New
The protester argues that DLA unlawfully bundled
requirements. Protest at 2. Specifically, the protester
asserts that the RFP improperly combines requirements that
have been, or are being, performed through “separate
small” contracts. Id. In response, the agency denies that
its solicitation bundles requirements because the RFP
“provides that DLA Energy will evaluate ‘offers on a line
item‑by‑line item basis.’” DLA Req. for Dismissal at 2.
Moreover, DLA explains that “[e]ach line item will be
evaluated and awarded independently from all other line
items.” Id.
The Competition in Contracting Act (CICA) generally
requires that solicitations permit full and open
competition and contain restrictive provisions only to the
extent necessary to satisfy the procuring agency’s needs.
10 U.S.C. § 2305(a)(1). An allegation of improper bundling
under CICA reflects a claim that a contract combines
separate requirements beyond what is necessary to meet the
agency’s needs, thereby limiting competition by excluding
offerors that can only perform a portion of the
requirement. See e.g., Manus Med. LLC, B‑412331, Jan. 21,
2016, 2016 CPD ¶ 49 at 5; Major Contracting Servs., Inc.,
B-406980, Oct. 10, 2012, 2012 CPD ¶ 288 at 3‑4.
Similarly, the Small Business Act provides that “each
Federal agency, to the maximum extent practicable, shall .
. . avoid unnecessary and unjustified bundling of contract
requirements that precludes small business participation
in procurements as prime contractors.” 15 U.S.C. §
631(j)(3). The Small Business Act defines bundling of
contract requirements as “consolidating 2 or more
procurement requirements for goods or services previously
provided or performed under separate smaller contracts
into a solicitation of offers for a single contract that
is likely to be unsuitable for award to a small-business
concern[.]” 15 U.S.C. § 632(o)(2); see also FAR § 2.101.
Here, we agree with the agency’s conclusion that its
decision to place these requirements under one
solicitation does not constitute improper bundling because
the protester, a small business concern, has not been
precluded from competing. To the contrary, the protester
submitted a proposal responding to the solicitation’s
requirements, asserting that it is capable of performing.
On this record, the protester’s assertion that the
solicitation improperly bundles requirements fails to
state a valid basis of protest. Bid Protest Regulations, 4
C.F.R. §§ 21.1(c)(4), (f); 21.5(f); Navarre Corp.,
B‑414505.4, Jan. 4, 2018, 2018 CPD ¶ 15 at 4 n.3 (GAO will
not consider bundling allegations where small business
protesters represent that they are capable of performing
the allegedly bundled requirements); see also, Manus Med.
LLC, supra, at 5‑6. Accordingly, this protest ground is
dismissed. AeroSage, LLC; SageCare, Inc., B-416279, July
16, 2018, 2018 CPD ¶ 243, at 3. (AeroSage,
LLC B-416381: Aug 23, 2018)
MTU characterizes its protest as a challenge to the
agency’s proposed sole-source award of the CLS contract to
Boeing. According to the protester, the agency is required
to separate the engine maintenance element of its overall
requirement from the balance of the CLS requirement
because MTU can perform that aspect of the requirement,
and because, in MTU’s view, there are other potential
contractors with the capability to perform the engine
maintenance element of the requirement. MTU also notes
that the solicitation itself contemplates that the engine
maintenance element of the requirement will be
subcontracted, and that this further demonstrates that it
is suitable for competition. MTU argues that the agency’s
decision to include the engine maintenance element of the
requirement with the balance of the CLS requirements
reflects a lack of advanced planning on the part of the
agency.
We find no merit to MTU’s protest. As an initial matter,
we point out that MTU does not object generally to the
agency’s sole-source approach to this acquisition. In
fact, in its February 19 response to the agency’s final
sources sought notice, MTU’s consultant specifically
stated that a sole-source award to Boeing “appears
justified” and stated further that: “In summary, l fully
appreciate that the government's market research was
properly conducted and resulted in the decision to award
the E-4B contract sole source to Boeing.” AR, exh. 8, MTU
E-Mail to the Air Force, at 1-2. We note as well that,
inasmuch as MTU has never alleged or demonstrated that it
is capable of performing the entire CLS requirement, it is
not an interested party to challenge the agency’s overall
approach to awarding a contract for its CLS requirements
on a sole-source basis. H.L. Boulton Co., Inc., B-256014,
B‑256014.4, Oct. 24, 1994, 94-2 CPD ¶ 149 at 4.
Notwithstanding MTU’s characterization of its protest as a
challenge to the agency’s proposed sole-source
acquisition, its protest actually is a challenge to the
agency’s decision to include the engine maintenance
element of the requirement within the larger CLS contract.
In effect, MTU maintains that the agency’s market
research‑‑and correspondingly, its advance planning--was
flawed because it failed to take cognizance of the fact
that MTU is (and, allegedly, other concerns are)
interested in, and capable of, competing separately for
the engine maintenance element of the CLS effort. MTU
therefore takes the position that the agency improperly
has included the engine maintenance element of its
requirement with the larger CLS requirement.
As noted, the record shows that, at the time it was
engaged in market research for the current requirement,
the agency contemporaneously considered whether it would
be feasible or beneficial to separately compete the engine
maintenance element under Boeing’s predecessor contract.
In this connection, the record shows that the Air Force’s
Deputy Assistant Secretary for Contracting (DASC) inquired
about the viability of acquiring engine maintenance
services through a separate contract.
The agency considered the question and responded to the
DASC’s inquiry, finding, among other things, that, because
the size of the E-4B fleet is so small (just four
aircraft), the administrative costs of separately awarding
a contract for engine maintenance would not justify any
potential benefit. In addition, the agency noted that, on
a different program for maintaining a similarly-configured
engine system separately from maintenance of the remainder
of the aircraft system, the cost for performing engine
overhauls under that contract was more than double what
the agency was paying for the same services under Boeing’s
predecessor contract. AR, exh. 7, Considerations Relating
to the Extension of the Boeing Predecessor Contract, at
1-2.[2] MTU has advanced no evidence to rebut these agency
findings.
In addition to these considerations, during the course of
the protest the agency has offered a reasonable
explanation for consolidating all of the CLS requirements
into a single contract vehicle. The agency’s program
manager explains that the small size of the fleet, coupled
with the extremely high demand for these aircraft because
of critical national security requirements, translates
into an unusually high demand for fleet readiness. The
program manager explained in an affidavit as follows:
To meet the demanding commitment of having [a] nuclear
hardened flying command post always ready for war, the
integrated Contractor Logistics Support (CLS) concept was
adopted over 30 years ago. By having an integrated CLS
concept with the prime contractor fully responsible for
the whole air vehicle (including engines), we have the
agility to fix problems on the alert jet
immediately--without additional administrative actions. If
the Government were to start breaking apart our
requirement, additional administrative delays would be
incurred as the Government mediates to get contractor “A”
to work with contractor “B” to fix a broken alert jet. The
mission risk in this scenario is unacceptable. The current
integrated CLS sustainment concept has succeeded and will
continue to succeed in meeting national security
requirements.
Affidavit of the E-4B Program Manager at 1 (emphasis in
original).
In addition, the agency’s justification and approval for
acquiring its requirement on a sole-source basis echoes
these considerations, and also details the unique
engineering and proprietary information only possessed by
Boeing that is necessary to maintain the aircraft in the
required heightened state of readiness. AR, exh. 1,
Justification and Approval, at 3-6. Inasmuch as our Office
affords considerable weight to an assertion on the part of
a military agency that a requirement is necessary to meet
critical human safety and military requirements, Coastal
Seal Servs., LLC, B-406219, Mar. 12, 2012, 2012 CPD ¶ 111
at 4, and in light of the agency’s explanation here, we
have no basis to object to the agency’s decision to
include its engine maintenance requirements within its
larger CLS requirement.
As a final matter, as discussed above, the record shows
that the agency engaged in extensive market research that
described in detail the CLS requirement. That research was
intended to assist the agency in determining whether the
overall CLS requirement was suitable for competition, as
well as determining whether the various elements
comprising the requirement were suitable for separate
competition.
Notwithstanding the agency’s extensive efforts to probe
the market for its requirements, MTU elected to remain
silent and not participate in the agency’s research.
During the course of this protest, MTU has not explained
why it elected not to participate in the agency’s market
research efforts. Thus, to the extent that MTU now
characterizes the agency’s market research conclusions as
inaccurate, the record shows that MTU itself is at least
partially responsible for the state of the agency’s
information because of its failure to participate in the
RFI process. We also conclude that the extent and duration
of the agency’s market research efforts belie any
suggestion that the agency failed to engage in adequate
advance planning.
The protest is denied. (MTU
Maintenance Canada, LTD B-411185, B-411185.2,
B-411185.3: Jun 9, 2015) (pdf)
The agency has historically satisfied its requirement for
storage of household goods and baggage through two procurements,
one for the East Coast and one for the West Coast. Guardian is
the incumbent contractor for the East Coast, which had been set
aside for small businesses. In order to explore the feasibility
of combining those procurements while maintaining them as
set-asides, the agency issued a request for information (RFI)
that was posted on the Federal Business Opportunities (FedBizOps)
website on February 28, 2014. Agency Report (AR), Exh. 7, RFI.
The agency also provided notice of the RFI posting to the
incumbent contractors and all other companies that had
previously responded to an earlier, similar announcement. AR,
Exh. 16, Market Research Report at 2.
Potential offerors were asked to respond to a series of
questions, including whether the firms considered it appropriate
to combine the requirements and whether the firms would be
interested in providing services to both coasts. Market Research
Report at 8, 23-24. Six of the seven firms that responded were
small businesses. Id. Of those six small businesses, one
(Guardian) was a HUBZone small business concern, one a
woman-owned small business, and one a small disadvantaged
business. Id. All of the respondents were interested in
providing service on both coasts, while five of the respondents
(including Guardian) stated that a single service provider would
be appropriate. Id. at 15, 30-31. According to Guardian, “[t]he
benefit of a single service provider is the cost savings to be
achieved . . . .” Id. at 30. The agency checked the System of
Award Management (SAM) to validate the vendors’ registration and
business information. The contracting officer considered these
responses and determined that, while it was unlikely that two or
more HUBZone businesses would submit proposals, it was
reasonable to expect at least two offers from small businesses.
