ASC also argues that the
award, on a sole-source basis, of a bridge contract to BAH
was improper. The protester argues that the urgency of the
requirement that resulted in the sole-source award to BAH
was the result of a lack of adequate advance planning. See
Protest (Dec. 16, 2015) at 9-10; ASC’s Comments (Jan. 27,
2016) at 16. ASC further contends that the delay between
the authorization of the J&A and execution of the bridge
contract undermines the agency’s position that there were
urgent and compelling circumstances justifying the use of
noncompetitive acquisition procedures, and the agency
otherwise failed to reasonably demonstrate that BAH was
the only contractor that could satisfy the government’s
requirements. See Supp. Protest (Jan. 27, 2015) at 12-13;
ASC’s Supp. Comments (Feb. 12, 2016) at 4-8. For the
reasons that follow, we find no basis to sustain ASC’s
protest challenging the Navy’s award of the sole-source
bridge contract to BAH.
The Competition in Contracting Act, 10 U.S.C. §
2304(c)(2), permits an agency to use other than
competitive procedures in acquiring goods or services
where the agency’s requirement is of such an unusual and
compelling urgency that the government would be seriously
injured unless the agency is permitted to limit the number
of sources from which it solicits proposals. Although the
Competition in Contracting Act requires that agencies
solicit offers from as many potential sources as is
practicable when using the unusual and compelling urgency
exception to limit competition, 10 U.S.C. § 2304(e), an
agency nonetheless may limit a procurement to the only
firm it reasonably believes can properly perform the work
in the time available. Camden Shipping Corp., B-406171,
B-406323, Feb. 27, 2012, 2012 CPD ¶ 76 at 6; McGregor Mfg.
Corp., B‑285341, Aug. 18, 2000, 2000 CPD ¶ 151 at 6.
When using noncompetitive procedures pursuant to 10 U.S.C.
§ 2304(c)(2), such as here, agencies are required to
execute a written J&A with sufficient facts and rationale
to support the use of the cited authority. See 10 U.S.C.
§§ 2304(f)(1)(A), (b); FAR §§ 6.302-2(c)(1), (d)(3),
6.303, 6.304. Noncompetitive procedures may not justify a
noncompetitive award on the basis of urgency where the
agency’s requirements have become urgent as a result of a
lack of advanced planning. 10 U.S.C. § 2304(f)(4)(A); FAR
§ 6.301(c)(1); eAlliant, LLC, B-407332.4, B‑407332.7, Dec.
23, 2014, 2015 CPD ¶ 58 at 5. While an agency may not
justify a noncompetitive award on the basis of urgency
where the agency’s requirements have become urgent as a
result of a lack of advanced planning, such planning need
not be entirely error-free or successful. eAlliant, LLC,
supra; Pegasus Global Strategic Solutions, LLC,
B‑400422.3, Mar. 24, 2009, 2009 CPD ¶ 73 at 9.
In this regard, we have found that an immediate need for
services that arises as a result of an agency’s
implementation of corrective action in response to a
protest does not generally constitute a lack of advanced
planning. See eAlliant, LLC, supra, at 8; Systems
Integration & Mgmt., Inc., B‑402785.2, Aug. 10, 2010, 2010
CPD ¶ 207 at 3; Chapman Law Firm Co., LPA, B‑296847, Sept.
28, 2005, 2005 CPD ¶ 175 at 3. Our review of an agency’s
decision to conduct a noncompetitive procurement focuses
on the adequacy of the rationale and conclusions set forth
in the J&A; where the J&A sets forth a reasonable
justification for the agency’s actions, we will not object
to the award. Camden Shipping Corp., supra.
ASC first contends that any need for a sole-source bridge
contract arising from the Navy’s decision to terminate
ASC’s task order, cancel the RFP, and resolicit the
agency’s requirements was the result of the agency’s lack
of adequate advance planning. Specifically, the protester
contends that the agency failed to adequately determine
its requirements and associated evaluation criteria, and
points to the Navy’s apparently unsuccessful attempt to
remedy the concerns with the cost realism evaluation
criteria in amendment No. 3 to the RFP. See Protest (Dec.
