New
Although not binding on this court, a template for evaluating an override
determination was offered by a Judge of this court in Reilly’s Wholesale Produce v. United
States, 73 Fed. Cl. 705 (2006).11 See Supreme Foodservice GmbH v. United States, 109
Fed. Cl. at 384 (“In Reilly’s Wholesale Produce v. United States, 73 Fed. Cl. 705 (2006),
one judge of our court surveyed the field of prior decisions and was able ‘to distill from
the relevant cases a variety of factors that an agency must consider in making an override
decision.’” (quoting Reilly’s Wholesale Produce v. United States, 73 Fed. Cl. at 711)); but
see PMTech, Inc. v. United States, 95 Fed. Cl. at 343 (“The court in Reilly’s Wholesale
has provided excellent guidance to this court, and to the procurement community, in
identifying factors that may be relevant to most CICA stay override decisions. As to the
precedential weight to be accorded the Reilly’s Wholesale factors, however, the court in
this decision must express some reservations.”). Override protests, however, are very
fact specific inquiries. See PMTech, Inc. v. United States, 95 Fed. Cl. at 344 (quoting
Automation Techs., Inc. v. United States, 72 Fed. Cl. at 727); Automation Techs., Inc. v.
United States, 72 Fed. Cl. at 727, 730. As explained in Beechcraft Defense Co.,
LLC, the Reilly’s Wholesale court identified four factors
to consider:
(1) “whether significant adverse consequences will
necessarily occur if the stay is not overridden”; (2)
“whether reasonable alternatives to the override exist
that would adequately address the circumstances
presented”; (3) “how the potential cost of proceeding with
the override, including the costs associated with the
potential that the GAO might sustain the protest, compare to the benefits associated with the approach being considered for
addressing the agency’s needs”; and (4) “the impact of the override on
competition and integrity of the procurement system.”
Beechcraft Defense Co., LLC v. United States, 111 Fed. Cl. at 31 (quoting Reilly’s
Wholesale Produce v. United States, 73 Fed. Cl. at 711); see also Supreme Foodservice
GmbH v. United States, 109 Fed. Cl. at 384. The court in Reilly’s Wholesale Produce
further stated that the “decisional law also indicates that certain factors are irrelevant to
this analysis, among them: (i) that the new contract would be better than the old one . . .
or (ii) the override and continuation of the contract is otherwise simply preferable to the
agency . . . .” Reilly’s Wholesale Produce v. United States, 73 Fed. Cl. at 711.
In discussing Reilly’s Wholesale, although a Judge of this court argued that “[t]he
court’s focus should be on whether the CICA stay override decision was rational and
whether the agency considered relevant factors, not on whether the agency conformed
its analysis to a specific framework elaborated by this court,” the Judge, nonetheless
acknowledged “the court recognizes the utility of the analytical framework provided by
Reilly’s Wholesale, but does not consider that the Reilly’s Wholesale factors govern the
outcome of this case.” PMTech, Inc. v. United States, 95 Fed. Cl. at 345. Likewise, the
undersigned is not bound by the Reilly’s Wholesale factors, but believes the factors are
a useful tool to help analyze the Agency’s decision to override the automatic stay based
on urgent and compelling circumstances in the context of APA review. See 5 U.S.C. §
706(2)(A).
The court in Reilly’s Wholesale Produce v. United States set forth an analytical
framework that was based on “a variety of factors that an agency must consider in making
an override decision based upon urgent and compelling circumstances.” Reilly’s
Wholesale Produce v. United States, 73 Fed. Cl. at 711. The factors articulated in Reilly’s
Wholesale Produce v. United States “have been applied when the stay override is based
upon urgent and compelling circumstances, or based upon the best interests of the United
States.”13 Charles F. Day & Assocs., LLC v. United States, 120 Fed. Cl. 767, 771 (2015);
see also Supreme Foodservice GmbH v. United States, 109 Fed. Cl. at 384 (noting that
the factors articulated in Reilly’s Wholesale Produce v. United States “have been
employed in cases reviewing overrides based on either justification”); E-Mgmt.
Consultants, Inc. v. United States, 84 Fed. Cl. 1, 6 (2008) (applying the Reilly’s Wholesale
Produce v. United States factors to an agency’s decision to override the CICA stay, in
which the agency justified the override decision as being in the “best interests of the
United States”). The undersigned is not bound by the Reilly’s Wholesale factors when
evaluating the Agency’s best interests justification for overriding the CICA stay, but
believes that the Reilly’s Wholesale factors are a useful analytical tool for evaluating
whether the Agency’s best interests justification was “arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.” See 5 U.S.C. § 706(2)(A).
(sections deleted)
CONCLUSION
Protestor has not demonstrated that the Agency’s decision to override the CICA
automatic stay was arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.
(Safeguard Base Operations, LLC
v. U. S. and B&O Joint Venture, LLC, No. 18-1515C,
November 5, 2018)
II. Application to This Case
The Court concludes that emergency and/or preliminary injunctive relief is not warranted
in this case. Most pertinently, SVD is not likely to succeed on the merits of its claim because the
premise of its legal theory—that the June 12 task order constitutes a de facto override of the
CICA stay—is flawed and unsupported. The remaining factors likewise do not break in SVD’s
favor.
A. Chance of Success on the Merits
First, SVD has not shown that it is likely to succeed on the merits of its claim. This is so
because an agency’s decision to obtain a bridge contract during a CICA stay does not ordinarily
constitute the functional equivalent of a stay override. See Carahsoft Tech. Corp. v. United
States, 86 Fed. Cl. 325, 346–47 (2009); Access Sys., Inc. v. United States, 84 Fed. Cl. 241, 243
(2008). Thus, a stay override may prejudice the protester with respect to the protested contract
because by the time the GAO reviews the protest, it may have become “too costly to undo the
contract and award the contract to a successful bid protester.” See Lear Siegler, Inc., Energy
Prods. Div. v. Lehman, 842 F.2d 1102, 1111 (9th Cir. 1988), withdrawn in part, 893 F.2d 205
(9th Cir. 1989) (en banc); see also Carahsoft, 86 Fed. Cl. at 346–47 (observing that absent a stay,
the procuring agency may be more likely to “disregard the [GAO’s] recommendations to cancel
the challenged award”). In contrast, when the agency issues a bridge contract, the protester
generally is not “prejudice[d] . . . in its protest . . . or in subsequently performing the work if it is
successful in its protest,” because “if [the] plaintiff is successful at the GAO, the original
contract, in its entirety, will still be available.” Access Systems, 84 Fed. Cl. at 243.
Access Systems presented facts nearly identical to those at issue here. In that case, an
agency seeking IT services awarded a 120-day bridge contract to a contract awardee after a
disappointed offeror protested the contract award at GAO. See id. at 242. After reviewing
evidence provided by the CO, Judge Bruggink held that even though the bridge contract covered
“identical information technology services involved in the original contract,” it did not work a de
facto override of the CICA stay. Id. at 243. He so held because the bridge contract was “a
separate, self-contained contract” whose “term [would] not lessen the amount of work” under the
protested contract, and whose funding was likewise segregated from the protested contract’s
funding. Id. As Judge Bruggink observed, “[c]ontracts may share the same subject matter and yet
remain separate and distinct from one another.” Id. Given these differences, Judge Bruggink
concluded that “the bridge contract d[id] not disturb the status quo with respect to the original
contract,” and thus that “the character of the bridge contract [wa]s distinctly different from an
override.” Id.
SVD offers no persuasive rebuttal to the logic of Access Systems. Rather, the gravamen
of its position appears to be that if an agency awards a bridge contract during a GAO protest, the
status quo may only be preserved by awarding the bridge contract to the incumbent. See Pl.’s
Mot. at 8–9; Status Conf. at 3:11:30–3:12:50 p.m. The CICA stay, however, is not intended to
freeze an incumbent’s status while GAO processes a protest. Rather, the stay preserves the status
quo with respect to the awarded contract, on the reasoning that—with the contract on hold as
awarded but unperformed—the agency is more likely to heed GAO’s recommendations if GAO
finds fault with the award.
5 See Carahsoft, 86 Fed. Cl. at 347; Access Systems, 84 Fed. Cl. at
242.
In short, the direct award of the June 12 task order to 22nd Century does not share the
relevant features of an override of the CICA stay with respect to the protested contract. It
therefore cannot be considered the functional equivalent of an override, such that the Army
would have needed to comply with CICA’s stay override requirements when issuing it.
Accordingly, SVD has not demonstrated that it is likely to succeed on the merits of this protest.
(SVD Stars II, LLC v. U. S. and
22nd Century Technologies, Inc., No. 18-846C, June 22,
2018)
This court regularly applies a four-part test to determine whether an agency override
of a CICA stay based on urgent and compelling circumstances was “arbitrary and
capricious.” See Reilly’s Wholesale Produce v. United States, 73 Fed. Cl. 705,
711 (2006).2 In weighing its decision to override the
stay, the agency considered the four Reilly factors,
despite stating that the decision was based on the “best
interests” exception rather than “urgent and compelling
circumstances.” Plaintiff also relies heavily on these
factors in arguing that the override should be declared
invalid. However, the focus here is on the standard provided by the Administrative Procedures Act as this court has interpreted it in
relation to the “best interest” exception.
A. “Best Interests”
Presumably, prompt performance of most contracts awarded by government
agencies would be in the country’s best interests or the contracts would not be awarded in
the first place. It follows that the justification for an automatic stay override mandated by
Congress requires something more than showing that the contract’s original purpose serves
the United States’ interests. See Nortel Gov’t. Solutions, Inc. v. United States, 84 Fed. Cl.
243, 247-248 (2003) (explaining that a best interests determination calls for more than an
argument that the override serves the original purpose of the contract) (citations omitted);
see also Advanced Sys. Dev., 72 Fed. Cl. 25, 31 (2006); PGBA, 57 Fed. Cl. at 662. An
assertion that a new contract is in essence better than a current one is not sufficient to show
“best interests.” Advanced Sys. Dev., 72 Fed. Cl. at 31 (“To allow a best interests
determination to rest on such a common ground would permit the override exception to
swallow the Congressionally mandated rule that stays be automatic.”)(citations omitted).
This court has provided varying interpretations as to whether the standards for
“urgent and compelling” should be stricter than those for “best interests.” See Spherix, Inc.
v. United States, 62 Fed. Cl. 497, 505 (2004) (noting that “one of the two justifications
recognized by the CICA for allowing a stay is minimal; hence, plaintiff’s ability to succeed
on the merits-to demonstrate that the Chief of the [agency]’s written finding is arbitrary or
capricious-faces an uphill battle.”); Advance Sys. Dev., 72 Fed. Cl. at 31 (noting
disagreement with the Spherix opinion that “best interests” requires a lesser showing.).
Regardless of whether the standard is less strict for a “best interests” justification than for
an “urgent and compelling circumstances” justification, the reasoning provided by the
agency in this case does not show how the override is in the best interests of the United
States.
We have interpreted the “best interests” justification in a small number of cases,
none of which has included agency justifications similar to those in this case. The court
came closest in Spherix, where the agency’s “best interests” justification for an override of
an automatic stay was sufficient because the justification emphasized the importance of
sticking to a specific timeline for implementation of the services at issue. Spherix, 62 Fed.
Cl. at 506. In that instance, a stay on the performance of the contract would have
jeopardized the ability of the system to be operational during a busy season. Id. The key
fact in that case dealt with the additional time constraint placed on the Government to meet
a go-live date in the contract prior to the use of the system during the busy season. In other
words, meeting the deadline was crucial to the purpose of the entire contract. In addition, the court noted that the particular program was “a Presidential priority, not an ordinary
governmental program.” Id.
Defendant contends that the timing in this case is crucial but does not explain why
the timing of performance of the new task order is crucial where a continuation or bridge
contract could suffice. Instead, defendant simply argues that a lapse in services is an
“unacceptable risk.”
The agency had ample time to consider such a lapse and take appropriate measures
to avoid it. CICA provides an exception to the override when the override is in the best
interests of the United States, not an individual agency or subset of citizens. We
acknowledge the importance of this agency’s mission, and we considered carefully whether
its constituents could be harmed by a delay, if any. Defendant did not show a direct
connection between any possible delay in performance of the new task order and a harm
that will necessarily affect veterans adversely. Certainly, no claim was made that the
program is a “Presidential priority,” for example, or that timing of performance of the new
task order, as opposed to continuation of the old order or an interim bridge contract, would
be crucial to the health or safety of veterans. See Spherix, 62 Fed. Cl. at 506.
B. Legislative Interpretation
In enacting the automatic stay,
Congress provided an automatic and immediate injunction
pending the disposition of a bid protest in certain
circumstances rather than requiring a protester to incur
the onerous burden of proof otherwise required for
injunctive relief
Permitting agencies to override the stay based on broad assertions and routine
administrative roadblocks would eviscerate the automatic stay. We have noted that “[t]he
automatic stay is intended to preserve the status quo during the pendency of the protest so that an agency would not cavalierly disregard the GAO’s recommendation to cancel the
challenged award.” Advanced Sys. Dev., 72 Fed. Cl. at 30-31 (citing PGBA, 57 Fed. Cl. at
660.) “The overarching goal of the stay is to preserve competition in contracting and ensure
a fair and effective process at the GAO.” Advanced Sys. Dev., 72 Fed. Cl at 31.
Defendant argued in its response to
the motion and during the hearing that the services
provided by the task order are so crucial that without
them, benefits to veterans will be suspended and may
result in death. We could not credit this line of
argument, however. The agency waited to award this
contract until just six days prior to the expiration of
the previous task order covering these crucial services.
Plaintiff could not have protested the bid until after
expiration of the original order. Defendant argued that
“it is not possible” to extend the previous order, and to
negotiate a bridge contract would take at least 18 to 30
days. Defendant’s argument is essentially that the stay
must be overridden to avoid a lapse in services because it
waited too late; it failed to extend the previous order or
enter into a bridge contract.
It is in the interest of the United States that the integrity of the competitive nature of
the bid process as mandated by Congress is upheld. See Reilly’s Wholesale Produce, 73
Fed. Cl. at 716 (“[T]he public’s interest likewise lies in preserving the integrity of the
competitive process – such, indeed, clearly was Congress’ view in providing that except in
circumstances not yet demonstrated here, the automatic stay should prevail.”) To allow an
override based merely on the fact that to work towards a bridge contract, or to have acted
timely and negotiated an extension are more difficult to accomplish than continuing to have
the incumbent perform the new contract, would allow agency manipulation of a
congressional mandate.
C. Declaratory Judgment
We find it prudent to provide declaratory judgment given the time constraints of this
stay. The effect of this judgment will be to reinstate the stay put into place by statute.
Defendant contends that injunctive relief is a “drastic and extraordinary remedy that is not
to be routinely granted.” Nat’l. Steel Car, Ltd. v. Canadian Pac. Ry., Ltd., 357 F.3d 1319,
1324 (Fed. Cir. 2004) (citations omitted). We have considered whether a declaratory
judgment in these circumstances requires review and analysis traditionally associated with
injunctive relief. Such an analysis, however, is not necessary, as “[d]eclaratory relief
preserves the scheme that Congress intended.” Chapman Law Firm Co. v. United States,
65 Fed. Cl. 422, 424 (2005) (holding that plaintiff need only establish that the override
determination is invalid; it need not meet the traditional four-part test for a preliminary
injunction to argue successfully that the override should be overturned). Because Congress
provided the automatic stay as the default, it is not necessary that additional criteria be met
to reinstate a stay that has been overridden by agency action. A ruling that the justification
provided for the override was “arbitrary and capricious,” as we have entered here, makes
it unnecessary to consider additional factors associated with injunctive relief.
(Intelligent Waves LLC v. U. S.
and Systems Made Simple Inc., No. 18-465 C, May 9,
2018)
“An injunction is a drastic and extraordinary remedy, which should not be granted as a
matter of course.” See Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 142 (2010); see also
11A C. WRIGHT, A. MILLER, & M. KANE, FEDERAL PRACTICE AND PROCEDURE § 2948 (3d ed.
2004). On a motion for temporary injunctive relief, the court must weigh four factors: (1)
plaintiff’s likelihood of success on the merits; (2) whether the plaintiff will suffer irreparable harm
if the court withholds injunctive relief; (3) “whether the balance of hardships to the respective
parties favors the grant of injunctive relief;” and (4) “whether it is in the public interest to grant
injunctive relief.” PGBA, LLC v. United States, 389 F.3d 1219, 1228–29 (Fed. Cir. 2004); see also
RCFC 65(c).
A. Likelihood Of Success On The Merits.
As the court advised the parties during the February 23, 2018 hearing, it was not in a
position to decide the merits of this bid protest and would need time to review the nearly 8,000
page Administrative Record and the parties’ briefs in light of the oral argument. 2/23/18 TR at
105. Therefore, the court is not in a position to rule on the likelihood of success on the merits.
B. Irreparable Harm.
When assessing irreparable harm, the relevant inquiry is whether the protestor has an
adequate remedy in the absence of an injunction. See PGBA, LLC v. United States, 60 Fed. Cl.
196, 221 (Fed. Cl. 2004), aff’d, 389 F.3d 1219 (Fed. Cir. 2014). In this case, GDMS argues that
it will be irreparably harmed, if the court does not grant injunctive relief, “because it has been
deprived the opportunity to fairly compete for the contract” and “would likely lose employees and
critical subcontractors during the transition process.” 2/23/18 Pl. Mot. at 3. In many cases, the
court has determined that the loss of the opportunity to fairly compete for a contract constitutes
irreparable harm. See FirstLine Transp. Sec., Inc. v. United States, 100 Fed. Cl. 359, 400 (Fed.
Cl. 2011); Wackenhut Servs., Inc. v. United States, 85 Fed. Cl. 273, 311 (Fed. Cl. 2008); Cardinal
Maint. Serv., Inc. v. United States, 63 Fed. Cl. 98, 110 (Fed. Cl. 2004); Hunt Building Co., Ltd. v.
United States, 61 Fed. Cl. 243, 279–80 (Fed. Cl. 2004); Gentex Corp. v. United States, 58 Fed. Cl.
634, 654 (Fed. Cl. 2003); United Payors and United Providers Health Servs., Inc. v. United States,
55 Fed. Cl. 323, 333 (Fed. Cl. 2003); see also SAI Indus. v. United States, 60 Fed. Cl. 731, 747
(Fed. Cl. 2004) (“Irreparable injury can be shown in the form of lost opportunity to fairly compete for and perform work under the contract[.]”) (internal quotation marks and citation omitted). These
decisions were issued under circumstances where the protestor “would not be able to recover lost
profits associate with its loss of business.” United Payors, 55 Fed. Cl. at 333. And, while “[a]
potential loss of employees is a monetary loss that several courts have determined is substantial
but not irreparable[,] . . . courts have [also] recognized that keeping a team together whose
existence is eliminated in the absence of injunctive relief can constitute irreparable harm.” Glob.
Computer Enters., Inc. v. United States, 88 Fed. Cl. 350, 454, modified on reconsideration, 88
Fed. Cl. 466 (Fed. Cl. 2009) (internal quotation marks and citations omitted).
During the February 23, 2018 hearing, the Government explained that it could only agree
to a voluntary stay through March 2, 2018, because GDMS’s bridge contract option expires on
March 18, 2018 and “it’s going to take about two weeks before then to reroll an extension of that.”
2/23/18 TR at 95–96. Therefore, beginning tomorrow, on March 3, 2018, in the absence of
injunctive relief, TSA could begin transitioning contract performance to Unisys and GDMS would
not be able to fairly compete for the contract nor recover lost profits associated with its loss of
business. For these reasons, GDMS has shown that it will be irreparably harmed, if the court does
not grant injunctive relief.
C. Balance Of Hardships.
When assessing the balance of hardships, “the court must consider whether the balance of
hardships leans in the plaintiff’s favor.” Overstreet Elec. Co v. United States, 47 Fed. Cl. 728, 744
(Fed. Cl. 2000). This requires “a consideration of harm to the [G]overnment.” Id. In this case,
the Government argues that it will be harmed, if the court grants injunctive relief, for three reasons.
First, granting injunctive relief will “delay testing to Credential Authentication Technology
(“CAT”),” that “is intended to automate the identification inspection process at airports[.]” 3/1/18
Gov’t Mot. at 8. Second, “in order to extend the bridge contract to GDMS, TSA must draw funds
from a limited risk reserve,” that “is needed to fund unanticipated costs associated with the
transition of the [Security Technology Integrated Program (“STIP”)] support contract, including
this bid protest, and will be exhausted on May 4, 2018 if used exclusively for the GDMS bridge
contract, leaving TSA without a risk reserve for the remaining transition.” 3/1/18 Gov’t Mot. at
8. Third, the award of a bridge contract to GDMS will “delay the awarded DOMAIN BPA[,]
including integration of the legacy [Transportation Security Equipment (“TSE”)].” 3/1/18 Gov’t
Mot. at 8.
With regard to the first alleged hardship, the Government acknowledges that “CAT
replaces manual inspection with an automated technology developed to ensure that only legitimate
passengers, airport personnel, affiliated airline crews, and non-traveling passengers using a gate
pass . . . gain access to sterile airport areas.” 3/1/18 Gov’t Mot. at 9. Therefore, although TSA
would be “able to better verify a passenger’s identity and ensure they receive the appropriate level
of screening” with CAT, it is possible to continue using manual inspections until this bid protest
is resolved. With regard to the second alleged hardship, the Government states that “[i]f the risk
reserve is used exclusively to continue funding the bridge contract [to GDMS], it will be exhausted
on May 4, 2018, leaving TSA without a risk reserve for remaining transition activities.” 3/1/18
Gov’t Resp. at 11. But, this implicitly acknowledges that the Government can continue funding
the bridge contract to GDMS for a period of time, not to exceed May 4, 2018. In fact, TSA has
awarded a bridge contract option to GDMS that will not expire until March 18, 2018. 3/1/18 Gov’t Resp. Ex. 1 at 2 (Wilson Decl.). In addition, the risk reserve funds will not be needed for transition
activities, if GDMS succeeds in this bid protest and is awarded the contract. Similarly, with regard
to the third alleged hardship, any need to integrate the legacy TSE would be obviated, if GDMS
were to succeed in this bid protest and is awarded the contract.
GDMS argues that “there would be no harm to the Government; rather a TRO might benefit
the Government[, because] GDMS is currently providing STIP support and could continue
providing this support during the protest.” 2/23/18 Pl. Mot. at 4. It is true that GDMS could
continue providing STIP support under a bridge contract during this bid protest, but this will
impose some hardship on the Government. TSA may be required to use funds from the risk reserve
to continue to fund a second option on the bridge contract, if this bid protest is not resolved by
March 18, 2018. GDMS also argues that “a TRO will keep the Government from paying to start
the implementation of Unisys’s solution, only to be forced to terminate the contract once GDMS’s
protest is sustained.” 2/23/18 Pl. Mot. at 4. This, however, seems to be a risk TSA is willing to
assume. In sum, issuance of a temporary restraining order will impose more harm to the
Government.
D. Public Interest.
As the United States Court of Appeals for the Federal Circuit has held, “[t]he function of
preliminary injunctive relief is to preserve the status quo pending a determination of the action on
the merits.” Cont’l Serv. Grp, Inc. v. United States, 2018 WL 388634, at *5 (Fed. Cir. Jan. 12,
2018) (citing Litton Sys., Inc. v. Sundstrand Corp., 750 F.2d 952, 961 (Fed. Cir. 1984)). Since this
case was filed, the court has adjudicated eight other cases on motions that have priority over this
bid protest. Therefore, the court has not been able to conduct a meaningful review of the
Administrative Record and briefs in this matter.
Accordingly, the court has determined that the four injunctive relief factors, on balance,
weigh in favor of the issuance of a temporary restraining order. See FMC Corp. v. United States,
3 F.3d 424, 427 (Fed. Cir. 1993) (“No one factor, taken individually, is necessarily dispositive . . . .
[T]he weakness of the showing regarding one factor may be overborne by the strength of others.”).
E. Security Bond.
RCFC 65(c) states, in relevant part,
(c) Security. The court may issue a preliminary injunction or a temporary
restraining order only if the movant gives security in an amount that the court
considers proper to pay the costs and damages sustained by any party found to have
been wrongfully enjoined or restrained.
RCFC 65(c).
The Government states that “entering injunctive relief will cause the Government to extend
the bridge contract to GDMS at the cost of $10,950.90 per day.” 3/2/18 Gov’t Resp. at 12. But,
the Government will not incur any costs or damages as a result of this injunctive relief, because
this 14-day temporary restraining order will expire on March 16, 2018, i.e., prior to the expiration
of the current bridge contract on March 18, 2018. 3/1/18 Gov’t Resp. Ex. 1 at 2 (Wilson Decl.) (TSA awarded a bridge contract to GDMS with “a one-month period of performance from January
19, 2018 to February 18, 2018, [that] was valued at $327,177.” And, an additional option period
was exercised on February 15, 2018 that extended the period of performance of GDMS’s bridge
contract from February 19, 2018 to March 18, 2018 “and increased the total value by $654,354,
from $327,177 to $981,351.”). For these reasons, the court has determined that GDMS
is not required to provide a security bond.
F. Temporary Restraining Order
Defendant, United States of America,
the Transportation Security Administration, and their
officers, agents, servants, employees, representatives,
and all persons acting in concert and participating with
them respecting the subject procurement, are hereby
temporarily restrained and enjoined from permitting
performance of and/or performing the contract awarded to
Unisys Corporation on October 27, 2017 for Domain
Awareness Integrated Network Support Services under
Request For Quotes No. HSTS04-17-Q-CT2506 for a period of
14 days, i.e., through March 16, 2018. (General
Dynamic Mission Systems, Inc. v. U. S. and Unisys
Corporation, No. 18-49, March 7, 2018.)
In a bid protest, the court may award any relief that it considers proper, including
injunctive relief. 28 U.S.C. § 1491(b)(2). When determining whether to grant a preliminary
injunction, the court must consider: (1) whether the movant is likely to succeed on the merits; (2)
whether the movant will suffer from irreparable harm if an injunction is not granted; (3) whether
the balance of hardships to the parties tips in the movant’s favor; and (4) whether the public
interest favors injunctive relief. Sciele Pharma Inc. v. Lupin Ltd., 684 F.3d 1253, 1259 (Fed. Cir.
2012) (citing Amazon.com, Inc. v. Barnesandnoble.com, Inc., 239 F.3d 1343, 1350 (Fed. Cir.