Id. at 6-7. The agency therefore decided, with the concurrence
of the agency’s small business specialist and the Small Business
Administration (SBA), to set the procurement aside for small
businesses. See AR, Exh. 13, Small Business Coordination Record.
(sections
deleted)
Guardian also
asserts that the agency engaged in improper consolidation of
requirements in violation of the Competition in Contracting Act
of 1984 (CICA), 10 U.S.C. § 2305(a)(1) (2000). In this regard,
CICA generally requires that solicitations include
specifications which permit full and open competition and
contain restrictive provisions and conditions only to the extent
necessary to satisfy the needs of the agency. See 10 U.S.C. §§
2305(a)(1)(A), (B). Since consolidated procurements may combine
separate, multiple requirements into one contract, they have the
potential for restricting competition by excluding firms that
can furnish only a portion of the requirements. Aalco
Forwarding, Inc., et al., B-277241.12, B‑277241.13, Dec. 29,
1997, 97-2 CPD ¶ 175 at 6. In interpreting CICA, we have
assessed whether an agency has a reasonable basis for its
contention that the consolidation is required to meet its needs,
and have sustained protests only where no reasonable basis is
demonstrated. Major Contracting Services, Inc., B-406980,
October 10, 2012, 2012 CPD ¶ 288 at 4.
According to the protester, the consolidation precludes
businesses capable of performing the requirement for only one
coast from participation in the competition. Protest at 4.
However, having responded to the agency’s inquiry during its
market research by asserting that consolidation was appropriate,
and indeed would result in cost savings, Market Research Report
at 30, Guardian cannot now assert that consolidation would be
inappropriate. The integrity of the protest process does not
permit a protester to espouse one interpretation or position
during the procurement, and then argue during a protest that the
interpretation or position is unreasonable or otherwise
improper. Northrop Grumman Space and Missile Systems Corp.;
Textron Marine & Land Systems Corp., B-400837 et al., Feb. 17,
2009, 2009 CPD ¶ 52 at 10; IBM Global Bus. Servs., B‑298833.4,
B-298833.5, Mar. 1, 2007, 2007 CPD ¶ 82 at 6; Northrop Grumman
Sys. Corp., B-298954 et al., Jan. 12, 2007, 2007 CPD ¶ 63 at 8;
BST Sys., Inc., B‑298761, B-298761.2, Dec. 1, 2006, 2007 CPD ¶
62 at 6; AAI Eng’g Support Inc., B-257857, Nov. 16, 1994, 95-1
CPD ¶ 2 at 3-4. In any case, the RFP makes clear that offerors
may propose to satisfy the requirement for services on either
coast, or both coasts; it is not the case that firms capable of
performance on only a single coast are precluded from the
competition. Moreover, Guardian’s proposal offered to satisfy
the agency’s requirements for both coasts. Guardian Proposal at
2. If, in fact, the solicitation language limits competition
from other small businesses, that limitation would be to
Guardian’s benefit, not detriment. enrGies, Inc., B-408609.9,
May 21, 2014, 2014 CPD ¶ 158 at 9-10 (prejudice is an essential
element of every viable protest, and where none is shown or
otherwise evident, we will not sustain a protest, even where a
protester may have shown that an agency’s actions arguably were
improper). (Guardian Moving &
Storage Co., Inc., B-410171: Nov 6, 2014) (pdf)
As an initial
matter, ACM argues that the solicitation constitutes
impermissible bundling under the Small Business Act, 15 U.S.C. §
631, in that the agency is bundling the work performed under 27
different manufacturer pricing agreements, 15 of which are
currently with small businesses, into one contract for each lot.
Protest at 12.
The Small Business Act, as amended, states that, “to the maximum
extent practicable,” each agency shall “avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors.” 15 U.S.C. § 631(j)(3) (2013). Bundling, for
purposes of the Small Business Act, means “consolidating 2 or
more procurement requirements for goods or services previously
provided or performed under separate smaller contracts into a
solicitation of offers for a single contract that is likely to
be unsuitable for award to a small-business concern.” 15 U.S.C.
§ 632(o)(2); see Federal Acquisition Regulation (FAR) § 2.101.
The term “separate smaller contract” is defined as “a contract
that has been performed by 1 or more small business concerns or
was suitable for award to 1 or more small business concerns.” 15
U.S.C. § 632(o)(3); FAR § 2.101.
ACM argues that the manufacturer pricing agreements that DLA
established with various beef manufacturers, several of which
are small businesses, constituted the “separate smaller
contracts” under the Small Business Act; thus, according to the
protester, the solicitation bundles several procurement
requirements that were previously provided under smaller
contracts by a small business. Protest at 7-8. However, we agree
with the agency that the Lot 2 requirements do not constitute
bundling, as defined by the Small Business Act. As relevant
here, the term “separate smaller contract” is defined as “a
contract that . . . was suitable for award to 1 or more small
business concerns.” 15 U.S.C. § 632(o)(3); FAR § 2.101. Here,
however, DLA previously satisfied its requirements for ground
beef and primal cuts through contracts with multiple prime
vendors, which are not small businesses, AR at 8, 12; under the
RFP, the beef items will be extracted from the prime vendor
contracts, and the prime vendors will be directed to place beef
item orders under the appropriate contract to be awarded under
the RFP. Thus, combining items from several prime vendor
contracts into one contract does not result in a contract that
has previously been performed by one or more small business
concerns or was suitable for award to one or more small business
concerns. Star Food Service, Inc., B‑408535, Nov. 1, 2013, 2013
CPD ¶ 246 at 3 (no improper bundling under Small Business Act
where requirement for chicken parts was previously provided by
prime vendors and not under separate smaller contracts that were
suitable for award to small business concerns). In these
circumstances, we find that ACM has furnished no basis for
concluding that the solicitation constitutes impermissible
bundling under the Small Business Act. (American
Custom Meats, LLC, B-409564: Jun 12, 2014) (pdf)
The protesters
contend that GSA failed to reasonably consider the economic
effect on small businesses that would result from the award of
the OS3 contracts. The protesters argue that despite the
requirements in the SB Jobs Act that GSA “identif[y] any
negative impact by the acquisition strategy on contracting with
small business concerns,” the agency failed to give any
consideration to the economic consequences of the OS3 program on
small businesses. The protesters note that while there are
several hundred office supply vendors currently on GSA MAS No.
75 for office supplies, this solicitation anticipates the award
of approximately 24 contracts. The protesters argue that the
companies that are not awarded contracts “are effectively locked
out of business with the government.” American Toner Protest at
1. Therefore the protester requests an “accurate economic
analysis of the consequences for small businesses, prior to the
acceptance of [proposals] for this solicitation.” Id. Similarly,
SBA joins the protesters in arguing that GSA’s consolidation
analysis did not adequately or meaningfully address the
requirements of the SB Jobs Act. For the reasons discussed
below, we conclude that GSA’s consolidation analysis was
reasonable.
Section 1313 of the SB Jobs Act requires agencies to consider
the effect of contract consolidation on small businesses for
procurements over $2 million. 15 U.S.C. § 657q(c). Consolidation
means the use of a solicitation to obtain offers for a single
contract or a multiple award contract:
(A) to satisfy 2 or more requirements of the Federal agency for
goods or services that have been provided to or performed for
the Federal agency under 2 or more separate contracts lower in
cost than the total cost of the contract for which the offers
are solicited; or
(B) to satisfy requirements of the Federal agency for
construction projects to be performed at 2 or more discrete
sites[.]
Id. § 657q(a).
The SB Jobs Act does not preclude agencies from consolidating
requirements. The Act states, however, that an agency may not
use an acquisition strategy that consolidates contract
requirements with a total value of more than $2 million unless
the agency’s senior procurement executive or chief acquisition
officer takes the following actions:
(A) conducts market research;
(B) identifies any alternative contracting approaches that would
involve a lesser degree of consolidation of contract
requirements;
(C) makes a written determination that the consolidation of
contract requirements is necessary and justified;
(D) identifies any negative impact by the acquisition strategy
on contracting with small business concerns; and
(E) ensures that steps will be taken to include small business
concerns in the acquisition strategy.
Id. § 657q(c)(1). In addition, the senior procurement executive
or chief acquisition officer must make a determination that the
consolidation is “necessary and justified” and that “the
benefits of the acquisition strategy substantially exceed the
benefits of each of the possible alternative contracting
approaches” identified by the agency. Id. § 657q(c)(1), (2).
Our Office has addressed the bundling or consolidation of
contract requirements with regard to the Small Business Act, 15
U.S.C. § 631(j)(3), and the Competition in Contracting Act of
1984 (CICA), 41 U.S.C. § 3306(a)(2)(B). Because bundled or
consolidated procurements combine separate and multiple
requirements into one contract, they have the potential for
restricting competition by excluding firms that furnish only a
portion of the requirement; we therefore review challenges to
such solicitations to determine whether the approach is
reasonably required to satisfy the agency’s needs. 2B Brokers et
al., B-298651, Nov. 27, 2006, 2006 CPD ¶ 178 at 9. We have
recognized that bundling may serve to meet an agency’s needs
where the agency reasonably determines that consolidation will
result in significant cost savings or operational efficiencies.
Id.; Teximara, Inc., B‑293221.2, July 9, 2004, 2004 CPD ¶ 151 at
6.
Although our Office has not previously addressed the
consolidation analysis requirements under the SB Jobs Act, we
conclude that the statute requires an inquiry similar to that
set forth in our decisions concerning consolidation or bundling
under the Small Business Act and CICA. Specifically, we will
look to whether GSA has conducted market research, and has
reasonably found that the consolidation is “necessary and
justified,” and that the benefits “substantially exceed” those
of other contracting approaches. See 15 U.S.C. § 657(q)(c)(2).