16, 2015) at 10; ASC’s Comments (Jan. 27, 2016) at 16. The
protester relies on our recent decision in XTec, Inc.,
B-410778.3, Oct. 1, 2015, 2015 CPD ¶ 292, in support of
its argument that the Navy here engaged in a lack of
adequate advanced planning by cancelling the RFP based on
inadequate solicitation requirements. We find, however,
that the facts here are readily distinguishable from the
facts presented in XTec, and the record otherwise does not
show a lack of advanced planning by the Navy.
In XTec, our Office found that an agency had a reasonable
basis to cancel a solicitation where it determined, after
multiple rounds of awards, protests, and corrective
action, that the solicitation failed to contain adequately
detailed information regarding various contract
performance requirements. XTec, Inc., supra, at 9-10. We
sustained XTec’s protest challenging the cancellation of
the solicitation, and the award of a sole-source bridge
contract extension for the incumbent, because the record
showed that the procuring agency was aware of, and had
documented the need for, more detailed solicitation
requirements for nearly four years. Id. at 10-12. Thus,
our Office’s decision sustaining the protest was based on
the procuring agency’s failure to adequately plan how it
would address the flaws with the solicitation that had
been known by the agency for years.
In stark contrast to the facts in XTec, the record here
demonstrates that the Navy proactively sought to address
concerns with the RFP’s cost realism evaluation criteria
through issuance of amendment No. 3. To the extent the
Navy’s efforts in this regard introduced new problems
associated with the agency’s cost realism methodology, and
were ultimately unsuccessful, that is not the applicable
legal standard. eAlliant, LLC, supra; Pegasus Global
Strategic Solutions, LLC, supra. Thus, the circumstances
in XTec, where the procuring agency passively ignored
potential defects in the solicitation for almost four
years, are materially different than the circumstances
here.
ASC also challenges the urgent and compelling
justification for the sole-source bridge contract award to
BAH. The protester first contends that the urgency basis
for the award, which was predicated on preventing a lapse
in contract support when BAH’s incumbent task order ended
on December 1, is undermined by the fact that the bridge
contract was not fully executed by both parties until
December 29. See ASC’s Supp. Comments (Feb. 12, 2016) at
4-7. ASC further alleges that the delay in awarding the
bridge contract undermines the Navy’s position that BAH
was the only contractor capable of performing without a
significant material impact on the agency’s mission. See
id. at 7-9. We find that neither argument provides a basis
on which to sustain the protest. (American
Systems Corporation B-412501.2, B-412501.3: Mar 18,
2016) (pdf)
Cancellation of Solicitation
XTec first asserts that cancellation of RFQ No. 858797 was
improper since the RFQs “broadly worded requirements” were
sufficient in scope to cover all of the more detailed
requirements GSA now asserts must be included in the
solicitation. Protest at 8-14.
A contracting agency need only have a reasonable basis to
support a decision to cancel an RFQ. Progressive Servs. Corp.,
B-404183, B-404251.2, Jan. 11, 2011, 2011 CPD ¶ 18 at 2. A
reasonable basis to cancel exists when, for example, an agency
determines that a solicitation does not accurately reflect its
needs. MedVet Dev. LLC, B-406530, June 18, 2012, 2012 CPD ¶ 196
at 2-3.
The agency responds that, early in 2015, it was “made aware by
its customer agencies” that the solicitation “insufficiently
captured various agencies’ requirements.” Agency Legal
Memorandum, July 27, 2015, at 8. More specifically, the agency
maintains that the solicitation failed to contain detailed
requirements regarding the SIP interface between the customer
agencies’ systems and the USAccess system; failed to reflect
sufficient requirements regarding customer-owned hardware; and
identified a performance period that was too short. Id. at 8-10;
AR, Tab 10, Contracting Officer’s Cancellation Memo, May 6,
2015, at 2. Although not reflected in the contracting officer’s
cancellation memo, the agency’s response to this protest also
asserts that the solicitation should reflect a requirement for
“derived credentials,” which was “being developed” at the time
of cancellation. Agency Legal Memorandum, July 27, 2015, at 10.
