New
The protester contends that the agency engaged in unfair
and misleading discussions. In this regard, CACI argues
that it was directed to provide only limited revisions to
its proposal, while discussions with Digital Management
“more broadly invited proposal revisions.” Comments at 2.
In support of this argument, the protester asserts that
the only area of its proposal where it was directed to
provide anything beyond “confirmation” or “clarification”
related to a request from the agency to provide additional
price discounts for option years 3 and 4. Id. at 1. The
protester contends that the awardee, by contrast, was
invited to provide broader revisions to its proposal,
including a rationale for its staffing hours and
substantiation for its discounts across all of its rates.
The protester contends that had it been specifically
advised that it could broadly revise its proposal, it
would have increased its price discounts for the other
contract periods, beyond option years 3 and 4, and thereby
reduced its final price.
With regard to competitions for task and delivery
orders under indefinite-delivery, indefinite-quantity
contracts, Federal Acquisition Regulation § 16.505
does not establish specific requirements for discussions;
instead, exchanges with offerors under task order
competitions, like other aspects of such a procurement,
must be fair, equal, and not misleading. CGI Fed. Inc.,
B-403570 et al., Nov. 5, 2010, 2011 CPD ¶ 32 at 9. In
general, when an agency opens or reopens discussions with
offerors, the offerors may revise any aspect of their
proposals, including portions of their proposals which
were not the subject of discussions. Imagine One Tech. &
Mgmt., Ltd., B-412860.4, B-412860.5, Dec. 9, 2016, 2016
CPD ¶ 360 at 22. In appropriate circumstances, however,
agencies may limit the revisions that offerors may make to
their proposals following discussions. Id.
Based on our review of the evaluation record, we conclude
that the agency did not engage in unfair or misleading
discussions. In this regard, we note that the record does
not support the protester’s assertion that the agency
limited the scope of CACI’s final proposal revisions to
those proposal areas expressly addressed during
discussions. Although the protester broadly avers that
this was the case, the agency’s contemporaneous notes of
the discussions meeting do not reflect any such
instruction being provided. See generally AR, Tab 8,
Discussion Minutes. Nor does the protester provide any
support for its assertion that a limitation instruction
was given.
To the extent CACI inferred such a limitation based on the
narrow areas raised during discussions, we find that this
was not a reasonable inference to draw. The general rule,
cited above, that offerors may revise any aspect of their
proposals during discussions, applies even when an agency
does not expressly advise offerors of this right and
instead instructs them to answer specific questions about
their proposals. See, e.g., Medical Receivables Solution,
B-409358, Mar. 19, 2014, 2014 CPD ¶ 99 at 3. Moreover, we
note that the protester could have sought clarification on
this point with the agency during its discussions meeting.
In sum, we find no merit to the protester’s contention
that it was reasonably unaware of its right to broadly
revise its price proposal.
Additionally, based on our review of the record, we find
that the agency’s discussions with offerors were not
unfair or unequal. While discussions may not be conducted
in a manner that favors one offeror over another, they
need not be identical among offerors; rather, discussions
are to be tailored to each offeror’s proposal. Joint
Logistics Managers, Inc., B-410465.2, B-410465.3, May 5,
2015, 2015 CPD ¶ 152 at 4. Here, the agency tailored its
discussions to each offeror’s proposal and reasonably led
both CACI and Digital Management to the areas of their
proposals that required amplification or revision. Indeed,
the final proposal of each offeror received the highest
possible ratings for the two non-price factors. (CACI,
Inc.-Federal B-416549: Sep 13, 2018)
GDIT challenges the agency’s source selection decision on
the basis that the agency failed to conduct meaningful
discussions, asserting that this constituted a defect that
“tainted the entire competition.” Protest at 2.
Specifically, GDIT asserts that the agency’s discussions
following its evaluation of the initial cost/price
proposals were less than meaningful because the
discussions did not address the cost/price reasonableness
of task order No. 1. In asserting that the agency failed
to conduct meaningful discussions, GDIT has made three
specific assertions.
First, GDIT asserts that the agency’s determination that
GDIT’s initial cost/price proposal was “incomplete” should
not have precluded the agency from making a cost/price
reasonableness assessment. Specifically, GDIT asserts
that, “[e]ven assuming . . . that there were impediments
to conducting the Completeness evaluation before the close
of discussions, there were no similar impediments to
conducting the [cost/price] Reasonableness evaluation.”
Protest at 19.
Second, GDIT asserts that, because the agency made a
competitive range determination following its evaluation
of initial proposals, it was required to make a cost/price
reasonableness determination. Id. More specifically, GDIT
maintains that the agency “was obligated to conduct a
price reasonableness analysis before establishing its
competitive range.” Id.
Third, relying on this Office’s recent decision in
Veterans Evaluation Services, Inc., et al., B‑412940 et
al., July 13, 2016, 2016 CPD ¶ 185, GDIT notes that, where
an agency identifies an issue after the close of
discussions that “should have been identified prior to the
close of discussions,” the agency is required to reopen
discussions. Id. at 2-3. In this context, GDIT asserts
that, here, the agency “belatedly” determined that GDIT’s
proposed cost/price for task order No. 1 was unreasonably
high and, accordingly, the agency was “required” to reopen
discussions with GDIT. Id. at 21.
The agency responds that it was unable to make any
reliable determination regarding the cost/price
reasonableness of GDIT’s initial proposal due to the
multiple defects and omissions in that proposal. The
agency further responds that during the discussions it
conducted with GDIT following submission of initial
proposals, the agency provided multiple IFDs to GDIT that
reasonably directed GDIT’s attention to the various
defects and omissions in its proposal. Finally, the agency
responds that it was not until submission of FPRs that
GDIT provided sufficient information responding to the
RFP’s stated requirements that the agency was able to make
a reliable cost/price reasonableness determination.
Accordingly, the agency maintains that it did, in fact,
conduct meaningful discussions with GDIT.
When an agency engages in discussions with an offeror, the
discussions must be “meaningful,” that is, they must lead
an offeror into the areas of its proposal that requires
amplification or revision. Hanford Envtl. Health Found.,
B-292858.2, B‑292858.5, Apr. 7, 2004, 2004 CPD ¶ 164 at 8.
Although an agency’s discussions must address proposal
deficiencies and significant weaknesses that are
identified, or are reasonably identifiable, see Federal
Acquisition Regulation (FAR) § 15.306(d)(3), where
proposal defects are first introduced in a response to
discussions, there is no requirement for an agency to
reopen discussions. See, e.g., L-3 Comms. Corp., BT Fuze
Prods. Div., B-299227, B‑299227.2, Mar. 14, 2007, 2007 CPD
¶ 83 at 19; Cube‑All Star Servs. Joint Venture, B-291903,
Apr. 30, 2003, 2003 CPD ¶ 145 at 10-11.
Here, our review of the record supports the agency’s
assertion that, during the discussions following GDIT’s
submission of its initial cost/price proposal, the agency
reasonably directed GDIT’s attention to the multiple
aspects of its proposal that failed to comply with the
solicitation requirements. See AR, Tab E.1.a, GDIT IFDs.
Further, we reject GDIT’s assertion that the agency was
required to make a cost/price reasonableness determination
on the basis of GDIT’s incomplete initial cost/price
proposal--and to conduct discussions with GDIT regarding
that allegedly required assessment. As discussed above,
the solicitation specifically provided that proposals
would be evaluated for completeness, warning offerors that
an incomplete proposal would be ineligible for award. RFP
at 180. Further, where, as here, a cost/price proposal is
incomplete, that incompleteness precludes an analysis of
whether the overall proposed cost/price is higher or lower
than other proposals received. See Orion Tech., Inc.,
B-405077, Aug. 12, 2011, 2011 CPD ¶ 159 at 6-7. Finally,
it is well settled that a proposal that fails to comply
with the solicitation requirements cannot form a valid
basis for award. See, e.g., For Your Information, Inc.,
B-278352, Dec. 15, 1997, 97-2 CPD ¶ 164 at 2-3. Consistent
with these principles, we believe that if the agency,
here, had communicated some conclusion regarding the
cost/price reasonableness of GDIT’s initial, incomplete
proposal during the discussions following the agency’s
evaluation of initial proposals, such discussions could
well have been misleading. Accordingly, we reject GDIT’s
assertion that the submission of GDIT’s initial cost/price
proposal created an obligation for the agency to conduct
discussions with GDIT regarding the cost/price
reasonableness of that submission.
We similarly reject GDIT’s assertion that, because the
agency made a competitive range determination, it was
required to have made a cost/price reasonableness
determination regarding GDIT’s initial proposal. Here, it
is clear that the agency complied with the requirement
that an agency may not ignore cost/price in making a
competitive range determination. See FAR § 15.306(c);
Kathpal Techs., Inc.; Computer & Hi-Tech Mgmt., Inc.,
B‑283137.3 et al., Dec. 30, 1999, 2000 CPD ¶ 6 at 9. The
record here also reflects the fact that, after considering
GDIT’s proposed cost/price, the agency reasonably
determined that it was unable to make a reasonable and
reliable determination as to whether GDIT’s cost/price was
reasonable. Accordingly, we reject GDIT’s reliance on the
fact that the agency established a competitive range as a
basis for asserting that discussions were less than
meaningful.
Finally, GDIT’s reliance on Veterans Evaluation Services,
Inc., supra, is misplaced, since the facts here are
materially different from the facts on which that decision
was based. First, in Veterans Evaluation Services, Inc.,
the agency was able to determine that the prices reflected
in the protesters’ initial proposals were “fair and
reasonable,” and the agency communicated that
determination to the protesters during discussions.
Veterans Evaluation Services, Inc, supra, at 19. Following
discussions, the protesters submitted FPRs in which one
protester lowered its price and the other protester left
its price unchanged. Id. at 20. Finally, due solely to the
fact that the competing offerors substantially lowered
their prices in their FPRs, the protesters’ FPR prices
were found unreasonably high, even though the agency had
previously advised the protesters that their prices were
reasonable. Id. On those facts, we concluded that the
agency was required to reopen discussions.
In contrast, here, as discussed above, the agency was
unable to determine the cost/price reasonableness of
GDIT’s initial proposal due to multiple defects and
omissions within GDIT’s proposal. Consistent with the
agency’s determination that it was unable to make a
reliable cost/price reasonableness determination, the
agency declined to potentially mislead GDIT during
discussions and, accordingly, did not advise GDIT that its
cost/price was either reasonable or unreasonable. Finally,
GDIT does not dispute that its price for the task order
No. 1 requirements increased from $92,179,800 to
$96,886,739 between its initial proposal and its FPR. GDIT
Comments, Nov. 27, 2017, at 19. On these facts, we reject
GDIT’s assertion that the holding in Veterans Evaluation
Services, Inc. is applicable here. In summary, we reject
all of the arguments that GDIT timely presented regarding
the agency’s alleged failure to conduct meaningful
discussions. (General
Dynamics Information Technology, Inc. B-415568,
B-415568.2: Jan 25, 2018)
Misleading and Unequal Discussions
The protester asserts that the agency’s discussions were
misleading and unequal. Specifically, AT&T contends that
AT&T’s and CDWG’s proposals were both evaluated to have
potential bias in their multi-carrier approaches, but only
CDWG’s technical exchange addressed potential bias.
Comments and Supp. Protest (.3) at 22.
The regulations concerning discussions under Federal
Acquisition Regulation (FAR) part 15, which pertain to
negotiated procurements, do not, as a general rule, govern
task and delivery order competitions conducted under FAR
part 16, such as the procurement for the task order here.
See NCI Info. Sys., Inc., B-405589, Nov. 23, 2011, 2011
CPD ¶ 269 at 9. In this regard, FAR § 16.505 does not
establish specific requirements for discussions in a task
order competition; nonetheless, when exchanges with the
agency occur in task order competitions, they must be fair
and not misleading. Id. More specifically, an agency may
not mislead an offeror through the framing of a discussion
question into responding in a manner that does not address
the agency’s actual concerns, or otherwise misinform the
offeror concerning a problem with its proposal. Nexant,
Inc., B-407708, B-407708.2, Jan. 30, 2013, 2013 CPD ¶ 59
at 3. When holding discussions, procuring agencies are not
permitted to engage in conduct that favors one offeror
over another. Deloitte Consulting, LLP, B-412125.2,
B-412125.3, Apr. 15, 2016, 2016 CPD ¶ 119 at 17; SRA
Int’l, Inc., B-410973, B-410973.2, Apr. 8, 2015, 2016 CPD
¶ 32 at 7.
Here, the record shows that CDWG’s proposal initially
stated that it had pre-negotiated data plans and fees with
[DELETED], and provided details on service plan changes.
AR, Tab 22, CDWG Initial Proposal, at 22. The agency
evaluated CDWG’s technical approach, and expressed concern
that “CDWG’s pre-negotiated rates with [DELETED]
[presented] a risk that could result in bias during the
cellular carrier analysis,”--that is, the rates could
affect carrier selection. AR, Tab 27, Draft TET Ranking,
at 11. The agency’s technical exchange asked, “[h]ow does
CDWG plan to ensure that its pre-negotiated rates with
cellular carriers are unbiased.” AR, Tab 30, CDWG
Technical Exchange Letter, at 2. In response, CDWG
continued to mention its pre-negotiated data plans with
[DELETED], and heavily revised its response, stating, as
relevant here, “[DELETED].” AR, Tab 33, CDWG Revised
Proposal, at 31-32. The agency evaluated CDWG’s response
and concluded that the response eliminated the technical
risk. AR, Tab 41, TER, Attach. B, at 5.
The record shows that AT&T initially proposed to use
[DELETED] carriers and detailed their approach to
selecting the best carrier for [DELETED]. AR, Tab 21, AT&T
initial Proposal at 29-30. The agency evaluated AT&T’s
technical approach, and noted, “[DELETED].” AR, Tab 27,
Draft TET Evaluation at 30. Unlike the exchange with CDWG,
the agency’s technical exchange with AT&T did not mention
bias, even though the evaluators expressly raised a
concern about bias for both companies. Instead, the agency
asked, “[how] does AT&T plan to include multiple cellular
carriers into their cellular network approach?” Tab 29,
AT&T Technical Exchange Letter, at 2. In response, AT&T
stated that its approach to multi-network carrier
selection would include [DELETED] to determine the
best-value carrier. AR, Tab 32, AT&T Revised Proposal, at
45-47. AT&T’s proposal also stated that it would use
[DELETED] to select the best carrier for each geographic
area, and provided a chart that detailed the selection
process. Id. at 46. As reflected in the source selection
decision, “[DELETED].” AR, Tab 44, SSD, at 7.
Here, the record as a whole demonstrates the impropriety
in the conduct of discussions. To the extent the agency
contends that it was concerned about CDWG’s rates, and
AT&T’s lack of detail--rather than bias--the record does
not support the agency’s contentions. As noted above,
AT&T’s response was found lacking because it did not
address bias in carrier selection. To the extent the
agency was concerned with the potential bias in each
offeror’s approach, and raised bias with CDWG, it was
obligated to similarly raise this concept with AT&T.
Accordingly, the agency’s discussions with CDWG were
misleading and unequal in this respect, and we sustain the
protest. (AT&T Corporation
B-414886, B-414886.2, B-414886.3: Oct 5, 2017)
Following submission of the revised proposals, the agency
evaluated offerors’ proposals as follows:
|
KBR |
Offeror A |
Offeror B |
Centerra |
Overall Technical |
Good |
Acceptable |
Good |
Good |
Corporate Experience |
Outstanding |
Outstanding |
Outstanding |
Outstanding |
Technical Approach/ Management
Approach |
Acceptable |
Marginal |
Acceptable |
Acceptable |
Safety |
Acceptable |
Acceptable |
Acceptable |
Acceptable |
Past Performance |
Substantial Confidence |
Substantial Confidence |
Substantial Confidence |
Substantial Confidence |
Non-Price Ranking |
2 |
3 |
1 |
1 |
Price |
$90,838,446 |
$95,078,039 |
$135,603,472 |
$152,756,038 |
Overall Ranking |
1 |
2 |
3 |
4 |
DISCUSSION
Centerra challenges Navy’s price evaluation and argues
that the agency failed to conduct meaningful discussions.
In this regard, the protester asserts that the large
differences in pricing and staffing between KBR’s and
Centerra’s proposals evidence that the two offerors based
their approaches on differing understandings of the
solicitation requirements. Centerra argues that the agency
failed to evaluate prices on a common basis and erred in
not discussing the disparity with Centerra.
(sentences deleted)
Price Evaluation and
Discussions
The protester asserts that the large pricing and staffing
differences between Centerra’s and KBR’s proposals
demonstrate that offerors did not possess a common
understanding of the solicitation requirements. In this
regard, KBR’s total price was more than 40 percent lower
than Centerra’s. See Tab 20, Addendum to SSAC Report, at
3. KBR also proposed more than [DELETED] percent fewer
full-time equivalents (FTEs) than Centerra during both the
base and option periods. Compare AR, Tab 15, Centerra FPR,
at 133 with AR, Tab 16, KBR FPR, at 109. This disparity
was more stark within certain PWS annexes with Centerra
proposing, for example, [DELETED] FTEs for annex 1503010
custodial services, while KBR proposed only [DELETED]
FTEs. Compare AR, Tab 15, Centerra FPR, at 122 with AR,
Tab 16, KBR FPR, at 123. The protester contends that these
staffing differences “underscore[] that the two offerors
had very different understandings of what number of
personnel was required to perform the requirements.” Supp.
Comments at 3. The protester argues that the agency’s
price evaluation was flawed because the offerors were not
competing based on a common understanding and that,
because of this, the agency was obligated to clarify its
staffing requirements during discussions.
The protester primarily relies on our Office’s decisions
in Baytex Marine Commc’n, Inc., B-237183, Feb. 8, 1990,
90-1 CPD ¶ 164 and US Sprint Commc’ns Co. Ltd. P’ship,
B-243767, Aug. 27, 1991, 91-2 CPD ¶ 201 to assert that the
agency was obligated to “clarify its imprecise
requirements” once it became clear that offerors lacked a
common understanding of the solicitation requirements.
Protest at 14. In those cases, however, the lack of a
common understanding could be traced to unclear or
latently ambiguous requirements found within the
solicitation, which resulted in offerors proposing
differing products or solutions.
Here, Centerra has not identified any PWS requirements
that are ambiguous or unclear, and has therefore not
provided us with a basis to conclude that KBR proposed to
meet different PWS requirements from the requirements
Centerra proposed to meet. Instead, Centerra broadly
asserts that the staffing and pricing differences, by
themselves, evidence that something in the solicitation
caused offerors to possess differing understandings of the
solicitation requirements. Centerra additionally notes
that KBR proposed fractional FTEs throughout its proposal
and relied on [DELETED], but the protester does not
explain how either approach would be inconsistent with the
solicitation requirements. Supp. Comments at 4. Indeed,
the solicitation permitted offerors to propose their own
staffing solutions, so long as they provided the basis for
their staffing estimates and explained how such staffing
would meet the PWS requirements. See RFP at 558. Because
the protester has not specifically traced the offerors’
differing solutions to a differing understanding of the
solicitation requirements, we see no basis to conclude
that the agency was obligated to clarify its requirements.
See The Gerard Co., B-242976, Feb. 27, 1991, 91-1 CPD ¶
240 at 2 (dismissing protest where protester only raised a
general assertion that the solicitation contained a latent
ambiguity without identifying clear evidence that the
awardee interpreted the solicitation differently than the
protester).
We also conclude that the Navy was not otherwise obligated
to tell Centerra that its staffing and pricing were high
in relation to other offerors. When an agency engages in
discussions with an offeror, the discussions must be
meaningful, that is, sufficiently detailed so as to lead
an offeror into the areas of its proposal requiring
amplification or revision. Hanford Envtl. Health Found.,
B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD ¶ 164 at 8.
Weaknesses in an offeror’s proposal relative to the merits
of a competitor’s offer are not for discussion, however,
and it would be improper to disclose to one competitor
another offeror’s innovative approach or solutions to
problems. Bioqual, Inc., B-259732.2, B-259732.3, May 15,
1995, 95-1 CPD ¶ 243 at 5. Further, unless an offeror’s
proposed price is so high as to be unreasonable or
unacceptable, an agency is not required to inform an
offeror during discussions that its proposed price is high
in comparison to a competitor’s proposed price, even where
price is the determinative factor for award. DeTekion Sec.
Sys., Inc., B-298235, B-298235.2, July 31, 2006, 2006 CPD
¶ 130 at 15. Here, since the Navy did not conclude that
Centerra’s price was so high as to be unreasonable or
unacceptable, the agency was not required to discuss
Centerra’s comparatively high price with the firm.
Centerra further asserts that because the Navy found KBR’s
“much lower” staffing level to be acceptable, the agency
was obligated to find Centerra’s 57 percent higher
staffing to be unreasonably high. Supp. Comments at 5. We
do not agree. The record evidences that the agency
reasonably evaluated Centerra’s staffing levels in
relation to the PWS requirements, and that Centerra’s
staffing levels were not considered a deficiency or
weakness in need of revision. See AR, Tab 17, Technical
Evaluation Team (TET) Report, at 19 (“Overall staffing
levels are acceptable to perform the contract.”). Indeed,
Centerra received a strength for one aspect of its
staffing: proposing [DELETED] quality control personnel.
See id. Further, while the protester contends that the
agency should have found Centerra’s staffing levels to be
unreasonably high, the protester does not assert that
Centerra’s high staffing levels presented a technical risk
that the agency should have acknowledged. Instead, the
protester appears to assert that its staffing should have
been found to be unreasonably high solely because it led
to Centerra’s noncompetitive price. As discussed above,
however, the agency was under no obligation to tell
Centerra that its price was comparatively high; we
therefore conclude that the agency similarly was not
obligated to tell Centerra its high staffing was causing
its overall price to be comparatively high.
Centerra also contends that it was misled during
discussions into increasing its staffing because the Navy
told the firm that its staffing may be low for certain
annexes. In this regard, the agency advised Centerra
that its staffing “may be low” for these annexes and asked
Centerra to “[p]lease describe per annex, how you will
perform with your proposed staffing level or
review/validate/revise as appropriate.” AR, Tab 13,
Centerra Discussion Items, at 3. In response to this
notice, Centerra provided further explanation and also
raised its staffing in these categories by approximately
[DELETED] FTEs. AR, Tab 15, at 117-118, 129.
During discussions, agencies may not consciously mislead
or coerce an offeror into raising its prices. Eagle Tech.,
Inc., B-236255, Nov. 16, 1989, 89-2 CPD ¶ 468 at 3-4. We
will not find coercion in discussions, however, where an
agency in good faith provides accurate information to an
offeror about its concern, and provides the offeror with
the opportunity to explain or revise its rates. First
Info. Tech. Servs., Inc., B-405602, Dec. 1, 2011, 2011 CPD
¶ 261 at 10.
Here, we find that the agency’s discussions were not
misleading. The evaluation record demonstrates that the
Navy accurately identified its concern that Centerra’s
staffing was low under certain annexes and asked Centerra
to provide more explanation or revise its proposal. In
response, Centerra provided further explanation and also
increased its FTEs by a small number. We find that this
small increase was not the result of coercion, and instead
reflected Centerra’s business decision to increase its
staffing. Moreover, given the size of the staffing
increase ([DELETED] FTEs), we do not conclude that the
resulting price increase had a prejudicial impact on Centerra’s overall chance at an award.
(Centerra Group, LLC
B-414768, B-414768.2: Sep 11, 2017)
Piton raises various challenges to the agency's conduct of
discussions and its evaluation of price. While our
decision here does not specifically discuss each and every
argument, and/or variation of the arguments, we have
considered all of the protester's assertions and find none
furnishes a basis for sustaining the protest.
We first address Piton's contentions that discussions were
misleading, and not meaningful. In this regard, the
protester essentially argues that it was unreasonable for
the agency to fail to disclose during discussions that it
considered Piton's price to be not fair and reasonable,
and improper for the agency to ultimately conclude that
Piton's price was not fair and reasonable after Piton
reduced its price in response to the agency's discussion
question. Protest at 8; Comments at 5.
When an agency engages in discussions with an offeror, the
discussions must be "meaningful," that is, sufficiently
detailed so as to lead an offeror into the areas of its
proposal requiring amplification or revision in a manner
to materially enhance the offeror's potential for
receiving the award. FAR § 15.306(d); WinStar Fed. Servs.,
B-284617 et al., May 17, 2000, 2000 CPD ¶ 92 at 10. The
requirement that discussions be meaningful, however, does
not obligate an agency to spoon-feed an offeror or to
discuss every area where the proposal could be improved.
FAR § 15.306(d)(3); Cubic Simulation Sys., Inc., B-410006,
B-410006.2, Oct. 8, 2014, 2014 CPD ¶ 299 at 12.