As discussed above, prior to the issuance of the RFP, GSA
prepared a consolidation analysis, which was signed by its
senior procurement executive. This analysis concluded that the
benefits of the consolidation approach under the OS3 program
outweigh the potential negative impact to small business
concerns. AR, Tab 2, Consolidation Analysis, at 7‑11. The agency
contends that it “gave careful consideration to increasing small
business concerns’ ability to participate in this solicitation
and specifically chose to solicit this as a full and open
competition to get the widest small business participation
possible.” Supp. AR at 2.
As discussed in the consolidation analysis, GSA found that
although government-wide purchasing through MAS schedule No. 75
has worked well for many years, the growth of that contract
vehicle has resulted in scattered purchases and a wide range of
prices for similar items. AR, Tab 2, Consolidation Analysis, at
3. To support its approach of using a non-MAS contract vehicle,
GSA conducted market research and outreach to industry. Id. The
market research found that small office supply providers often
specialize within an office supply sub-segment, as opposed to
offering the full range of office supplies. Id. at 3, 7. In the
consolidation analysis, GSA states that it took “active steps”
to include small businesses in the OS3 acquisition strategy by
engaging with the industry through the GSA’s Interact web blog
site, and sponsoring one-on-one listening sessions with small
businesses to gather information. Id. at 1. GSA also states that
it hosted an “OS3 Listen to Industry Day” event to solicit
feedback to the OS3 solicitation and engage in an “open and
transparent dialogue” with the industry. Id. at 5.
GSA stated that it anticipates “very substantial benefits” from
the OS3 consolidation, such as part number standardization to
enable smart shopping, better terms and conditions, reduced
cycle time, and improvements for the needs of the federal
employee. Id. at 10. The agency estimated that this
consolidation would result in a savings of 18 percent, as
compared to alternative procurement approaches that did not
involve consolidation. Id. at 8, 10.
GSA’s analysis also addressed the negative impact of the
potential reduction in sales for small businesses not chosen as
OS3 CLIN providers, but “determined the benefits to be gained
through OS3 CLINs will outweigh this negative impact.” Id. To
increase small business participation, and in response to the
results of the market research described above, the agency
divided the contract requirements into four separate CLINs of
office supply products. These CLINS were intended to be broad
enough to allow for adequate sales volume to drive pricing
discounts, and narrow enough to ensure small businesses are not
excluded. Id. at 7. GSA states that to increase small business
awards that it anticipates that “[a]t least 95%” of the awards
will be made to small businesses. Id. In this regard, the
solicitation expresses a “significant preference” for small
businesses. RFP, SOW, at 2. Although the RFP does not explain in
detail the term “significant preference,” neither the protesters
nor SBA dispute GSA’s expectation that 23 of 24 contracts will
be awarded to small businesses. The agency further notes that
the OS3 contracts will not be mandatory, and that small business
vendors who have MAS contracts will still be eligible to receive
orders under those contracts. AR at 4.
GSA states that it also considered other contracting approaches
that would result in less consolidation of the contract
requirements, such as establishing single-agency contracts,
placing orders against existing MAS contracts, and full-and-open
single-award contracts. AR, Tab 2, Consolidation Analysis, at 8.
The agency concluded that these alternative approaches would
have yielded less in savings than the estimated 18 percent
savings benefit that is estimated for under the OS3 program. Id.
The protesters generally contend that GSA has failed to give
adequate consideration to the economic consequences of the OS3
procurement. In particular, Dolphin Blue and Capital Shredder
contend that GSA should be required to conduct a cost-benefit
analysis to specifically quantify the economic impact on small
businesses that would result from the OS3 procurement approach.
Dolphin Blue’s Supp. Comments at 3; Capital Shredder Comments at
2.
Similarly, in a brief submitted in support of the protesters,
SBA argues that GSA was required to perform “some type of data
analysis” of the potential impact by OS3 on the federal
government’s small business suppliers. SBA Comments (Apr. 3,
2014) at 7. Although SBA acknowledges that the SB Jobs Act
requires an agency’s consolidation analysis to “identif[y] any
negative impact by the acquisition strategy on contracting with
small business concerns,” 15 U.S.C. § 657q(c)(1)(D), the agency
contends that the statute should be interpreted to require “some
type of data analysis” to justify the consolidation. SBA
Comments (Apr. 3, 2014) at 7. With regard to GSA’s analysis, SBA
argues that GSA’s assessment of the effect of consolidation on
small businesses was “perfunctory” and lacked concrete data or
analysis. SBA Comments (Apr. 11, 2014) at 3.
We find that GSA met the requirement under the Small Business
Jobs Act to perform an analysis addressing whether the benefits
of the consolidation acquisition strategy “substantially exceed”
the benefits of each of the possible alternative contracting
approaches. 15 U.S.C § 657q(c)(2)(A). While the protesters and
SBA argue that the SB Jobs Act requires a more detailed or
quantified cost-benefit analysis to justify the agency’s
solicitation approach, we do not find such a requirement in the
Act. Instead, as discussed above, the SB Jobs Act requires
agencies to: conduct market research; identify potential
alternative contracting approaches that involve lesser degrees
of consolidation; issue a written determination in support of
the consolidation; identify negative impacts on small
businesses; and ensure that steps will be taken to include small
business concerns in the acquisition strategy. 15 U.S.C. §
657q(c)(1).
As discussed above, GSA conducted market research and considered
alternatives to the procurement approach set forth in the
solicitation. Further, the agency prepared a consolidation
analysis which recognized that there was a potential for a
reduction in sales for small business contractors who did not
receive awards under the OS3 solicitation. AR, Tab 2,
Consolidation Analysis, at 7. The agency concluded, however,
that the benefits to be gained through OS3 outweigh the
potential negative impact to small business concerns. Id. at
7-11. We find that GSA’s analysis addressed the relevant
requirements of the SB Jobs Act, and therefore find no basis to
sustain the protest. (American
Toner & Ink; KPaul Properties, LLC; Dolphin Blue, Inc.;
Capital Shredder Corp., B-409528.7, B-409528.11,
B-409528.14, B-409528.18: Jun 9, 2014) (pdf)
Star complains
that the RFP’s aggregation of 24 chicken parts (such as breasts,
thighs, or tenderloins, and processed chicken products like
nuggets, strips, or patties) in Lot 2 constitutes an
unreasonable bundling and consolidation, as defined by FAR §
2.101 and DFARS § 207.170-2. Protest at 2. Specifically, Star
argues that the RFP’s requirements are not new, and that DLA
unreasonably bundled the Lot 2 chicken parts that were
previously provided under the 13 prime vendor contracts into a
single contract in violation of the Small Business Act. Comments
at 2-3. Star also argues that bundling the Lot 2 requirements is
unduly restrictive of competition and violates CICA. As
discussed below, we deny Star’s protest that the RFP’s Lot 2
requirements violate the bundling requirements of the Small
Business Act and dismiss as untimely Star’s complaint that that
RFP otherwise violates CICA.
The Small Business Act, as amended, states that, “to the maximum
extent practicable,” each agency shall “avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors.” 15 U.S.C. § 631(j)(3) (2013). Bundling, for
purposes of the Small Business Act, means “consolidating 2 or
more procurement requirements for goods or services previously
provided or performed under separate smaller contracts into a
solicitation of offers for a single contract that is likely to
be unsuitable for award to a small-business concern.” See 15
U.S.C. § 632(o)(2); see also FAR § 2.101; DFARS § 201.170-2. The
term “separate smaller contract” is defined as “a contract that
has been performed by 1 or more small business concerns or was
suitable for award to 1 or more small business concerns.” 15
U.S.C. § 632(o)(3); FAR § 2.101.
Here, DLA explains that the RFP’s Lot 2 requirements for various
chicken parts does not constitute bundling or consolidation
under the Small Business Act, because the agency does not
currently procure chicken parts directly through separate
contracts. That is, DLA’s requirements for chicken parts are now
satisfied under the prime vendor contracts, where the prime
vendors procure the chicken parts directly from chicken
suppliers under pricing established under manufacturer pricing
agreements. DLA also states that the prime vendor contracts will
not be eliminated as a result of the new acquisition strategy.
Under the RFP, DLA will contract directly with chicken
suppliers, and the prime vendors will obtain the chicken parts
through DLA’s contracts with the chicken suppliers. AR at 5-6.
We agree with the agency that the RFP Lot 2 requirements do not
constitute bundling, as defined by the Small Business Act,
because DLA is not consolidating requirements that were
previously provided under separate contracts into a solicitation
for a single contract. Here, DLA extracted the chicken parts
requirement from multiple prime vendor contracts and combined
them into a single contract, from which the prime vendors will
meet the requirements for their regions. With respect to Star’s
argument that the prime vendor contracts are the relevant
separate small contracts referred to in the definition of
bundling, Comments at 2, Star misinterprets the meaning of the
Small Business Act provision. As relevant here, the term
“separate smaller contract” is defined as “a contract that . . .
was suitable for award to 1 or more small business concerns.” 15
U.S.C. § 632(o)(3); FAR § 2.101. The prior contracts relevant to
this analysis are the prime vendor contracts, which Star
acknowledges are being performed by large businesses. See
Protest, Exhib. A, Agency-Level Protest, at 11. Thus, although
Star contends that small businesses were capable of providing
chicken parts--and indeed, were providing chicken parts under
subcontracts to the prime vendors, Star has not established that
the prime vendor contracts were suitable for award to 1 or more
small businesses. See Vox Optima, LLC, B-400451, Nov. 12, 2008,
2008 CPD ¶ 212 at 3.
With respect to Star’s argument that the consolidation of the
RFP’s Lot 2 requirements otherwise violates DFARS § 207.170-2,
this section defines “[c]onsolidation of contract requirements”
as “the use of a solicitation to obtain offers for a single
contract or a multiple award contract to satisfy two or more
requirements of a department, agency, or activity for supplies
or services that previously have been provided to, or performed
for, that department, agency, or activity under two or more
separate contracts.” For the reasons discussed above, we find
that the Lot 2 requirements do not constitute consolidation as
defined in DFARS § 207.170-2 because the chicken parts were not
previously procured by DLA under two or more separate contracts.
Star also argues that awarding a single contract for the Lot 2
requirements constitutes an undue restriction upon competition
in violation of CICA. Protest at 2; Comments at 1. We find that
this ground of protest is untimely.
