The
Bona Fide Needs Rule |
B. 8. Multi-Year Contracts
a. Introduction
Page 5-37
Page 5-38
Page 5-39 |
Any discussion of multiyear contracting must inevitably combine the
bona
fide needs rule with material from Chapter 6 on the Antideficiency
Act and
from Chapter 7 on obligations.
The term “multiyear contract” has been used in a variety of
situations to
describe a variety of contracts touching more than one fiscal year.
To
prevent confusion, we think it is important to start by establishing
a
working definition. A multiyear contract, as we use the term in this
discussion, is a contract covering the requirements, or needs, of
more than
one fiscal year.22 A contract for the needs of the current year,
even though
performance may extend over several years, is not a multiyear
contract. We
discuss contracts such as these, where performance may extend beyond
the
end of the fiscal year, in sections B.4 and
B.5 of this chapter.
Thus, a
contract to construct a ship that will take 3 years to complete is
not a
multiyear contract; a contract to construct one ship a year for the
next
3 years is.
Multiyear contracting, like most things in life, has
advantages and
disadvantages. Some of the potential benefits are:23
-
Multiyear contracting can reduce costs by permitting the
contractor to
amortize nonrecurring “start up” costs over the life of the
contract.
Without multiyear authority, the contractor may insist on recovering
these costs under the 1-year contract (since there is no guarantee
of
getting future contracts), thus resulting in increased unit prices.
-
Multiyear contracting may enhance quality by reducing the
uncertainty
of continued government business and enabling the contractor to
maintain a stable workforce.
-
Multiyear contracting may increase
competition by enabling small businesses to compete in situations
where nonrecurring start-up costs would otherwise limit
competition to larger concerns.
However, the situation is not
one-sided. Multiyear contracting authority also has potential
disadvantages:24
-
Competition may decrease because there will be fewer opportunities
to
bid.
-
A contractor who is able to amortize start-up costs in a multiyear
contract has, in effect, a government-funded competitive price
advantage over new contractors in subsequent solicitations. This
could
evolve into a sole-source posture.
-
Being locked into a contract for several years is not always
desirable,
particularly where the alternative is to incur cancellation charges
that
could offset initial savings.
An agency may engage in multiyear
contracting only if it has (1) no-year
funds or multiple year funds covering the entire term of the
contract or
(2) specific statutory authority. Cray Research, Inc. v. United
States,
44 Fed. Cl. 327, 332 (1999);
67 Comp. Gen. 190, 192 (1988);
B-171277, Apr. 2,
1971 (multiyear contract permissible under no-year trust fund). An
agency
may enter into a multiyear contract with fiscal year appropriations
(or for a
term exceeding the period of availability of a multiple year
appropriation)
only if it has specific statutory authority to do so. See 71 Comp.
Gen. 428,
430 (1992); B-259274, May 22, 1996. Most agencies now have some form
of
multiyear contracting authority, as we will describe in the next
section.
|
b. Multiple Year and No-Year
Appropriations Page
5-39 (As of 3/12/15)
Page 5-40
Page 5-41 |
If an agency does not have specific
multiyear contracting authority but enters into a multiyear contract
solely under authority of a multiple year or no-year appropriation,
the full contract amount must be obligated at the time of contract
award. See, e.g.,
B-322160, Oct. 2, 2011;
B-195260, July 11,
1979. This is also true for revolving funds,
which authorize expenditures without fiscal year limitation.
Revolving funds must have sufficient budget authority against which
to record the entire amount of long-term contracts at the time of
the obligation. 72 Comp. Gen. 59, 61 (1992). A revolving fund may
not count anticipated receipts from future customer orders as budget
authority.
B-288142, Sept. 6, 2001. See also U.S. General Accounting
Office, The Air Force Has Incurred Numerous Overobligations In Its Industrial Fund,
AFMD-81-53 (Washington, D.C.: Aug. 14, 1981).
However, there have been some circumstances under which GAO approved
the incremental funding of a multiyear contract using no-year funds.
For
example, 43 Comp. Gen. 657 (1964) involved a scheme in which funds
would be made available, and obligated, on a year-by-year basis,
together
with a “commitment” to cover maximum cancellation costs. The
cancellation costs represented amortized start-up costs, which would
be
adjusted downward each year. Thus, funds would be available to cover
the
government’s maximum potential liability in each year. See also
62
Comp.
Gen. 143 (1983) (similar approach for long-term vessel charters
under the
Navy Industrial Fund);
51 Comp. Gen. 598, 604 (1972) (same);
48
Comp.
