FAR
6.303: Justifications |
Comptroller General - Key Excerpts |
As a general matter, when an agency uses noncompetitive
procedures, it must execute a J&A with sufficient facts and
explanation to support the use of the specific authority. See 10
U.S.C. § 2304(f). Our review of an agency’s decision to conduct
a sole-source procurement focuses on the adequacy of the
rationale and conclusions set forth in the J&A. When the J&A
sets forth reasonable justifications for the agency’s actions,
we will not object to the award. Turbo Mechanical, Inc.,
B‑231807, Sept. 29, 1988, 88-2 CPD ¶ 299 at 3-4. The protester’s
disagreement with the agency’s rationale does not provide a
basis to sustain the protest; rather, the protester must show
that the agency’s position is unreasonable. Allied-Signal Inc.,
B-247272, May 21, 1992, 92-1 CPD ¶ 461 at 10.
Regarding the allegation that DARPA has unreasonably defined its
requirements, the protesters essentially attempt to re-cast this
contract as a “back-door” attempt to award a major weapons
system contract to Lockheed, on behalf of the Navy. Protest at
19. In this connection, the protesters’ arguments concerning the
rationale set forth in the sole-source notice and J&A proceed
from the premise that DARPA’s requirement is not the completion
of additional LRASM missile technology maturation, fabrication,
and test flights for the LRASM Development Program, as claimed,
but is in fact the production of a weapon system to meet Navy
requirements and fulfill the DOD capability gap in anti-surface
warfare capability. By redefining DARPA’s current requirement as
a generic “capability,” required by the Navy, rather than as the
completion of an ongoing LRASM research and development effort
involving highly specialized and proprietary skills and
equipment, the protesters position themselves to make the
argument that their competing missile technologies can meet the
government’s “true requirement.”
We conclude that the protesters’ attempts in this regard are
misplaced. As our office has held, agencies have broad
discretion to determine their needs and the best way to meet
them. URS Federal Support Servs., Inc., B-407573, Jan. 14, 2013,
2013 CPD ¶ 31. In this case, both the sole-source notice and J&A
define DARPA’s requirement as relating to the specific LRASM
missile technologies developed by Lockheed pursuant to the 2008
LRASM BAA.
For example, as stated in part above, the sole-source notice
published by DARPA described a requirement to:
Continue maturation of the LRASM subsystems
and system design that Lockheed Martin has developed under the
current contract awarded in 2009 after full and open
competition. The follow-on effort will conduct further sensor
and avionics hardware development based on previous results
achieved under the current contract. It will also provide for
fabrication of missile hardware to enable additional flight
tests.
AR, Tab 17, Sole-Source Notice, at 1.
Similarly, the DARPA J&A contains a statement of requirements
providing that:
Under the follow-on effort [Lockheed] will
provide specialized services for continuing technology
maturation work on the LRASM subsystems and system design.
[Lockheed] will also continue to mature technologies developed
under the current R&D contract for the air-launched
anti-surface warfare (ASuW) LRASM.
AR, Tab 3, J&A, at 1. The J&A also further
specified six specific areas of LRASM technological development
to be pursued during the follow-on contract, including: the long
range target sensor; sensor algorithms and software; missile
control unit; electro-optical terminal target sensor hardware;
missile autonomy and situation awareness software; and weapon
data link.
We see nothing unreasonable or misleading in the agency’s
statement of its requirement. Pursuant to the 2008 BAA, DARPA
has invested substantially in the research and development of
the LRASM technologies proposed by Lockheed in its response to
the 2008 BAA. Related to this effort, DARPA has now identified a
need to devote additional resources in order to complete the
maturation of Lockheed’s specific LRASM technologies. We view
this need, as identified in DARPA’s sole-source notice and J&A,
as reasonable and within DARPA’s broad discretion as the DOD
agency tasked with developing new technologies, without regard
to whether the Navy, or DOD, has an operational requirement for
similar capabilities in this area. (Raytheon
Company and Kongsberg Defence & Aerospace AS, B-409615,
B-409615.2: Jun 24, 2014) (pdf)
As a preliminary matter, USDA argues that the Coulson and Minden
protests should be dismissed because these protesters are not
interested parties. Specifically, the agency contends that
Coulson and Minden did not have additional large airtankers
available at the time the J&A was signed that would be capable
of performing the requirements of the Neptune sole-source
contract (which has an April 28, 2014, start date).[31] The USDA
contends, citing to our decision in Merlin Int’l, Inc.,
B-310611, Jan. 2, 2008, 2008 CPD ¶ 66, that a protester is not
an interested party to challenge a sole-source award unless it
can meet all of the agency’s requirements at the time of the
sole-source determination.
Coulson and Minden respond that they are interested parties to
protest here because they have a direct economic interest that
would be affected by the award of a sole-source contract to
Neptune. Coulson points to the fact that in October 2013 it
offered to provide the Forest Service with two additional large
airtankers under the NextGen contract, and argues it would be
available and ready to perform by an April 28, 2014, start date
(as established by the contract awarded to Neptune). Coulson
Protest, Dec. 20, 2013, at 7-8; Coulson Protest, Feb. 10, 2014,
at 4. Likewise, Minden states that it owns a second aircraft
(BAe-146) that it is converting into an airtanker, and would be
able to submit a proposal should the Forest Service conduct
another competitive procurement. Minden Protest, Feb. 10, 2014,
at 2-3. Both Coulson and Minden also point to the fact that the
sole-source award to Neptune makes it less likely that the
Forest Service would execute airtanker options under the
competitively-awarded NextGen contract.
(section deleted)
The Settlement Agreement
The protesters contend that the sole-source award to Neptune was
improper, insofar as the agency promised to enter into the
contract in exchange for Neptune withdrawing its protests of the
NextGen contract awards. In this regard, the protesters claim
that the agency’s actions have been motivated by the desire to
fulfill the terms of a settlement agreement and to avoid a
lawsuit by Neptune for allegedly breaching that agreement. The
protesters argue that the agency “put the cart before the
horse,” and agreed to settle Neptune’s protest before properly
determining that the promised sole-source award complied with
CICA. Coulson Protest, Feb. 10, 2014, at 55. The protesters also
point to the fact that the only legitimate financial analysis
conducted (the analysis by FI) demonstrated that Neptune did not
require a sole-source contract to remain viable, as recognized
by the agency’s SPE, who refused to approve the J&A. 10 Tanker
Protest, Feb. 10, 2014, at 120-35.
The USDA does not dispute that its consideration of a
noncompetitive award to Neptune was motivated by its promise of
a sole-source contract in exchange for Neptune withdrawing its
bid protest and thereby ending the CICA stay that then precluded
the Forest Service from fielding NextGen large airtankers for
the 2013 fire season. See AR, Jan. 31, 2014, at 55.
Nevertheless, USDA argues that it did not act improperly because
the sole-source award complied with all applicable procurement
statutes and regulations. Id. at 55‑56.
A settlement agreement promising award of a contract on a
sole-source basis in exchange for abandoning ongoing litigation,
such as a bid protest, is not a permissible basis for
restricting competition and excluding potential offerors. Earth
Prop. Servs., Inc., B-237742, Mar. 14, 1990, 90-1 CPD ¶ 273 at
4-5, aff’d, B-237742.2, June 11, 1990, 90-1 CPD ¶ 546; Techplan
Corp., B-234161, May 12, 1989, 89-1 CPD ¶ 452 at 5. For example,
our Office upheld a protest of a sole‑source award where an
agency justified its failure to conduct a full and open
competition on the basis that it had entered a settlement
agreement promising the award of a contract in exchange for
abandoning a threatened contract claim. Earth Prop. Servs.,
Inc., supra. Quite simply, the existence of a settlement
agreement does not permit a contracting agency to act in ways
not otherwise permitted by applicable statutes and regulations.
Id. at 5; see York Int’l Corp., B-244748, Sept. 30, 1991, 91-2
CPD ¶ 282 at 4-5 (settlement agreements will not be enforceable
if they fail to comply with applicable statutes and
regulations).
As detailed below, the Forest Service entered into a settlement
agreement with Neptune on the basis that the award of a
sole-source, NextGen-type contract was necessary to maintain
Neptune as a vital source of large airtankers. The independent
financial analysis subsequently performed by FI on behalf of
USDA concluded that Neptune did not require the award of a
sole-source contract to remain financially viable. Nothing in
the record refutes FI’s conclusions, nor is there any evidence
to suggest that Neptune intends to go out of business now merely
because its future prospects appear uncertain. In sum, while the
agency may not have entered into a settlement agreement
promising to disregard applicable procurement statutes and
regulations, the agency’s subsequent decision to award a
sole-source contract to Neptune so as to comply with the terms
of the settlement agreement and avoid a Neptune-threatened
lawsuit was without a reasonable basis.
Sole-Source Award Justification
As set forth above, agencies are generally required to conduct
procurements using procedures designed to obtain full and open
competition. 41 U.S.C. § 3301(a)(1); FAR § 6.101. One exception
to this requirement is where an agency determines that it is
necessary to maintain a vital source of supply for industrial
mobilization. In relevant part, the FAR states as follows:
(2) Full and open
competition need not to be provided for when it is necessary
to award the contract to a particular source or sources in
order--
(i) To maintain a facility, producer, manufacturer, or other
supplier available for furnishing supplies or services in case
of a national emergency or to achieve industrial mobilization.
FAR § 6.302-3(a).
The protesters generally do not dispute that the Forest Service
requires additional large airtankers to perform its firefighting
mission. Rather, the protesters challenge the reasonableness of
the agency’s determination that the sole-source contract here is
necessary to maintain a vital source of supply. Specifically,
the protesters argue that: (1) Neptune is not a vital supplier
such that the large airtanker industrial base can be maintained
without resorting to noncompetitive procurements; and (2)
Neptune does not require a sole-source contract to remain a
source of large airtankers.
In responding to the protests, the agency has acknowledged that
it was initially concerned that Neptune would “immediately go
out of business in during [sic] the 2013 fire season, leaving
the Forest Service without any of the Legacy air tankers Neptune
supplied under the contract awarded March 27, 2013.” Agency
Post- Hearing Comments, Mar. 18, 2014, at 5. The agency admits,
however, that ultimately it concluded there was no concern with
Neptune’s present viability, but only with its viability after
2017. Id. at 6-7. Consequently, the agency argues, the J&A was
not grounded on the agency’s belief that Neptune would
immediately go out of business without a NextGen contract, but
was based on its concern with Neptune’s continued availability
as a large airtanker supplier after 2017 when its Legacy
contract expired. AR, Feb. 19, 2014, at 3-7. However, changing
its focus during the course of the protests, the agency has also
argued that its actual concern is whether it could obtain
sufficient NextGen airtankers for the 2014 fire season. See
Agency Post-Hearing Comments, Mar. 18, 2014, at 9-10, 21; see
also Tr. at 657-693. In this regard, the agency maintains that
it cannot tolerate any further delay in acquiring additional
NextGen airtankers for the 2014 fire season. Agency Post-Hearing
Comments, Mar. 18, 2014, at 28. The Forest Service contends that
this immediate need for additional NextGen airtankers provided
it with “an industrial mobilization need in December 2013” when
it decided to award Neptune a sole‑source, 9-year contract for
NextGen airtanker services. Id. at 32.