Our Bid Protest Regulations provide that where, as here, a
protest has been initially filed with the contracting agency we
will consider a subsequent protest if the initial protest with
the agency was timely filed. 4 C.F.R. § 21.2(a)(3) (2013).
Because our regulations do not provide for the unwarranted
piecemeal presentation of protest issues, where a protester
initially files a timely agency-level protest, and subsequently
files a protest with our Office which includes additional
grounds, the additional grounds must independently satisfy our
timeliness requirements. MediaNow, Inc., B-405067, June 28,
2011, 2011 CPD ¶ 133 at 2; ABF Freight Sys., Inc.; Old Dominion
Freight Line, Inc; Overnite Transp. Co.; Roadway Express, Inc.;
and Yellow Freight Sys., Inc., B-291185, Nov. 8, 2002, 2002 CPD
¶ 201 at 7.
Here, Star argued in its agency-level protest that the RFP’s Lot
2 requirements constituted unlawful bundling as defined by FAR §
2.101 (which implements the Small Business Act bundling
requirements) and unlawful consolidation as defined by DFARS §
207.170-2. Protest, Exhib. A, Agency-Level Protest, May 31,
2013, at 10-12. Star did not contend in its agency-level protest
that the RFP Lot 2 requirements constituted an undue restriction
of competition in violation of CICA. Rather, these arguments
were first made in its protest to our Office on July 12, nine
days after the closing date for receipt of proposals. To be
timely, this challenge to the terms of the solicitation was
required to be filed before the closing time for receipt of
proposals, but was not. See 4 C.F.R. § 21.2(a)(1). (Star
Food Service, Inc. B-408535, Nov 1, 2013) (pdf)
MCS, a portable
latrine contractor, alleges that most portable latrine
contractors do not service permanent latrines/septic tanks, that
portable and permanent latrine services are separate industries
requiring specialized equipment and personnel, and that
consolidating the requirements in this RFP is restrictive of
competition in violation of CICA.
CICA generally requires that solicitations permit full and open
competition and contain restrictive provisions and conditions
only to the extent “necessary to satisfy the needs of the
executive agency.” 10 U.S.C. § 2305(a)(1)(A) (2006). Since
consolidated or “bundled” procurements may combine separate,
multiple requirements into one contract, they have the potential
for restricting competition by excluding firms that can furnish
only a portion of the requirements. Aalco Forwarding, Inc., et
al., B-277241.12, B-277241.13, Dec. 29, 1997, 97-2 CPD ¶ 175 at
6. In interpreting CICA, we have assessed whether an agency has
a reasonable basis for its contention that the consolidation is
required to meet its needs, and have sustained protests only
where no reasonable basis is demonstrated. U.S. Electrodynamics,
Inc., B-403516, B-403516.2, Nov. 12, 2010, 2010 CPD ¶ 275 at 9;
2B Brokers et al., B-298651, Nov. 27, 2006, 2006 CPD ¶ 178 at 9;
Teximara, Inc., B-293221.2, July 9, 2004, 2004 CPD ¶ 151 at 6.
We have noted that mere administrative convenience alone does
not provide a reasonable basis for restrictive competition
through consolidation of requirements, but substantial cost
savings through reduction of duplicative efforts and operational
efficiencies may provide a reasonable basis for consolidation.
See U.S. Electrodynamics, Inc., supra.
The agency identifies its overall procurement needs as
protecting the health and safety of the community through the
provision of highly reliable, effective disposal of sanitary
refuse in a cost effective and administratively efficient manner
while encouraging full and open competition among small business
concerns for the agency’s refuse disposal requirements.
Contracting Officer (CO) Statement at 7. Based on the market
research results, the agency found that combining the portable
and permanent latrine waste disposal services would
substantially reduce contract costs by avoiding duplicative
services in terms of overhead, manpower, materials and
transportation costs. In reaching this conclusion the agency
notes that approximately 63 percent of the permanent latrines
are co-located with portable latrines and that, based on the RFI
responses, the services are substantially the same, utilizing
the same personnel, skills, and equipment. Id. at 6, 8. Further,
the agency determined that combining these requirements under
one contract would reduce the agency’s administrative costs by
eliminating the costs associated with conducting and overseeing
separate acquisitions, as well as the costs and inefficiencies
associated with performing potentially twice as many
inspections, which would only be required if the requirements
are separately procured since the majority of the portable and
permanent latrines are co-located. Id. at 8. Additionally, given
the RFI responses indicating that firms did not desire to
compete for smaller requirements, the agency was concerned that
competition for the significantly smaller permanent latrine
requirement would be limited if it was separately procured. Id.
Based on the above considerations, the agency maintains that it
was reasonably necessary to combine the portable and permanent
latrine waste disposal requirements.
The record, to include the RFI responses, confirms the agency’s
findings and the reasonableness of the agency’s decision to
combine its portable and permanent latrine disposal
requirements. As noted above, most of the contractors that
responded to the RFI expressly indicated that separating the
requirements would increase their prices, and the protester has
not challenged the factual bases for the agency’s asserted
operational savings associated with using two separate
contractors to service the portable and permanent latrines, the
majority of which are co-located. Further, as the agency points
out, the RFI responses contradict the protester’s general
assertion that separating the requirements would increase
competition among small businesses. In this regard, based on the
RFI responses, the agency was reasonably concerned that
separating the requirements could potentially decrease
competition since at least one otherwise interested small
business stated that it would not be worthwhile for the firm to
compete for the smaller, separated requirements, and another
firm pointed out that the smaller requirements would be less
financially attractive to firms located outside the geographical
area. Moreover, notwithstanding the protester’s assertions to
the contrary, the results of the agency’s market research do not
reflect a need for different specialized equipment or personnel
when performing the portable latrine waste disposal services as
compared with the permanent latrine disposal services. As the
agency reasonably found, the RFI responses uniformly indicate
that the services are substantially similar.
Although the protester ultimately disagrees with the agency’s
conclusion that procuring the portable and permanent latrine
waste disposal services on a combined basis is reasonably
necessary to meet its needs, and believes that the agency should
not have relied on the market research results because, in the
protester’s view, the RFI responses do not accurately reflect
the industry, it has not shown that the agency’s findings of
cost savings, operational efficiencies, and the potential for
enhanced competition, were unreasonable. See U.S.
Electrodynamics, Inc., supra. Accordingly, we have no basis to
question the propriety of the agency’s decision to procure, on a
combined basis, the portable and permanent latrine disposal
services at issue. (Major
Contracting Services, Inc., B-406980, Oct 10, 2012) (pdf)
First, CYIOS
contends that the agency’s consolidation of the requirements
constitutes “unnecessary and unjustified” contract bundling.
CYIOS asserts that it is the “incumbent small business concern”
performing some of the services that are being consolidated, and
that the Army “has provided no justification for its decision”
to consolidate the requirements. In this regard, CYIOS asserts
that the consolidation violates the provisions of the Small
Business Act and the Competition in Contracting Act of 1984 (CICA),
along with their applicable implementing regulations. Protest at
2-5.
The Small Business Act, as amended, states that, “to the maximum
extent practicable,” each agency shall “avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors.” 15 U.S.C. § 631(j)(3) (2012). Bundling, for
purposes of the Small Business Act, means “consolidating 2 or
more procurement requirements for goods or services previously
provided or performed under separate smaller contracts into a
solicitation of offers for a single contract that is likely to
be unsuitable for award to a small-business concern.” 15 U.S.C.
§ 632(o)(2). The term “separate smaller contract” is defined as
“a contract that has been performed by 1 or more small business
concerns or was suitable for award to 1 or more small business
concerns.” 15 U.S.C. § 632(o)(3); FAR § 2.101.
Because bundled or consolidated procurements combine separate
and multiple requirements into one contract, they have the
potential for restricting competition by excluding firms that
furnish only a portion of the requirement; we therefore review
challenges to such solicitations to determine whether the
approach is reasonably required to satisfy the agency’s needs.
2B Brokers et al., B-298651, Nov. 27, 2006, 2006 CPD ¶ 178 at 9.
We have recognized that bundling may serve to meet an agency’s
needs where the agency reasonably determines that consolidation
will result in significant cost savings or operational
efficiencies. Id.; Teximara, Inc., B-293221.2, July 9, 2004,
2004 CPD ¶ 151 at 6.
Under the Small Business Act, an agency may determine that
consolidation of requirements is “necessary and justified” if,
as compared to the benefits that would be derived from
contracting to meet those requirements if not consolidated, the
government would derive “benefits, including any combination of
benefits that . . . are measurably substantial.” 15 U.S.C. §
644(e)(2)(B); 2B Brokers et al., supra, at 6. The FAR states in
pertinent part that:
[m]easurably substantial benefits may include, individually or
in any combination or aggregate, cost savings or price
reduction, quality improvements that will save time or improve
or enhance performance or efficiency, reduction in acquisition
cycle times, better terms and conditions, and any other
benefits. The agency must quantify the identified benefits and
explain how their impact would be measurably substantial. Except
as provided in paragraph (d) of this section, the agency may
determine bundling to be necessary and justified if, as compared
to the benefits that it would derive from contracting to meet
those requirements if not bundled, it would derive measurably
substantial benefits equivalent to
(1) Ten percent of the estimated contract or order value
(including options) if the value is $94 million or less. . . .
FAR § 7.107(b)(2).
As discussed above, the agency performed an analysis regarding
the benefits to be obtained by consolidation. Among other
things, the agency determined that transitioning to a single
contractor will result in improved IT support, operational
efficiencies, increased task coordination, better
accountability, more effective contractor incentives and cost
savings. AR, Tab 6, DISA D&F, at 3, 5-7. With regard to cost
savings, the agency specifically calculated savings of
$5,421,753, which reflect “approximate[ly] 18%-19% cost savings
when compared to overall contract value and historical cost
trends. . . .” Id. at 6. DISA explains that these projected
savings are the result of the “elimination of redundant
program/project management and administrative support,” as well
as a reduction of certain technical staff. Id.
In its comments responding to the agency report, CYIOS has not
meaningfully challenged any aspect of the agency’s analysis.
