FAR 6.401: Preference for sealed bidding |
Comptroller General - Key Excerpts |
Ceres contends that the Corps’ decision to conduct this
procurement using negotiated procedures, instead of using sealed
bidding procedures, violates the Competition in Contracting Act
(CICA). In this regard, Ceres disputes the agency’s conclusion
that the complexity of this procurement requires the agency to
use non‑price evaluation factors. Ceres also asserts that
discussions are not needed for this procurement, and that the
Corps failed to sufficiently document its decision to use
negotiated procedures instead of sealed bidding. CICA
requires the use of sealed bidding when: (1) time permits; (2)
award will be based on price and other price-related factors;
(3) discussions are not necessary; and (4) more than one bid is
expected. 10 U.S.C. sect. 2304(a)(2)(A); Federal Acquisition
Regulation (FAR) sect. 6.401(a); Specialized Contract Servs.,
Inc., B-257321, Sept. 2, 1994, 94-2 CPD para. 90 at 4. When an
agency determines that these conditions are not met, CICA
requires the use of negotiated procedures. 10 U.S.C. sect.
2304(a)(2)(B). The determination as to whether circumstances
support the use of negotiated procedures is largely a
discretionary matter within the purview of the contracting
officer. FAR sect. 6.401; Military Base Mgmt., Inc., B-224115,
Dec. 30, 1986, 86-2 CPD para. 720 at 3. However, an agency must
reasonably conclude that the conditions requiring use of sealed
bidding are not present. F&H Mfg. Corp., B-244997, Dec. 6, 1991,
91-2 CPD para. 520 at 3. As an initial matter, there is no
dispute that the RFP here anticipates an evaluation that will
include non-price factors. On this basis alone, this procurement
is different from those that CICA requires to be conducted using
sealed bidding. In addition, the RFP anticipates a best value
procurement, and anticipates a possible price/technical
tradeoff; neither of these options would be appropriate in a
sealed bid environment.
Given that the RFP, on its face,
anticipates the use of non-price evaluation factors and a
possible price/technical tradeoff, Ceres’ remaining arguments
essentially challenge the reasonableness of the agency’s stated
needs. Specifically, Ceres argues that previous canal
construction projects have been awarded without using non-price
evaluation factors, and that the agency has improperly concluded
that it needs to assess technical merits and possibly perform a
trade-off analysis to determine which proposal constitutes the
best value to the government. The record here shows that, in
making this determination, the contracting officer cited the
complexity of the project and the need for an accelerated
schedule to complete the project. AR, Tab B, Contracting
Officer’s (CO) Statement, at 10. In addition, the Corps’ Lead
Structural Engineer submitted an affidavit explaining that the
awardee must, among other activities, coordinate multiple crews
within a narrow space, keep the main evacuation route out of New
Orleans open throughout construction, schedule work to avoid
interfering with completion of the pumping station, and maintain
existing structures while building new ones in close proximity.
AR, Tab N, Affidavit of Corps Lead Structural Engineer, at 2.
