did
not indicate why it found that Framaco’s prequalification
submission demonstrated the requisite existing technical
resources - - why [***] United States employees were sufficient
- - the Court cannot ascertain whether DOS’ determination was
arbitrary or capricious. Of the 10 offerors seeking to be
prequalified for the Port Moresby project, Framaco proposed by
far the fewest full-time United States employees - - Pernix had
[***] United States employees, BL Harbert had [***], ECCI had at
least [***] United States employees, Nan Incorporated had [***],
Perini had [***], ACC Construction Company had [***], Caddell
had [***], AICI-SP had [***], and Watts had [***]. Although
Framaco had the lowest number of United States employees in a
wide range, spanning from [***] to [***], DOS did not articulate
why it determined that so few full-time United States employees
met the criteria of the Security Act.
This is a
significant omission in a procurement of this nature. Offerors
could only submit proof that they met Security Act requirements
for a United States person in the Phase I prequalification. See
AR 317. This aspect of compliance with the Security Act was not
to be revisited in Phase II and was not an element of the
technical evaluation. Id. As such, DOS’ Phase I evaluations took
on enhanced importance as they not only opened the door for
offerors to submit proposals for the Phase II round of
evaluations, but they determined whether offerors met a
statutory mandate for fitness to perform work overseas in the
context of potential security concerns. (Caddell
Construction Company v. U. S. and Pernix Group and Framaco
International, Inc., No. 15-914C, February 17, 2016) (pdf) |
|
U.
S. Court of Federal Claims - Listing of Decisions |
For
the Government |
For
the Protester |
|
New
Caddell
Construction Company v. U. S. and Pernix Group and Framaco
International, Inc., No. 15-914C, February 17, 2016 (pdf) |
|
|