Based upon on our review of the record, including the J&A, its
supporting documentation, the agency’s submissions in response
to these protests, and the testimony of the agency’s
representatives at the hearing held at our Office, the agency
has failed to demonstrate that Neptune requires a sole-source
contract to remain a source of large airtanker services for the
Forest Service. Although the J&A documents the agency’s belief
that Neptune is, presently, a vital supplier of large airtanker
services under Neptune’s Legacy contract,[35] the J&A is devoid
of evidence or analysis supporting the need to provide Neptune
with a sole-source award for the firm to remain a viable source
of supply. Rather, the record demonstrates, as acknowledged by
the agency, that Neptune is presently financially viable and is
expected to remain financially viable through the term of its
Legacy airtanker contract (2017). Moreover, apart from Neptune’s
own unsupported statements and the anecdotal views of various
agency officials, the record contains no analysis or evidence of
Neptune’s financial condition after 2017.
As detailed above, the agency had two financial analyses of
Neptune conducted after the company alleged it would go out of
business without a NextGen contract award. First, RUS’s
conclusion, that Neptune needed a NextGen contract to remain
viable, was based entirely on unverified financial projections
as provided by Neptune. By contrast, the second analysis
conducted by FI--which did not simply accept Neptune’s
projections--found that Neptune’s revenue projections were
inconsistent with the terms of the Legacy contract, that
Neptune’s expected costs were lower than the company had itself
projected, and that Neptune did not require a NextGen contract
to remain viable through the term of the Legacy contract. At no
time before the J&A was approved were FI’s conclusions disputed
or shown to be in error. Moreover, while FI’s conclusions were
limited to the period through 2017, at no time did the agency
conduct any other analysis to determine Neptune’s financial
viability after 2017. Tr. at 735; Agency Post-Hearing Comments,
Mar. 18, 2014, at 7. Accordingly, while the agency contends that
the J&A did not rely on the FI financial analysis to assess
Neptune’s long-term viability, neither did the agency rely on
any other information when making such an assessment. In fact,
there is simply no record--in the J&A or otherwise--of any
assessment by the agency of Neptune’s long-term viability.
Additionally, the agency’s apparent belief that an immediate
need for NextGen airtankers in 2014 justified the award of a
sole-source, 9-year contract on the basis of industrial
mobilization is not supported and has no rational basis. The
industrial mobilization exception to competition requirements
may be used where an agency determines that “it is necessary to
award the contract to a particular source . . . in order . . . [t]o
maintain a . . . [vital] supplier . . . .” FAR § 6.302-3(a)(2)(i).
As noted above, no reasoned analysis has been presented to
support a determination that a 9-year, sole-source contract was
required to maintain Neptune as a source. To the extent the
agency believed an urgent need for large airtanker services
would justify a noncompetitive 9-year contract, there is no
analysis or explanation in the record demonstrating that this is
so.
We find it both premature and unreasonable for USDA to determine
that Neptune requires a sole-source contract now in order to
maintain Neptune as a source of large airtanker services after
2017. In addition to its current Legacy contract (including
options for more airtankers being placed under the Legacy
contract), Neptune is not precluded from competing on
work--Forest Service or otherwise--in the coming years. The
record also reflects that the NextGen contracts represent the
primary, but not only, means by which the Forest Service plans
to meet its modernization strategy goal of 18-28 modern large
airtankers. In fact, the ASA testified that the agency plans to
conduct additional competitions in the coming years under which
Neptune is eligible to compete and could receive awards. Tr. at
735-36. Moreover, given the contract options available to the
Forest Service under the competitively-awarded NextGen
contracts, Neptune may no longer represent a vital source that
must be maintained by the Forest Service after 2017. While
agencies have authority to make noncompetitive awards when
necessary to maintain vital sources, they do not have authority
to make noncompetitive awards merely because an offeror is
unsuccessful in a competitively-conducted procurement, or
because such action was promised in a settlement agreement. See
York Int’l Corp., supra; Department of the Army--Recon.,
B-237742.2, June 11, 1990, 90-1 CPD ¶ 546.
Accordingly, while the J&A may demonstrate that the Forest
Service needs more large airtanker services than it currently
has under contract, the J&A completely fails to demonstrate that
Neptune must be the supplier of such services or that Neptune
currently requires a 9-year sole-source contract to keep it in
business as a vital supplier for the agency’s post-2017 needs.
Just as an agency is not permitted to make a noncompetitive
award that exceeds the size or duration of an identified
urgency, see FAR § 6.302-2(d), an agency is also not permitted
to make a noncompetitive award for industrial mobilization
reasons where, as here, there has been no showing that the award
is presently necessary to maintain a supplier even if deemed
vital. NI Indus., Inc., Vernon Div., supra. Neptune would
undoubtedly prefer the financial security that would accompany a
long-term NextGen contract, but this is simply not the standard
by which an agency is permitted to make a noncompetitive award
for industrial mobilization purposes. See FAR § 6.302-3.
Inaccuracies in J&A
As a final matter, in addition to the fundamental lack of
support for the J&A’s premise that Neptune now requires a 9-year
sole-source contract in order to maintain the firm in the future
as a vital supplier of aircraft, the record reflects that the
J&A was premised on materially inaccurate information. As stated
above, our review of an agency’s decision to conduct a
noncompetitive procurement focuses on the adequacy of the
rationale and conclusions set forth in the J&A. The adequacy of
the rationale and conclusions set forth in the J&A is dependent
on the completeness and accuracy of the information included in
the J&A. See Sabreliner Corp., supra. We find the J&A to be
incomplete and inaccurate in certain key regards.
FAR § 6.303-2 identifies information required for an agency’s
justification of a noncompetitive procurement, stating, among
other things, that the J&A “shall include . . . [a] description
of the supplies or services required to meet the agency’s needs
(including the estimated value),” “[a] demonstration that the .
. . nature of the acquisition requires use of the authority
cited,” and “[a] description of the market research conducted .
. . and the results or a statement of the reason market research
was not conducted.” FAR § 6.303-2(b)(3), (5), (8). Here, the
Forest Service’s description in its J&A of its noncompetitive
requirements, as well as its consideration of alternative
sources of supply, is inaccurate.
Specifically, the J&A describes the services to be provided by
Neptune as two NextGen large airtankers for up to 9 years, at a
total estimated value of $141 million. AR, Tab 49, J&A, Dec. 9,
2013, at 1. The record shows, however, that the contract
subsequently awarded to Neptune included the option of five
additional large airtankers, for up to 9 years each, at a total
estimated value of approximately $496 million--more than three
times greater than what was approved. See AR, Tab 54, Contract
No. AG-024B-C-14-9000, at B-1. Thus, the agency’s J&A
inaccurately described the services to be obtained from Neptune
on a noncompetitive basis. This is significant because where, as
here, an agency proposes to award a sole-source contract under
the industrial mobilization exception to the general competition
requirements, the amount being ordered must meet--not
exceed--the objectives of this authority. See FAR §
6.302‑3(b)(iii) (when the quantity required is substantially
larger than the quantity that must be awarded in order to meet
the objectives of this authority, that portion not required to
meet such objectives will be acquired by providing for full and
open competition); Honorable Dan Burton, B-265884, Nov. 7, 1995,
1995 U.S. Comp. Gen. LEXIS 735 at *12. Alternatively, if the J&A
was accurate here, then the contract awarded to Neptune
impermissibly exceeded what the ASA had approved.
Similarly, when considering alternative sources and the market
research regarding such sources, the J&A states that “[t]here
are no certified [large airtankers] currently available that
aren’t already under contract with the Forest Service. Aircraft
capable of meeting these standards and requirements are not
readily available and would take a considerable amount of time
to be developed and operationally ready for service.” AR, Tab
49, J&A, Dec. 9, 2013, at 4. This statement is also factually
inaccurate insofar as 10 Tanker had a certified large airtanker
currently available, which the Forest Service actually
contracted for in 2013. The J&A also failed to consider the
additional large airtankers that Coulson had offered to make
available to the Forest Service. The fact that the J&A was
inaccurate with regard to alternative sources is also important
because where, as here, an agency proposes to award a
sole-source contract premised on the vital nature of a supplier,
it must accurately consider whether the industrial base can be
maintained without resorting to noncompetitive procurements.
While the agency argues the fact that other contractors may have
airtankers available to perform Neptune’s contract to be
irrelevant here, AR, Jan. 31, 2014, at 52, we fail to see how
the agency can reasonably find Neptune to be a vital source
without accurately considering all sources. See FAR § 6.302-3;
see also Lance Ordnance Co. Inc.; Martin Elecs., Inc., B-246849,
B-246952, Mar. 31, 1992, 92-2 CPD ¶ 29 at 3-4. (Coulson
Aviation (USA) Inc.; 10 Tanker Air Carrier, LLC; Minden Air
Corp., B-409356.2, B-409356.3, B-409356.4, B-409356.5,
B-409356.6: Mar 31, 2014)
Among the reasons identified by the Navy for its decision to
issue a sole-source contract to DIT-MCO is the fact that its
existing AWAs (which are manufactured by DIT-MCO) use software
that is proprietary to DIT-MCO. The agency’s J&A explains that
the upgraded AWA, if purchased from DIT-MCO, will maintain
commonality and compatibility with the agency’s other AWAs.
Additionally, the agency’s J&A explains that the aircraft’s
original equipment manufacturer (OEM), Northrup Grumman
Corporation, uses a DIT-MCO proprietary software known as test
assistance II (TA2) software for purposes of generating test
programs. The agency’s J&A explains that procuring a DIT-MCO AWA
allows the agency to standardize design information exchange
between the agency’s engineers and the OEM, and also allows the
agency to use the OEM’s existing data and test programs; the
upgraded AWA will be able to utilize all legacy test programs
previously written for the agency. AR, exh. 1, Agency J&A, at
2-3.
The Navy’s J&A also notes that the agency has developed a host
of customized applications and utilities that were developed
around the unique hardware and software architecture of the
DIT-MCO AWA, and that these customized tools will not be
compatible with another manufacturer’s AWA. The agency estimate
of the cost of duplicating these customized tools was an added
consideration in deciding to procure an AWA upgrade on a
sole-source basis from DIT-MCO. AR, exh. 1, Agency J&A, at 2.
The Navy’s J&A goes on to explain that, in order for other
manufacturers to be able to provide an AWA that is interoperable
with the agency’s existing hardware and software, it would be
necessary for them to develop software patches and use
additional hardware in order to communicate with the aircraft’s
software. In that connection, the agency’s J&A specifically
notes that the agency previously had awarded Eclypse a contract
for an AWA, but that the AWA that was provided was not
compatible with the agency’s existing AWAs software. AR, exh. 1,
Agency J&A, at 3.