Here, based on our review of the entire record, we cannot
conclude that the agency’s decision to cancel the solicitation
was unreasonable. That is, we cannot conclude that the
solicitation’s “high level” requirements were, in fact, adequate
to meet the government’s needs. Accordingly, we reject XTec’s
assertion that cancellation of the solicitation was
unreasonable.
[Agency’s failure to engage in reasonable and adequate
advance planning.]
Alternatively, XTec asserts that
cancellation of the solicitation was caused by the agency’s
failure to engage in reasonable and adequate advance planning.
We agree.
The Competition in Contracting Act of 1984 (CICA) generally
requires that agencies engage in “full and open competition”
when conducting government procurements. 41 U.S.C. § 3301(a).
While there are specific exceptions to this general requirement,
under no circumstances may noncompetitive procedures be used due
to a lack of advance planning by contracting officials. 41 U.S.C.
§ 3304(e)(5); New Breed Leasing Corp., B‑274201, B-274202, Nov.
26, 1996, 96-2 CPD ¶ 202 at 6; TeQcom, Inc., B‑224664, Dec. 22,
1986, 86-2 CPD ¶ 700. Our Office has recognized that, while the
requirement for advance planning does not mean that such
planning must be completely error‑free, see, e.g., Sprint
Communications Co., L.P., B-262003.2, Jan. 25, 1996, 96-1 CPD ¶
24, as with all agency procurement actions, the advance planning
required by CICA must be reasonable. In considering this
statutory requirement, we have noted that contracting officials
have a duty to promote competition. Precision Logistics, Inc.,
B-271429, July 18, 1996, 96-2 CPD ¶ 24 at 5; National Aerospace
Group, Inc., B‑282843, Aug. 30, 1999, 99‑2 CPD ¶ 43. That is,
contracting officials must act affirmatively to obtain and
safeguard competition; they cannot take a passive approach and
remain in a sole-source situation when they could reasonably
take steps to enhance competition. HEROS, Inc., B-292043, June
9, 2003, 2003 CPD ¶ 111 at 7.
Here, as discussed above, the agency asserts that it was
required to cancel the solicitation due to the solicitation’s
failure to adequately address various requirements of the
customer agencies, including the SIP interface requirements;
agency-owned hardware; training of agency personnel; and the
length of the performance period. See Agency Legal Memorandum,
July 27, 2015, at 8-10; AR, Tab 10, Contracting Officer’s
Cancellation Memorandum, May 6, 2015, at 2. In responding to
XTec’s protest, the agency asserts that it had no reason to know
of these solicitation omissions until its customer agencies
began expressing their concerns early in 2015. Id.
Contrary to the agency’s assertions, the record establishes that
the agency knew in 2011--when it justified, and defended, its
prior award of a sole-source task order to HPES--that the
USAccess system was “built around a proprietary set of
technologies that combine databases and middleware”; that
customer agencies had “invested heavily” in hardware for light
credentialing configurations; and that “[m]ost of the USAccess
customers have slightly different requirements for interface
with their internal systems,” each of which had required a
“custom interface.” Protest, exh. 1, Contracting Officer’s
Statement, Sept. 8, 2011, at 3-4. In short, the agency’s 2011
justification for not competing the logical follow-on task order
awarded to HPES expressly referenced the very concerns on which
it now relies to support its decision to cancel RFQ No. 858797.
Notwithstanding the agency’s 2011 documented recognition of the
need for detailed requirements, the agency published RFQ No.
858797 with only “high level” requirements, received and
evaluated quotations on that basis, and twice selected XTec for
award--asserting that it only reasonably knew that the
requirements were inadequate early in 2015. On the record here,
we reject the agency’s assertion that it did not know of the
necessity for more detailed requirements until earlier this
year.