We find no merit to the protester's arguments. The record
shows that the agency clearly led Piton to the area of its
proposal needing revision by indicating that Piton's total
price, as well as its price for a particular labor
category, were high. AR, Tab 13, Agency Discussions with
Piton, at 3. As such, the agency fulfilled its obligation
to conduct meaningful discussions. Additionally, contrary
to the protester's assertions, the record also shows that
the agency only concluded that Piton's price was not fair
and reasonable after evaluating FPRs. AR, Tab 13, Agency
Discussions with Piton, at 1; Tab 27, SSDD, at 10.
Although Piton asserts that it should have received an
award because it lowered its pricing in response to the
discussion question, the record shows that other proposals
from technically-acceptable offerors received awards
because they offered lower prices. In light of the record
here, the protester has not shown that the agency's
conduct of discussions was unreasonable. (Piton
Science and Technology B-414634: Jul 28, 2017)
Global Dynamics contends that the Army repeatedly asked it
during discussions to raise its prices. Protest at 4. The
protester further contends that the agency’s
identification of its prices as being low during
discussions was a directive to raise its prices. Protester
Comments at 3.
In conducting discussions with offerors, an agency may not
consciously mislead or coerce an offeror into raising its
price. Serco Inc., B-407797.3, B-407797.4, Nov. 8, 2013,
2013 CPD ¶ 264 at 5. However, we will not find discussions
to be improper where the agency in good faith provides
accurate information to an offeror, even where the offeror
uses that information to its ultimate competitive
detriment. XtremeConcepts Sys., B‑406804, Aug. 31, 2012,
2012 CPD ¶ 253 at 4; EMR, Inc., B‑406625, July 17, 2012,
2012 CPD ¶ 209 at 4-5.
The record shows that the agency did not ask the protester
to raise its price. As noted above, the discussions letter
merely advised Global Dynamics of the relative standing of
the firm’s proposed evaluated price and specific labor
rates relative to the prices of the proposals received,
and asked that the firm review its prices. AR, Tab 4,
Global Dynamics Discussion Letter, at 5. We see nothing in
the agency’s communications with the protester that could
be construed as directing the protester to take any
particular action, but rather it left to the firm’s
business judgment whether it should raise its prices or
explain the prices earlier submitted. See ITW Military GSE,
B-403866.3, Dec. 7, 2010, 2010 CPD ¶ 282 at 4 (agency
informing offeror that pricing was lower than government
estimate does not compel offeror to take a specific action
or mislead offeror). (Global
Dynamics, LLC B-413313, B-413313.2: Sep 20, 2016)
EDT maintains that there were “significant procurement
administration errors” in the acquisition. Protest at 2.
Specifically, EDT contends that the agency engaged in
improper and misleading discussions. In this connection,
EDT asserts that each of the three response options set
forth in the Corps’ discussion letter “is presented as
equal,” and that the discussion letter “provided no
indication that one type of response is preferred over
another.” Protest at 12. EDT explains that it “took the
discussion letter at face value in submitting its
comments,” and, as a consequence, employed the first
option where “an identified weakness was self-evident
(that is, a detailed narrative response was not necessary
to explain how it would comply with the RFP
requirements).” Id. at 12-13. EDT further argues that the
CO’s comments in the debriefing letter revealed the
agency’s “previously unstated preference for narrative
responses to its discussion questions.” Id. at 14.
According to the protester, it was arbitrary for the
agency to consider narrative responses more favorably than
mere acknowledgments of compliance given that the
discussion letter indicated that both would be acceptable.
As explained below, we find EDT’s argument to be
unpersuasive.
The regulations concerning discussions under Federal
Acquisition Regulation (FAR) part 15, which pertain to
negotiated procurements, do not, as a general rule, govern
task and delivery order competitions conducted under FAR
subpart 16.5, such as the procurement here. NCI Info. Sys.
Inc., B-405589, Nov. 23, 2011, 2011 CPD ¶ 269 at 9. In
this regard, FAR § 16.505 does not establish specific
requirements for discussions in a task order competition;
nonetheless, when exchanges with the agency occur in task
order competitions, they must be fair and not misleading.
CGI Fed. Inc., B-403570 et al., Nov. 5, 2010, 2011 CPD ¶
32 at 9. In our decisions addressing an agency’s
obligations in conducting discussions under FAR part 15,
we have held that an agency may not mislead an offeror
through the framing of a discussion question into
responding in a manner that does not address the agency’s
actual concerns, or otherwise misinform the offeror
concerning a problem with its proposal. Refinery Assocs.
of Texas, Inc., B-410911.2, Mar. 18, 2015, 2015 CPD ¶ 116
at 6. CEdge Software Consultants LLC, B‑408203, July 19,
2013, 2013 CPD ¶ 177 at 7.
The discussion letter here advised EDT that it could
respond in “at least one” of three ways, including an
option that permitted a clarifying narrative response.
Although the protester is correct that the discussion
letter did not indicate that one response was preferred by
the agency over another, the discussion letter also did
not indicate that all permitted response options would be
equally advantageous to an offeror.
EDT appears to have made a business decision to rely on
simple statements of compliance with regard to most of the
weaknesses identified by the agency in discussions. Where
an agency affords an offeror a choice in how to respond to
a weakness identified during discussions, and the offeror
exercises its business judgment in electing one of the
alternatives, the agency has not engaged in misleading
discussions. See Onyx-Technica, JV, B-412474, B-412474.2,
Feb. 26, 2016, 2016 CPD ¶ 65 at 4. In addition, it was not
reasonable for EDT to assume that, because a simple
statement of compliance, without explanatory information,
would be acceptable under the RFP, submission of
associated explanatory information could not improve its
chances of a higher evaluation rating. When an RFP asks
firms to provide a discussion of their technical approach,
the agency evaluation may reasonably consider the level of
detail provided in the requested discussion. TtEC-Tesoro,
JV, B-405313, B‑405313.3, Oct. 7, 2011, 2012 CPD ¶ 2 at 8.
Furthermore, where a firm merely indicates that it will
meet a particular requirement, thereby discussing only the
end results, but provides little or no detail about how it
plans to meet or exceed the requirement, the agency may
reasonably downgrade the proposal. SunGard Data Sys.,
Inc., B-410025, Oct. 10, 2014, 2014 CPD ¶ 304 at 4; Leader
Commc’ns Inc., B-298734, B-298734.2, Dec. 7, 2006, 2006
CPD ¶ 192 at 6. Ultimately, an agency’s evaluation is
dependent upon information furnished in a proposal, and it
is the firm’s burden to submit an adequately written
proposal for the agency to evaluate. Id. A simple
statement of compliance promises but does not demonstrate
compliance. As the agency points out, “[a]n offeror can
say that it intends to comply with the requirements in the
RFP but if it describes how it will comply with the
requirements, the evaluators have more information with
which to judge the quality and likelihood of successful
performance by the offeror.” Memorandum of Law at 2-3. In
sum, we find to be without merit the protester’s argument
that the agency misled it by failing to advise it that
narrative responses to discussion questions might result
in more favorable ratings than simple statements of
compliance.
EDT further argues that the Corps improperly used unstated
evaluation criteria by preferring narrative responses over
straightforward statements of the intent to comply. The
protester also asserts that the agency’s best-value
trade-off was flawed and resulted in an erroneous award
decision. These arguments are based on substantially the
same arguments raised by EDT in its challenge to the
agency’s discussions, which, as indicated above, we found
unpersuasive. We also note that the agency responded to
both arguments in its agency report, and the protester did
not take issue with or seek to rebut the agency response
in its comments on the report; thus, we consider it to
have effectively abandoned these arguments. TPMC-Energy
Solutions Envtl. Servs. 2009, LLC, B-408343.2 et al., Aug.
23, 2013, 2013 CPD ¶ 215 at 8. (Engineering
Design Technologies, Inc. B-413281: Sep 21, 2016)
AAR Airlift Group, Inc., of Palm Bay, Florida, protests the
award of contracts to Erickson Inc., of McMinnville, Oregon,
under request for proposals (RFP) No. N62387-15-R-8008 (‑8008)
and RFP No. N62387-15-R-8009 (‑8009), issued by the Department
of the Navy, Military Sealift Command, for ship-based and/or
shore-based vertical replenishment services.
(* * * * *)
This table shows the results of the
evaluation of proposals under solicitation -8008::
Offeror |
Technical Rating |
Past Performance |
Price |
Erickson |
Acceptable |
Acceptable |
$36,634,581 |
ACHI (submission one) |
Acceptable |
Acceptable |
$55,028,722 |
ACHI (submission two) |
Acceptable |
Acceptable |
$50,152,895 |
AAR |
Acceptable |
Acceptable |
$60,301,046 |
This table shows the results of the
evaluation of proposals under solicitation ‑8009:
Offeror |
Technical Rating |
Past Performance |
Price |
Erickson |
Acceptable |
Acceptable |
$32,550,667 |
ACHI (submission one) |
Acceptable |
Acceptable |
$40,837,235 |
ACHI (submission two) |
Acceptable |
Acceptable |
$50,490,307 |
AAR |
Acceptable |
Acceptable |
$59,383,184 |
(emphasis added)
(* * * * *)
AR, Tab M, Source Selection Decision,
at 5; Protest at 8.
The agency notified the protester on February 12, that it
had made award to Erickson, the lowest‑priced,
technically-acceptable offeror under each solicitation.
The agency provided AAR with a debriefing on February 22.
Protest at 2. This protest followed on February 26.
Discussions
AAR next argues that the agency failed to conduct
meaningful discussions by failing to inform it that its
price was higher than other offerors’ prices and the
independent government estimate (IGE). We disagree and
find no basis to conclude that the agency failed to
conduct meaningful discussions with AAR.
When an agency engages in discussions with an offeror, the
discussions must be “meaningful,” that is, sufficiently
detailed so as to lead an offeror into the areas of its
proposal requiring amplification or revision. Southeastern
Kidney Council, B‑412538, March 17, 2016, 2016 CPD ¶ 90 at
4. Although discussions must address deficiencies and
significant weaknesses identified in proposals, the
precise content of discussions is largely a matter of the
contracting officer’s judgment. FAR § 15.306(d)(3);
Southeastern Kidney Council, supra. Where an
offeror’s price is high in comparison to competitors’
prices or the government estimate, the agency may, but is
not required to, address the matter during discussions.
IAP World Services, Inc. B-297084, November 1, 2005, 2005
CPD ¶ 199 at 4. That is, there is no requirement that an
agency inform an offeror during discussions that its price
may be too high where the offeror’s price is not
considered excessive or unreasonable. Southeastern Kidney
Council, supra. Thus, if an offeror’s price is not so high
as to be unreasonable and unacceptable for contract award,
the agency reasonably may conduct discussions without
advising the offeror that its prices are not competitive.
IAP World Services, Inc., supra. (emphasis added)
Here, there is nothing in the record to indicate that the
agency considered the protester’s price to be excessive or
unreasonable. As such, the agency was under no obligation
to inform AAR that its price was high in comparison to the
prices proposed by ACHI or Erickson. In this regard, the
record indicates that the agency’s price evaluation of
initial proposals included: (1) a comparison of the prices
submitted by all four offerors; (2) a comparison to an
independent government estimate; and (3) a comparison to
historical prices for the services sought by the
solicitation. AR, Tab K, Price Evaluation Report, at 3, 8,
and 10. Based on its findings, the record reflects that
the agency informed AAR, during discussions, that it
considered its prices high in certain areas. Specifically,
the agency advised AAR that its delivery and redelivery
price for heavy lift appeared high in comparison to the
IGE. AR, Tab P, AAR Discussion Items and Responses, at 1.
The agency also informed AAR that its escalation rate from
the base period to option period one for per diem was
unbalanced and appeared high. Id. In response, AAR made
adjustments to its prices proposed in those areas.
Additionally, although the agency did not conclude that
AAR’s total evaluated price was excessive or unreasonable,
it did find that AAR’s overall price was high, and
mentioned during discussions that “this is a competitive
procurement” and that AAR “should provide its best and
final offer.” Id. at 2; AR, Tab K, Price Evaluation
Report, at 3. In response, AAR acknowledged the message,
and confirmed that it was revising its proposed price to
provide its best and final offer. Id. In sum, the record
shows that the agency conducted meaningful discussions,
and went beyond what is required with regard to the
protester’s proposed price. (AAR
Airlift Group, Inc. B-412789.2, B-412790.2: Jun 2,
2016) (pdf)
Crowley alleges that the agency’s
discussions regarding the evaluation of the firm’s proposal
under technical capability subfactor 4, operational support,
were not meaningful. Protest at 16-21. Crowley points out that
the agency documented a significant concern that the firm’s
proposal lacked detail as to how Crowley would be proactive in
identifying performance issues before notification by the
agency. Protest at 19. Crowley then alleges that the agency
improperly failed to raise this issue in discussions. Id. at
16-19. For the reasons discussed below, we agree.
It is a fundamental principle of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions must identify deficiencies and significant
weaknesses in an offeror’s proposal that could reasonably be
addressed so as to materially enhance the offeror’s potential
for receiving award. Sentrillion Corp., B-406843.3 et al., Apr.
22, 2013, 2013 CPD ¶ 207 at 6; Spherix, Inc., B‑294572,
B-294572.2, Dec. 1, 2004, 2005 CPD ¶ 3 at 13; Federal
Acquisition Regulation (FAR) § 15.306(d).
Here, the record reflects that after the initial evaluation of
Crowley’s proposal, the SSEB assessed no strengths, weaknesses,
or deficiencies under subfactor 4, and assigned it a technical
rating of acceptable and a risk rating of moderate under this
subfactor. AR, Tab 60, SSEB Rep., at 14. However, the SSEB also
documented its finding that “[t]he proposal lacked indication
that the Offeror would be proactive in identifying issues prior
to notification by the Government which could cause degradation
in performance throughout the life of the contract.” Id.
As stated above, the evaluation criteria for the technical
capability subfactors included numerous areas. The SSEB finding
quoted above apparently relates to the area of quality
assurance, or, more specifically, the solicitation’s statement
that under subfactor 4, the agency would evaluate the extent to
which an offeror’s quality assurance surveillance plan “reflects
that the contractor, not the government, is responsible for
ensuring performance meets the terms of the contract” and the
extent to which the plan “[e]nsures early identification and
resolution of performance issues to minimize impact on mission
performance.” RFP at 53. As relevant here, other subfactor 4
evaluation areas included staffing and, under the heading
quality control, shipment loss/damage mitigation, claims
processing, and low volume/low frequency sites. Id. at 52.
Following the initial evaluation of Crowley’s proposal, four
evaluation notices (EN) regarding subfactor 4 were issued to the
firm. AR, Tab 60, SSEB Rep., at 317-20, 334-37. These ENs were
identified as pertaining to the areas of shipment loss/damage
mitigation, claims processing, low volume/low frequency sites,
and staffing. Id. Hence, none of the ENs were identified as
pertaining to the early identification and resolution of
performance issues. Additionally, none of the ENs addressed
Crowley’s approach to being proactive in identifying issues
before notification from the agency.
Crowley submitted responses to the ENs, which the SSEB evaluated
as “satisfactory.” See AR, Tab 60, SSEB Rep., at 23. However,
the SSEB also repeated its finding that “[t]he proposal lacked
indication that the Offeror would be proactive in identifying
issues prior to notification by the Government,” and it added
that this issue “could cause degradation in performance
throughout the life of the contract.” Id. No further ENs
regarding subfactor 4 were issued to Crowley.
Following the submission and evaluation of Crowley’s FPR, the
firm’s subfactor 4 technical rating remained acceptable, and its
subfactor 4 risk rating remained moderate. AR, Tab 60, SSEB
Rep., at 30. At this point, the SSEB prepared a comparative
analysis of the proposals in the competitive range. Under
subfactor 4, the SSEB documented the following:
Crowley’s proposed approach is
considered to be the least preferable under this Subfactor as
they received a technical rating of Acceptable along with a
Moderate risk rating. The moderate risk associated with
Crowley’s proposal is due to a lacking indication that the
Offeror would be proactive in identifying issues prior to
notification by the Government which could cause degradation in
performance throughout the life of the contract.
Id. at 36 (emphasis in original).
Thus, the SSEB made clear that the concern regarding whether
Crowley would be proactive in identifying issues before
notification from the agency was the reason for the elevated
risk rating assigned to the firm’s proposal.
As discussed above, the SSA selected GENCO’s higher-rated,
higher-priced proposal for award based essentially on three
factors: Crowley’s past performance rating of unknown
confidence/neutral versus GENCO’s rating of satisfactory
confidence, Crowley’s technical rating of acceptable under
subfactor 4 versus GENCO’s rating of outstanding, and Crowley’s
risk rating of moderate under subfactor 4 versus GENCO’s rating
of low. See AR, Tab 62, SSDD, at 4-7. As also discussed above,
the source selection decision specifically highlighted the
finding underpinning Crowley’s elevated risk rating (i.e., the
concern over whether Crowley would be proactive in identifying
issues before notification from the agency), as well as the
finding that [DELETED]. Id. at 4.
As previously stated, in order to be meaningful, discussions
must identify deficiencies and significant weaknesses in an
offeror’s proposal. Here, the agency did not label its concern
regarding whether Crowley would be proactive in identifying
issues as a significant weakness or deficiency. For the reasons
discussed below, however, we find that the issue represented a
significant weakness.
First, SSEB repeatedly documented its view that the issue “could
cause degradation in performance throughout the life of the
contract.” AR, Tab 60, SSEB Rep., at 14, 23, 36. Second, the SSA
echoed this conclusion in his source selection decision. AR, Tab
62, SSDD, at 4. We have previously concluded that when an agency
finds, as it did here, that the risk associated with a given
aspect of an offeror’s proposal may jeopardize successful
performance of a contract, it represents a significant weakness.
See Raytheon Co., B-404998, July 25, 2011, 2011 CPD ¶ 232 at 7;
AT&T Corp., B‑299542.3, B-299542.4, Nov. 16, 2007, 2008 CPD ¶ 65
at 11; see also FAR § 15.001 (defining a “significant weakness”
as a proposal flaw that appreciably increases the risk of
unsuccessful performance). Given the degree of risk that both
the SSEB and the SSA attributed to the concern, we view it as a
significant weakness, regardless of the fact that the agency did
not expressly characterize it as such. See Raytheon Co., supra;
AT&T Corp., supra.
Prejudice is an element of every viable protest. See Piquette &
Howard Electric Serv., Inc., B-408435.3, Dec. 16, 2013, 2014 CPD
¶ 8 at 10; Supreme Foodservice GmbH, B-405400.3 et al., Oct. 11,
2012, 2012 CPD ¶ 292 at 14. Here, the SSA selected GENCO’s
proposal for award notwithstanding its evaluated price premium
of more than $1 billion. AR, Tab 62, SSDD, at 6-7. Further, he
based his tradeoff decision essentially on only three factors,
one of which was Crowley’s elevated risk rating under subfactor
4. As discussed above, the record shows that the sole basis for
the elevated risk rating was a concern that should have been,
but was not, raised in discussions. Given the magnitude of
difference in the total evaluated price of the two proposals
(more than $1 billion), we cannot say what the award decision
might have been had Crowley been provided the opportunity to
improve its risk rating under subfactor 4. In such
circumstances, we resolve doubts regarding prejudice in favor of
a protester since a reasonable possibility of prejudice is a
sufficient basis for sustaining a protest. See Supreme
Foodservice GmbH, supra; Kellogg, Brown & Root Servs.,
Inc.--Recon., B-309752.8, Dec. 20, 2007, 2008 CPD ¶ 84 at 5.
Accordingly, we conclude that there is a reasonable possibility
that Crowley was prejudiced by the agency’s actions.
In sum, we sustain Crowley’s claim regarding discussions
because: (1) in its initial evaluation, the agency documented
concern over whether Crowley would be proactive in identifying
issues before agency notification; (2) the agency did not raise
this issue in discussions but instead documented it as a
significant performance risk; and (3) the issue was a material
factor in the agency’s best-value tradeoff, demonstrating
prejudice to Crowley. We therefore recommend that the agency
reopen the competition, conduct meaningful discussions with the
competitive-range offerors, request and evaluate revised
proposals, and make a new source selection decision. (Crowley
Logistics, Inc. B-412628.2, B-412628.3, B-412628.4: Apr 19,
2016) (pdf)
MetalCraft also claims that, during discussions, the Navy misled
the protester into believing that the agency simply wanted
MetalCraft to “clarify” its initial proposal with regard to the
impact of its proposed [DELETED] on stability and buoyancy, but
not necessarily revise its initial proposal in that regard.
Supp. Protest at 2-3; Comments at 10-11, 14-16. In this respect,
the protester cites the agency’s written discussions questions,
which explicitly requested that MetalCraft “provide
clarification” regarding specified items. Comments at 10.
MetalCraft also maintains that the Navy was required to reopen
discussions because the agency only identified concerns over the
weight of water on deck after reviewing MetalCraft’s FPR. Supp.
Comments at 9-10.
The Navy maintains that it should have been clear to the
protester that the Navy was simply using the term “clarify” in
its discussion questions to mean “address” or “explain,” and
that the substance of the questions and the required responses
otherwise constituted discussions under FAR § 15.306(d). Id. at
13. The agency also disputes that it was required to reopen
discussions because MetalCraft, in its FPR, submitted a new
stability analysis, including new stability curve data and
related information. Supp. AR at 11-14; 1st Declaration of Naval
Architect & Sr. Craft Design Mgr. at 4-5, citing AR, Tab 11,
MetalCraft FPR, Vol. 1, § 2.a.4, Rev. Stability Analysis.
FAR § 15.306 describes a spectrum of exchanges that may take
place between a contracting agency and an offeror during
negotiated procurements. Clarifications are limited exchanges
between the agency and offerors that may occur when contract
award without discussions is contemplated; an agency may, but is
not required to, engage in clarifications that give offerors an
opportunity to clarify certain aspects of proposals or to
resolve minor or clerical errors. FAR § 15.306(a); Satellite
Servs., Inc., B-295866, B‑295866.2, Apr. 20, 2005, 2005 CPD ¶ 84
at 2 n.2. Discussions, by contrast, occur when an agency
communicates with an offeror for the purpose of obtaining
information essential to determine the acceptability of a
proposal or quotations, or provides the vendor with an
opportunity to revise or modify its proposal. Diversified
Collection Services, Inc., B-406958.3, B‑406958.4, Jan. 8, 2013,
2013 CPD ¶ 23 at 11-12; see FAR § 15.306(d). It is the actions
of the parties that determine whether discussions have been held
and not merely the characterization of the communications by the
agency. See Priority One Servs., Inc., B‑288836, B‑288836.2,
Dec. 17, 2001, 2002 CPD ¶ 79 at 5.
We find that, notwithstanding the Navy’s request that the
protester “provide clarification” under certain enumerated
discussion questions, the exchanges at issue constituted
discussions, not clarifications.[8] Here, the information the
agency requested that MetalCraft provide with regard to sea
state conditions, stability, and buoyancy, was necessary to
determine the acceptability of MetalCraft’s technical proposal,
including its alternate design for a craft with [DELETED]. See,
e.g., ADNET Sys., Inc., et al., B‑408685.3 et al., June 9, 2014,
2014 CPD ¶ 173 at 14-16. Moreover, the protester was permitted
an opportunity to revise its proposal through the submission of
a FPR.
We also find no merit to the protester’s arguments that the
agency should have reopened discussions with the protester.
Discussions, when conducted, must identify proposal deficiencies
and significant weaknesses that reasonably could be addressed in
order to materially enhance the offeror’s potential for
receiving award. Serco Inc., B-405280, Oct. 12, 2011, 2011 CPD ¶
237 at 11. However, agencies are not required to reopen
discussions to afford an offeror an additional opportunity to
revise its proposal where a weakness or deficiency is first
introduced in the firm’s revised proposal. Raytheon Co.,
B‑403110.3, Apr. 26, 2011, 2011 CPD ¶ 96 at 7. Here, the
protester essentially concedes that the agency’s stability
concerns regarding weight on water on deck arose from new
stability data introduced in MetalCraft’s FPR. See, e.g., Supp.
Comments at 8. (MetalCraft
Marine Inc., B-410199, B-410199.2: Nov 13, 2014) (pdf)
First, NPP challenges the scope of the agency’s corrective
action, asserting that the agency failed to comply with the FAR
requirement that, in conducting discussions, an agency must
identify deficiencies, significant weaknesses, and adverse past
performance to which the offeror has not yet had an opportunity
to respond. See FAR § 15.306(d)(3). NPP asserts that the
agency’s ultimate determination that approximately [redacted]
percent of NPP’s proposed cost savings were not feasible
constituted a significant weakness in NPP’s proposal and,
therefore, the agency was obligated to have brought to NPP’s
attention during discussions the particular bases for the
non-feasibility determinations.