Eclypse asserts that it has a software conversion tool that will
allow it to easily make its AWA compatible with the agency’s
existing systems. However, in response to Eclypse’s allegation,
the agency’s engineer explains that the Navy based its decision
to procure the AWA on a sole-source basis from DIT-MCO, in part,
because of personal knowledge of problems associated with the
Eclypse software’s compatibility that arose under the earlier
contract awarded to Eclypse.[2] AR exh. 7, Declaration of the
Agency’s Engineer, at 3. The agency’s engineer goes on to
explain that Eclypse’s software conversion tool is only
semi-automatic and requires manual intervention for any software
conversion or development effort, such that it requires manual
input of much of the necessary data, and that this process would
have to be performed by agency personnel. Id. at 4-5.
We conclude that the Navy’s concerns associated with software
compatibility and commonality among its AWAs provide a
reasonable basis for its decision to award the contract on a
sole-source basis. We also conclude that the agency’s concern
with maintaining that compatibility and commonality with the
aircraft’s OEM provides further support for the agency’s
decision. While Eclypse disagrees with the agency’s position,
and contends that it has what it characterizes as a
straightforward conversion solution, the record supports the
agency’s reservations with Eclypse’s conversion approach based
on its actual experience. In addition, the record shows that the
agency also would have to expend significant funds in order to
recreate the custom tools it has developed in-house that
function with the DIT-MCO AWA; Eclypse has not rebutted this
conclusion on the part of the agency. (Eclypse
International Corporation B-408795, Nov 25, 2013) (pdf)
The protester argues that when the Air Force transferred the
operation of mission essential food services at Barksdale AFB
and Dyess AFB to the [Air Force Mission Essential Feeding Fund]
AFMEFF, it was required to do so through a competitive
procurement process under CICA, and, having failed to obtain
competition, the Air Force’s transfer of this requirement to the
[Nonappropriated Fund Instrumentality] NAFI essentially
constituted an improper sole-source award in violation of CICA.
The Air Force maintains that it has special authority under 10
U.S.C. § 2492 (2006) to obtain the services in question from the
AFMEFF through a MOA, and that, as a consequence, CICA was
inapplicable. As explained below, we conclude that section 2492
does not provide authority for the Air Force to transfer the
provision of mission essential food services to a NAFI. By its
terms, section 2492 limits such agreements to those in support
of morale, welfare, and recreation (MWR). Because mission
essential food services--supported entirely with appropriated
funds--are not within the [Morale, Welfare, and Recreation] MWR
system, the transfer of such requirements to AFMEFF without
obtaining competition, or justifying an award to the NAFI on a
sole-source basis, was in contravention of CICA and FAR.
The statutory provision upon which the Air Force relies, 10
U.S.C. § 2492, provides as follows:
An agency or instrumentality of the
Department of Defense that supports the operation of the
exchange system, or the operation of a morale, welfare, and
recreation system, of the Department of Defense may enter into
a contract or other agreement with another element of the
Department of Defense or with another Federal department,
agency, or instrumentality to provide or obtain goods and
services beneficial to the efficient management and operation
of the exchange system or that morale, welfare, and recreation
system.
As an initial matter, we note that Air
Force does not appear to take the position that the mission
essential food services, which are at issue in this case, fall
within the ambit of the MWR system. We specifically asked the
Air Force to address this point and, instead, it provided a
rather lengthy discussion of how the FTI program operates, and
the advantages and efficiencies to be achieved through the
consolidation of these programs. We take the Air Force’s
non-answer in this regard to be an implicit recognition that
such requirements do not fall within the MWR system. In any
event, to the extent the Air Force’s own characterization of the
requirements as “mission essential” does not settle the point,
the conclusion that these services do not fall within the MWR
system is inescapable, where they are paid for entirely with
appropriated funds, there is no indication that they have ever
previously been considered to fall within the MWR system, and
they do not fit within any reasonable understanding of the DoD’s
definition of Class C MWR food services activities.
Since mission essential food services do not fall within the MWR
system, it appears that the Air Force has taken the position
that section 2492 gives it the authority to consolidate
management and accounting for its mission essential and
non-mission essential MWR food serving operations so long as
consolidation will benefit the efficient management and
operation of its MWR food operations. See Agency Response to GAO
Questions, July 18, 2012, at 2. Thus, the agency’s argument, as
we understand it, is that section 2492 authorizes the AFMEF, a
NAFI, to provide mission essential feeding services to the Air
Force because it is of benefit to the MWR system for the Air
Force to acquire both operation of essential food service
facilities and operation of non-essential food services
facilities (such as officers’ clubs) from the same contractor.
We do not find this to be a reasonable reading of the statute.
While section 2492 authorizes a NAFI such as the AFMEFF to enter
into an agreement with the Air Force to provide services
beneficial to the efficient management and operation of the MWR
system, there is nothing to suggest that it authorizes an
agreement between the NAFI and the Air Force for the provision
of mission essential services on the theory that consolidating
such activities under the MWR system may provide a benefit the
MWR system. Such an application would constitute a radical
departure from the general understanding that DoD NAFIs are
established to engage in MWR related activities. See DoD
Instruction 1015.15, supra (stating that “NAFIs shall be
established for military morale, welfare, and recreation (MWR)
programs”). We also find the Air Force’s interpretation
particularly strained in this instance where, by all reasonable
measures, the value of the mission essential services to be
provided by the NAFI under its agreement with the Air Force
substantially exceeds the value of any non-mission essential
food (i.e., MWR-related) services, which are the traditional
bailiwick of NAFIs and to which section 2492 is expressly
directed. See, e.g., AR, Tab 26, RFQ F41999-10-Q-0495, Portfolio
I, FTI Schedule of Services (reflecting that historical usage
associated with mission essential food services at airbases has
been much greater than MWR, NAFI operated food activities).
Without authority under section 2492, the only way that the Air
Force could have properly transferred appropriated funds to the
NAFI for the provision of mission essential food services would
have been through a competitive procurement process. In this
regard, although NAFIs are considered to be instrumentalities of
the United States government, obtaining services from a NAFI is
“tantamount to obtaining services from nongovernment commercial
sources”; therefore, NAFIs are required to compete to provide
goods or services to agencies through the usual procurement
process mandated by CICA, and implemented in the FAR. See
University Research Corp., B-228895, Dec. 29, 1987, 87-2 CPD ¶
636 at 5-6.
Thus, before restricting competition for the mission essential
food services to a single source (i.e., the AFMEFF), the Air
Force was required to comply with statutory requirements
pertaining to competition, including preparing a Justification &
Approval (J&A) for the use of other than competitive procedures
and publishing notice of its intention to use other than
competitive procedures on the FedBizOpps website. 10 U.S.C. §
2304(f)(1); FAR Subpart 6.3. Because the Air Force failed to
comply with these mandates, we sustain Asiel’s protest. (Asiel
Enterprises, Inc., B-406780, B-406836, Aug 28, 2012) (pdf)
Sikorsky argues that this RFP improperly
restricts competition because the D&F does not set forth an
adequate basis for specifying the Mi-17 helicopter. The
protester primarily argues that the statements set forth in the
D&F regarding the required effort and associated delay
associated with transitioning the Afghanistan Air Force from the
Mi-17 helicopter to a different helicopter platform are not
reasonable, and also argues that it can offer a variant of the
Sikorsky S-61 helicopter that can meet the same altitude
performance requirements as the Mi-17.
As indicated above, the FAR requires the public interest
exception be justified by a D&F that "set[s] forth enough facts
and circumstances to clearly and convincingly justify the
specific determination made." FAR sect. 1.704. Our review of an
agency's invocation of the public interest exception is based on
this regulatory requirement implementing CICA's public interest
exception. In this regard, we note that the Court of Federal
Claims has reviewed the invocation of the public interest
exception on this basis. See Spherix v. United States, 58 Fed.
Cl. 514, 515 (2003); Spherix v. United States, 58 Fed. Cl. 351,
358 (2003). Our review of a D&F issued by an agency in support
of the public interest exception to full and open competition
addresses whether the D&F provides, on its face, a clear and
convincing justification that the restricted competition
furthers the public interest identified. We will consider a
protester's arguments that the D&F relies on facts that have no
relation to the stated public interest, or that the D&F relies
on materially inaccurate information. We will not, however,
sustain a protest based on the protester's mere disagreement
with the conclusions set forth in the D&F. See Raytheon
Co.–Integrated Def. Sys., B-400610 et al., Dec. 22, 2008, 2009
CPD para. 8 at 6.
Here, Sikorsky does not challenge the D&F's identification of
the public interest furthered by the limited competition, i.e.,
the requirement to support the development of the Afghanistan
Air Force and its need for a multipurpose helicopter. AR, Tab
21, D&F, at 1-2. Instead, the protester argues that the facts
set forth in the D&F do not support the Acting Secretary of the
Navy's conclusion that limiting the competition to the Mi-17 is
necessary to meet the identified public interest. Specifically,
the protester argues that the facts set forth in the D&F
concerning the training requirements associated with providing
other than Mi-17 helicopters, and the performance requirements
of the Mi-17 with regard to altitude do not support the D&F. For
the reasons discussed below, we conclude that Sikorsky does not
demonstrate that the D&F was defective.
The Afghanistan Air Force's Familiarity
with the Mi-17 Helicopter
(Sections deleted)
Altitude Performance
Requirements
(Sections deleted)
Buy American Act and
Balance of Payments Program
(Sections deleted)
(Sikorsky
Aircraft Corporation, B-403471; B-403471.3, November 5,
2010) (pdf)
If noncompetitive
procedures are used pursuant to 10 U.S.C. sect. 2304(c)(2), such
as here, the agency is required to execute a written J&A with
sufficient facts and rationale to support the use of the
specific authority. See 10 U.S.C. sect. 2304(f)(1)(A), (B); FAR
sections 6.302-1(d)(1), 6.302-2(c)(1), 6.303, 6.304. Our review
of the agency's decision to conduct a noncompetitive procurement
focuses on the adequacy of the rationale and conclusions set
forth in the J&A. Signals & Sys, Inc., B-288107, Sept. 21, 2001,
2001 CPD para. 168 at 9. However, noncompetitive procedures may
not properly be used where the agency created the urgent need
through a lack of advanced planning. 10 U.S.C. sect.
2304(f)(5)(A); Worldwide Language Resources, Inc.; SOS Int'l
Ltd., B-296984 et al., Nov. 14, 2005, 2005 CPD para. 206 at 12.
In addition, the urgency justification cannot support the
procurement of more than the minimum quantity needed to satisfy
the immediate urgent requirement. See Immunalysis/Diagnostixx of
Calif. Corp., B‑254386, Dec. 8, 1993, 93-2 CPD para. 309 at 5.
Military mission readiness and personal safety are important
considerations in judging the reasonableness of an agency's
determination that unusual and compelling urgency prevents the
agency from conducting a procurement on the basis of full and
open competition, as provided for by CICA. See McGregor Mfg.