Even if we were to conclude that the agency did not previously
know of the customer agencies’ need for more detailed
requirements, we reject the argument that such lack of knowledge
was reasonable. As noted above, pursuant to CICA’s requirements
for advance planning, contracting officials have an affirmative
obligation to promote competition and may not take a passive
approach to remaining in a sole-source situation when they could
reasonably take steps to enhance competition. HEROS, Inc.,
supra. Here, the [HSPD-12 Managed Services Office] MSO program
manager acknowledged at the GAO hearing that GSA had “a very
robust communication mechanism with our agency customers,” but,
nonetheless, that the customer agencies “felt like the things
they were concerned about . . . had not ended up in the RFQ.”
Tr. at 34, 36. In this context, the MSO program manager
acknowledged that “GSA should have reached out more strenuously
to the agency customers to ask them for further detail.” Id.
Similarly, the HCA testified that: “we . . . had some leadership
turnover in the last three years. . . [a]nd . . .the leadership
down to the program folks had not had experience in these kinds
of transitions and programs and just had not adequately thought
it through or planned for it.” Tr. at 501. On this record, we
sustain XTec’s protest based on the agency’s failure to engage
in reasonable advance planning.
Extension of HPES’s Task Order
XTec also protests that the extension of HPES’s sole-source task
order similarly flowed from the agency’s failure to engage in
advance planning, and further asserts that the extension was
illegal in that the agency provided no justification for that
action until nearly two months after it had taken place. For the
reasons discussed above, we agree that the agency’s extension of
the task order was caused by its failure to engage in reasonable
advance planning, and sustain the protest.
We further view the agency’s failure to either execute or
publish the LSJ for nearly two months after the action was taken
to be contrary to the requirements of CICA, under which such
justification must generally be executed prior to the action
being taken, and notice of the action must be published within
14 days. 41 U.S.C. §§ 3304(e), (f). Here, there can be no
dispute that the agency failed to comply with these
requirements. Nonetheless, in light of our decision sustaining
the protest for failure to engage in reasonable advance
planning, and our recommendations below, we do not further
address this matter.
RECOMMENDATION
Since we do not question the reasonableness of the agency’s
determination that RFQ No. 858797 failed to adequately address
the government’s requirements, and there is no dispute that the
government has an ongoing need for the HSPD-12 services, we do
not recommend that the cancelled solicitation be reinstated or
that HPES’s ongoing performance of the sole-source task order be
terminated. We do recommend that the agency make expeditious
efforts to prepare the new solicitation and conduct a
competition thereunder. Further, based on the agency’s extension
of the HPES task order for up to two years, we recommend that
GSA reimburse XTec for the proposal preparation costs it
incurred in responding to the solicitation that GSA now
concludes was fatally flawed. See The Jones/Hill Joint Venture,
B‑286194.4 et al., Dec. 5, 2001, 2001 CPD ¶ 194 at 22; COBRO
Corp., B‑287578.2, Oct. 15, 2001, 2001 CPD ¶ 181 at 9. Finally,
we recommend that the protester be reimbursed the reasonable
costs of filing and pursuing its protest, including reasonable
attorneys’ fees. 4 C.F.R. § 21.8(d)(1). The protester’s
certified claim for costs, detailing the time spent and costs
incurred, must be submitted to the agency within 60 days of
receiving this decision. 4 C.F.R. § 21.8(f)(1). (XTec,
Inc. B-410778.3: Oct 1, 2015) (pdf)
Trison contends that the Army's decision to limit the
competition to existing MATOC holders is inconsistent with its
proposed corrective action, which caused our Office to dismiss
Trison's prior protest as academic. Protest at 5. The protester
argues that the goals of the protest system are circumvented
where the agency does not promptly implement its promised
corrective action. Id. at 5--7. In this respect, the protester
suggests that (although it states that it does not allege that
the Army acted in bad faith) the agency's actions are a "mere
pre-text and not rationally related to the agency's own stated
corrective action." Comments at 4. Finally, Trison challenges
the urgency of the agency's needs, complaining that the agency
waited 12 days to decide how to procure the requirement after
terminating EEC's contract and canceling the IFB, and argues
that the urgency associated with the agency's requirements are
the result of poor procurement planning. Id. at 7.
