Rotair argues that the Army did not provide a reasonable
opportunity to become an approved source for maintenance and
overhaul of drag braces. The protester also contends that the
agency’s award was improper because it was based on an outdated
J&A that incorrectly stated that the agency had not received
expressions of interest from non-approved sources. For the
reasons discussed below, we find no basis to sustain the
protest.
The Competition in Contracting Act of 1984 (CICA) requires
agencies to obtain full and open competition in procurements
through the use of competitive procedures. 10 U.S.C. §
2304(a)(1)(A). An exception to this general requirement is where
there is only one responsible source, or a limited number of
sources, able to meet the agency’s requirements. 10 U.S.C. §
2304(c)(1); HEROS, Inc., B 292043, June 9, 2003, 2003 CPD ¶ 111
at 6. This is the exception cited in the J&A here. AR, Tab 2.6,
J&A, at 2.
CICA further states, however, that noncompetitive procedures may
not be used due to a lack of advance planning by contracting
officials. 10 U.S.C. § 2304(f)(5); New Breed Leasing Corp.,
B-274201, B-274202, Nov. 26, 1996, 96-2 CPD ¶ 202 at 6; TeQcom,
Inc., B-224664, Dec. 22, 1986, 86-2 CPD ¶ 700 at 5. Our Office
has recognized that the requirement for advance planning does
not mean that such planning must be completely error-free, but,
as with all actions taken by an agency, the advance planning
required under 10 U.S.C. § 2304 must be reasonable. WorldWide
Language Resources, Inc.; SOS Int’l Ltd., B 296984 et al., Nov.
14, 2005, 2005 CPD ¶ 206 at 12.
In addition, when a contracting agency restricts a contract to
an approved product or source, and uses a qualification
requirement as the basis for that restriction, it must give
other offerors a reasonable opportunity to qualify. Barnes
Aerospace Grp., B-298864, B-298864.2, Dec. 26, 2006, 2006 CPD ¶
204 at 3; see 10 U.S.C. § 2319(b). This opportunity to qualify
includes ensuring that an offeror is promptly informed as to
whether qualification has been attained and, if not, promptly
furnishing specific information about why qualification was not
attained. Advanced Seal Tech., Inc., B-250199, Jan. 5, 1993,
93-1 CPD ¶ 9 at 3. Failure to act upon a potential offeror’s
request for approval within a reasonable period of time deprives
the requester of an opportunity to compete and is inconsistent
with the CICA mandate that agencies obtain full and open
competition through the use of competitive procedures. Barnes
Aerospace Grp., supra; Advanced Seal Tech., Inc., supra.
Rotair first contends that the Army failed to provide the
company a reasonable opportunity to be qualified as an approved
source for maintenance and overhaul of drag braces.
Specifically, Rotair noted that the agency delayed approximately
30 days in providing the protester all of the specifications
needed to prepare its SAR package. Protest at 9. Rotair contends
that this delay, combined with the agency’s unwillingness to
delay contract award until after completion of its review of the
protester’s SAR package, unreasonably deprived Rotair of an
opportunity to compete. Id. We find no merit to the protester’s
arguments.
As discussed above, Rotair requested the Army provide the
necessary documents to prepare and submit a SAR package on June
7, 2013. AR, Tab 1.6, Email from Rotair to Contract Specialist
(June 7, 2013). The agency acknowledges that it did not provide
all of the required information until July 9. Contracting
Officer’s Statement at 2. The protester, however, did not submit
its SAR package until January 29, 2014 (which was received by
the agency on February 3)--almost 7 months later. Id.
Additionally, the Army advises that Rotair’s SAR package was
“prioritized” for review on February 28, that the SAR package
was moved “to the top of the list of unsolicited SARs” for
review on April 24, and that the review process of Rotair’s SAR
package began on April 28. Supp. Contracting Officer’s Statement
(Aug. 25, 2014) at 1. As discussed above, the Army awarded the
contract on May 2. Subsequent to the award, on August 15, the
agency sent Rotair an “on hold” letter because its SAR package
did not meet certain requirements. Letter to Rotair from Army
Engineering Directorate (Aug. 15, 2014), at 1-3. The agency
requested that Rotair address the outlined issues and submit
corrected documents within 60 days. Id. at 3.