Corp., B-285341, Aug. 18, 2000, 2000 CPD para. 151 at 7; Logics,
Inc., B‑256171, May 19, 1994, 94-1 CPD para. 314 at 2. It is
beyond cavil that an agency need not risk injury to personnel or
property in order to conduct a competitive acquisition. Signals
& Sys, Inc., supra, at 10.
Here, from our review of the agency's J&A and the record, we
find reasonable the agency's determination that only SRCTec
could meet the agency's urgent requirements within the time
required. The record specifically supports the Army's arguments
that it has a continuing and urgent need to address the use of
more sophisticated IEDs on other frequency bands to protect its
personnel and property. See Improvised Explosive Devices (IEDS)
in Iraq and Afghanistan: Effects and Countermeasures, CRS Report
for Congress, supra, at 1; Declaration of CREW Product Manager,
Jan. 8, 2009, at 1. In this regard, SRCTec's contract here and
the Navy's Spiral 3.2 contract reflect the need to continually
evolve and upgrade CREW systems to counter the threat of
radio-controlled IEDs in other frequencies. Moreover, as the GAO
attorney noted to the parties in the ADR conference in Pegasus's
earlier protest, upgrading SRCTec's Duke ECM system was within
the scope of SRCTec's contract, but for the fact that the
upgrade was accomplished by a contract modification that
exceeded the contract's maximum ceiling value.
Pegasus argues, however, that the lack of competition to satisfy
these requirements was caused by the agency's lack of advance
procurement planning. Pegasus advances a variety of arguments in
support of this assertion, including that the Army improperly
modified SRCTec's contract to obtain the upgraded systems rather
than seeking to test other firms' products, such as Pegasus's
Jukebox Alpha and Jukebox Alpha Upgrade systems. In this regard,
Pegasus continues to complain that SRCTec had an unfair "headstart"
because of the agency's earlier modification of that firm's
contract to obtain SRCTec's upgraded system.
Although, as we note above, an agency may not justify a
noncompetitive award on the basis of urgency where the agency's
urgent requirements are the result of a lack of advance
planning, see 10 U.S.C. sect. 2304(f)(4)(A), such planning need
not be entirely error-free or successful. See Sprint Commc'ns
Co., L.P., B-262003.2, Jan. 25, 1996, 96-1 CPD sect. 24 at 8-9.
Here, the record shows that the Army's procurement planning was
not error-free, given the agency's improper modification of
SRCTec's contract that exceeded the maximum contract value.
Nevertheless, we do not find unreasonable, as explained below,
the agency's conclusion that only SRCTec could satisfy the
agency's urgent requirement, nor do we find that Pegasus has
shown that it could have satisfied the agency's requirements,
even if the agency had conducted error-free advance planning,
given the agency's estimate of the time that would be required
for Pegasus to develop a device that would meets the agency's
requirements.
As a result of market research and testing of Pegasus's device
in December 2008, the Army found that Pegasus did not have a
device that would satisfy the agency's technical requirements.
In fact, the Army found that Pegasus's Jukebox Alpha Upgrade
device could not counter most of the threat bands that the Army
required and that Pegasus's device otherwise failed to satisfy
[deleted]. The agency concluded, given the time that would be
required to develop a system to satisfy these requirements and
the time needed to test an upgraded device, that the earliest
that Pegasus could field a system meeting the agency's current
requirements would be February 2010. In this regard, Pegasus has
not shown, even 3 months after the agency's testing of the
firm's device, that Pegasus has a product that would satisfy the
agency's current urgent requirements.
Pegasus disagrees with the Army's assessment of how long it
would take for Pegasus to develop a system, and states that
within 6 months it could meet the agency's needs. See 2nd
Declaration of Pegasus's Chief Operating Officer, at 2. Pegasus,
however, has offered no testing data, or any other evidence, to
support these assertions, and the chief operating officer's
declaration is at best an admission that the firm needs
additional time to provide these items. Pegasus's disagreement
does not show that the agency's technical judgment was
unreasonable. See Foster-Miller, Inc., B-296194.4, B-296194.5,
Aug. 31, 2005, 2005 CPD para. 171 at 9. Moreover, the
protester's admission that it would need 6 months to develop a
device that would meet the agency's needs establishes that
Pegasus cannot satisfy the agency's urgent requirements. Under
these circumstances, we find reasonable the agency's urgency J&A
supporting the modification of SRCTec's contract, and thus there
is no basis to sustain the protest. (Pegasus
Global Strategic Solutions, LLC, B-400422.3, March 24, 2009)
(pdf)
Although
the overriding mandate of the Competition in Contracting Act of
1984 (CICA), 10 U.S.C. sect. 2304(a)(1)(A) (2000), is for full
and open competition in government procurements, obtained
through the use of competitive procedures, it permits
noncompetitive acquisitions in certain circumstances. 10 U.S.C.
sect. 2304(c). The agency’s J&A cites one of the exceptions to
the mandate that competitive procedures be used, namely, that
there is only one responsible source and no other supplies or
services will satisfy the agency’s requirements. J&A, citing 10
U.S.C. sect. 2304(c)(1). The J&A must contain sufficient facts
and rationale to support the use of the chosen exception. See 10
U.S.C. sect. 2304(f)(1)(A), (B); Federal Acquisition Regulation
(FAR) sections 6.302-1(d)(1), 6.303, 6.304; Marconi Dynamics,
Inc., B-252318, June 21, 1993, 93-1 CPD para. 475 at 5. Our
review of the agency’s decision to conduct a sole-source
procurement focuses on the adequacy of the rationale and
conclusions set forth in the J&A. When the J&A sets forth a
reasonable justification for the agency’s actions, we will not
object to the award. Global Solutions Network, Inc., B‑290107,
June 11, 2002, 2002 CPD para. 98 at 6; Diversified Tech. and
Servs. of Virginia, Inc., B‑282497, July 19, 1999, 99-2 CPD para.
16 at 3.
We conclude that the rationale advanced by the agency in the
J&A--in essence, the critical benefits from weapon
standardization--is sufficient to support the decision to
procure the Glock pistol on a sole-source basis. Specifically,
the agency asserts that prior wide use of the Glock pistol by
the fighting forces mentioned above has created “a baseline of
standardization of operations and support that is critical to be
continued.” J&A at 1. Procuring more of the same pistol would
lessen the logistical burden on the Pakistan Army, the agency
states, in part by reducing the effort required for spare parts
administration; retraining the various forces also would be
unnecessary if the same pistol were procured.
In its challenge to the agency’s rationale, the protester points
out that the J&A does not support a conclusion that the
Pakistanis cannot effectively defend themselves if they procure
a pistol other than the Glock that they use now. The protester
also maintains that the disassembly and cleaning of the Glock
and the proposed Smith & Wesson firearms are identical; that,
given its worldwide popularity, there is no shortage of spare
parts for the protester’s pistol; and that personnel are
typically trained to service and repair or replace the parts for
many different types of semi-automatic weapons. The protester
also asserts that the difference between the trigger pulls of
the two weapons--the protester’s pistol has a heavier trigger
pull and a longer trigger travel--are at best minor distinctions
that would have no impact on the war fighting capabilities of
the Pakistani forces.
As an initial matter, to the extent that the protester argues
that the J&A is inadequate because it does not show that the
Glock pistol is indispensable to the forces who would use it,
its argument is based on a flawed premise. As discussed above,
the standard is not whether the item being procured is
indispensable, or even whether the Glock performs better than
the selected pistol, but whether the agency has offered
sufficient facts and rationale to support the decision to
procure it on a sole- source basis. The protester’s claim that
many organizations with armed personnel train them on several
different firearms is unpersuasive; what is at issue here is the
level of training received by the Pakistani fighting forces and
not, as in one example offered by the protester, the training
regimen of metropolitan cities in this country. There is nothing
in the record to suggest that the forces that would be supplied
with a different pistol than the current Glock would easily
adapt to a change in firearms.
It is undisputed that the parties using these weapons do so
under extremely hazardous and unstable conditions. Under these
circumstances, we conclude that the benefits to the fighting
forces cited in the J&A from procuring the same pistol currently
in use, such as avoiding the need for retraining on a different
model or the need to stockpile spare parts for different models,
are sufficient to support the agency’s decision to procure the
pistols on a sole-source basis. (Smith
& Wesson, Inc., B-400479, November 20, 2008) (pdf)
Turning to the July 2005 sole-source award to OSS for
expansion of the BBA-SME requirement, we find that the agency’s
J&A in support of the sole-source award to OSS was flawed
because it was premised on the unsupported conclusion that OSS
was the only contractor capable of meeting the BBA-SME
requirement in a timely and cost-effective manner. We therefore
sustain the protesters’ challenge to this second sole-source
award as well. The July 2005 J&A, which nominally cited “unusual
and compelling urgency” as the justification for the sole-source
award to OSS, was in fact prepared based on the exception to
full and open competition set forth in 10 U.S.C. sect.
2304(c)(1), which applies when the agency concludes that
required services are only available from one responsible
source. Specifically, the contracting officer testified with
regard to the July J&A as follows: “I wrote this J&A, believing
that I was going to use one responsible source. . . . I think
the situation in Iraq is urgent, but it was written for [‘only]
one responsible source’.” Tr. at 277. Moreover, the reasoning
set forth in the J&A is consistent with the “only one
responsible source” exception. The J&A expressly asserts that
OSS is “the only provider [deleted]. They are the only provider
that can perform the contract without significant additional
start-up costs and recruitment delays.” AR, Tab 1.b.1., J&A at
para. 5. (WorldWide Language
Resources, Inc.; SOS International Ltd., B-296984;
B-296984.2; B-296984.3; B-296984.4; B-296993; B-296993.2;
November 14, 2005) (pdf)
Turning to the propriety of the sole-source bridge
contract with EG&G, we first find that the sole-source award was
improper because it is not supported by a written J&A. In this
regard, when an agency uses noncompetitive procedures, such as
41 U.S.C. 253(c)(1) (2000), which authorizes the use of
noncompetitive procedures when the property or services are
available from only one responsible source, the contracting
officer is required to execute a written justification with
sufficient facts and rationale to support the use of the
authority, certify its accuracy and completeness, and obtain
approval of the action from the cognizant agency official prior
to making an award. See 41 U.S.C. 253(f)(1)(A), (B), (C);
Federal Acquisition Regulation (FAR) 6.303, 6.304. The only
exception to this requirement is where the agency uses
noncompetitive procedures because the agency's need for the
property or services is of such an unusual and compelling
urgency that the government would be seriously injured unless
the agency is permitted to limit the number of sources from
which it solicits bids or proposals. See 41 U.S.C. 253(c)(2),
(f)(2). Here, the agency did not execute a J&A prior to awarding
the letter contract, as required by the statute. While a draft
J&A has been provided during the course of our consideration of
this protest, the agency advises that this document is only the
agency's "deliberative processes" until a final document is
issued. See Agency Letter, Apr. 1, 2003, at 1. In fact, despite
our requests, the agency still has not provided an executed and
approved J&A. Thus, the agency's letter contract award to EG&G
constitutes an improper sole-source award. See Saltwater,
Inc.--Recon. and Costs , B-294121.3, B-294121.4, Feb. 8, 2005,
2005 CPD 33 at 3. (VSE Corporation;
Johnson Controls World Services, Inc., B-290452.3;
B-290452.4; B-290452.5, May 23, 2005) (pdf)
When an agency uses noncompetitive procedures under 10 U.S.C. §
2304(c)(1), it is required to execute a written J&A with
sufficient facts and rationale to support the use of the cited
authority, and publish a notice to permit potential competitors
an opportunity to challenge the agency’s decision to procure
without full and open competition. See 10 U.S.C. §
2304(f)(1)(A), (B); Federal Acquisition Regulation §§
6.302-1(d)(1), 6.303, 6.304; Marconi Dynamics, Inc., B-252318,
June 21, 1993, 93‑1 CPD ¶ 475 at 5. Our review of the agency’s
decision to conduct a sole-source procurement focuses on the
adequacy of the rationale and conclusions set forth in the J&A.