The agency responds that resoliciting under a new IFB (as the
agency originally contemplated) would "endanger the Agency's
ability to assure that the work could be completed within the
necessary time limits." Contracting Officer's Statement, Sept.
4, 2009, at 2. Specifically, the agency states that a wide
variety of operations and activities are being transferred to
APG under base realignments and closures (BRAC) and that the
renovations are necessary to prepare a building that houses the
APG's data center, a mission critical facility for the entire
APG installation. Id. In this regard, the agency expects an
influx of personnel and a four-fold expansion of the capacity of
existing systems in the building and states that the
construction services (which would take at least 270 days) must
be completed by June 2010 to allow for occupancy in August. Id.
Following the July 17 dismissal of Trison's prior protest,
agency officials met on July 21 to consider how to satisfy the
agency's urgent requirements; among the acquisition methods
considered were whether to resolicit under a new IFB or to
conduct a limited competition among MATOC holders. The agency
concluded that, if it resolicited under a new IFB, award would
likely not be made until mid-October, which the agency believed
would likely not leave sufficient time for completion of the
renovation services by June. The Army decided that it would
conduct a limited competition among MATOC holders to satisfy its
requirements. Id. at 2--3.
The record provides no basis to conclude that the agency acted
unreasonably in deciding to restrict the resolicitation of the
renovation services to MATOC holders to satisfy the agency's
urgent requirements. Although Trison complains that the agency
waited 12 days to decide how to reprocure the requirement after
taking corrective action in response to the prior protest, the
protester does not assert that the agency lacks an urgent basis
for the completion of these renovation services by June 2010,
nor show that the agency's urgent requirement could be timely
satisfied by issuing a new IFB. Given that the agency reasonably
found that resoliciting these requirements under a new IFB would
not timely satisfy its urgent requirements, we have no basis to
object to the agency's decision not to issue a new IFB.
Also, we are not persuaded by Trison's arguments that the
agency's urgent requirements were created by the agency's taking
12 days after announcing that it would initiate corrective
action to decide how to obtain these services or from the errors
made in drafting the prior IFB. Although the prior IFB was
ambiguous with respect to the price evaluation of certain
contract line items, this alone does not establish that the
agency's urgent requirements were the result of a lack of
advanced procurement planning. See, e.g., New Breed Leasing
Corp., B-274201, B-274202, Nov. 26, 1996, 96-2 CPD para. 202 at
6; Sprint Commc'ns Co., LP, B-262003.2, Jan. 25, 1996, 96-1 CPD
para. 24 at 9 (an agency's obligation to engage in reasonable
advance planning prior to conducting procurements does not
constitute a requirement that procurement planning be perfect or
completely error-free). We also think that taking 12 days to
determine an appropriate acquisition approach was
unobjectionable.
Finally, the record does not support Trison's allegation that
the cancellation of the IFB and decision to conduct a limited
competition among MATOC holders was a "mere pretext" to avoid
resoliciting Trison. As noted above, the record shows that the
Army reasonably found that resoliciting under a new IFB likely
would not meet the agency's urgent requirements. Trison's
arguments that the agency's actions are a "mere pretext" are
based upon no more than inference and supposition, upon which
our Office will not attribute unfair or prejudicial motives to
procurement officials. See Shinwha Elecs., B-290603 et al.,
Sept. 3, 2002, 2002 CPD para. 154 at 5 n. 6. (Trison
Construction, Inc., B-401537.2, November 9, 2009) (pdf)
We agree with the agency that the circumstances presented met
the requirements for an exception to full and open competition
due to an unusual and compelling urgency, when, at the end of
DAV Prime JV's contract, it did not have a follow-on contract in
place for services during the summer months--when the portable
chemical toilet services would be most used. However, the record
here evidences that the urgency resulted from the Army's failure
to adequately plan for this procurement in advance and that DAV
Prime JV was not the only firm interested and capable of
performing these services.