The Lead Engineer also explains that the contractor will have to
do all of these things while operating under a compressed time
schedule. Id. at 5. Because of the need to mitigate the risk of
further flooding in an area that was so recently devastated by
Hurricane Katrina, and to encourage redevelopment, the Corps
decided to shorten the construction timeframe by almost 9
months, and to include a duration evaluation factor to encourage
offerors to propose even shorter timeframes. AR, Tab B, CO
Statement, at 10-12; RFP amend. 1 at 2. Under these
circumstances and as explained below, we find that the Corps
reasonably concluded that selection of a contractor here
requires the use of negotiated procedures. First, we note that
the fact that previous canal construction projects have been
awarded without using non-price evaluation factors is not
dispositive on the issue of whether the agency can properly use
non-price evaluation factors now. See Comfort Inn South,
B-270819.2, May 14, 1996, 96‑1 CPD para. 225 at 3. In addition,
the need to move quickly to restore and improve flood‑control
capabilities in a hurricane-stricken area, the relatively
complex coordination and scheduling requirements of doing so,
coupled with the compressed time frames in which the work is to
be completed, provide reasonable support for the agency’s
determination to consider non-price factors in evaluating
proposals for award. See TLT Constr. Corp., B-286226, Nov. 7,
2000, 2000 CPD para. 179 at 3 (complex coordination and
scheduling requirements provided reasonable support for
negotiated procurement); W.B. Jolley, B-234490, May 26, 1989,
89-1 CPD para. 512 at 4-5 (decision to consolidate numerous,
diverse services into one contract created a complex procurement
justifying use of negotiated procurement procedures). To
the extent that Ceres argues that the Corps failed to provide an
adequate legal analysis for its decision to use negotiated
procurement procedures, Ceres correctly noted that the Corps did
not explicitly mention the requirements of 10 U.S.C. sect.
2304(a)(2) in its acquisition plan. Nonetheless, the Corps
sufficiently addressed the factors that influenced its decision
to use negotiated procurement procedures in its acquisition plan
and other documentation provided with the agency report, which
satisfies the CICA requirements. (Ceres
Environmental Services, Inc., B-310902, March 3, 2008) (pdf)
CICA does provide, however, that
sealed bidding is to be used if (1) time permits, (2) award will
be based on price, (3) discussions are not necessary, and (4)
more than one bid is expected. 10 U.S.C. sect. 2304(a)(2)(A).
Thus, an agency need not solicit sealed bids if it reasonably
determines that it must evaluate factors other than price, F & H
Mfg. Corp., B-244997, Dec. 6, 1991, 91-2 CPD para. 520 at 4, or
that it will be necessary to conduct discussions with responding
sources about their offers. TLC Sys. and King-Fisher Co.,
B-227842, B-227842.2, Oct. 6, 1987, 87-2 CPD para. 341 at 3.
Here, as explained more fully below, we think that the agency
reasonably determined to use negotiated procedures instead of
sealed bids. (TLT
Construction Corporation, B-286226, November 7, 2000) |
|
Comptroller General - Listing of Decisions |
For the
Government |
For the Protester |
Ceres Environmental Services, Inc.,
B-310902, March 3, 2008 (pdf) |
|
TLT Construction Corporation, B-286226, November 7, 2000 |
|
U. S. Court of Federal Claims - Key Excerpts |
As grounds for its protest, Weeks
asserts that SAD’s1 proposed change to IDIQ task order
contracting is contrary to law, and is without any rational
basis. Weeks relies upon 10 U.S.C. § 2304(a) and Federal
Acquisition Regulation (“FAR”) ¶ 6.401(a), mandating that an
agency shall use sealed bidding procedures when (1) time
permits, (2) awards will be made solely based on price, (3)
discussions are not necessary, and (4) the agency reasonably
expects to receive more than one bid. Weeks contends that each
of these four conditions is met for SAD’s dredging contracts,
and that no legal basis exists to use negotiation procedures.
See also FAR ¶ 14.103-1(a) (“Sealed bidding shall be used
whenever the conditions in 6.401(a) are met.”); FAR ¶ 36.103(a)
( “The contracting officer shall use sealed bid procedures for a
construction contract if the conditions in 6.401(a) apply.”).
Weeks further states that the agency has violated Corps of
Engineers FAR Supplement (“EFARS”) ¶ 16.501, S-103(a) because
none of the five identified conditions for using indefinite
delivery contracts has been satisfied. Weeks also argues that
SAD’s attempt to justify a move to negotiated IDIQ task order
contracting lacks any rational basis. Defendant argues in
opposition that SAD’s proposed IDIQ task order contracting is
lawful, that the agency has wide discretion in selecting an
appropriate procurement method, and that SAD’s justification for
the change is reasonable under current circumstances. Defendant
alleges that SAD expects to save time through task order
contracting, and that SAD’s future awards will not be made on
the basis of price alone, but will consider other factors such
as “past performance.” Defendant also contends that Weeks has
not shown any prejudice if the solicitation is allowed to go
forward because Weeks is a prominent contractor in the dredging
industry, and will likely receive ample work under the new
procedures.