When the J&A sets forth a reasonable justification for the
agency’s actions, we will not object to the award. Global
Solutions Network, Inc., B-290107, June 11, 2002, 2002 CPD ¶ 98
at 6; Diversified Tech. and Servs. Of Virginia, Inc., B‑292497,
July 19, 1999, 99-2 CPD ¶ 16 at 3. Here, based on our review of
the record, we find no basis to question SSP’s overall
determination that only Draper could satisfy the agency’s need
for the establishment and certification of an ISF for the MK 6
guidance system. As documented in its J&A justifying award to
Draper, SSP determined that only Draper could establish and
certify the ISF SSP because, while individual ISCs were familiar
with their particular individual subsystems, only Draper, as the
design and development agent for the MK 6 guidance system, as
well as for the fleet ballistic missile guidance systems
generally, had (1) “comprehensive knowledge” of “all critical
elements unique to the guidance system’s performance,” and (2)
“comprehensive knowledge” of “the interrelationships of these
elements with the entire Trident II weapon system.” J&A at 2.
SSP concluded that Draper’s “overall systems engineering
knowledge and technical expertise in the MK 6 guidance system is
unmatched as a result of over forty years as sole design and
development agent on the [fleet ballistic missile] guidance
systems.” Id. We conclude that SSP reasonably determined that
Draper’s overall knowledge of all of the critical components of
the MK 6 guidance system, including the IMU, electronic
assembly/IMUEs, and 10-PIGA, was essential in view of the broad
scope of the requirement to establish and certify the ISF. (Kearfott
Guidance & Navigation Corporation, B-292895.2, May 25, 2004)
(pdf)
As explained below, the J&A and
its supporting documentation, as well as the agency's
submissions prepared in response to this protest and the
testimony of the agency representatives at the hearing held at
our Office in connection with this protest, contain so many
inconsistencies and inaccuracies that they cannot reasonably
justify the agency's intended award of a sole-source contract to
Rolls-Royce. Specifically, the J&A inaccurately describes
the overhaul services to be acquired, the dollar value of the
services to be acquired, and the length of time for which the
services will be needed. Additionally, the record does not
support the J&A's statement that only Rolls-Royce is capable
of providing either the engineering or overhaul services, and
similarly, fails to support the agency's position, as reflected
in the J&A and argued by the agency during this protest,
that the engineering and overhaul services must be performed by
the same contractor (Rolls-Royce). (Sabreliner
Corporation, B-288030; B-288030.2, September 13, 2001)
Agency's justification for
sole-source procurement is inadequate where the documentation
does not reasonably show that only this exact product will
satisfy the agency's needs, and does not show that the agency's
need for the item is of unusual and compelling urgency that was
not created by a lack of advance planning. (National
Aerospace Group, Inc., B-282843, August 30, 1999) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
Raytheon Company and Kongsberg Defence
& Aerospace AS, B-409615, B-409615.2: Jun 24, 2014 (pdf) |
Coulson Aviation (USA) Inc.; 10
Tanker Air Carrier, LLC; Minden Air Corp., B-409356.2,
B-409356.3, B-409356.4, B-409356.5, B-409356.6: Mar 31, 2014 |
Eclypse International Corporation
B-408795, Nov 25, 2013 (pdf) |
Asiel Enterprises, Inc., B-406780,
B-406836, Aug 28, 2012 (pdf) |
Sikorsky Aircraft
Corporation, B-403471; B-403471.3, November 5, 2010 (pdf) |
WorldWide Language Resources,
Inc.; SOS International Ltd., B-296984; B-296984.2;
B-296984.3; B-296984.4; B-296993; B-296993.2; November 14, 2005
(pdf) |
Pegasus Global Strategic Solutions,
LLC, B-400422.3, March 24, 2009 (pdf) |
VSE Corporation; Johnson
Controls World Services, Inc., B-290452.3; B-290452.4;
B-290452.5, May 23, 2005 (pdf) |
Smith & Wesson, Inc., B-400479,
November 20, 2008 (pdf) |
Sabreliner Corporation, B-288030; B-288030.2, September 13,
2001
|
Kearfott Guidance & Navigation
Corporation, B-292895.2, May 25, 2004 (pdf) |
National Aerospace Group, Inc., B-282843, August 30, 1999 |
EADS North America, Inc., B-291805, March 26, 2003 (txt
version) |
|
MFVega & Associates, LLC, B-291605.3, March 25, 2003 (pdf)
(txt
version) |
|
U.
S. Court of Federal Claims - Key Excerpts |
C. Relevant Statutes and Regulations
Because two of plaintiff’s claims for relief concern whether DHS and its components
have, and are, complying with the statutes and regulations related to the use of noncompetitive
acquisition procedures, a brief summary of the pertinent statutes and regulations is required.
1. The Competition in Contracting Act of 1984
Under the Competition in Contracting Act of 1984, when a federal executive agency
conducts a procurement for property or services, it normally must “obtain full and open
competition through the use of competitive procedures in accordance with” the pertinent statutes
and the FAR. 41 U.S.C. § 3301(a)(1) (2012); accord FAR 6.101 (2014). However, an executive
agency may use noncompetitive procedures in certain specified circumstances, see 41 U.S.C.
§ 3304(a); FAR 6.301(a); FAR 6.302, or when they are “expressly authorized by statute,” 41
U.S.C. § 3301(a); accord id. § 3304(a)(5); FAR 6.302-5.
If an executive agency plans to use noncompetitive procedures, it may not do so until (1)
“the contracting officer for the contract justifies the use of those procedures in writing and
certifies the accuracy and completeness of the justification”; (2) if the amount of the contract
exceeds $500,000, the appropriate agency official approves the justification; and (3) any required
notice is published. 41 U.S.C. § 3304(e)(1); accord FAR 6.303-1; FAR 6.304. Moreover, “[i]n
no case may an executive agency . . . procure property or services from another executive agency
unless the other executive agency complies with [the pertinent statutes] in its procurement of the
property or services.” 41 U.S.C. § 3304(e)(5)(A).
The justification required to use noncompetitive procedures must include the following
information:
(1) Identification of the agency and the contracting activity, and specific
identification of the document as a “Justification for other than full and open
competition.”
(2) Nature and/or description of the action being approved.
(3) A description of the supplies or services required to meet the agency’s needs
(including the estimated value).
(4) An identification of the statutory authority permitting other than full and open
competition.
(5) A demonstration that the proposed contractor’s unique qualifications or the
nature of the acquisition requires use of the authority cited.
(6) A description of efforts made to
ensure that offers are solicited from as many potential
sources as is practicable . . . .
(7) A determination by the
contracting officer that the anticipated cost to the
Government will be fair and reasonable.
(8) A description of the market
research conducted . . . and the results or a statement of
the reason market research was not conducted.
(9) Any other facts supporting the
use of other than full and open competition . . . . . . .
.
(10) A listing of the sources, if
any, that expressed, in writing, an interest in the
acquisition.
(11) A statement of the actions, if
any, the agency may take to remove or overcome any
barriers to competition before any subsequent acquisition
for the supplies or services required.
(12) Contracting officer
certification that the justification is accurate and
complete to the best of the contracting officer’s
knowledge and belief.
FAR 6.303-2(b); accord 41 U.S.C. § 3304(e)(2). The executive agency must, in most cases,
make the justification publicly available within fourteen days of contract award. 41 U.S.C.
§ 3304(f)(1); FAR 6.305.
2. The Economy Act
As previously noted, executive agencies can avoid obtaining full and open competition if
an alternative procurement procedure is set forth in another statute. See 41 U.S.C.
§ 3301(a). One such statute is the Economy Act, which
provides that an agency “may place an order with a major
organizational unit within the same agency or another
agency for goods or services if”:
(1) amounts are available;
(2) the head of the ordering agency
or unit decides that the order is in the best interest of
the United States Government;
(3) the agency or unit to fill the
order is able to provide or get by contract the ordered
goods or services; and
(4) the head of the agency decides ordered goods or services cannot be provided
by contract as conveniently or cheaply by a commercial enterprise.
31 U.S.C. § 1535(a) (2012). The FAR applies to Economy Act agreements “when one agency
uses another agency’s contract to obtain supplies or services,” but not when “the interagency
transaction does not result in a contract or an order . . . .” FAR 17.502-2(a); accord FAR 17.500
(noting that FAR subpart 17.5 applies to interagency acquisitions and not to “[i]nteragency
reimbursable work performed by Federal employees (other than acquisition assistance) or
interagency activities where contracting is incidental to the purpose of the transaction”). If the
FAR applies, an agency planning to order goods or services from another agency must first
determine that “an interagency acquisition represents the best procurement approach.” FAR
17.502-1(a)(1). That determination must include “an analysis of procurement approaches” and
“an evaluation . . . that using the acquisition services of another agency (i) [s]atisfies the
requesting agency’s schedule, performance, and delivery requirements, (ii) [i]s cost effective, and
(iii) [w]ill result in the use of funds in accordance with appropriation
limitations and compliance with the requesting agency’s
laws and policies.” Id.
In addition, the requesting agency
must support its order with a D&F.11 FAR 17.502- 2(c)(1).
The D&F must contain statements affirming that the
acquisition is in the government’s best interest and that
a commercial acquisition would be less convenient and more
expensive. Id. It must also contain a statement that one
of the following three circumstances applies to the
acquisition:
(A) The acquisition will
appropriately be made under an existing contract of the
servicing agency, entered into before placement of the
order, to meet the requirements of the servicing agency
for the same or similar supplies or services.
(B) The servicing agency has the
capability or expertise to enter into a contract for such
supplies or services that is not available within the
requesting agency.
(C) The servicing agency is
specifically authorized by law or regulation to purchase
such supplies or services on behalf of other agencies.
Id. The D&F must be approved by a contracting officer from the requesting agency, and it must
be provided to the servicing agency with the order. FAR 17.502-2(c)(2) to (3).
If the interagency acquisition requires the servicing agency to award a contract, the
servicing agency is responsible for complying with the FAR’s competition requirements,
including those for full and open competition and those for other than full and open competition.