The Army knew in August 2008 of the OHA's decision that DAV
Prime JV was not an SDVOSBC. Both the SBA and our Office's
decision in November 2008 suggested that the Army should
consider whether to exercise an option, since DAV Prime JV had
been found not to be an eligible SDVOSBC. In early March 2009,
approximately 5 months later, the agency finally determined that
it would not exercise the first option year because DAV Prime JV
was not pursuing efforts to meet the eligibility requirements
for an SDVOSBC joint venture.
The agency points to the delay in issuing a new
solicitation--due to a rather broad NAICS Code for septic tank
and related services--as the reason for the delay in procuring
follow-on services and the cause of the urgency. However, as the
market survey took longer than expected, it is apparent that the
agency should reasonably have been aware that the follow-on
contract would not be in place by May 31, the date DAV Prime
JV's contract expired, and that the agency was required to plan
how it would obtain these services until the follow-on contract
would be in place.
If there was not time for full and open competition for the
interim services until the follow-on contract was executed, in
accordance with FAR Subpart 6.3, the agency should have
conducted a limited competition among qualified sources who the
agency found would be interested in performing the services.
While the final results of the market survey, which ultimately
led to the agency's decision to issue the follow-on procurement
as a small business set-aside, took longer than the Army
anticipated, the survey identified potential qualified sources
that would be interested in providing these services and could
have been included in a limited competition. Further, because
the Fort Drum requirement for portable chemical restroom
services was "a recurring requirement that has been procured by
contract for at least the last 10 years," see MCS's Sept. 19,
2008 Protest, Agency Acquisition Strategy, at 1, the Army was
presumably already familiar with the potential sources who could
provide these interim services. Indeed, MCS, a qualified firm,
had already indicated its interest and capability of providing
these services. Thus, the record evidences that DAV Prime JV was
not the only firm capable of performing these services.
Based on this record, the agency's has not provided a reasonable
basis for the sole‑source extension. It is apparent that the
Army did not properly plan in advance for its requirement to
extend this contract; we do not think that the agency could sit
idly by in the face of the circumstances here and not take
action to obtain more competition for its requirements. VSE
Corp.; Johnson Controls World Servs., Inc., B‑290452.3, et al.,
May 23, 2005, 2005 CPD para. 103 at 9.
MCS's protest is sustained. (Major
Contracting Services, Inc., B-401472, September 14, 2009)
(pdf)
Under CICA, 41 U.S.C. sect. 253(a)(1)(A), contracting officers
have a duty to promote and provide for competition and to
provide the most advantageous contract for the government. In
their role of promoting and providing for competition,
contracting officials must act affirmatively to obtain and
safeguard competition; they cannot take a passive approach and
remain in a noncompetitive position where they could reasonably
take steps to enhance competition. VSE Corp., Johnson Controls
World Servs., Inc., B-290452.3 et al., May 23, 2005, 2005 CPD
para. 103 at 8; HEROS, Inc., B-292043, June 9, 2003, 2003 CPD
para. 111 at 7; National Aerospace Group, Inc., B-282843, Aug.