When an agency engages in discussions with an offeror, the
discussions must be meaningful. For discussions to be
meaningful, they must identify significant weaknesses,
deficiencies, and adverse past performance to which the offeror
has not yet had an opportunity to respond. FAR § 15.306(d)(3). A
significant weakness is a flaw that appreciably increases the
risk of unsuccessful contract performance. FAR § 15.001. A
deficiency is a material failure to meet a government
requirement or a combination of significant weaknesses that
increases the risk of unsuccessful contract performance to an
unacceptable level. Id. In contrast to the requirement to
discuss significant weaknesses and deficiencies, an agency need
not discuss areas in which a proposal may merely be improved,
JWK Int’l, Corp. v. U.S., 279 F.3d 985, 988 (Fed. Cir. 2002),
nor is an agency required to point out every aspect of a
proposal that offers a less desirable approach than that offered
by its competitors. ProLog, Inc., B‑405051, Aug. 3, 2011, 2012
CPD ¶ 84 at 7; PWC Logistics Servs., Inc., B‑299820, B-299820.3,
Aug. 14, 2007, 2007 CPD ¶ 162 at 6.
The agency responds that NPP’s proposed cost savings did not
constitute a significant weakness in its proposal. To the
contrary, the agency points out that NPP’s proposal was rated
excellent under the management approach/cost savings evaluation
factor, and was assigned a significant strength specifically
because of its proposed cost savings. As noted above, in
assigning this strength, the agency stated:
The IPT found approximately
[redacted] B[illion] of the cumulative savings . . . to be
feasible without impact to effective security and mission
deliverables (See Exhibit E). The size of the feasible
cumulative cost savings to the Government is approximately
[redacted] of the total projected ten year budget for the CLIN
001 scope of work. . . . The [redacted] B[illion] feasible
savings is a significant benefit to the Government because it
represents a substantial amount of cost savings relative to the
operating budget. . . . The size of these cost savings for
reinvestment will become increasingly more important as federal
budgets continue to decline.
AR for NPP’s Current Protest, Tab
E-1, IPT Supp. Evaluation Report, Oct. 28, 2013, at 11-12.
In short, the agency asserts that, rather than constituting a
significant weakness or deficiency in NPP’s proposal, the
proposal offered a substantial amount of feasible cost savings
that constituted a significant benefit to the government. The
fact that NPP also proposed cost savings which the agency found
to be infeasible did not constitute a deficiency or significant
weakness. See Hearing Transcript for NPP’s Current Protest (Tr.C),
Testimony of SSA, at 841-42.
In asserting that the agency’s infeasibility determinations
regarding [redacted] percent of its proposed cost savings
constituted a significant weakness in its proposal, NPP refers
to the solicitation’s “gateway” provision, which provides that
in order to be eligible for exercise of a contract option, the
awardee must have achieved, by the end of year three, at least
80 percent of the cost savings that it proposes to achieve by
that time. RFP at 21. NPP further notes that, in his source
selection decision, the SSA stated that, because NPP’s feasible
cost savings constituted a lower percentage of its total
proposed cost savings than that of CNS, NPP would need to “reach
farther” than CNS to extend contract performance, noting that
NPP’s efforts in this regard “could lead to a loss of management
focus on security, safety, and mission.” SSD at 6.
Here, we do not view the portion of NPP’s proposed cost savings
that the agency found to be infeasible as constituting a
significant weakness or deficiency. As noted above, the IPT and
the SSA both concluded that NPP’s proposal was properly rated as
excellent under the management approach/cost savings evaluation
factor, and further recognized that the substantial amount of
feasible cost savings that NPP proposed constituted a
significant benefit to the government. Further, the evaluation
record supports the view that NPP fully understood the contract
requirements and the SSA testified that he did not question
NNP’s capability to successfully perform the contract. Tr.C at
841-42.
In arguing that its proposed cost savings constituted a
significant weakness, NPP’s reliance on the solicitation’s
“gateway” provision is misplaced. Successful performance of the
contract requirements was not conditioned on achieving 80
percent of the proposed cost savings, or upon being eligible for
contract extension. Rather, the solicitation’s “gateway”
provision was clearly intended to function as both an incentive
for offerors to propose achievable cost savings, and a tool for
the agency to use in administering the contract. In our view,
the SSA’s recognition that a contractor’s interest in achieving
greater cost savings could lead to loss of management focus did
not constitute a determination that this aspect of NPP’s
proposal constituted a “flaw that appreciably increases the risk
of unsuccessful contract performance”--that is, the agency
reasonably concluded that it did not rise to the level of being
a significant weakness.
Even if we were to conclude that NPP’s infeasible cost savings
constituted a significant weakness (which we do not), the record
supports the agency’s alternative argument that it did not
know--and could not have known--the bases for finding a portion
of NPP’s proposed cost savings to be infeasible when it
evaluated NPP’s previously-submitted FPR. That is, it was not
until NPP submitted its corrective action addendum, with the
additional information required, and in the format mandated by
the agency, that the magnitude of NPP’s infeasible cost savings
became reasonably apparent. Accordingly, the agency was not
required to reopen discussions. See L-3 Communications Corp., BT
Fuze Products Div., supra.
Finally, as the agency also notes, NPP was, in fact, advised by
the agency’s discussion letter that it must provide supporting
information for each and every cost savings initiative it had
proposed. Among other things, the agency directed NPP to
“[e]xplain the basis for each initiative,” and to “provide a
concise description of the basis for each estimate.” AR for
NPP’s Current Protest, Tab F.1, Discussion Letter for NPP, at 1
(underlining added). NPP does not dispute that it did, in fact,
provide additional supporting information for each and every
cost savings initiative, and it has not identified any
particular additional information that it would have provided if
discussions had been reopened. On this record we reject NPP’s
assertion that the agency failed to conduct meaningful
discussions in connection with its corrective action. (Nuclear
Production Partners LLC, B-407948.10, B-407948.11: Feb 27,
2014) (pdf)
Significant Weakness 1: Individual Approach for Sub-Annexes
West argues that the Navy failed to conduct meaningful
discussions regarding West’s sub-annex approach under annexes 15
and 16. The protester contends that although the agency directed
it to amplify its approach for four of the six sub-annexes under
annex 15, the agency made no mention of any concerns with West’s
approach to the eight sub-annexes under annex 16. For this
reason, West argues that by pointing out problems with its
approach to addressing the requirements of annex 15, but saying
nothing about annex 16, the agency’s discussion questions here
were inadequate and misleading. We agree.
To address the first significant weakness, the agency’s
discussion question requested that West “explain the method and
approach proposed to accomplish the requirements of the BUMED,
Pest Control, Integrated Solid Waste, and Pavement Clearance
annexes.” AR, Tab I2, Evaluation Notice, Enclosure 2, Non-Price
Discussion Questions, at 1. The discussion questions made no
mention of any issues regarding a method or approach to any of
the eight sub-annexes under annex 16. Id. In response to the
discussion questions, West revised its proposal regarding annex
15. In its final evaluation, the agency concluded that West’s
revised proposal did not address the annex 15 and 16
requirements, and that the significant weakness remained. AR,
Tab D2B, Final Technical Evaluation-West, at 8.
During the course of this protest, the Navy acknowledged that
its question to West “may have omitted by typing error” any
mention of the utilities requirements, under the annex 16
sub-annexes. Agency Response to Comments (May 13, 2013), at 8.
The agency contends, however, that its question about annex 15
should have been sufficient to advise West of the agency’s
concerns about annex 16 because the question also “clearly
reminded the offeror that they must discuss their approach for
each annex.” Id. at 7. In essence, the agency argues that,
because the question advised the protester of the need to
address--in detail--four of the six sub-annexes under annex 15,
the protester was on notice that it should have also addressed
in detail the eight sub-annexes under annex 16. The Navy also
asserts that its price discussion questions should have also put
West on notice of issues with its utility annex.
Based upon our review of the record, we find that the specific
nature of the agency’s questions misled West to respond only to
concerns about annex 15, and not about annex 16. We do not agree
with the agency that its reference to an individual approach for
four sub-annexes under annex 15 could have alerted West to the
agency’s concerns regarding West’s approach to the eight
sub-annexes under annex 16. We also have no basis to conclude
that the Navy’s price discussion questions notified West of the
agency’s concerns with regard to utilities under the technical
approach/methods factor. These questions, which alerted West to
its apparent high or low prices and requested West ensure
adequate consideration of its FTEs, did not address West’s
approach to meeting the annex requirements. Accordingly, we
sustain the protest on this basis.
Significant Weakness 2: FTEs/Staffing Level
West also argues that the Navy failed to conduct meaningful
discussions regarding its concern with West’s proposed FTEs. The
protester contends that although the agency advised West that
its proposed FTEs were low in annex 15 and 18, the agency failed
to notify it with regard to the other annexes it had determined
to be low. In this regard the agency’s decision to eliminate the
protester’s proposal from the competitive range was based on a
finding that the protester had proposed low FTEs in ten annexes.
See AR, Tab H2, SSA Report, at (unnumbered) 6. West argues that
the specific nature of the agency’s questions about annex 15 and
18 misled it into believing that its proposed FTEs for annexes
other than 15 and 18 were adequate.
In response, the Navy asserts that West was reasonably alerted
to the agency’s concerns about low FTEs in seven of the ten
annexes considered low by the Navy--even though the Navy
acknowledges that to reach this conclusion requires reviewing
the overall mix of both price and non-price discussion
questions. With regard to the remaining three annexes, the Navy
argues it was not required to conduct discussions about these
annexes because the proposed FTEs were not found to be low until
the agency’s second evaluation.
As discussed above, the agency’s initial technical evaluation
concluded that West proposed low FTEs for annexes 15 and 18. AR,
Tab D1b, Technical Evaluation- West, at 6-7. The technical
evaluation team also found that “[a]ll other annex staffing is
commensurate with the IGE.” Id. at 7. The price evaluation team
concluded that West’s proposed FTEs were low for six recurring
annexes: 1502000, 1503030, 1503060, 1603000, 1607000, and
1609000. AR, Tab E, Price Evaluation, at 59-101. The SSAC
initial evaluation did not conduct an assessment of West’s
proposed FTEs.
The agency’s non-price discussion questions, for the technical
approach/method factor, stated that “Annex 15 and 18 proposed
staffing appears low when compared to the RFP requirements for
these annexes. Please confirm your staffing is sufficient to
comply with the solicitation’s scope.” AR, Tab I2, Evaluation
Notices, Enclosure 2, Non-Price Discussion Questions, at 1. The
price discussion questions notified the protester of each annex
where the agency found its proposed price was outside of the
normal distribution, that is, the annex pricing appeared high or
low. For the recurring work annexes with pricing outside the
normal distribution, the agency also requested that West “ensure
that adequate consideration was given to FTEs.” Id., Enclosure
1, Price Discussion Questions, at 1-2.
West’s revised proposal modified its proposed FTE levels for
some, but not all annexes. See AR, Tab C3, West Revised
Proposal, Full Time Equivalent Worksheet, at 1-4. The technical
evaluation team concluded that West’s revised proposal failed to
make significant changes to its FTE levels. AR, Tab D2B, Final
Technical Evaluation-West, at 7. The price evaluation team
concluded that West’s revised proposal continued to offer low
FTEs for the same six recurring work annexes as its initial
proposal. AR, Tab E2, Final Price Evaluation, at 70-128. The
SSAC’s assessment of West’s revised proposal found that ten
annexes offered low FTEs: 1501000, 1502000, 1503060, 163000,
1604000, 1605000, 1606000, 1607000, 1609000, and 1800000. AR,
Tab G2, Final SSAC Report, at 6. As result, the significant
weakness assessed for West’s initial proposal remained.
Based upon the record, we agree with the agency that West was
reasonably alerted about the agency’s concerns with low FTEs in
seven of the ten annexes as set forth in greater detail below.
First, the agency expressly stated that it was concerned with
low FTEs in annex 15 and 18. Thus, this concern alerted West to
problems with four of the ten annexes the SSAC ultimately
concluded offered low FTEs: 1501000, 1502000, 1503060, and
1800000. Second, we agree with the Navy that the price
discussion questions lead West into the area of its proposal
where the Navy had concerns about low FTEs under 1603000,
1607000, and 1609000. Specifically, these questions advised that
the overall price for these sub-annexes “appears low,” and
requested that the protester “[r]eview proposed Sub-LIN as well
as supporting prices . . . and ensure that adequate
consideration was given to FTEs.” AR, Tab I2, Evaluation Notice,
Enclosure 1, at 2. Accordingly, we think the agency reasonably
advised West of seven of the ten annexes where it had concerns
with low FTE levels. See Insignia-Spectrum, LLC, B-406963.2,
Sept. 19, 2012, 2012 CPD ¶ 304 (in order for discussions to be
meaningful, the agency need only lead an offeror into the areas
of its proposal requiring amplification or revision).
For the final three annexes, 1604000, 1605000, and 1606000, we
see no basis in the record to conclude that the Navy advised
West of its concerns. The Navy argues that it was not required
to discuss these three remaining annexes with West, since the
agency had not evaluated these annexes as containing low FTEs
until its evaluation of revised proposals. The record shows,
however, that the protester did not revise its proposed FTEs for
these annexes. Where, as here, an agency identifies new concerns
during a post-discussions reevaluation, and those concerns would
have been required to be raised had they been identified before
discussions were held, the agency is required to reopen
discussions in order to raise the concerns with the offeror for
discussions to be meaningful. Ewing Constr. Co., Inc.,
B-401887.3, B-401887.4, April 26, 2010, 2010 CPD ¶ 108 at 3.
Moreover, the documents provided to our Office with regard to
the initial and final evaluation of these annexes were heavily
redacted. Based on the record provided by the agency, we cannot
determine whether (or when) the agency concluded that these
three annexes had low FTEs. Although an agency is not required
to retain every document generated during its evaluation of
proposals, the agency’s evaluation must be sufficiently
documented to allow our Office to review the merits of a
protest. Supreme Foodservice GmbH, B-405400.3 et al., Oct. 11,
2012, 2012 CPD ¶ 292 at 10. Thus, for these three annexes, we
conclude that the agency failed to provide meaningful
discussions.
In sum, we conclude that West was advised of low FTEs for the
four annexes raised in the non-price discussion questions, and
the three annexes raised in the price discussion questions
(1603000, 1607000, 1609000). These questions address only seven
of the ten annexes cited to as the basis for the agency’s
significant weakness and serious concern with regard to West’s
low FTEs. Accordingly, we find that the agency’s discussion
questions did not properly alert West to the agency’s concerns
with its low FTEs, and we sustain the protest on this basis.
(West Sound Services Group, LLC,
B-406583.2, B-406583.3, Jul 3, 2013) (pdf)
Sentrillion primarily contends that the Marshals Service failed
to conduct meaningful discussions. Specifically, the protester
argues that, although the agency advised the protester during
discussions of concerns regarding missing or expired business
licenses or applications, the agency failed to advise it of
deficiencies regarding certain license applications that were
viewed by the agency as incomplete. Because the agency’s
evaluation of the protester’s revised proposals found these same
incomplete license applications rendered Sentrillion’s proposals
technically unacceptable, the protester argues that the agency’s
discussions were misleading and not meaningful. For the reasons
discussed below, we agree.
In reviewing a protest challenging an agency’s evaluation of
proposals, our Office will not reevaluate proposals but instead
will examine the record to determine whether the agency’s
judgment was reasonable and consistent with the stated
evaluation criteria and applicable procurement statutes and
regulations. While we will not substitute our judgment for that
of the agency, we will question the agency’s conclusions where
they are inconsistent with the solicitation criteria,
undocumented, or not reasonably based. DRS ICAS, LLC,
B-401852.4, B-401852.5, Sept. 8, 2010, 2010 CPD ¶ 261 at 4-5
(sustaining a protest where the agency’s evaluation was not
reasonable and consistent with the solicitation).
It is a fundamental principle of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions must identify deficiencies and significant
weaknesses in an offeror’s proposal that could reasonably be
addressed so as to materially enhance the offeror’s potential
for receiving award. PAI Corp., B-298349, Aug. 18, 2006, 2006
CPD ¶ 124 at 8; Spherix, Inc., B-294572, B-294572.2, Dec. 1,
2004, 2005 CPD ¶ 3 at 13; Federal Acquisition Regulation (FAR) §
15.306(d). An agency may not mislead an offeror through the
framing of a discussions question into responding in a manner
that does not address the agency’s actual concerns, or otherwise
misinform the offeror concerning a problem with its proposal.
Metro Mach. Corp., B-281872 et al., Apr. 22, 1999, 99-1 CPD ¶
101 at 6. Additionally, if an agency identifies concerns during
a re-evaluation of proposals that should have been raised had
they been identified before discussions were held, the agency is
required to reopen discussions in order to raise the concerns
with the offerors for discussions to be meaningful. See Ewing
Constr. Co., Inc., B-401887.3, B-401887.4, April 26, 2010, 2010
CPD ¶ 108 at 3.
As discussed above, the Marshals Service’s initial evaluation
assigned a deficiency for each of Sentrillion’s three regional
proposals under the business licenses subfactor because the
protester did not provide proof of a current license, or an
application for a license, for all of its service providers. AR,
Tab 27, Price Negotiation Memorandum, at 9, 12, 15. The agency
also assigned a second deficiency under the business licenses
subfactor to Sentrillion’s Central and Eastern region proposals
because Sentrillion submitted expired licenses for certain of
its proposed service providers. Id. at 10, 13. Both of these
deficiencies were raised in discussions with Sentrillion. AR,
Tab 21, Sentrillion Discussions Letter, at 1-4. The agency’s
discussions letter did not, however, advise the company that, in
the agency’s view, some of Sentrillion’s other license
applications were incomplete.
As a result, the record shows that Sentrillion addressed the
issues that were identified in the agency’s discussions letter,
but made no changes to the applications that were submitted in
its initial proposals and were not questioned by the agency. See
AR, Tab 23, Sentrillion Revised Proposals (Nov. 15, 2012), at
1-2; Technical Proposals, Business Licenses (Central, Eastern,
and Western). Nonetheless, in its final evaluation, the agency
found that these license applications failed to contain the
information required. Consequently, Sentrillion’s proposals
received an unacceptable rating under the business licenses
subfactor, which eliminated the protester from further
consideration for award.
Sentrillion argues that if it had been advised during
discussions that the agency viewed its applications as
incomplete, it would have addressed this issue in its revised
proposals. See Protest at 18. In response, the agency asserts
that it did not mislead Sentrillion because its discussions
letter led Sentrillion into the general area of its proposals
that required amplification or revision. In this regard, the
agency contends that it advised Sentrillion that it needed to
provide “a current company license or the application for a
company license” for each service provider performing services
in each region proposed. AR, Tab 21, Sentrillion Discussions
Letter, at 1, 3, 4.
Based upon our review of the record, we find that the agency
failed to convey its concerns with the protester’s license
applications, which ultimately led to Sentrillion’s unacceptable
rating under the business licenses subfactor. Whether the agency
was aware of the incomplete applications during its initial
evaluation, or became aware of the issue only in its final
evaluation, the agency’s ultimate concerns relate to a
deficiency that existed in Sentrillion’s initial proposals, that
was not identified as a problem during discussions. Since this
deficiency led to Sentrillion’s ultimate elimination from the
competition, we conclude that Sentrillion was not provided with
meaningful discussions. See Ewing Constr. Co., supra. (Sentrillion
Corporation, B-406843.3, B-406843.4, B-406843.5, Apr 22,
2013) (pdf)
Sharp argues that the Navy’s discussions were misleading because
the Navy advised Sharp to “increase its proposed [cost] on the
basis that it was ‘understated,’ when, in reality, Sharp’s total
proposed cost was already $3 million higher than Global’s
overall evaluated [cost].” Protest at 6. Sharp contends that it
should have been advised that its proposed costs were too high,
and advised to find ways to reduce its costs. Id. Sharp argues
that by advising Sharp that its costs were understated, the Navy
misled Sharp into thinking that the only cost adjustment it
could reasonably consider making would be an upward adjustment.
Sharp’s Response to Navy’s Request for Partial Summary
Dismissal, at 2. As a result, Sharp argues it was denied an
opportunity to make its cost proposal more competitive.
In negotiated procurements, if an agency conducts discussions,
the discussions must be meaningful. E.g., The Communities Group,
B-283147, Oct. 12, 1999, 99-2 CPD ¶ 101 at 4. That is, agencies
must lead offerors into the areas of their proposals that
contain significant weaknesses or deficiencies, and it may not
mislead offerors. While an agency must advise an offeror if its
proposed cost/price is considered unreasonably high, Price
Waterhouse, B-220049, Jan. 16, 1986, 86-1 CPD ¶ 54 at 6-7, an
agency need not advise an offeror that its costs are higher than
those of its competitors if the higher costs are not viewed as
unreasonable. E.g., DeTekion Sec. Sys., Inc., B-298235,
B-298235.2, July 31, 2006, 2006 CPD ¶ 130 at 15.
We do not find that the Navy’s discussions with Sharp were
misleading. As an initial matter, the record does not support
Sharp’s assertion that the Navy advised Sharp to increase its
“total proposed cost.” To the contrary, the record shows that,
the Navy accurately conveyed its cost realism concerns regarding
specific elements of Sharp’s costs, which initially appeared
understated based on a comparison of the proposed costs with
Sharp’s incumbent contract costs, as well as information from
DCAA and DCMA.
By informing Sharp of its concerns, the Navy properly lead Sharp
into the areas of its proposal that required Sharp’s own input
in the form of revisions, explanations, clarifications, or
amplifications. Rather than encouraging Sharp to raise its
costs, the agency requested further justification for the prices
the protester had initially proposed.
Additionally, the Navy did not prohibit Sharp from lowering its
total proposed cost, and, in fact, explicitly encouraged Sharp
to review all the cost elements of its proposal, in light of the
competitive environment. Protest, Exhibit 5, Discussion Letter
from Navy, August 29, 2012, at 2. Sharp’s decision to preserve
its initial cost estimate, with the exception of its fee, was an
exercise of its independent business judgment and in no way
suggests misleading or otherwise improper discussions. See
Enterprise Information System, B-401037.5, B-401037.6, Dec. 1,
2009, 2009 CPD ¶ 233 at 3.
In addition to arguing that the Navy misled it to believe that
the only cost adjustment Sharp could make would be an upward
adjustment, Sharp also asserts that the Navy should have
explicitly advised it to lower its costs in order to be
competitive with the lower cost proposal submitted by Global.
Where, as here, an offeror’s costs are high in comparison to
those of its competitors, the agency may, but is not required
to, address the matter during discussions. Mechanical Equipment
Company, Inc. et al., B-292789.2, et al., Dec. 15, 2003, 2004
CPD ¶ 192 at 18. Accordingly, if an offeror’s costs are not so
high as to be unreasonable and unacceptable for contract award,
the agency may reasonably conduct meaningful discussions without
advising the offeror that its costs are not competitive. Id.
As mentioned above, the Navy reminded Sharp of the competitive
environment and encouraged the company to review its proposed
costs. That said, since the agency viewed Sharp’s cost proposal
as acceptable for contract award, considering its proposed
approach, and did not view its proposed costs as unreasonably
high, it was not required to expressly raise the matter in more
detail than to advise Sharp to be mindful of the competitive
environment. In our view, this reminder should have served as a
caution to Sharp. In short, we find that the agency did not
mislead Sharp during discussions. (George
G. Sharp, Inc., B-408306, Aug 5, 2013) (pdf)
Misleading Discussions
DynCorp finally contends that the agency engaged in misleading
discussions with the firm. According to DynCorp, the agency
posed discussion questions that led it to increase its proposed
staffing. The protester asserts that, ultimately, it was led to
propose more staffing than was necessary to perform the
contract, and that it was thereby prejudiced by the agency’s
actions. In support of this assertion, DynCorp points to an
observation allegedly made by the contracting officer during one
of DynCorp’s debriefings to the effect that the evaluators
thought DynCorp may have included requirements or processes
relating to performance of the predecessor contract that were
not required by the current solicitation.
However, the evaluation record, not the agency’s alleged
statements during a debriefing, provide the basis for our
review. Our concern is with the manner in which the evaluation
was conducted, not the protester’s understanding of the agency’s
subsequent explanation of how it cnducted its evaluation, and a
debriefing is only an explanation of the agency’s evaluation and
source selection, not the evaluation or decision itself.
Keystone Sealift Servs., Inc., B-401526.3, Apr. 13, 2010, 2010
CPD ¶ 95 at 5.