Although the record shows that the Army delayed in providing
data to Rotair that was required for the preparation and
submission of its SAR package, the protester was nonetheless
responsible for the majority of the delay in submitting the SAR
package to the agency. In light of the protester’s delay in
submitting its SAR package, and the agency’s subsequent efforts
to review that package, we find no basis to conclude that the
agency failed to meet its obligation to provide Rotair with an
opportunity to become an approved source.
Rotair next contends that the Army was required to delay award
of this contract until the agency completed the review of the
protester’s SAR package. As discussed above, a potential offeror
may not be denied the opportunity to submit an offer for a
contract solely because the potential offeror is not an approved
source; similarly, a prospective offeror must be provided an
opportunity to be qualified as an approved source. 10 U.S.C. §§
2319(b), (c)(3).
The protester’s argument here, however, raises a separate
question--whether the agency must delay award of a contract in
order to allow an offeror an opportunity to become qualified. As
our Office has recognized, the approval process for critical
safety items used in aviation can be involved. See Barnes
Aerospace Grp., supra, at 6. In addition, the applicable
statutes and regulations expressly provide that agencies need
not delay proposed procurements in order to provide potential
offerors enough time to become qualified. 10 U.S.C. §
2319(c)(5); FAR § 9.202(e). Accordingly, we cannot conclude that
the Army acted improperly by not delaying the award here.
Finally, Rotair contends that the award to Overhaul was improper
because the J&A restricting the competition to approved sources
inaccurately stated that there were no pending expressions of
interest by non-approved sources. The protester is correct that
the May 16, 2013, J&A’s findings regarding expressions of
interest was outdated as of the time the agency awarded the
contract to Overhaul on May 2, 2014--as shown by the protester’s
own expression of interest. The J&A, however, concerned the
issuance of a solicitation that was limited to two approved
sources. AR, Tab 2.6, J&A, at 2. Based on the J&A’s authority,
the solicitation stated that the competition was limited to
approved sources for drag brace maintenance and overhaul. RFP at
2. Thus, at the time the solicitation was issued, the J&A’s
statement concerning the absence of other expressions of
interest was accurate.
Because Rotair was not an approved source at the time of award,
the agency could not make award to that firm in accordance with
the terms of the solicitation. AR, Tab 1.3, Agency-Level Protest
Decision (June 10, 2014), at 2. Moreover, as discussed above,
the agency was not required to delay the award until the review
of the protester’s SAR. For this reason, we do not think that
Rotair’s submission of a SAR package provides any basis to
challenge the agency’s award under the terms of the J&A or the
solicitation.
The protest is denied (Rotair
Industries, Inc., B-409950: Sep 25, 2014) (pdf)
This protest
relates to RBC's efforts over almost 10 years to become a second
approved source for Black Hawk helicopter swashplate bearings.
In simple terms, two swashplates join the main rotor to the top
of the main fuselage of a helicopter; the lower swashplate is
stationary, while the upper swashplate rotates. Duplex ball
bearings, known as the swashplate bearings, allow the upper
swashplate to rotate in response to torque from the engine.
RBC argues that the delay in granting its request for source
approval undermines DLA's justification for limiting the
procurement to the original equipment manufacturer (OEM) of the
Black Hawk (Sikorsky) or to the OEM's supplier (Kaydon). For its
part, DLA argues that it has taken appropriate steps to allow
RBC to pursue source approval, but since RBC is not currently an
approved source, the sole-source procurement is proper. As
explained in greater detail below, after RBC filed its protest,
DLA revised the requirement from 33 bearings to six, and again
directed award to the OEM, based on urgency. RBC also protested
the revised procurement.
(sections deleted)
The Competition in Contracting Act of 1984
(CICA) requires that an agency obtain full and open competition
in its procurements through the use of competitive procedures.
10 U.S.C. sect. 2304(a)(1)(A). Exceptions to this general
requirement are provided in the statute where (among other
enumerated exceptions) there is only one responsible source able
to meet the agency's requirements, 10 U.S.C. sect. 2304(c)(1),
or the requirement is of unusual and compelling urgency, 10
U.S.C. sect. 2304(c)(2). Since DLA took corrective action in
response to the initial protest here--and thus no longer
justified this procurement on a conclusion that there is only
one responsible source for these bearings--the remaining issue
in this protest is DLA's reliance on urgency to justify its
reduced requirement for swashplate bearings.