FAR 17.503(d)(3). Finally, prior to the servicing agency acquiring the goods or services for the
requesting agency, the two agencies must “sign a written interagency agreement that establishes
the general terms and conditions governing the relationship between the parties, including roles
and responsibilities for acquisition planning, contract execution, and administration and
management of the contract(s) or order(s).” FAR 17.502-1(b)(1)(i).
3. The Government Management
Reform Act of 1994
Executive agencies may also avoid obtaining full and open competition if they proceed
with the procurement under section 403 of the Government Management Reform Act of 1994.
See Pub. L. No. 103-356, 108 Stat. 3410, 3413 (codified as amended at 31 U.S.C. § 501 note).
That statute authorizes the establishment of franchise funds at six executive agencies. Id.
§ 403(a). With respect to such funds, the statute provides:
Each such fund may provide,
consistent with guidelines established by the Director of
[OMB], such common administrative support services to the
agency and to other agencies as the head of such agency,
with the concurrence of the Director, determines can be
provided more efficiently through such a fund than by
other means. To provide such services, each such fund is
authorized to acquire the capital equipment, automated
data processing systems, and financial management and
management information systems needed. Services shall be
provided by such funds on a competitive basis.
Id. § 403(b). Further, “nothing in
[section 403(b) is to] be construed as relieving any
agency of any duty under applicable procurement laws.” Id.
§ 403(e).
One of the franchise funds authorized
by the Government Management Reform Act of 1994 was
established for the use of the United States Department of
the Interior. See Pub. L. No. 104-208, 110 Stat. 3009,
3009-200 to 3009-201 (1997) (codified as amended at 31
U.S.C. § 501 note). The fund is “to be available . . . for
costs of capitalizing and operating administrative
services as the Secretary determines may be performed more
advantageously as centralized services[,]” and is to
“provide services on a competitive basis[.]” Id.
(sections deleted)
The only substantive issue remaining for the court s resolution is whether the
Coast Guard, [Transportation Security Administration] TSA, and [Domestic Nuclear
Detection Office] DNDO violated the Competition in Contracting Act of 1984, the
regulations implementing the Competition in Contracting Act of 1984, or the regulations
implementing the Economy Act when they decided to forgo competition and acquire
financial
management software systems and related services on a sole-source basis from the
Interior
Business Center. The court addresses this issue in the context of the parties
cross-motions for
judgment on the administrative record.
III. THE PARTIES CROSS-MOTIONS FOR JUDGMENT ON THE
ADMINISTRATIVE RECORD
Both parties have moved for judgment on the administrative record pursuant to Rule
52.1(c) of the Rules of the United States Court of Federal Claims ( RCFC ). In
ruling on such
motions, the court asks whether, given all the disputed and undisputed facts, a
party has met its
burden of proof based on the evidence in the record. A & D Fire Prot., Inc. v.
United States, 72
Fed. Cl. 126, 131 (2006) (citing Bannum, Inc., 404 F.3d at 1356). Because the court
makes
factual findings . . . from the record evidence, judgment on the administrative
record is
properly understood as intending to provide for an expedited trial on the
administrative record.
Bannum, 404 F.3d at 1356.
A. Standard of Review
When entertaining a motion for judgment on the administrative record in a bid protest,
the Court of Federal Claims reviews the challenged agency action pursuant to the
standards set
forth in 5 U.S.C. § 706. 28 U.S.C. § 1491(b)(4). Although section 706 contains several
standards, the proper standard to be applied in bid protest cases is provided by 5
U.S.C.
§ 706(2)(A): a reviewing court shall set aside the agency action if it is
arbitrary, capricious, an
abuse of discretion, or otherwise not in accordance with law. Banknote Corp. of
Am., 365 F.3d
at 1350.
In this bid protest, the only question before the court is whether the procuring
agencies
acted in accordance [to] law. The court may set aside a procurement action if . . .
the procurement
procedure involved a violation of regulation or procedure. Centech Grp., Inc. v.
United States,
554 F.3d 1029, 1037 (Fed. Cir. 2009) (quoting Impresa Construzioni Geom. Domenico
Garufi v.
United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)). Because procurement officials
are entitled to exercise discretion upon a broad range of issues confronting them
in the procurement
process, Impresa, 238 F.3d at 1332 (internal quotation marks omitted), when a
protestor claims
that the procuring agency's decision violates a statute, regulation, or procedure,
it must show that
the violation was clear and prejudicial, id. at 1333 (internal quotation marks
omitted).
B. The Competition in Contracting Act of 1984 and Its Implementing Regulations
Plaintiff first argues that the Coast Guard, TSA, and DNDO violated the Competition in
Contracting Act of 1984 and its implementing regulations when they decided to forgo
competition and acquire financial management software systems and related services
on a sole source
basis from the Interior Business Center. Specifically, plaintiff contends that the
Coast
Guard, TSA, and DNDO did not fulfill the requirements of 41 U.S.C. § 3304(e)(1) and FAR
6.303 to justify, in writing, the use of other than full and open competition.
Although executive agencies are normally required to obtain property and services
through full and open competition, they may use noncompetitive procedures in certain
circumstances. 41 U.S.C. §§ 3301(a), 3304(a). When, as here, a statute authorizes an
executive
agency to procure property or services from another executive agency, the procuring
agency must
justify its decision to forgo competition in writing. Id. § 3304(e)(1); FAR
6.303-1(a). The
justification must include certain, specified information. 41 U.S.C. § 3304(e)(2);
FAR 6.303-
2(a) to (b). And, the justification must be approved by the appropriate official and
made publicly
available within fourteen days after contract award. 41 U.S.C. § 3304(e)(1), (f);
FAR 6.305.
Plaintiff is correct that the administrative record does not include any documents
that are
specifically designated as the justifications required by the Competition in
Contracting Act of
1984 and its implementing regulations. However, the administrative record does
include an A-
127 Justification, which was prepared by the Coast Guard on July 3, 2013, to allow
it, TSA, and
DNDO to use a noncompetitive method (migration to an FSSP) to acquire financial
management
software systems and related services. In section 7.D of Circular No. A-127, OMB
specifies that
a justification to forgo full and open competition should generally include the
information
required by FAR 6.303-2. Accordingly, an A-127 Justification can satisfy the
requirements of
the Competition in Contracting Act of 1984 and its implementing regulations.
The A-127 Justification prepared by the Coast Guard, broadly construed, contains much
of the required information. However, five required elements are missing: (1) [a]n
identification of the statutory authority permitting other than full and open
competition, FAR
6.303-2(b)(4); accord 41 U.S.C. § 3304(e)(2)(B); (2) [a] demonstration that the
proposed
contractor s unique qualifications or the nature of the acquisition requires use of
the authority
cited, FAR 6.303-2(b)(5); accord 41 U.S.C. § 3304(e)(2)(B); (3) [a]
determination by the
contracting officer that the anticipated cost to the Government will be fair and
reasonable, FAR
6.303-2(b)(7); accord 41 U.S.C. § 3304(e)(2)(C); (4) [a] statement of the actions,
if any, the
agency may take to remove or overcome any barriers to competition before any subsequent
acquisition for the supplies or services required, FAR 6.303-2(b)(11); accord 41
U.S.C. § 3304(e)(2)(F); and (5) [c]ontracting officer certification that the
justification is accurate and
complete to the best of the contracting officer s knowledge and belief, FAR
6.303-2(b); accord
41 U.S.C. § 3304(e)(1)(A). By omitting these required elements, the Coast Guard,
TSA, and
DNDO violated the Competition in Contracting Act of 1984 and its implementing
regulations.
Of course, it is not enough for plaintiff to establish violations of statute and
regulation.
Plaintiff must also demonstrate that it was prejudiced by the violations. Bannum,
Inc., 404 F.3d
at 1351. To establish prejudice . . . , a protester must show that there was a
substantial chance
it would have received the contract award absent the alleged error. Banknote Corp.
of Am., 365
F.3d at 1350 (quoting Emery Worldwide Airlines, Inc., 264 F.3d at 1086); see also
Data Gen.
Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996) ( [T]o establish prejudice, a
protester
must show that, had it not been for the alleged error in the procurement process,
there was a
reasonable likelihood that the protester would have been awarded the contract. ).
Plaintiff has
not made the necessary showing.
First, some of the information omitted from the A-127 Justification is found
elsewhere in
the administrative record. In particular, DHS's September 9, 2013 D&F identifies
the Economy
Act as the statutory authority for the acquisition of financial management software
systems and
related services from an [federal shared service provider] FSSP and explains why an Economy Act agreement is
appropriate. In
addition, a number of documents including the alternatives analyses and the A-127
Justification reflect the conclusion of the Coast Guard, TSA, and DNDO that
migration to an
FSSP was a comparatively low-cost option, strongly suggesting their belief that the
costs that
they anticipated incurring were fair and reasonable. Second, requiring the Coast
Guard, TSA,
and DNDO to add a statement regarding how they might be able to conduct a full and open
competition in a future procurement would not affect whether plaintiff had a chance
of being
awarded a contract in the present procurement. Finally, although the A-127
Justification lacks
any contracting officer certifications, its conclusion was endorsed by the Chief
Financial
Officers, Chief Information Officers, and Chief Acquisition Officers of the Coast
Guard, TSA,
and DNDO, all of which are higher-level officials than a contracting officer. In
sum, the Coast
Guard s failure to include all of the information in the A-127 Justification that
is required by 41
U.S.C. § 3304(e) and FAR 6.303-2(b) amounts to nothing more than harmless error. As
such,
plaintiff was not prejudiced by the omissions. Consequently, plaintiff cannot
prevail on its claim
that the Coast Guard, TSA, and DNDO violated the Competition in Contracting Act of
1984 and
its implementing regulations.
C. The Economy Act s Implementing Regulations
Plaintiff also argues that the Coast Guard, TSA, and DNDO violated the Economy Act s
implementing regulations when they decided to forgo competition and acquire financial
management software systems and related services on a sole-source basis from the
Interior
Business Center. Specifically, plaintiff contends that the Coast Guard, TSA, and
DNDO violated
FAR subpart 17.5 because the Determination of Best Procurement Approach and the D&F
prepared by DHS on September 9, 2013, upon which they relied did not meet the
requirements of
FAR subpart 17.5. However, as explained above, FAR subpart 17.5 does not apply to the
acquisition at issue here, where one executive agency (DHS) is acquiring goods or
services
directly from another executive agency (the Interior Business Center). Thus, any
deficiencies in
DHS s Determination of Best Procurement Approach and D&F are irrelevant in the
context of
plaintiff s bid protest. Accordingly, plaintiff cannot prevail on its claim that
the Coast Guard,
TSA, and DNDO violated the Economy Act s implementing regulations.