2001)); see also FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993). “Although the
factors are not applied mechanically, a movant must establish the existence of both of the first
two factors to be entitled to a preliminary injunction.” Altana Pharma AG v. Teva Pharm. USA,
Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009) (citing Amazon.com, 239 F.3d at 1350). With that
caveat regarding a preliminary injunction, “[n]o one factor, taken individually, is necessarily
dispositive. . . . [T]he weakness of the showing regarding one factor may be overborne by the
strength of the others.” FMC Corp., 3 F.3d at 427. A preliminary injunction is “an extraordinary
and drastic remedy, one that should not be granted unless the movant, by a clear
showing, carries the burden of persuasion.” Mazurek v.
Armstrong, 520 U.S. 968, 972 (1997) (emphasis omitted)
(citation omitted).
1. Likelihood of success on the
merits.
(sections deleted)
In concluding that Mr. Montano did not unconditionally own at least 51 percent of
Veterans pursuant to 13 C.F.R. § 125.12, the SBA area office examined Articles 9.01 to 9.03 of
Veterans’ shareholder agreement. AR 2-7; see also AR 48-450. Those Articles provide that if a
shareholder dies, is found to be incompetent, or becomes insolvent, that shareholder “shall be
deemed to have offered all the [s]hares of the [c]orporation owned by such [s]hareholder at the
time of occurrence of any of the events specified above to the [c]orporation and the [c]orporation
shall purchase such [s]hares at the Certificate Value and upon the terms and conditions
hereinafter set forth.” AR 48-450. Relying upon a dictionary definition of “unconditional” that
formed the basis for two previous SBA decisions, International Logistics Grp., 2009 WL
5942359, and Wexford, 2006 WL 4726737, the SBA area office stated that Articles 9.01 to 9.03
placed “impermissible conditions” on Mr. Montano’s ownership interest in Veterans, AR 2-7.
In essence, the shareholder agreement provision cited by SBA is a clause that provides
the company with the first opportunity to purchase the shareholder’s shares when death, incompetency, or insolvency arises. This court previously examined a clause calling for an
optional buy-out in the event of an involuntary withdrawal in the context of 38 C.F.R. § 74.3. In
AmBuild Co., LLC v. United States, 119 Fed. Cl. 10 (2014), the court held that particular clauses
within a company’s operating agreement, including a clause calling for involuntary withdrawal
in the event of bankruptcy and another providing for transfer of ownership by operation of law,
did not affect the unconditional nature of ownership under 38 C.F.R. § 74.3. Id. at 23-26
(concluding that [the VA’s Office of Small and Disadvantaged Business Utilization’s
(“OSDBU”)] decision to decertify AmBuild and remove it from the VetBiz VIP Database was
arbitrary and capricious and not in accord with VA’s regulations”). Correlatively, in Miles
Construction, the court addressed a clause providing a right of first refusal on the part of a
minority shareholder that would arise when a service-disabled veteran owner had a bona fide
offer to sell shares. Miles Constr., 108 Fed. Cl. at 803. The court noted that the right was not
presently executory and was a customary business provision that did not fall afoul of 38 C.F.R. §
74.3:
In sum, the right of first refusal provision in Article XI is not presently executory,
is a standard provision used in normal commercial dealings, and does not burden
the veteran’s ownership interest unless he or she chooses to sell some of his or her
stake. As a result, Article XI, Paragraph 11.01 does not affect the veteran’s
unconditional ownership with regard to C.F.R. § 74.3(b). The decision by
OSDBU to the contrary, i.e., that Articles X, XI, and XII of the operating
agreement rendered Miles ineligible for the VIP database,
was arbitrary and capricious and contrary to law.
Id. at 803.
Additionally, the definition of “unconditional” set forth in Wexford, 2006 WL 4726737,
at *6, and adopted by the SBA area office in its decision addressing Veterans’ eligibility, see AR
2-7, is based upon a dictionary definition of “unconditional,” see Wexford, 2006 WL 4726737, at
*6; see also International Logistics Grp., 2009 WL 5942359, at *4-5 (quoting Wexford, 2006
WL 4726737, at *6). Resort to a dictionary definition of “unconditional” is both unnecessary
and inappropriate. SBA regulations expressly define unconditional ownership in the context of
“socially and economically disadvantaged individuals.” 13 C.F.R. § 124.105. Such regulatory guidance relates to eligibility for a business development program, and it provides insight into
the scope of unconditional ownership for SDVOSB-eligibility. Notably, 13 C.F.R. § 124.105(e)
states that “SBA will disregard any unexercised stock options or similar agreements held by
disadvantaged individuals” in determining whether an applicant unconditionally owns the
company at issue. This provision, which was not addressed by the SBA area office, directly
bears on Veterans’ shareholder agreement and its status as a SDVOSB.
In sum, based upon the foregoing analysis, the SBA area office’s findings underlying the
VA’s decision to remove Veterans from the VIP database fail to provide “a coherent and
reasonable explanation” for SBA’s exercise of discretion, Impresa Construzioni Geom.
Domenico Garufi v. United States, 238 F.3d 1324, 1333 (Fed. Cir. 2001) (citation omitted), or
articulate a “rational connection between the facts found and the choice made,” Motor Vehicle
Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43 (1983) (internal quotation marks
omitted) (quoting Burlington Truck Lines v. United States, 371 U.S. 156, 168 (1962)). The court
therefore finds that Veterans is more likely than not to succeed in proving that the government’s
actions were arbitrary and capricious or not in accordance with law.
2. Irreparable harm.
Veterans asserts that if it is not granted injunctive relief, it will suffer irreparable harm
because it will be deprived of the opportunity to compete for SDVOSB procurements. See Pl.’s
Mem. at 14-15. Upon removal of Veterans from the VIP database, it will be unable to compete
for the roofing and relocation solicitations at issue in this case, as well as any future SDVOSB
solicitations respecting which it would otherwise be an eligible competitor. Id. Further, as a
small business, Veterans represents that its inability to obtain work as a SDVOSB could threaten
its viability. See id. at 15.
The “[d]enial of the opportunity to compete for a contract can constitute irreparable
harm.” Miles Constr., 108 Fed. Cl. at 806 (citing Electronic On-Ramp, Inc. v. United States,
104 Fed. Cl. 151, 169 (2012); NetStar-1 Gov’t Consulting, Inc. v. United States, 101 Fed. Cl.
511, 530 (2011), aff’d, 473 Fed. Appx. 902 (Fed. Cir. 2012)); see also United Int’l Investigative
Servs., Inc. v. United States, 41 Fed. Cl. 312, 323 (1998) (“[T]he opportunity to compete for a
contract and secure any resulting profits has been recognized to constitute significant harm.”)
(citing cases). Providing the injunctive relief contemplated here, i.e., setting aside the CVE’s
removal of Veterans from the VIP database and reinstating Veterans as a qualified SDVOSB,
would circumvent the potential harm to Veterans by allowing it to compete for the SDVOSB setaside
procurements at issue. Thus, the court finds that Veterans will suffer irreparable harm if
injunctive relief is not provided.
3. Balance of hardships.
The government argues that it will be harmed if the relocation solicitation is indefinitely
stayed. Def.’s Resp. at 21-22. Reinstating Veterans into the VIP database, however, would
render Veterans eligible for the relocation solicitation without further delay of that contract.
Given Veterans’ likelihood of success on the merits of its claim and the irreparable harm it will
suffer if injunctive relief is not provided, the court finds that the balance of hardships weighs in favor of granting Veterans’ preliminary injunction and temporarily reinstating Veterans into the
VIP database as a qualified SDVOSB.
4. Public interest.
Finally, the government contends that the public interest does not weigh in favor of
injunctive relief because the upcoming SDVOSB solicitations at issue here have “operate[d]
within the bounds of the law.” Def.’s Resp. at 22 (citation omitted). Such an argument is
misplaced. If the government has wrongfully prevented Veterans from competing for a contract
award that it should be eligible to receive, as Veterans claims, the integrity of that procurement is
compromised. “The public has a strong interest in preserving the integrity of the procurement
process.” KWV, 108 Fed. Cl. at 458 (citing Bona Fide Conglomerate, Inc. v. United States, 96
Fed. Cl. 233, 242-43 (2010); SAI Indus. Corp. v. United States, 60 Fed. Cl. 731, 747 (2004)); see
also PGBA, LLC v. United States, 60 Fed. Cl. 196, 221 (2004), aff’d, 389 F.3d 1219 (Fed. Cir.
2004). Thus, the court finds that the public interest will be served by ensuring that Veterans has
the opportunity to fairly compete for the SDVOSB procurements. (Veterans
Contracting Group, Inc., vs. U. S., No.
17-1015C, August 29, 2017)
On April 13, 2017, the court convened a Status Conference in Alltran, No. 17-517, during
which the Government proposed a thirty-day stay of proceedings in four Bid Protests related to
Solicitation No. ED-FSA-16-R-0009. The Government advised the court that the proposed stay
would maintain the status quo while ED explored a global solution. On the same day, the court
informed all of the parties in Continental Services, No. 17-449, Account Control Technology, No.
17-493, Pioneer Credit Recovery, No. 17-499, and Alltran Education, No. 17-517 of the proposed
stay.
On April 17, 2017, the Government advised the court by email that all of the parties in
Continental Services, No. 17-449, Account Control Technology, No. 17-493, Pioneer Credit, No.
17-499, and Alltran, No. 17-517 agreed to the proposed stay, except intervenor-defendants
Windham Professionals, Inc. (“Windham”) and Premiere Credit of North America, LLC
(“Premiere”). Windham and Premiere argue that the court should not enjoin the ED from
authorizing the awardees, under Solicitation No. ED-FSA-16-R-0009, to perform on contracts that
were properly awarded. Windham and Premiere also argue that the Protestors do not have standing
to seek injunctive relief, because Solicitation No. ED-FSA-16-R-0009 was an indefinite quantity
procurement and the Protestors therefore were not prejudiced by the ED’s decision to award
contracts to other bidders. The objections raised by Windham and Premiere, however, do not
address the need for a stay. Instead, they attempt to re-litigate the merits of the March 29, 2017
TRO and April 10, 2017 TRO Extension.
The court has determined that the proposed stay properly would maintain the status quo
while the parties attempt to reach a global solution. Accordingly, the stay will preserve judicial
resources without prejudicing the interest of any of the parties. For this reason, all proceedings in
Continental Services, No. 17-449, Account Control Technology, No. 17-493, Pioneer Credit, No.
17-499, and Alltran, No. 17-517 are stayed for thirty days, i.e. until Friday, May 19, 2017. See
Cherokee Nation of Oklahoma v. United States, 124 F.3d 1413, 1416 (Fed. Cir. 1997) (“The power
of a federal trial court to stay its proceedings . . . is beyond question. This power springs from the
inherent authority of every court to control the disposition of its cases. When and how to stay
proceedings is within the sound discretion of the trial court.” (internal citations omitted)). On May
19, 2017, the parties will file a Joint Status Report and the court will convene a Status Conference
thereafter at the earliest date convenient to all the parties. The Status Conference previously
scheduled for April 21, 2017 is cancelled.
Under the Rules of the United States Court of Federal Claims, a TRO “expires at the time
after entry—not to exceed 14 days—that the court sets, unless before that time the court, for good
cause, extends it for a like period or the adverse party consents to a longer extension.” RCFC
65(b)(2). For this reason, on April 24, 2017, the court will extend the April 10, 2017 TRO until
May 8, 2017. On May 8, 2017, the court will extend the TRO until May 22, 2017.
(Continental Services
Group, Inc., v. U. S., No. 17-449, April 19, 2017)
On December 11, 2015, the United States Department of Education (“ED”) issued
Solicitation No. ED-FSA-16-R-0009 (“the Solicitation”) for “the collection and administrative
resolution of debts resulting from non-payment of student loans and grants made under several
federal programs, including the Federal Family Education Loan Program, Stafford Loans, Federal
Perkins Loans, and the Pell Grant Program.” Compl. at ¶ 25. Under the Solicitation, ED would
award an “Indefinite Delivery Indefinite Quantity contract [with] a five (5) year Base Ordering
Period [and] an additional Optional Ordering Period of five (5) years.” Compl. at ¶ 26.
On February 22, 2016 and February 29, 2016, Continental Services Group, Inc.
(“Continental Services”) submitted an offer for the Solicitation. Compl. at ¶ 35.
On December 9, 2016, ED notified Continental Services that it was not selected for award;
Continental Services requested a debriefing. Compl. at ¶ 19.
On December 29, 2016, ED issued a
Debriefing Letter, stating that,
Although [Continental Services’]
proposal was one of the most highly rated proposals,
[Continental Services], was not selected for an award
based on the fact that the [ED] determined that they were
not responsible [because] [Continental Services] did not
submit an acceptable subcontracting plan that reflects and
is consistent with the commitments it offered in its small
business participation plan,
as required by the Solicitation.
Compl. at ¶ 51.
On January 3, 2017, Continental Services filed bid protest at the General Accountability
Office (“GAO”). Compl. at ¶ 60. Because Continental Services filed a bid protest in the GAO
within five days of receiving a debriefing, the bid protest triggered an automatic stay of the
performance, pursuant to 31 U.S.C. § 3553(d)(3)(A), (4)(B). Compl. at ¶ 60. “Several other
disappointed offerors also filed protests of this procurement at the GOA.” Compl. at ¶ 60. Some
of these protests also triggered the automatic stay. Compl. at ¶ 60.
On a motion for temporary injunctive relief, the court must weigh four factors: “(1)
immediate and irreparable injury to the movant; (2) the movant’s likelihood of success on the
merits; (3) the public interest; and (4) the balance of hardship on all the parties.” U.S. Ass’n of
Importers of Textiles & Apparel v. United States, 413 F.3d 1344, 1347-48 (Fed. Cir. 2005). “No
one factor, taken individually, is necessarily dispositive . . . . [T]he
weakness of the showing regarding one factor may be
overborne by the strength of others.” FMC Corp. v. United
States, 3 F.3d 424, 427 (Fed. Cir. 1993) (emphasis added).
Regarding the first factor, the court
has determined that Continental Services would be
immediately and irreparably injured, if ED moved forward
with performance on the contract at issue in this case, or
otherwise transferred work to another contracting vehicle
to circumvent or moot this bid protest.
Regarding the second factor, since
the Government has not yet produced the Administrative
Record and the parties have not had an opportunity to
brief the merits of this bid protest, the court is not in
a position to decide Continental Services’ likelihood of
success.
Regarding the third factor, the public interest is served by open and fair competition in
public procurement and preserving the integrity of the competitive process. See PGBA, LLC v.
United States, 57 Fed. Cl. 655, 663 (2003).
Regarding the fourth factor, the balance of hardships weighs in favor of Continental
Services. Courts have generally recognized that any harm to the Government caused by delay in
performance is generally less significant than the harm caused to the bid protestor. Id.
For these reasons, the court has determined that the weight of the factors is in favor of
injunctive relief. See FMC Corp, 3 F.3d at 427 (“[T]he weakness of the showing regarding one
factor may be overborne by the strength of others.”). Accordingly, it is hereby ordered that the
United States of America, the United States Department of Education, and their officers, agents,
servants, employees, and representatives are Temporarily Restrained, pursuant to RCFC
65(d), from:
(1) authorizing the purported
awardees to perform on the contract award under
Solicitation No. ED-FSA-16-R-0009 for a period of fourteen
days, i.e. until April 12, 2017; and
(2) transferring work to be performed
under the contract at issue in this case to other
contracting vehicles to circumvent or moot this bid
protest for a period of fourteen days, i.e. until April
12, 2017. (Continental
Services Group, Inc. v. U. S., No. 17-449, March 29,
2017)
A temporary restraining order is an “extraordinary and drastic remedy, one that should
not be granted unless the movant, by a clear showing, carries the burden of persuasion.” Jones
Automation, Inc. v. United States, 92 Fed. Cl. 368, 370 (2010) (quoting Mazurek v. Armstrong,
520 U.S. 968, 972 (1997)). The standards for determining whether to grant a temporary
restraining order are the same as those that apply to a motion for a preliminary injunction. They
require the moving party to demonstrate that: (1) it is likely to succeed on the merits; (2) it will
be irreparably harmed without injunctive relief; (3) the balance of hardships tips in its favor and
(4) the public interest favors the grant of injunctive relief. Am. Signature, Inc. v. United States,
598 F.3d 816, 823 (Fed Cir. 2010) (citing Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 19
(2008)); see also Erico Int’l Corp. v. Vutec Corp., 516 F.3d 1350, 1353–54 (Fed. Cir. 2008)
(discussing injunctive relief in a patent context); FMC Corp. v. United States, 3 F.3d 424, 427
(Fed. Cir. 1993). “No single factor is determinative, and ‘the weakness of the showing regarding
one factor may be overborne by the strength of the others.’” Contracting Consulting Eng’g LLC
v. United States, 103 Fed. Cl. 706, 709 (2012) (quoting FMC Corp., 3 F.3d at 427). At the same
time, “the absence of an adequate showing with regard to any one factor may be sufficient, given
the weight or lack of it assigned the other factors, to justify . . . denial” of a preliminary
injunction or temporary restraining order. See Chrysler Motors Corp. v. Auto Body Panels of
Ohio, Inc., 908 F.2d 951, 953 (Fed. Cir. 1990). In this case, Munilla has failed persuade the
Court that the balance of the equities favors the extraordinary remedy of a TRO.
First, Munilla has not established a likelihood of success on the merits. Even assuming
that its legal challenge to the award to Seaward were likely to succeed (an issue upon which the
Court expresses no opinion at this point), it is not clear that Munilla possesses standing to bring
such a challenge. To possess standing to bring a bid protest, a plaintiff must be an interested
party within the meaning of 28 U.S.C. § 1491(b)(1), i.e., an actual or prospective bidder (or
offeror) who possesses a direct economic interest in the matter. Sys. Application & Techs., Inc.
v. United States, 691 F.3d 1374, 1382 (Fed. Cir. 2012) (citing Weeks Marine, Inc. v. United
States, 575 F.3d 1352, 1359 (Fed. Cir. 2009)); see also Orion Tech., Inc. v. United States, 704
F.3d 1344, 1348 (Fed. Cir. 2013). In post-award protests, a plaintiff is an interested party, and
thus has standing, where it would have had a “substantial chance” of winning the award “but for
the alleged error in the procurement process.” Info. Tech. & Applications Corp. v. United States,
316 F.3d 1312, 1319 (Fed. Cir. 2003); see also Weeks Marine, Inc., 575 F.3d at 1359; Rex Serv.
Corp. v. United States, 448 F.3d 1305, 1308 (Fed. Cir. 2006).
Here, Munilla has not established that it would have had a substantial chance of winning
the award but for the errors it alleges because—even if the award to Seaward were set aside—the
next lowest-priced technically acceptable offer after Seaward’s was made by another offeror,
Crowley. Def.’s Opp’n App. at Appx248–49; see also SOS Int’l LLC v. United States, 127 Fed.
Cl. 576, 587–88 (2016) (finding that plaintiff lacked standing because, inter alia, the record
indicated it would not have been next in line for the award if its allegations of error were
correct). Crowley’s offer was priced [***] lower than Munilla’s, and [***] higher than
Seaward’s. See Def.’s Opp’n App. at Appx248–49. Particularly given the fact that Crowley’s
total price is so close to Munilla’s the Court has no basis at this time for concluding, as counsel
suggested at oral argument, that an award to Crowley would be subject to the same legal defects
as are alleged with respect to the award to Seaward. Therefore Munilla has not shown a
likelihood of success on the merits and the first factor weighs against the granting of a temporary
restraining order.
Further, the second factor, whether the plaintiff will suffer irreparable harm absent
injunctive relief, also counsels against the issuance of a temporary restraining order. “To
demonstrate an irreparable injury, a plaintiff must show that without a preliminary injunction or TRO it will suffer irreparable harm before a decision can be rendered on the merits.” OAO Corp.
v. United States, 49 Fed. Cl. 478, 480 (2001). Given the expedited briefing schedule the Court is
establishing (which will result in a final decision by January 31, 2017), this means that—to
justify a TRO—Munilla must show that it will suffer irreparable harm in the next month if the
transition activities that began last week continue.
In that regard, Munilla alleges that it will suffer such injury because Seaward “may begin
to hire MCM employees and MCM may not be able to replace or rehire those personnel given
restrictions on personnel who can travel to and work at the Guantanamo Bay Naval Station.”
Pl.’s Mem. at 25. “[A] turnover of MCM's employees,” Munilla further forecasts, “could lead to the loss of personnel with expertise in work at the Guantanamo Bay [N]aval Station,” thereby
“disrupt[ing] MCM's ability to continue to provide services at the base.” Id. In addition,
according to Munilla, “if an injunction is not issued and another contractor begins work but
MCM is ultimately successful in its protest, there could be a second turnover which would result
in significant extra costs.” Id. Finally, Munilla expresses concern that its chances for securing
relief other than bid preparation costs would be adversely affected if the transition to Seaward
were permitted to move forward at this time. See id. at 24.
The Court finds these allegations insufficient to establish irreparable harm. First, the loss
of personnel by an incumbent contractor during a transition period generally does not constitute
irreparable injury. See, e.g., IBM Corp. v. United States, 118 Fed. Cl. 677, 684–85 (2014) (“the
mere fact that an incumbent's employees begin to move over to work for the awardee does not,
without more, constitute irreparable harm”); Eskridge Research Corp. v. United States, 92 Fed.
Cl. 88, 99 (2010) (stating that “the decision of [incumbent-protester's] employe[e]s to work for
[awardee] is not the kind of injury that constitutes irreparable harm”); Comput. Scis. Corp. v.
United States, 51 Fed. Cl. 297, 323 n.91 (2002) (“[A] potential loss of employees is not an
irreparable harm.”); PGBA, LLC v. United States, 60 Fed. Cl. 196, 221 (2004) (loss of
employees is “significant,” but not an irreparable injury, because the court would then be
required “to consider any incumbent contractor's loss of a successor contract to be irreparable
harm”), aff’d, 389 F.3d 1219 (Fed. Cir. 2004).
Further, and in any event, Munilla’s claims that it is likely to lose personnel over the next
month if a temporary restraining order is not granted appear to be supported by little more than
conjecture. See Pl.’s Mem. Ex. 1 ¶ 23 (observing that if another contractor is permitted to
mobilize “that contractor may begin to hire MCM employees and MCM may not be able to
replace or rehire those personnel given restrictions on personnel who can travel to and work at
the Guantanamo Bay Naval Station”). Indeed, it seems likely that even if the employees who are
currently performing the work at Guantanamo Bay Naval Station for Munilla accept job offers
from Seaward for work to begin on February 1, they would choose to remain as Munilla’s
employees if the Court enjoined the award of the contract to Seaward at the end of January.
The Court finds similarly unpersuasive Munilla’s other allegation of irreparable injury,
which is based on an argument that allowing a transition to begin now would impair its chances
of securing any relief other than bid protest costs even if it ultimately prevails in this litigation. A
“contention that without a preliminary injunction, [the awardee] will become so entrenched that
[the protester] will have lost its opportunity to compete does not demonstrate irreparable harm.”
Eskridge Research Corp., 92 Fed. Cl. at 99; see also Sierra Military Health Servs., Inc. v. United
States, 58 Fed. Cl. 573, 582 (2003) (noting that other courts have rejected the claim that the
contract awardee would become so entrenched during transition that the protester would be
irreparably harmed without an injunction).
Finally, given the lack of irreparable harm to Munilla, the balance of the hardships
weighs against a TRO. The transition process has already begun. Halting it now with the
possibility of having to resume it in February would be, if nothing else, disruptive to the government and to Seaward.2 Nor does the public interest support the issuance of a temporary
restraining order. To be sure, the public has an interest “in honest, open, and fair competition in
the procurement process.” GEO Grp., Inc. v. United States, 100 Fed. Cl. 223, 230 (2011)
(quoting Software Testing Sols., Inc. v. United States, 58 Fed. Cl. 533, 538 (2003)). Nonetheless,
“[i]t is equally clear . . . that a procuring agency should be able to conduct procurements without
excessive judicial infringement upon the agency’s discretion.” Id. (quoting Aero Corp. S.A. v.
United States, 38 Fed. Cl. 237, 242 (1997)). In this case, given that Munilla has failed, at least at
this early stage, to demonstrate a likelihood of success on the merits, the Court concludes that the
latter interest should prevail. (Munilla
Construction Management, LLC v, U. S. Seaward Services,
Inc. No. 16-1684C, January 10, 2017)
The Government’s failure to institute the CICA’s automatic stay in this case is founded
neither in fact nor law. The record is absolutely clear that Plaintiff learned of the contract award
via the September 27, 2016 Notice of Award. The Notice of Award is marked “September 27,
2016,” and no other date appears that awards the BPAs. Pl. Mem. Ex. A. Nor were there any
other publically available notices of the award date, and nothing in the nearly 300-page October
24, 2016 Appendix submitted by the Government suggests anything to the contrary. In addition,
the Government has not demonstrated, either in the two status conferences convened by the court
in this case or in its filings, how Plaintiff was supposed to know that the contract was awarded by
DIA on September 26, 2016.
The Government attempts to overcome the facts by suggesting that Plaintiff’s Notice of
Award within one day of the actual award date was “timely under any reasonable definition.” Gov’t Resp. at 3–4. Although this may be so, it does not overcome the evidence that the Notice
of Award stated that award was made on September 27, 2016.
In addition, Systems Plus, Inc. v. United States, 58 Fed. Cl. 206, 208 (2005), does not stand
for the rule suggested by the Government, that the automatic stay deadline is measured from the
date of award, regardless of the knowledge of Plaintiff, nor is it precedent. Systems Plus concerned
whether a bid protestor was entitled to an automatic stay under section 3353(d)(4)(B), because that
section provides a 5 day deadline for an automatic stay, after a requested and required debriefing.
Id. at 208 (“[The bid protestor] contends that, because a debriefing was required … the GAO’s
[notice that] a protest was pending triggered a suspension of performance under 31 U.S.C.
§ 3553(d)(4)(B).”). Instead, this case concerns section
3553(d)(4)(A), the section that provides a 10- day
deadline from the date of contract award.
Congress enacted the automatic stay
to provide the GAO with a “strong enforcement mechanism.”
H.R. Conf. Rep. No. 98–861 at 1435 (1984). The automatic
stay provision cannot function, as intended, if potential
bid protestors do not know how long they have to file
before they lose their right to an automatic stay. Without
knowledge of the actual award date, potential bid
protestors would be forced to guess how much of the 10-day
period was remaining before filing a protest with the GAO
and effectively would be deprived of a statutory right.