Gen. 497, 502 (1969) (either obligational approach acceptable
under revolving fund).26
(As we will see later, this type of
arrangement under a
fiscal year appropriation presents problems.)
If an agency has neither multiple year or no-year funds, nor uses
multiyear
contracting authority, a multiyear contract violates statutory
funding
restrictions, including the Antideficiency Act (prohibiting
obligations in
advance of an appropriation for that fiscal year, 31 U.S.C. §
1341(a))27 and
the bona fide needs statute (prohibiting the obligation of an
appropriation
in advance of need, 31 U.S.C. § 1502(a)). See Cray Research, Inc. v.
United
States, 44 Fed. Cl. 327,332 (1999). E.g., 67 Comp. Gen. 190 (1988);
66 Comp.
Gen. 556 (1987);
64 Comp. Gen. 359 (1985);
48 Comp. Gen. 497 (1969);
42 Comp. Gen. 272 (1962); 27 Op. Att’y Gen. 584 (1909). Multiyear
commitments were found illegal in various contexts in each of these
cases,
although each case does not necessarily discuss each funding
statute.
In 42 Comp. Gen. 272, for example, the Air Force, using fiscal year
appropriations, awarded a 3-year contract for aircraft maintenance,
troop
billeting, and base management services on Wake Island. Because an
agency typically incurs an obligation at the time it enters into a
contract,
and must charge that obligation to an appropriation current at that
time,28 the Air Force contract raised two issues: (1) whether the services
to be
provided in the second and third years of the contract constituted a
bona
fide need of the Air Force’s fiscal year appropriation, and (2) if
not,
whether the Air Force had incurred an obligation in the first fiscal
year for
the needs of the second and third years in advance of appropriations
for
those 2 years. The Air Force contended that no funds were obligated
at
time of contract award; instead, the Air Force argued that it had a
“requirements” contract, and that it incurred no obligation unless
and until
it issued requisitions, thereby exempting the contract from the
statutory
funding restrictions. However, the Comptroller General refused to
adopt
this characterization of the contract. Although the contractor had
expressly
agreed to perform only services for which he had received the
contracting
officer’s order, GAO found that there was no need for an
administrative
determination that requirements existed since the contract services
were
“automatic incidents of the use of the air field.” Id. at 277. Only
a decision to close the base would eliminate the requirements.
Consequently, the
contract was found to be an unauthorized multiyear contract—the Air
Force, using fiscal year appropriations, had entered into a contract
for its
needs of subsequent fiscal years in advance of appropriations for
those
years.
|
c. Fiscal Year Appropriations
Page 5-41
(As of 3/12/15)
Page 5-42
Page 5-43
(As of 3/12/15) |
If an agency is contracting with fiscal year
appropriations and does not have multiyear contracting authority,
one course of action, apart from a series of separate fiscal year
contracts, is a fiscal year contract with renewal options, with each
renewal option (1) contingent on the availability of future
appropriations and (2) to be exercised only by affirmative action on
the part of the government (as opposed to automatic renewal unless
the government refuses). Leiter v. United States, 271 U.S. 204
(1926);
66 Comp. Gen. 556 (1987);
36 Comp. Gen. 683 (1957); 33 Comp.
Gen. 90 (1953);
29 Comp. Gen. 91 (1949);
28 Comp. Gen. 553 (1949);
B-88974, Nov. 10, 1949. The inclusion of a renewal option is
key; with a renewal option, the government incurs a financial
obligation only for the fiscal year, and incurs no financial
obligation for subsequent years unless and until it exercises its
right to renew. The government records the amount of its obligation
for the first fiscal year against the appropriation current at the
time it awards the contract. The government also records amounts of
obligations for future fiscal years against appropriations current
at the time it exercises its renewal options. The mere inclusion of
a contract provision conditioning the government’s obligation on
future appropriations without also subjecting the multiyear contract
to the government’s renewal option each year would be insufficient.
Cray Research, Inc. v. United States, 44 Fed. Cl. 327, 332 (1999).
Thus, in
42 Comp. Gen. 272 (1962), the Comptroller General, while
advising the Air Force that under the circumstances it could
complete that particular contract, also advised that the proper
course of action would be either to use an annual contract with
renewal options or to obtain specific multiyear authority from
Congress. 42 Comp. Gen at 278.