(Savantage Financial Services, Inc. v. U. S., No. 14-307C, September 3, 2015) (pdf)
VI. Whether the Air Force’s Sole-Source Award to Harris was Justified
Plaintiff asserts that the sole-source award to Harris was improper, arbitrary
and capricious, and contrary to law. Compl. ¶¶ 5, 76-77. One specific violation of
regulation noted by plaintiff is the failure to publish a timely notice of the proposed
sole-source award to Harris. Id. ¶ 35. The more general violation of law alleged by
plaintiff is that the Air Force ignored its responsibility to foster fair and open
competition for government contracts. Id. ¶ 70. In support of this contention,
plaintiff asserts that the Air Force improperly ignored IDEA’s repeatedly
expressed interest in competing for the [Air Force’s Command Man-Day Allocation
System] CMAS contract requirement. Pl.’s Mot. ¶ 5.
Plaintiff notes that the contract file contains concessions by the contract
specialist that violations of procurement regulations occurred. Pl.’s Mot. ¶ 8.
Defendant concedes that errors were made in the sole-source award to Harris, but
dismisses them as “technical” or “minor” errors. Def.’s Mot. at 14, 19. Plaintiff
argues, however, that by excluding IDEA from any competition for the CMAS
bridge contract, and by only soliciting a bid from Harris, the Air Force’s sole-source
award was not in accordance with law. Pl.’s Resp. at 14. Plaintiff also notes,
correctly, that there is no review of IDEA’s qualifications or responsibility in the
administrative record; thus, the agency’s failure to solicit a bid from IDEA is
entirely unexplained in the J&A or in any other contemporaneous documents that
were before the agency at the time it made its sole-source award. Id. at 8. Finally,
plaintiff asserts that the Air Force violated procurement law when it failed to
conduct a proper search for responsible sources to perform the CMAS contract
requirement. Id. at 12. Although plaintiff’s protest is less than robust in citations to specific FAR
provisions or caselaw, the court agrees that this procurement was fundamentally
flawed. The sole-source award to Harris was arbitrary and capricious, and included
numerous violations of procurement regulations which were significant. The court
notes that sole-source procurements were specifically addressed by CICA and that
agencies must operate within the restrictions placed upon them by Congress:
Congress establishes the rules for federal procurement and
federal agencies have only the discretion that Congress allows them. In the CICA, Congress expressed concern
that federal agencies had misused the authority Congress
had granted them and too often resorted to sole source
contracts. To control this practice, Congress mandated
that unless a statutory exception applies,
federal agencies must purchase products and services
based upon “full and open competition through the use of
competitive procedures.”
ATA Def. Indus., Inc. v. United States, 38 Fed. Cl. 489, 504 (1997) (ATA Defense)
(quoting 10 U.S.C. § 2304(a)(1)(A)). The court turns first to the issue of advance
planning by the Air Force for a CMAS procurement.
A. Lack of Advance Planning
CICA provides that sole-source procurements may not be used when the
circumstances justifying the award were due to the agency’s own lack of advance
planning. 10 U.S.C.A. § 2304(f)(4)(A); FAR 6.301(c)(1); WorldWide Language
Res., Inc., B-296993, 2005 CPD ¶ 206, 2005 WL 3143870, at *9 (Comp. Gen. Nov.
14, 2005). To the extent that the Air Force justifies its sole-source award to Harris
on “the short time line” available to properly research responsible sources for the
CMAS contract, AR at 97, this justification violates CICA. The time-frame for
the award of this bridge contract was, on the record before the court, entirely
the result of a lack of advance planning on the part of the Air Force.
As the court noted earlier in this opinion, the Air Force
could not have been unaware of the expiring five-year contract with Harris well
in advance of 2009 and 2010. Further, given the generous time-frame available
for procurement planning here, there have been no representations made by the
government that any impediments precluded advance planning. There is no evidence
in the record of any efforts by the Air Force to conduct adequate market
research, or to plan and prepare for a competitive procurement, before Harris’s
old contract expired on March 31, 2010.18 Mr. Crain also persistently reminded
Air Force personnel of their obligation to foster full and open competition for the CMAS program, beginning in
February 2009. This court’s rules indicate that procurement planning documents
should be included in the administrative record, see, e.g., RCFC App. C ¶ 22(b), but
here there are none which evidence an attempt to conduct a timely, competitive
procurement.19 The court concludes that the sole-source contract awarded to Harris
violates 10 U.S.C.A. § 2304(f)(4)(A), because of the lack of advance planning on
the part of the Air Force.
Much of the sole-source justification provided by the Air Force relies on the
unacceptably long transition time that would have been required before a new
contractor could provide CMAS support services. See AR at 96 (estimating that
approximately six to ten months would be necessary for a transition to a new
contractor), 98 (noting the “lengthy learning curve” that a new CMAS contractor
would face ), 98 (estimating that “upwards of ten months” would be necessary for a
transition to a new contractor). Based on the record before the court, this problem,
too, cannot be attributed to anything but the Air Force’s lack of advance planning.
Failure to account for transition periods between an incumbent contractor and a new
contractor is yet another form of lack of advance planning. See, e.g.,
Techno-Sciences, Inc., B-257686, 94-2 CPD ¶ 164, 1994 WL 606131, at *5 (Comp.
Gen. Oct. 31, 1994) (citation omitted).
For all of these reasons, the court finds that the sole-source award violates CICA because it is based on the agency’s lack of advance planning.
B. Arbitrary and Capricious Reasoning
According to the J&A, the agency determined that Harris was the only
responsible source for CMAS support services. AR at 96. However, the same
document concedes that no market research was performed. Id. at 97. Thus, the
agency’s determination that Harris was the only contractor that could provide
CMAS support services appears to be founded on: (1) the fact that the Air Force
examined other existing contract vehicles to see if CMAS could be incorporated
into those existing contracts; and (2) the fact that CMAS support services are
“highly specialized and unique to” Harris. Id. at 96-97. There is no indication,
however, that the Air Force engaged in a meaningful consideration of the
capabilities of other potential sources, before drafting the J&A, to support its
conclusion that CMAS support services are unique.21 Thus, the Air Force’s
determination that Harris was the one responsible source for CMAS support
services was unreasonable. See, e.g., WorldWide Language, 2005 WL 3143870, at
*12 (finding “a critical error” in a sole-source award where “firms other than [the
incumbent] and their capabilities were simply not meaningfully considered”).
The court also questions, as did Mr. Crain in his first post-J&A email to the
Air Force, AR at 211, the factual presumptions supporting the sole-source award to
Harris. The J&A states that “the Government is confident that the proposed number
of hours, labor rates, and labor categories will be comparable and reasonable [as
they have been in the past],” apparently because Harris would keep the same
personnel and Harris’s prices for the old contract had been determined to be fair and
reasonable in 2009.22 AR at 97. The only figures in the administrative record
regarding the last option year of Harris’s old contract show that the annual cost of
the CMAS contract from October 1, 2008 through September 30, 2009 was
$403,338.40. AR at 16. In contrast, the cost of a six to ten month transition to a new contractor was estimated in the J&A to be $1,500,000.23 Id. at 96. This figure
is unexplained, other than an assertion that it is based on “current labor rates.” Id.
There is no credible explanation in the record for this estimate, which triples the
annual cost of the contract, to explain a transition period of approximately six to ten
months. Based on the facts in the record, the agency’s reliance on its calculations
as to the “substantial duplication of costs” of the transition to a new contractor is
arbitrary and capricious.
C. Violations of Procurement Regulations
1. Overview
The violations of procurement regulations in the
sole-source award to Harris are numerous, troubling and prejudicial to IDEA.
These are not mere technical errors. Although there is no indication that the
Air Force conducted this procurement in bad faith, the record suggests that
compliance with regulatory mandates was needlessly sacrificed so that a contract
vehicle could be put in place with a minimum amount of effort. The cumulative
effect of these regulatory violations was to frustrate full and open competition
for the CMAS support services requirement.
2. Reliance on FAR 6.302-1 and FAR 6.302-2
The two types of authority for sole-source procurements at issue in this protest
are “only one responsible source” authority, FAR 6.302-1, and “unusual and
compelling urgency” authority, FAR 6.302-2. Although the FedBizOpps notice
confirmation identifies only FAR 6.302-1 as authority, AR at 101, the text of
the J&A relies on both FAR 6.302-1 and FAR 6.302-2 for authority, AR at 96. The
court notes that reliance on both of these provisions as authority for a
sole-source procurement J&A is extremely rare, at least in procurements
protested to the GAO or this court. In fact, the court is not aware of another
J&A which has attempted to rely on both of these statutory authorities for the
same sole-source award.
The simple reason that this is such a rare circumstance is that the FAR forbids
reliance on FAR 6.302-1 when FAR 6.302-2 is applicable. See FAR 6.302-1(b)
(“This authority . . . shall not be used when any of the other circumstances [in FAR
sections 6.302-2, 6.302-3, 6.302-4, 6.302-5, 6.302-6] is applicable.”); ATA Defense,
38 Fed. Cl. at 497-98 (noting that a contracting officer may not justify a sole-source
award under FAR 6.302-1 if FAR 6.302-2 also applies). In other words, if a
contracting officer is faced with a situation which can be addressed by applying the
“unusual and compelling urgency” provisions of FAR 6.302-2, he or she may not
rely on the “only one responsible source” provisions of FAR 6.302-1 to justify a
sole-source award. One logical reason for this prohibition is that under FAR 6.302-
2, the government is permitted in appropriate circumstances to “limit [but not
automatically reduce to one] the number of sources from which it solicits bids or
proposals.” FAR 6.302-2(a)(2); see also FAR 6.302-2(c)(2) (“This statutory
authority requires that agencies shall request offers from as many potential sources
as is practicable under the circumstances.”). Under FAR 6.302-1, however, the
government is permitted in appropriate circumstances to solicit an offer from one
source only. See FAR 6.302-1(b)(1). In essence, the prohibition in FAR 6.302-1(b)
forces the agency to solicit offers from as many sources as is practicable, in
situations of unusual and compelling urgency, before resorting to soliciting offers
from only a single source, in circumstances which may also present unusual and
compelling urgency.
The court concludes that the Air Force’s apparent attempt to rely on both FAR
6.302-1 and FAR 6.302-2 for the sole-source award to Harris violates FAR
6.302-1(b). Such an approach shows a disregard for the regulatory framework
governing sole-source awards, and also demonstrates a disregard for one of the goals
of CICA, which is to obtain as much competition as is practicable under the
circumstances. The violation of FAR 6.302-1(b) would be less serious if the Air
Force had strictly observed the procedural requirements of FAR 6.302-1, and had
reasonably ascertained that only Harris could provide CMAS support services. The
record shows, however, that neither the letter nor the spirit of FAR 6.302-1 was
respected in the award of the sole-source contract to Harris. Furthermore, the Air
Force similarly failed to respect the safeguards in FAR 6.302-2 which ensure that the
“unusual and compelling urgency” justification for sole-source awards is not abused.
The violation in the J&A of FAR 6.302-1(b), if not a scrivener’s error, was
significant.
3. No Market Research, as Required by FAR Part 10
If, as it appears, the Air Force’s primary justification for the sole-source award
was its determination that Harris was the one responsible source for CMAS support
services, such a determination, to be rational, required adequate market research. As
discussed supra, the Air Force did not conduct any significant market research. As
the contract specialist conceded, the lack of market research to support this solesource
procurement violates FAR Part 10. AR at 70.