The record here does not show that DynCorp’s proposal was
downgraded or otherwise less favorably evaluated based on its
alleged offer of excess staffing, and DynCorp has not directed
our attention to anything in the evaluation record to support
its argument. Since DynCorp’s allegation relating to misleading
discussions would necessarily have to be predicated on a finding
by the agency that its proposed staffing was excessive, and
since the record does not reflect such a finding, it follows
that the agency did not mislead DynCorp during discussions into
proposing excessive staffing. We therefore deny this aspect of
DynCorp’s protest. (DynCorp
International LLC, B-407762.3, Jun 7, 2013) (pdf)
Misleading Discussions
The protester contends that it was misled during discussions
into raising its building and maintenance reserve from
$[deleted] to $[deleted], despite the fact that Fedcar’s lower
reserve was later evaluated to be acceptable. Protest at 4.
Walsh argues that it was misled by the characterization of its
reserve as “too low,” and misled by the agency’s use of the
average amount proposed for building and maintenance reserve to
provide feedback even though the agency did not rely on this
average when evaluating proposals. Comments at 4-5.
The Federal Acquisition Regulation (FAR) requires that when
conducting discussions pursuant to FAR part 15, contracting
officers must raise with each offeror proposal deficiencies and
significant weaknesses; contracting officers are also
“encouraged to discuss other aspects of the offeror's proposal
that could, in the opinion of the contracting officer, be
altered or explained to enhance materially the proposal’s
potential for award.” FAR § 15.306(d)(3). During discussions,
agencies may not consciously mislead or coerce an offeror into
raising its prices. Eagle Tech., Inc., B-236255, Nov. 16, 1989,
89-2 CPD ¶ 468 at 3-4. However, we will not find coercion in
discussions where an agency in good faith provides accurate
information to an offeror, even where the offeror uses that
information to its ultimate competitive detriment.
XtremeConcepts Syst., B-406804, Aug. 31, 2012, 2012 CPD ¶ 253 at
5; EMR, Inc., B-406625, July 17, 2012, 2012 CPD ¶ 209 at 5.
Here, the record does not support the protester’s assertion that
it was misled or coerced into raising the amount of its building
and maintenance reserve. During discussions, the agency informed
each offeror of the relationships between the average prices
proposed by all offerors and the prices proposed by that offeror.
In this regard, the agency informed both Walsh and Fedcar that
their building and maintenance reserve was low compared to the
average proposed by all offerors. As GAO has long made clear, it
will not sustain a protest where, as here, an agency has treated
offerors equally by providing them with the same information
during discussions, and where the protester responds by
increasing its proposed price primarily for reasons within its
business judgment. XtremeConcepts Sys., supra; see Robinson’s
Lawn Servs., Inc., B-299551.5, June 30, 2008, 2009 CPD ¶ 45 at
8. We therefore find nothing unfair or improper about the
agency’s discussions.
Further, we find no basis to sustain the protest based on the
agency’s decision to advise offerors of the average amounts
proposed by all offerors. We find the decisions cited by the
protester, Ranor, Inc., B-255904, Apr. 14, 1994, 94-1 CPD ¶ 258
and DTH Mgmt. Group, B-252879.2, B-252879.3, Oct. 15, 1993, 93-2
CPD ¶ 227, to be distinguishable from the case here. In Ranor,
the agency repeatedly advised the protester that its price was
“too low” in comparison to the government’s cost estimate. After
the agency advised the firm to raise its price, the agency made
award to an offeror with a price lower than the protester
without regard to the government estimate. In DTH Mgmt. Group,
the agency advised the protester that its price was so low in
comparison to the government estimate that it had been evaluated
as unrealistic. The protester raised its price based on the
agency’s advice, but the agency then awarded to a lower-priced
offeror, disregarding the government estimate.
In contrast to those cases, the agency here never advised Walsh
that its price was “too low,” despite the protester’s numerous
claims that it did. Rather, the agency advised each offeror of
where various portions of their price proposal stood in relation
to the averages of all offerors. Both the protester and the
awardee were informed that their reserve prices were below the
average and both the protester and awardee decided to raise
their reserve prices when submitting their FPRs. Further, the
agency here made award to the higher-priced offeror. Under these
circumstances, we cannot find that the information provided by
the agency during discussions was misleading. This protest
ground is denied. (Walsh
Investors, LLC, B-407717, B-407717.2, Jan 28, 2013) (pdf)
After evaluating initial proposals, AID assigned Nexant’s
proposal a weakness for misunderstanding the geographic scope,
as well as the nature of the tasks, outlined in the
solicitation. Specifically, the evaluators identified the
following weakness in the Nexant proposal:
Nexant failed to understand that
Optional Task 6 is designed to support focused country-level
PFAN activities in any country, not just countries in South
Asia. Thus, Nexant did not provide any creative ideas on
leveraging sufficient resources and partnerships to engage South
Asia as part of the overall program rather than relying entirely
on Optional Task 6 resources . . . .
AR, exh. 7, Initial TEC Report, at
33.
During discussions, AID asked Nexant to address the following
question: “Please clarify Nexant’s overall understanding [of]
Optional Task 6.” AR, exh. 9, Nexant Discussion Questions, at 2.
In response to the question, Nexant explained that it would
expand PFAN activities in up to 4 South Asian countries, should
funding be made available, and explained that Nexant already had
a presence in three of the South Asian countries identified in
the solicitation: India, Maldives and Sri Lanka. AR, exh. 11,
Nexant Discussion Responses, at 10-11.
In evaluating Nexant’s response, the agency evaluators continued
to assign Nexant’s proposal a weakness in this area, finding
that Nexant did not understand that task 6 was not limited to
the South Asian countries identified in the solicitation. AR,
exh. 13, Final TEC Report, at 24.
Nexant argues that AID’s discussion question was misleading
because it did not afford it an opportunity to address the
agency’s actual concerns regarding this weakness. As noted, the
evaluators were concerned with two aspects of Nexant’s proposal
in this area: (1) its apparent failure to understand that
optional task 6 was intended to be available for exercise in any
country, and not just in the countries identified by the RFP as
South Asia; and (2) Nexant’s apparent failure to provide any
creative ideas for leveraging resources and partnerships to
engage South Asian countries as part of the overall program,
rather than relying entirely on optional task 6 resources. AR,
exh. 7, Initial TEC Report, at 33. We agree with Nexant that the
agency’s discussion question in this area was misleading.
To the extent the agency’s discussion question focused on either
of these two areas of concern, it was limited to directing
Nexant’s attention--obliquely--to the first concern, namely,
Nexant’s apparent misunderstanding of the geographical scope of
optional task 6. We agree with the protester, however, that the
discussion question did not adequately convey to Nexant the
nature of the first concern because the protester was only
asked, without elaboration, to clarify its understanding of
optional task 6, and was never advised of its apparent
misunderstanding of the geographic scope of optional task 6.
More importantly, the question entirely failed to advise the
protester of the agency’s second concern, which was Nexant’s
apparent failure to provide creative ideas for leveraging
resources and partnerships to engage South Asian countries as
part of the overall PFAN program. Nexant therefore improperly
was deprived of the opportunity to improve its proposal in this
area. (Nexant, Inc.,
B-407708, B-407708.2, Jan 30, 2013) (pdf)
Program Manager Turnover and Invoicing Delays
MEP maintains that the agency unreasonably assigned weaknesses
to its proposals for having turnover in its program manager
position, and for delaying the submission of its invoices.
According to the protester, these problems were the result of
agency actions rather than its own deficient performance. For
example, the protester maintains that the only reason there was
turnover with its program manager was because the agency hired
its original program manager and, thus, MEP had to engage in
various interim and remedial actions to put another permanent
hire in place. MEP also maintains that its delays in submitting
invoices were caused by the inconsistent directions of the
Army’s contracting officers concerning how the invoices should
be prepared. The protester also argues that, to the extent the
agency had concerns in these two areas, the agency never
discussed these concerns with the protester.
Despite the fact that these concerns are reflected in the
contemporaneous record, the agency responds that these two areas
were not the cause for its assignment of a “No Go” ratings to
the protester’s proposals. According to the agency, it assigned
the “No Go” ratings to MEP’s proposals solely because of MEP’s
allegedly low fill rates. The agency therefore maintains that,
even if the protester is correct that these two concerns were
improperly identified in the evaluation of MEP’s proposals, this
did not prejudice the protester because they were not the
underlying reason for rating its proposals “No Go.” The agency
also contends that, since these concerns were not the underlying
cause for the assignment of the “No Go” ratings, it was not
required to discuss them with MEP.
As stated above, the record shows that, in fact, the agency
identified three concerns during its evaluation--turnover in the
program manager position, delays in submitting invoicing and
MEP’s fill rate--and these three concerns together appear to
have formed the underlying basis for the agency’s “No Go”
rating. For both acquisitions, the agency’s competitive range
determinations and source selection decision documents provided
as follows:
MEP – Most categories were rated Above Average with performance
in accordance with the PWS, with the exception of Program and
staff management. The rating for this category for June was
Average with a notation that the incumbent PM [program manager]
resigned without notice. The rating for July was Below Average
with a notation that MEP was now on its fourth in-country PM
within a 3-month period which was impacting continuity. The
ratings for August were mostly Average with the exception of
promptness in submission of required deliverables, which was
give[n] a rating of Unsatisfactory with the notation that MEP is
six months late in submitting invoices and submitted Feb[.]
through July 2012 invoices in one batch. The PWS, para[.] 3.0.8
requires submission of invoices within seven days of the end of
a billing cycle. MEP has experienced difficulty with achieving
the required 90% fill rate. MEP’s overall average fill rate for
June was [deleted]%, July was [deleted]%, and August was
[deleted]%. The latest report submitted by MEP shows that for
Task Order 0002 and 0003, it has a [deletetd]% fill rate. For
the remaining Task Orders the fill rates are: 0004 – [deleted]%,
0005 – [deleted]%, and 0006 – [deleted]%. Therefore, the current
overall average fill rate for MEP is [deleted]%. While monthly
rates continue to improve, MEP has not yet achieved the required
90% rate. MEP received a “No Go” on Current Contract
Performance.
AR (B-407493), exh. 10, at 2.
Thus, contrary to the agency’s current position, the record
shows that there were three concerns (rather than just one) that
it identified in its “No Go” rating of MEP’s proposals. Of the
three concerns identified by the agency, turnover in the program
manager position and delays in submitting invoices were the
first and second reasons, respectively, that the agency
identified as concerns, ahead of its concern relating to MEP’s
fill rate. Additionally, in concluding that the MEP proposals
merited “No Go” ratings, the contemporaneous evaluation
materials do not differentiate among the three reasons
identified as the basis for the agency’s assignment of the “No
Go” rating, except to the extent that one of them--delays in
invoicing--was assigned a rating of unsatisfactory. In our view,
a fair reading of the contemporaneous evaluation was that it was
a combination of the three concerns that resulted in the “No Go”
ratings.
Where, as here, an agency proffers an explanation of its
evaluation during the heat of litigation that is not borne out
by the contemporaneous record, we give little weight to the
later explanation. CIGNA Gov’t Serv’s., LLC, B-401062.2,
B-401062.3, May 6, 2009, 2010 CPD ¶ 283 at 6; Boeing Sikorsky
Aircraft Support, B-277263.2, B-277263.3, Sept. 29, 1997, 97-2
CPD ¶ 91 at 15. We therefore find that, contrary to the agency’s
current explanation, the contemporaneous record appears to show
that the agency identified three apparently equal concerns that
provided the underlying basis for rating the MEP proposal “No
Go.”
In light of our conclusion above, we also find that, to the
extent that the agency identified program manager turnover and
delays in invoicing as weaknesses or deficiencies in MEP’s
performance on previous task orders, it was required to raise
those concerns during the discussions the agency chose to
conduct. In this connection, although the regulations concerning
discussions under Federal Acquisition Regulation (FAR) part 15
do not, as a general rule, govern task and delivery order
competitions conducted under FAR part 16, Hurricane Consulting,
Inc., B-404619 et al., Mar. 17, 2011, 2011 CPD ¶ 70 at 6, our
Office nonetheless will review task order competitions to ensure
that the competition is conducted in accordance with the
solicitation and applicable procurement laws and regulations.
Imagine One Tech. & Mgmt., Ltd., B-401503.4, Aug. 13, 2010, 2010
CPD ¶ 227 at 7. While FAR § 16.505 does not establish specific
requirements for discussions in task order competitions,
exchanges in that context, like other aspects of such a
procurement, must be fair and not misleading. CGI Fed. Inc.,
B-403570 et al., Nov. 5, 2010, 2011 CPD ¶ 32 at 9. Here, we do
not regard the discussions as fair because the record shows that
the agency identified two weaknesses or deficiencies that appear
to have formed the underlying basis for its assignment of a “No
Go” rating to the MEP proposal, but those weaknesses or
deficiencies were never brought to MEP’s attention.
In view of the foregoing considerations, we sustain this aspect
of MEP’s protests. (Mission
Essential Personnel, LLC, B-407474, B-407493, Jan 7, 2013)
(pdf)
EMR also asserts that it was improperly coerced into raising its
labor rates, thereby putting its proposal outside of the range
of awardees. According to the protester, “[w]hen the government
cites a weakness in a contractor’s proposal, that contractor is
compelled to revise its proposal in response.” Protest at 4.
This issue is without merit. During discussions, agencies may
not consciously mislead or coerce an offeror into raising its
prices. Eagle Tech., Inc., B-236255, Nov. 16, 1989, 89-2 CPD ¶
468 at 3-4. Here, however, the record does not support EMR’s
assertion that it was misled or coerced into raising its labor
rates. The first EN advised EMR that the agency had found its
field rates for certain labor categories to be “low in relation
to other offerors,” and EMR does not dispute, nor is there any
basis in the record to question, the accuracy of this
information. AR, Tab 14, at 1. Further, the EN did not require
EMR to raise its labor rates, but instead simply directed that
“[t]he offeror shall verify that the prices are what it intended
to propose or make adjustments as necessary and provide the
revised prices in response to the Evaluation Notice.” Id.
(emphasis added).
The fundamental purpose of discussions is to afford offerors the
opportunity to improve their proposals "to maximize the
Government's ability to obtain best value, based on the
requirement and the evaluation factors set forth in the
solicitation." FAR § 5.306(d); see Gulf Copper Ship Repair,
Inc., B-293706.5, Sept. 10, 2004, 2005 CPD ¶ 108 at 6. In
discussions, an agency is required to discuss with each offeror
still being considered for award, deficiencies, significant
weaknesses, and adverse past performance information to which
the offeror has not yet had an opportunity to respond. In
addition, the contracting officer also is encouraged to discuss
other aspects of the offeror’s proposal that could, in the
opinion of the contracting officer, be altered or explained to
enhance materially the proposal’s potential for award. FAR §
15.306(d)(3).
Here, the agency advised EMR of areas of its proposal that
needed to be explained or altered to enhance the proposal’s
potential for award. We will not find coercion in discussions
where, as here, the agency in good faith provides accurate
information to an offeror, even where the offeror uses that
information to its ultimate competitive detriment. See Academy
Facilities Management--Advisory Opinion, B-401094.3, May 21,
2009, 2009 CPD ¶ 139 at 6 (discussions were not misleading or
coercive where information provided by agency accurately
reflected the agency’s concerns); SIMSHIP Corp., B-253655.2,
Dec. 2, 1993, 93-2 CPD ¶ 293 at 4-5 (agency did not coerce or
mislead protester into raising its price where, based on concern
that protester had offered unreasonably low prices, agency
during discussions advised protester to review proposed prices,
without stating that the protester was required to raise its
prices). In sum, EMR’s decision to revise certain prices upward
reflected the exercise of the firm’s own business judgment, not
improper conduct by the agency. See First Preston Housing
Initiatives, LP, B-293105.2, Oct. 15, 2004, 2004 CPD ¶ 221 at 3.
The protest is denied. (EMR,
Inc., B-406625, Jul 17, 2012) (pdf)
Misleading Discussions
KPMG first notes that, consistent with the RFP requirement that
offerors “must include a professional resume” for all proposed
personnel, RFP at L-5, the CIA instructed KPMG during
discussions that it must propose 14 FTEs in each contract year,
and that “[r]esumes should be provided for all personnel
proposed to perform over the lifespan of the contract.” AR
Binder 1, Tab 12, Discussions Letter from CIA to KPMG, at 1. As
quoted above, KPMG notes that the CIA’s discussions with
Deloitte provided essentially the same instruction (“Deloitte
should either submit resumes for the less experienced personnel
forecasted, or revise the cost proposal to reflect the labor
categories for the resumes provided . . .”). Supp. AR Binder 3,
Tab 6, Discussions Letter from CIA to Deloitte, Jan. 13, 2012,
at 1. Yet, the agency thereafter found Deloitte’s submission of
a single “representative resume” for each of the three labor
categories to be acceptable. On this record, KPMG argues that it
was misled by the agency during discussions and/or subsequently
treated unequally, because although KPMG complied with the
agency’s direction, Deloitte did not--and, indeed, Deloitte’s
noncompliance formed the basis for effectively lowering its
evaluated costs.
The CIA responds that the RFP did not require resumes for
employees that were proposed to perform beyond the initial
performance period, that the agency’s discussions question to
KPMG did not reflect a mandatory requirement, and that KPMG
bears the responsibility for its voluntary decision to submit
resumes of existing employees for the full term of the contract.
CIA Response to Third Supplemental Protest, at 4-6. The CIA
further asserts that, even if the RFP, or the agency’s
discussions, required KPMG’s submission of additional resumes,
the agency could waive the requirement, and if it has done so
here, the agency’s actions did not prejudice KPMG. We disagree.
In negotiated procurements, whenever discussions are conducted
by an agency, they are required to be meaningful, equitable, and
not misleading. Metro Mach. Corp., B-295744, B-295744.2, Apr.
21, 2005, 2005 CPD ¶ 112 at 19. In conducting discussions with
offerors, agency personnel also may not engage in conduct that
favors one offeror over another. FAR § 15.306(e)(1). Thus,
agencies may not engage in what amounts to disparate treatment
of the competing offerors. Front Line Apparel Group, B-295989,
June 1, 2005, 2005 CPD ¶ 116 at 3-4. Where the manner in which
an agency communicates with an offeror during discussions
misleads an offeror into responding in a way that does not
address the agency’s concerns, the discussions are inadequate.
Metro Mach. Corp., B-281872 et al., Apr. 22, 1999, 99-1 CPD ¶
101 at 6-7. Thus, for example, where an agency advises an
offeror in discussions to revise its proposal in a way that does
not reflect the agency’s evaluation, the discussions are
misleading. SeKON Enter., Inc.; Signature Consulting Group,
B-405921, B-405921.2, Jan. 17, 2012, 2012 CPD ¶ 26 at 7 (protest
sustained where agency discussions advising protester to
increase staffing level were not based on initial evaluation,
and agency gave no consideration to increased staffing level in
evaluation of revised proposal).
Here, as discussed above, the agency clearly advised KPMG that
it “should” provide personnel resumes “for all personnel
proposed to perform over the lifespan of the contract.” In the
context of the CIA’s current position that the RFP did not
require submission of resumes for personnel that were proposed
to perform beyond the initial performance period, the agency’s
discussions with KPMG were clearly misleading. Further, in cases
such as this, we need not establish with certainty what the
protester’s approach would have been if the discussions had been
meaningful; rather, a protester’s reasonable assertion of a
claim that it could have improved its competitive position is
sufficient to demonstrate prejudice. Hughes STX Corp., B-278466,
Feb. 2, 1998, 98-1 CPD ¶ 52 at 11. In this regard, KPMG has
reasonably maintained that the agency’s misleading discussions
precluded the firm from proposing its own cost-saving approach.
See Second Supp. Protest (Mar. 26, 2012) at 20-22; Third Supp.
Protest (Apr. 16, 2012) at 24, 31. We find this sufficient to
establish prejudice. Accordingly, we sustain the protest on this
basis. (KPMG LLP, B-406409,
B-406409.2, B-406409.3, B-406409.4, May 21, 2012) (pdf)
UC first asserts
that the agency misled UC during discussions by “inducing” UC to
“needlessly” increase its proposed staffing levels, while
permitting HP to retain lower staffing levels. Protest at 1,
7-8. The record does not support UC’s assertion.
It is fundamental that a procuring agency’s discussions with
offerors must be meaningful and may not be misleading. See,
e.g., The Boeing Co., B-311344 et al., June 18, 2008, 2008 CPD ¶
114 at 49. That said, an agency need not “spoon-feed” an offeror
by specifying a particular approach, nor is it required to
effectively write an offeror’s proposal for the offeror by
identifying each and every particular aspect of a proposal that
could be improved. Rather, an agency must lead an offeror into
the areas of its proposal that requires the offeror’s own input
in the form of revisions, explanations, clarifications, or
amplifications. See, e.g., L-3 Commc’ns Corp., BT Fuze Prods.
Div., B-299227, B-299227.2, Mar. 14, 2007, 2007 CPD ¶ 83 at 19.
Here, in its discussions with UC, the agency provided the
following detailed information with regard to weaknesses in UC’s
initial proposal:
1. Total project cost on [UC’s] summary spreadsheet is incorrect
as [UC] neglected to include the base period in its summary.
2. [UC] deviates from the government’s IGE [internal government
estimate] for staffing projections, in some cases significantly.
Starting [in] the base period, the government believes [UC’s]
projection of [deleted] FTEs [full time equivalent] for task
3.1.7 – Application Hosting is insufficient. The government’s
estimate was 51 FTEs. Over time, [UC] cuts this number to
[deleted] [FTEs] by the end of OY1 [option year one] and
[deleted] [FTEs] in OY2. [UC] holds this count steady from OY2
through the end of the contract. Unfortunately [UC] does not
justify this reduction in staff. Nothing in its technical
proposal indicates how [UC] would complete the tasks in the PWS
with a [deleted] staff reduction for this task. No automation
tools that might garner efficiencies in this area are noted or
priced in [UC’s] proposal.
3. A number of [UC’s] labor categories see reduced rates over
the course of this contract. Some examples: A database
administrator’s starting rate in the base period is [deleted]
per hour. By the end of OY4 it is [deleted]. Most other labor
categories show similar decreases over time that the government
finds unrealistic. Customarily there is an escalation in labor
rates over time. This refutes [UC’s] claim it can attract and
retain qualified staff and places project success at serious
risk.
4. [UC] reduces staffing and comes under government estimates in
other tasks as well. The most egregious is section 3.1.5 –
Compliance. In the base period [deleted] staff members provide
[deleted] hours. In OY1 only [deleted] staff member supplies
[deleted] hours. From OY2 through OY4 [UC] supplies no labor for
this task. In its pricing proposal, [UC] justifies this on page
2-3 in the first bullet under section 3.0 –Assumptions: “[UC]
assumes that CDC OPB will want to obtain ISO 20000 certification
under their names as soon as May 2013. Therefore we assume that
current ISO leadership roles will be assumed by government staff
with assistance from [UC] after the May 2012 annual audit. . . .
[UC] will continue to provide significant support to CDC to
ensure we maintain compliance with all ISO requirements for this
certification.[”] In its technical proposal, [UC] stressed it
had looked at and understood the government’s organizational
structure appendix. That appendix shows contractor staff
supplying significant labor to the compliance section, doing
more than just transferring the ISO certification to CDC. The
government does not believe compliance needs can be met with no
staff and refutes [UC’s] assumption above that ISO certification
and compliance can be satisfied with no contractor staff.
AR, Tab 10, Discussions Questions/Request for UC’s Revised
Proposal, at 10.
UC refers to the agency’s discussions in paragraph 1 above,
which stated that “the Government believes [UC’s] projection of
[deleted] FTEs for task 3.1.7 – Application is insufficient,”
maintaining that the agency’s use of the word “insufficient”
effectively required UC to increase its proposed staffing level
to the government estimate. Protest at 10. In this regard, UC
asserts that, even though UC “continued to believe” its initial
staffing was “adequate,” it would have been “foolish” for UC to
attempt to justify its initially proposed staffing levels, and
maintains that “the only rational action that [UC] could take”
was to “propose an FTE level at or very close to the
Government’s estimate.” Id. In this context, and in light of the
agency’s ultimate acceptance of HP’s staffing levels, which were
below the agency estimate (but substantially higher than UC’s
initially proposed levels), UC maintains that the agency’s
discussions with UC were misleading. We disagree.
First, we do not view the agency’s statement that it “believed”
UC’s initially-proposed staffing was “insufficient” in any way
precluded UC from explaining why the agency’s belief was not
well founded. Directly following the agency’s observation that
it believed the staffing was insufficient, the agency expressly
advised UC that it had not justified its lower
staffing---clearly communicating to UC that its revised proposal
could, and should, include such justification, if it existed.