Specifically, CYIOS’s comments do not address the agency’s
calculation of cost savings, nor otherwise discuss the
substantial benefits the agency maintains it will obtain.
Rather, CYIOS merely asserts that the agency “has provided no
justification for its decision.”
On this record, we reject the protester’s arguments challenging
the agency’s consolidation of contract requirements. See 2B
Brokers et al., supra, at 10-11, 13 n.20 (protester has burden
of showing agency’s analysis and explanation supporting bundling
are unreasonable); Teximara, supra, at 7, 9 (protester failed to
dispute that significant savings and efficiencies will occur by
consolidating tasks). CYIOS’s protest alleging that the agency
has engaged in improper bundling is denied. (CYIOS,
Inc., B-402728.3, Jul 13, 2012) (pdf)
Consolidation of
Requirements
As noted above, between December 2006 and November 2010, the Air
Force investigated the consolidation of logistics support
requirements for the C-20 and C-37 aircraft. See, e.g.,
www.fbo.gov, Special Notice, Dec. 20, 2006; Sources Sought
Notice, Nov. 9, 2010. The agency sent RFIs to potential
contractors asking their views as to possible cost savings or
operational efficiencies that could be achieved by
consolidating. The agency also conducted its own economic
analysis to consider possible benefits of consolidating the
requirements. See AR, Tab 8.1, Economic Analysis. From the RFI
responses it received and its own analysis, the Air Force found
that consolidation of these requirements would achieve
significant cost savings and operational efficiencies. For
example, the Air Force found that it would save more than
$[Deleted] million by consolidating the requirements. See AR,
Tab 8, Consolidation D&F, at 5. The agency also found that
consolidation would result in significant operational
efficiencies through a streamlined and centrally controlled
inventory system, centralized depot scheduling, and increased
field maintenance capabilities. Id. at 5-6; see also AR at
65-66. The Air Force also considered whether comparable benefits
could be achieved under other alternative contracting
approaches, including the approach advocated by Northrop Grumman
in its protest (that is, award separate contracts for the
aircraft). The Air Force concluded that none of these other
approaches would provide the same level of cost savings or
operational efficiencies. See AR, Tab 8.1, Economic Analysis, at
14.
The Competition in Contracting Act of 1984 (CICA) requires that
solicitations generally permit full and open competition and
contain restrictive provisions only to the extent necessary to
satisfy the needs of the agency. 10 U.S.C. § 2305(a)(1)(B)(ii)
(2006). Because bundled or consolidated procurements combine
separate and multiple requirements into one contract, they have
the potential for restricting competition by excluding firms
that furnish only a portion of the requirement; we therefore
review challenges to such solicitations to determine whether the
approach is reasonably required to satisfy the agency’s needs.
See 2B Brokers et al., B-298651, Nov. 27, 2006, 2006 CPD ¶ 178
at 9; Pemco Aeroplex, Inc., B-280397, Sept. 25, 1998, 98-2 CPD ¶
79 at 8-9. An agency may consolidate or bundle requirements
where the agency reasonably determines that consolidation will
result in significant cost savings or efficiencies. B.H.
Aircraft Co., Inc., B-295399.2, July 25, 2005, 2005 CPD ¶ 138 at
7.
Here, the record supports the agency’s determination that
consolidation of the logistics support requirements for the C-20
and C-37 aircraft will result in significant cost savings and
operational efficiencies. Although Northrop Grumman believes
that these requirements should not be consolidated, it does not
show, or even argue, that the Air Force will not achieve the
substantial cost savings and significant operational
efficiencies identified by the agency in its market research and
economic analysis. As a result, we see no basis for concluding
that the Air Force’s approach unreasonably consolidated these
requirements. (Northrop Grumman
Technical Services, Inc., B-406523, Jun 22, 2012) (pdf)
BlueStar first
contends that the full and open portion of the procurement
improperly bundles six federal accounts in violation of the
Small Business Act, 15 U.S.C. sect. 631(j)(3) (2009).
The Small Business Act requires that "federal agencies, to the
maximum extent practicable, shall avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors." Id. In addition, the Act defines bundling as
follows:
bundling of contract requirements means consolidating 2 or more
procurement requirements for goods or services previously
provided or performed under separate smaller contracts [that is,
contracts being performed by a small business concern or
suitable for award to a small business concern] into a
solicitation of offers for a single contract that is likely to
be unsuitable for award to a small business concern.15 U.S.C.
sect. 632(o)(2)(3); see Federal Acquisition Regulation (FAR)
sect. 2.101.
The agency explains that the seven accounts in the current
solicitation have been included in a single contract requirement
"since electric deregulation began in the ComEd service
territory 7 to 8 years ago." Contracting Officer's Statement at
1. Thus, we agree with GSA that this solicitation did not
constitute "bundling," as defined by the Small Business Act,
because GSA has not consolidated separate smaller contracts into
a single contract. See Outdoor Venture Corp.; Applied Cos.,
B-299675, B-299676, July 19, 2007, 2007 CPD para. 138 at 3 (no
bundling where all requirements already procured as a single
system). While BlueStar argues that the bundling rules should be
applicable because these requirements should not have been
consolidated in the Pepco contract, this provides no basis to
challenge the current solicitation, which did not consolidate
separate small contracts. (BlueStar
Energy Solutions, B-405690, December 12, 2011) (pdf)
Vox argues that
the RFP impermissibly bundles several separate requirements that
could be performed by small businesses if the agency solicited
them separately. According to the protester, it has been
providing services to CHINFO in the areas of speechwriting and
executive communications for the agency’s senior personnel,
long-term strategic communications planning and time and
event-based tactical planning, large-scale trade show planning,
custom publishing, writing and editing, video and multimedia
production, and internal and external program promotion. The
protester asserts that these services are being solicited under
sections 2.1, 2.3 and 5.3 of the RFP’s performance work
statement, but are impermissibly bundled with a host of other
services. Vox, a service-disabled, veteran-owned small business,
concludes that, since it previously provided these services, it
is improper under the requirements of the Small Business Act for
the agency to bundle these requirements with the other
requirements of the RFP. (The protester also maintains that
there are three other small business contracts for work that is
subsumed under the current solicitation.)
The agency responds that this is a new requirement for which it
has not previously contracted, either with a small or a large
business. In this connection, the agency notes that, although it
has acquired certain limited services from the protester, it did
so through a task order issued against a contract held by a
different concern, the Cynergy Group of Baltimore, with which
the protester has a subcontract. The agency also points out that
the contract with Cynergy was entered into between the company
and another Naval procuring activity, the Naval Sea Systems
Command (NAVSEA). Moreover, according to the agency, while the
solicitation includes a variety of individual tasks that might
be required, the overarching requirement is for integrated use
of the individual tasks together in connection with the agency’s
overall requirement, which is for integrated, and at times
worldwide, public affairs campaigns.
We find no merit to this aspect of Vox’s protest. The Small
Business Reauthorization Act of 1997, Pub. L. No. 105‑135, 111
Stat. 2592, 2617‑20 (1997), amended the Small Business Act and
provided that, “to the maximum extent practicable,” each agency
shall “avoid unnecessary and unjustified bundling of contract
requirements that precludes small business participation in
procurements as prime contractors.” 15 U.S.C. sect. 631(j)(3)
(2000). Bundling, for purposes of the Small Business Act, as
amended, means “consolidating 2 or more requirements for goods
or services previously provided or performed under separate
smaller contracts into a solicitation of offers for a single
contract that is likely to be unsuitable for award to a
small-business concern.” 15 U.S.C. sect. 632(o)(2); see Federal
Acquisition Regulation (FAR) sect. 2.101, “separate smaller
contract” is defined as “a contract that has been performed by 1
or more small business concerns or was suitable for award to 1
or more small business concerns.” 15 U.S.C. sect. 632(o)(3); see
FAR sect. 2.101.
The record does not support the protester’s assertion that the
agency has bundled two or more requirements that previously have
been acquired from small businesses under smaller, separate
contracts. Two of the contract actions identified by the
protester--Cynergy’s task order under its NAVSEA contract, under
which Vox performed as a subcontractor, and work performed by a
second subcontractor under that same task order--were under a
contract executed by an entirely different activity (NAVSEA),
and the protester has submitted no evidence to show that the
NAVSEA contract is for requirements similar to the requirements
being solicited for CHINFO under the current RFP. Accordingly
there is no basis for us to find that the earlier work performed
by Vox and the other Cynergy subcontractor constituted separate,
smaller contracts previously entered into by CHINFO with small
businesses. AR, exh. 15.
The third contract action identified by the protester is a
contract that was entered into between a Department of Defense
contracting activity (as opposed to CHINFO) and was for
performance of computer programming work, as opposed to public
affairs work. Agency Letter, Sept. 25, 2008, attach. 3-7. As
with the task order discussed above, this is a contract with a
different contracting activity for work not contemplated under
the current solicitation, and it therefore cannot be
characterized as a smaller, separate contract entered into by
CHINFO for services included under the subject RFP. Finally, Vox
has identified a request for quotations that currently is being
competed that requires the preparation and publication of a DVD
that the agency must submit to Congress. However, this cannot be
said to be an earlier, smaller, contract previously entered into
by the contracting activity, inasmuch as it is a solicitation
for a future requirement.
In sum, we conclude that the current solicitation does not
combine two or more smaller requirements for which the agency
had previously entered into contracts with small businesses.
Accordingly, the RFP is not inconsistent with the Small Business
Act requirements regarding bundling. See USA Info. Sys., Inc.,
B-291417, Dec. 30, 2002, 2002 CPD para. 224 at 3. (Vox
Optima, LLC, B-400451, November 12, 2008) (pdf)
1. Measurably Substantial Benefits
NEI argues that the Coast Guard’s bundling analysis is flawed in
several respects. The protester first argues that the Coast
Guard’s reliance on the Navy’s bundling justification is not
reasonable because the Coast Guard did not adequately explain
why it can expect the same efficiencies for the WHEC cutters the
Navy claimed for its destroyers. The protester further argues
that the Coast Guard unreasonably assumes that it will
experience the same level of savings as the Navy, and thus the
assumption of a similar 5.29 percent savings is not reasonable.