The relevant implementing regulations require that “after award, ordering activities should
provide timely notification to unsuccessful offerors,” and, in cases where an award is based on
factors other than price, the awarding agency should provide a “brief explanation of the basis of
the award.” 48 C.F.R § 8.405-3(b)(3) (emphasis added). For an offeror to exercise the right to file
a protest before the GAO, the offeror is entitled to both notice of award and an explanation of why
they did not receive the award.
An analogous provision, governing bid protests before the GAO, provides that:
Protests [other than protests based upon alleged improprieties in a solicitation] shall
be filed not later than 10 days after the basis of protest is known or should have
been known (whichever is earlier)[.]
4 C.F.R. § 21.2 (emphasis added ).
In other words, a potential bid protestor cannot be
expected to file a bid protest before they know when an
award is made and the grounds upon which a protest may be
based.
Even assuming, arguendo, that the section 3553(d)(4)(A) 10-day deadline is measured
regardless of the actual notice of the date of award, the Government has not proffered evidence in
this case that the date of award was September 26, 2016. The BPAs surfaced only after Plaintiff
was informed that the 10-day stay would not be instituted, but they all indicate an award date of
September 27, 2016. The signature block on all three BPAs state that the “Date Signed” by the
Contracting Officer was September 27, 2016. Gov’t App’x at A118, A143, A244. In addition,
two out of the three BPAs—the Axiologic and IIC awards, respectively—indicate that the
“Award/Effective Date” of the Contract was September 27, 2016. Gov’t App’x at A118, A244.
Although the BPAs indicate that they were signed by the awardees on September 26, 2016,
(Gov’t App’x at A118, A143, A244), the general rule is that a contract is not formed, until mutual
intent to contract is expressed, including offer and acceptance. See Trauma Service Group
v. United States, 104 F.3d 1321, 1325 (Fed. Cir. 1997) (providing that the requirements of a
government contract are “mutual intent to contract including an offer and acceptance,
consideration, and a Government representative who had actual authority to bind the
Government”). Acceptance by the Government requires agreement by a person with actual
authority to bind the Government in contract. Id. In this case, the BPAs show that the documents
were signed by the Contracting Officer, i.e., the person authorized to bind the Government, on
September 27, 2016, so that contract formation did not occur until that date.
The Government included in the October 24, 2016 Appendix internal DIA e-mails that
demonstrate that the agency’s CMS system generated a “fully-executed contract package” on
September 26, 2016. The Government argues that these internal communications conclusively
establish that the contract was signed on September 26, 2016, because, according to a sworn
Declaration of a DIA contract specialist, “CMS will not distributed a final contract package
without a signature page.” Gov’t Resp. at 1 (citing Gov’t App’x at A144–145). 12 The fact that
the contracts were shared internally within DIA on September 26, 2016, however, does not change
the fact that the only notice furnished to Plaintiff stated a date of September 27, 2016. Of course, this is why the Government did not provide any legal authority for the proposition that the date of
a computer-generated “contract package” takes precedence over the signed contracts at issue.
The Government declarants attempt to explain why the September 27, 2016 date on the
face of the BPAs should be disregarded. Gov’t App’x at A1–A3 (Declaration of Donald F.
Camden); A4–A7 (Declaration of Ryan Corcoran Luhman); A144–148 (Declaration of Holly
Carr). The Declarations essentially assert the following: (1) the September 27, 2016 date was
“prepopulated” on the face of the BPAs, because the contracts were originally planned to be
awarded on that date; (2) the BPAs were actually signed by hand by representatives of the awardees
and by a DIA representative on September 26, 2016; (3) that DIA forgot to change and/or failed
to notice the September 27, 2016 date before the documents were signed and uploaded into the
CMS.13
These Declarations, however, do not explain how Plaintiff was supposed to learn of the
actual date of award, other than the Notice of Award sent by DIA. And, again, the Government
cites no law in support of the proposition that intent of a contracting officer can vary the face of a
signed contract. In other words, DIA did not institute the automatic stay, because it contends that
internal agency documentation should control the date of award. But, that is contrary to the
CICA’s automatic stay provision.
or these reasons, the court has determined that DIA’s decision not to institute the
automatic stay, based on the timeliness of Plaintiff’s filing was arbitrary, capricious, contrary to
law and an abuse of agency discretion. (Favor
TechConsulting, LLC v. U. S., No. 16-1365 C, November
3, 2016)
On a motion for temporary injunctive relief, the court
must weigh four factors: “(1) immediate and irreparable
injury to the movant; (2) the movant's likelihood of
success on the merits; (3) the public interest; and (4)
the balance of hardship on all the parties.” U.S. Ass'n of
Importers of Textiles & Apparel v. United States, 413 F.3d
1344, 1347-48 (Fed. Cir. 2005). “No one factor, taken
individually, is necessarily dispositive . . . . [T]he
weakness of the showing regarding one factor may be
overborne by the strength of others.” FMC Corp. v. United
States, 3 F.3d 424, 427 (Fed. Cir. 1993) (emphasis added).
With respect to the first factor,
Plaintiff’s immediate and irreparable injury is the denial
of the right to an automatic stay at the GAO. The CICA
provides that, timely notification of the contracting
agency of the pending protest triggers an automatic stay
of performance. See § 31 U.S.C. 3353(d). Absent an
automatic stay, an awarding agency would be able to move
forward with performance. Therefore, in this case,
Plaintiff will be deprived of a statutory right provided
by Congress to preserve GAO review of the merits of a bid
protest. See 31 U.S.C. § 3553(d).
With respect to the second factor,
the exhibits attached by Plaintiff to the October 19, 2016
Memorandum In Support evidence a Notice of Award date of
September 27, 2016. Pl. Mem. Ex. A. The statutory period
for timely notice is ten days after contract award. See 31
U.S.C. 3353(d)(4)(A). Plaintiff filed the protest on
October 7, 2016, which is within 10 days of September 27,
2016. Absent any documentation to the contrary, Plaintiff
has shown a likelihood of success on the merits.
With respect to the third factor,
during the October 19, 2016 telephone Status Conference,
counsel for the Government stated that immediate
performance was “mission critical.” The CICA provides that
an awarding agency may override an automatic stay and
proceed with contract performance upon a written
determination that: either (1) performance of the contract
is in the best interest of the United States; or (2)
urgent and compelling circumstances that significantly
affect interests of the United States will not permit
waiting for the decision of the Comptroller General. 31
U.S.C. § 3553(d)(3)(C). To date, the awarding agency in
this case has not issue a statutory override. Furthermore,
nothing before the court demonstrates that “urgent and
compelling circumstances” dictate that the agency not wait
for the GAO’s determination. The public interest would not
be impaired by a temporary restraining order to allow the
Government to furnish the necessary documents to the court
to establish the award date was September 26, 2016.
With respect to the final factor, the
balance of hardships weigh in favor of Plaintiff. Absent a
TRO, Plaintiff will be deprived of the statutory automatic
stay of performance.
Accordingly, for the reasons set
forth herein, it is hereby ordered that: the United States
of America, the Defense Intelligence Agency, and their
officers, agents, servants, employees, and representatives
are Temporarily Restrained from authorizing the purported
awardees to perform under the BPAs for a period of 7 days,
i.e., until October 26, 2016, from the issuance of this
Order. See RCFC § 65(d). In the interim, the Government is
ordered to provide documentation demonstrating that the
award of the contract was on September 26, 2016, as
opposed to September 27, 2016. In light of the limited
time period of this Order, the court has determined that
Plaintiff need not issue a security. See RCFC 65(c).
(Favor TechConsulting, LLC v.
U. S., No. 16-1365 C, October 19, 2016)
Pursuant to Rule 62(c) of the Rules of the United States Court of Federal Claims,
“[w]hile an appeal is pending from . . . a final judgment that grants, dissolves, or denies an
injunction, the court may suspend, modify, restore, or grant an injunction on terms for bond or
other terms that secure the opposing party’s rights.” Rule 62(c). Because Plaintiff in its
complaint requested only declaratory relief, the Court did not technically deny an injunction.
See Compl. 33; 126 Fed. Cl. at 236. Nevertheless, by declining to declare the award illegal, the
Court refused to set aside the contract or grant what would have been tantamount to injunctive
relief. As such, Rule 62(c) is the proper procedural vehicle for the relief Plaintiff now seeks.
An injunction pending appeal pursuant to Rule 62(c) is an extraordinary remedy, and the
Court will not grant such an injunction lightly. RLB Contracting, Inc. v. United States, 120 Fed.
Cl. 681, 682 (2015); see also Akima Intra-Data, LLC v. United States, 120 Fed. Cl. 25, 27
(2015); Acrow Corp. of Am. v. United States, 97 Fed. Cl. 182, 183 (2011). As with injunctions
at other stages of an action, the movant carries the burden of persuasion. Akima Intra-Data, 120
Fed. Cl. at 27 (citing OAO Corp. v. United States, 49 Fed. Cl. 478, 480 (2001)).
Similar to the Court’s consideration of a request for a preliminary injunction, the Court
will consider the following factors when determining whether to grant an injunction pending
appeal: whether the movant has shown that (1) the movant is likely to prevail on the merits of the
appeal; (2) the movant will be irreparably harmed absent an injunction; (3) the injunction will
not substantially injure the other interested parties; and (4) issuance of an injunction is in the
public interest. Int’l Res. Recovery, Inc. v. United States, 60 Fed. Cl. 1, 6 (2004) (citing FMC
Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993)); RLB Contracting, 120 Fed. Cl. at 682
(citing Acrow Corp. of Am., 97 Fed. Cl. at 184); Akima Intra-Data, 120 Fed. Cl. at 27-28 (citing
Standard Havens Prods., Inc. v. Gencor Indus., Inc., 897 F.2d 511, 513 (Fed. Cir. 1990)). The
Court’s consideration of these four factors is “flexible” - - no single factor is determinative, and
the Court need not give each factor equal weight. Standard Havens Prods., 897 F.2d at 512; see
also Akima Intra-Data, 120 Fed. Cl. at 28; Int’l Res. Recovery, 60 Fed. Cl. at 6.
(sections deleted)
Conclusion
This protest does not involve any
novel or close legal questions. Plaintiff has failed to
show a likelihood of success on the merits, and the
balance of harms and the public interest support denying
the requested injunctive relief. Plaintiff’s motion for
stay and injunction pending appeal is DENIED. (Lawson
Environmental Services, LLC, v. U. S. No. 15-1550C,
August 16, 2016)
In sum, Wallace has not met its heavy burden to show that
it is entitled to a temporary restraining order or to a
preliminary injunction. First, Wallace does not appear to
have standing to challenge the contract awards for four of
the five contracts in dispute in this matter. In addition,
even if the Court were to accept that Wallace would suffer
irreparable harm if the Court were to deny its motions,
Wallace has failed to demonstrate that it is likely to
succeed upon the merits of its claims. In this regard, the
record currently before the Court shows that HUD conducted
a reasonable evaluation of the past/present performance
factor for the offers submitted by Wallace and BLM. The
record also shows that HUD appropriately investigated the
potential organizational conflict of interest involving
BLM, and that BLM is qualified to perform the subject
contracts. Lastly, the public interest in ensuring that
the properties maintained by HUD are safe for the public
is best served by denying Wallace’s motion.
For these reasons, the Court will not interfere with this
procurement by enjoining BLM’s performance under the
contracts. And so, the Court denies Wallace’s motion for a
temporary restraining order. (Wallace
Asset Management, LLC v. U. S. and BLM Companies, LLC,
No. 15-1527C, April 20, 2016) (pdf)
STANDARDS FOR DECISION
To grant the “extraordinary
relief” of preliminarily enjoining a prospective award of
a contract before a hearing on the merits of a protest,
the court must consider four factors: (1) likelihood of
the protestor’s success on the merits, (2) irreparable
harm to the protestor if an injunction is not granted, (3)
whether the balance of hardships tip in movant’s favor,
and (4) the public interest. FMC Corp. v. United States, 3
F.3d 424, 427 (Fed. Cir. 1993); see also KWV, Inc. v.
United States, 108 Fed. Cl. 448, 455 (2013); EOD Tech.,
Inc. v. United States, 82 Fed. Cl. 12, 19 (2008). “No one
factor, taken individually, is necessarily dispositive.”
FMC Corp., 3 F.3d at 427. Nonetheless, the protestor must
establish the first two factors (likelihood of success on
the merits and irreparable harm) before a preliminary
injunction can be granted; the other two factors “are not
required but are weighed in the balance.” KWV, Inc., 108
Fed. Cl. at 455 (citing Altana Pharma AG v. Teva Pharm.
USA, Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009) (“Although
the factors are not applied mechanically, a movant must
establish the existence of both of the first two factors
to be entitled to a preliminary injunction.”)).
ANALYSIS
A. Per Aarsleff’s Likelihood
of Success on the Merits
The court’s review of the merits
of a bid protest is governed by the Administrative
Procedure Act (“APA”), 5 U.S.C. § 706. See 28 U.S.C. §
1491(b)(4) (“In any action under this subsection, the
courts shall review the agency’s decision pursuant to the
standards set forth in section 706 of title 5.”). A court
may set aside an agency decision that was “arbitrary,
capricious, an abuse of discretion, or otherwise not in
accordance with law.” 5 U.S.C. § 706(2)(A). In the context
of a bid protest, the court may set aside a procurement
decision where “(1) the procurement official’s decision
lacked a rational basis; or (2) the procurement procedure
involved a violation of regulation or procedure.” Impresa
Construzioni Geom. Domenico Garufi v. United States, 238
F.3d 1324, 1332 (Fed. Cir. 2001); see also Innovation Dev.
Enters. of Am., Inc. v. United States, 108 Fed. Cl. 711,
723 (2013) (discussing this standard in the context of a
sole-source procurement). The protestor must establish “‘a
clear and prejudicial violation of applicable statutes or
regulations.’” Impresa Construzioni, 238 F.3d at 1333
(quoting Kentron Hawaii, Ltd. v. Warner, 480 F.2d 1166,
1169 (D.C. Cir. 1973)).
Per Aarsleff argues that the Air
Force incorrectly determined in its Justification and
Approval that there was an “unusual and compelling
urgency” for the bridge contract. Pl.’s Mot. for Prelim.
Inj. at 5. Per Aarsleff notes that the Air Force had
another contract vehicle available—the six-month extension
of the incumbent contract under FAR § 52.217-8—to cover a
short-term need for services at Thule, which would
preserve the open, competitive solicitation for the
longer-term contract. Id. Per Aarsleff contends that even
if there was an “unusual and compelling urgency” for
services at Thule, the Air Force violated FAR §
6.302-2(c)(2) by pursuing a sole-source bridge contract
instead of considering offers from other sources,
including Per Aarsleff’s offer under the original
solicitation. Id. at 5-6 (citing California Indus.
Facilities Res., Inc. v. United States, 100 Fed. Cl. 404,
410-11 (2011)). Per Aarsleff supports these contentions by
suggesting that the Air Force engaged in “gamesmanship” by
not awarding the long-term Thule contract to Per Aarsleff
after the court enjoined the award to Exelis Services on
May 28, 2015, and instead spending weeks working on the
Justification and Approval for the bridge contract. Id. at
7-8. As a result, Per Aarsleff claims the Justification
and Approval violates FAR § 6.301(c), which states that
“lack of advance planning” and “concerns related to the
amount of funds available” are not sufficient
justifications for contracting without full and open
competition. Id. at 8-9.
Per Aarsleff asserts that if it
were to have been awarded the contract in mid-August 2015,
it would have “fully anticipate[d] completing transition
by December 2015 or January 2016.” Pl.’s Mot. for Prelim.
Inj. App. (Decl. of Karl Andreassen (Aug. 13, 2015) (“Andreassen
Decl.”))) at 2. Per Aarsleff indicated that it “can begin
mobilization immediately,” and that the impending end of
the “port season” is not a problem because “Greenland
Contractors has already ordered all of the supplies needed
for the winter.” Andreassen Decl. at 2; see also Hr’g Tr.
65:24-25, 66:1-12 (confirmation by counsel for Greenland
Contractors that the supply of Thule for the winter has
essentially been completed). Per Aarsleff also stated that
it “intends to [***].” Andreassen Decl. at 2. However, Per
Aarsleff does not dispute that the Air Force must extend
Greenland Contractors’ existing contract at least until
December 2015, to enable a transition with Per Aarsleff to
be completed. See id. (“We are asking the Court to . . .
compel [the Air Force] to use the shorter option period
available under the existing incumbent contract, for a
period no longer than necessary to effectuate the
transition [with Per Aarsleff] (likely no more than three
months).”).
All parties agree that the Air
Force needs to extend its contract with Greenland
Contractors beyond September 30, 2015. See, e.g., First
King Decl. at 11-12 (estimating that even if the Air Force
awarded the Thule contract to Per Aarsleff in mid-June
2015, Per Aarsleff could not assume the full
responsibilities until January 2016 the earliest);
Andreassen Decl. at 2 (stating that if Per Aarsleff was
awarded the contract in mid-August 2015, it could assume
full responsibilities in December 2015 or January 2016).
Transition time between Greenland Contractors and the new
awardee was contemplated in the original solicitation
because of Thule’s remote location and limited access to
the base outside of the summer months. See Per Aarsleff,
121 Fed. Cl. at 607-08, 618; see also AR 20e-777 (RFP No.
FA2523-12-R006) (noting the planned eight-month transition
time). Although the Air Force and Greenland Contractors
have ensured Thule will be supplied for the winter, any
new awardee would still need to assemble the necessary
staff and make arrangements to sustain operations before
Greenland Contractors could depart. Andreassen Decl. at 2.
In this sense, the Air Force’s decision to extend its
contract with Greenland Contractors to allow for
additional transition time is justified.
It is also nonetheless evident
that the Air Force did not fully consider all available
alternatives before deciding to pursue a bridge contract
with Greenland Contractors. Following the injunction of
the award to Exelis Services, the Air Force’s contracting
officer stated that the Air Force considered options for
proceeding that included (1) awarding the contract to Per
Aarsleff, as the next-lowest-price offer under the prior
solicitation, (2) cancelling the solicitation and
conducting a new competitive procurement after the United
States and Denmark finished developing the new eligibility
criteria, or (3) seeking revised proposals under the prior
procurement “with or without amending the solicitation.”
Second King Decl. at 18. If so, any such consideration of
those exceptions is not apparent from the Justification
and Approval because none of those options is mentioned
there. Rather, the main focus of the Air Force’s efforts
during the time after the injunction was securing a bridge
contract with Greenland Contractors and not preparing for
the longer-term provision of services at Thule.
The Air Force points to the
pending appeals of the decision in the prior protest as a
reason for waiting to address or prepare for a long-term
contract. Even with an expedited schedule for the
appeals—which none of the five parties to the appellate
case had requested as of the hearing on Per Aarsleff’s
motion for a preliminary injunction on August 28, 2015,
see Hr’g Tr. 12:21-25, 49:10-13—considerable time will
pass before final disposition of the appeals. In short,
although the Air Force has established an “unusual and
compelling urgency” for a bridge contract of six to eight
months’ duration, it has not provided a rational basis for
a longer term extension.
The likelihood of success is
currently in balance. The bridge contract has not yet been
awarded and the original solicitation is still open.
Several factors important to the merits of this protest
are uncertain. The salient dispute is whether, by
selecting a contract vehicle with the potential for
extending the bridge contract for up to two years in lieu
of an award under the prior solicitation, the Air Force
acted arbitrarily, capriciously, or unlawfully. This
question cannot be answered with any assurance in the
context of the pending motion for a preliminary
injunction. [Note: Excerpt ends here for
protester's failure to establish first factor.] (Per
Aarsleff A/S v U. S. and Greenland Contractors I/S,
No. 15-873C, September 16, 2015) (pdf)
As described earlier, plaintiff was the incumbent
contractor providing the [Federal Bureau of Prisons] BOP
with [Residential Reentry Center] RRC Services in
Clarksburg, West Virginia. AR 711. On June 5, 2012, the
BOP issued the RFP, seeking RRC Services for inmates in
northern West Virginia. Id. at 1. For the next three
years, plaintiff filed three protests that delayed the
award of the contract. The procurement continued, and
plaintiff’s existing contract expired on July 31, 2013.
Id. at 711. Consequently, in the absence of a contract
award, the BOP executed three consecutive seven-month
sole-source bridge contracts with plaintiff. Id. at 711,
715, 727, 736. Ultimately, on March 30, 2015, while
plaintiff’s third sole-source bridge contract was ongoing,
defendant awarded the contract for RRC Services in
northern West Virginia to Dismas. Id. at 275. On April 6,
2015, plaintiff filed its protest with the GAO, id. at
531, and on April 10, 2015, the BOP suspended all actions
pertaining to the newly awarded contract to Dismas, id. at
275, 277-78. Because plaintiff filed its protest within
five days of receipt of the debriefing letter, plaintiff
was entitled to an automatic stay under CICA. 48 C.F.R. §
33.104(c)(1). Plaintiff’s third seven-month sole-source
bridge contract expired on April 30, 2015. AR 736. After
that date, defendant transferred the inmates from
plaintiff’s Clarksburg facility to defendant-intervenor’s
facility in Charleston, West Virginia and Renewal’s
facility in Pittsburgh, Pennsylvania. Id. at 866.
In its motion, plaintiff contends
that because defendant failed to provide the requisite
written notice of the transfer of inmates, the transfer
amounted to a de facto override of the automatic stay,
thus violating CICA. Pl.’s Mot. 4, 7. Plaintiff alleges
injury arising from the transfer of inmates, which
required Bannum to shut down its Clarksburg facility,
resulting in the loss of a significant number of
employees. Id. at 4-5. Additionally, plaintiff argues that
an injunction is justified because the transfer of inmates
to two other cities, each over 100 miles away, interrupted
the inmates’ “entire treatment plan” by severing their
ties with the Clarksburg community. Id. at 5. Given the
totality of the circumstances, plaintiff asserts, the BOP
should be preliminarily enjoined from transferring the
inmates to defendant-intervenor’s and Renewal’s respective
facilities. Id. at 14.
The court rejects plaintiff’s
contentions. First, plaintiff cannot prevail because the
BOP’s transfer of the inmates to other RRC facilities
pursuant to separate, pre-existing contracts between the
BOP and Dismas, and between the BOP and Renewal,
respectively, did not constitute a de facto override of
the CICA stay. The newly awarded contract for RRC services
in northern West Virginia, which is the subject of the
pending protest before the GAO, is wholly distinct from
the extension of the BOP’s pre-existing contract with
Dismas and from the use of the BOP’s pre-existing contract
with Renewal to provide RRC Services at their respective
facilities in Charleston, West Virginia and Pittsburgh,
Pennsylvania. Indeed, “[w]hile an override is meant to
authorize performance on the protested contract because of
special circumstances,” the extension of a pre-existing
contract to provide services during the pendency of the
protest is “a separate, self-contained contract.” Access
Sys., Inc. v. United States, 84 Fed. Cl. 241, 243 (2008).
For example, the BOP’s three seven-month sole-source
bridge contracts with plaintiff were merely “interim
contract[s]” to perform the “exact same services” required
by the June 2012 solicitation. Reilly’s Wholesale Produce
v. United States, 73 Fed. Cl. 705, 708 (2006). These
contracts were initiated to fulfill the BOP’s need for RRC
Services as the procurement process continued, and were
different from the contract that was ultimately awarded to
defendant-intervenor pursuant to the solicitation.
Similarly, when plaintiff’s third bridge contract expired
on April 30, 2015, the BOP’s transfer of some inmates from
plaintiff’s facility to defendant-intervenor’s facility
constituted an extension of a pre-existing contract to
perform the same services required by the solicitation, in
order to fulfill the BOP’s need for RRC Services during
the pendency of the GAO protest. Along the same lines, the
BOP’s transfer of the remaining inmates from plaintiff’s
facility to Renewal’s facility was the use of an existing
contract to obtain the same services required by the
solicitation. The BOP’s extension of its pre-existing
contract with Dismas and the BOP’s use of its pre-existing
contract with Renewal is different from the newly awarded
contract award that plaintiff is protesting before the
GAO.
Plaintiff contends that “some
amount of th[at newly awarded] contract work (i.e. inmate
referrals) [is] being given to” Dismas under the extension
of its pre-existing contract with the BOP, and that the
court in Access Systems held that that is a “functional
equivalent of an override.” Pl.’s Reply 3. Contrary to
plaintiff’s assertion, in Access Systems, the court
specifically held that if the other “contract is for the
identical . . . services involved in the original
contract, this fact alone is insufficient to prove that
the [other] contract is an iteration, in whole or in part,
of the original contract and, thus, an override.” 84 Fed.
Cl. at 243. Indeed, the court reasoned that “[c]ontracts
may share the same subject matter and yet remain separate
and distinct from one another,” and that the other
“contract is not a partial iteration of the original
contract but is a new contract with a distinct character
and function.” Id. Thus, even as the subject matter of the
two contracts here is the same—i.e. providing RRC Services
to the same group of inmates—the contracts are distinct,
and therefore, extending the BOP’s pre-existing contract
with Dismas did not override the stay of the newly awarded
contract pursuant to the solicitation.
Second, the court is similarly
unpersuaded by plaintiff’s argument that there was no
reason for the transfer of inmates because, as the
incumbent contractor, it had a “fully compliant facility.”
Pl.’s Mot. 8. Pursuant to 18 U.S.C. § 3621(b), Congress
conferred on the BOP the authority and discretion to
“designate the place of [a federal] prisoner’s
imprisonment.” The BOP “may designate any available penal
or correctional facility that meets minimum standards of
health and habitability established by the [BOP], whether
maintained by the Federal Government or otherwise . . .
that the [BOP] determines to be appropriate and suitable,
considering . . . the resources of the facility
contemplated[,]” among other factors. 18 U.S.C.
§ 3621(b). Moreover, the BOP “may at any time, having
regard for the same matters, direct the transfer of a
prisoner from one penal or correctional facility to
another.” Id. Here, plaintiff provides no evidence for its
contention that its facility was fully compliant. It
appears that the predicate for plaintiff’s argument is its
sense of entitlement to a fourth bridge contract. There is
no legal support for plaintiff’s view. The law is well
settled that the court will not consider arguments made
without proper substantiation. Gilda Indus. Inc. v. United
States, 446 F.3d 1271, 1281 (Fed. Cir. 2006) (stating that
attorney argument is not considered evidence).