Moreover, in addition to suggesting that UC justify its staffing
approach in its revised proposal, the agency went further and
identified the specific form that such justification might take,
referring to “automation tools that might garner efficiencies.”
AR, Tab 10, Discussion Questions/Request for UC’s Revised
Proposal, at 10. On this record, we find no merit in UC’s
assertions that the agency’s discussions were “misleading” and
that “the only rational action” was for UC to propose staffing
that was “at or very close to the Government’s estimate.”
Protest at 10.
In a similar vein, UC protests that the agency treated the
offeror’s “unequally” with regard to discussions, asserting that
the agency “apparently” did not question HP’s proposed staffing
levels. Protest at 12. The record is to the contrary.
In connection with the requirement that discussions be
meaningful, offerors may not be treated unequally; that is,
offerors must be afforded equal opportunities to address the
portions of their proposals that require revision, explanation,
or amplification. However, the requirement for equal treatment
does not mean that discussions with offerors must, or should, be
identical. To the contrary, discussions must be tailored to each
offeror’s own proposal. Federal Acquisition Regulation (FAR) §§
15.306(d)(1), (e)(1); WorldTravelService, B-284155.3, Mar. 26,
2001, 2001 CPD ¶ 68 at 5-6.
Here, HP’s initial proposal contemplated a higher staffing level
than the staffing level in UC’s initial proposal. Nonetheless,
because HP’s staffing level was lower than the agency estimate,
the agency’s discussions with HP did, indeed, include
expressions of concern with regard to particular aspects of HP’s
proposed approach. For example, the agency specifically
questioned HP’s proposed staffing levels with regard to tasks
[deleted] and task [deleted], stating, among other things,
“[s]taffing reductions in task [deleted] are especially
difficult to understand.” SAR, Tab 3, Discussion
Questions/Request for HP’s Revised Proposal, at 7.
On this record, we reject as factually inaccurate UC’s assertion
that the agency failed to question HP with regard to its
proposed staffing levels. To the contrary, the record
establishes that the agency, in fact, tailored its discussion
questions to HP in a manner that sought HP’s responses to
various aspects of its proposed staffing approach. Accordingly,
we find no merit in UC’s assertion that the agency’s discussions
were unequal. (Unisys
Corporation, B-406326, B-406326.2, B-406326.3, Apr 18, 2012)
(pdf)
Signature contends that the agency misled the firm into
increasing its FTEs, which resulted in the firm's evaluated
costs being higher than Tantus's. Signature Protest at 14.
Specifically, Signature complains that in directing the firm to
increase its FTEs for task order 1, CMS ignored the firm's
evaluated technical approach (which relied upon the use a
subcontractor that was already performing the task order 1 work
for CMS). Signature contends that, instead, CMS mechanically
applied an unstated staffing level in the agency's IGCE. See
Signature Comments at 14-15. In this regard, Signature states
that the agency informed it during discussions that it needed to
increase its FTEs because the agency "had funding for additional
positions under Task Order 1 and wanted to obligate these
funds." See id. at 14; see also Declaration of Signature
President ¶ 12. The protester also contends that the contracting
officer informed Signature at its debriefing that CMS requested
the increased FTEs for task order 1 due to "budgeting concerns;"
Signature states that the contracting officer represented that
he did not know what the budget would be for the next year, and
increasing the FTEs would ensure the agency kept the necessary
funding. Signature Protest at 18.
CMS denies that it requested that Signature increase its FTEs
for task order 1 because of budget considerations. See Legal
Memorandum at 15. CMS states that its discussions with Signature
reflected the agency's concern that Signature had proposed less
FTEs than the agency estimated as necessary in its IGCE. The
agency argues that if Signature had not proposed additional
FTEs, it would have adjusted the firm's costs in the agency's
cost realism evaluation. Id.
It is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful, equitable, and
not misleading. See Federal Acquisition Regulation (FAR) §
15.306(d); The Boeing Co., B-311344 et al., June 18, 2008, 2008
CPD ¶ 114 at 49.
Here, we find that Signature was misled during discussions. As
explained below and contrary to CMS's arguments, the agency's
direction to Signature during discussions--to increase its FTEs
for task order 1--was not based upon an evaluation of the
protester's proposed approach to performing the task order.
Consistent with the RFP's instructions, Signature's technical
proposal identified its approach and staffing allocation
(approximately [deleted] FTEs) for performing task order 1. See,
e.g., AR, Tab 65a, Signature Technical Proposal at 1, 4-6,
14-16. There is no document in the contemporaneous evaluation
record showing that the agency had concerns about the level of
Signature's proposed staffing for task order 1. Rather, the
agency assigned 461 of 500 possible points to Signature's
proposal under the managerial and operational approach factor
(under which the RFP provided for the evaluation of proposed
staffing). In addition, the agency identified eight strengths in
the proposal, including that the protester was currently
performing the task order 1 work. The one weakness identified
was that Signature's [deleted] was offered for only [deleted] of
an FTE, rather than [deleted] FTE. See AR, Tab 21, TEP Score
Sheet for Signature, at 3. Also, the agency's documentation of
Signature's oral presentation does not indicate any concern by
the technical evaluators with Signature's staffing level for
task order 1. See AR, Tab 25, Feedback on Signature Case
Presentation.
The agency's failure to assess the merits of Signature's
approach to performing task order 1 is corroborated by the fact
that, after the adjustment, no change was made to Signature's
technical score for performing task order 1, despite the firm's
40 percent increase in FTEs.
Moreover, the contemporaneous record supports the protester's
contention that CMS's direction to Signature to increase its
proposed number of FTEs for task order 1 was based upon budget
concerns and not upon an evaluation of the firm's technical
approach. For example, in its direction to Signature to increase
its FTEs for task order 1, the agency stated that the additional
positions could be determined later but that the agency "require[d]
the work requirements to be considered and budget allocated."
See AR, Tab 40, Evaluation of Signature Final Revised Proposal,
at 3-4.
We also find no merit to the agency's contention that, even
without discussions, it could have simply increased Signature's
proposed FTEs for task order 1 during the cost realism
evaluation. Where, as here, an agency evaluates proposals for
the award of a cost-reimbursement contract, the agency is
required to perform a cost realism analysis to determine the
extent to which an offeror's proposed costs represent what the
contract costs are likely to be under that offeror's technical
approach, assuming reasonable economy and efficiency. See FAR §§
15.305(a)(1), 15.404-1(d)(1), (2); Systems Tech., Inc.,
B-404985, B-404985.2, July 20, 2011, 2011 CPD ¶ 170 at 5. The
record here is devoid of any evidence that these cost realism
adjustments were based on an assessment of the offerors' likely
costs of performance considering their proposed approaches to
performing the task order work. That is, the record does not
show that, for any of the competitive range offerors, CMS
assessed the proposed hours and labor mix in light of the firms'
individual approaches to performing the task order work. Absent
such a reasoned assessment, the agency could not simply increase
FTEs to an unstated staffing level.
In sum, the record shows that the agency's direction to
Signature to increase its proposed FTEs for performance of task
order 1 was not based upon a reasonable assessment of the
realism of Signature's proposal. CMS has identified no
reasonable basis for its direction to Signature to increase its
FTEs by approximately 40 percent, thus increasing Signature's
proposed costs for task order 1 by $[deleted]. Absent this
adjustment, Signature's overall costs would have been lower than
the awardee's, which would have required the agency to conduct a
cost/technical tradeoff analysis to determine which firm's
proposal represented the best value to the government. Under
these circumstances, we find that CMS prejudicially misled
Signature during discussions by directing the firm to increase
its FTEs for the performance of task order 1. (SeKON
Enterprise, Inc.; Signature Consulting Group,
B-405921,B-405921.2, Jan 17, 2012) (pdf)
Next, L-3 argues that the agency's discussions were inadequate
because they failed to advise the protester that it had not
provided sufficient detail regarding the asset identification
information to be recorded and stored in its configuration
management database. In this connection, the SOW instructed
offerors to "provide, configure, populate, and manage a
Configuration Management Database (CMDB)" identifying all assets
supporting NRC services. The SOW further instructed that
offerors should
Minimize the discrepancy between
assets/inventory recorded in the CMDB and actual NRC
assets/inventory. This includes ensuring minimally the
following information for each unit:
-
Asset Tag
-
Serial Number
-
User Location (PCs and related
peripherals only)
-
Configuration (OS, loaded
software, etc.)
-
Asset Status
-
Responsible Owner
-
Host Name (Servers only)
-
IP Address (Servers only)
-
Business Function/Application
(Servers only)
-
Business Owner (Servers only)
-
Make/Model
-
Physical Location (Non-mobile
units)
-
Warranty Info/Maintenance
Certificate Number (Servers only)
SOW sect. C.5.2.3.3.2(5).
During the initial round of discussions, the agency instructed
the protester to address the requirement to "minimize the
discrepancy between assets/inventory recorded in CMDB and actual
NRC assets/inventory. (PSOW C.5.2.3.3.2(5), p. 61)," since L-3
had not addressed this requirement in its initial proposal. AR,
Tab 11c, Discussion Questions for L-3 at 1. In its response, L-3
failed to describe how it would ensure that the specific
information identified in SOW sect. C.5.2.3.3.2(5) (i.e., asset
tag, serial number, etc.) was recorded in the CMDB. In his
source selection determination, the SSO found the lack of detail
regarding the information concerning assets to be recorded and
stored in the protester's CMDB to be a "worrisome" aspect of
L-3's proposal.
The protester argues that the agency's discussion question
failed to furnish it with adequate notice of the weakness in its
proposal because it cited only the first sentence of SOW sect.
C.5.2.3.3.2(5)--that is, according to the protester, while the
agency notified L-3 that it had failed to address the
requirement to minimize the discrepancy between assets/inventory
recorded in the CMDB and actual NRC assets/inventory, the agency
did not also indicate that its failure to address the recording
of the asset tag, serial number, etc., was also considered to be
a weakness.
We find the protester's argument to be without merit. Agencies
are not required to "spoon-feed" offerors during discussions,
but rather need only lead offerors into the areas of their
proposals that require amplification or revision. Martin Elecs.,
Inc.; AMTEC Corp., B-404197 et al., Jan. 19, 2011, 2011 CPD para.
25 at 6. The agency's discussion question here specifically
informed the protester that it had not adequately addressed the
requirement set forth in SOW sect. C.5.2.3.3.2(5) to minimize
the discrepancy between actual and recorded assets/inventory.
Moreover, the clear terms of SOW sect. C.5.2.3.3.2(5) furnished
notice that minimizing the discrepancy required that, at a
minimum, information such as the asset tag and serial number be
recorded in the CMDB. In our view, the foregoing was more than
sufficient to lead the protester into the area of its proposal
that required amplification. Having sufficiently led L-3 to the
area of concern in the first round of discussions, NRC was not
required to raise the matter again in any subsequent round of
discussions, even where it continued to be considered a concern
by the agency. U.S. Filter Operating Serv's., Inc., B-293215,
Feb. 10, 2004, 2004 CPD para. 64 at 3. (L-3
STRATIS, B-404865, June 8, 2011) (pdf)
ACS protests the adequacy of the agency's discussions in
connection with a single aspect of its proposed solution to the
requirement. ACS, the incumbent contractor, has been providing
the agency's requirements using a highly customized software
product developed for DOL, and [deleted]. In its initial
proposal, ACS offered to transition its software product from
the [deleted] it currently uses to an [deleted] solution
(referred to in the record as [deleted] or [deleted]), and to do
so during performance under its predecessor contract, so that
ACS could offer the [deleted] solution to the agency for the
solicited requirement. The protester maintains that the
[deleted] solution would offer improved performance and,
potentially, lower cost over the life of the solicited
requirement.
After evaluating ACS's initial proposal and advising the firm
that implementation of the [deleted] solution under its
predecessor contract was not acceptable, the agency subsequently
advised the protester during discussions that its proposal was
based on an incorrect assumption, specifically, the assumption
that the agency would allow ACS to migrate its existing system
to an [deleted] solution during performance of the predecessor
contract. The agency therefore advised ACS that "'[b]ecause [ACS's]
assumption is incorrect, the Offeror may wish to reconsider the
effect of this incorrect assumption and revise its proposal
accordingly."' AR, exh. C-5, Initial Ratings, Factor 1,
deficiency.
In response to the agency's initial discussion question, ACS
eliminated the proposed migration from its current [deleted]
system to its originally proposed [deleted] solution, stating as
follows:
ACS understands, respects, and
will attend to the DOL's remarks regarding the [deleted]
Migration referenced in our original proposal. In response to
DOL's concerns, ACS has halted the [deleted] Migration and
removed [deleted] from the revised proposal. Instead, ACS will
deliver a . . . solution based upon the proven [deleted].
AR, exh. J-1-1, File 6, at 2.
In the source selection decision,
the agency identified a risk associated with the firm's use of
its existing [deleted] system. Specifically, the agency noted
that, because ACS was proposing legacy technology (i.e., its
[deleted] system), support for the system might end, and the
expertise required for the [deleted] system and the [deleted]
used by ACS in its [deleted] system solution could become scarce
over time. Source Selection Decision Document, at 9.
ACS asserts that the agency never identified this specific risk
during discussions, despite the fact that the agency engaged in
several additional rounds of discussions after ACS proposed
eliminating the [deleted] solution and using its [deleted]
solution instead. According to the protester, the agency's
failure in this regard amounted to inadequate discussions
because this risk constituted a new deficiency in its proposal,
and the agency was obliged to discuss it with ACS.
We have no basis to object to the adequacy of discussions here.
Discussions are adequate where offerors are advised of the
weaknesses, excesses or deficiencies in their proposals. US
Filter Operating Serv's., Inc., B-293215, Feb. 10, 2004, 2004
CPD para. 64 at 3. While discussions should be as specific as
practicable, there is no requirement that they be
all-encompassing or extremely specific in describing the
agency's concerns; rather, the legal requirement is that they
generally lead the offerors into the areas of their proposals
that require amplification or correction, without being
misleading. Id. Moreover, where an agency has advised an offeror
of its concern, there is no requirement that it raise the issue
again in subsequent rounds of discussions, even where the issue
continues to be a concern to the agency. Id.
Subsequent to the written discussions described above, the
agency and ACS engaged in oral discussions, during which ACS
again represented that it intended to use its [deleted] solution
instead of the [deleted] solution originally proposed.
Specifically, the protester's representative stated:
ACS has withdrawn and completely
removed any references to our technology refresh initiative.
We referred to this previously as [deleted] migration . . . .
We intended to have this refresh completed in our current
contract year. And quite frankly, cost . . . lower cost
infrastructure was the driver behind that . . . . We decided
not to put it in our current proposal because we believe that
implementing both the enhancements [to the [deleted] system]
to meet the additional requirements and the technology refresh
quite honestly compounded the complexity and introduced risk.
Video 1, at 13:00-13:49. ACS's
representative also specifically recognized during those oral
discussions that its current [deleted] solution, while generally
meeting the solicitation requirements, nevertheless was, in his
words, "'short of state-of-the-art."' Id. at 40:15.
The protester's representatives went on to suggest that, once
its [deleted] solution was fully implemented and certified, ACS
intended again to propose to the agency migration from the
[deleted] solution to the [deleted] solution. Video 1, at
41:55-42:22. In response to that suggestion, the agency's
technical evaluation panel chairman specifically cautioned the
protester that it would not receive credit for any proposed
migration from one [deleted] to another, unless such a migration
was included in the firm's proposal:
[A]ny tech value enhancement . . .
would probably, may, add value to the best value decision that
we have to make. But, what you just stated about doing this
sometime in the future, we can't consider that unless it's
part of the proposal.
Video 1, at 42:31-42:49. In
response, the protester's representative specifically
acknowledged that he understood, but that the firm had made a
decision--based on its assessment of implementation risk--to
forego offering the migration from one [deleted] to another as
part of its proposal. Id.
In summary, the record shows that ACS understood that its
proposed [deleted] solution was "'short of state-of-the-art,"'
but that it had made a business decision to forego
implementation of the state of the art [deleted] solution
because of risks inherent in implementing any migration. The
record further shows that ACS understood that the agency would
not give it credit in the evaluation and source selection
decision based merely on a suggestion that the migration could
take place sometime in the future. While the protester is
correct that the agency did not expressly identify the specific
risk it ultimately articulated in its source selection decision
during discussions, we think it nonetheless adequately led the
protester into that area of its proposal, and made clear to the
protester that the consequences of not including the [deleted]
solution in its proposal would affect the agency's best value
deliberations. In response, the protester clearly decided, on
the basis of its business judgment, that not including the
[deleted] solution in its proposal was its best--least
risky--proposal strategy. We therefore conclude that the
agency's discussions with the protester in this area were
adequate. Simply stated, an agency need not identify every
conceivable consequence of an offeror's business decision in
order to discharge its duty to engage in meaningful discussions.
(ACS Federal Solutions, LLC,
B-404129, January 7, 2011) (pdf)
ITW complains that it was misled
during discussions. Specifically, the protester maintains that
the Navy improperly advised it during discussions that its
prices for two contract line item numbers (CLIN) were "somewhat
lower" than the independent government estimate (IGE). ITW
states that, in reliance on this notification, it increased its
final price for these two CLINS. ITW also maintains that it was
required to review its final pricing for all CLINs as result of
the Navy's comments with respect to these two CLINs. Protester's
Comments at 3.
When discussions are conducted, they must at a minimum identify
deficiencies and significant weaknesses in each
competitive-range offeror's proposal. Federal Acquisition
Regulation (FAR) sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12.
Discussions must be "meaningful," that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12. An
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency's concerns, or
misinform the offeror concerning a problem with its proposal or
about the government's requirements. Academy Facilities
Mgmt.--Advisory Opinion, B-401094.3, May 21, 2009, 2009 CPD para.
139 at 6; Multimax, Inc., et al., supra. In the context of
discussions relating to cost or price, agencies may not coerce
or mislead an offeror during discussions into raising its
prices. Academy Facilities Mgmt.--Advisory Opinion, supra.
Here in its discussions with ITW, the Navy identified a number
of weaknesses and deficiencies in the protester's initial
proposal; these weaknesses and deficiencies were identified in
25 evaluation notices (ENs). AR at 3. The agency's concerns with
ITW's proposed prices were not discussed in any of the ENs, but
were communicated to ITW in the letter transmitting the ENs.[3]
With respect to the pricing for the two CLINs (for which the
agency was concerned the pricing was low), the agency informed
ITW as follows:
[Y]ou are advised to carefully
review the price proposal for any misunderstanding of the
requirements, as several proposed . . . CLINs appear out of
line with the Government estimate. . . . [B]ased on market
research . . . CLINs . . . appear to be priced somewhat lower
than the government estimate; therefore you are advised to
carefully review your price proposal for any misunderstanding
of the requirements.
AR, Tab 2, Navy Discussions with
ITW, at 1.
In its FPR, ITW raised its prices for these two CLINs by
approximately $32,000, and lowered its overall price by more
than $1 million. AR, Tab 11, Navy Analysis of ITW's Prices, at
3.
We do not find that the Navy's discussions with ITW were
misleading. The record shows that the Navy found that in these
two particular instances ITW's prices appeared understated in
comparison to the IGE. The agency accurately conveyed its
concerns to ITW in discussions. ITW does not dispute that its
pricing for these two CLINs was below the IGE. Rather, ITW
essentially argues that the Navy "implie[d]" that unless the
offeror raised its prices it would be removed from the
competition and/or downgraded regarding its ability to perform
the work at the proposed price. Protest, Sept. 14, 2010, at 1;
Protest, Oct. 23, 2010, at 3 ("how else would ITW be expected to
respond other than increase [its] pricing?"). We find no merit
to this argument. The agency simply communicated to ITW that its
CLIN pricing appeared lower than that of the IGE in two
particular regards, and asked the protester to review its
pricing. This did not compel ITW to take any particular action,
but left to the firm's business judgment whether it should raise
its prices or explain the prices earlier submitted. (ITW
Military GSE, B-403866.3, December 7, 2010) (pdf)
CIGNA points out that while the
agency conducted three rounds of discussions with the
competitive range offerors, the only issue regarding CIGNA's
approach to printing and postage costs raised by the agency
concerned CIGNA's initial failure "to include HH&H claims volume
in calculating the proposed costs for Internet/Communications
and Output Mail Postage," which CIGNA corrected in its FPR.
Protester's Comments at 11; see AR, Tab 17, CIGNA Discussion
Questions and Responses (Sept. 30, 2008), at 101. As noted by
CIGNA, the record shows that the agency did not raise any other
concerns during discussions regarding CIGNA's proposed printing
and postage costs.
The Federal Acquisition Regulation (FAR) requires that where an
agency undertakes discussions with offerors, the contracting
officer shall discuss with each firm being considered for award
deficiencies and significant weaknesses identified in the firm's
proposal. FAR sect. 15.306(d)(3). Discussions must be
meaningful, equitable, and not misleading. Cygnus Corp., Inc.,
B-292649.3; B-292649.4, Dec. 30, 2003, 2004 CPD para. 162 at 4;
Lockheed Martin Corp., B-293679, May 27, 2004 CPD para. 115 at
7. Discussions cannot be meaningful unless they lead an offeror
into those weaknesses, excesses or deficiencies in its proposal
that must be addressed in order for the proposal to have a
reasonable chance of being selected for contract award. Cygnus
Corp., Inc., supra; Lockheed Martin Corp., supra.
The agency does not argue that it raised its concerns regarding
CIGNA's proposed printing and postage costs during its
discussions with the protester, acknowledging that, as reflected
in the record, the "discrepancy" between the printing and
postage costs proposed by the other competitive range offerors
and CIGNA "was only identified after the submission of FPRs,
when each offeror's proposed costs were compared with one
another." AR at 45 n.7; Agency Supp. Report at 11. Rather, the
agency contends that its "cost adjustment to [CIGNA's] proposal
was minor," in that "it increased [CIGNA's] total evaluated cost
by [DELETED]% and reduced the cost difference between [CIGNA]
and [Highmark] from [DELETED]% to [DELETED]%." Agency Supp.
Report at 17. The agency continues here by arguing that because
the adjustment was "minor," the "adjustment was not the
equivalent of a 'significant weakness,' nor did it concern 'an
aspect[] of the offeror's proposal that could, in the opinion of
the contracting officer, be altered or explained to enhance
materially the proposal's potential for award," and thus the
agency's concerns here did not have to be raised with CIGNA
during discussions. Agency Supp. Report at 17 (quoting FAR sect.
15.306(d)(3)).
We disagree. In this regard, we first reject the agency's
contention that its concerns with CIGNA's proposed printing and
postage costs, and the resultant upward adjustment to CIGNA's
proposed costs, were "minor" or otherwise concerned matters that
did not have to be raised with CIGNA in order for discussions to
be meaningful. As set forth above, the agency's upward
adjustment constituted, by the agency's own calculations, an
$[DELETED] or [DELETED] percent increase to CIGNA's proposed
costs, which caused the cost advantage associated with CIGNA's
proposal to be reduced from [DELETED] percent to [DELETED]
percent. We simply fail to see, and do not believe that the
agency has adequately explained, why an upward adjustment to
CIGNA's proposed costs of [DELETED] percent can reasonably be
characterized as "minor" or otherwise inconsequential under the
circumstances here. Additionally, we note that the agency has
not pointed to anything in the contemporaneous record of the
evaluation and source selection stating or otherwise providing
that the failure to raise this issue with CIGNA during
discussions was due to the agency's view that the cost
adjustment was "minor." As such, we give little weight to the
agency's assertions crafted in the heat of litigation that the
agency's upward cost adjustment to CIGNA's proposal would have
been and should be considered "minor," and thus was not required
to be raised during discussions. Novex Enters., B-297660;
B-297660.2, Mar. 6, 2006, 2006 CPD para. 51 at 4; Boeing
Sikorsky Aircraft Support, B-277263.2, B‑277263.3, Sept. 29,
1997, 97-2 CPD para. 91 at 15. In the context of the trade-off
actually made here, we cannot conclude that this adjustment was
"minor."
Although the agency correctly points out that an agency has no
duty to reopen discussions to allow an offeror to address
proposal defects or significant weaknesses first introduced in
the offeror's response to discussions or in a post-discussion
proposal revision, Honeywell Tech. Solutions, Inc., B-400771;
B-400771.2, Jan. 27, 2009, 2009 CPD para. 49 at 10, such was not
the case here. That is, the agency does not claim, and there is
nothing in the record to indicate, that the discrepancy between
CIGNA's proposed printing and postage costs and the other
offerors' proposed printing and postage costs was different in
any material way between the offerors' initial proposals and
FPRs. In other words, the aspect of CIGNA's cost proposal that
caused the agency concern was present in CIGNA's initial
proposal. The fact that the agency did not realize until after
discussions had concluded and the agency had received FPRs that
CIGNA's proposed printing and mailing costs were substantially
lower than the costs proposed for these same services by the
other offerors, and thus, in the agency's view, were
understated, does not relieve the agency of its obligation to
conduct meaningful discussions. Al Long Ford, B-297807, Apr. 12,
2006, 2006 CPD para. 68 at 8. Where, as here, an agency, after
discussions are completed, identifies a concern pertaining to
the proposal as it was prior to discussions that would have had
to be raised if it had been identified before discussions were
held, the agency is required to reopen discussions in order to
raise its concern with the relevant offeror. Id.