In a 1-year contract with renewal options, the contractor can never
be sure
whether the renewal options will be exercised, thereby preventing
the
contractor from amortizing initial investment costs. To protect
against this
possibility, contractors occasionally seek a contract termination
penalty
equal to the unamortized balance of initial investment costs if the
government fails to renew the contract for any fiscal year. However,
the
Comptroller General has held that these provisions contravene the
bona
fide needs rule:
“The theory behind such obligations (covering
amortized
facility costs unrecovered at time of termination) has been
that a need existed during the fiscal year the contracts were
made for the productive plant capacity represented by the
new facilities which were to be built by the contractor to
enable him to furnish the supplies called for by the
contracts. After thorough consideration of the matter, we
believe that such obligations cannot be justified on the
theory of a present need for productive capacity.
“ …The real effect of the termination liability is to obligate
the Commission to purchase a certain quantity of
magnesium during each of five successive years or to pay
damages for its failure to do so. In other words, the
termination charges represent a part of the price of future,
as distinguished from current, deliveries and needs under
the contract, and for that reason such charges are not based
on a current fiscal year need.”
36 Comp. Gen. 683, 685 (1957). See also
37 Comp. Gen. 155 (1957).
Attempts to impose penalty charges for early termination (sometimes
called “separate charges”) have occurred in a number of cases
involving
automated data processing (ADP) procurements. In one case, a
competitor
for a contract to acquire use of an ADP system for a 65-month period
proposed to include a provision under which the government would be
assessed a penalty if it failed to exercise its annual renewal
options. The
Comptroller General noted that the penalty was clearly intended to
recapitalize the contractor for its investment based on the full
life of the
system in the event the government did not continue using the
equipment.
Accordingly, the Comptroller General concluded that the penalty did
not
reasonably relate to the value of the equipment’s use during the
fiscal year
in which it would be levied. The penalty charges would, therefore,
not be
based on a bona fide need of the current fiscal year and their
payment
would violate statutory funding restrictions.
56 Comp. Gen. 142
(1976), aff’d in part,
56 Comp. Gen. 505 (1977).
See also 56 Comp. Gen. 167
(1976);
B-190659, Oct. 23, 1978.
One scheme, however, has been found to be legally sufficient to
permit the
government to realize the cost savings that may accrue through
multiyear
contracting. The plan approved by the Comptroller General in
48
Comp.
Gen. 497, 501–02 (1969) provided for a 1-year rental contract with
an option to renew each subsequent year. If the government completed
the full rental
period by continuing the contract on a year-by-year basis, it would
be
entitled to have monthly rental credits applied during the final
months of
the rental period. The Comptroller General noted that:
“Under this arrangement the Government would not be
obligated to continue the rental beyond the fiscal year in
which made, or beyond any succeeding fiscal year, unless or
until a purchase order is issued expressly continuing such
rental during the following fiscal year. In effect, the
company is proposing a 1 year rental contract with option to
renew. Also, under this proposal rental for any contract year
would not exceed the lowest rental otherwise obtainable
from [the contractor] for one fiscal year. We have no legal
objection to this type of rental plan for ADP equipment.”
Another course of action for an agency with
fiscal year money to cover possible needs beyond that fiscal year is
an indefinite- delivery/indefinite-quantity (IDIQ) contract. An IDIQ
contract is a form of an indefinite-quantity contract, which
provides for an indefinite quantity of supplies or services, within
stated limits, during a fixed period. 48 C.F.R. § 16.504(a). Under
an IDIQ contract, actual quantities and delivery dates remain
undefined until the agency places a task or delivery order under the
contract. When an agency executes an indefinite-quantity contract
such as an IDIQ contract, the agency must record an obligation in
the amount of the guaranteed minimum purchase. At the time of award,
the government commits itself to purchase only a minimum amount of
supplies or services and has a fixed liability for the amount to
which it committed itself. See 48 C.F.R. §§ 16.501-2(b)(3) and
16.504(a)(1). The agency has no liability beyond its minimum
commitment unless and until it places additional orders. An agency
is required to record an obligation at the time it incurs a legal
liability.
65 Comp. Gen. 4, 6
(1985);
B-242974.6,
Nov. 26, 1991. Therefore,
for an IDIQ contract, an agency must record an obligation for the
guaranteed minimum amount at the time of contract execution.
See, e.g.,
B-318046, July 7, 2009
(in the
absence of reliable historical usage data, an agency may use $500 as
the guaranteed minimum for IDIQ contracts, which amount must be
obligated at the time of award).