Third, there is no dispute that
the BOP retained the authority conferred upon the agency
by Congress to make the decision regarding where to assign
inmates. The court notes that the BOP’s inspection of
plaintiff’s Clarksburg facility revealed concerns
regarding sanitary conditions, inmates’ physical safety,
and satisfactory provision of food and medicine. The BOP
was also aware of unprofessional conduct demonstrated by
two of plaintiff’s staff members, one who engaged in
discriminatory behavior, and the other, the director of
the facility, who arrived at work intoxicated. It is clear
that the BOP exercised the discretion granted to it by
Congress when declining to offer plaintiff a fourth bridge
contract, and instead chose to exercise its rights under
separate, pre-existing RRC Services contracts with
defendant-intervenor and Renewal, respectively. See Def.’s
App’x 4-6. Moreover, defendant merely extended its
pre-existing contract with Dismas and used its
pre-existing contract with Renewal to meet the ongoing
need for RRC Services until the current GAO protest is
resolved.
(section deleted)
In sum, because the separate,
pre-existing contract between the BOP and Dismas, as well
as the separate, existing contract between the BOP and
Renewal, are distinct from the contract awarded pursuant
to the June 2012 solicitation, the court finds that the
transfer of inmates to defendant-intervenor’s facility in
Charleston, West Virginia and Renewal’s facility in
Pittsburgh, Pennsylvania was not a de facto override of
the automatic CICA stay. See Access Sys., 84 Fed. Cl. at
243 (finding that because the other contract was different
from the contract subject to the protest, it was “not an
override of the automatic stay” required by CICA). The
absence of an override leads inextricably to the
conclusion that the automatic stay pursuant to CICA was
not violated. Accordingly, the court need not engage in a
merits evaluation concerning whether a de facto override
of the stay was defensible. (Bannum, Inc. v. U. S.
and Dismas Charities, Inc., No. No. 15-440C, June 15,
2015) (pdf)
On February 10, 2015, CF Day filed a size protest with the Small Business
Administration (“SBA”) alleging that Loyal Source is not an eligible small
business because it is unduly reliant on a large business subcontractor to
perform the work. On March 12, 2015, the SBA issued a decision finding that
Loyal Source was not a small business on the date of award. Loyal Source has
appealed SBA’s decision to the SBA Office of Hearings and Appeals.
On February 23, 2015, CF Day filed a bid protest at the GAO
arguing that the Army failed to follow the solicitation criteria and that Loyal
Source’s award should be terminated. AR 41. CF Day asserts that the Army
misevaluated the offerors’ past performance by improperly assessing relevance,
misapplying NAICS codes, and failing to consider public information about Loyal
Source’s past performance. Additionally, CF Day argues that the Army
misevaluated offerors’ proposals under the Management/Technical factor of the
solicitation. CF Day’s protest is pending at the GAO, and a decision is expected
within 100 days from the date of filing, not later than June 3, 2015. 31 U.S.C.
§ 3554(a)(1).
On March 11, 2015, General Dennis L. Via, Head of the
Army’s Contracting Activity, authorized an override of the automatic stay. In
his determination, General Via stated:
The timely execution of contract W15QKN-15-D-0015 plays a
critical role in the Army’s and Marine Corps’ combat operations. The CICA stay
seriously jeopardizes the ability of the Army and the Marine Corps to execute
planned fieldings that substantially enhance the performance of their mission,
and save the lives of Warfighters. Waiting for GAO’s resolution of this
protest would significantly increase the time within which these critically
needed services would be delivered to the Warfighter. Such a delay would also
result in the increased risk of injury and loss of life. Therefore, based on
the findings set out in this document, it is my determination that
authorization for continued performance of the contract, notwithstanding the
pendency of this protest, is in the best interests of the United States.
AR 21.
CF Day filed suit in this Court on March 19, 2015
challenging the Army’s stay override, and on March 23, 2015, the Court conducted
a telephonic hearing on CF Day’s application for a temporary restraining order
(“TRO”). Upon considering the arguments of counsel, the Court entered a TRO as
CF Day had requested, principally on the basis that Loyal Source is not an
eligible small business. Even though the stay override determination was issued
one day before the SBA’s size decision, Defendant made no mention in its filings
or in the TRO argument of Loyal Source’s ineligibility to receive the award.
Moreover, based upon the representations of Plaintiff’s counsel, the Court found
that the Army easily could have continued with CF Day until the GAO bid protest
was decided. While acknowledging the mission-critical importance of the required
field training, the Court was persuaded that CF Day could have been reinstated
as the contractor until the GAO’s June 3, 2015 decision date. The Court also was
mindful of obtaining a prompt SBA decision on Loyal Source’s size appeal. The
TRO took effect on the afternoon of March 23, 2015.
On March 25, 2015, Defendant filed an Emergency Motion
to Vacate the TRO, accompanied by the Declaration of Rachael Houle, a
Contracting Officer for the Army Contracting Command in New Jersey. Ms. Houle
made a compelling case for the need to continue with the newly awarded Loyal
Source contract, and for the adverse effects of the service interruption caused
by the TRO. Ms. Houle further asserted that the Army has no legal way to
reinstate or re-procure the services from CF Day, and she pointed out that CF
Day had not rehired any of the staff necessary to continue the field services.
Since CF Day’s contract expired on March 5, 2015, the Army was not able to
exercise any option or to extend the contract. Under the circumstances, the
Court also was mindful of the national security considerations that must be
addressed under the Tucker Act: “In exercising jurisdiction under this
subsection, the courts shall give due regard to the interests of national
defense and national security and the need for expeditious resolution of the
action.” 28 U.S.C. § 1491(b)(3). Based upon Ms. Houle’s declaration and the
above provision, the Court vacated the TRO on March 26, 2015.
(sentences deleted)
In a supplemental declaration from the Contracting
Officer, Ms. Houle explained that the Army had decided to award a competitive
bridge contract to cover the period until after the GAO issues its decision on
CF Day’s bid protest. Ms. Houle released a solicitation for the bridge contract
on April 6, 2015. She requested offerors to submit proposals by April 10, 2015.
The competition was limited to the three companies that submitted acceptable
proposals in response to the original solicitation, and was not considered a
small business set-aside. The Army made award of the bridge contract to Loyal
Source on April 15, 2015. The scope of work is identical to the contract awarded
to Loyal Source in February 2015, and the period of performance will be from May
2 until June 30, 2015, with the option to extend the contract if necessary. Ms.
Houle states that the Army intends to comply with GAO’s recommendation on the
protest, even if corrective action may be suggested.
(sections deleted)
B. The Reasonableness of the Army’s
Corrective Action
Under the circumstances presented, the
Army’s award of a competitive bridge contract while the GAO protest is still
pending is eminently reasonable. By awarding a bridge contract for the period
May 2 through June 30, 2015, with an option to extend, the Army will receive its
mission-critical services through the expected GAO decision date of June 3,
2015, and for nearly one month after that date if the GAO recommends any
corrective action. Suppl. Houle Decl. ¶ 9. Moreover, the Army should receive the
decision of the SBA’s Office of Hearings and Appeals within the period of the
bridge contract advising whether Loyal Source is considered an eligible small
business. By not restricting the bridge contract as a small business set-aside,
the Army will avoid any small business eligibility issues during the performance
of the bridge contract. Id. ¶ 8. The Army’s corrective action represents a
variation from the action authorized in General Lia’s March 11, 2015 stay
override determination. Indeed, the award of a competitive bridge contract did
not require a stay override from the Head of the Contracting Activity. The
effect of the bridge contract is to stay performance of the Loyal Source
contract being protested at the GAO. Def.’s Mot. at 8-9. (Charles
F. Day & Associates, LLC v. U. S. and Loyal Source Government Services, No.
15-289C, April 24, 2015) (pdf)
The fundamental reason offered by the agency for its override decision
is that it is in the government’s best interest to proceed with transition to PAE
in order to ensure that essential life support services, including food, fuel for
electricity, and emergency response services continue uninterrupted. The D&F
is 14 pages in length. It begins by summarizing the mission in Iraq and
describing the contracts that are currently in place to enable the government
to carry out that mission. The D&F catalogs the current contracts and
interagency agreements by type, by contractor and agency, and by duration.
The Head of Contracting Activity in [Department of State] DOS, Cathy J. Read, recites that she
considered sole-source extensions and bridge contracts and decided that
pursuing an alternative to PAE’s performance was not in the government’s
best interest because, in transitioning to PAE, even a best-case scenario left no
more than a three month cushion. If there are unexpected difficulties, and she
believes that to be plausible given the location, that cushion could disappear
and there might be a gap in performance.
B. Was the Override Determination Arbitrary and Capricious?
The D&F attempts to assess the viability of contract extensions or solesource
bridge contracts against the backdrop of variables involved in the
transition to the new BLiSS contractor.
The D&F assesses the feasibility of
extending each of the contracts in turn.
The life support contract being performed by KBR is set to expire on
December 31, 2013. The agency acknowledges that KBR’s contract could be
extended through June of 2014. PAE needs approximately 45 to 90 days to
obtain authorization to mobilize from the government of Iraq. Then, KBR
requires 90 days for demobilization which is coextensive with PAE’s time for
transition. Thus, there is a 130 to 180 day window projected for PAE to
acquire approval, for PAE to transition, and for KBR to demobilize. Even
with PAE beginning the process in September of 2013, KBR’s contract will
likely need to be extended into January, February, or March of 2014 in order
to complete the transition to PAE without a lapse in services. If the window
for transition of this contract was delayed until after GAO issues its decision,
then approval, transition, and demobilization is projected to be complete
anywhere from April to June 2014. Shifting the transition process for this
contract eliminates or significantly reduces the cushion that DOS must
preserve in order to “accommodate any unforeseen delays or external events
that may further impact the transition schedule.” AR 5.
The Army Sustainment Command – First contract with URS
Corporation also ends on December 31, 2013. The agency asserts in the D&F,
without explanation, that URS Corporation’s contract cannot be extended
beyond March of 2014. While the D&F did not provide an estimate for the
time needed to accomplish PAE’s transition and URS Corporation’s
demobilization, the D&F does anticipate that it will take PAE six months to
obtain the International Traffic in Arms license that is required to maintain and
support a system with radiological materials under the BLiSS contract.
Assuming that PAE applied for this license in September of 2013, it could be
February of 2014 before PAE secures the license. Even in a best-case
scenario, there is roughly a month of cushion during which unforeseen
complications could be addressed. If PAE was forced to delay application for
the license until after GAO resolves the protest, then PAE would likely not
have the license necessary to carry on URS Corporation’s work when the
contract expires on March 31, 2014.
DLA’s contract with Ram Dis Ticaret A.S. for fuel ends on December
31, 2013. This contract could be extended through June 30, 2014. The D&F
notes that “there is no requirement for demobilization that would impact the
schedule.” AR 7. DOS estimates, however, that it will take PAE 90 to 120
days to obtain licenses, diplomatic notices, and register as a commodity
supplier with the government of Iraq. While PAE could accomplish this
before the existing contract ends, that contract might have to be extended into
January of 2014. In the event this process began after GAO issued its
decision, then PAE would have all of the necessary requirements in place in
April or May of 2014. That would leave at most three months, and worst case
only two months, of buffer time to safeguard against a disruption in services
due to unforseen circumstances.
DOS considered a partial override, i.e., having PAE take
over the work which had the least room for unexpected problems, and found that
this option was untenable and would add to the government’s risk because it
would require cooperation between contractors who have conflicting interests. AR
15. The agency also explained that it considered multiple sole-source bridge
contracts, but each would involve negotiations and a 60-90 day transition in
period for obtaining visas and clearances, making these interim measures
unreliable. AR 10.
The agency has taken the position that, even if PAE’s transition for each
of these contracts began in September of 2013, there is still a very real
possibility that DOS will have to unilaterally extend some of the incumbent
contracts pursuant to 48 C.F.R. § 52.217-8 to ensure continuity of services.
After listing all of the steps involved in maintaining the status quo, the
agency concluded, “even if the extensions were granted, it is not a feasible
approach and cannot ensure continuity of services.” AR 5. The agency further
explained that, if approval for contract extensions,
was granted in a reasonable amount of time, even a full
six month extension would not ensure adequate time for transition and would not
accommodate any unforeseen delays or disruptions. Given the current volatile
situation in the Middle East there is significant concern that there will be
evacuations and/or delays for contractor staff transitioning.
AR 9.
The relevant question is whether plaintiff has shown that this analysis
as to the government’s best interest was arbitrary or capricious. Plaintiff
contends that the agency failed to give sufficient attention to whether there
were reasonable alternatives to the stay override, specifically through contract
extensions, or sole-source bridge contracts. It suggests that contract extensions
could be made pursuant to 48 C.F.R. § 52.217-8, which provides, “The
Government may require continued performance of any service within the
limits and at the rates specified in the contract. . . . The option provision may
be exercised more than once, but the total extension of performance hereunder
shall not exceed 6 months.” It also argues that there is no suggestion in the
D&F that the agency began the process of invoking 48 C.F.R. § 52.217-8 or
that it attempted to negotiate with existing contractors to enter into sole-source
contracts extending performance.
While it is correct that there is no reason to believe
the agency actually began the process of triggering contract extensions, or
attempted to negotiate sole-source bridge contracts, what is clear is that the
agency was aware of those possibilities, seriously considered them, and rejected
them with coherent and reasonable explanations. The extensions that the
government could invoke by right would only take the existing contracts out
until March 31 or June 30, 2014. Given the need to allow for demobilization and
transition, the cushion periods effectively ranged from 0 days to 90 days. Other
contract vehicles beyond that time would have involved negotiation, competition,
and their attendant uncertainties.
Given the fact that all the transition activities would occur in Iraq,
which the agency describes as a dangerous place and one in which it is in the
government’s best interest to limit personnel and the size of its “footprint” in
order to minimize security concerns, AR 12, and that multiple contract
vehicles would have to be extended, with the attendant need for visas, housing
and licensing, it was not arbitrary or capricious to limit the risks of transition
by overriding the stay. These are not illusory concerns. In light of the
possibility that extending existing contracts or implementing sole-source
bridge contracts would not unfold with the efficiency of a Swiss watch, the
agency’s decision that the best interest of the government was served by
initiating immediate transition to PAE rather than pursuing what it believed
was a risky alternative approach was not unreasonable. While the government
may have been cautious, it was not arbitrary or capricious to insist on a stay
override to ensure a buffer period during the transition schedule. (Dyncorp
International LLC and Kellogg, Brown & Root Services, Inc. v. U. S. and PAE
Government Services, No. 13-689C, November 5, 2013) (pdf)
Under CICA, after Supreme timely filed its pending protest with the GAO on December
17, 2012, see AR, Tab 8 at 649, the contracting officer was required to “immediately direct the
contractor to cease performance under the contract and to suspend any related activities that may
result in additional obligations being incurred by the United States under that contract.” 31
U.S.C. § 3553(d)(3)(A)(ii) (2006). This cessation of performance, commonly referred to as
CICA’s “automatic stay,” is the rule, by command of Congress, lasting through the
determination of the protest, see 31 U.S.C. § 3553(d)(3)(B). The stay is legally mandated, until
performance is authorized by the head of procurement activity in a written finding that either
“performance of the contract is in the best interests of the United States” or “urgent and compelling circumstances that significantly affect interests of the United States will not permit
waiting for the decision of the Comptroller General concerning the protest.” 31 U.S.C.
§ 3553(d)(3)(C)(i).
Instead of the stay kicking in upon notice of Supreme’s protest, until overridden by a
D&F, Anham’s performance was never directed to cease. See AR, Tab 9 at 717 (explaining
“DLA Troop Support did not issue a stop work order when it received Supreme’s most recent
protest”). The head of contracting activity was of the unusual opinion that if a reevaluation of
offers occurring under corrective action results in the decision to reaffirm an earlier award, the
CICA stay does not apply when this new decision is protested before the GAO (since it will
necessarily be more than ten days after the initial award and more than five after the initial
debriefing). See id. at 715, 717.8 Thus, the D&F he issued on December 21, 2012, contained the
primary determination that the CICA stay did not apply in the circumstances presented. Id.
Neither the defendant nor the intervenor defended this aspect of the D&F, which appears to the
Court to have clearly been erroneous --- performance of Anham’s contract should have been
ordered to cease upon notice of Supreme’s timely GAO protest.
Rather than using the D&F to authorize the resumption of performance of the protested
contract, the head of contracting authority used it to rationalize the unceased and continuing
performance of that contract. But he also “did consider whether suspending performance under
the subject contract was in the Government’s best interest.” Id. at 715. While the premise of this
exercise had things backwards --- the issue to be determined was whether a stay should be
overridden, not whether one should be imposed --- the result is the same. By determining
whether performance of Anham’s contract during the pendency of the GAO proceedings was in
the government’s best interests or justified by urgent and compelling circumstances, the head of
contracting authority satisfied procedurally the written override requirements (for the period
beginning the date the D&F was issued). The question before the Court is whether this D&F
substantively met the arbitrary and capricious APA review standard that applies under 28 U.S.C.
§ 1491(b)(4). See RAMCOR, 185 F.3d at 1290.
The parties all acknowledge that the variation of this review standard that has been
termed the “hard-look doctrine,” see CBY Design Builders v. United States, 105 Fed. Cl. 303,
337 (2012), articulated by the Supreme Court in Motor Vehicle Manufacturers Ass’n v. State
Farm Mutual Automobile Insurance Co., 463 U.S. 29, 43 (1983), applies in this context. See
Def.’s Br. at 19; Intervenor’s Br. at 13; Pl.’s Opp’n at 9. Under this approach,
an agency decision
would be arbitrary and capricious if the agency has relied
on factors which Congress has not intended it to consider, entirely failed to
consider an important aspect of the problem, offered an explanation for its
decision that runs counter to the evidence before the agency, or is so
implausible that it could not be ascribed to a difference in view or the product
of agency expertise.
Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43; see also Ala.
Aircraft, 586 F.3d at 1375.
(sections deleted)
After repeated elaboration, it should be beyond controversy that the point of the CICA
automatic stay was to enhance the GAO as a forum for bid protests, so that the integrity of the
competitive procurement process could be protected. See, e.g., PMTech, 95 Fed. Cl. at 346-47;
CIGNA Gov’t Servs., LLC v. United States, 70 Fed. Cl. 100, 112 (2006); PGBA, LLC v. United
States, 57 Fed. Cl. 655, 657-58 (2003). Before the stay existed, a contract whose award was the
subject of a protest could have been performed for several months while the matter was
considered by the GAO. That office’s ultimate determination that the award was improper ---
and thus, may not have been the best option for an agency to follow --- would come with a
recommendation, not a mandate, that the award be cancelled, which an agency might have been
inclined to disregard because of the costs incurred and progress made under the awarded
contract. “Thus, ‘the automatic stay is intended to preserve the status quo during the pendency
of the protest so that an agency would not cavalierly disregard GAO’s recommendations to
cancel the challenged award,’ thereby ‘preserv[ing] competition in contracting and ensur[ing] a
fair and effective process at the GAO.’” Reilly’s Wholesale, 73 Fed. Cl. at 710 (alterations in
original) (quoting Advanced Sys. Dev., Inc. v. United States, 72 Fed. Cl. 25, 31(2006)).
In light of this purpose, even though the stay may be overridden when in the best interests
of the government or when certain urgent and compelling circumstances so require, see 31 U.S.C. § 3553(d)(3)(C)(i), it is hard to see how an override decision could fail to consider “the
impact of the override on competition and the integrity of the procurement system,” Reilly’s
Wholesale, 73 Fed. Cl. at 711, and still be rational. And since the stay was the rule, and an
override the exception, it would make little sense were the latter to be available whenever an
agency felt its latest solicitation was an improvement over the previous contract. Competition is,
after all, supposed to lead to lower prices and higher quality, see Arch Chems., Inc. v. United
States, 64 Fed. Cl. 380, 400 (2005), and agencies would be expected to learn from past
procurements when updating solicitations. Thus, if an agency’s belief that the awardee’s
proposal offered the best value --- in response to a solicitation that was an advancement over
prior procurements --- were sufficient to override the stay, “as a practical matter, the automatic
stay would be meaningless in virtually every single instance in which a GAO protest was filed.”
University Research Co. v. United States, 65 Fed. Cl. 500, 503 (2005); see also PGBA, 57 Fed.
Cl. at 662-63.
From this, it follows that rather than focusing on the benefits of the new contract
(particularly since that means performance by a contractor whose award might prove to have
been arbitrarily made), agencies should consider the existence of “significant adverse
consequences [that] will necessarily occur if the stay is not overridden.” Reilly’s Wholesale, 73
Fed. Cl. at 711. To determine the necessity of contract performance to avoid these
consequences, it could hardly be rational for an agency to ignore the existence of “reasonable
alternatives to the override” that would also do the job. Id. And in all events, if the costs of an
override when a protest might be sustained would outweigh the benefits received through
immediate performance of a contract, the override would neither be in the best interests of the
United States nor justified by the urgency of the circumstances. If no effort is made to compare
these costs and benefits, an agency cannot rationally find an override of the stay to be
warranted.
(sections deleted)
The Court acknowledges that, particularly in a war zone, conflicting claims on resources
may make them unavailable at certain times. But this unavailability, and the resulting impact on
the government, is simply not explained in the J&A nor supported in the administrative record.
If the need to accomplish transitions quickly when contracts are to be performed in a war zone
were enough to justify the override of the CICA stay, this would also seemingly justify ignoring
any resulting GAO recommendation --- which the agency disclaims. See AR, Tab 9 at 724. The
administrative record contains no evidence supporting an immediate threat of harm to health,
safety or welfare, and the explanation regarding the diversion of resources is too implausible to
attribute to differing judgment and expertise. Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43. On this
record, it was arbitrary for the agency to find that urgent and compelling circumstances justified
an override of the automatic stay.
(sections deleted)
For the foregoing reasons, the Court concludes that the decision to override the CICA
stay of performance issued by DLA Troop Support on December 21, 2012, was arbitrary,
capricious and contrary to 31 U.S.C. § 3553(d)(3)(C)(i), and is thus invalid and of no effect.
(Supreme Foodservice GmbH v. U. S. and Anham FZCO,
No 13-1, March 4, 2013) (pdf)
B. Standards for Preliminary Injunction
The court must consider four factors when contemplating whether to grant a preliminary
injunction: (1) likelihood of plaintiff’s success on the merits, (2) irreparable harm to plaintiff if
an injunction is not granted, (3) the balance of hardships, and (4) the public interest. Sciele
Pharma Inc. v. Lupin Ltd., 684 F.3d 1253, 1259 (Fed. Cir. 2012); see also Winter v. National
Res. Def. Council, Inc., 555 U.S. 7, 20 (2008). Plaintiff must establish the existence of a
reasonable likelihood of success on the merits and irreparable harm in the absence of an
injunction, while the last two factors are not required but are weighed in the balance. See Altana
Pharma AG v. Teva Pharm. USA, Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009) (“Although the
factors are not applied mechanically, a movant must establish the existence of both of the first
two factors to be entitled to a preliminary injunction.”). A preliminary injunction is “an
extraordinary and drastic remedy, one that should not be granted unless the movant, by a clear
showing, carries the burden of persuasion.” Mazurek v. Armstrong, 520 U.S. 968, 972 (1997)
(quoting 11A Charles Alan Wright et al., Federal Practice and Procedure § 2948, at 129–30 (2d
ed. 1995)) (emphasis in the original).
1. Likelihood of success on the merits.
Plaintiff must demonstrate that it is more likely than not to succeed on the merits of its
claim to qualify for a preliminary injunction. See Revision Military, Inc. v. Balboa Mfg. Co., 700
F.3d 524, 526 (Fed. Cir. 2012) (holding that for matters unique to the Federal Circuit, a
preliminary injunction with the effect of altering the status quo must meet the standard of “more
likely than not,” not a “clear or substantial likelihood” standard as required by certain other
circuits in particular types of cases).
On the merits, KWV will have to prove that the government’s decision was arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law. 28 U.S.C.
§ 1491(b)(4) (adopting the standard of 5 U.S.C. § 706(2)(A)). KWV contends that
[VA’s Office of Small and Disadvantaged Business Utilization] OSDBU’s
determination was far less searching and careful than the prior verification by
[VA’s Center for Veterans Enterprise] CVE, and relied
solely, and wrongly, on the assumption that Mr. Maron could not exercise effective control of
KWV when he spends six months and a day of each year in Florida rather than Rhode Island.
Pl.’s Mem. in Support of Pl.’s Emergency Mot. for Prelim. Inj. (“Pl.’s Mem.”) at 15. The
government counters that OSDBU’s decision was neither arbitrary and capricious nor contrary to
standards because OSDBU based its decision on a fact unknown to CVE at the time of CVE’s
VOSB certification, i.e., Mr. Maron’s residency, which came to light during the OSDBU
investigation. Hr’g Tr. 28:20-29:5 (Jan. 4, 2013); see also Def.’s Resp. to Pl.’s Mot. for
Preliminary Inj. (“Def.’s Opp’n”) at 6-7. Whether CVE actually lacked this information is
disputed by the parties. The record before CVE and produced with its decision does not place
Mr. Maron’s residency in any particular state, giving the court no indication as to whether CVE
was in fact aware of it at the time. See AR 1-517; Hr’g Tr. 33:14-25 (Jan. 4, 2013); Hr’g Tr.
22:9-23:10 (Dec. 20, 2012).
The OSDBU inquiry was markedly less thorough than that of CVE. The CVE
examination included a site visit in December 2011 to KWV’s headquarters to examine KWV’s
physical setting and to interview Mr. Maron and others, as well as to provide a context for
review of documentary records. See AR 495-515.2 (Letter from Dan Friend to Bruce St. John
(Dec. 19, 2011)); AR 1-159 (Initial Application for CVE Verification). Additionally, CVE
requested supplemental documentation from plaintiff, beyond what was filed with the application
for VOSB verification, and asked specific questions to illuminate certain areas of the application.
AR 160-61 (E-mail from Dawn Monahan to James Maron (Sep. 15, 2011)). KWV and Mr.
Maron provided the requested information and responded to CVE’s questions. AR 162-450
(Additional Documentation and Correspondence). After CVE initially declined to verify KWV
as a VOSB, AR 451-53 (CVE Denial Letter), Mr. Maron was permitted to cure the alleged
defects in his application by amending KWV’s by-laws, and to request reconsideration, AR 454-
94 (Correspondence and Documentation Regarding Reconsideration). By the time CVE issued
the VOSB certification for KWV on February 7, 2012, CVE had reviewed hundreds of pages of
documents, performed a site visit and interviews in December 2011, and had been corresponding
with Mr. Maron for nearly five months. See AR 516-17 (CVE Approval Letter). Aspects of the
CVE investigation were documented thoroughly and are now in the administrative record before
the court.