As RBC points out, CICA mandates that noncompetitive procedures
may not be used because agency contracting officials failed to
perform advance planning. 10 U.S.C. sect. 2304(f)(4); HEROS,
Inc., B-292043, June 9, 2003, 2003 CPD para. 111 at 6; New Breed
Leasing Corp., B-274201, B-274202, Nov. 26, 1996, 96-2 CPD para.
202 at 6; TeQcom, Inc., B-224664, Dec. 22, 1986, 86-2 CPD para.
700 at 5. Our Office has recognized that the requirement for
advance planning does not mean that such planning must be
completely error-free, but, as with all actions taken by an
agency, the advance planning required under 10 U.S.C. sect. 2304
must be reasonable. Barnes Aerospace Group, B-298864,
B-298864.2, Dec. 26, 2006, 2006 CPD para. 204 at 4-5.
In addition, when a contracting agency restricts a contract to
an approved product or source, and uses a qualification
requirement, it must give other potential sources a reasonable
opportunity to qualify. Lambda Signatics, Inc., B-257756, Nov.
7, 1994, 94‑2 CPD para. 175 at 4; Advanced Seal Tech., Inc.,
B-250199, Jan. 5, 1993, 93-1 CPD para. 9 at 3; see generally 10
U.S.C. sect. 2319(b). Failure to act upon a potential offeror's
request for approval within a reasonable period of time deprives
the requester of an opportunity to compete and is inconsistent
with the CICA mandate that agencies obtain full and open
competition through the use of competitive procedures. Lambda
Signatics, Inc., supra; Advanced Seal Tech., Inc., supra; see
also Freund Precision, Inc., B‑223613, Nov. 10, 1986, 86-2 CPD
para. 543 at 3-4, aff'd, Freund Precision, Inc.--Recon.,
B‑223613.2, May 4, 1987, 87-1 CPD para. 464 (protest sustained
where agency failed to evaluate protester's alternate product
for unreasonable period of time); Rotair Indus., Inc., B‑232702,
Dec. 29, 1988, 88-2 CPD para. 636 at 3 (protest sustained where
agency unreasonably delayed processing of source approval
request).
In our view, the actions of DLA and AMCOM chronicled above have
unreasonably deprived RBC of an opportunity to compete for a
contract to provide these bearings. While we do not question the
urgency or necessity of obtaining the six bearings at issue
here, we nevertheless conclude that DLA has failed to adequately
plan for a requirement that was foreseeable and therefore the
agency has failed in its statutory duty to perform adequate
advance planning and to promote competition. In this regard, we
view the earlier sole-source solicitations (some of which were
canceled, possibly as a result of RBC's objections) as
confirming the foreseeability of a continuing requirement for
significantly larger quantities of swashplate bearings than are
covered by this procurement. In the face of these continuing
requirements, RBC has sought source approval from DLA or the
Army since February 2000--i.e., for almost 10 years prior to the
date of this decision. We think these facts amply establish a
failure to conduct adequate and reasonable advance planning, as
required under CICA. 10 U.S.C. sect. 2304(f)(4). Thus we
conclude that the sole-source procurement here is not properly
justified. (RBC Bearings
Incorporated, B-401661; B-401661.2, October 27, 2009)
(pdf)
Viking argues
that it offered a previously-approved, as opposed to an
alternate, product, and thus should not have been required to
submit a data package for evaluation. The protester further
argues that the agency improperly failed to request information
pertaining to the acceptability of its valve from the Marine
Corps.
As previously noted, the RFQ here incorporated by reference DLAD
sect. 52.217-9002, which instructed offerors to indicate in
their quotations whether they were offering an "exact product,"
an "alternate product," a "superceding part number," or a
"previously-approved product," and to furnish the data required
for whichever was applicable. For an alternate product, offerors
were required to furnish "drawings, specifications, or other
data necessary to clearly describe the characteristics and
features of the alternate product being offered;" in addition,
they were required to furnish data describing the exact product
cited in the item description to the extent that this
information was not already available to the government. The
section further instructed that if, as was the case here, the
solicitation did not identify the level of data in the
government's possession, offerors were to assume that no data
was available and to "furnish drawings and other data covering
the design, materials, etc., of the exact product cited in the
AID [acquisition item description], sufficient to establish that
the Offeror's product is equal to the product cited in the AID."