A disturbing feature of SAD’s new
procurement method is that approximately $2 billion in task
order awards during the next five years would become virtually
immune from any judicial or administrative bid protest review.
The Federal Acquisition Streamlining Act of 1994 (“FASA”)
provides that “[a] protest is not authorized in connection with
the issuance of a task order or delivery order except for a
protest on the ground that the order increases the scope,
period, or maximum value of the contract under which the order
is issued.” 10 U.S.C. § 2304c(d); see also FAR ¶ 16.505(a)(9)
(same provision). While SAD’s current sealed bid awards
routinely are subject to bid protest review by the Government
Accountability Office (“GAO”) or this Court, SAD’s task order
awards would be insulated from review except in very limited
circumstances. Thus, while purporting to use highly
discretionary “best value” evaluation procedures in awarding
task orders, SAD effectively would remove itself from any bid
protest oversight. Defendant argues that the Court must apply
the FASA provision that Congress created. However, this
provision did not authorize SAD to convert all of its
procurements into task orders. The agency’s Administrative
Record contains no mention or discussion of this important
concern. Despite SAD’s attempt to insulate itself from any bid
protest review, the Court would be constrained to uphold SAD’s
new procurement method if it complied with law, and if the
reasoning behind the new method was rationally based. However,
this is not the case. The new method violates 10 U.S.C. §
2304(a) and related procurement regulations. SAD has raised a
number of reasons for its purported move to IDIQ task order
contracting, such as: (1) shortening the procurement cycle; (2)
reducing administrative costs; (3) reducing the need for
emergency contracting with less than full and open competition;3
and (4) eliminating competition among SAD districts for
contractor equipment and resources.
Despite SAD’s attempt to insulate
itself from any bid protest review, the Court would
be constrained to uphold SAD’s new procurement method if it
complied with law, and if the
reasoning behind the new method was rationally based. However,
this is not the case. The
new method violates 10 U.S.C. § 2304(a) and related procurement
regulations. SAD has
raised a number of reasons for its purported move to IDIQ task
order contracting, such as:
(1) shortening the procurement cycle; (2) reducing
administrative costs; (3) reducing the need
for emergency contracting with less than full and open
competition;3 and (4) eliminating
competition among SAD districts for contractor equipment and
resources. As will be
explained, SAD’s Acquisition Plan conspicuously is lacking in
empirical data supporting its
rationale, and not one of the reasons advanced, except for the
ability to respond to emergencies, justifies SAD’s new
procedures. See AR 1-71. Moreover, the need to respond
to emergencies does not justify a sweeping five-year change for
approximately $2 billion in
expected procurements. The agency states that its sealed bid
approach “has excelled in
program execution” during the last two years. AR 10, 50-51. The
agency has provided no
evidence that the current system is failing or in need of
revision. In fact, the Court would be
hard-pressed to identify any contracts better suited to sealed
bid procurement than dredging.
If not appropriate for dredging work, it is difficult to imagine
when sealed bidding ought to
be used.
As will be explained, SAD’s
Acquisition Plan conspicuously is lacking in empirical data
supporting its rationale, and not one of the reasons advanced,
except for the ability to respond to emergencies, justifies
SAD’s new procedures. See AR 1-71. Moreover, the need to respond
to emergencies does not justify a sweeping five-year change for
approximately $2 billion in expected procurements. The agency
states that its sealed bid approach “has excelled in program
execution” during the last two years. AR 10, 50-51. The agency
has provided no evidence that the current system is failing or
in need of revision. In fact, the Court would be hard-pressed to
identify any contracts better suited to sealed bid procurement
than dredging. If not appropriate for dredging work, it is
difficult to imagine when sealed bidding ought to be used.