In comparison, the OSDBU investigation appears to have been cursory. No site visit was
conducted by OSDBU. See Hr’g Tr. 10:2-10; 11:19-12:1 (Dec. 20, 2012). No interviews were
conducted by OSDBU. Id. OSDBU afforded Mr. Maron an opportunity to respond to the
protest but did not follow up with any questions or concerns it may have had. Much of the
OSDBU decision is taken up by a word-for-word recitation of regulations found in Parts 819 and
74. AR 568-71. The findings themselves give few clues as to how OSDBU reached its decision,
stating merely that “[b]ecause construction requires the direct supervision of the work to be
performed, the location of the [veteran] is considered in determining whether the [veteran]
controls an applicant construction company.” AR 570 (emphasis added). This statement is
followed by a citation to a decision by the Small Business Administration’s ("SBA's") Office of
Hearings and Appeals (“OHA”) and a summary of Alares’ bid protest allegations. Id. As will be
discussed, the cited decision by SBA supports KWV’s position, not that of OSDBU, and the
protestor’s allegations turn on tenuous inferences. Importantly, OSDBU never even purports to
determine Mr. Maron’s actual level of involvement in the control of KWV.
By contrast, CVE’s detailed investigation focused on the extent and effectiveness of
Mr. Maron’s personal activities in relation to his control of KWV. Nevertheless, the government
urges that the OSDBU decision should control because OSDBU knew Mr. Maron resides in
Florida for just over half the year. Hr’g Tr. 21:10-17 (Dec. 20, 2012). That fact, plus the general
statement that “[t]he nature of construction requires on-site supervision and direct human contact
to adequately complete projects,” constitutes the sum of OSDBU’s rationale. AR 570.
The SBA decision, In the Matter of First Capital Interiors, Inc., SBA No. VET-112,
2007 WL 2438401 (2007) (“First Capital”), is instructive for what it decides as well as for what
it does not decide. The decision concludes that a service-disabled veteran did not control the
applicant construction firm. The veteran resided in Visalia, California, while the construction
company was based in Chillicothe, Ohio. 2007 WL 2438401, at *1. OSDBU considered that the
First Capital ruling was made simply “because [the veteran] lived thousands of miles from the
[company’s] headquarters.” AR 570. In actuality, SBA explicitly rejected the proposition that
distance alone could determine control. First Capital, 2007 WL 2438401, at *7 (“[N]either
OHA nor SBA maintains a concern cannot manage a job that is 2000 miles away from its
headquarters.” (emphasis added)). Rather, SBA took into account additional factors that
included the veteran’s seemingly full-time residence three time zones away from the company’s
situs, the lack of a long-distance management infrastructure, the absence of management
experience on the part of the veteran, and the circumstance that the veteran was simultaneously
self-employed at two other jobs, both of which were located in California. Id. at *7-8.
Mr. Maron, unlike the veteran in First Capital, physically is present in Rhode Island,
where KWV is based, for nearly half the year and spends the remainder of his time in Florida,
both of which are in the same time zone. AR 540. While in Florida, Mr. Maron employs various
electronic means to keep track of the day-to-day business of KWV. Id.; Pl.’s Mem.
at 16. KWV typically only performs one job at a time, with most of the work being performed when
Mr. Maron is in Rhode Island. Id. Additionally, during periods he spends in Florida, Mr. Maron
nonetheless travels to Rhode Island for “any meeting in which anything of importance is
discussed.” AR 540. He has ample management experience in construction, as his work historyshows. See AR 434. Mr. Maron currently maintains no other jobs or positions, allowing him to
focus solely on KWV. See AR 434, 541. There is nothing in the record to suggest credibly that
Mr. Maron could not meet the requirements of the control standard found in Part 74 and
incorporated into Part 819, and the government has manifestly failed to articulate any other
rationale for denying KWV VOSB status. OSDBU neither “provided a coherent and reasonable
explanation of its exercise of discretion, Impresa Construzioni Geom. Domenico Garufi v.
United States, 238 F.3d 1324, 1333 (Fed. Cir. 2001), nor articulated a ‘rational connection
between the facts found and the choice made.’” Motor Vehicle Mfrs. Ass’n v. State Farm Mut.
Auto. Ins. Co., 463 U.S. 29, 43 (1983).
Based on the foregoing analysis, the court finds that
plaintiff is more likely than not to succeed in proving that the government’s
actions were arbitrary and capricious or not in accordance with law.
(sections deleted)
CONCLUSION
For the foregoing reasons, KWV’s motion for a preliminary injunction is GRANTED.
OSDBU’s decision dated October 24, 2012, rendering KWV ineligible for awards of contracts as
a VOSB, is set aside. VA shall restore KWV to its roster of approved VOSB entities. KWV’s
verified eligibility to participate in VA’s Veterans First Contracting Program shall be extended
by 72 days, to April 22, 2013, to take account of the days it was wrongfully removed from
eligibility.
With the agreement of the parties, the court has adopted an accelerated schedule for
consideration of the merits of this protest. This grant of preliminary relief should remain in
effect for a relatively brief time, expected to be no more than several months, until the court
resolves KWV’s claim for permanent relief and the government’s opposition to that claim.
Because this preliminary relief has been structured to avoid the harms that the government
indicated might arise with delays in VA’s procurement activities,14 KWV is not required to
provide security in any amount. (KWV, Inc. v. U.
S., No. 12-882C, January 25, 2013) (pdf)
F. A Preliminary Injunction Is Warranted.
The August 20, 2012 Complaint requests that the court
“preliminarily and permanently enjoin and set aside the [Army’s] decision,
actions, and all findings and conclusions that are alleged to support such
decision.” Compl. at 37. Although Linc’s September 19, 2012 Motion For Judgment
On The Administrative Record seeks a permanent injunction (Pl. Mot. JAR at 37),
the court considers a preliminary injunction more appropriate to the
circumstances in this case. See 28 U.S.C. § 1491(b)(2) (authorizing the court to
“award any relief that the court considers proper, including . . . injunctive
relief”).
In considering whether to issue a preliminary injunction
the court is required to weigh four factors, i.e., affect a decision whether to
grant a preliminary injunction: “(1) immediate and irreparable injury to the
movant; (2) the movant’s likelihood of success on the merits; (3) the public
interest; and (4) the balance of hardship on all the parties.” U.S. Ass’n of
Imp. of Textiles & Apparel v. United States, 413 F.3d 1344, 1346 (Fed. Cir.
2005). “No one factor, taken individually, is necessarily dispositive . . . . [T]he
weakness of the showing regarding one factor may be overborne by the strength of
the others.” FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993).
As to the first factor, the Administrative Record
evidences violations of the Competition in Contracting Act, FAR, and/or contains
no documents showing that the Army even considered some of Linc’s proposed
“betterments,” much less any discussion of the merits of those proposed
“betterments.” Without injunctive relief, however, Linc will suffer immediate
and irreparable harm by losing the opportunity to be awarded a MATOC Contract.
See Google, Inc. v. United States, 95 Fed. Cl. 661 (2011) (issuing a preliminary
injunction after finding that plaintiff had made a prima facie showing of a
violation of the Competition in Contracting Act and relevant FAR provisions);
see also Savantage Fin. Servs., Inc. v. United States, 81 Fed. Cl. 300, 306-08
(2008) (same). Therefore, the first factor weighs in favor of an injunction.
As to the second factor, the Administrative Record has
established that the Army also evaluated certain of Linc’s proposals in any
arbitrary manner that was prejudicial to Linc’s financial interests. Therefore,
Linc has met the second test, i.e., a likelihood of success on the merits. See
PGBA, LLC v. United States, 57 Fed. Cl. 655, 664 (2003) (“This court has
acknowledged that a lost opportunity to compete may constitute an irreparable
harm[.]”).
As to the third factor, in many instances, the
Administrative Record in this case contains only the perfunctory summaries of
the Army’s completed evaluations as reflected in the SSEB’s Consensus Proposal
Evaluation Worksheets, but does not contain any internal documents from which
the consensus worksheets would have been compiled or documents evidencing
whether and how the Army evaluated those documents. “A protest case cannot be
efficiently processed until production of the administrative record” is
provided. RCFC App. C ¶ 23; see also Google, Inc., 95 Fed. Cl. at 679 (“[T]he
Administrative Record should include all relevant documents” relating to the
procurement process at issue); PGBA, 57 Fed. Cl. at 663 (“Clearly the public
interest in honest, open, and fair competition in the procurement process is
compromised whenever an agency abuses its discretion in evaluating a
contractor’s bid.”). Therefore, the court has determined that the public
interest is served by a preliminary injunction in this case.
As to the fourth factor, unfortunately, the Army has
been working on this procurement since September 2010. The Government argues
that “an injunction would imperil the agency’s ability to repair and maintain
the infrastructure of military medical facilities throughout the world.” Gov’t
Resp. to Pl.-Int. at 50. The Government also predicts higher costs to taxpayers
and poorer outcomes for the patients served by those facilities. Gov’t Resp. to
Pl.-Int. at 50. Linc counters that it will be harmed if the MATOC Contracts go
forward, since it will be denied a fair opportunity to compete. Pl. Mot. JAR at
38; Pl.-Int. Mot. JAR at 38. The hardship that a preliminary injunction will
impose on the Army is largely attributed to the Army’s lack of care in
conducting the evaluation process that has led to two bid protests, both of
which, in the court’s judgment, could and should have been avoided. For this
reason, the court finds that the balance of the hardships favors granting an
injunction.
IV. CONCLUSION.
For these reasons, it is hereby ordered that:
This procurement is remanded to Army “for additional
investigation or explanation.” Fla. Power & Light Co. v. Lorion, 470 U.S. 729,
744 (1985) (“If the record before the agency does not support the agency action,
if the agency has not considered all relevant factors, or if the reviewing court
simply cannot evaluate the challenged agency action on the basis of the record
before it, the proper course, except in rare circumstances, is to remand to the
agency for additional investigation or explanation.”). The United States Army
and its officers, agents, servants, employees, and representatives are
preliminarily enjoined from proceeding with or awarding any MATOC Contracts for
the design-build of medical facilities in the United States and overseas
pursuant to Solicitation No. W912DY-10-R-0005 or any related procurement,
solicitation, task order, or activity. (Linc
Government Services LLC, et al, v. U. S., et al, No. 12-522, December 28,
2012) (pdf)
New On
October 29, 2010, Google, Inc. and Onix Networking Corporation, a licensed
vendor of Google products and solutions (hereinafter collectively “Google”),
filed a pre-award bid protest in the United States Court of Federal Claims,
challenging an August 30, 2010 Request for Quotation No. 503786 (the “RFQ”) by
the Department of the Interior (“Interior” or “DOI”) to provide “hosted email
and collaboration services and [Interior’s] supporting ‘Limited Source
Justification.’” Compl. ¶ 1-2. After reviewing the Administrative Record from
November 5, 2010 and updated through December 21, 2010, Google filed an Amended
Complaint on December 30, 2010 to challenge the entire procurement, including a
June 10, 2010 Modification No. 0003 to an existing contract with Dell Marketing
(“Dell”) to implement a pilot project to migrate the Bureau of Indian Affairs
email systems to Microsoft Exchange and two July 15, 2010 Standardization
“Determination and Findings” to “establish Microsoft’s Business Productivity
Online Suite–Federal as the Department-side standard for Messaging and
Collaboration” and Microsoft Desktop and Service Software, as the
“Department-wide standard for computer operating, systems desktop and service,
office automation, and systems management software.” Am. Compl. ¶¶ 41-48.
(sections deleted)
D. The Administrative Record In This Case Supports Issuing
A Preliminary Injunction At This Juncture.
On July 15, 2010, the Assistant Secretary-Policy,
Management, and Budget signed a “Determination and Findings,” establishing
Microsoft’s Business Productivity Online Suite-Federal as “the Department-wide
standard for Messaging and Collaboration.” AR 748-56. On that same date, the
Assistant Secretary-Policy, Management, and Budget also signed a separate
“Determination and Findings,” establishing Microsoft Desktop and Service
Software as the “Department-wide standard for computer operating, system desktop
and service, office automation, and systems management software.” AR 757-62.
Both July 15, 2010 Standardization “Determination and
Findings” are quintessential “non-competitive procedure[s],” that must be
justified by the “contracting officer.” 41 U.S.C. § 253(f)(1)(A). In addition,
since these Standardization “Determinations and Findings” concern an amount
exceeding $50 million (AR 753), they require the additional approval of “the
senior procurement executive of the agency.” 41 U.S.C. § 253(f)(1)(B)(iii)
(emphasis added).
The Assistant Secretary–Policy, Management, and Budget,
however, is neither the “Contracting Officer,” nor appears to be the Department
of Interior’s “senior procurement executive.” In fact, the establishment of a
“Department-wide standard for messaging and collaboration” and a
“Department-wide standard for Office Automation and Systems Management Software”
does not appear to fall within the responsibilities of the Assistant
Secretary–Policy, Management, and Budget. On Interior’s website, the job
description of the Assistant Secretary–Policy, Management, and Budget is to
“oversee[] programmatic, administrative and financial policy for the Department,
including budget formulation and implementation.” Department of Interior, Office
of Policy, Management and Budget Website, http://www.doi.gov/pmb/about.html
(last visited 1/3/2011).
In addition, the General Organizational Chart for the
U.S. Department of the Interior shows that the CIO reports directly to the
Secretary of the Department of the Interior, not the Assistant Secretary–Policy,
Management, and Budget. Instead, the CIO only “receives administrative guidance
and support from the Assistant Secretary-Policy, Management, and Budget.”
http://elips.doi.gov/elips/release/images/DM3170CT.htm
(last visited 12/27/2010).
Both of the July 15, 2010 Standardization “Determination
and Findings,” however, originated from the CIO, but were directed to the
Assistant Secretary-Policy, Management, and Budget for approval, circumventing
line authority to the Secretary of the Department of the Interior or the
Secretary’s Deputy and reversing the roles of the Assistant Secretary-Policy,
Management, and Budget and the CIO.
In addition, both of the July 15, 2010 Standardization
“Determination and Findings” failed to comply with the requirements of FAR
6.302-1(a), 6.303-1, 6.303-2, and 6.304. Since both the July 15, 2010
Standardization “Determination and Findings” are based on a decision that “only
one responsible source . . . and no other supplies or services will satisfy
[Interior’s] requirements” (48 C.F.R. § 6.302-1), the contracting officer is
prohibited from “commenc[ing] negotiations for a sole source contract . . .
unless the contracting officer”: (1) provides a justification per FAR 6.302, the
contents of which are specified at FAR 6.303-2; (2) certifies the “accuracy and
completeness of the justification”; and (3) “obtains the approval required by
[FAR] 6.304.” 48 C.F.R. § 6.303-1(a). As the Administrative Record evidences,
negotiations for a sole source contract with Microsoft “commenced” many months
prior to July 15, 2010. See, e.g., AR 1039-89 see also AR 1041 (April 8, 2010
Microsoft email to Deputy Assistant Secretary Jackson regarding “Call follow up
deliverables.”).
In addition, neither Standardization “Determination and
Findings” is accompanied by a proper justification or appropriate approvals. To
the extent the Standardization “Determination and Findings” were intended to
substitute for a justification, several deficiencies are apparent. First,
neither document identifies the “statutory authority permitting other than full
and open competition.” FAR 6.303-2(a)(4) (emphasis added).
Second, the “anticipated cost” discussion (AR 753-54)
contains no estimate of internal agency cost, e.g., Project Management Office
and Independent Verification and Validation costs that apparently will be the
subject of a “separate procurement.” AR 767. More importantly, there is no
consideration or discussion about the more significant embedded costs associated
with what [REDACTED] described in a March 16, 2010 report as the cost of
“organizational lock-in . . . making alternative [products] difficult to use.”
AR 647. In the context of describing “organizational lock-in” regarding
Microsoft Office products, [REDACTED] specifically stated that: [REDACTED]. AR
651; see also AR 677 ([REDACTED]); AR 252 ([REDACTED]). Nevertheless, on July
15, 2010, Interior preceded to standardize on the Microsoft Office desktop
productivity suite. AR 762. Google described the effect of “organizational
lock-in” in more pragmatic terms: Interior’s decision to standardize the
Microsoft Exchange Messaging Solution “provides [Microsoft] technology [with] a
significant prejudicial, if not insurmountable, advantage in any future
competition.” Compare AR 1004 with e.g., AR 1586 (Interior reporting that “other
components of the BPOS-Federal suite will be made available to [Interior]
bureaus and offices on an optional basis”). The value of organizational lock-in
certainly was not lost on Microsoft. AR 1087 ([REDACTED]) (emphasis added); AR
1040-41 (describing Microsoft as the largest provider of BES services in the
world, and 90% of Exchange Online Dedicated customers uses BlackBerry service[.]
[REDACTED]). Without considering embedded costs, including the cost of
organizational lock-in, it is not surprising that the July 15, 2010
Standardization “Determination and Findings” fails to include the required
statement that “anticipated cost to the Government would be fair and
reasonable.” FAR 6.303-2(a)(7).
Third, there is no “listing of sources . . . that
expressed in writing an interest in the [procurement].” FAR 6.303-2(a)(10). The
failure to list Google’s repeated express interest in this procurement cannot be
explained as an oversight.
Fourth, there is no statement of the actions that
Interior plans “to remove or overcome [a] barrier to competition before any
subsequent acquisition for the supplies or services required.” FAR
6.303-2(a)(11).
By July 22, 2010, however, Interior was aware that
Google had a government-only version of the Google Apps product and claimed it
had obtained FISMA certification. AR 783-84. Nevertheless, on August 20, 2010,
Interior’s CTO, Mr. Corrington, recommended that this information did “not
warrant a change in the standardization decision(s) that [were] made on July 15,
2010.” AR 784. None of this is mentioned in the subsequent August 30, 2010
Limited Source Justification, citing the dual July 15, 2010 Standardization
“Determination and Findings” as the predicate agency authority for the
“Justification.” AR 848. Of course, Mr. Corrington suggests a formal
re-evaluation in the second quarter of FY2013. AR 785. By that time, however,
the migration of Interior’s email system will be completed and “organizational
lock-in” achieved. AR 1584; AR 1616.
On a motion for preliminary injunctive relief, the court
must weigh four factors: “(1) immediate and irreparable injury to the movant;
(2) the movant's likelihood of success on the merits; (3) the public interest;
and (4) the balance of hardship on all the parties.” U.S. Ass'n of Imp. of
Textiles & Apparel v. United States, 413 F.3d 1344, 1346 (Fed. Cir. 2005). “No
one factor, taken individually, is necessarily dispositive. . . . [T]he weakness
of the showing regarding one factor may be overborne by the strength of others.”
FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993) (emphasis added).
As to the first factor, the court has been informed that
Interior intends to award a contract, pursuant to RFQ No. 503786 on January 25,
2011. As discussed herein, the July 15, 2010 Standardization “Determination and
Findings,” on which the August 30, 2010 Limited Source Justification was based,
violate the Competition in Contracting Act and FAR. Without a preliminary
injunction, the award will put into motion the final migration of Interior’s
email system, achieve “organizational lock-in” for Microsoft, and cost Google
the opportunity to compete. Therefore, without injunctive relief, Google will
suffer immediate and irreparable harm. See PGBA, LLC v. United States, 57 Fed.
Cl. 655, 664 (2003) (“This court has acknowledged that a lost opportunity to
compete may constitute an irreparable harm[.]”). Therefore, the first factor
weighs in favor of an injunction.
The second factor concerns the likelihood of success on
the merits. Based on the allegations set forth in the October 29, 2010
Complaint, as amended on December 30, 2010, the court’s review of the
Administrative Record has established that Google has made a prima facie showing
that Interior violated the Competition in Contracting Act and relevant FAR
provisions and that such violation was prejudicial to Google’s interests.
Therefore, Google has met the second test, i.e., a likelihood of success on the
merits for a preliminary injunction. See Savantage Fin. Servs., Inc. v. United
States, 81 Fed. Cl. 300, 306-08 (2008) (holding that the Department of Homeland
Security’s decision to use financial management software systems of two
incumbent contractors by means of a brand name justification to standardize the
agency’s financial software systems was an improper sole source procurement that
violated the CICA, where there were other responsible sources).
As to the third factor, the court has determined that
the public interest is served by the issuance of a preliminary injunction to
ensure Interior’s compliance with the requirements set forth in the Competition
in Contracting Act and the FAR. See PGBA, 57 Fed. Cl. at 663 (“Clearly, the
public interest in honest, open, and fair competition in the procurement process
is compromised whenever an agency abuses its discretion in evaluating a
contractor’s bid.”). In addition, the Administrative Record in this case is far
from complete. Apart from specific items noted herein, this procurement concerns
more than “RFQ No. 503786.” As the United States Court of Appeals for the
Federal Circuit has held the scope of the “procurement or proposed procurement”
includes “all stages of the process in acquiring property or services, beginning
with the process for determining a need for property or services and ending with
contract completion and close out.” Distributed Solutions, 539 F.3d at 1345
(emphasis added).
29
As such, the Administrative Record should include all relevant documents from
late 2007 to date, including those relating to the 2009 BPOS-Federal Pilot
Program, the July 15, 2010 Standardization “Determination and Findings,” the
August 30, 2010 Limited Source Justification, as well as the August 30, 2010 RFQ
No. 503786. The email communications between Interior and Microsoft establish
that the Administrative Record is not complete. The most striking example is the
September 24, 2009 email from Interior’s CTO, Bill Corrington, to Microsoft’s
Vice President, Federal Government, Ms. Theresa Carlson, and other Microsoft
representations, wherein Mr. Corrington expressed a “demonstrated . . .
commitment to the success of the project by both DOI and Microsoft. I look
forward to . . . continuing to work with the Microsoft team to achieve a
successful project outcome.” AR 1088 (emphasis added). The only document that
precedes this is a July 31, 2009 email referencing a meeting between Microsoft’s
Ms. Justina Glavin, Deputy Assistant Secretary Jackson, and Mr. Corrington. AR
1088. It is inconceivable that Interior decided to commit to “Microsoft’s team
to achieve a successful project outcome” within 30 days without other internal
documents being generated. In addition, the Administrative Record contains none
of the attachments to emails between Interior and Microsoft. See e.g. AR
1035-37, 1041, 1052, 1055, 1064, 1067, 1068, 1073, 1077, 1088. Moreover, the
court finds it unusual that the Deputy Assistant Secretary Jackson had “regular
monthly one-on-one” meetings with Ms. Carlson, but apparently took no notes or
didn’t maintain them. AR 1039. As the Rules of the United States Court of
Federal Claims provide: “a protest case cannot be efficiently processed until
production of the administrative record” is provided. RCFC App. C ¶ 23. For this
additional reason, the court has determined that the public interest is served
by a preliminary injunction in this case.
With respect to the fourth factor, Interior has been
engaged in a process to ascertain the requirements of a new email, calendaring,
and collaboration system at least since 2007. See, e.g., AR 1-2, 97, 150,
154-68, 175, 184, 748-56, 762, 765-72, 844-51, 855, 1584. As of July 19, 2010,
Ms. Debra Glass, Division Chief, Acquisition Services Directorate, National
Business Center advised Google that it would be impossible to complete this
procurement in fiscal year 2010. AR 1016. Under these circumstances, any de
minimis inconvenience to Interior caused by the court’s Preliminary Injunction
is outweighed by the above referenced public interest and the secondary
competitive harm to the Google. During this period, the Secretary of the
Department of the Interior will have an opportunity to correct the deficiencies
herein cited, with the advice of the Solicitor and the Inspector General. The
Secretary also may wish to seek the independent views of outside experts as to
whether reconsideration of the July 15, 2010 Standardization Decisions is
warranted in light of the subsequent availability of Google’s Apps offering, if
for no reason other than continued congressional appropriations will be required
to implement the procurement, whether it is delivered by Microsoft, Google, or
some other contractor. See General Accountability Office Report to the Committee
on Oversight and Government Reform, House of Representatives, “Federal
Contracting: Opportunities Exist to Increase Competition And Assess Reasons When
Only One Offer Is Received,” GAO-10-833 (July 2010); see also AR 1531-75
(Inspector General’s FY2009 FISMA Evaluation Report).
The court emphasizes that it has made no judgment as to
whether Interior’s basis for this procurement was rational or whether the
procurement was conducted in a manner that was arbitrary and capricious. The
court, however, discerns no basis in the present Administrative Record to
support Google’s allegations of bad faith, [REDACTED]. Likewise, the court
discerns no improper conduct by Microsoft, the actions of which show only
competitive zeal and interest in customer satisfaction.
IV. CONCLUSION.
For the reasons set forth herein, it is hereby ordered
that: the United States of America, the Department of the Interior, and their
officers, agents, servants, employees, and representatives are preliminarily
enjoined from proceeding with or awarding a contract to implement a Microsoft
Business Productivity Online Suite-Federal Messaging solution, pursuant to RFQ
No. 503786 or any related procurement, solicitation, task order, or activity,
including proceeding with the June 14, 2010 Amendment Modification 0003 to
Contract No. GS35F4072D/NBCF09382. See RCFC 65(a). In addition, this
procurement is remanded to Interior “for additional investigation or
explanation.” Florida Power & Light Co. v. Lorion, 470 U.S. 729, 744 (1985).
(Google, Inc. and Onix Networking Corporation v. U.
S. and Softchoice Corporation, No. 10-743C, January 4, 2011) (pdf)
This unusual case involves Congress’s recent
decision to limit the jurisdiction of a
parallel system for protesting certain government procurements, and expand the
existing process at the Government Accountability Office (“GAO”). The protestor
asserts that the procurement at
issue is within the jurisdiction of GAO and that the procuring agency, the
Transportation Security
Administration (“TSA”) must either stay performance of the contract until the
conclusion of the
protest in accord with 31 U.S.C. § 3553 or follow the statutory procedure for
overriding that
automatic stay. The Government contends that this solicitation remains under the
former,
parallel system, and that the automatic stay provision of § 3553 is
inapplicable. The Court
concludes that whether or not the procurement was conducted under the former
system, the
automatic stay provision is applicable, and TSA is therefore required to stay
performance of the
contract at issue until GAO resolves the protest or TSA seeks to override the
stay. The
Intervenor’s Motion for Declaratory Judgment and the Defendant’s Motion to
Dismiss are
therefore DENIED, and the Plaintiff’s Motion for Declaratory Judgment is
GRANTED.I. Background
A. Statutory and Regulatory History
GAO (sometimes referred to by the title
of its director, i.e., the Comptroller General) has
exercised informal authority to adjudicate bid protests essentially since its
formation as the
Government Accounting Office in 1921. Letter from Comptroller General McCarl to
the
Postmaster General, Acceptance of Other than the Lowest Bid, A-11757, 5 Comp.