30, 1999, 99-2 CPD para. 43 at 8. See also S. Rep. No. 98-50, at
18 (1984), reprinted in 1984 U.S.C.C.A.N. 2174, 2191 (stating
that CICA requires agencies to “make an affirmative effort to
obtain effective competition”). CICA further provides that under
no circumstance may noncompetitive procedures be used due to a
lack of advance planning by contracting officials. 41 U.S.C.
sect. 253(f)(5)(A); Signals & Sys., Inc., B-288107, Sept. 21,
2001, 2001 CPD para. 168 at 9. Although the requirement for
advance planning is not a requirement that such planning be
successful or error-free, see Abbott Prods., Inc., B-231131,
Aug. 8, 1988, 88-2 CPD para. 119, at 8, the advance planning
must be reasonable. Signals & Sys., Inc., supra, at 13. Here, we
conclude that the agency has failed to comply with the CICA
mandate for reasonable advance planning. With regard to the
feasibility of alternatives to a sole-source award, the agency
principally focuses on the difficulties associated with either
acquiring a new software system, or having another firm perform
the required services without license rights to the RGII
software. The agency also asserts that its advance planning
efforts have been reasonable in that it has taken steps to avoid
expansion of its reliance on RGII. In this regard, the agency
notes, for example, that it has been considering using a program
developed by another agency office, the Bureau of European
Affairs, to meet its needs here, instead of contracting with
RGII for the development of additional proprietary software.
Agency’s Response to GAO Questions, supra, at 4. While, as
discussed above, it is reasonable to conclude that, given the
restrictive nature of the agency’s current licensing agreement
with RGII, only RGII can now meet its needs, the agency’s
arguments simply do not address the issue of whether the
agency’s acquisition planning--in the face of those
restrictions--was reasonable, given the requirement that the
agency make an affirmative effort to obtain competition. The
agency has produced no record of any steps that it has taken to
end its reliance on the services of the incumbent to maintain
the existing software systems; in fact, this latest proposed
sole-source award has a potential term of 5 years. It is
possible, for example, that the agency could purchase additional
rights to the proprietary software in order to promote
competition, see Environmental Tectonics Corp., B‑248611, Sept.
8, 1992, 92-2 CPD para. 160 at 5, rights that the government
relinquished nearly 6 years ago. In this regard, the protester
asserts that in 2004 RGII offered the agency a source code
license to multiple copies of Monument for less than $1.2
million, and that at the time RGII stated that the value of
Monument was less than $1 million. Protest, Tab E, Letter from
Protester to Agency, Aug. 7, 2006, at 2. Further, the agency
acknowledges that the “value of the software may in fact now be
quite limited.” Agency’s Response to GAO Questions, supra, at 3.
Under the circumstances here--where the agency ceded substantial
rights in the software created by RGII under the development
contract, and where there is no indication that the agency has
explored the possibility of acquiring additional rights from
RGII--we think that, to satisfy its obligation to engage in
reasonable advance planning and to promote competition, the
agency was required to consider whether the costs associated
with a purchase of additional license rights, or some other
alternative, outweigh the anticipated benefits of competition.
See HEROS, Inc., supra, at 7, 10. (eFedBudget
Corporation, B-298627, November 15, 2006) (pdf)
While we do not question the agency's need for a
transition period (even though the record does not clearly
establish that this period is required to take as much as 4
months), we agree with VSE that the agency's predicament of not
being able to complete a transition period in the event of an
award to a firm other than EG&G was caused by the agency's
failure to consider meeting its requirement for these bridge
services with any firm other than EG&G. In this regard, the
record evidences that the agency was aware from the start of
2004, and increasingly certain as the year passed, that the RFP
might well be canceled; that EG&G's latest contract extension
would expire on April 1, 2005; that a follow-on contract would
require a transition period; and that there were other capable
contractors, such as VSE and Johnson Controls, which had
competed during the agency's protracted competitive procurement,
that might be interested in the agency's interim requirements.
Yet the agency did not take any steps to avoid having to
negotiate exclusively with EG&G to satisfy its requirements.
Under the Competition in Contracting Act of 1984 (CICA), 41
U.S.C. 253(a)(1)(A), contracting officers have a duty to promote
and provide for competition and to provide the most advantageous
contract for the government. In doing so, contracting officials
must act affirmatively to obtain and safeguard competition; they
cannot take a passive approach and remain in a noncompetitive
position where they could reasonably take steps to enhance
competition. See Signal & Sys., Inc. , B-288107, Sept. 21, 2001,
2001 CPD 168 at 14-15. Thus, 41 U.S.C. 253(f)(5)(A) provides
that under no circumstance may noncompetitive procedures be used
due to a lack of advanced planning by contracting officials.