Our review of the Coast Guard analysis shows that the agency
does not directly compare the details of its maintenance and
repair operations to the Navy’s operations. Instead, the
analysis focuses on the benefits of adopting the phased
maintenance model to address inefficiencies in the current
practice of making single-contract awards. See AR, Tab 27,
Bundling Analysis, at 3-4. Based on our review, we think the
Coast Guard’s approach of identifying similar problems and
adopting similar solutions to those identified and adopted by
the Navy, was reasonable. Furthermore, the Coast Guard’s
analysis did not assume, as the protester argues, that the same
precise savings will result. Rather, the analysis relied on the
combination of the projected cost savings as well as other
benefits, discussed below, to conclude that the overall benefit
to the government would exceed 10 percent of the value of the
contract. See id. at 4. On this record, we believe that the
Coast Guard’s reliance on the Navy data was reasonable.
Next, NEI argues that the Coast Guard’s use of the Navy’s data
resulted in a double counting of “savings” by relying on both
the 5.29 percent cost savings and the 18 percent reduction in
the length of maintenance availabilities. The protester
correctly notes that the Navy’s justification relied on the 18
percent reduction in the length of maintenance availabilities as
a contributing factor to the overall 5.29 percent cost savings,
and argues that it would not be appropriate to conclude that a
transition by the Coast Guard to the phased maintenance model
would result in both a 5.29 percent cost savings plus an
additional 18 percent cost savings. The Coast Guard’s
justification did not, however, rely on the Navy’s data in this
way. Instead, as discussed below, while the 18 percent reduction
in maintenance time was a component of the 5.29 percent cost
savings for the Navy, it was also separately relied upon by the
Coast Guard as a basis to conclude that the WHEC cutters would
be available for more operational time. The Navy’s bundling
justification for the destroyers did not attempt to quantify the
benefit to the government from having additional operational
time for the ships as a result of the decreased length of
maintenance availabilities. Instead, the 18 percent savings in
the Navy’s analysis represented costs saved by avoiding 2 weeks
of maintenance costs; these savings were thus a component of the
overall 5.29 percent savings anticipated by the Navy. See AR,
Tab 22, Navy Small Business Justification, at 17. The
Coast Guard, however, chose to use the Navy’s data to quantify
an additional benefit to the government from the increased
operational time for the WHEC cutters. The Coast Guard’s
analysis notes that although the Navy was “reluctant to quantify
the benefits of returning a ship to operational status sooner,”
the agency believed that “the benefits to [the] Coast Guard of
increasing the available operational time for WHEC’s can be
quantified.” CO Statement para. 46. In this regard, the
intention of the new acquisition strategy was based on the
“central goal of reducing the period of time for performance of
maintenance tasks,” and thereby increasing “the number of days
that the WHEC’s are available to perform national defense and
homeland security missions.” Id. Thus, this benefit, although
quantified, was not a calculation of “cost savings.” Put
differently, the Coast Guard’s justification relied on two
different benefits to the government: decreased maintenance and
repair costs (quantified as a savings of 5.29 percent), and
increased time that the WHEC cutters will be performing their
duties (18 percent more time). The Coast Guard’s
identification of two benefits is consistent with the FAR, which
states that measurably substantial benefits “may include,
individually or in any combination or aggregate, cost savings or
price reduction, quality improvements that will save time or
improve or enhance performance or efficiency, reduction in
acquisition cycle times, better terms and conditions, and any
other benefits.” FAR sect. 7.107(b). NEI’s argument thus
incorrectly characterizes the Coast Guard’s identification of
benefits as a double-counting of “anticipated savings.”
Protester’s Comments on AR at 22. The two benefits identified by
the Coast Guard are, however, distinct, and each is an
appropriate measure under the FAR. We find no basis on this
record to challenge the reasonableness of the Coast Guard’s
determination.
Finally, NEI argues that the agency inappropriately relied on
the “reimbursable” rate of $178,488 per day to quantify the
benefit to the government from increased operational time of the
WHEC cutters. COMDIST 7310.1I states that the components of the
reimbursable rate “should not be used to calculate reimbursement
for [the Federal Emergency Management Agency] and foreseeable
costs related to contracting actions,” because the rate contains
“both fixed and variable components.” AR, Tab 27, COMDIST
7310.1I, at 2. Instead, the COMDIST states that “[r]ates for
these purposes shall be promulgated separately.” Id. As noted in
the facts above, the agency did separately promulgate rates for
“variable and foreseeable costs” for the cutters of $39,384 per
day. See AR, Tab 27, Coast Guard Variable Rate FY 06 Cost
Tables, encl. 1. The Coast Guard’s bundling analysis
calculated the benefit to the government of increased
operational time for the cutters based on the full reimbursable
rate of $178,488 per day. AR, Tab 27, Bundling Analysis at 4.
However, the analysis also noted that using the lower variable
rate still results in measurably substantial benefits to the
government that justifies bundling. AR, Tab 27, Bundling
Analysis, at 3. Thus, the analysis concludes, that even the rate
of $39,384 per day yields a benefit to the government of
$2,363,040--approximately 20 percent of the estimated contract
value. Although the protester only challenges the agency’s
reliance on the $178,488 per day rate, rather than the $39,384
rate, we think that neither of these rates on their own is a
reasonable measure of the benefit to the government for 1 day of
use of a WHEC cutter. In this regard, the variable rate
represents costs that the government will avoid during a
maintenance availability, such as fuel. See CO Statement para.
48; AR, Tab 27, Coast Guard Variable Rate FY 06 Cost Tables,
encl. 1. Thus, the variable rate of $39,384 per day represents
costs avoided, rather than the increased benefit to the
government from an additional day of operation for a cutter.
During the course of this protest, the CO conceded a better
calculation of the benefit to the government is achieved by
subtracting the variable rate from the full reimbursable rate.
CO Statement para. 48. Thus, in the CO’s view, the benefit to
the government of an increased day of use for a cutter is
$178,488 per day, less the variable costs of $39,384. Id. We
think that this approach appears reasonable because it captures
the quantifiable benefit to the government from the operation of
ship, less the costs of operation. Further, this approach is
consistent with COMDIST 7310.1I, which states that the
reimbursable rate should not be used to calculate foreseeable
costs relating to contracting actions because of its inclusion
of both fixed and variable costs. AR, Tab 27, COMDIST 7310.1I,
at 2. This calculation of a benefit to the government falls
between the two calculations cited in the Coast Guard’s bundling
analysis, but in any event well exceeds 10 percent of the value
of the contract. Id.
In sum, we conclude that even if the consolidation of the dry
dock and dockside requirements constituted bundling under the
Small Business Act, the Coast Guard reasonably justified any
such bundling by identifying measurably substantial benefits to
the government from the consolidation. Even allowing for some
margin of error in adopting the Navy’s estimates, the record
supports the Coast Guard’s determination that the consolidation
of the requirements will result in measurably substantial
benefits to the government equal to at least 10 percent of the
anticipated contract value.
B. Bundling in Violation of CICA
NEI argues that even if the Coast
Guard’s approach of consolidating the maintenance and repair
services does not violate the Small Business Act’s prohibitions
on bundling, the solicitation violates CICA’s prohibition on
improperly consolidating requirements. CICA generally requires
that solicitations permit full and open competition and contain
restrictive provisions and conditions only to the extent
“necessary to satisfy the needs of the executive agency.” 41
U.S.C. sect. 253a(a)(2)(B). Since bundled or consolidated
procurements may combine separate, multiple requirements into
one contract, they have the potential for restricting
competition by excluding firms that can furnish only a portion
of the requirement. Aalco Forwarding, Inc., et al., B-277241.12,
B-277241.13, Dec. 29, 1997, 97-2 CPD para. 175 at 6. In
interpreting CICA, we have looked to see whether an agency has a
reasonable basis for its contention that bundling is required,
and we have sustained protests only where no reasonable basis is
demonstrated. Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD para. 24 at 10.
Here, the agency concluded that the combination of the dockside
and shipside maintenance and repair work will result in
measurably substantial benefits to the government. As discussed
above, we conclude that these benefits, including maintenance
and repair cost savings and increased operational time for the
WHEC cutters based on reduced duration of maintenance
availabilities, justified bundling under the Small Business Act.
In our view, these benefits also provide a reasonable basis to
justify the consolidation of the two requirements for purposes
of CICA. See Teximara, Inc., B-293221.2, July 9, 2004, 2004 CPD
para. 151 at 8-9. (Nautical
Engineering, Inc., B-309955, November 7, 2007) (pdf)
The protesters
first contend that this requirement violates the bundling
restrictions under the Small Business Act, and that the agency
failed to conduct appropriate market research to show that the
bundling was necessary; failed to reasonably justify the
bundling of requirements; and failed to timely notify the Small
Business Administration (SBA) of its decision to bundle the
requirements and provide a statement regarding its justification
for bundling. In response, the agency explains that the TMSS
routinely has been purchased as a packaged system under the
earlier DLA contract. The agency further explains that the TMSS
components cannot be purchased separately in a cost effective
manner but rather, must be procured as an integrated package.
The agency states that its market research consisted of
reviewing vendors’ literature, pamphlets, specifications, and
face-to-face briefings/meetings, as well as observing and
discussing vendors’ evolving capabilities and products at
exhibitions, symposiums, and trade shows. The agency also argues
that any challenge to bundling in this solicitation is untimely.
The Small Business Reauthorization Act of 1997, Pub. L. No.
105-135 (1997), provided that “to the maximum extent
practicable,” each agency shall “avoid unnecessary and
unjustified bundling of contract requirements that precludes
small business participation in procurements as prime
contractors.” 15 U.S.C. sect. 6319 (j)(3) (2000). Bundling, for
purposes of the Act means “consolidating 2 or more requirements
for goods or services previously provided or performed under
separate smaller contracts that is likely to be unsuitable for
award to a small-business concern.” 15 U.S.C. sect. 632(o)(2);
see FAR sect. 2.101. “Separate smaller contract . . . means a
contract that has been performed by 1 or more small business
concerns or was suitable for award to 1 or more small business
concerns.” 15 U.S.C. sect. 632(o)(3); see FAR sect. 2.101. Our
review of the record here shows that the SICPS/TMSS is currently
being purchased as a packaged system under a DLA contract with
DHS, and that the system has not been provided under separate
smaller contracts. Further, the record shows that the SBA and
the Small and Disadvantaged Business Utilization Specialist
agreed that this requirement was not suitable for award to 1 or
more small business concerns. Accordingly there is no
“consolidation” of two or more requirements in this procurement
as contemplated by the Small Business Act and the Small Business
Act requirements pertaining to bundling are therefore not
applicable here.