DLAD sect. 52.217-9002(c)(3)(a). For a previously-approved
product, offerors were required to identify the contract or
solicitation under which the product had previously been
furnished or evaluated and approved; offerors were cautioned as
follows, however:
If the product was furnished or evaluated and approved by a
contracting activity different from the one issuing this
solicitation, Offerors are advised that the Contracting Officer
may not have access to records of another activity or other
information sufficient to reasonably determine the offered
product's acceptability. Therefore, in order to ensure that
adequate data is available for evaluation, Offerors may elect to
furnish with their offer the information requested by
subparagraph (b) [pertaining to submission of an exact product]
or (c) [pertaining to submission of an alternate product] of
this provision, whichever is applicable for the offered product.
Offerors are advised that if the additional data is not
furnished, the Government may not be able to evaluate the offer.
DLAD sect. 52.217-9002(e)(2).
The foregoing paragraph makes clear that if, as was the case
here, a vendor offers a product that was furnished to, or
approved by, a contracting activity different from the one
conducting the procurement in question, the contracting officer
may not be able to obtain the records establishing the product's
acceptability, and that if the contracting officer is unable to
gain access to such records, the offeror must submit a data
package to ensure evaluation of its offer. The agency explained
that while the protester furnished evidence that it had
previously furnished the valves to the Marine Corps, it did not
furnish evidence that the valves had been approved. The agency
noted in this connection that while one of the military services
can decide to accept the risk associated with buying an item
that has not been approved by the responsible ESA (which in this
case was the Naval Inventory Control Point, Mechanicsburg,
Pennsylvania), DLA will only acquire an exact product or one
that the ESA has determined to be a technical equivalent. DLA
also noted that in response to the protest here, it had
attempted to gain access to archived files of the Marine Corps
to determine if Viking had undergone some form of technical
evaluation and approval for the item offered, but was
unsuccessful.
The agency further explained that in an attempt to resolve
Viking's protest, it had contacted the individual at the ESA
whom the protester's attorney had identified to agency counsel
as a source who could provide information regarding the approval
of Viking's product; this individual stated that he did not have
the authority to approve the item (his authority being limited
to making recommendations regarding approval to a senior
engineer), and thus had not approved Viking's part. This
individual further advised that if Viking's part had been
approved, a "certificate of conformance" would have been issued
to Viking. DLA personnel followed up on the foregoing
representations by contacting the senior engineer in question,
who stated that he had no recollection of approving Viking's
part for this NSN; in addition, DLA personnel contacted Viking
to inquire whether it had a certificate of conformance and were
told that it did not have such a document.
Given that, despite their reasonable efforts, DLA personnel were
unable to locate documentation establishing that Viking's part
had been approved as an acceptable alternate to the specified
part, we think that it was both reasonable and consistent with
the terms of the RFQ for the agency to require a data package
for evaluation.
In commenting on the agency report, the protester raised an
additional argument-- that the agency had deprived it of the
opportunity to gain approval of its item in time for award under
this RFQ by failing to refer its drawing to the ESA for
approval.
The master solicitation for automated simplified acquisitions
explicitly provides that "[a]lternate offers will not be
considered for automated award," but that they "may be submitted
for evaluation for future procurements . . . ." Master
Solicitation at 5. To the extent that the protester had an
objection to the above clause barring consideration of alternate
offers for automated award, it needed to raise its objection
prior to the closing date for receipt of quotations. See Bid
Protest Regulations, 4 C.F.R. sect. 21.2(a)(1) (2009) (to be
timely, a protest based on an alleged impropriety in a
solicitation must be filed prior to the closing date for receipt
of offers/quotations). In any event, the provision is clearly
intended to prevent delay in making automated awards, which is
consistent with statutory authority providing that an agency
need not delay a procurement in order to provide an offeror an
opportunity to demonstrate its ability to become qualified. 10
U.S.C. sect. 2319(c)(5) (2006); Advanced Seal Tech., Inc.,
B‑400088; B‑400089, July 14, 2008, 2008 CPD para. 137 at 4-5.