(Sections deleted)
In sum, we find that the agency's
concerns with CIGNA's proposed printing and postage costs should
have been raised with CIGNA during discussions in order for
discussions to have been meaningful, and sustain the protest on
this basis. (CIGNA Government
Services, LLC, B-401062.2; B-401062.3, May 6, 2009) (pdf)
AMEC argues that the agency's discussions regarding the weakness
identified in its proposal under factor 3, preliminary project
schedule, were not meaningful because they did not disclose the
true nature of the agency's concern regarding its proposed use
of the Microsoft Project software. AMEC also contends that the
agency failed to properly consider as part of its technical
evaluation under factor 2, particular project execution
strategies, the fact that the seed project site has been
designated as a wetlands area, as disclosed by AMEC during its
discussions with the agency.
The record reflects that the agency's discussions with AMEC with
respect to factor 3 were flawed. It is a fundamental precept of
negotiated procurements that discussions, when conducted, must
be meaningful, equitable, and not misleading. AT&T Corp.,
B-299542.3, B-299542.4, Nov. 16, 2007, 2008 CPD para. 65 at 6.
An agency may not mislead an offeror‑‑through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency's concerns, or
misinform the offeror concerning a problem with its proposal or
about the government's requirements. MCT JV, B-311245.2,
B-311245.4, May 16, 2008, 2008 CPD para. 121 at 15-16; Multimax,
Inc., et al., B-298249.6 et al., Oct. 24, 2006, 2006 CPD
para.165 at 12; Metro Mach. Corp., B‑281872 et al., Apr. 22,
1999, 99-1 CPD para. 101 at 6.
Here, as noted above, the agency's technical evaluation team
identified a weakness in AMEC's technical proposal based on its
use of the software program Microsoft Project, which the agency
concluded was "not the most applicable for managing the
[design/build] process or construction projects . . . lacks the
analytical capabilities of other construction oriented software
. . . and may adversely impact the overall management and
reporting effort." AR, Tab 15, Technical Evaluation, at 000485.
In its discussions with AMEC, the agency's questions, however,
focused on specific features of the Microsoft Project software,
in particular, its ability to manage schedule "float." While
AMEC was able to satisfactorily address the agency's specific
questions in this regard, the record reflects that the agency
continued to fault AMEC for proposing Microsoft Project as
adversely impacting the overall management and reporting effort
of the project, and that it was the presence of this weakness
which prevented AMEC from achieving a higher rating under factor
3, therefore materially affecting the agency's technical
evaluation of AMEC's proposal. In this regard, the record
reflects the agency's view that AMEC's proposal had several
strengths under factor 3 and no other weaknesses, but that,
based on the risks associated with its software selection, AMEC
was not entitled to a higher technical rating. AR, Tab 19,
Technical Evaluation Report, at 000584. By being asked only to
address specific questions regarding the particular features of
Microsoft Project, AMEC could not have reasonably understood the
true nature of the agency's broader concerns about the use of
Microsoft Project. As a consequence, the agency's discussions
were materially misleading, thereby depriving AMEC of an
opportunity to address the agency's concern regarding the use of
Microsoft Project in the management of the seed project.
The agency raises several arguments in defense of the adequacy
of discussions, none of which alters our conclusion that its
discussions with AMEC were fundamentally flawed. Specifically,
the agency contends that, pursuant to FAR sect. 15.306(d)(3), it
was not required to discuss its general concerns regarding
AMEC's use of Microsoft Project since the weakness was not
"significant," and it was not identified as a deficiency. In
this regard, the agency suggests that it did not consider AMEC's
use of Microsoft Project to be an unacceptable approach since
the technical evaluation team determined that it had the
"minimum acceptable level of scheduling capabilities." AR, Tab
15, Technical Evaluation, at 000485. Moreover, the agency argues
that identifying the use of Microsoft Project as a weakness
would have been inappropriate since it would have been
tantamount to directing AMEC to implement a particular technical
approach and thereby imposing an undisclosed requirement.
While it is true that agencies are only required to address
"significant" weaknesses and deficiencies during discussions,
FAR sect. 15.306(d)(3) further indicates that these are the
"minimum" areas for discussion. The record reveals that the
agency went well beyond these minimum requirements during its
discussions with the eight firms in the phase II competition. In
this regard, the record reflects that the agency identified
nearly every weakness, in most instances verbatim, from the
technical evaluation findings, without regard to whether the
weakness was considered "significant" or whether the weakness
was associated with an "unacceptable" approach. By way of
example, in its discussions with one of the awardees, the agency
indicated that it considered the offeror's use of soil-supported
ground slabs to be "acceptable," yet the agency advised the
offeror that its proposed approach was considered "to be more
prone to long term settlement issues." AR, Tab 16, Agency's
Discussion Questions, at 000572. Given the agency's decision to
hold broad discussions with all firms, which went well beyond
the FAR's minimum requirements, it was incumbent on the agency
to do so with all offerors equally, and it may not now defend
its failure to have apprised AMEC of a perceived weakness in
AMEC's proposal based on the FAR's minimum discussion
requirements. See also, FAR sect. 15.306(e) (an agency shall not
engage in exchanges that "favors one offeror over another.")
In addition, we find the agency's concerns about directing AMEC
toward a particular technical approach to be misplaced. Had the
agency simply identified to AMEC the perceived risks associated
with AMEC's proposed software, AMEC would then have been in a
position to develop an appropriate response, which could have
ranged from continuing to propose the software notwithstanding
the associated risk, justifying its decision to the agency, or
proposing to use a different software package, any of which
could have addressed the agency's concerns. While there might
have been tradeoffs associated with these various options, AMEC
should have been allowed to make such a decision based on an
understanding of the true nature of the agency's concerns
regarding its technical proposal.
We also find that the agency's consideration of the wetlands
issue under evaluation factor 2 was improper. AMEC argues that
it was the only offeror to have identified the project site as a
potential wetland and that the agency failed to reasonably
consider this fact in its evaluation of the other offerors'
proposals. As noted above, for factor 2, particular project
execution strategies, offerors were required to address project
site specific conditions at Cape May, New Jersey, to include
"environmental, and complications related to doing work in the
New Jersey area." RFP at 82. This provision essentially required
offerors to perform due diligence regarding the nature of the
agency's requirements and to incorporate their findings in their
proposals.
In its initial proposal, AMEC
advised the agency that the project site "may be classified as
wetlands in accordance with State of New Jersey standards," and
went on to address the potential wetlands designation as an
aspect of the permitting process, which was incorporated in
AMEC's project schedule. AMEC Proposal at 000686-000688. The
record indicates that the other offerors did not specifically
identify this potential concern.
During discussions, the agency asked AMEC to clarify its wetland
reference and to identify "information which would alter the
conclusion that the site is not in a designated wetland area."
AR, Tab 17, Discussion Questions, at 000566. In its response,
AMEC provided the agency with publicly available information
contained in the New Jersey Department of Environmental
Protection's iMap-NJ system, which specifically identified the
project site as a wetland, and provided the basis for AMEC's
belief that there was a need for the wetland issue to be
addressed with the state of New Jersey, notwithstanding the fact
that it was unlikely the project site ultimately would be found
to be a wetland.
The agency concedes that the iMap-NJ system does in fact
identify the project site as a wetland and it does not dispute
the propriety of AMEC's consideration of the iMap information.
Contracting Officer's Supplemental Statement, at 000873. Rather,
the agency asserts that the site is not in fact considered a
wetland by the state of New Jersey, as reflected by a 2003
Integrated Natural Resources and Environmental Assessment, which
had been provided to the agency by the New Jersey Department of
Environmental Protection, as well as information solicited from
an official within the New Jersey Department of Environmental
Protection, thereby rendering immaterial the failure of the
other offerors to identify the project as potentially a wetland.
Supplemental Agency Report, at 000865. We disagree.
The information upon which the agency now relies was not
publicly available and was not otherwise made available to any
of the offerors during the competition. For this reason, once
the agency learned of AMEC's reasonable reliance on the publicly
available iMap information, which was in direct conflict with
the information that was in the agency's sole possession which
shaped the premise of its technical evaluation of the other
offerors' proposals, the agency was obligated to clarify the
agency's understanding of wetland requirement with AMEC. Absent
clarification of the matter, AMEC was placed in the position of
addressing a solicitation requirement in a manner different than
the other offerors and which placed it at a competitive
disadvantage to the other offerors given the conflicting public
and nonpublic information. The agency's failure to clarify the
wetland issue was contrary to the fundamental principle that a
solicitation must provide for the submission of proposals based
on a common understanding of the agency's requirements. See
Media Funding, Inc. d/b/a Media Visions, Inc., B-265642,
B-265642.2, Oct. 20, 1995, 95-2 CPD para. 185 at 3. We therefore
sustain the protest on this basis as well. (AMEC
Earth & Environmental, Inc., B-401961; B-401961.2, December
22, 2009) (pdf)
Sabre asserts that the agency
failed to provide it with meaningful discussions regarding
previously unidentified weaknesses under the demonstrated
understanding and management/technical approach subfactors. For
example, it maintains that the weaknesses related to its DPM,
quality assurance surveillance plan, updated CSA manuals, and
work breakdown structure (WBS) stemmed from issues present in
its original proposal and were unrelated to the discussion
questions raised, such that it was not on notice of the specific
issues of concern to the agency.
When an agency engages in discussions with an offeror, the
discussions must be meaningful, that is, they must lead the
offeror into the areas of its proposal that require correction
or amplification. Hanford Envtl. Health Found., B‑292858.2,
B‑292858.5, Apr. 7, 2004, 2004 CPD para. 164 at 8. However, an
agency is not obligated to reopen negotiations to give an
offeror the opportunity to remedy a defect that first appears in
a revised proposal. American Sys. Corp., B-292755, B‑292755.2,
Dec. 3, 2003, 2003 CPD para. 225 at 8.
The discussions here were unobjectionable. For example, the
agency's initial discussions noted that Sabre's WBS did not
provide sufficient detail to depict all SOW requirements. In our
view, the initial question was sufficient to lead Sabre to
provide a response that included a more detailed WBS, and the
TET found Sabre's response to this weakness to be adequate
during the FPR evaluation. In re-evaluating the FPRs, however,
the TEP came to a different conclusion based on its identifying
continuing weaknesses, specifically, missing milestones
regarding some operational tasks and deliverables. There was
nothing unreasonable or improper in the TEP's changing its
original view as to the adequacy of Sabre's discussions response
based on the re-evaluation. Since the identified weaknesses
represented defects first appearing in Sabre's FPR in response
to the original discussions--rather than newly identified
weaknesses in Sabre's initial proposal--the agency was not
required to reopen negotiations to provide Sabre another
opportunity to respond.
We reach the same conclusion with regard to Sabre's proposed DPM.
As mentioned above, during the original discussions, the TEP
identified a weakness regarding Sabre's failure to clearly
identify the different roles and responsibilities related to
implementing its communications initiatives. TEP Evaluation at
10. When Sabre's FPR added a DPM as part of its solution, the
TEP identified a new weakness based on the lack of information
on this individual; since the weakness was introduced in Sabre's
FPR, the agency did not raise the matter again. Id. Sabre argues
that, since its initial proposal mentioned the DPM (e.g., in its
organization chart and part of its risk review team), but did
not then identify him, his role, or his function, the DPM
concern really was a weakness in its original proposal--rather
than a new weakness--that the agency should have raised during
the original discussions. Thus, once the agency's re‑evaluation
identified the lack of that information as a weakness, the
agency was required to re‑open discussions to address it. See
Lockheed Martin Simulation, Training & Support, B-292836 et al.,
Nov. 24, 2004, 2005 CPD para. 27 at 11 (where weakness, present
in initial proposal, is identified for first time in
re-evaluation, agency must discuss the new weakness).
We disagree. The fact that Sabre's initial proposal contained
little information on the DPM is irrelevant; it was Sabre's
proposing the DPM as part of its communication initiatives,
without detailed information, that led to the agency's specific
concern. Prior to that time, the agency had no specific reason
to be concerned about the lack of detail on the DPM's role and
function. Once Sabre proposed the DPM as part of its solution to
an identified weakness, it was Sabre's responsibility to provide
complete information. See Carlson Wagonlit Travel, B‑287016,
Mar. 6, 2001, 2001 CPD para. 49 at 3 (offeror is responsible for
submitting an adequately written proposal). Its failure to do so
here led to a new evaluated weakness, which--because it was
introduced for the first time in its FPR--did not obligate the
agency to reopen discussions following the re-evaluation.
American Sys. Corp., supra.
The protest is denied. (Sabre
Systems, Inc., B-402040.2; B-402040.3, June 1, 2010) (pdf)
The protester argues that the
agency conducted materially misleading discussions regarding
Ewing's proposed roofing system, and that the agency's
evaluation of Ewing's and Overland's proposals was unreasonable
in a number of respects.
This protest is illustrative of one of the challenges an agency
faces when, for whatever reason (but here in taking corrective
action in response to a previous protest), the agency
reevaluates proposals after discussions are complete. In this
regard, we have held that where an agency, during a reevaluation
of proposals, identifies new concerns in a proposal and those
concerns would have had to be raised had they been identified
before discussions were held, the agency is required to reopen
discussions and raise the new concerns with the offeror.
Lockheed Martin Simulation, Training & Support, B-292836.8 et
al., Nov. 24, 2004, 2005 CPD para. 27 at 11; DevTech Sys., Inc.,
B-284860.2, Dec. 20, 2000, 2001 CPD para. 11 at 4.
Here, prior to taking corrective action, the agency raised its
concerns regarding Ewing's proposed roofing system during
discussions, and specifically identified its concerns as a
"significant weakness." After evaluating Ewing's final proposal
revision, the agency assigned the proposal ratings of "marginal"
under the technical solution factor and "satisfactory" overall.
AR, Tab 5, Ewing Discussion Letter (June 8, 2009). These ratings
were consistent with the terms of the solicitation, which stated
that a "significant weakness" may result in an adverse impact on
the proposal's rating under the technical solution factor and
overall rating. RFP at 10.
In contrast, during the reevaluation--performed as part of the
agency's corrective action in response to Ewing's initial
protest--the agency determined that Ewing's proposed roofing
system constituted a "deficiency in meeting the stated
solicitation requirements." Rather than downgrading Ewing's
proposal, this reassessment rendered the proposal "ineligible
for award," in accordance with the terms of the RFP--which, as
quoted above, expressly stated that proposals with uncorrected
deficiencies would be ineligible for award. AR, Tab 2, BCM, at
15, 19-20; RFP at 10. Because the agency did not reopen
discussions with the offerors, Ewing was never informed that its
proposal was deficient. Although the agency is correct that its
concern with Ewing's proposed roofing system was raised during
discussions (such that the concern is not a "new concern"), the
identification of the concern as a "significant weakness,"
rather than a "deficiency," misled the protester. Specifically,
the protester was never apprised of the severity of the agency's
concern, or the ramifications of not adequately addressing it--i.e.,
ineligibility for award.
It is a fundamental concept of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror's
proposal that could reasonably be addressed in a manner to
materially enhance the offeror's potential for receiving award.
Federal Acquisition Regulation (FAR) sect. 15.306(d); Lockheed
Martin Corp., B-293679 et al., May 27, 2004, 2004 CPD para. 115
at 7. An agency may not, through silence, the framing of a
discussion question, or in a response to a question, mislead an
offeror into responding in a manner that does not address the
agency's concerns, or that misinforms the offeror concerning a
problem with its proposal or the government's requirements.
Lockheed Martin Corp., supra; Metro Mach, Corp., B-281872 et
al., Apr. 22, 1999, 99-1 CPD para. 101 at 6.
Under the circumstances here, since the agency's concerns with
the protester's proposed approach changed during the
reevaluation to the point that, should they remain unaddressed,
the proposal would be rejected as ineligible for award, the
agency was required to reopen discussions. On this issue, the
protester represents that "[h]ad the Agency identified the
proposed roof design as a deficiency during discussion[s],
[Ewing] would have been made aware that its proposal was
ineligible for award, which would have elicited a different
response from [Ewing] to the Discussion Letter." Protest at 6;
see Protester's Comments at 6.
The protest is sustained. (Ewing
Construction Co., Inc., B-401887.3; B-401887.4, April 26,
2010) (pdf)
Lack of
Meaningful Discussions
The protester argues that the evaluators failed to conduct
meaningful discussions with it by failing to advise it that they
considered its schedule to be overly aggressive. We agree.
When an agency engages in discussions with a vendor, the
discussions must be "meaningful," that is, sufficiently detailed
to lead the vendor into the areas of its quotation requiring
amplification or revision. Honeywell Tech. Solutions, Inc.,
B‑400771, B-400771.2, Jan. 27, 2009, 2009 CPD para. 49 at 10.
Here, we do not think that the request for a new schedule
reasonably conveyed to the protester that the evaluators viewed
its proposed schedule as too aggressive; given that a period of
over a year had elapsed between submission of the vendors'
initial quotations and submission of their final quotations, we
think that vendors could reasonably have understood the request
to be nothing more than a request for updated information. We
note in this connection that the evaluators furnished precisely
the same request for a new schedule to Privasoft, and in its
case, the request was not intended to convey a concern over the
duration of the schedule. We think that by failing to advise the
protester in discussions that they considered its project
schedule to be too short, the evaluators failed to conduct
meaningful discussions with it. Moreover, we think under these
circumstances that the advice given at the debriefing did not
obviate the need to raise this concern when the agency reopened
discussions. (AINS, Inc.,
B-400760.4; B-400760.5, January 19, 2010) (pdf)
As discussed
above, on June 6, after various conference calls regarding the
terms of the Velos license agreement, the contracting officer
prepared a marked up version of the document that reflected the
areas where the agency and Velos had agreed upon the terms of
the special license agreement for the software. See AR, Tab 33,
Email from Contracting Officer to Velos (June 6, 2008); Tr. at
323-28, 338. As indicated above, however, the contracting
officer, in his award determination, found the Velos license
agreement submitted with its July 7 final proposal revision was
unacceptable because the language containing paragraph 2.1
(quoted above) conflicted with the RFP requirements that the
agency be granted a perpetual use license to distribute and use
the software without limits within the boundaries of the NCI
Clinical Research Enterprise. The record evidences that
paragraph 2.1 of the license submitted with Velos's final
proposal revision is the exact language that Velos and the
contracting officer agreed was acceptable after lengthy
discussions. Tr. at 323‑28; compare AR, Tab 33, Velos's Final
Proposal Revision (July 7, 2008), Special License Agreement)
(also designated Hearing exh. No. 3) with Hearing exh. No. 15,
Marked Up Velos License Prepared by Contracting Officer (June 6,
2008).
As to Velos's refusal to agree to a provision stating that "any
conflict between the terms of this Agreement, and the Contract
or applicable Federal law of regulation, shall be resolved by
the terms of the Contract or applicable Federal Law or
Regulation," Velos asserts that this was a matter discussed
earlier in the negotiations. Velos's Post-Hearing Comments at
10. According to Velos, this matter was resolved by including
the following language defining "Contract" in the software
license and agreeing to include the license in Attachment J-1 to
the contract:
"Contract" shall mean Contract No. 1406-04-08-CT-20201,
executed by and between the Parties hereto on June XX, 2008.
This Special License Agreement shall be Attachment J-1 to the
Contract and shall be incorporated by reference into the
Contract at Section J.
AR, Tab 33, Velos's Final Proposal Revision (July 7, 2008),
Special License Agreement), Definitions, at 1. Velos explains
that under the contract's order of precedence clause,
incorporating the license in Attachment J would subordinate it
to the rest of the contract. Velos Post‑Hearing Comments at 10;
see FAR sect. 52.215-8 (incorporated by the RFP at 38). As
argued by Velos, the record shows that the identical provision
defining "Contract" included in the earlier markup that Velos
and the contracting officer agreed was acceptable to the parties
was contained in the final proposal revision. See Tr. at 329-30;
compare Tab 33, Velos's Final Proposal Revision (July 7, 2008),
Special License Agreement) (also designated Hearing exh. No. 3)
with Hearing exh. No. 15, Marked Up Velos License Prepared by
Contracting Officer (June 6, 2008).
The problems the contracting officer found with the language in
Schedule B are based solely upon the problems that he now has
with paragraph 2.1 of the license and not the Schedule B
language per se. See AR, Tab 51, Award Summary, at 15. In fact,
at the hearing, the contracting officer admitted that he may
well have prepared the Schedule B language in question. Tr. at
352.
As to the escrow agreement, the record shows that this agreement
was not required by the RFP and was only included at the request
of the agency. See Contracting Officer's Statement at 12. The
contracting officer also testified that he never advised Velos
during the negotiations that there was a problem with the
proposed terms of Velos's escrow provision. Tr. at 350.
The agency asserts that there was no agreement on the terms of
the Velos license. Hearing exh. No. 16, Statement of Contracting
Officer (Oct. 31, 2008). In support of this assertion the agency
references a string of emails that occurred after June 6,
culminating in the June 27 email closing negotiation because of
numerous unresolved issues and advising that the competition
would be reopened. Id. The agency also references the request
for final proposal revisions (quoted above) and an email in
response to a question submitted after the request for final
proposal revisions that advised offerors to be aware that
licenses that were inconsistent with federal law, regulation, or
the solicitation requirements might result in the proposal being
eliminated. AR, Tab 37, Request for Final Proposal Revisions
(June 27, 2008); Hearing Exh. No. 13, Email from Contracting
Officer (July 2, 2008). In fact, Velos agrees that there was no
final agreement on the terms of its license when the
negotiations were closed. Velos's Post Hearing Comments at 6.
However, there is no evidence in the record that the contracting
officer ever specifically or even generally told Velos that the
previously agreed-upon language in its license agreement in the
"Grant of License" paragraph and in the "Contracts" definition
was considered unacceptable by the agency. Because the reasons
provided by the contracting officer in determining that the
Velos license was unacceptable are based upon the precise
language that Velos and the agency had found acceptable, and
because the agency had not advised Velos that this language was
no longer acceptable, we find that Velos was prejudicially
misled in submitting its final proposal revision that included
the agreed-upon language. We sustain the protest on this basis.
(Velos, Inc.; OmniComm Systems, Inc.;
PercipEnz Technologies, Inc., B-400500; B-400500.2;
B-400500.3; B-400500.4; B-400500.5; B-400500.6; B-400500.7,
November 28, 2008) (pdf)
Clark/Caddell
also argues that the agency failed to engage in meaningful
discussions regarding the performance capability evaluation
factor issue in that the agency asked misleading questions and
failed to provide meaningful responses. Specifically, the
protester contends that the agency did not provide meaningful
guidance to remedy the purported discrepancy between the
protester's CLIN schedule and its summary schedule.
Discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror's
proposal that could reasonably be addressed in a manner to
materially enhance the offeror's potential for receiving award.
PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Agencies are not required to "spoon-feed" an offeror during
discussions; agencies need only lead offerors into the areas of
their proposals that require amplification. LaBarge Elecs.,
B-266210, Feb. 9, 1996, 96-1 CPD para. 58 at 6.
As a preliminary matter, we recognize that the first IFN
erroneously directed Clark/Caddel to confirm the correct number
of days proposed for construction duration, as opposed to
contract duration. On the other hand, the words of the schedule
were clear, i.e., the CLIN entry (identified in the discussion
question) was preceded by the words "Contract Duration in
Calendar Days After the Notice to Proceed is received." RFP at
1.
That said, we think that by holding two rounds of discussions,
the agency guidance was ultimately sufficient to put the
protester on notice that the agency wanted the CLIN schedule to
include the total contract duration. As discussed above, the
agency's concerns that the protester's summary schedule in its
technical proposal for contract duration was different from the
enforceable contract duration listed in the CLIN schedule was
reasonable, especially given the liquidated damages provisions
of the RFP.