Signal & Sys., Inc. , supra , at 9. Although the requirement for
advanced planning is not a requirement that such planning be
successful or error-free, see Abbott Products, Inc. , B-231131,
Aug. 8, 1988, 88-2 CPD 119, the advanced planning must be
reasonable. Signal & Sys., Inc. , supra , at 13. Also, even
where the agency has a basis to conduct a noncompetitive
procurement, it is still required to request offers from as many
potential sources as is practicable under the circumstances. 41
U.S.C. 253(e); Signal & Sys., Inc. , supra , at 8-9. As
described above, even though the agency was increasingly aware
many months in advance that the on-going competitive
solicitation for these services might well be cancelled, the
only alternative considered by the agency was the sole-source
extension of EG&G's contract. If the agency had earlier planned
to compete for these interim services, as required, a transition
period between EG&G's existing contract and the bridge contract
could have been accommodated, given that there were more than 4
months between when the RFP was actually cancelled and when EG&G's
contract expired. In this regard, the record evidences that the
agency could easily have decided earlier to cancel the RFP,
given that virtually all of the reasons for the cancellation
were apparent months earlier. Thus, we find that the
circumstance of not having sufficient time to complete a
transition period was created by the CBP's failure to engage in
reasonable advanced procurement planning. See Techno-Sciences,
Inc. , B-257686, B-257686.2, Oct. 31, 1994, 94-2 CPD 164 at 9,
11 (agency needs to account for reasonable phase-in periods to
achieve adequate advance procurement planning). The situation
here is exacerbated by the fact that EG&G's incumbent contract
expired in May 2001 and has been extended on a sole-source basis
for the past 4 years. Moreover, while the base period for the
protested sole source contract extension is only for 6 months,
the record evidences that the agency anticipates that the full
18 months will be needed before the new contractor selected
under the anticipated competitive procurement can start contract
performance. See Draft J&A. In sum, we do not think that
the agency could sit idly by in the face of the circumstances
present here and not consider obtaining more competition for its
sole-source requirements. (VSE
Corporation; Johnson Controls World Services, Inc.,
B-290452.3; B-290452.4; B-290452.5, May 23, 2005) (pdf)
In enacting CICA, Congress explained: “Effective competition is
predicated on advance procurement planning and an understanding
of the marketplace.” S. Rep. No. 50, 98th Cong., 2d Sess. 18
(1984), reprinted in 1984 U.S.C.C.A.N. 2191. The Senate Report
also quoted with approval the following testimony regarding the
need for advance planning:
Opportunities for obtaining or
improving competition have often been lost because of
untimely, faulty, or the total lack of advance procurement
planning. Noncompetitive procurement or inadequate competition
also has resulted many times from the failure to develop
specifications . . . . By requiring effective competition,
Congress will serve notice on the agencies that they will need
to do more than the minimum to comply with the statute.
S. Rep. No. 50, 98th Cong., 2d Sess. 19 (1984), reprinted in
1984 U.S.C.C.A.N. 2192. Finally, in interpreting this
statutory requirement, our Office has noted that contracting
officials have a duty to promote and provide for competition
and to obtain the most advantageous contract for the
government. Precision Logistics, Inc., B-271429, July 18,
1996, 96-2 CPD ¶ 24 at 5; National Aerospace Group, Inc.,
B‑282843, Aug. 30, 1999, 99-2 CPD ¶ 43. In other words,
contracting officials must act affirmatively to obtain and
safeguard competition; they cannot take a passive approach and
remain in a sole-source situation when they could reasonably
take steps to enhance competition. Here, the Army's
actions over the past several years fail to comply with CICA's
statutory mandate for reasonable advance planning.
(HEROS,
Inc., B-292043, June 9, 2003) (pdf) |