The protesters also argue that this solicitation represents an
improperly bundled or total package procurement in violation of
the Competition in Contracting Act of 1984 (CICA). 10 U.S.C.
sect. 2305 (a)(1) (2000). The protesters maintain that the Army
has consolidated these requirements for no reason other than
convenience, which, the protesters argue is not a sufficient
rationale for bundling. The reach of the restrictions against
total package or bundled procurements in CICA is broader than
the reach of restrictions against bundling under the Small
Business Act, Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD para. 24 at 9-10. Specifically, CICA generally requires
that solicitations include specifications which permit full and
open competition and contain restrictive provisions and
conditions only to the extent necessary to satisfy the needs of
the agency. See 10 U.S.C. sections 2305(a)(1)(A), (B). Because
procurements conducted on a bundled or total package basis can
restrict competition, we will sustain a challenge to the use of
such an approach where it is not necessary to satisfy the
agency’s needs. Better Serv., B-265751.2, Jan. 18, 1996, 96-1
CPD para. 90 at 2. The determination of a contracting agency’s
needs and the best method for accommodating them are matters
primarily within the agency’s discretion. Specialty Diving,
Inc., B-285939, Oct. 16, 2000, 2000 CPD para. 169 at 3. Of
particular relevance here, where a requirement relates to
national defense or human safety, an agency has discretion to
define the solicitation requirements to achieve not just
reasonable results, but the highest possible reliability and
effectiveness. Tucson Mobilephone, Inc., B-250389, Jan. 29,
1993, 93-1 CPD para. 79 at 5, aff’d, B-250389.2, June 21, 1993,
93-1 CPD para. 472. The Army states that the SICPS/TMSS is a
mission critical system. CO’s Rebuttal Comments at 1- 3. It is
currently fielded for troops in Iraq and Afghanistan to provide
a quick and easy way to establish temporary battlefield
communication centers. Military commanders use these centers to
issue instructions and warn soldiers of approaching dangers.
Moreover, the agency explains that untested, unsafe, or
incompatible systems could cause delays and risks. As a result,
the Army contends it needs to be certain these items will
perform as a system, rather than as a collection of separate
parts. While the protesters disagree with the Army’s need for
the proven integration and compatibility of these systems, we
think the agency has met its burden of showing a reasonable need
for buying these items as a total system. We also see nothing
unreasonable in the Army’s rejection of the protesters’
contention that the agency could enter into a separate
integration contract. The Army responds that having a separate
contract for an additional company to integrate all the separate
components would not be time or cost effective, and that the
Army would run the risk of not being able to procure enough
systems in the event of a surge requirement. (Outdoor
Venture Corporation; Applied Companies, B-299675; B-299676,
July 19, 2007) (pdf)
When a proposed acquisition involves bundled requirements,
the agency must first conduct market research to determine
whether the bundling is necessary and justified, given the
potential impact on small business participation, by
ascertaining whether the government will derive measurably
substantial benefits from the bundling and quantifying these
benefits. FAR sect. 7.107(a), (b). In addition, the agency must,
at least 30 days before issuing a solicitation, provide its
acquisition package to the SBA procurement representative for
review and also provide a statement why the (1) proposed
acquisition cannot be divided into reasonably smaller lots for
small businesses, (2) delivery schedules cannot be established
that will encourage small business participation, (3) proposed
acquisition cannot be structured so to make it likely that small
businesses can compete for the prime contract, (4) consolidated
construction project cannot be acquired as separate discrete
projects, or (5) bundling is necessary and justified. FAR sect.
19.202-1(e). Furthermore, within the same 30 days, an agency
must notify any affected incumbent small business concerns of
the Government’s intention to bundle the requirement. FAR sect.
10.001(c)(2). However, the agency argues that FAR sections
7.107(a), (b); 10.001(c)(2); and 19.202-1 do not apply to the
task orders or the BPA issued under Sverdrup’s FSS contract
because these provisions applying bundling rules to FSS
contracts were implemented after TACOM had completed the
development of its acquisition plan. The requirements that
agencies perform a bundling analysis and notify the SBA when
requirements are bundled were specifically made applicable to
BPAs and orders placed against FSS contracts by a Federal
Register notice published October 20, 2003, with an "effective
date" of October 20, 2003. 68 Fed. Reg. 60,000 (Oct. 20, 2003);
FAR sect. 8.404(a). The FAR states that "[u]nless otherwise
specified . . . FAR changes apply to solicitations issued on or
after the effective date of the change.” FAR sect. 1.108(d)(1).
Since the solicitation that led to the award of the BPA was not
issued until December 5, 2003, which was after the effective
date of the revised bundling regulations, the agency was
required to comply with these regulations, even though at the
time the Army finished its acquisition planning the regulations
had not gone into effect. The Army next argues that these FAR
bundling requirements do not apply because the SETA services
previously performed by Sigmatech were not bundled with the
other requirements and were merely a “follow on” to the Camber
contract. However, the record shows that, for the past 15 years,
the SETA services for the RSJPO have been provided by small
businesses (including Sigmatech) under AMCOM contracts. These
services were not, as the agency contends, a “follow on” to the
Camber contract previously issued by TACOM because, although
SETA services were provided under the Camber contract, this
support for the RSJPO was not provided by Camber. Even after the
RSJPO came under the control of TACOM, the Army still procured
the RSJPO services from small businesses through the AMCOM
contracts and BPAs for example, through exercising options under
the ID/IQ contract as recently as 2004 (with performance into
2005) and through the BPA issued to Sigmatech in 2004, all as
part of small business reserves. Thus, the inclusion of the
RSJPO SETA services in Sverdrup’s BPA is a consolidation of two
or more procurement requirements that were previously performed
by small businesses under separate, smaller contracts. We also
find that the procurement appears to result in a single contract
(the Sverdrup BPA and resulting task orders) that is unsuitable
for award to small businesses due to its size and the aggregate
dollar amount of the anticipated award. In this regard, the
estimated contract value is approximately $130 million over a
5‑year period and only two large businesses (and no small
businesses) responded to the RFQ that resulted in the BPA award.
We thus conclude, under these circumstances, that the
consolidation of the SETA services for the RSJPO under the
Sverdrup BPA meets the definition of bundling under the Small
Business Act. However, the record shows that the Army failed to
perform a bundling analysis as required by FAR sect. 7.107(a),
(b), or comply with the requirements of FAR sect. 19.202-1 in
providing notice of bundling to the SBA. The record further
shows that the agency failed to provide notice to Sigmatech (the
incumbent small business concern) of its intent to bundle the
requirements and thus failed to comply with FAR sect.
10.001(c)(2). We sustain the protest on these bases. (Sigmatech,
Inc., B-296401, August 10, 2005) (pdf)
Although DLA initially identified 3,431 NSNs as F404 consumable
parts to be covered under the contract, DLA has since determined
that 665 of those NSNs were already being provided under a
separate Navy PBL contract, leaving 2,766 NSNs for which the
contractor will provide logistical support services. Of those,
DLA indicates that it will source and supply 312 "mainly
competitive small business NSNs," for which General Electric
will supply only logistical support, leaving 2,454 NSNs for
which General Electric will provide logistical support,
sourcing, and supply. CO Statement at 11. The record shows that
prior to proceeding with the solicitation, DLA fulfilled its
obligation to seek the views of the Small Business
Administration (SBA), through its procurement center
representative, regarding the anticipated bundling. See 15 U.S.C.
Section 644 (2000); FAR Section 7.107. Initially the SBA
objected to the bundling as unjustified, and pursued an appeal
to reverse the bundling. Ultimately, however, the SBA withdrew
its appeal and agreed to the bundling with certain conditions
intended to promote and preserve small business participation
for these parts, which were memorialized in writing between the
SBA and DLA. AR, Tab 14, Defense Department Form 70, at 2. (B.
H. Aircraft Company, Inc., B-295399.2, July 25, 2005) (pdf)
We find that there is no improper bundling here. Where there is
a consolidation of two or more agency requirements, the Small
Business Act, as amended, requires that agencies avoid bundling
them together where the result would be a single contract that
is likely to be unsuitable for award to a small business
concern. 15 U.S.C. 632(o)(2). On the other hand, where, as here,
the record shows that the agency has reserved its requirement
for small businesses, and there is an expression of interest in
the requirement by legitimate small businesses, there is no
basis to conclude that the consolidated requirement is
unsuitable for award to a small business within the meaning of
the Small Business Act. Phoenix Scientific Corp. , supra , at 9.
Here, the agency proceeded with the acquisition notwithstanding
the protest, and on October1, 2004, made award of a contract for
the consolidated requirement to a small business concern. Under
the circumstances, we have no basis to conclude that the
agency's consolidation of these requirements into a single
contract was improper or inconsistent with the Small Business
Act. (Health & Human Services Group,
B-294703, December 15, 2004) (pdf)
The agency explains that the
combined solicitation is necessary because Group Seattle
contains only one MLB (located at Station Bellingham), which may
not generate sufficient repair work to meet the $10,000 minimum
amount under the contemplated IDIQ contract. A separate contract
for Group Seattle also would deprive the agency of the potential
cost benefit from a single contractor’s economies of scale that
would result from repairs on more than one boat, and also would
unnecessarily increase contract administration costs. The agency
determined that, notwithstanding that Reedsport would not be
able to compete, combining the Groups would not result in a
limited competition, since 10 firms expressed interest in the
requirement as structured. The agency’s approach is
unobjectionable. We see no reason why the agency should not be
permitted to consider, in configuring the lots for solicitation
purposes, the amount of work that would be generated under
different combinations of groups, stations and boats, and the
potential effect on the prices for that work (due, for example,
to economies of scale), as well as whether the work generated
for the single MLB would satisfy the contract minimum. While
these considerations resulted in Reedsport’s exclusion from the
competition, it is clear that the Coast Guard gave due
consideration to the broader competitive impact of its approach.