Furthermore, we note evidence in the record that suggests the
protester understood the agency's concerns. In a declaration
submitted by a representative of Clark/Caddell describing his
conversation with the contract specialist on September 18, the
representative stated that he asked the contract specialist "how
Clark/Caddell could commit to a fixed duration when Clark/Caddell
had no control over the actions of others." Clark/Caddell
Response to Agency Dismissal Request, Nov. 2, 2009, Exh. 10, at
2. The Clark/Caddell official explained that his "was an attempt
to get [the contract specialist] to understand that the longest
fixed duration in the solicitation is the 450-day duration for
construction, which would be the only reasonable and enforceable
entry on the CLIN Schedule." Id. Thus, it appears that the
protester was concerned about being bound to an overall contract
duration period as opposed to the construction duration period.
In conclusion, we see no support for the protester's arguments
that the discussions here were misleading.
The protest is denied. (Clark/Caddell
Joint Venture, B-402055, January 7, 2010) (pdf)
In its revised
proposal, TMM provided a revised drawing of its plan and a chart
that compared the proposed size of TMM’s rooms with that
required by the SFO. TMM’s chart showed that a number of TMM’s
proposed rooms were smaller than that specified by the SFO.
TMM’s Revised Proposal, Room Size Chart. With regard to
renovations to its existing building, TMM informed VA that
“[o]ther than painting, we do not believe there will be many
renovations in the existing space.” TMM also did not propose to
widen the 5-foot corridor, but did offer that “[i]f the VA wants
all the fifty doors to be enlarged from 36” doors to 42” doors,
the cost would be an additional $50,000 ($1,000 per door).” AR,
Tab 4, TMM Revised Proposal, at 2.
VA determined that TMM’s revised proposal did not reflect the
best value to the government, although TMM offered the lowest
evaluated price of $4,790,436. Specifically, VA noted that TMM
failed to meet the contract requirements for corridor width,
room square footage, and TMM “would only [be] making minor
renovations (painting) to the existing . . . space.”[3] AR, Tab
6, Price Negotiation Memorandum, at 11. In contrast, the agency
found that Alpine’s proposal at an evaluated price of $5,215,654
offered “the best proposed” layout for the space, meeting the
specified room sizes. Id. at 10. Award was made to Alpine, and
this protest followed.
TMM complains that VA did not conduct meaningful discussions
with the firm. Specifically, TMM argues that the agency’s
request that TMM “clarify” its room sizes was inadequate to put
the firm on notice that the agency had found TMM’s room sizes to
be a deficiency. We disagree.
Discussions, when conducted, must be meaningful; that is,
discussions may not mislead offerors and must identify
deficiencies and significant weaknesses in each offeror’s
proposal that could reasonably be addressed in a manner to
materially enhance the offeror’s potential for receiving award.
PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Here, we find that VA conducted meaningful discussions with TMM.
Specifically, VA informed TMM that it should “clarify” its room
sizes “in accordance with Schedule A.” This request should have
informed TMM of the agency’s concern under the technical quality
evaluation factor that TMM had not demonstrated “how they are
going to meet the identified space and square footage
requirements and room build‑out details in Schedule A.” See SFO
at 17. Although TMM believes that the agency should have been
more specific about its concerns, an agency is not required to
“spoon-feed” an offeror during discussions, but need only lead
the offeror into the areas of its proposal that requires
amplification. LaBarge Elecs., B-266210, Feb. 9, 1996, 96-1 CPD
para. 58 at 6.
TMM also appears to argue that VA’s discussions were not
meaningful because the agency did not inform TMM that the agency
viewed the firm’s proposed build-out plans to be inadequate. The
record indicates that TMM was also led into this area of its
proposal that required amplification. In any event, the
protester fails to show that it was prejudiced. Competitive
prejudice is an essential element of a viable protest; where the
protester fails to demonstrate that, but for the agency’s
actions, it would have had a substantial chance of receiving the
award, there is no basis for finding prejudice, and our Office
will not sustain the protest. Trauma Serv. Group, B‑254674.2,
Mar. 14, 1994, 94-1 CPD para. 199 at 6; see Statistica, Inc. v.
Christopher, 102 F.3d 1577 (Fed. Cir. 1996). TMM does not state
that, had it been notified of the agency’s concerns in this
regard, it would have offered any renovations to its space or
otherwise modified its proposal in any way. (TMM
Investments, Ltd., B-402016, December 23, 2009) (pdf)
Argon maintains that any inadequacy of the MTBOMF1
information it provided was the result of its being misled by
the agency regarding its MTBF information during discussions.
Specifically, Argon asserts that, because the agency did not
object to Argon’s MTBF data (provided in its response to the
initial discussion questions) being based on performance of its
CPS at 55C, it assumed that it could also present its MTBOMF
data based on 55C.
This argument is without merit. Discussions, when held, must be
meaningful; that is, they must lead offerors into those areas of
their proposals requiring amplification or revision, and may not
prejudicially mislead the offeror. American States Utilities
Servs., Inc., B-291307.3, June 30, 2004, 2004 CPD para. 150 at
6-7. However, agencies are not required to engage in successive
rounds of discussions until all proposal defects have been
corrected, nor are agencies required to reiterate concerns that
were not alleviated by a firm’s proposal revisions. Id. Where an
agency engages in initial discussions that lead an offeror to
revise its proposal, the agency’s subsequent silence in
connection with those proposal revisions during a subsequent
round of discussions cannot reasonably be understood as an
indication that the agency determined that the initial weakness
or deficiency was cured. Id.
Here, under the circumstances, there was no reasonable basis for
Argon to interpret the agency’s silence regarding the MTBF data
as a waiver of the plainly stated RFP requirements regarding
MTBOMF. See American States Utilities Servs., Inc., supra.
Simply stated, since the RFP clearly required MTBOMF information
to be presented in terms of a particular temperature, and the
RFP was not amended in this regard, Argon was required to
provide the information in those terms. To the extent Argon
chose to rely on its impressions from the agency’s silence
instead of complying with the RFP’s clear requirements, it did
so at its peril.
(Argon ST, Inc., B-401387, August
6, 2009) (pdf)
---------------------------
1 mean time between operation mission failure.
Discussions
AAA next argues that the Forest Service never advised the
company that its dressing area drainage was insufficient, and
therefore the agency failed to conduct meaningful discussions
regarding this perceived deficiency in its units. Protest at 15.
In negotiated procurements, contracting agencies generally must
conduct discussions with all offerors whose proposals are within
the competitive range. Federal Acquisition Regulation sect.
15.306(d)(1). Agencies are not required to afford offerors
all-encompassing discussions. Reflectone Training Sys., Inc.;
Hernandez Eng'g Inc., B-261224; B-261224.2, Aug. 30, 1995, 95-2
CPD para. 95 at 10. Although discussions must be meaningful,
leading an offeror into the areas of its proposal requiring
amplification or revision, the agency is not required to
"spoon-feed" an offeror as to each and every item that could be
revised or addressed to improve its proposal. Comprehensive
Health Serv., Inc., B-310553, Dec. 27, 2007, 2008 CPD para. 9 at
7.
Here, as noted above, the agency conducted oral and written
discussions with AAA, during which it noted the apparent
problems with drainage in the dressing area. In the handwritten
notes attached to the May 17 discussion letter, the Forest
Service expressed a "concern that [the] dressing area does not
have the ability to contain all gray water" and that the units
"may have a drainage issue." AR at 448 (AAA Discussion Letter
Notes at 1). As evidenced by the record here, the agency clearly
communicated its concerns that the dressing area drainage was
deficient. Also, it is clear from the protester's cover
letter--discussed in greater detail below--that it was aware of
these issues from the discussions. AR at 455-56 (AAA's Cover
Letter to its Final Proposal, May 29, 2008 at 2-3). Therefore,
we deny AAA's contention that discussions in this area were
inadequate. (AAA Mobile
Showers, Inc., B-311420.2, March 27, 2009) (pdf)
Lack of
Meaningful Discussions
Honeywell protests that the agency failed to conduct meaningful
discussions by failing to raise the one technical weakness it
found in Honeywell's FPR.
As set forth above, the RFP contained four RTOs that offerors
were to address in their technical proposals, either by the
submission of a TIP and cost proposal (RTOs #1-3) or a study
paper (RTO #4). RTO #1 concerned a new space-to-ground link
terminal (SGLT) at the White Sands Complex, New Mexico. The RFP
informed offerors that as part of an effort to ensure adequate
SN grounds systems resources were available, a project to
develop a new SGLT was being initiated. The stated task
requirement was for the contractor to complete the first phase
of the new SGLT project, including planning, definition of the
architecture, operations concepts, requirements, external
interfaces, and preliminary design. RFP, RTO #1, at 01245. The
solicitation also informed offerors that a TIP submission was to
include, at a minimum, the technical approach for the specific
requirements of the task, identification of potential technical
challenges, identification and mitigation of risks, and a
detailed description of any assumptions made in the response.
SOW at 00845.
Honeywell submitted its TIP for RTO #1 as part of its initial
proposal. AR, Tab 13, Honeywell Initial Proposal (Mission
Suitability), at 2021-47. The SEB rated Honeywell's initial
proposal, including RTO responses, excellent under the technical
approach subfactor, and identified a total of seven strengths
and two weaknesses supporting its determination. Id., Tab 40,
Initial SEB Report, at 09941-47. Both of the technical approach
weaknesses identified in Honeywell's initial proposal concerned
its RTO #1 TIP. The SEB first found that Honeywell's RTO #1
response did not identify certain specific noteworthy risks
associated with the completion of the RTO #1 requirement.
Second, the agency evaluators found that Honeywell's RTO #1 TIP
contained various questionable assumptions. Id. at 09946-47. It
is the second of the identified weaknesses that is the subject
of Honeywell's protest here.
NASA then conducted discussions with Honeywell and informed the
offeror of both identified technical approach weaknesses. With
regard to the second weakness, the agency stated, "Honeywell's
RTO #1 response contains the following questionable assumptions,
which require clarification and/or substantiation, or should be
corrected and their impact on the RTO be addressed," and then
identified the specific assumptions the agency evaluators had
questioned. Id., Tab 43, NASA Discussions with Honeywell, at
10143.
Honeywell addressed the agency's discussion topics as part of
its FPR. The offeror's FPR included a "highlighted" version that
specifically indicated those portions of its revised proposal
that had been changed (either added or deleted). The SEB
considered Honeywell's discussion responses as part of the
evaluation of the offeror's revised proposal, and determined
that Honeywell had remedied both originally-identified
weaknesses. Specifically, with respect to the second
weakness--that Honeywell's RTO #1 TIP contained various
questionable assumptions--the SEB found the offeror's revised
proposal had adequately addressed each assumption. Id., Tab 80,
Final SEB Report, at 23649-50.
The SEB determined, however, that Honeywell's FPR contained a
new weakness, namely that the offeror's response demonstrated an
inadequate understanding of the requirements analysis, trade
study execution and analysis, and requirements identification
aspects of the systems engineering process. Id. at 23647-48.
Each of the findings on which the SEB based its determination of
the new weakness in Honeywell's FPR resulted from the new (i.e.,
highlighted) sections in the offeror's revised proposal. Id.,
Tab 46, Honeywell's FPR, at 10663-80. For example, Honeywell's
assertion that the candidate architecture could be interfaced
with the legacy antenna interconnect mechanisms was a new
section in the offeror's revised proposal, as was Honeywell's
assertion that a to-be-completed upgrade to the White Sands
Complex local area network would have sufficient margin to
support the requirements for the new SGLT. Id. at 10674-75,
10680.
Although discussions must address deficiencies and significant
weaknesses identified in proposals, the precise content of
discussions is largely a matter of the contracting officer's
judgment. See FAR sect. 15.306(d)(3); American States Utils.
Servs., Inc., B-291307.3, June 30, 2004, 2004 CPD para. 150 at
6. When an agency engages in discussions with an offeror, the
discussions must be "meaningful," that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Hanford Envtl. Health
Found., B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD para. 164
at 8. Where proposal defects are first introduced either in a
response to discussions or in a post-discussion proposal
revision, an agency has no duty to reopen discussions or conduct
additional rounds of discussions. L-3 Commc'ns Corp., BT Fuze
Prods. Div., B-299227, B-299227.2, Mar. 14, 2007, 2007 CPD para.
83 at 19; Cube-All Star Servs. Joint Venture, B-291903, Apr. 30,
2003, 2003 CPD para. 145 at 10-11.
We conclude that NASA's discussions with Honeywell were
meaningful. As set forth above, the discussions expressly
informed Honeywell of the specific weaknesses that the SEB had
identified in the offeror's initial proposal. Further, the
record clearly reflects that the specific significant weakness
which Honeywell claims that NASA failed to mention in
discussions was first introduced in Honeywell's post-discussions
FPR and was not part of its initial proposal. As a result, NASA
had no obligation to conduct additional rounds of discussions in
order to permit the offeror to address this matter. See L-3
Commc'ns Corp., BT Fuze Prods. Div., supra. (Honeywell
Technology Solutions, Inc., B-400771; B-400771.2, January
27, 2009) (pdf)
As noted above, if the agency in accordance with FAR sect.
25.502 determines that Tiger’s vehicles are TAA-compliant, then
the agency must evaluate Tiger’s quotation, including whether
Tiger’s quoted price is fair and reasonable. We recognize that
the agency determined that Tiger’s price was “exorbitantly
unreasonable” and found Tiger ineligible for award on this
basis. AR, Tab 56, Price Negotiation Memorandum, at 13. However,
the record also confirms that the agency failed to raise this
issue during discussions, even though it held numerous rounds of
discussions with the vendors and requested revised quotations
inviting vendors to reduce their price. Although the agency
asserts that “discussions were not intended” and were not held,
we find that the “numerous questions and clarifications” issued
to vendors followed by the agency’s request for “best and final
offers,” which included revisions to vendor’s prices,
constitutes discussions as contemplated by the FAR. AR, Tab 56,
Price Negotiation Memorandum, at 12; Contracting Officer’s
Statement at 9; Tr. at 173; see FAR sect. 15.306(d).
Although the solicitation here did not require the agency to
hold discussions with vendors, once an agency chooses to do so,
as occurred here, the discussions are required to be meaningful;
that is, the agency is required to raise with a vendor
significant weaknesses and deficiencies identified in the
vendor’s quotation. FAR sect. 15.306(d)(3). Discussions cannot
be meaningful if a vendor is not advised of the significant
weaknesses or deficiencies that must be addressed in order for
its quotation to be in line for award. DevTech Sys., Inc.,
B-284860.2, Dec. 20, 2000, 2001 CPD para. 11 at 4. There is no
doubt that Tiger’s quoted price was viewed by the agency as a
deficiency, as Tiger’s price was the sole basis for the agency’s
finding that the quotation was ineligible for award. In holding
discussions with Tiger, but not raising with the firm the
concern that Tiger’s price was unreasonable, the agency did not
provide Tiger with meaningful discussions. DevTech Sys., Inc.,
supra, at 4-5.
We find a reasonable possibility that Tiger was prejudiced by
the agency’s failure to hold discussions concerning the
reasonableness of the firm’s price. Had the agency raised its
concern with Tiger, then Tiger would have had the opportunity to
explain why its price was fair and reasonable or to reduce it,
such that the agency may have ultimately found the price to be
fair and reasonable and, thus, Tiger’s quotation would have been
in line for award. Coupled with the agency’s failure to properly
evaluate TAA eligibility, we find that the agency’s failure to
hold meaningful discussions prejudiced the protester, and we
sustain the protest on these bases. See Cogent Sys., Inc.,
B‑295990.4, B‑295990.5, Oct. 6, 2005, 2005 CPD para. 179 at
10-11. (Tiger Truck, LLC,
B-400685, January 14, 2009) (pdf)
Burchick complains that VA did not conduct meaningful
discussions with Burchick, given that VA did not apprise the
firm of, or provide it with the opportunity to address,
significant evaluated weaknesses in its technical proposal. The
protester contends that it could have resolved the agency’s
concerns with the firm’s proposal had the firm been provided
with discussions concerning its technical proposal.
VA argues that the scope and extent of discussions to be
conducted with offerors is “a matter of contracting officer
judgment” and that agencies are not required to discuss every
area in which a proposal can be improved. In this regard, VA
contends that the agency was not required to conduct discussions
with respect to Burchick’s technical proposal, given that the
contracting officer concluded that the firm could not have
materially improved its technical proposal. AR at 6-7.
We agree with VA that a procuring agency has considerable
discretion in determining whether and how to conduct discussions
in a negotiated procurement under Federal Acquisition Regulation
(FAR) Part 15. However, where, as here, discussions are
conducted, they must at a minimum identify deficiencies and
significant weaknesses in the proposals of each competitive
range offeror. FAR sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12; PAI
Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Discussions must be “meaningful,” that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B‑298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12;
Symplicity Corp., B-297060, Nov. 8, 2005, 2005 CPD para. 203 at
8.
We find that VA did not conduct meaningful discussions with
Burchick, since the agency limited its discussions to the firm’s
cost proposal and did not identify any of the agency’s
significant concerns with Burchick’s technical proposal that
resulted in the firm’s proposal receiving only 50.8 points out
of 100 possible points.[6] In particular, the protester’s
proposal received only 22 of 40 available points under the past
performance factor, based upon the agency’s judgment that
Burchick had provided detailed information on only one relevant
project, where the solicitation requested a minimum of four
projects. Similarly, Burchick’s proposal received only 14.4 of
30 available points under the construction management factor,
based upon the agency’s conclusion that Burchick had failed to
identify a project manager and to detail its quality control
plan, as required by the RFP. Burchick’s proposal received no
points under the small business participation factor, because
the agency found that Burchick had essentially not provided the
required small business participation plan. Given the
significant reductions in Burchick’s technical point score
associated with these identified concerns, and the importance to
the agency of the omitted information, we find that these
concerns can only be considered to be significant weaknesses or
deficiencies, and that the agency’s failure to identify them
during discussions was inconsistent with its obligation to
conduct meaningful discussions.
We also do not agree with VA that Burchick could not have
materially improved its proposal if discussions were conducted
with the firm with respect to the evaluated concerns in its
technical proposal. The protester has explained that it could
have addressed each of the agency’s concerns that resulted in
Burchick’s technical proposal being downgraded. For example,
with respect to the evaluation of the firm’s past performance,
Burchick contends that it identified 37 other healthcare
projects in its technical proposal, which the protester could
have detailed if the firm had been asked in discussions.
Protester’s Comments at 4. With respect to the identity of its
project manager and to its proposed quality control plan under
the construction management factor, Burchick states that, had it
received discussions, the firm would have clarified the identity
of its project manager and provided further detail with respect
to its quality control plan. Id. at 6-7. With respect to the
small business participation factor, Burchick states that it
could have further explained the firm’s proposed teaming
relationship with a service-disabled veteran-owned small
business.
In sum, we find that VA failed to conduct meaningful discussions
with Burchick, because the agency failed to identify significant
weaknesses or deficiencies in the firm’s technical proposal. We
also find a reasonable possibility that Burchick was prejudiced
by the agency’s failure to conduct meaningful discussions, given
that Burchick offered the lowest price and could have addressed
these concerns in its technical proposal such that it may have
been found to offer the best value to the agency. (Burchick
Construction Company, B-400342, October 6, 2008) (pdf)
The record
demonstrates that the agency, in conducting discussions with the
protester, forwarded a detailed list of discussion questions to
IVI, and answered a number of questions from IVI regarding the
discussion questions. Contrary to the protester’s assertion, we
find based upon our review of the record that the agency’s
discussions were meaningful.
For example, IVI argues that the agency “failed to conduct
meaningful discussions regarding software engineering.”
Protester’s Comments at 21. In this regard, the protester first
points that the agency’s initial technical evaluation noted as a
weakness under the technical approach criterion to the technical
factor that
[t]he Software Engineering section of this proposal is not
discussed in detail. This could lead to major deficiencies in
the design, implementation, and testing of the suggested
software development tasks.
AR, Tab 3, Initial Technical Evaluation, at 26. The protester
next points out that the relevant discussion question it
received was as follows:
The software section of the proposal is not discussed in
detail. This could lead to major deficiencies in the design,
implementation, and testing of the offeror’s proposed changes
in software.
AR, Tab 5, IVI Discussion Questions, at 5. The protester argues
that “[s]oftware engineering is a different concern than
software in general,” and that because of the discussion
question IVI received from the agency, “IVI was not informed of
the potential significant weakness in its software engineering.”
Protester’s Comments at 21.
The agency explains that the reference in the initial evaluation
to “software engineering” was a simple error, given that the
neither the RFP nor IVI’s proposal contained “software
engineering” sections, but rather, both included sections
addressing software maintenance and security. Agency Supp.
Report at 10; RFP amend. 6, at 5-6. The agency explains that the
contracting officer, in preparing IVI’s discussion questions,
deleted the discussion question’s reference to “software
engineering” in order to correct this error, and that IVI was in
fact properly informed during discussions of the agency’s
perceived weaknesses in the software section of IVI’s proposal.
Agency Supp. Report at 10.
Although IVI continues to complain “that the agency misled IVI
from addressing the evaluators’ actual concern: software
engineering,” and that because of this, the “evaluators may have
downgraded IVI for failing to answer a question that was not
asked,” see Protester’s Supp. Comments at 12, the protester does
not explain, and we cannot see, how this could possibly be the
case, given that neither the RFP nor IVI’s proposal included a
“software engineering” section, and given that there is no
evidence in the agency’s evaluation of FPRs that IVI’s FPR was
downgraded for failing to address “software engineering.”
As another example, the protester argues that the agency “failed
to conduct meaningful discussions regarding the biweekly
literature surveillance memoranda.” Protester’s Comments at 4;
Protester’s Supp. Comments at 13. The record reflects that the
agency noted as a “strength” in IVI’s proposal that it provided
“a clear discussion of how the biweekly literature reports will
be organized,” and that the “[o]rganization of [the biweekly
literature reports appears to be relevant to the aims of the . .
. staff.” AR, Tab 3, Initial Evaluation, at 25. The agency also
commented while noting the various weaknesses in IVI’s initial
proposal that “[b]iweekly literature surveillance memos would be
helpful in judging the potential quality of the data output.”
Id. at 26.
In response to the protester’s complaint that it “was not
informed during discussions that the agency found IVI’s proposed
biweekly literature surveillance memoranda problematic,”
Protester’s Supp. Comments at 13, the agency explains that it
did not raise this evaluated weakness with IVI during
discussions given its overall view that “IVI’s proposal with
respect to biweekly literature surveillance reports was at least
as much a strength as it was a weakness.” Agency Supp. Report at
13. The agency concludes that the concern expressed in its
initial evaluation regarding IVI’s biweekly literature
surveillance memoranda was not significant, and that under the
circumstances, did not have to be raised with IVI during
discussions. Id. We agree.
As stated previously, the record reflects that the agency had
extensive discussions with IVI regarding its proposal, and that
the agency’s concerns regarding this aspect of IVI’s proposal
were insignificant given the other evaluated weaknesses in IVI’s
proposal, as well as the fact that overall this aspect of IVI’s
proposal was found to constitute a strength. Additionally, IVI
has not pointed to, and we cannot find, any indication in the
evaluation of IVI’s FPR, or source selection documents, that
this aspect of IVI’s proposal was considered a weakness or had
any effect on either IVI’s overall rating or the source
selection. In light of this, and the fact that agency’s are not
required to identify other than deficiencies and significant
weaknesses in each offeror’s proposal, or to conduct discussions
that are all encompassing, we cannot find the agency’s conduct
here to be objectionable. See PAI Corp., supra. (Information
Ventures, Inc., B-299361.2; B-299361.3, October 1, 2008) (pdf)
Turning to
NAVSEA’s evaluation of the cost proposal submitted by MCT JV,
while we find that the agency had reasonable concerns about MCT
JV’s allocation of labor hours in its cost proposal, we conclude
that the agency’s discussions regarding this matter were not
meaningful. Specifically, the record reflects a wide disparity
between MCT JV’s proposed allocation of labor hours in its
technical proposal and the allocation of labor hours in its cost
proposal. As noted above, in its technical proposal MCT JV
allocated [Deleted] percent of the labor hours to MHI, [Deleted]
percent to Colonna’s, [Deleted] percent to Tecnico, and the
remaining [Deleted] percent to other specialty subcontractors.
NAVSEA, however, determined that MCT JV’s final cost proposal
reflected an allocation of [Deleted] percent of the total labor
hours to MHI, [Deleted] percent to Colonna’s, [Deleted] percent
to Tecnico, and [Deleted] percent to other subcontractors. The
[Deleted] percent allocation to other subcontractors had the
effect of significantly reducing MCT JV’s estimated cost since
MCT JV proposed a significantly lower labor rate for those
subcontractors.