The specific provisions in FAR Part 10 that have been violated here, in the
court’s view, include FAR 10.001(a)(2)(ii), FAR 10.001(3)(i), and FAR 10.002(b).
These provisions require market research if the contract is valued to exceed a
threshold amount, require market research that identifies potential sources for the
contract requirement, and require market research into the availability of commercial
items. The record before the court does not show that the Air Force satisfied the
market research requirements of FAR Part 10. The failure to conduct adequate
market research also implicates FAR 6.302-1(b)(1), which requires a “reasonable
basis” for the determination that only one responsible source exists to fulfill a
contract requirement. See, e.g., WorldWide Language, 2005 WL 3143870, at *12
(sustaining a protest of a sole-source award justified by the authority of FAR 6.302-1
because “firms other than [the incumbent] and their capabilities were simply not
meaningfully considered”). The violation of FAR Part 10 in this procurement was a
significant and serious violation of procurement regulations.
4. No Contract Synopsis Posted, as Required by FAR
5.207(c)(15)(ii) and FAR 6.302-1(d)(2)
As a general rule, a procuring agency must provide notice of upcoming
contract actions. See FAR 5.201(c) (“The primary purposes of the notice are to
improve small business access to acquisition information and enhance competition
by identifying contracting and subcontracting opportunities.”). These contract
action synopses are required to include specified content. FAR 5.207. As pertinent
here, “[w]hen using the sole source authority at 6.302-1, insert a statement that all
responsible sources may submit a capability statement, proposal, or quotation, which
shall be considered by the agency.” FAR 5.207(c)(15)(ii) (now found at 48 C.F.R. §
5.207(c)(16)(ii)). The requirement for this statement in a posted synopsis is also
found in FAR 6.302-1, which contains the additional requirement that “any bids,
proposals, quotations, or capability statements [received in response to the synopsis]
must have been considered” by the agency. FAR 6.302-1(d)(2).
Here, there was no synopsis posted prior to contract award; no statement
encouraging potential sources to submit proposals; and, necessarily, no
consideration by the Air Force of information received in response to such a notice.
The failure to post a proper synopsis on FedBizOpps was a significant departure
from regulatory requirements, and further weakens the rationality of the agency’s
determination that only Harris could have performed the bridge contract for CMAS
support services. See, e.g., M.D. Thompson Consulting, LLC, B-297616, 2006 CPD
¶ 41, 2006 WL 463154, at *3 (Comp. Gen. Feb. 14, 2006) (stating that “a synopsis
must provide prospective alternative sources a meaningful opportunity to
demonstrate their ability to provide what the agency seeks to purchase”) (citation
omitted); see also Barnes Aerospace Grp., B-298864, 2006 CPD ¶ 204, 2006 WL
3849071, at *6 (Comp. Gen. Dec. 26, 2006) (“We think agencies undercut their
credibility when they prepare and execute sole-source J & As on the basis that there
is only one responsible source available, before the time they have received
expressions of interest and capability from potential offerors. The entire purpose of
issuing notices seeking expressions of interest and capability is to avoid the need for
such sole-source procurements, if possible.”). The sole-source award to Harris was
not in accordance with FAR 5.207(c)(15)(ii) or FAR 6.302-1(d)(2) and was
improper for this reason.
5. No Explanation in the J&A as to the Failure to Post a
Synopsis, and No Citation to Authority Justifying Such a
Failure, as Required by FAR 6.303-2(a)(6)
There are exceptions to the requirement for the posting of a contract action
synopsis, and these exceptions are delineated in FAR 5.202. One such exception
permits an agency to refrain from posting a contract action synopsis for a sole-source
award justified under FAR 6.302-2 when certain conditions are met:
The contracting officer need not submit the notice required
by [FAR] 5.201 when . . . [t]he proposed contract action is
made under the conditions described in 6.302-2 . . . and the
Government would be seriously injured if the agency
complies with the time periods specified [for the posting of
contract action synopses] in [FAR] 5.203.
FAR 5.202. Thus, a sole-source award justified under FAR 6.302-2 may, in
appropriate circumstances, be exempt from the synopsis requirements set forth in
FAR Subpart 5.2.
However, the above-mentioned exception in FAR 5.202 was not invoked in
the J&A for this sole-source procurement; indeed, the J&A is silent as to the Air
Force’s failure to post a synopsis before contract award. The J&A thus fails to
conform to FAR 6.303-2, which requires that each J&A include “[a] description of
efforts made to ensure that offers are solicited from as many potential sources as is
practicable, including whether a notice was or will be publicized as required by
subpart 5.2 and, if not, which exception under 5.202 applies.” FAR 6.303-2(a)(6)
(now found at 48 C.F.R. § 6.303-2(b)(6)). This is not a mere technical error - the
officials approving the J&A should have been made aware of the Air Force’s failure
to synopsize the contract action (and the ramifications that failure might have had on
the rationality of the sole-source award); in the absence of this vital information,
their approval signatures do not carry the same weight. See United States Marshals
Serv., B-224277, 87-1 CPD ¶ 430, 1987 WL 102234, at *1 (Comp. Gen. Apr. 22,
1987) (finding a sole-source award improper because the agency’s J&A did not
contain a statement noting and explaining the agency’s failure to post a synopsis
prior to award). For this reason, the Air Force’s sole-source award to Harris violated
FAR 6.303-2(a)(6) and was improper.
6. No Mention of IDEA as an Interested Source, as Required by
FAR 6.303-2(a)(10)
Another minimum requirement of a sole-source J&A is a listing of contractors
that have expressed an interest in the contract requirement. This requirement is set
forth in FAR 6.303-2, which states in relevant part: “As a minimum, each
justification shall include . . . [a] listing of the sources, if any, that expressed, in
writing, an interest in the acquisition.” FAR 6.303-2(a)(10) (now found at 48 C.F.R.
§ 6.303-2(b)(10)). This regulation, too, was violated in the sole-source award to
Harris.
Here, it is undisputed that IDEA repeatedly expressed, in writing, an interest
in the CMAS procurement, in emails sent February 9, 2009, March 24, 2009, April
17, 2009, and December 11, 2009. These expressions of interest were received
despite the agency’s failure to post a synopsis of the upcoming sole-source award to
Harris. In the circumstances of this procurement, where Mr. Crain and IDEA had
extensive CMAS experience and contacts with officials responsible for CMAS, these
written expressions of interest by IDEA should have earned IDEA an “Interested
Source” listing in the J&A, but did not.
If, indeed, IDEA’s interest in the CMAS contract requirement had been noted
in the J&A, it is likely that a more thoughtful analysis of the agency’s “only one
responsible source” determination would have been conducted by the approving
authorities. As the record stands, however, there is no useful comparison of the
qualifications of IDEA and Harris in the record. The court finds that the violation of
FAR 6.303-2(a)(10) was significant.
7. Failure to Solicit Offers from As Many Sources As
Practicable, as Required by FAR 6.302-2(c)(2)
Finally, even if this sole-source procurement had been
justified only under the “unusual and compelling urgency” circumstances
described in FAR 6.302-2, the Air Force did not make the required effort to
solicit offers from as many sources as practicable. FAR 6.302-2(c)(2). The GAO has repeatedly sustained protests where
an agency has made only minimal efforts to expand its consideration of potential
sources beyond an incumbent contractor. The following passage in WorldWide
Language describes a flawed procurement not unlike the sole-source procurement in
this case:
Moreover, the actions associated with the J & A were
inconsistent with the requirements of the “unusual and
compelling urgency” justification ultimately relied upon by
the agency as the basis for the sole-source award to [the awardee]. When relying on the urgency justification, as
noted above, an agency is required to obtain competition to
the maximum extent practicable. However, as a
consequence of the agency’s focus on the capabilities of
[the awardee] to the exclusion of all others, the agency
failed to take any steps to obtain any competition for the
expanded . . . requirement. For example, in testimony
before our Office regarding the consideration of other
contractors, the Air Force indicated that due to the short
time frame to fulfill the requirement, transition issues, and
because [the awardee] was “performing admirably [on an
existing contract],” the Air Force determined that [the
awardee] “was uniquely qualified to be the source on this
follow-on.” The record shows that the expanded . . .
requirement was formally approved by the Under Secretary
of Defense on May 2, 2005 and [the awardee’s]
sole-source contract was ultimately awarded in late July –
but during that entire period no effort was apparently made
to identify other firms, consider their capabilities or
provide for any degree of competition, even on a limited
basis. In addition, while it may be the case that [the
awardee’s] customers in Iraq were pleased with [the
awardee’s] performance, their satisfaction did not provide
a basis for disregarding the requirement to seek
competition to the maximum extent practicable. As a
consequence, we sustain the protesters’ challenge to the
second sole-source award to [the awardee].
WorldWide Language, 2005 WL 3143870, at *12 (citations and
footnotes omitted).
In this case, the Air Force neglected to look into its own
contract files to discover IDEA, a potential competitor to Harris, as a source
for CMAS services; neglected to post a synopsis which might have produced
expressions of interest from competitors to Harris; and performed only the most
cursory searches for contractors capable of fulfilling the CMAS bridge contract. As in WorldWide Language, the Air
Force failed to solicit offers from as many sources as was practicable under the
circumstances. This is a clear violation of FAR 6.302-2(c)(2). At a minimum, the
agency could have solicited an offer from IDEA. See, e.g., Bausch & Lomb, Inc., B-
298444, 2006 CPD ¶ 135, 2006 WL 2711794, at *2 (Comp. Gen. Sept. 21, 2006)
(sustaining a protest because “the agency has not reasonably demonstrated why it
could not have opened the requirement up to an expedited limited competition
among those firms that had expressed interest in the acquisition”).
Although the government, during the course of this protest, has suggested that
IDEA was not a qualified, responsible source for CMAS support services, the record
is devoid of any assessment of IDEA’s qualifications by the Air Force. The glowing
description of Harris’s capabilities in the J&A permits the inference that the agency
considered Harris to be superior to any potential competitor. Superiority, however,
is not adequate justification for a sole-source award. See, e.g., Savantage Fin.
Servs., Inc. v. United States, 81 Fed. Cl. 300, 308 (2008) (citing Aero Corp. v. Dep’t
of the Navy, 540 F. Supp. 180, 208 (D.D.C. 1982)). Superiority, instead, permits
an agency to award a contract after the evaluation of competing proposals. Id.
(citation omitted). On the record before the court, there is no reasonable
explanation why the Air Force did not solicit a proposal from IDEA. (Innovation
Development Enterprises of America, Inc., V. U. S., No 11-217C, January 29,
2013) (pdf) |
|
U.
S. Court of Federal Claims - Listing of Decisions |
For
the Government |
For
the Protester |
Savantage Financial Services, Inc. v. U. S.,
No. 14-307C, September 3, 2015 (pdf) |
Innovation Development
Enterprises of America, Inc., V. U. S., No 11-217C, January
29, 2013 (pdf) |
|
|
|
|