In this regard, based on the numerous expressions of interest,
the agency concluded that it could achieve the operational
benefits of its approach while possibly receiving greater
competition than it did under IFB 003. In arguing that its
own inability to compete renders the solicitation restrictive,
Reedsport ignores other legitimate competitive considerations
that would lead to a different conclusion. For example, while
splitting the requirement would enable Reedsport to compete for
the Station Port Angeles MLBs, this might at the same time
result in little or no competition for the single MLB at Station
Bellingham. Similarly, Reedsport’s position fails to take into
account the possibility that combining the two groups could make
the requirement more attractive to some potential bidders, and
ultimately result in greater competition overall. We conclude
that the agency reasonably combined the two groups under Lot 5.
(Reedsport Machine & Fabrication,
B-293110.2; B-293556, April 13, 2004) (pdf)
The reasons that the agency has offered, however, for grouping
the travel locations by geographic region, and for issuing a
single consolidated procurement, are not solely based on
administrative convenience. As indicated previously, the
underlying purposes behind the agency's single procurement
included the legitimate requirement to reengineer the antiquated
and costly DoD travel process, in part by consolidating the
process, and structuring geographical groupings to allow for
more small business participation. Agency officials testified
that a major factor that was considered in structuring the RFP
into 28 travel areas, with 89 locations was whether there was
adequate sales volume to achieve effective competition. See Tr.,
June 11, 2003, at 12, 40-41. Moreover, this procurement approach
allowed more choices by potential small business offerors to
select the travel areas where they would be most competitive and
able to successfully perform the contracts. Finally, unlike the
protesters, DTS/PMO officials found, based on discussions with
the Army, that the MEPS travel needs were well suited for
support by small businesses because the travel services for MEPS
are relatively “cut and dry”; the protesters have not shown this
judgment was unreasonable. See Tr., June 6, 2003, at 41; Tr.,
June 9, 2003, at 105; Tr., June 11, 2003, at 12-15. Since
the agency had a legitimate requirement to reengineer DoD travel
processes by consolidating them, and the agency did reasonably
consider the impact on small businesses, we find the agency has
justified its approach to consolidating the agency's
requirements. In this regard, we have upheld the consolidation
of requirements where, as here, an agency has provided a
reasonable basis for using such an approach--e.g., a definitive
agency requirement that mirrors the agency's minimum needs and
necessitates the questioned consolidation. See The Sequoia
Group, Inc., supra. (AirTrak
Travel etal., B-292101; B-292101.2; B-292101.3; B-292101.4;
B-292101.5, June 30, 2003) (pdf)
We do not question the agency's decision to classify food
services as logistics support functions to be administered by
the DOL. Rather, our concern is whether the agency has provided
a reasonable justification of its needs in terms of including
food services in the same RFP with base, vehicle, and aircraft
maintenance services. In our view, the fact that the agency is
organized in a manner which results in the administration of the
performance of all of these functions by one particular office
(which may itself be reasonable) does not provide a basis for
insisting that all of these varied services be procured from one
source. In other words, Fort Riley could, consistent with its
view that food services are just as integral to the work of its
DOL as the other functions, continue to have the contract for
food services, as well as the contract for the other services,
administered by the DOL. Beyond the question of whether all of
the services are part of logistics and relate to supporting the
troops, the agency's reason for bundling them all in a
solicitation seems to merely reflect the belief that it is
administratively more convenient to manage one entity performing
all of the requirements--either the MEO or a private-sector
offeror--as opposed to two entities--either the MEO or a
private-sector offeror for the food services, and either another
MEO or another private-sector offeror for the other base,
vehicle, and aircraft maintenance requirements. Administrative
convenience is not a legal basis to justify bundling of
requirements, if the bundling of requirements restricts
competition, as we believe it does here. Vantex Serv. Corp.,
supra, at 4; National Customer Eng'g, supra, at 6. (EDPEnterprises, Inc.,
B-284533.6, May 19, 2003 (pdf))
This solicitation does not
represent a “consolidation” of two or more requirements,
inasmuch as the record establishes that all of the requirements
here were previously provided under the one predecessor contract
with IHS, a large business, and were not provided under separate
smaller contracts. Thus, the Small Business Act requirements
pertaining to bundling are not applicable to this solicitation.
USA also argues that this
solicitation represents an improperly bundled or total package
procurement in violation of the Competition in Contracting Act
of 1984 (CICA). The reach of the restrictions against total
package or bundled procurements in CICA is broader than the
reach of restrictions against bundling under the Small Business
Act. Phoenix Scientific Corp., B-286817, Feb. 22, 2001,
2001 CPD ¶ 24 at 9‑10. Specifically, CICA generally requires
that solicitations include specifications which permit full and
open competition and contain restrictive provisions and
conditions only to the extent necessary to satisfy the needs of
the agency. See 10 U.S.C. §§ 2305(a)(1)(A), (B) (2000).
Because procurements conducted on a bundled or total package
basis can restrict competition, we will sustain a challenge to
the use of such an approach where it is not necessary to satisfy
the agency's needs. Better Serv., B‑265751.2, Jan. 18,
1996, 96-1 CPD ¶ 90 at 2. The determination of a contracting
agency's needs and the best method for accommodating them are
matters primarily within the agency's discretion. Specialty
Diving, Inc., B-285939, Oct. 16, 2000, 2000 CPD ¶ 169 at 3.
Of particular relevance here, where a requirement relates to
national defense or human safety, an agency has discretion to
define the solicitation requirements to achieve not just
reasonable results, but the highest possible reliability and
effectiveness. Tucson Mobilephone, Inc., B-250389, Jan.
29, 1993, 93-1 CPD ¶ 79 at 5, aff'd, B-250389.2, June 21,
1993, 93-1 CPD ¶ 472. (USA Information Systems, Inc., B-291417,
December 30, 2002)
While
we recognize that there are instances where an agency awards
identical ID/IQ contracts so that it might be reasonable to
define what was solicited and awarded as one procurement
requirement (a question we need not resolve here), that is not
what occurred in this instance. In this case, although a single
solicitation (the MLA) was issued, it listed a variety of
equipment needed by the agency. The MLA thus was not a statement
of a single procurement requirement, as the agency suggests, but
instead functioned more as a list of a range of multiple
procurement requirements. As the protester notes, the nine
contracts awarded under the MLA were of varied scope and covered
varying lists of equipment. If the MLA referenced a single
requirement, as the agency contends, that would mean that the
contracting agency had awarded many (perhaps all) of the nine
contracts even though (since they did not cover the entire MLA)
they did not satisfy the agency's procurement requirement. The
fact that all of the containers and all of the related equipment
can be accurately described as intermodal container equipment
does not establish that they are simply elements in a large
unitary procurement requirement; otherwise, separate equipment
contracts for different types of furniture, or for identical
services in different regions of the country, would have to be
viewed as contracts for a single procurement requirement. In our
view, to define "procurement requirement" so broadly could
shield from meaningful review the very sort of arbitrary
consolidation of requirements that the Act's restrictions on
bundling are intended to prevent. (TRS
Research, B-290644, September 13, 2002) (pdf)
On the record before us, we find that the Army has not
adequately demonstrated that combining its requirements for
portable latrine and waste removal services was necessary to
satisfy the agency's needs. The agency has not adequately
explained why it chose to bundle the two kinds of work at Fort
Campbell, yet did not bundle two kinds of work at either of the
other two locations, and in fact structured the solicitation so
that services for the three locations can be obtained by
separate or combined awards, thus facilitating competition while
not excluding the possibility of a combined contract. The
agency's justification, quoted above, essentially amounts to
reliance on administrative convenience as the basis for the
bundling. However, the fact that the agency may find that
combining the requirements is more convenient administratively,
in that it has found dealing with one contract and contractor
less burdensome, is not a legal basis to justify combining the
requirements, if the combining of requirements restricts
competition. CICA and its implementing regulations require that
the scales be tipped in favor of ensuring full and open
competition, whenever concerns of economy or efficiency are
being weighed against ensuring full and open competition. See
Better Serv., supra; National Customer Eng'g, B-251135, Mar. 11,
93-1 CPD ¶ 225 at 6. (Vantex
Service Corporation, B-290415, August 8, 2002) (pdf)
Given the
fundamentally expanded scope and complexity of the agency's food
services requirement, we think USMC reasonably concluded that
there was no reasonable expectation that such small business
concerns, with primarily limited messhall contracts on the
installation level, possessed the capabilities, resources and
experience to satisfactorily perform the contemplated regional
contracts. (MCS
Management, Inc., B-285813; B-285882, October 11, 2000)
Treasury reports that
it projects achieving substantial technical benefits from
consolidating its IT requirements, including the requirement
here, under the Seat Management program. For example, Treasury
expects that having a single contractor responsible for all of
its desktop IT requirements--rather than continuing to rely on
the current fragmented approach of using different sources for
hardware/software and services--will result in significant
quality improvements as a result of (1) having a single
contractor responsible for infrastructure interoperability and
product compatibility, (2) eliminating the confusion, delays and
denials of responsibility for service interruptions or
installation problems, and (3) facilitating consistent, timely
upgrades and refreshment of technology. Treasury Reports, Apr.
2, 1999, at 25-26, Apr. 28, 1999, at 5-6, and Apr. 30, 1999, at
1-2; Agency Report, Tab 26, Acquisition Plan, Feb. 9, 1999, at
3, 9.
SKE has not rebutted
the basis for Treasury's determination to procure the services
in question under the Seat Management contract; it has made no
showing that Treasury in fact had no reasonable expectation of
achieving substantial technical benefits from consolidating
these IT requirements under the Seat Management contract. Thus,
there is no basis for finding that the agency's approach
violates the prohibition against improper bundling. (S&K
Electronics, B-282167, June 10, 1999) |