After carefully considering the
Administrative Record and the parties’ arguments, the Court
finds that the solicitation violates applicable statutes and
regulations, and that SAD’s attempted justification for the new
procurement approach is without a rational basis. The agency’s
Acquisition Plan (AR 1-71) is the principal document on which
SAD relies, but it fails even to address the legality of the
proposed action, and does not satisfy the rational basis test.
See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co.,
463 U.S. 29, 43 (1983) (“[T]he agency must examine the relevant
data and articulate a satisfactory explanation for its action
including a ‘rational connection between the facts found and the
choice made.’”) (quoting Burlington Truck Lines v. United
States, 371 U.S. 156, 168 (1962)). Accordingly, the Court GRANTS
Plaintiff’s Motion for Judgment on the Administrative Record,
and DENIES Defendant’s Motion for Judgment on the Administrative
Record. The Court permanently enjoins Defendant and the
procuring agency, SAD, from employing the solicitation at issue
for negotiated IDIQ task order contracting. (Weeks
Marine, Inc., v. U. S., No. 07-700C, Reissued November 6,
2007) (pdf)
------------------------------
1
United States Army Corps of Engineers, South Atlantic Division. |
|
U. S. Court of Federal Claims - Listing of Decisions |
For the Government |
For the Protester |
|
Weeks Marine, Inc., v. U. S., No.
07-700C, Reissued November 6, 2007 (pdf) |
Court of Appeals for the Federal Circuit - Key Excerpts |
In the Initial Opinion, the Court of Federal Claims ruled that
the MATOC solicitation violated 10 U.S.C. § 2304(a)(2), which
provides that sealed bidding must be used when an agency plans
to award a contract based solely on price and price-related
factors. Initial Opinion, 79 Fed. Cl. at 29–30. Although the
Corps indicated it would be evaluating non-price-related
factors, the court found that the “evaluation factors will not
permit the determination of any meaningful distinctions among
the offerors, nor will they allow for any different ways to make
task orders awards.” Id. at 30. Thus, the court reasoned the
Corps would actually be making its determination based on price.
Id.
The Court of Federal Claims also ruled that
the MATOC solicitation had no rational basis. Having ruled in
its disposition of the § 2304(a) issue that the Corps would not
be considering non-price related factors, such as contractor
qualifications, the court rejected the additional justifications
proffered for the Corps’s procurement action. Initial Opinion,
79 Fed. Cl. at 31–34. The government asserted the use of IDIQ
MATOCs would reduce the procurement cycle, but the court found
“the record contain[ed] no evidence showing that a shortened
procurement cycle would enhance [the] ability to complete
projects in a timely manner.” Id. at 32. Although the government
asserted that the new procurement scheme would reduce
administrative costs by $1.5 million over two years, the court
found “no evidence of how this savings is calculated, or how it
will occur.” Id. at 33. Further, the court found that the hours
estimated for evaluating the proposals received in response to
the solicitation were too low for a negotiated procurement, and
that administrative costs thus would likely be much higher than
estimated. Id. The government also argued that IDIQ MATOCs would
reduce the need for emergency procurements. However, the court
rejected this contention as well, indicating that emergency
procurements had constituted only 2.4 percent of South Atlantic
Division expenditures in the prior two years, and did not
justify a “procurement overhaul.” Id. Additionally, the
government asserted that the IDIQ MATOCs would increase
coordination between the districts in the Corps’s South Atlantic
Division. The Court of Federal Claims found, though, that the
need for increased coordination did not warrant a change from
sealed bidding, but rather necessitated the vesting of oversight
in one office. Id. at 33–34. The court then dismissed in summary
fashion all other arguments proffered by the government, stating
that the record was “devoid of credible evidence” that
competition would increase, that small businesses would benefit,
or that national security would be improved through the use of
IDIQ MATOCs. Id. The court thus concluded that the proposed
solicitation lacked a rational basis. Addressing the regulatory
framework, the court concluded that the solicitation did not
comply with the EFARS requirement that indefinite delivery
contracts could only be used in certain limited circumstances.