Gen. 330, 331
(Nov. 5, 1925). This authority became formal with the passage of the Competition
in
Contracting Act of 1984, Pub. L. No. 98-369, 98 Stat. 1175 (1984) (codified in
scattered sections
of 31 U.S.C. and 41 U.S.C.) (“CICA”).
In 1996, however, Congress decided to
require the Federal Aviation Administration
(“FAA”) to develop its own unique acquisition system, ultimately called the
Acquisition
Management System (“AMS”). Department of Transportation Appropriations Act of
1996, Pub.
L. No. 104-50, § 348, 109 Stat. 436, 460 (1995) (codified as amended in
scattered sections of 49
U.S.C.). This act exempted the AMS from “all federal acquisition laws and
regulations,”
including CICA, and GAO thus no longer possessed jurisdiction to resolve
disputes arising out of
FAA procurements. Id. The FAA created an Office of Dispute Resolution for
Acquisition
(“ODRA”) with exclusive jurisdiction over FAA bid protests. See, e.g., Pub. L.
No. 108-176, §
224(b), 117 Stat. 2490, 2528 (codified as amended at 49 U.S.C. § 40110(d)(4));
Attachment 1 to
Defendant’s Motion to Dismiss and Opposition to Plaintiff’s Motion for
Declaratory Judgment
(docket entry 15, Dec. 4, 2009) (“Def.’s Mot.”) (memorandum of Sept. 16, 2002
delegating
authority to ODRA); Attachment 2 to Def.’s Mot. (memorandum last signed in 2004
delegating
authority to ODRA). As of 1996, therefore, there were, as is pertinent here, two
separate
administrative fora for bid protests, depending upon whether the FAA was the
procuring agency.
In November 2001, Congress created the TSA to improve aviation security in the
wake of
the terrorist attacks that September. Aviation and Transportation Security Act,
Pub. L. No. 107-
71, 115 Stat. 597 (2001) (“ATSA”). Congress directed TSA to utilize the AMS, as
established
by the FAA, for its acquisitions of “equipment, supplies, and materials.” Id. §
101(n), 115 Stat. at 600. Although in 2002 the TSA was placed under the control
of the new Department of
Homeland Security (“DHS”), the 2002 Homeland Security Act did not alter the
handling of TSA
procurements through the AMS rather than generally applicable laws and
regulations.
Homeland Security Act of 2002, Pub. L. No. 107-296, § 424, 116 Stat. 2135, 2185
(2002). In
2005, Congress included “services” among the items TSA was required to procure
through the
AMS. Department of Homeland Security Appropriations Act of 2006, Pub. L. 109-90,
119 Stat.
2064, 2070 (2005). Because DHS is subject to those generally applicable laws and
regulations,
including the Federal Acquisition Regulation (“FAR”) and the jurisdiction of
GAO, TSA’s use of
the AMS created some problems.
In part to place all DHS entities on the
same system and thus improve efficiency in
contracting, in 2007 Congress repealed the statutory provision placing TSA
procurements under
the AMS.1 Consolidated Appropriations Act of 2008, Pub. L. No. 110-161, § 568,
121 Stat.
1844 (2007). The change in jurisdiction was to take place “180 days after the
date of enactment
of this Act”—that is, on June 23, 2008. Id. § 528(b). In response to this new
law, DHS
promulgated a regulation stating that “TSA acquisitions initiated after June 22,
2008” would be
subject to the FAR. 73 Fed. Reg. 30,317 (May 27, 2008) (codified at 48 C.F.R. §
3001.104(b)).
GAO issued a final rule stating that it would “hear protests of TSA procurements
covered by
TSA solicitations issued on or after June 23, 2008.” 73 Fed. Reg. 32,427, 32,429
(June 9, 2008).
These are two slightly differing statements of when the new regime begins: when
an
“acquisition” is “initiated” versus when a “solicitation” is “issued.”
(sections deleted)
The issue presented here
deals with the so-called “automatic stay” that applies to protests
filed at GAO. Section § 3553 of CICA provides that “if the Federal agency
awarding the
contract receives notice of a protest in accordance with this section . . . the
contracting officer
shall immediately direct the contractor to cease performance under the contract.
. . . .” 31 U.S.C.
§ 3553(d)(3)(A)(ii). A “protest” is a “written objection by an interested party
to . . . [a]
solicitation or other request by a Federal agency for offers for a contract for
the procurement of
property or services . . . [or] [a]n award or proposed award of such a
contract.” Id. § 3551(1).
The agency may override the automatic stay if it makes a “written finding that .
. . performance of
the contract is in the best interests of the United States; or . . . urgent and
compelling
circumstances that significantly affect interests of the United States will not
permit waiting for a
decision of the Comptroller General concerning the protest.” Id. § 3553(3)(C)(i)(I)
& (II).
(sections deleted)
C. The Automatic Stay
Applies When Statutory Requirements Are Met Whether or
Not the Protest is Properly Filed at GAO
The parties brief a great deal of law, but do not adequately focus on the
language of the
statute at issue in this case, CICA. Section 3553(b)(1) of CICA requires GAO to
notify the
“Federal agency involved” within “one day after the receipt of a protest.” Once
that notice
occurs, then either (1) the agency must provide a report at a specified time or
(2) GAO may
dismiss the protest under § 3554(a)(4).
The agency only has a duty
to suspend performance under § 3553 if it receives notice
from GAO within ten calendar days of contract award or within five days after
debriefing of an
unsuccessful offeror. See, e.g., Tech. for Commc’ns Int’l v. Garrett, 783 F.
Supp. 1446, 1453
(D.D.C. 1992) (concluding that post-award stay provision was not triggered
although protester
filed protest within ten days of contract award, because GAO did not notify
agency until the
fourteenth day after contract award). GAO may simply decline to notify the
agency if the filing
does not meet the definition of a “protest” under 4 C.F.R. § 21.1(c)(4). See
Steven W. Feldman,
GOVERNMENT CONTRACT AWARDS: NEGOTIATION AND SEALED BIDDING § 31:2 (2007) (noting
GAO can decide not to provide notice when protest fails “to state legal and
factual grounds for a
complaint”).
Under § 3554(a)(4) and GAO’s
implementing regulations, “[t]he Comptroller General
may dismiss a protest that the Comptroller General determines is frivolous or
which, on its face,
does not state a valid basis for protest.” See M.B. Shaw Co.-Reconsideration,
B-247247, 92-1
CPD ¶ 182, 1992 WL 30871 (Comp. Gen. Feb. 12, 1992) (“Since Shaw’s protest did
not on its
face state a valid basis for protest, there was no need for us to obtain a
report from the agency.”);
Beretta USA Corp.-Reconsideration, B-232681 et al., 89-1 CPD ¶ 16, 1989 WL
240292, at *3
(Comp. Gen. Jan. 9, 1989) (“[W]e consistently rely on section 21.3(m) as the
basis for dismissing
protests which, like Beretta’s, lack merit on their face.”). GAO thus possesses
ample authority to
deal with frivolous or facially deficient protests, and the defendant is simply
incorrect in predicting a parade of horribles if the Court were to find in favor
of the plaintiff. The decision
to give notice or utilize the § 3554 dismissal process, however, is entirely
within GAO’s
province.
As for the application of
the stay itself, § 3553(d)(3)(A)(ii) provides that once “the
Federal agency awarding the contract” receives proper notice of a GAO protest,
then “the
contracting officer shall immediately direct the contractor to cease performance
under the
contract and to suspend any related activities that may result in additional
obligations being
incurred by the United States under that contract.” A “protest” is “a written
objection by an
interested party” to, among other things, the “award or proposed award” of a
contract. 31 U.S.C.
§ 3551(1).
The parties do not dispute
that the prerequisites to the application of the automatic stay
have been met: (1) GAO has provided (2) timely notice to (3) the “federal
agency” (that is, TSA),
that (4) a protest (i.e., a written objection to an award) has been filed with
GAO. Moreover,
GAO has not dismissed the protest as facially deficient or frivolous. Defendant
argues, citing no
authority, that “protest should be read to mean a protest that is properly
before GAO.” Def.’s
Mot. at 14. That is not what the statute says: by its plain terms, when an
agency receives notice
of a protest filed at GAO the automatic stay kicks in, even if the protest is
ultimately determined
to be beyond the jurisdiction of GAO. See, e.g., Meyers Cos., Inc., B-275963,
97-1 CPD ¶ 148,
1997 WL 196349 (Comp. Gen. Apr. 23, 1997) (noting agency’s stay of performance
in case
ultimately dismissed for lack of jurisdiction).
Defendant and intervenor
rely upon five protests of TSA procurements filed at GAO prior
to the June 23, 2008 termination of TSA’s authority to conduct AMS acquisitions.
In each case,
GAO properly took jurisdiction of the protest in order to determine its
jurisdiction, resulting in a
decision dismissing the protest. Laser Shot, Inc., B-310406 (Comp. Gen. Oct. 4,
2007);
Worldwide Recruiters, Inc., B-298570 (Comp. Gen. Aug. 8, 2006); Knowledge
Connections,
Inc., B-298172, 2006 CPD ¶ 67, 2006 WL 1319542 (Comp. Gen. April 12, 2006);
Rimpau
Enters., B-298463 (Comp. Gen. July 18, 2006); Seal-It, Inc., B-294422 (Comp.
Gen. Aug. 25,
2004).
After the conclusion of briefing, the Court asked defendant to report whether
performance
had continued during the pendency of these five protests at GAO. That is, did
the parties treat
the CICA stay as applicable to those protests of AMS procurements regardless of
GAO’s lack of
jurisdiction? For four of the five pre-2008 cases, defendant could not ascertain
whether performance had continued during the pendency of the protest at GAO. In
the fifth case, Laser
Shot, “[a] stop-work order was issued and remained in place until GAO dismissed
the protest. At
that point, the stop-work order was cancelled.” Def.’s Response to Dec. 10, 2009
Order at 2.
For the four cases where it
lacks evidence regarding whether work stopped during the
GAO protest, defendant notes that “when TSA received notice of a protest at GAO
over which
GAO lacked jurisdiction, it would file a motion to dismiss within ten days of
receiving notice of
the protest.” Id. at 2. GAO would then “ordinarily dismiss[] the protest within
ten days of
TSA’s motion to dismiss.” Id. Because only 20 days elapsed between the filing of
the protest
and GAO’s dismissal, “even if contract performance proceeded, very little
contract performance
actually occurred while the protest was pending.” Id. at 3. This is consistent
with GAO’s
practice of “promptly dismiss[ing] protests that do not state a valid legal
basis or are otherwise
procedurally defective, consistent with [their] broad statutory authority.”
Report to Congress on
Bid Protests Involving Defense Procurements, B-401197 (Comp. Gen. Apr. 9, 2009).
GAO is
obliged to consider the “serious potential disruption that protests have on the
procurement
process,” and thus utilizes § 3554 and its regulations to warn protestors that
failing to set forth
legal and factual grounds for protest will result in a quick dismissal. The
Honorable Eldon Rudd
House of Representatives, B-22061, 1986 WL 65105, at *1 (Comp. Gen. Feb. 10,
1986).
In Laser Shot, the procurement was conducted entirely under the Federal Supply
Schedule and the solicitation did not include any reference to the AMS. Def.’s
Mot. at 17. It
was therefore not clear that the procurement had been conducted under the AMS,
and TSA did
not challenge GAO’s jurisdiction to entertain the protest. Id. TSA issued a
stop-work order for
the duration of the GAO protest, though GAO ultimately determined that the
acquisition was a
procurement under the AMS to which CICA did not apply and dismissed the case for
lack of
jurisdiction. Id. That is, TSA treated the CICA stay as applicable where the GAO
arguably had
jurisdiction. Based upon Laser Shot and the initial stop-work order in this
case, it does not
appear that TSA has previously taken the position that TSA is exempt from CICA
and its stay
requirement. But that is precisely the effect of the Government’s argument here.
Whether an AMS procurement is subject to CICA and whether TSA is subject to CICA
are two different questions, as demonstrated by Laser Shot and Resource
Consultants, Inc., B-290163, 2002 CPD ¶ 94, 2002 WL 1335283 (Comp. Gen. June 7,
2002).9 The ATSA, which
created the TSA, mandates that the AMS “shall apply to acquisitions . . . by the
Transportation
Security Administration.” Pub. L. No. 107-71, § 101(n), 115 Stat. at 602. The
earlier statute
creating the AMS dictates that the CICA (of which 31 U.S.C. § 3553 is a part)
“shall not apply to
the new acquisition management system developed and implemented” by the FAA. 49
U.S.C.
§ 40110(d)(2)(E). But this language is directed to the AMS itself, not TSA. That
is, it does not
render TSA exempt from following the directive to a “federal agency” contained
in § 3553 when
a protest of an acquisition conducted under the AMS is filed at GAO. See
Resource Consultants,
Inc., 2002 WL 1335283, at *3 (TSA is “federal agency” under CICA). It simply
renders CICA
inapplicable to an AMS acquisition, which in turn leads GAO to dismiss the
protest as filed in
the wrong forum. The properly presented question in this case is not whether the
Phase 2
solicitation is an AMS acquisition, but whether CICA applies to TSA when a
protest of the Phase
2 solicitation is filed at GAO. Because TSA is a “federal agency” within the
meaning of CICA
and the other statutory prerequisites to the application of the automatic stay
have been met, the
answer is yes.
The parties focus their
briefing on such matters as the timing of the termination of TSA’s
AMS authority, whether Phase 2 is a new “acquisition” within the meaning of the
TSA
regulation versus a new “solicitation” under the GAO rule, and the terms of the
Phase 2
Solicitation language versus the terms of the EAGLE contract. These arguments go
to whether
GAO possesses merits jurisdiction over the task order—i.e., whether the Phase 2
solicitation is
an AMS procurement. As defendant correctly notes, this is not a question within
the court’s
purview. Def.’s Mot. at 14 (“[T]he Court need not directly decide whether GAO
possesses
jurisdiction, rather, the Court must determine whether the automatic stay
provision of 31 U.S.C.
§ 3553 applies . . . . As this Court has noted, it lacks authority to directly
review GAO’s
determination of its own jurisdiction.”); see also Centech Group, 78 Fed. Cl. at
498 n.6. At
minimum, GAO possesses jurisdiction to determine its jurisdiction (i.e., as in
the cases cited
above). See, e.g., 13D Charles A. Wright et al., FED. PRAC. & PROC. § 3536 (3d
ed. 2008).
When the proper notice is given, the automatic stay applies. Because TSA must
comply with the
automatic stay provision whether or not the protest is properly filed at GAO, it
acted contrary to
law in failing to abide by § 3553.
D. The Court Declares that
TSA’s Actions Did Not Comply with the Law and Orders TSA to Implement a Stay of Performance Until GAO Resolves the Protest or TSA
Makes the Statutorily Required Override Findings
Where the agency fails to
either implement the automatic stay or properly override the
stay, this court will undertake the now-familiar four-part analysis to determine
whether to grant
an injunction enforcing the stay: (1) plaintiff’s success on the merits; (2)
irreparable injury to plaintiff; (3) balance of hardships; and (4) the public
interest. ES-KO, 44 Fed. Cl. at 435-36. If
the court determines, as it does in this case, that the automatic stay applies,
the Government’s
failure to heed that requirement establishes the protestor’s success on the
merits. Id. at 435.
Furthermore, “plaintiff’s injury is adequately established by the denial of its
right to an automatic
stay.” Id. The third factor to be considered in granting an injunction is the
balance of hardships,
but the “inclusion of this override exception builds consideration of
defendant’s potential
hardship” into the system. Id. at 436. That is, if the defendant concludes it
will suffer an undue
hardship from the stay, it has a remedy, and that remedy is not to ignore the
automatic stay. Thus
TSA’s decision to ignore the stay results in a balance of hardships favoring
plaintiff. The final
factor, the public interest, likewise favors plaintiff when the law is simply
ignored. Id. (“To a
large extent, this inquiry too is subsumed within the override exception . . .
.”). Congress’s
policy judgment is that there shall be a stay unless the agency makes the
requisite findings.
Where there are no findings, then the public interest requires adherence to the
law.
Plaintiff has shown
entitlement to a declaratory judgment that the CICA automatic stay
applies and to an injunction requiring TSA either to comply with the automatic
stay provision of
§ 3553 or seek to make a proper override determination in accord with the terms
of that statute. (Unisys Corp. v U. S. and
Computer Sciences Corporation, No. 09-800c, December 18, 2009) (pdf)
Plaintiff, The Analysis Group, LLC, is
before this Court seeking reinstatement of a
Competition in Contracting Act automatic stay of performance pending its
Government
Accountability Office protest of a Task Order award to Science Applications
International
Corporation. Plaintiff argues that the Defendant failed to justify the General
Services Administration’s decision to override the mandatory stay. In response,
the Government asserts that
it was in the best interests of the United States to perform the contract and
that imposing a stay of
performance would jeopardize the Air Force’s ability to meet its ongoing
national security
obligations.
(sections deleted)
On August 7, 2009, TAG filed its
post-award bid protest with the Government
Accountability Office (GAO) which triggered a mandatory stay under the
Competition in
Contracting Act (CICA). 31 U.S.C. § 3553(d)(3)(A) (2006). On August 14, 2009,
GSA FEDSIM
announced its decision to override the automatic stay finding that it was in the
best interests of the United States. AR482-91.
(sections deleted)
II. DISCUSSION
Usually, the filing of a protest action by a disappointed bidder on a federal
contract triggers
an automatic stay of performance under CICA. 31 U.S.C. § 3553(d)(3)(C). However,
there are
instances were CICA permits an agency to override the automatic stay provision
provided that there
is a written finding that either: (1) “performance of the contract is in the
best interests of the United
States;” or (2) “urgent and compelling circumstances which significantly affect
interests of the
United States will not permit waiting” for the bid protest decision. RAMCOR
Servs. Group, Inc. v.
United States, 185 F.3d 1286, 1287 (Fed. Cir. 1999). Here, GSA FEDSIM found that
performance
of the contract was in the best interests of the United States and overrode the
automatic stay.
Plaintiff asks this Court to reinstate that stay.
A. The Four APA Factors for Override Decisions
Review of override decisions are guided by the standards as set forth in the
Administrative
Procedure Act (APA), 5 U.S.C. § 706(A)(2) (2006), 28 U.S.C. §1491(b)(4) (2006).
Under the APA,
a decision may be overturned only upon finding the agency’s action to be
“arbitrary, capricious, an
abuse of discretion, or otherwise not in accordance with law.” Id. In
determining whether the
decision was arbitrary or capricious, four factors must be considered.
Specifically, the Court must
determine whether GSA FEDSIM: (1) relied on factors that Congress did not intend
it to consider;
(2) entirely failed to contemplate an important aspect of the problem; (3)
offered an explanation for
its decision that runs counter to the evidence; or (4) offered an explanation so
implausible that it
could not be ascribed to a difference in view or the product of agency
expertise. E-Management
Consultants, Inc. v. United States, 84 Fed. Cl. 1, 4 (2008) (quoting Motor
Vehicle Mfrs. Ass’n of the
United States v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)).
B. The Four Reilly
Factors for Override Decisions
In past cases involving CICA
override decisions, this Court has identified four factors for
consideration of whether an agency properly determined to override a CICA stay.
See Reilly’s
Wholesale Produce v. United States, 73 Fed. Cl. 705, 711 (2006). The four Reilly
factors are: (1)
whether significant adverse consequences would occur absent the override; (2)
whether reasonable
alternatives to override were available; (3) the potential costs of proceeding
with the override
relative to the purported benefits; and (4) the effect of the override on the
competition and integrity
of the procurement. See id. However, while these four additional factors may be
helpful in
analyzing the agency’s override decision, they are not dispositive.
In PlanetSpace Inc. v. United States, 86 Fed. Cl. 566 (2009), the Court held
that when
considering injunctive relief in override cases, the Court should only apply the
APA four-factor test
for injunctive relief and not the additional four Reilly factors. Id. at 567.
Planetspace held that
“Congress limited the court’s review on an agency’s decision in a CICA override
action to the
Administrative Procedure Acts standards.” Id. This Court agrees. Even so, if the
Court applied the
Reilly factors in this case, it is clear that GSA FEDSIM justified its override
of the stay.
1. Significant Adverse
Consequences Absent Override?
In its D&F, GSA FEDSIM
seriously considered all of the important aspects of the contract
and its need for continuity, and concluded that if required to impose the stay,
such a stay would
jeopardize A5XP’s mission. Specifically, GSA FEDSIM found that significant
lapses in the
continuous services provided would be comprised, such as its on going
international treaties, health
and welfare of military personnel, H1N1 virus planning, troop deployments, air
flight planning for
military operations in Afghanistan and similar locations, Air Force
Counter-Radiological Warfare
capabilities, and the implementation of toxins handling procedures and
recommendations.
Although TAG asserts that there would not be a problem with continuity since
most of the current
employees on the project were also on the project previously through TAG, it
appears to the Court
that lapses in services could occur as TAG and SAIC no longer have a working
relationship.
Therefore, the decision--that significant adverse consequences would likely
occur absent the
override--was not an unreasonable conclusion.
2. Reasonable Alternatives to Override?
Plaintiff further argues that reasonable alternatives did exist, mainly, that
the Air Force could
have extended Plaintiff’s contract through various means. Plaintiff asserts that
the decision not to
extend the contract was based on a number of faulty assumptions and, therefore,
was unreasonable.
Although the Court agrees that on its face Plaintiff’s argument does have some
merit, the bottom line
is that GSA FEDSIM, after reviewing the information it had received and the
interviews it had
conducted, concluded again that the continuity of the contract would be in
jeopardy resulting in an
increased risk to essential Air Force operations. While it is certainly possible
that continuity might
not have been threatened by an extension of TAG’s contract, it is by no means a
logically required
conclusion. The Court is unable to say that the agency’s concerns were
unreasonable in light of the working relationship issues. This is sufficient to
hold that the agency’s decision was not arbitrary
or capricious.
3. The Potential Cost of Override and Impact on the Procurement System?
With regard to the last two prongs, potential cost of the override and impact on
competition
and the integrity of the procurement system, the Court again holds that the
agency’s decision was
reasonable. However, Plaintiff does raise an issue that the Court feels it must
address, that is, the
argument that award was intentionally timed to foreclose the Government’s
options. Here, the
contract was awarded to Intervenor one day before the expiration of Plaintiff’s
contract. It is clear
that this left the Defendant with no choice but to override the stay in order
for continuity of the
contract and for the safety and protection of the United States. Although the
Defendant gives its
reasons for the lateness of the award, the Court suggests that in the future GSA
FEDSIM awards
contracts in a more timely manner in order for the bid protest process to be
preserved. The
Government’s delay also raises questions about the integrity of the process.
While there is no
evidence of specific bad intent here, a pattern of such late awards would raise
troubling issues.
C. Injunctive Relief
Denied
Lastly, the Court addresses
Plaintiff’s request for injunctive relief. In order to obtain a
preliminary equitable relief, a party must demonstrate: (1) a substantial
likelihood of success on the
merits; (2) specific, irreparable harm; (3) the balance of the hardships tips in
its favor; and (4) that
the preliminary injunction is in the public interest. Anton/Bauer, Inc. v. PAG,
Ltd., 329 F.3d 1343, 1348 (Fed. Cir. 2003).
Even though it seems to the
Court that it would have made more sense for the Defendant to extend the
previous Task Order, the Court cannot say that the decision was arbitrary and
capricious in light of the balance of delay. The possibility of delay was not
insignificant. If the Court were to award injunctive relief it would cause an
immediate work discontinuity. The length of time for TAG to reassemble its team
is unclear, which would leave many of A5XP’s critical functions, as discussed
above, without support. These concerns, therefore, favor the denial of
injunctive relief as the balance of the hardship weighs in favor of the
Defendant. Further, even if it is ultimately found by the GAO that TAG is
entitled to the award, the balance of the hardships weighs in the agency’s
favor. More damage would be done to the Government by a stay that was not
overridden when circumstances justified an override, than to the Plaintiff by an
overridden stay that was followed by a reinstatement of Plaintiff’s contract. In
one case, Plaintiff loses money for a limited period and perhaps some staff. In
the other case, the Government could lose critical continuity. (The
Analysis Group, LLC, v. U. S. and Science Applications International Corporation,
No. 09-542c, November 5, 2009) (pdf)
On request for preliminary injunctive
relief, the court must weigh the following four
factors: (1) the likelihood of plaintiff’s success on the merits; (2)
irreparable harm to plaintiff
if the injunction is not granted; (3) the balance of hardships on all the
parties; and (4) the
public interest. Erico Int’l Corp. v. Vutec Corp., 516 F.3d 1350, 1353-54 (Fed.
Cir. 2008)
(vacating trial court’s grant of preliminary injunction); see also Abbott Labs.
v. Sandoz, Inc.,
544 F.3d 1341, 1344-45 (Fed. Cir. 2008) reh’g and reh’g en banc denied (Feb. 23,
2009)
(affirming trial court’s grant of preliminary injunction). No single factor is
determinative,
and “the weakness of the showing regarding one factor may be overborne by the
strength of
the others.” FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993).
(sections deleted)
As discussed in the court’s
earlier opinion, defendant’s principal argument is that
plaintiff cannot establish jurisdiction. Jurisdiction, of course, is the
predicate to qualify for
a substantial likelihood of success on the merits. U.S. Ass’n of Imp. of
Textiles & Apparel
v. United States, 413 F.3d 1344, 1348 (Fed. Cir. 2005) (finding error in trial
court’s ignoring
jurisdictional arguments in ruling on motion for preliminary injunction).
Defendant’s
penultimate contention – made during a March 25, 2009 off-the-record telephone
conference
(defendant later submitted a motion to dismiss on April 2, 2009, arguing
mootness) – that
plaintiff’s failure to submit a response to the Solicitation renders plaintiff a
non-interested
party is not convincing. Defendant cited Rex Serv. Corp. v. United States, 448
F.3d 1305
(Fed. Cir. 2006). In Rex the United States Court of Appeals for the Federal
Circuit held that
Rex was not an actual or prospective bidder because although Rex could have
submitted bid
it chose not to bid on the contract. Id. at 1307-08. Similarly, Rex did not
achieve status as
an interested party by submitting a timely bid protest establishing that it
expected to bid, prior
to the close of the solicitation, but was prevented from doing so because of
improper agency action. Id. at 1308. The Federal Circuit also ruled that Rex did
not possess direct economic
interest as a putative bidder. Id. Rex could not establish that it had a
substantial chance of
receiving the contract because Rex did not bid; therefore, even if Rex prevailed
on its protest
a reevaluation of the procurement would not result in giving Rex the opportunity
to secure
the procurement. Id.