In
B-302358, Dec. 27, 2004, GAO determined that the Bureau
of Customs and Border Protection’s (Customs) Automated Commercial
Environment contract was an IDIQ contract. As such, Customs incurred
a legal liability of $25 million for its minimum contractual
commitment at the time of contract award. However, Customs failed to
record its $25 million obligation
until 5 months after contract award. GAO determined that to be
consistent with the recording statute, 31 U.S.C. § 1501(a)(1),
Customs should have recorded an obligation for the contract minimum
of $25 million against a currently available appropriation for the
authorized purpose at the time the IDIQ contract was awarded.
In establishing the guaranteed minimum
quantity in an IDIQ contract, an agency must consider both
contracting and appropriations law principles. The guaranteed
minimum must not only constitute sufficient consideration to make
the contract binding, but also reflect the
bona fide
needs of the agency at the time of execution of the contract.
B-321640, Sept. 19, 2011, at 6.
|
d. Contracts with No Financial
Obligation Page 5-43
Page 5-44 |
Multiyear arrangements may be permissible, even without specific
statutory authority, if they are structured in such a way that the
agency, at
time of contract award, incurs no financial obligation. Without a
financial
obligation, the agency does not violate the Antideficiency Act or
the bona
fide needs rule. In
63 Comp. Gen. 129 (1983), the Comptroller
General
considered the General Services Administration proposal to use
3-year
“Multiple Award Schedule” (MAS) contracts for Federal Supply
Schedule
items. There was no commitment to order any specific quantity of
items.
Rather, the commitment was for an agency with a requirement for a
scheduled item to order it from the contractor if the contractor has
offered
the lowest price. If an agency found the item elsewhere for less
than the
contract price, it was free to procure the item from that other
source
without violating the contract. Since entering into the MAS
contracts did
not require the obligation of funds, there was no violation of
statutory
funding restrictions. Obligations would occur only when agencies
placed
specific orders, presumably using funds currently available to them
at the
time. Another example is a 1935 decision, A-60589, July 12, 1935,
which
concerned a requirements contract for supplies in which no definite
quantity was required to be purchased and under which no financial
obligation would be imposed on the government until an order was
placed.
In order to retain the availability of the vendor and a fixed price,
the
government agreed not to purchase the items elsewhere. See also
B-259274,
May 22, 1996.
Also, contracts that do not require the expenditure of appropriated
funds
are not subject to the same fiscal year strictures. E.g., 10 Comp.
Gen. 407(1931) (no legal objection to multiyear leases or contracts
for the operation
of concessions on federal property). |
Footnotes |
22 This is essentially the same as the
definition in the Federal Acquisition Regulation, “a
contract for the purchase of supplies or services for more than 1,
but not more than 5,
program years.” 48 C.F.R. § 17.103. (BACK)
23 S. Rep. No. 98-417, at 4–8 (1984). This is a report by the Senate
Committee on
Governmental Affairs on a bill (S. 2300) designed to extend limited
multiyear contracting
authority to civilian agencies. That legislation was not enacted.
Ten years later, in 1994,
Congress enacted the Federal Acquisition Streamlining Act,
permitting civilian agencies to
use fiscal year appropriations to enter into contracts for as many
as 5 years. Pub. L. No. 103-
355, § 1072, 108 Stat. 3243, 3270 (Oct. 13, 1994), codified at 41 U.S.C.
§ 254c. We discuss the Federal Acquisition Streamlining Act in
section B.9.b of this chapter. (BACK)
24 H.R.
Rep. No. 97-71, pt. 3, at 21 (1981) (report of the House Committee
on Government Operations on the 1982 Defense Department
authorization bill). (BACK)
25 [When
an agency uses multiyear or other contracting authorities, such as
the Federal Acquisition Streamlining Act, that authority may permit
the agency to obligate its appropriations differently. We discuss
the Federal Acquisition Streamlining Act and other examples of
multiyear contracting authorities in section B.9 of this chapter.]
(Note: In the 3/13/14
revision, this footnote was omitted in the text but there was no
clear mention about the footnote. I am placing it in brackets
because I don't know what GAO's intent is.)
(BACK)
26 While
43 Comp. Gen. 657 had used the somewhat cryptic term “commitment,”
the three subsequent decisions require the actual obligation of the
cancellation costs. (BACK)
27 We discuss the Antideficiency
Act in Chapter 6. (BACK)
28 We
discuss the concept of obligations in Chapter 7. (BACK) |
|
|