Moreover, we think the agency made a reasonable effort to obtain
information bearing on whether Viking's part was approved and
that Viking had an opportunity to provide evidence for the
assertion in its quotation that its item was a
previously-approved part. (Viking
Inc.--USA, B-401528, August 25, 2009) (pdf)
In its protests here AST argues that its ability to attain
prompt requalification of its product has been hampered by the
agency’s failure to promptly notify it of the revocation of its
source approval and immediately provide technical information
related to the revocation, as well as by the agency’s proposed
180-day timetable for the review of revisions to AST’s alternate
item. AST requests that all procurements of NSN 2321 be
suspended until AST can become requalified. DSCC responds that
its decision to proceed with the procurement of NSN 2321 was not
improper where AST was notified that it had been removed as an
approved source before the challenged RFQs were issued, and DSCC
is not required to--and, in view of its needs for the part,
cannot--delay the procurement of NSN 2321 while AST pursues the
requalification of its alternate item.
The Competition in Contracting Act of 1984 (CICA) requires that
an agency obtain “full and open” competition in its procurements
through the use of competitive procedures. 10 U.S.C. sect.
2304(a)(1)(A) (2000). Accordingly, when a contracting agency
restricts contract award to an approved product and imposes a
qualification requirement, it must give nonapproved sources a
reasonable opportunity to qualify. Newguard Indus., Inc.,
B-257052, Aug. 11, 1994, 94-2 CPD para. 70 at 2. This
opportunity to qualify includes providing offerors a prompt
opportunity to demonstrate their qualification and ensuring that
the offeror is promptly informed as to whether qualification has
been attained and, if not, promptly furnishing specific
information why qualification was not attained. 10 U.S.C. sect.
2319(b)(6); FAR sect. 9.202(a)(2)(ii), (4).
DSCC sustained AST’s earlier agency-level protests on the basis
that DSCC had failed to promptly inform AST of its removal as an
approved source and of the reasons for that removal, thereby
denying AST a prompt opportunity to qualify in connection with
the earlier-issued RFQs. Those facts are not repeated in the
current protests. Here, AST had notice that it had been removed
as an approved source by January 17, and was formally notified
and given specific information as to why it had been removed on
February 26. Therefore, because AST had the notice and
information necessary to undertake requalification before the
RFQs were issued on March 3, we see no basis to conclude that
DSCC denied AST a reasonable opportunity to qualify its
alternate item in connection with the currently challenged RFQs.
AST also argues that DSCC has denied AST a prompt opportunity to
demonstrate its qualification by suggesting a 180-day review
process for revisions to AST’s alternate item. The 180-day time
period is derived from the ESA’s Source Approval Information
Brochure, which states that “within 180 days of a SAR being
prioritized for review, the contractor shall be advised of the
approval or disapproval thereof, or if additional time is
required to process the request, the date on which approval or
disapproval will be provided.” Source Approval Information
Brochure at 13. AST has not explained why that time period is
unreasonable other than to cite its previous experiences in
which review has occurred more rapidly, and on the record here
we see no basis on which to find that the 180-day review period
violates the prompt opportunity requirement in 10 U.S.C. sect.
2319(b)(6). Further, we note that AST’s seal failed to qualify
previously, and therefore AST’s alternate item must be evaluated
again.
With regard to whether DSCC must delay or suspend procurement of
NSN 2321 in order to allow AST to requalify, a potential offeror
may not be denied the opportunity to submit and have considered
an offer for a contract solely because the potential offeror is
not an approved source, if the potential offeror can demonstrate
to the satisfaction of the contracting officer or ESA that the
potential offeror or its product can meet the standards of
qualification before the date specified for award. 10 U.S.C.
sect. 2319(c)(3). However, there is no statutory requirement
that an agency delay a procurement in order to provide an
offeror an opportunity to demonstrate its ability to become
qualified. 10 U.S.C. sect. 2319(c)(5); Marc Ave. Corp.,
B-261968.2, Jan. 11, 1996, 96-1 CPD para. 79 at 3. Accordingly,
we agree with DSCC that it has no obligation to suspend its
procurements of NSN 2321 here. (Advanced
Seal Technology, Inc., B-400088; B-400089, July 14, 2008) (pdf)
A procuring agency may limit competition for the supply of parts
if doing so is necessary to ensure the safe, dependable and
effective operation of military equipment, see, e.g., Tura Mach.