As plaintiff contends, Rex
is factually distinguishable from this case. Plaintiff in the
case at bar protested the Air Force’s decision to not solicit a small business
for the NSS
procurement, and “[t]he Air Force’s decision to issue a solicitation providing
for full and
open competition is precisely what the protest was intended to prevent. Unlike
Rex Service,
[plaintiff’s] protest was already pending when the Solicitation was issued.”
Pl.’s Br. filed
Mar. 31, 2009, at 3. Plaintiff is a prospective bidder for the NSS procurement,
but it did not
“submit[] a proposal in response to” the Solicitation because plaintiff was
improperly and
unfairly “pre-judged” by the Air Force to be “incapable of satisfying its
requirements, and
[plaintiff] could not afford the significant expense and effort of proposal
preparation, given
the apparent futility of such effort.” 4/ Supplemental Declaration of Anthony J.
D. Contri,
Mar. 25, 2009, ¶ 5. The question of jurisdiction “closely affects” plaintiff’s
likelihood of
success on the merits. See U.S. Ass’n of Imp. of Textiles & Apparel, 413 F.3d at
1348. The
court thoroughly addressed defendant’s jurisdictional arguments in RhinoCorps.,
2009 WL
320642, at *5-6, 10, and plaintiff has established that jurisdiction will not be
a bar to
consideration of plaintiff’s arguments on the merits.
Having moved for injunctive
relief prior to the Solicitation’s due date for submission
of proposals, plaintiff seeks to enjoin the Air Force from evaluating the one
response to the
Solicitation. Plaintiff summarizes its position stating that it filed its
protest months before
the Solicitation was issued and before the Air Force issued its “after-the-fact
D&F. This
protest properly laid the axe at the root of the problem – the Air Force’s
failure to continue
to procure the services at issue using a small business set-aside, follow-on
contract.” Pl.’s
Br. filed Mar. 31, 2009, at 6.
(sections deleted)
Defendant did not file an
opposition to plaintiff’s renewed motion for preliminary
injunctive relief on April 2, 2009, as ordered. See Order entered Mar. 26, 2009,
¶ 3. 2).
While the court cannot discount the reasonableness of the D&F, as supplemented
by the
earlier Declaration of Shirley D. Lindom, USAF, Mar. 27, 2009, and the
Declaration of Capt.
James D. Norman, USAF, Mar. 26, 2009, the court deems that plaintiff has made
compelling
showings with respect to the three other factors that outweigh the
prognostication of
plaintiff’s ultimate success on the merits of its complaint for permanent
injunctive relief. See
Amoco Prod. Co. v. Vill. of Gambell, 480 U.S. 531, 546 n.12 (1987) (noting that
standard
for permanent injunction is essentially same as temporary injunction, except
actual success
replaces need to show likelihood of success on merits). Moreover, defendant has
focused
its attention on jurisdiction. 5/ With respect to this challenge, plaintiff has
carried its burden.
See RhinoCorps, 2009 WL 320642, at *5-6, 10.
Regarding the second and
third factors – immediate and irreparable injury to plaintiff and balance of
hardships on all the parties – plaintiff has shown that the irreparable harm it
would suffer if an interim injunction is denied outweighs the harm the Air Force
will suffer if this relief is declined. Defense counsel represented during the
April 6, 2009 argument that the Air Force “desperately needs” to get a contract
in place, but defendant did not file on April 2, 2009, an opposition with a
declaration in response to plaintiff’s renewed motion.
Rather, defendant ratcheted up the anxiety level of this protest by moving to
dismiss because
the contracting officer wanted to issue a new D&F based on the same record.
The delay contemplated will
not unduly prejudice the Air Force. Although the
contracting officer completed the D&F on or about October 1, 2008, 6/ the
Solicitation was
not issued until almost five months later on February 23, 2009; defendant agreed
to a briefing
schedule that called for argument on May 22, 2009 (see Order entered Feb. 10,
2009); and
the latest revision to the briefing schedule, entered this date, calls for
argument on May 13,
2009. No showing has been made why a decision (as promised by the court) by May
18,
2009, will not be timely, given that the Air Force previously agreed to a
decision based on
May 22, 2009 date for argument.
In contrast, the risk of
harm associated with continuing with the procurement poses
greater danger to plaintiff in terms of both expense and opportunity cost:
first, the longer the
Air Force is allowed to proceed with this procurement, the more likely
additional interested
parties to this procurement will arise resulting in further litigation and
greater expense to
plaintiff; second, courts have found consistently that the loss of an
opportunity to compete
for a contract on a level playing field sufficiently establishes irreparable
harm. “An action
at law only allows recovery of ‘bid preparation costs in a suit for damages, but
not loss of
anticipated profits,’ leaving a bid protestor irreparably harmed.” Bannum Inc.
v. United
States, 60 Fed. Cl. 718, 730 (2004) (denying permanent injunctive relief), aff’d,
404 F.3d
1346 (Fed. Cir. 2005) (quoting Essex Electro Eng’rs, Inc. v. United States, 3 Cl.
Ct. 277, 287
(1983), aff’d, 757 F.2d 247 (Fed. Cir. 1985)).
Finally, the public interest
will be served by assuring that the Air Force is following a mandatory
procurement procedure when the record shows that initially the Air Force deemed
the procedure to be inapplicable.
CONCLUSION
Accordingly, based on the foregoing,
IT IS ORDERED, as follows:
1. Plaintiff’s Amendment to and Renewal of Application for Temporary Restraining
Order and Preliminary Injunction, filed on March 25, 2009, as supplemented on
March 31,
2009, is granted insofar as defendant, through the United States Air Force, its
officers,
agents, employees, and all other persons acting in connection therewith, shall
not proceed to
evaluate any offer submitted in response to Solicitation No. FA9453-09-R-0001,
for full and
open competition for the procurement of services for the 709th NSS
Counterproliferation and
Nuclear Weapon requirement, pending the entry of an order on plaintiff’s
complaint for a
permanent injunction, which the court commits to issue by midnight on May 18,
2009.
(Rhinocorps LTD,
Co., v U. S. 08-410C, April 7, 2009) (pdf)
An agency may override the mandatory CICA stay if it shows “urgent and
compelling circumstances” affecting interests of the United States. 31 U.S.C. §
3553(d)(3). We review CICA override decisions pursuant to the Tucker Act, 28
U.S.C. § 1491(b). The Tucker Act grants this court jurisdiction to hear
objections to agency decisions to override the mandatory stay provisions. RAMCOR
Servs. Group, Inc. v. United States, 185 F.3d 1286, 1290 (Fed. Cir. 1999). We
“review the merits of an override independent of any consideration of the merits
of the underlying contract award.” PGBA, LLC v. United States, 57 Fed. Cl. 655,
658 (2003) (citing RAMCOR, 185 F.3d at 1291).
The Supreme Court explained that a decision
is arbitrary and capricious “if the agency has relied on factors which Congress
has not intended it to consider, entirely failed to consider an important aspect
of the problem, offered an explanation for its decision that runs counter to the
evidence before the agency, or is . . . implausible . . . .” Motor Vehicle Mfrs.
Ass’n. of the United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S.
29, 43 (1983). The agency’s decision must be “based on a consideration of the
relevant factors.” Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S.
402, 416 (1971).
Plaintiff offered arguments regarding
four factors courts normally consider in deciding whether to grant an
injunction. It contended that NASA did not consider four additional “Reilly
factors” in making its decision. See Reilly’s Wholesale Produce v. United
States, 73 Fed. Cl. 705, 711 (2006) (listing factors “an agency must consider in
making an override decision based upon urgent and compelling circumstances.”).
We did not consider the Reilly factors at the hearing because Congress limited
the court’s review of an agency’s decision in a CICA override action to the
Administrative Procedure Act standards. See, e.g., Chapman Law Firm Co. v.
United States, 65 Fed. Cl. 422, 424 (2005) (stating that “it would be contrary
to the legislative scheme to impose such an additional requirement . . . in
order to reinstate the statutory stay applicable during the GAO protest
period.”); Advanced Sys. Dev., Inc. v. United States, 72 Fed. Cl. 25, 36-37
(2006) (holding that the factors for injunctive relief are not needed in a CICA
override determination because “declaratory judgment achieves the same
effect.”).
NASA justified its override of the stay
by reference to Presidential policy decisions concerning the shuttle program and
international commitments pertaining to the space station. Plaintiff argued that
the President could reverse the policies if necessary and that the international
partners could contribute to the supply program. However, such considerations
are speculative.
CONCLUSION
NASA considered all important aspects of
the contracts and showed that delay would adversely affect the interests of the
United States. Plaintiff’s arguments to the contrary do not diminish the fact
that NASA’s determination was not arbitrary or capricious but considered fully
and thoroughly. The Agency’s conclusions are reasonable. (Planetspace
Inc., v. U. S., Orbital Sciences Corporation, and Space Exploration Technologies
Corporation, No. 09-0099C, April 2, 2009) (pdf)
D. Was DEA’s
Override Decision Arbitrary and Capricious?
1. CICA’s automatic stay provision
When a bid protest action is initiated at the GAO, an automatic stay of the
protested contract
award is triggered under CICA until the protest action is resolved. 31 U.S.C. §
3553(c)(1). This
automatic stay serves the important purpose of preserving “competition in
contracting and ensur[ing]
a fair and effective process at the GAO.” Reilly’s Wholesale Produce, 73 Fed. Cl.
at 710 (citing
Advanced Sys. Dev., Inc. v. United States, 72 Fed. Cl. 25, 31 (2006)). The
automatic stay has been
described as CICA’s “teeth,” and was included in the Act to prevent agencies
from circumventing
the procurement process. PGBA LLC v. United States, 57 Fed. Cl. 655, 658 (2003).
Without the
automatic stay, agencies could proceed to perform a contract while it was being
protested at the
GAO, and then later reject the GAO recommendation because it would be in the
“best interest” of
the agency to continue the contract. Id. Thus, the automatic stay provision
“preclude[s] such fait accomplis and . . . facilitate[s] a fair and equitable remedy to venders who are
illegally denied
Government contracts.” Id. at 657 n.3 (citing H. Rep. No. 99-138, at 4-5
(1985)).
Nevertheless, an agency may override an automatic stay if it notifies the GAO in
writing that
either “performance of the contract is in the best interests of the United
States,” or “urgent and
compelling circumstances that significantly affect interests of the United
States will not permit
waiting for the decision of the Comptroller General concerning the protest.” 31 U.S.C. §
3553(d)(3)(C). When asserting that urgent and compelling circumstances require
immediate
performance of a contract, there are several factors an agency must consider,
including: (1) “whether
significant adverse consequences will necessarily occur if the stay is not
overridden;” (2) “whether
reasonable alternatives to the override exist;” (3) “how the potential cost of
proceeding with the
override, including the costs associated with the potential that the GAO might
sustain the protest,
compare[] to the benefits associated with the approach being considered for
addressing the agency’s
needs;” and (4) the impact of the override on competition and the integrity of
the procurement
system, as reflected in CICA. Reilly’s Wholesale Produce, 73 Fed. Cl. at 711;
see also Superior
Helicopter, 78 Fed. Cl. at 189. Failure by an agency to consider just one of
these factors is fatal to an override decision based on urgent and compelling
circumstances. When considering a best
interests determination, there must be some rationale asserted by the agency
that is above and beyond
its original purpose when it solicited bidders for the procurement, and “that
absolves the agency of
its obligation to await the GAO’s recommendation.” Advanced Sys. Dev., 72 Fed. Cl. at 31 (citing
PGBA, 57 Fed. Cl. at 662).
2. Urgent and compelling circumstances
Under the first prong of an “urgent and compelling circumstances” inquiry, an
agency must
show that significant adverse consequences will occur if the stay is not
overridden. Defendant
asserts its override decision is proper here because its IT systems are of [*]
importance to the
performance of DEA’s law enforcement mission, and urgent and compelling
circumstances affecting
the interests of this nation will not permit waiting for the recommendation of
the GAO. D&F at 2,
¶ 8. Defendant’s basic contention is that the current bridge contracts are no
longer a viable option
because of staffing shortages: “as EMS award neared, employers for the ‘bridge’
contracts began
experiencing difficulty retaining qualified employees who were familiar with,
knowledgeable about,
and cleared to work on DEA’s secure, law enforcement IT equipment.” D&F at 3, ¶
10.
Plaintiff contests defendant’s findings, claiming that they are without factual
support.
Plaintiff asserts that staffing levels have “remained adequate to perform the
required tasks.” Mem.
Of P. & A. In Supp. Of Pl.’s Application, at 16-17. Specifically, plaintiff
claims that DEA’s own
data “shows that NGS has maintained a consistently high level of performance
without any
significant impact on the level of service,” and cites to DEA metrics data,
which shows that DEA
server and network availability has been consistently greater than 99% since
January 2007. Id. at
17 (citing First Smith Decl. ¶ 4). Moreover, plaintiff contends that staffing
levels are consistent with
contractual requirements. See Id. at 18 (In the EMS procurement, DEA states a
need for 57 onsite
systems administrators; currently, the incumbent contractor employs 65.
Furthermore, “the current
help desk staffing level is based on a competitive bid selected by DEA in August
2007").
In the D&F, the first and second
declarations of Dennis R. McCrary, and in Mr. McCrary’s
testimony at oral argument on October 7, 2008, defendant cites to several
specific examples of how
NGS staff shortages have adversely affected DEA’s law enforcement mission.
Plaintiff, however,
claims that the examples and incidents listed by defendant bear no relation to
services provided
under the bridge contracts. The Court will address each incident in turn.
(sections deleted)
The decision in Advanced Systems Development
is instructive here. See 72 Fed. Cl. 25.
In that case, the plaintiff was an incumbent provider of IT solutions to the
Department of Defense,
and was protesting the award of a consolidated IT support contract at the GAO.
Id. at 27. The
defendant there asserted three primary reasons justifying an override of the
CICA stay: “inefficiency
of the current model, the need for a smooth transition by permitting the awardee
to immediately hire
incumbent personnel, and avoiding a loss of IT services to the customer.” Id.
Like the case at bar,
the D&F in that case stated “[t]heir current employer, even with a contract
extension, could not offer
stable employment for more than a few months and these individuals would likely
seek other
opportunities elsewhere.” Id. at 28. The court expressed that while “loss of
service might be a valid
concern,” there was no indication that service would be jeopardized, and
defendant’s concern
regarding the availability of personnel during the transition period was not
sufficient to justify an
override of the CICA stay. Id. at 31-32. Moreover, the court found that the
defendant’s justification
on the basis of “an exodus of required specialists” was internally inconsistent,
because defendant had
asserted that the awardee could fully staff the job, and then voiced “the
unfounded concern that
incumbent workers who might otherwise be interested in accepting employment with
[the awardee],
will be placed in limbo.” Id. The court found that this justification for
lifting the stay presented “the
very type of competitive disadvantage that the CICA seeks to prevent.” Id. at
32.
Similarly here, defendant bases its override
decision on alleged staffing shortages.
Nonetheless, defendant does not allege that there will be a loss of IT service;
rather, its most severe
contention is that DEA’s current IT O&M support has deteriorated. D&F at 6, ¶ 6.
Plaintiff has
shown, however, that current staffing levels are adequate and that they are able
to hire additional
employees as needed. Tr. at 17-18. The specific examples provided by defendant
allegedly
demonstrating deterioration of IT services due to staffing shortages, are
without support in the
record. In order for the court to uphold an override decision, the agency must
“not only sort between
the relevant and irrelevant factors, but must also render findings with respect
to those that are
relevant that do not ‘run[] counter to the evidence before the agency.’”
Reilly’s Wholesale Produce, 73 Fed. Cl. at 711 (citing Motor Vehicle
Mfrs. Ass’n, 463 U.S. at 43 (additional citations omitted)).
Moreover, defendant has failed to provide any support for its bald assertion
that the current bridge
contracts leave DEA open to [***]. Perhaps even more importantly, however,
defendant has not
given any indication as to how proceeding with the EMS contract will alleviate
these concerns. See
Superior Helicopter, 78 Fed. Cl. at 188-89. SRA itself noted during oral
argument that it will be
staffing the contract with employees from NGS as well as from the other bridge
contractors. Tr. at
74-76. Thus, while the staffing situation under the protested contract may be
preferable to defendant,
defendant has failed to show that significant adverse consequences make
proceeding with the
contract necessary.
As a corollary to this Court’s finding that there are no significant adverse
consequences to
maintaining the status quo that necessitate the override, and for the reasons
explored in detail above,
the bridge contracts provide a reasonable alternative to proceeding with the EMS
contract.
Defendant, however, failed to even consider whether reasonable alternatives to
the override exist,
stating only that “these ‘bridge’ contracts are no longer a viable option and
there are no other
alternatives available.” D&F at 3, ¶ 10. Therefore, defendant also fails to
satisfy the second prong
of the urgent and compelling circumstances inquiry. Additionally, the Court
notes that these bridge
contracts have been in place for 22 months. During that time, three contract
awards, including the
one currently at issue, have been protested at the GAO; yet, until now, DEA has
never attempted to
override the stay. Therefore, during the previous bid protests, DEA must have
found the bridge
contracts to be a reasonable alternative to proceeding with the protested
contract awards. The record
reveals no drastic change in the performance of the bridge contracts over the
past 22 months that
would alter this determination, aside from defendant’s preference to begin
performance of the EMS
contract. While frustration with the prolonged nature of this solicitation is
understandable, it alone
is not sufficient justification to override the stay.
The third prong of the inquiry requires an agency to fully consider how the
potential cost of
proceeding with the override, specifically the costs associated with the
possibility that GAO sustains
plaintiff’s protest, balance against the benefits associated with proceeding to
perform the protested
contract. Defendant fails to do so here. With regard to the pending protest at
the GAO, the D&F
states:
I have considered the possibility that the GAO could sustain NGS’ protest. In
the
event that should happen, any corrective action directed would naturally result
in
additional costs and effort by DEA. Notwithstanding those costs and energies, it
is
essential that DEA have in place a sustainable IT O&M capability now and in the
future. By proceeding with this contract, DEA would have that capability and
would be able to maintain it, albeit at higher cost and effort, even if
corrective action is ordered.
D&F at 5, ¶ 16. This statement is
problematic for several reasons.
First, defendant gives unacceptably brief
treatment to the potential costs of a GAO recommendation sustaining the protest.
This is particularly disturbing in light of defendant’s
assertions regarding the extreme difficulties of recruiting and hiring IT
personnel in a timely manner,
the fact that “the personnel security clearance requirement generally adds an
additional 90 days to
the process,” and defendant’s concern over employees leaving the bridge
contractors to seek more
“stable” employment. D&F at 4, ¶¶ 11-12. Overriding the stay will do nothing to
alleviate the issue
of instability in employment; until the GAO issues its decision, employees of
SRA will have no more
job security than employees of the current bridge contractors. Moreover, the
difficulty in hiring and
obtaining security clearance for IT staff, which defendant cites as an incentive
to begin performance
on the new contract immediately, actually counsels against overriding the stay.
Defendant
emphasizes the cost of finding and screening new employees, which consequently
presents a great
risk to defendant if it proceeds with the contract and, in two months, the GAO
sustains the protest.
Second, the D&F refers to DEA’s ability to maintain its IT O&M capability in the
future -
even in the face of a recommendation invalidating the contract award - by
proceeding immediately
with contract performance. This indicates an attempt by defendant to circumvent
the competitive
process by exactly the type of action Congress intended the automatic stay
provision of CICA to
prevent. See Advanced Sys. Dev., 72 Fed. Cl. at 31 (“The automatic stay is
intended to preserve the
status quo during the pendency of the protest so that an agency would not
cavalierly disregard
GAO’s recommendations to cancel the challenged award”).
This, of course, indicates the fourth factor an agency must consider when
issuing an override
decision based on urgent and compelling circumstances: “the impact of the
override on competition
and the integrity of the procurement system.” Reilly’s Wholesale Produce, 73
Fed. Cl. at 711; see
also Superior Helicopter, 78 Fed. Cl. at 189. Defendant essentially asserts a
national security
argument regarding the necessity of the override:[***]. D&F at 3, ¶ 9.
Nonetheless, the record fails
to demonstrate that abiding by the CICA stay will compromise the safety and
welfare of agency
personnel. Moreover, defendant does not consider the impact of its override
decision on competition
at all. “Ultimately, the public’s interest in a fair, competitive federal
procurement system outweighs
unsubstantiated claims, even those related to the public safety.” Superior
Helicopter, 78 Fed. Cl.
at 200 (citing Reilly’s Wholesale Produce, 73 Fed. Cl. at 716). Thus,
defendant’s interest in overriding the stay here is outweighed by the public’s
interest in maintaining competition and the integrity of the procurement system.
In light of defendant’s failure to meet any of the four prongs of an urgent and
compelling circumstances inquiry, defendant’s override on this basis is invalid.
3. Best interests of the United States
Defendant also maintains that overriding the
stay and proceeding with the new contract is in the best interests of the United
States. D&F at 6, ¶ 1. In order for a stay override to be proper under
a best interests justification, “[t]here must be some rationale - above and
beyond the principle aim
originally sought when [the agency] decided to engage bidders in the competitive
procurement - that
absolves the agency of its obligation to await the GAO’s recommendation.
Advanced Sys. Dev., 72
Fed. Cl. at 31. Thus, simply stating that the new contract is better or more
cost effective is not
enough to justify overriding the stay. Id. The Court has already concluded that
defendant’s
assertions with regard to the necessity of overriding the stay amount to nothing
more than
defendant’s strong preference to begin performance of the protested contract.
Mr. McCrary testified
at oral argument that his problem is with the “bridge contract construct,” which
supports this finding.
Tr. at 60:6-7. In support of its best interests override decision, defendant has
also asserted a cost
savings of approximately [*] per month if it is able to proceed with performance
of the new contract,
rather than continue under the bridge contracts. Nonetheless, similar amounts
have been found
insufficient to support a best interests override. See Automation Techs., Inc.
v. United States, 72
Fed. Cl. 723, 728-29 (2006); PGBA, 57 Fed. Cl. 655. Defendant has therefore
failed to establish that
overriding the stay is in the best interests of the United States.
Because defendant has failed to establish that overriding the stay is necessary
because of
urgent and compelling circumstances, or because it is in the best interests of
the United States,
defendant’s override decision is invalid. DEA failed to consider important,
relevant aspects of the
override analysis, and offered explanations that run contrary to evidence before
it. Defendant’s
decision to override the automatic CICA stay is consequently arbitrary,
capricious, and contrary to
law. (Nortel Government Solutions, Inc., v. U.
S. and Systems Research and Application Corporation, No. 08-682C, October
20, 2008) (pdf)
III. Application of Legal Standards to
This Case
The court analyzes whether NHTSA’s decision to override was “arbitrary and
capricious” by examining NHTSA’s OM in the light of the Motor Vehicle factors,
as
further elaborated by the CICA cases in this court as to the “important aspect[s]
of the
problem” prong:
(1) whether significant adverse consequences would occur if the agency did
not override the stay (2) whether reasonable alternatives to the override
were available, (3) how the benefits of overriding the stay compared to the
potential cost of the override, including costs associated with the potential
that the protester might prevail before GAO, and (4) the impact of the
override on the competition and integrity of the procurement system.
Superior Helicopter, 78 Fed. Cl. at 189 (citing Reilly’s Wholesale, 73 Fed. Cl.
at 711).
A. Significant Adverse Consequences
The first factor to consider is whether the agency analyzed “whether significant
adverse consequences will necessarily occur if the stay is not overridden.”
Reilly’s
Wholesale, 73 Fed. Cl. at 711; see also Chapman Law Firm Co. v. United States
(Chapman 2004), 62 Fed. Cl. 464, 468 (2004) (discussing, in a “best interests”
case, how
the agency’s consideration of consequences of abiding by an automatic stay
influenced
the court’s decision).
The OM states that the “purpose of the contract is to provide critical
[information
technology] services throughout the agency.” AR 1. These services include
maintaining
the grants tracking system (GTS) which tracks NHTSA traffic safety grants to
states that
are worth “hundreds of millions of dollars.” Id. Without an IT contractor, the
OM notes,
“the agency has neither the staff nor the requisite expertise to maintain [its
IT] systems for
several months on its own without outside support,” especially considering
“fiscal-yearend
closeout activities.” Id. While the court understands that IT is important to
maintain
these systems, NHTSA failed to address whether, without Centech’s services, the
“adverse consequences will necessarily occur.” See Reilly’s Wholesale, 73 Fed. Cl. at
711 (emphasis added). The necessity of engaging the awardee is closely related
to the
second factor: whether the agency considered reasonable alternatives to
overriding the
automatic stay. See id. (noting that the second factor is an alternative way of
considering
the first factor). If the agency had reasonable alternatives to engaging the awardee,
adverse consequences to the agency’s mission would not necessarily result from
the stay.
Here, NHTSA has shown some possible adverse consequences of not having an IT
contractor but, in light of the possible availability of reasonable
alternatives, the OM does
not support the conclusion that such consequences would necessarily occur if
NHTSA did
not override the automatic stay.
B. Reasonable Alternatives
The second factor the court evaluates is whether the agency considered “whether
reasonable alternatives to the override exist that would adequately address the
circumstances presented.” Reilly’s Wholesale, 73 Fed. Cl. at 711; see also
Alion
Sci. &
Tech. Corp. v. United States (Alison Sci.), 69 Fed. Cl. 14, 27–29 (2005)
(discussing
reasonable alternatives in a case where the agency used both “best interests”
and “urgent
and compelling circumstances” to justify an override).
NHTSA claims to have considered a variety of options. See AR 2. It claims to
have evaluated whether it could forego IT services, extend e-Mangement’s
contract, or
use an “existing procurement vehicle.” AR 2. As noted in Part III.A, NHTSA
concluded
it could not forego any IT contractor support. AR 1 (“[NHTSA] cannot lose its IT
systems for that length of time and continue to successfully carry out its
mission.”); see
supra Part III.A (noting that without IT services there could potentially be
significant
adverse effects on the agency). It also concluded that it could not extend e-
Management’s current contract. AR 2. NHTSA stated that “absent a waiver” the e-
Management contract was capped by the General Services Administration (GSA) at
five
million dollars, and that amount would have continued the contract only for a
few weeks
after contract extension. Id. Finally, defendant “reviewed other agency
contracts” to
assess if other existing contracts could fulfil NHTSA’s IT needs. Id. The OM
found that NHTSA did not have any available contracts that would fulfil the needs of the
agency.