Id. at 31.
(sections deleted)
We have stated that procurement decisions
“invoke[ ] ‘highly deferential’ rational basis review.” CHE
Consulting, Inc. v. United States, 552 F.3d 1351, 1354 (2008)
(quoting Advanced Data Concepts, Inc. v. United States, 216 F.3d
1054, 1058 (Fed. Cir. 2000)). Under that standard, we sustain an
agency action “evincing rational reasoning and consideration of
relevant factors.” Advanced Data Concepts, 216 F.3d at 1058.
The Corps has presented seven reasons for
its new procurement scheme. As seen, through the use of IDIQ
MATOCs, the Corps expects to (1) obtain qualified contractors;
(2) reduce procurement time; (3) realize savings in
administrative costs; (4) reduce or eliminate the need for
emergency procurements; (5) allow for greater coordination
between the districts in the South Atlantic Division; (6)
facilitate the use of small businesses; and (7) be able to
address national security needs through more timely execution of
dredging near military bases. We think it can hardly be argued
that any one of these is not a legitimate procurement objective.
Recognizing our deferential review of an
agency’s procurement decision, Weeks does not argue that the
Corps’s objectives are not legitimate. Rather, it takes the
position that the Corps has not demonstrated that IDIQ MATOCs
are necessary to achieve those objectives. In so doing, Weeks
makes much of the fact that the solicitation and the Acquisition
Plan provide little empirical evidence connecting the Corps’s
needs to the new procurement scheme. For the following reasons,
we are not persuaded by Weeks’s argument.
After the Court of Federal Claims decided
this case, we rendered our decision in CHE Consulting. In CHE
Consulting, the United States Naval Oceanic Office (“NAVO”)
sought to solicit a single provider for the hardware and
software maintenance of a complex supercomputer system. 552 F.3d
at 1352. Eventually, after a request by CHE Consulting (“CHE”),
the General Services Administration separated the procurement
into two contracts—one for hardware and one for software. Id. at
1353. In response to the revised solicitation, CHE submitted a
hardware maintenance proposal, but NAVO indicated it would not
accept “de-bundled” proposals. Id. Following direction from NAVO,
the General Services Administration, which had issued the
solicitation, cancelled it, and issued a new solicitation
requiring a single provider for both hardware and software
maintenance. Id. Thus, the two maintenance requirements were
“bundled.”
CHE brought a protest in the Court of
Federal Claims, arguing that the bundling requirement lacked a
rational basis and requesting an injunction with respect to the
bundled solicitation. CHE, 552 F.3d at 1353. After examining the
administrative record, the Court of Federal Claims found the
evidence supporting the new solicitation “sparse,” and requested
supplementation of the record. Specifically, the court asked for
a cost analysis and empirical survey evidence on the practices
of other agencies. Id. After the record was supplemented, the
court ruled the bundling requirement had a rational basis. Id.
at 1353–54. Accordingly, the court rejected CHE’s challenge to
the solicitation. Id.
CHE appealed. On appeal, we determined not
only that NAVO established a rational basis based on the
supplemented record, but also that no supplementation was
required in the first place. Id. at 1354 (“NAVO established a
rational basis to combine hardware and software services into
one contract before the trial court requested supplementation.