Co., B-241426, Feb. 4, 1991, 91-1 CPD para. 114 at 3, and the
contracting agency is primarily responsible for determining its
minimum needs and for determining whether a potential offeror
will satisfy those needs, since it must bear the burden of
difficulties resulting from defective determinations in this
regard. Chromalloy Gas Turbine Corp., B-234272, May 17, 1989,
89-1 CPD para. 474 at 2. When a contracting agency restricts a
contract award to only approved sources and imposes
qualification requirements, unapproved sources should be given a
reasonable opportunity to qualify. 10 U.S.C. sect. 2319 (2000).
However, an agency is not required to delay a procurement solely
to provide a potential offeror an opportunity to demonstrate its
ability to become approved. 10 U.S.C. sect. 2319 (c)(5); The
Purdy Corp., B-259066, Mar. 1, 1995, 95-1 CPD para. 120 at 3.
This is particularly true where the offeror contributes to its
failure to obtain timely source approval. Id.
Here, HFMC has not meaningfully challenged either the substance
of the DLA’s determination regarding the critical nature of the
valve assemblies, nor the authority of DLA to establish source
approval qualification requirements. Rather, its entire protest
rests on the assertion that unidentified TACOM personnel
previously advised HFMC that it “need only qualify the assembly
component [NSN-1063] in order to qualify the entire [NSN-]6205
tank valve assembly.”[4] HFMC Comments, May 14, 2008. In short,
HFMC argues that, because unidentified TACOM representatives
allegedly misled HFMC several years ago regarding the
qualification requirements--or alternatively, that HFMC
misunderstood the scope of the qualification requirements--DLA
is now obligated to list HFMC as an approved source for this
procurement.
Based on the record here, we reject HFMC’s protest that the
agency improperly failed to include HFMC as an approved source
for acquisition of the valve assemblies at issue. Indeed, it is
clear that HFMC has been given an opportunity to meet the
requirements to become a qualified source for the valve stem
assemblies, but has declined to do so. Accordingly, there is no
basis to question the agency’s determination not to identify
HFMC as an approved source in this solicitation. (Hydro
Fitting Manufacturing Corporation, B-311452, July 8, 2008) (pdf)
With regard to the specific procurement challenged here, AST
argues that DSCC’s failure to inform it of the results of the
installation test of PFS-0822-21A denied AST a reasonable
opportunity to qualify its alternate item before the issuance of
the order. By statute and regulation, agencies imposing
qualification requirements must fulfill specific
responsibilities. As relevant here, they must provide offerors a
prompt opportunity to demonstrate their qualification and must
ensure that any offeror seeking qualification is promptly
informed as to whether qualification has been attained, and if
not, promptly furnish specific information on why qualification
was not attained. 10 U.S.C. sect. 2319(b)(4), (6); FAR sect.
9.202(a)(2)(ii), (4).
In response to AST’s argument, DSCC contends that it fulfilled
the requirements of 10 U.S.C. sect. 2319(b)(6) by notifying the
attorney who had represented AST in the protest that led to the
installation test. DSCC also argues that, even assuming it
failed to properly notify AST of the result of the installation
test, AST was not prejudiced because, even if it had been
promptly notified of the results, the firm could not have
successfully qualified in time to compete for this order.
In our view, even assuming that notification of the attorney who
represented AST in its previous protests was sufficient to
constitute notice to AST, DSCC’s notification of AST’s former
attorney was unreasonably delayed, contrary to the requirements
in 10 U.S.C. sect. 2319(b)(6). The installation test was
completed on August 22 and the test report was completed on
September 19, but the report was not forwarded to AST’s former
attorney until November 27. Whether this more than 2-month delay
between the completion of the test report and formal
notification was attributable to DSCC or the ESA, we conclude
that it did not constitute prompt notice as required under 10
U.S.C. sect. 2319(b)(6). However, we also conclude that AST was
not prejudiced by DSCC’s failure to promptly notify it of the
results of the installation test. AST first received the results
of the installation test on December 28. By January 9, AST had
modified its alternative item and sent a revised TDP to DSCC.