Id.
As to the second option–extending e-Mangement’s contract–the court found that
information in the AR in this case is not fully consistent with statements in
the OM.
Compare AR 118–22, 171, with AR 1–3 (the OM). The AR suggests that NHSTA was
ready to abide by the stay and prepared to continue using the existing IT
service
contractor. AR 118–22, 171. The Chief Information Officer (CIO) of NHTSA,
Margaret
O’Brien, made statements in email pointing to this conclusion, such as, “We
could add
more funding to ensure coverage for Centech phase-in and/or protest response
decisionmaking.
. . . If the current delegation of authority could apply, we could do a
mod[ification] for more to cover bringing [e-Mangement employees] and possible
others
back for 2 or more weeks.” AR 119. Ms. O’Brien also sent an e-mail stating:
E-management is still under contract and
could have people here as soon as
tomorrow if you so direct them. If you want us to also to do a
mod[ification] to the existing contract to add funds under the current ceiling
to carry us to the end of September, please let me know.
AR 121. In addition to the possible
short-term engagement of e-Management, the AR
shows that NHTSA also discussed proceeding under Federal Acquisition Regulation
(FAR) section 16.505. AR 118. Section 16.505 of the FAR includes an option for
solesource
contracting “in the interest of economy and efficiency . . . [as] a logical
follow-on
to an order already issued.” 48 C.F.R. § 16.505(b)(2)(iii) (2008). Ms. O’Brien,
on
September 23, 2008, wrote:
I would like to issue a sole source task order under COMMITS for a logical
follow-on with e-Management for a period of 6 months. That period will
allow time for the protest to be resolved and also for an orderly phase-in to
the awardee. Centech ha[s] already hired some of the critical staff, such as
the lead for infrastructure and web and GTS developers. They are now
without work and could become unavailable altogether. It is essential that
we move as rapidly as possible to get e-Management back on board.
AR 122 (emphasis added). Mr. Ross Jefferies, a NHTSA contracting official,
replied to
the CIO stating, “I am considering all available options to the agency including
continuing the work with e-[M]anagement in the short term.” AR 171. The AR does
not
make clear how and why NHTSA concluded that it could not extend e-Management’s
contract.
Notes from a meeting with Rebecca Pennington, the official who signed the OM,
do not indicate much discussion of the reasoning stated in the OM. AR 174–78.
The
notes indicate that the parties discussed “CICA,” AR 174, 175, and the $5
million dollar
cap, AR 175, but mention nothing about the substance of the need for an
override, AR
174–78. The notes do not reflect discussion of the options for continuing with
e-Management, except for noting the GSA cap, AR 175, and containing the statement
“[e-Management] personnel critical task support,” AR 178.
The OM says nothing about Ms. O’Brien, the CIO, who, in her September 23,
2008, email, AR 118, suggested that the e-Management contract could be extended
under
FAR § 16.505(b)(2). See AR 1–3. The lack of evidence of a serious exploration of
options for obtaining temporary IT services appears to the court to veer close
to, if not to
reach, NHTSA’s “failing to consider an important aspect of the problem.” Motor
Vehicle, 463 U.S. at 43.
NHTSA also cannot render findings that
“run[] counter to the evidence before
[it].” See Advanced Sys., 72 Fed. Cl. at 30 (quoting Motor Vehicle, 463 U.S. at
43). The
OM states a conclusion that appears counter to the discussions in the AR. See AR
118–22, 171. The email correspondence in the AR indicates that there may have
been
reasonable alternatives and NHTSA choose not to pursue them. See AR 118–22, 171.
This decision could be considered “arbitrary and capricious.” Nevertheless, it
is possible
that the discussion about alternatives in the OM fits into the “zone of
acceptable results”
that “requires only that the final decision reached by an agency be the result
of a process
which ‘considers the relevant factors’ and is ‘within the bounds of reasoned decisionmaking.’”
Reilly’s Wholesale, 73 Fed. Cl. at 709 (quoting Balt. Gas & Elec. Co. v.
Natural Resources Def. Council, Inc., 462 U.S. 87, 105 (1983)).
C. Cost-Benefit Analysis
The third factor is whether the agency considered “how the potential cost of
proceeding with the override, including the costs associated with the potential
that the
GAO might sustain the protest, compare to the benefits associated with the
approach
being considered for addressing the agency's needs.” Reilly’s Wholesale, 73 Fed. Cl. at
711; see Superior Helicopter, 78 Fed. Cl. at 189 (noting that the agency must
consider
“how the benefits of overriding the stay compared to the potential cost of the
override,
including costs associated with the potential that the protester might prevail
before
GAO”); see also Chapman 2004, 62 Fed. Cl. at 468 (discussing, in a “best
interests” case,
how the cost-benefit analysis influenced the court’s decision). The court views
this factor
in light of CICA’s legislative history. The legislative history of CICA states
that the
agencies should consider the costs of GAO’s sustaining the protest before it
issues an
override:
[T]he head of the procuring activity should consider potential costs to the
government from carrying out relief measures as may be recommended by
the Comptroller General if the protest is subsequently sustained. This is to
insure that if the Comptroller General sustains a protest, such forms of relief
as termination, recompetition, or re-award of the contract will be fully
considered for recommendation. Agencies in the past have resisted such
recommendations on the grounds that the government’s best interest would not be
served by relief measures of this sort because of the additional expenses
involved. [The automatic stay] is designed to preclude that argument in the
future, and thus to avoid prejudicing those relief measures in the Comptroller
General’s review.
H.R. Rep. No. 98-861 at 1436 (Conf.
Rep.).
The OM’s cost-benefit analysis is flawed.
First, the OM identifies the costs of
GAO’s sustaining the protest as “reprocurement costs.” AR 2. These are not the
only
costs of the override. One additional cost for an agency to consider is the cost
to the
integrity of the procurement system. See H.R. Rep. No. 99-138, at 4–5 (1985)
(noting the
importance of the override); Automation Techs., Inc. v. United States
(Automation
Techs.), 72 Fed. Cl. 723, 730 (2006) (noting that an agency is “constrained by a
consideration of relevant factors, including the ramifications of an agency loss
in the
GAO protest, and the impact of an override on the competition in contracting and
bid
protest process, as well as respect for the GAO, an important component in the
statutory
structure of how to address protests to government procurement actions”).
The OM discounts reprocurement costs. It compares the costs of the override with
the costs of continuing e-Management’s contract. AR 2 (“On balance, I believe
that the
agency has an equal ([though] small) chance of incurring reprocurement costs,
whether or
not it extends contract performance with the awardee. Stated another way,
extending the
protester’s performance . . . would not lesson the agency’s risk of incurring
reprocurement costs.”). The agency concluded that the costs were balanced. Id.
This is
because e-Management was not the “next in line for award” and NHTSA concluded
that,
if e-Management were successful in its bid protest, then “it would have little
choice but to
decide to recompete the effort.” Id.
Furthermore, the OM determined that, because NHTSA “has a reasonable chance
of prevailing on the merits,” the cost of the override was low. Id. This is an
impermissible consideration. This type of balancing would allow an agency to
employ
the very reasoning that CICA sought to prevent. See H.R. Rep. No. 99-138,
at 4–5 (noting the importance of the override in preventing agencies from
“ignoring the protest process” and “facilitat[ing] a fair and equitable remedy
to vendors who are illegally denied Government contracts”). The government
articulated its optimistic view of the likely outcome of the protest to discount
the costs of the override.
The OM lists the benefits of overriding
the stay as (1) avoiding “termination costs” and (2) “uninterrupted performance
beyond the calendar year.” AR 2. These are not the sorts of benefits envisioned
in the cost-benefit calculation. If, after considering reasonable alternatives,
an agency believes that significant adverse consequences will result if the stay
is not overridden, then the “benefit” variable to be used in the calculation
is the benefit of avoiding the significant adverse consequences. See Chapman Law
Firm
v. United States (Chapman 2005), 67 Fed. Cl. 188, 192 (2005) (noting that
without the
override the agency would lose three million dollars a month and public property
would
be subject to vandalism and other threats to public safety); Alion Sci., 69 Fed. Cl. at 25,
27, 29 (noting the time-critical nature of the contract and the lack of multiple
vendors).
There has been no showing, as there was in Chapman 2005, 67 Fed. Cl. at 192,
that
serious adverse consequences will necessarily befall the government in the
absence of an
override.
D. Impact on Competition and the Integrity of the Procurement System
The final factor is whether the agency considered “the impact of the override on
competition and the integrity of the procurement system, as reflected in the
Competition
in Contracting Act.” Reilly’s Wholesale, 73 Fed. Cl. at 711; see also Automation
Techs.,
72 Fed. Cl. at 729–30 (discussing the impact on the procurement system in a
“best
interests” case). Defendant claims to have “considered the impact on competition
and on
the integrity of the procurement process” in the OM. AR 2. However, the OM
failed to
offer any reasoning that shows that it actually considered the integrity of the
procurement
system Congress created in CICA. See id. at 2–3. The text of the paragraphs in
which
the consideration is mentioned reads in full as follows:
I considered the impact on competition and on the integrity of the
procurement process, should the agency decline to suspend performance.
In my view, the competition process is best served by allowing the awardee
to proceed. As noted above, I conclude from discussions with the relevant
agency officials that the agency has a reasonable chance of prevailing.
Moreover, the protester is not next in line for award. Taken together, these
two points lead me to conclude that allowing the awardee to proceed is the
fairest approach. As an extra safeguard, however, the awardee’s
performance will be limited to essential efforts during the pendency of the
protest.
Id.
The claimed consideration of the impact on the procurement system do not
recognize or vindicate the purpose of the automatic stay. NHTSA first states
that it “has a
reasonable chance of prevailing.” Id. at 3. This observation does not relate to
the
integrity of the procurement system. It relates to the merits of the protest,
not to the automatic stay in CICA. NHTSA also states that the protestor is not
“next in line.” Id.
Again, this is not an appropriate evaluation of the impact of the override on
the
procurement system. The purpose of the procurement system as envisioned in CICA
is a
fair process in which disappointed bidders can seek review at GAO. GAO was given
the
automatic stay in CICA to promote these policies. See H.R. Rep. No 98-861 at
1435–36
(Conf. Rep.). NHTSA then states that it has “limited [Centech’s performance] to
essential efforts during the pendency of the protest.” AR 3. Again, this
statement has
nothing to do with the integrity of the procurement process. The CICA stay was
meant to
prevent the “fait accompli” of a contractor establishing a relationship in a new
contract
with an agency long before GAO issued its decision. See H.R. Rep. No. 99-138, at
4–5.
Limiting the contractor to “essential efforts,” AR 3, does not address Congress’
concerns.
The court finds that NHTSA, by failing to consider the impact of its override on
the procurement system, has “failed to consider an important aspect of the
problem,”
Motor Vehicle, 463 U.S. at 43, and has, therefore, failed to act rationally and
in
accordance with law. NHTSA’s Override Memorandum fails to meet even the
deferential
standards of APA review and the court must set aside the override. (E-Management
Consultants, Inc., v. U. S. and Centech Group, Inc., 08-680C, October 14,
2008) (pdf)
The threshold inquiry in this case is whether there has indeed
been an
override of the automatic stay imposed on the original contract. Plaintiff
alleges that the bridge contract between MCSC and Avineon is the counterpart
to an override and that, in essence, defendant is using the bridge contract as a
method of circumventing the formal requirements of 31 U.S.C. §
3553(d)(3)(C)(i). Defendant contends that the CO’s affidavit and testimony
confirm that the bridge contract is distinct from the original contract and does
not constitute a de facto override. At the conclusion of the hearing, the court
announced its finding that the bridge contract between defendant and Avineon
did not constitute an override of the automatic stay. Our reasons for so finding
are summarized herein.
The
automatic stay was “intended to preserve the status quo during the
pendency of the protest so that an agency would not cavalierly disregard the
GAO's recommendation to cancel the challenged award.” Advanced Sys. Dev.,
Inc. v. United States, 72 Fed. Cl. 25, 30-31 (2006) (citing PGBA, LLC v.
United States, 57 Fed. Cl. 655, 660 n.8 (2003)). Furthermore, “‘Congress
included these bid protest provisions to help ensure that the mandate for
competition would be followed and that vendors wrongly excluded from
Federal contracts would receive fair relief.’” Reilly’s Wholesale Produce v.
United States, 73 Fed. Cl. 705, 710 n.8 (2006) (quoting H. Rep. No. 99-138
(1985)). The automatic stay therefore was intended to guarantee that plaintiffs
could receive “fair relief” and would not be prejudiced in their protest before
the GAO.
Section 3553(d)(3)(C), however, allows
the “head of the procuring
activity” to override an automatic stay and authorize performance of the
contract if performance “is in the best interests of the United States” or if
“urgent and compelling circumstances . . . will not permit waiting for the
decision of the [GAO].” Id. § 3553(d)(3)(C)(i). The head of the procuring
activity must first deliver a written finding to the Comptroller General. Id.
The government and the contract awardee may then commence performance
despite disturbing the status quo and possibly prejudicing the protesting
offeror
at the GAO.
No such finding was made in this case,
however, because the agency
takes the position that it was unnecessary. This case is therefore unlike
traditional override cases in that we are asked to decide whether the bridge
contract represents the functional equivalent of an override. We have not been
presented with any decisions discussing this question, but in our view the
relevant question is whether the bridge contract shares the same character or
function as a formal override and, thus, whether the bridge contract could
prejudice plaintiff in its protest before the GAO or in subsequently performing
the work if it is successful in its protest.
The facts here demonstrate that the
character of the bridge contract is
distinctly different from an override because the bridge contract does not
disturb the status quo with respect to the original contract. The testimony and
affidavit of the CO clearly show that she issued a stop-work order to Avineon,
preventing further performance on the original contract. While an override is
meant to authorize performance on the protested contract because of special
circumstances, a bridge contract can be a separate, self-contained contract. In
this case, it was. MCSC will receive information technology services only
during the pendency of the GAO protest. The appropriation used to fund the
bridge contract is also separate from that used to fund the original contract,
and
the appropriated funds for the original contract remain untouched. The CO has
also affirmed that the bridge contract’s 120-day term is independent of the
term of the original contract. The bridge contract’s term will thus not lessen
the amount of work. Although, as plaintiff points out, the bridge contract is
for the identical information technology services involved in the original
contract, this fact alone is insufficient to prove that the bridge contract is
an
iteration, in whole or in part, of the original contract and, thus, an override.
Contracts may share the same subject matter and yet remain separate and
distinct from one another. We therefore conclude that the bridge contract is
not a partial iteration of the original contract but is a new contract with a
distinct character and function. The status quo with respect to the original
contract remains unchanged.
There is also no reason to think that the
award to Avineon will
prejudice plaintiff in the action before the GAO. Moreover, if plaintiff is
successful at the GAO, the original contract, in its entirety, will still be
available to plaintiff.
For these reasons, the court finds that
the bridge contract between
MCSC and Avineon is not an override of the automatic stay as provided for by
section 3553(d)(3)(C)(i). The court is therefore not required to reach the
merits of an override. Accordingly, the Clerk is directed to enter judgment for
the United States and to dismiss the complaint. (Access
Systems, inc., v. U. S. and Avineon, inc., No. 08-708C, October 10, 2008) (pdf)
Generally, a reviewing court does not disturb an
agency award unless it is arbitrary,
capricious, an abuse of discretion, or otherwise violates applicable procurement
law. 28 U.S.C. § 1491(b)(4); 5 U.S.C. § 706; Impresa Construzioni Geom. Domenico Garufi
v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001). Alion offers several
reasons why DISA’s award to ITT was arbitrary, capricious, and an abuse of discretion. The
court was concerned primarily with two of these. First, we were uncertain whether DISA
meaningfully considered the extent and impact of the OCIs in ITT’s proposal. Alion maintains
that DISA relied heavily on ITT’s assurances that its firewalling of subcontractors would
mitigate such conflicts without reaching an independent conclusion. Second, we were bothered
by the source selection authority’s use of term “stranglehold” to describe Alion’s
incumbent status. This statement could suggest that DISA awarded the contract upon consideration
of factors other than those in the Solicitation.
We considered these issues fully. Alion is unlikely to succeed on the merits,
especially considering the deferential standard of review to which this court is
bound in analyzing “best value” procurements. See, e.g., Bean Stuyvesant, LLC v. United
States, 48 Fed. Cl. 303, 320 (2000). (Alion Science
and Technology Corporation v. U. S. and Advanced Engineering & Sciences, a
division of ITT Corporation, Defendant-Intervenor, No. 06-682C, October 11,
2006)
Given the ability and willingness of the incumbent
contractor to continue to
perform M&M services for Illinois and Indiana under its existing contract, which
has
been extended through December 13, 2004, together with any added services which
HUD deems necessary for the launch of the Chicago Homeownership Rehabilitation
Program, it is concluded that the HUD override determination of August 31, 2004,
lacks a rational basis on the record submitted as supplemented. The situations
cited
do not present urgent and compelling circumstances in that all of the required
services
can efficiently be obtained without performance of the new contract during the
GAO
protest period. The record also lacks the objective analysis required to support
a
determination that performance of the new contract is in the best interests of
the United
States. HUD’s override determination is based almost entirely on the performance
of
a limited aspect of the contract in a limited portion of the contract area, and
no relevant
or substantial adverse financial or administrative impact has been established
from
continuation of a stay during the GAO protest period. (Chapman
Law Firm Co., v. U. S., No. 04-1418c, October 13, 2004 (pdf)
Contrary to a case
in which conclusions of the agency are “rational and supported by the record,”
Sierra Military Healthcare Servs., Inc. v. United States, 58 Fed. Cl. 573, 581
(2003), the purported basis to justify the override decision was not mentioned
at all in the May 28, 2004, override memorandum approved by the Deputy Assistant
Secretary. There is only one mention in the documents supporting the override
decision that reflects a concern with plaintiff’s legal capacity to perform. A
May 26, 2004, memorandum by Brigadier General Green includes the statement that
the “current purchase order arrangement with three different contractors expires
on May 31, 2004 with no legal extension available.”10 The memorandum provides no
support for that assertion. Further, the memorandum goes on to imply in error
that maintaining the status quo would involve a five-month delay. These facts
alone indicate that the agency has “offered an explanation for its decision that
runs counter to the evidence before the agency . . . .” Motor Vehicle Mfrs., 463
U.S. at 43. On the basis of the record before the court and the arguments made
at the June 4, 2004, hearing, the court determines that the VA’s decision to
override the automatic stay is unsupported by the evidence, without rational
basis and, therefore, cannot be sustained. Accordingly, the status quo as of May
31, 2004, must be maintained. (Altos Federal
Group, Inc., v. U. S. and Intelistaf Healthcare, Inc., No. 04-936C, June 10,
2004) (pdf)
The Court ORDERS that the December 24, 2002 cancellation of IFB No.
DACW21-02-B-0005 is hereby SET ASIDE. Defendant, the Army Corps of Engineers,
its officers, agents, servants, employees, and representatives, and all persons
acting in concert and participating with them on IFB No. DACW21-02-B-0005 are
hereby PERMANENTLY ENJOINED from proceeding with performance of the contract
with any entity other than GLDD provided that the Corps finds GLDD to be a
responsible contractor. Each party shall bear its own costs. (Great
Lakes Dredge & Dock Company v. U. S., No 03-1891C, April 13, 2004, Reissued
April 20, 2004) (pdf)
Balancing the hardships between the government and WPS on the one hand and PGBA
on the other, the Court determines that adequate justification does not exist to
set aside the contract and require a new round of solicitation. This procurement
has already lasted nearly one and one half years, from the issuance of the RFP
in September 2002 to the anticipated work commencement date of April 1, 2004,
and WPS avers that it has expended significant resources preparing for
implementation. Interv.-Def.’s Opp. at 63; Interv.-Def.’s Reply at 24. Revoking
the contract and requiring a new solicitation would likely engender an
additional delay of at least the same length. In light of these considerations,
the Court determines that the balance of 30 hardships weighs in favor of denying
PGBA’s request for declaratory relief. In a bid protest case, 28 U.S.C. §
1491(b)(2) provides that “[t]o afford relief in such an action, the court[] may
award any relief that the court considers proper, including declaratory and
injunctive relief except that any monetary relief shall be limited to bid
preparation and proposal costs.” In the circumstances of this case, the Court
has determined that PGBA is entitled to recover its reasonable costs incurred in
preparing its proposal for the TDEFIC solicitation. “[A]losing competitor may
recover the costs of preparing its unsuccessful proposal if it can establish
that the Government’s consideration of the proposal submitted was arbitrary or
capricious or in violation of applicable statute or regulation.” Gentex Corp.,
58 Fed. Cl. at 656 (citing CSE Constr. Co. v. United States, 58 Fed. Cl. 230,
262- 3 (2003); 28 U.S.C. § 1491(b)(2)). In light of the errors discussed above
and because PGBA was prejudiced by such errors, PGBA may recover its bid
preparation and proposal costs. The amount of such recovery shall be determined
through further proceedings in this action. (PGBA,
LLC,v. U. S. (Defendant) and Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-2773C, March 31, 2004, Reissued April 22,
2004.) (pdf)
Absent a valid override decision the stay mandated by 31 U.S.C. § 3553(d)
remains in effect. However, the fact that the stay has remained in effect does
not, itself, create an urgent and compelling circumstance which would now
support an immediate, fresh override decision by the BOP. As purchase orders can
be used to meet the continuing BOP needs, an award of such an order to Dismas or
Keeton to meet BOP needs during the protest period could be used even if its
performance of the contract under protest remained stayed. Keeton has no
existing contractual right to perform the service and is not entitled to an
automatic extension of purchase orders. If purchase orders are continued to be
used during the stay period once a second facility in Memphis was available, the
BOP would be under an obligation to seek competition for each purchase order.
See 13 C.F.R. § 13.104. The BOP may also limit the number of sources from which
it solicits bids if the agency’s need for these services has an unusual and
compelling urgency. See 13 C.F.R. § 6.302-2. However, the agency is not limited
to entering into purchase orders only with Keeton during the stay period. See
Bannum v. United States, 56 Fed. Cl. 453, 456 (2003) (“That limitation is for
the benefit of the procuring agency and offers no support for directing an
extension of plaintiff’s contract by purchase order at the behest of the
contractor.”). While the agency has not shown any valid urgent and compelling
circumstances which would support overriding the automatic CICA stay, the
rationale for limiting its consideration for purchase orders to either Keeton or
Dismas during the stay period is based on the fact that these are the only two
available facilities. The agency is faced with the unusual circumstance where an
incumbent’s contract has expired yet the agency cannot proceed with the new
contract because of the stay. (Keeton
Corrections, Inc. v. U. S. and Dismas Charities, Inc. (No. 04-132C, March
17, 2004) (pdf)
What remains of the Director’s rationale for his override decision is his claim
that the new contracts will provide better and more efficient services to
TRICARE beneficiaries. Plaintiff does not contest this finding. Nonetheless,
without more, the court does not believe that the mere fact that the new
contracts would be better than the old is enough to support the override
decision under either prong of section 3553. Certainly, given the possibility of
either extending the existing contracts or shortening the period for the
transition into the new contracts, the desire to receive sooner, rather than
later, such contract benefits does not constitute “urgent and compelling
circumstances that significantly affect interests of the United States [and
that] will not permit waiting for the decision of the Comptroller General
concerning the protest.” Nor, without more, does the court believe that this
sort of benefit is what Congress had in mind in allowing an override in the
“best interests of the United States.” In deed, were the fact that a new
contract is better than the old sufficient for this purpose, little would be
left of Congress’ efforts in CICA to strengthen the stay provisions and, with
that, promote the integrity of the GAO review process. In this regard, the court
notes that the statute does not allow the agency to override the stay when it is
in the bests interests of that agency or the agency’s contracting officials.
Rather, the best interests of the “United States” must be involved and those
interests necessarily include weighing the benefits Congress obviously felt were
furthered by bolstering the bid protest process and, in turn, promoting
competition in contracting. In the instant case, the public’s interest
likewise lies in preserving the integrity of the competitive process – such,
indeed, clearly was Congress’ view in providing that, except in circumstances
not yet demonstrated here, the automatic stay should prevail. In so holding, the
court is mindful of the benefits that the new contracts might offer to TRICARE
beneficiaries. But, those same beneficiaries, as well as the public at large,
also have a long-term interest in ensuring that the new contract represents the
best overall value to the government. Given the fact that there is no real
indication that reinstituting the stay will impair services to a significant
extent, the court believes that these long-term interests are paramount here and
are best served by issuing the proposed injunction. See Metcalf Constr. Co. v.
United States, 53 Fed. Cl. 617, 645 (2002); DTH Management Group v. Kelso, 844
F. Supp. 251, 255 (E.D.N.C. 1993). (PGBA,
LLC,v. U. S. (Defendant) and Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-1986C, September 15, 2003, Reissued
September 29, 2003)
To gain injunctive relief, plaintiff must establish: 1) that it has achieved
actual success on the merits, 2) that it will suffer irreparable injury if
injunctive relief were not granted, 3) that the harm to plaintiff outweighs the
harm to the Government and third parties if the injunction were not granted, and
4) that granting the injunction serves the public interest. FMC Corp. v.
United States, 3 F.3d 424, 427 (Fed. Cir. 1993). No one factor is dispositive in
the court’s analysis. Id. Defendant at argument was unable to answer the
court’s queries regarding the specific impact of a 30-day delay on national
security issues. See Tr. at 49-50. However, plaintiff was also unable to provide
an explanation as to how such a delay would not impact national security,
stating instead that it “assumed” that a resolicitation could occur
“expeditiously and effectively, without any disruption to the services” required
by the Corps. Id. at 23. In light of the parties’ inability to provide the court
with specific information regarding the impact of delay, the court must defer to
the claim that national security concerns counsel against a grant of injunctive
relief. Thus, the court finds that the grant of a permanent injunction
would not be in the public interest. When considered in light of the asserted
possibility that a reprocurement would disrupt the Corps’s ability to provide
the facilities covered by the instant contract, the court must deny plaintiff’s
motion for a permanent injunction. (Al
Ghanim Combined Group Co. Gen. Trad. & Cont. W.L.L., v. U.S., No. 03-271C,
May 22, 2003) (pdf)
The court must "give due regard to the interests of national defense and
national security" when considering bid protests. 28 U.S.C. § 1491 (b)(3). There
is no specific irreparable injury to SDS, and any harm to SDS is outweighed by
the harm that will be suffered by the United States. (SDS
International, Inc., v. U. S. and CDB Training, Inc., No. 03-214C, February
6, 2003) |