The additions to the administrative record were thus not
necessary.”). In our decision, we pointed to several concerns
about “segregating the maintenance contracts,” which were stated
in a memorandum and affidavit of NAVO’s contracting officer
representative, both of which were present in the original
administrative record. Id. at 1354–55. We indicated that those
concerns provided a rational basis for NAVO’s procurement, even
though the documents provided no supporting evidence for the
concerns expressed. Id. at 1355. Affirming the decision of the
Court of Federal Claims based upon the original administrative
record, we stated:
NAVO has no obligation to point to past
experiences substantiating its concerns in order to survive
rational basis review. . . . Indeed NAVO has a responsibility to
assess risks and avoid them before they become a historical
fact. . . . In terms of this procurement, NAVO need not suffer
some maintenance failures in order to substantiate its
assessment of risks . . . . Thus, to satisfy its obligation to
supply a rational basis for its decisions, NAVO may supply a
reasoned chronicle of its risk assessment, as it did in this
case.
CHE Consulting, 552 F.3d at 1355.
CHE Consulting controls this case. The
Corps has put forth seven specific reasons for its procurement
action, each of which represents a legitimate procurement
objective. And as seen, in the case of each reason, the
Acquisition Plan states the underlying rationale. Perhaps the
Plan’s fullest statement of an underlying rationale relates to
emergency procurements. In that regard, the Acquisition Plan
states that “[t]he southeastern portion of the United States,
simply from its geographic proximity to warm, tropical climatic
conditions, is annually subjected to hurricanes and other
potentially catastrophic natural disasters.” Continuing, the
Plan explains how “during the past several years,” hurricanes
and other severe storm events have increased shoaling in many
channels, and it states that some shoaling became so severe that
emergency contracts were required in order to maintain channel
depths and allow access by both commercial and military vessels.
The Acquisition Plan recites that many of these emergency
contracts were solicited using less than full and open
competition in accordance with FAR 6.302-2, Unusual and
Compelling Urgency. See 48 C.F.R. § 6.302-2. The Acquisition
Plan adds that, “[b]ased upon expert technical analysis, it is
anticipated that this increase in shoaling will continue into
the foreseeable future.” It states in addition that storms
during the 2004 hurricane season “devastated many miles of
shoreline” in North and South Carolina and Florida. This damage,
the Acquisition Plan notes, resulted in the award of twenty
shore protection contracts with a total value of over $98
million. The Plan concludes the discussion by stating that
implementation of the MATOC procurement scheme “would virtually
eliminate the need to limit competition in the case of natural
disaster or other national emergencies.”
The Corps was required to “supply a
reasoned chronicle of the risk assessment.” CHE Consulting, 552
F.3d at 1455. We think it did that by stating the reasons for
its procurement decision and the thinking behind those reasons.
Put most simply, given the Corps’s mission, and what the
Acquisition Plan tells us, we conclude that the Corps has
sufficiently demonstrated that it is working to “avoid [risks]
before they become historical fact” and that it has supplied a
“reasoned chronicle of its risk assessment.”
In sum, we hold that the Corps’s decision
to issue the MATOC solicitation “evince[es] rational reasoning
and consideration of relevant factors.” Were we to conclude
otherwise, we would be second-guessing the Corps’s action. That
is something we are not permitted to do. “‘If the court finds a
reasonable basis for the agency’s action, the court should stay
its hand even though it might, as an original proposition, have
reached a different conclusion as to the proper administration
and application of the procurement regulations.’” Honeywell,
Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir. 1989)
(quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301
(D.C. Cir. 1971)) (holding that the General Accounting Office’s
determination that a bid for a procurement contract was
responsive and properly disclosed the bidder’s identity had a
rational basis). In this case, the Corps has demonstrated a
rational basis for the MATOC solicitation. (Weeks
Marine, Inc., v U. S., No. 2008-5034, August 10, 2009)
(pdf) |
|
Court of Appeals for the Federal Circuit - Listing of Decisions |
For
the Government |
For
the Protester |
Weeks Marine, Inc., v U. S.,
No. 2008-5034, August 10, 2009 (pdf)
(Reverses COFC decision Weeks
Marine, Inc., v. U. S., No. 07-700C, Reissued November 6,
2007, See above) |
|
|
|