DSCC forwarded the revised TDP to the ESA, which conducted an
evaluation and notified AST on April 1 that its revised TDP was
rejected because it was incomplete and contained insufficient
information to determine if the modified design would work. The
period of time from when AST learned of the result of the
installation test to when it was notified that its revised TDP
was rejected was 94 days. Based on that 94-day time period and
the ultimate rejection of AST’s revised TDP, it is clear that
AST would not have had a reasonable chance of receiving the
order even if it had been promptly notified of the results of
the installation test. Assuming that AST was officially notified
of the results of the installation test on September 19, based
on the 94-day time period, AST would have received notice that
its revised TDP was rejected on December 22, 2 days after DSCC
publicized the issuance of the order to another firm. Moreover,
because AST’s revised TDP was rejected, AST could not have
qualified in time for the order even if the evaluation of the
TDP had taken substantially less time. If AST had been notified
that its revised TDP was rejected even well ahead of the date
the order was issued, AST would have been required to revise its
TDP for a second time and submit it for reevaluation before it
would have had a chance of again becoming conditionally
approved. In our view, there was not a reasonable chance that
AST could have become a qualified source in time to receive the
order. (Advanced Seal Technology, Inc.,
B-311308, June 5, 2008) (pdf)
Here, the agency asserts that the required process was clear
from a drawing that was made available to the protester and
other prospective offerors (via posting on a web-site). The
agency further argues that even assuming that the RFP package
and drawing did not adequately apprise the protester of the
requirement, the protester was on notice of it because
“[s]hortly after CM submitted its qualification/ qualification
waiver package, [the engineer] conferenced with CM and explained
in detail to CM” the agency’s requirement and its importance.
Supp. Decl. of Air Force Engineer, Jan. 4, 2004, at 2-3.
According to the Air Force engineer, “CM responded to [his]
explanation of the requirement and its importance, not by
stating that it could or would comply with it, but rather by
challenging its necessity and claiming CM could achieve
acceptable part without using this anodize method.” Id.
at 3. The protester has neither taken issue with nor attempted
to rebut either the agency’s argument that the required
anodizing process was clear from the drawing or its argument
that the engineer personally advised CM of the required
process. With regard to the latter point, the protester indeed
confirmed in its January 5 submission to our Office that the Air
Force engineer had explained the required anodizing process to
it and that it had responded by claiming that it could produce
an acceptable part without using this method. Because the
protester has neither taken issue with nor attempted to refute
the agency’s position, it effectively has abandoned its argument
that the Air Force denied it the opportunity to qualify as a
source by failing to include in the RFP sufficiently detailed
information regarding the required anodizing procedure. O.
Ames Co., B-283943, Jan. 27, 2000, 2000 CPD ¶ 20 at 7. In
any event, it is clear from the record that CM was aware of the
agency’s requirement and failed to demonstrate that its item had
undergone the required anodizing process. As a result, it
clearly was reasonable for the agency to conclude that CM was
not a qualified source. (CM
Manufacturing, Inc., B-293370, March 2, 2004) (pdf)
Here, the record reflects that the agency did not require Pac
Sci Quantic to produce and test a qualification article, but
rather approved Pac Sci Quantic as a qualified source at its
Hollister, California facility, based on, among other things,
Pacific Scientific’s corporate experience with the BBU-63/B
cartridge, previous production of similar cartridges at the
Hollister facility, and an RFP requirement for first article
testing. As discussed below, we find that the agency’s approval
was reasonable and consistent with applicable law and
regulation, as well as the terms of the RFP. (Scot,
Incorporated, B-292580, October 3, 2003) (pdf)
Protest that award was improper
because contracting activity that approved awardee's part for
addition to qualified products list did not have approval
authority is denied, where contracting officer found part
approval valid based on consideration of information from
cognizant activities, consistent with his authority under 10
U.S.C. sect. 2319. (Phaostron
Instrument & Electronic Company, B-284456, April 20,
2000)
Where, as here, a solicitation
requires that the source of the product procured be qualified or
approved, it is improper for a contracting agency to include in
the list of approved sources a source that has not been properly
approved and whose product does not satisfy the applicable
specifications. Id. Including such a source in the list may
constitute a basis for sustaining a protest if the agency's
action prejudices the protester. Id.
Here, the Army ultimately
determined that TET should have been listed in the RFP as an
approved source, Contracting Officer's Statement para. 9, and
that it was unnecessary to "reapprove" a source (TET)
that was already qualified and manufacturing the panels. (Lavi
Systems, Inc., B-282295, June 24, 1999) |