In its protest, MCT JV specifically complains that NAVSEA’s
reallocation of its labor hours under item 999-99-999--where the
disparity between MCT-JV’s allocation of labor hours between its
technical proposal and cost proposal is even greater--was
unreasonable. As noted above, under item 999-99-999, MCT JV
allocated only [Deleted] percent of the work to its partners and
[Deleted] percent to “other subcontractors.” Because item
999-99-999 represented approximately [Deleted] percent of the
total projected labor hours used to estimate MCT JV’s total
cost, by allocating [Deleted] percent of these labor hours to a
category of other subcontractors with a significantly lower
labor rate, MCT JV was able to significantly reduce its
estimated cost. This extensive reliance on subcontractors for
the purpose of calculating its total estimated cost, however,
was clearly at odds with MCT JV’s technical proposal, which
indicated that MCT JV would allocate a much smaller percentage
[Deleted] of the work to specialty subcontractors.
NAVSEA was thus presented with a situation similar to the one it
faced in Metro Mach. Corp., B-297879.2, May 3, 2006, 2006 CPD
para. 80, where an offeror attempted to reduce its total
estimated cost by allocating all of its labor hours for notional
work items to its team member with the lowest labor rate,
notwithstanding the fact that the entire team would be
performing the actual work under the contract. In that case, we
held that the Navy’s cost realism evaluation was unreasonable
because the Navy accepted the proposed allocation without
further question and thus failed to consider the impact of the
team members’ higher rates in determining the offeror’s probable
cost of performance under the contract. In response to our
decision in Metro, NAVSEA included item 999-99-999 to capture
the total labor effort of a typical availability when combined
with the specific notional work items identified in the RFP, and
instructed offerors to ensure that their labor hour allocations
for this item were consistent with their proposed technical
approaches. AR at 23-24; RFP at 124-25.
While we commend NAVSEA’s efforts to adjust MCT JV’s allocation
of labor hours to reflect a labor mix that was more consistent
with its technical proposal and MCT JV’s joint venture
agreement, and therefore reflective of a more realistic total
probable cost for MCT JV, given our conclusion, discussed below,
that NAVSEA’s discussions with MCT JV regarding its concerns in
this regard were fundamentally flawed, any allegation regarding
the propriety of NAVSEA’s reallocation is academic at this
juncture.
It is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful, that is,
sufficiently detailed so as to lead an offeror into the areas of
its proposal requiring amplification or revision. Smiths
Detection, Inc., B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD
para. 5 at 12; Symplicity Corp., B‑297060, Nov. 8, 2005, 2005
CPD para. 203 at 8. Further, an agency may not mislead an
offeror--through the framing of a discussion question or
otherwise--into responding in a manner that does not address the
agency’s concerns, or misinform the offeror concerning a problem
with its proposal or about the government’s requirements.
Multimax, Inc., et al., B-298249.6 et al., Oct. 24, 2006, 2006
CPD para. 165 at 12; Metro Mach. Corp., B‑281872 et al., Apr.
22, 1999, 99-1 CPD para. 101 at 6.
Here, the record reflects that with respect to the allocation of
labor hours in MCT JV’s cost proposal, NAVSEA asked MCT JV to
explain why the allocation was inconsistent with its “resource
agreement.” As noted above, MCT JV responded that the resource
agreement did not apply to its proposal; rather, it was an
agreement among MHI, Colonna’s, and Tecnico relating to a
separate proposal submitted by MHI as the prime contractor. The
record further reflects that the CAP accepted MCT JV’s response,
agreeing that the resource agreement did not apply to the joint
venture. Thus, by questioning MCT JV’s allocation of labor hours
in its cost proposal solely by reference to a resource agreement
that by its terms did not apply to this proposal, NAVSEA never
conveyed to MCT JV its actual concern--that the labor hour
allocation in the cost proposal appeared to be inconsistent with
its technical proposal and joint venture agreement. Accordingly,
we find that the agency’s discussions in this regard were
misleading and therefore not meaningful.
(MCT JV, B-311245.2; B-311245.4,
May 16, 2008) (pdf)
Discussions, when
conducted, must be meaningful, that is, they may not be
misleading and must identify proposal deficiencies and
significant weaknesses that could reasonably be addressed in a
manner to materially enhance the offeror’s potential for
receiving award. PAI Corp., B-298349, Aug. 18, 2006, 2006 CPD
para. 124 at 8. While an agency generally need only lead an
offeror into the general areas of concern about its proposal,
the agency must impart during discussions sufficient information
to afford the offeror a fair and reasonable opportunity to
identify and correct deficiencies, excesses, or mistakes in its
proposal. Advanced Sci., Inc., B‑259569.3, July 3, 1995, 95-2
CPD para. 52; Aydin Computer and Monitor Div., Aydin Corp.,
B-249539, Dec. 2, 1992, 93-1 CPD para. 135.
The discussions here were not meaningful. While the record shows
that the agency indeed advised JPDT that it could improve its
technical score by providing amenities within its offered
building, this information was conveyed, not to identify
deficiencies in JPDT’s offer, but as part of the agency’s
general advice that every offeror received. This general advice
amounted to no more than a restatement of the SFO’s evaluation
criteria. It did not reasonably apprise JPDT that the agency had
found its proposal to contain specific significant weaknesses
regarding access to amenities, including the proximity and
number of amenities generally, the proximity and number of fast
food restaurants, and the variety, quantity, and proximity of
table service restaurants. See Integrity Int’l Sec. Sys., Inc.,
B‑261226, Sept. 1, 1995, 95‑2 CPD para. 98 at 8 (general
boilerplate-type reminder that was provided to all offerors
during discussions was insufficient to provide notice of
protester’s specific deficiency).
Further, while the record also supports the agency’s claim that
it informed JPDT that it was unable to verify the existence of
two of the identified restaurants and the identified sports
club, this very specific information likewise fell short of
advising JPDT that its proposed amenities were a concern
overall. Indeed, by providing its concerns regarding particular
restaurants and a particular fitness facility without indicating
that it considered JPDT’s offer to have significant weaknesses
regarding the proximity and number of amenities generally, the
proximity and number of fast food restaurants, and the variety,
quantity, and proximity of table service restaurants, we think
GSA led JPDT reasonably to believe that GSA’s concerns were
limited to those particular establishments and were not broader
in nature. See Spherix, Inc., B‑294572, B-294572.2, Dec. 1,
2004, 2005 CPD para. 3 at 14 (agency failed to conduct
meaningful discussions where it determined that offeror’s entire
quality control plan was a significant weakness, but identified
only two specific aspects of the quality control plan in
discussions). We conclude that the agency’s discussions failed
to provide JPDT with sufficient information to afford it a fair
and reasonable opportunity to identify and correct the evaluated
significant weaknesses in its offer. (New
Jersey & H Street, LLC, B-311314.3, June 30, 2008) (pdf),
(See Trammell Crow Company,
B-311314.2, June 20, 2008) (pdf)
It is a
fundamental precept of negotiated procurements that discussions,
when held, must be meaningful; that is, discussions may not
mislead offerors and must identify deficiencies and significant
weaknesses in each offeror’s proposal that could reasonably be
addressed in a manner to materially enhance the offeror’s
potential for receiving award. Federal Acquisition Regulation
(FAR) sect. 15.306(d); Lockheed Martin Corp., B-293679 et al.,
May 27, 2004, 2004 CPD para. 115 at 7. Based on our review of
the record, and for the reasons set forth below, we find that
the agency’s discussions with the protester were meaningful.
To the extent that ICRC argues that the agency was required to
consider its proposed costs unacceptable, and thus a proposal
deficiency, we note first that the contemporaneous evaluation
record indicates that the agency did not consider the matter to
be a proposal deficiency. Instead, the evaluators reached a
different conclusion. Specifically, the agency conducted a
detailed assessment of whether the number of hours identified
was reasonably related to ICRC’s approach to the sample task.
This assessment led the agency to conclude that the proposed
solution to the sample task was an acceptable one, but one that
involved a high number of labor hours. As a result, the agency
advised ICRC during discussions that the number of labor hours
proposed appeared high. Upon receipt of this information, ICRC
reduced its overall proposed labor hours, thereby altering its
proposed costs.
Our review of the record here has revealed nothing to lead us to
conclude that the agency’s assessment was unreasonable. In fact,
the cost realism analysis here fulfilled its purpose--i.e., it
examined whether the costs proposed by ICRC’s technical approach
were consistent with the firm’s likely actual cost of
performance. While the protester claims that its own proposed
costs were per se unreasonable, given the lower costs proposed
by the awardee, it has not shown that the cost realism analysis
produced an inaccurate measure of the likely cost of
implementing the company’s proposed technical solution.
Moreover, the record shows that the contracting officer
specifically noted in his source selection decision that the
significant variance in evaluated costs was directly
attributable to the significant differences in the technical
approaches adopted by the competing offerors.
Finally, the protester has not shown that the discussions were
misleading, or, in any way, inadequate. Where an offeror’s
proposed cost is high in comparison to competitors’ costs, the
agency may, but is not required to, inform the offeror that its
costs are not as competitive as those of its competitors during
discussions. See FAR sections 15.306(d)(3), (e)(3); SOS
Interpreting, Ltd., B-287477.2, May 16, 2001, 2001 CPD para. 84
at 3; see also Mechanical Equip. Co., Inc.; Highland Eng’g,
Inc.; Etnyre Int’l, Ltd.; Kara Aerospace, Inc., B-292789.2 et
al., Dec. 15, 2003, 2004 CPD para. 192 at 18; MarLaw-Arco MFPD
Mgmt., B-291875, Apr. 23, 2003, 2003 CPD para. 85 at 6. In sum,
since ICRC’s proposed costs were not evaluated as either
unreasonable or unrealistic, and since the agency was not
obligated to advise the company that its proposed costs were not
competitive, we conclude that the agency’s discussions with ICRC
were adequate. (Integrated
Concepts & Research Corporation, B-309803, October 15, 2007)
(pdf)
Boeing also complains that the agency conducted misleading
discussions with Boeing with respect to whether Boeing had fully
satisfied the KPP No. 7 objective, Net-Ready Capability. RFP,
SRD sect. 3.2.4.1.1; app. A, Net-Ready Capability KPP, at 3. The
KPP No. 7 objective provides that the offeror’s “system should
be capable of accomplishing all operational activities
identified in Table 5.” RFP, SRD, app. A, at 4. Table 5 of the
appendix identified a number of information exchange
requirements. Id. at 15-25.
Specifically, Boeing complains that at its mid-term briefing it
was informed of an uncertainty regarding the firm’s net ready
capability, see AR, Tab 129, Mid-Term Briefing to Boeing, at 77,
and that ultimately the firm responded to an EN concerning the
firm’s System Requirements Matrix and System Specification with
respect to complying with the SRD requirements for KPP No. 7.
See AR, Tab 210, Boeing Response to EN BOE-MC1-041. Boeing
believed that its EN response charted how its proposal met the
KPP No. 7 thresholds and objective in total, see Boeing’s
Comments at 29, and during the firm’s Pre-Final Proposal
Revision Briefing the Air Force informed Boeing that the firm
“met” both the KPP thresholds and the objective requirements for
KPP No. 7. See AR, Tab 135, Boeing’s Pre‑Final Proposal Revision
Briefing, at 57. Accordingly, Boeing made no further revisions
to its proposal in this area. Boeing’s Second Supplemental
Protest at 53. The Air Force, however, changed its evaluation
rating of this aspect of Boeing’s proposal to “partially met”
the KPP objective (the same rating that Northrop Grumman
received) without further notice to Boeing. Boeing contends that
the Air Force’s misleading discussions prevented the firm from
addressing the agency’s concerns with respect to this objective.
The Air Force does not dispute that it informed Boeing during
discussions that the firm had satisfied all of the thresholds
and the objective under KPP No. 7, but contends that at the time
it later determined that Boeing had not fully satisfied this
objective, discussions had already been closed. See Second
Supplemental COS at 77. The agency argues that, in any event, it
was under no obligation to inform Boeing of the changed
evaluation rating associated with this objective because the
objective “constituted trade space,” the absence of which would
not be a deficiency or weakness. Agency Memorandum of Law at
131.
We do not agree with the Air Force that the agency was
permitted, after informing Boeing that its proposal fully met
this objective, to change this evaluation conclusion without
affording Boeing the opportunity to satisfy this requirement. It
is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful, equitable, and
not misleading. See 10 U.S.C. sect. 2305(b)(4)(A)(i); AT&T
Corp., B-299542.3, B‑299542.4, Nov. 16, 2007, 2008 CPD para. 65
at 6. Here, by informing Boeing prior to the submission of the
firm’s final proposal revision that it satisfied all aspects of
KPP No. 7, the Air Force deprived the firm of the opportunity to
further address these particular requirements. See AT&T Corp.,
supra, at 12; see also Bank of Am., B‑287608, B-287608.2, July
26, 2001, 2001 CPD para. 137 at 13.
In contrast, the Air Force informed Northrop Grumman prior to
the submission of that firm’s final proposal revision that it
had only partially met this KPP objective, which permitted that
firm the opportunity to further address the KPP objective
requirements. See AR, Tab 205, Northrop Grumman’s Pre-Final
Proposal Revision Briefing, at 61. Moreover, Boeing submitted
its final submission addressing this KPP objective several
months prior to the pre-FPR briefing, and, as indicated above,
the agency actually reopened discussions on other subjects after
submission of the FPRs and obtained revised FPRs. Boeing’s
Protest at 66; Boeing’s Second Supplemental Protest at 53. In
short, the Air Force misled Boeing when the agency advised the
firm that it met this objective, but later determined that
Boeing did not fully meet this objective, and did not reopen
discussions with Boeing on this issue. The Air Force also
treated the firms unequally when it provided Northrop Grumman,
but not Boeing, with continued discussions on this same
objective. It is axiomatic that procuring agencies may not
conduct discussions in a manner that favors one offeror over
another. See FAR sect. 15.306(e)((1); Chemonics Int’l, Inc.,
B-282555, July 23, 1999, 99-2 CPD para. 61 at 8-9.
We also find a reasonable possibility that Boeing was prejudiced
by the Air Force’s misleading and unequal discussions, given the
greater weight that KPPs were supposed to receive in the
agency’s evaluation. In this regard, if Boeing had been
evaluated as fully satisfying this KPP objective, which was the
only KPP objective in the operations utility area, it could well
have been considered to be superior in this area to Northrop
Grumman, which was evaluated as only partially satisfying this
KPP objective.
(The
Boeing Company, B-311344; B-311344.3; B-311344.4;
B-311344.6; B-311344.7; B-311344.8; B-311344.10; B-311344.11,
June 18, 2008) (pdf)
The protester next argues that the EPA failed to conduct
meaningful discussions regarding several issues. The record,
however, does not support the protester’s allegations with
regard to any of the areas where it argues that the agency
failed to provide meaningful discussions. For example, IBM
argues that it was misled during discussions regarding page
limitations. Specifically, IBM claims that the agency advised
IBM that Volume 3 of its proposal exceeded the page limitation,
but orally advised that IBM could include additional pages
regarding its work breakdown structure (WBS) and integrated
master plan (IMP) in Volume 5, rather than Volume 3 of its
proposal--despite the fact that the RFP expressly required that
these matters be addressed in Volume 3. IBM contends that it
relied on the agency’s advice and placed those items in Volume
5, which, unlike Volume 3, had no page limitations. In
evaluating IBM’s proposal, the agency did not provide the WBS
and IMS documents to the evaluators because they were not
contained in Volume 3; the agency evaluators concluded that the
absence of a detailed WBS and IMP constituted a weakness in the
proposal. AR, Tab 41, SSD at 23. The protester argues that
the agency’s discussions here were misleading, and therefore not
consistent with the agency’s obligation to ensure that
discussions are meaningful. See L-3 Comm. Corp., BT Fuze Prods.
Div., B-299227, B-299227.2, Mar. 14, 2007, 2007 CPD para. __ at
18-19. The agency denies making such a statement, and notes that
such instructions would have been contrary to the RFP
instructions. Because the allegedly misleading agency statements
would have resulted in a material deviation from the
solicitation, namely the page limitation, the protester could
not reasonably rely on such oral advice--even if the record
demonstrated that the agency made such a statement, which it
does not. S3 LTD, B-287019.2 et al., Sept. 14, 2001, 2001 CPD
para. 165 at 6. Offerors cannot rely on oral modifications to an
RFP which are inconsistent with its written terms, absent a
written amendment to the RFP or written confirmation of the oral
modification. Id. This clear principle provides fairness to all
parties by ensuring that competitions are conducted under equal
terms, and protects both protesters and agencies from the kind
of credibility disputes raised here, as well as protecting the
integrity of the procurement process overall. Id. (IBM
Corporation, B-299504; B-299504.2, June 4, 2007) (pdf)
AT&T protests that the agency failed to adequately raise the
concerns it had regarding AT&T’s staffing plan during the
discussions held with the offeror. AT&T also contends that the
agency’s discussions were misleading, because SSA identified one
narrow area of the offeror’s staffing plan as lacking sufficient
detail and failed to inform AT&T of the true nature and breadth
of the evaluated weaknesses here. The protester argues that the
lack of meaningful discussions was prejudicial to it, since the
perceived weaknesses in AT&T’s staffing plan became a major
factor in the agency’s subsequent best value tradeoff
determination. Protest, Sept. 20, 2007, at 44-51.
When discussions are conducted, they must at a minimum identify
deficiencies and significant weaknesses in each
competitive-range offeror’s proposal. Federal Acquisition
Regulation (FAR) sect. 15.306(d)(3); Multimax, Inc., et al.,
B-298249.6 et al., Oct. 24, 2006, 2006 CPD para. 165 at 12; PAI
Corp., B-298349, Aug. 18, 2006, 2006 CPD para. 124 at 8.
Discussions must be “meaningful,” that is, sufficiently detailed
so as to lead an offeror into the areas of its proposal
requiring amplification or revision. Smiths Detection, Inc.,
B-298838, B-298838.2, Dec. 22, 2006, 2007 CPD para. 5 at 12;
Symplicity Corp., B-297060, Nov. 8, 2005, 2005 CPD para. 203 at
8. For example, discussions are not meaningful where the agency
fails to apprise an offeror that its staffing levels are viewed
as unreasonably low. Professional Servs. Group, Inc.,
B-274289.2, Dec. 19, 1996, 97-1 CPD para. 54 at 4. Further, an
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency’s concerns, or
misinform the offeror concerning a problem with its proposal or
about the government’s requirements. Multimax, Inc., et al.,
supra; Metro Mach. Corp., B-281872 et al., Apr. 22, 1999, 99-1
CPD para. 101 at 6.
(sections deleted)
In its report to our Office,
SSA argues that its actions here were proper for the following
reasons: (1) the weaknesses found by the agency in AT&T’s
staffing plan were not significant ones, so no discussions were
in fact required here; (2) the agency nevertheless conducted
meaningful discussions with AT&T regarding its staffing plan;
and (3) the agency was not required to re-open discussions with
AT&T simply because AT&T’s staffing plan subsequently became a
discriminator for source selection purposes. AR, Oct. 1, 2007,
at 1-5, AR, Nov. 2, 2007, at 1-6. As discussed in detail
below, we conclude that the agency’s actions were improper
because: (1) the agency’s initial technical evaluation regarded
AT&T’s staffing plan as a significant weakness; (2) the agency
failed to conduct meaningful discussions with AT&T regarding
this significant weakness; and (3) the agency’s substantial
reliance on AT&T’s staffing plan in its best value tradeoff
determination clearly demonstrates that the lack of meaningful
discussions here was prejudicial to AT&T.
As set forth above, the record reflects that the TET’s initial
evaluation of proposals identified two separate concerns with
AT&T’s proposed staffing plan. First, the evaluators found that
AT&T’s staffing appeared to be at minimal levels in relation to
the RFP’s requirements. Second, the TET also believed that
AT&T’s entire staffing plan lacked sufficient detail, as
exemplified by the offeror’s staffing for the VNOC and help-desk
personnel at the Durham and NCC locations. Moreover, the agency
evaluators considered AT&T’s staffing plan to be a significant
weakness, as evidenced by the initial evaluation report.
Specifically, in addition to stating that “[t]he proposed
staffing at current levels would be considered inconsistent with
the proposal implementation schedule without a clear
understanding of the support personnel,” the TET expressly found
that “[t]he risk of implementing a minimal staffing plan as
[AT&T] presented could jeopardize the success of the project.”
AR, Tab 13, Initial Technical Evaluation Report, app. 5,
Evaluation of Proposed Project Lifecycle Staffing Plans, at 7.
We think that when an agency finds, as it did here, that the
risk associated with a given aspect of an offeror’s proposal may
jeopardize the overall success of the project, this represents a
significant weakness. See FAR sect. 15.001 (a “significant
weakness” in an offeror’s proposal is a flaw that appreciably
increases the risk of unsuccessful contract performance). Given
this finding regarding the risk associated with AT&T’s staffing
plan, the fact that SSA did not expressly characterize the
staffing plan as a significant weakness is not controlling. See
Alliant Techsystems, Inc.; Olin Corp., B-260215.4, B-260215.5,
Aug. 4, 1995, 95-2 CPD para. 79 at 7-8. Accordingly, we conclude
that the agency was required to conduct discussions with AT&T
regarding its staffing plan. Further, while the record
shows that SSA did conduct discussions with AT&T regarding its
staffing plan, we think that these discussions were not
meaningful. As set forth above, the agency provided AT&T with
one discussion item regarding its staffing plan. This item
informed AT&T only of SSA’s concern that the staffing plan
lacked sufficient detail (“the personnel staffing charts do not
provide sufficient information to determine that the staffing
levels are consistent with AT&T’s proposed programmatic
methods,” AR, Tab 15, Discussions with AT&T, at 13-14), and
completely failed to mention the agency’s equal, if not greater,
independent concern that AT&T’s staffing levels were considered
too low. An agency’s belief that an offeror’s staffing levels
are too low is materially different from a concern that a
staffing plan lacks sufficient detail; the fact that both
involve staffing is not sufficient to conclude that the agency
here provided meaningful notice to AT&T as to the total scope of
its concern. See Andrew M. Slovak, B-253275.2, Nov. 2, 1993,
93-2 CPD para. 263 at 4 (discussions limited to a food menu’s
item cycle did not put offeror on notice of the agency’s
separate concern that the menu also failed to provide for
healthy food items). Moreover, the discussion item here
specified only one particular area of AT&T’s staffing plan as
lacking sufficient detail (“[s]pecifically, staffing levels for
VNOC and Help Desk problem intake,” id. at 14), when the
agency’s real concern was that AT&T’s entire staffing plan
lacked sufficient information. See Spherix, Inc., B-294572,
B-294572.2, Dec. 1, 2004, 2005 CPD para. 3 at 14 (agency failed
to conduct meaningful discussions when it determined that
offeror’s entire quality control plan was a significant
weakness, but identified only two specific aspects of the
quality control plan in discussions). In our view, not only was
AT&T inadequately advised of other areas of its staffing plan
that lacked sufficient detail, but the agency’s failure to
identify the scope of its concern may have misled the offeror
into believing that those areas did not require further
adjustment.[18] Also, unlike other identified management
approach weaknesses, the discussions here did not characterize
AT&T’s staffing plan as a significant weakness, or inform the
offeror of the agency’s belief that the risk associated with
AT&T’s minimal staffing plan could jeopardize the success of the
project. See AR, Tab 15, Agency Discussions with AT&T, at 8,
13-14. Under the circumstances here, we cannot conclude that
AT&T, reviewing the agency’s discussions in conjunction with the
material that it had submitted with its proposal, reasonably
could have recognized the total scope of the agency’s concerns
regarding both the staffing levels and the lack of detail in
AT&T’s entire staffing plan. The record also reflects that
AT&T was prejudiced by the lack of meaningful discussions
regarding its staffing plan. In its final evaluation report, the
TET found that AT&T’s staffing levels, while higher than those
proposed originally, were still “minimal and conservative,” and
the lack of detail in AT&T’s staffing plan (in areas other than
VNOC and Help desk, which AT&T’s FPR specifically addressed)
represented potential performance risks if AT&T was unable to
staff appropriately. Id., Tab 33, Final Technical Evaluation
Report, at 9, app. II, Evaluation of Proposal Project Lifecycle
Staffing Plans, at 6. The agency’s subsequent best value
tradeoff determination then went further, and characterized
AT&T’s staffing levels as the offeror’s “principal weakness and
area of risk,” since its staffing levels were “so low as to
potentially threaten the ability of the vendor to successfully
deliver the proposed solution in accordance with the
Government’s delivery schedule and to support the TSRP user
community across the contract term in a fully satisfactory
manner.” Id., Tab 35, Best Value Tradeoff Memorandum, at 22.
Quite simply, AT&T’s staffing plan, which the agency considered
to be a significant weakness from the time of the initial
evaluation, was a material factor in the agency’s source
selection determination. (AT&T
Corp., B-299542.3; B-299542.4, November 16, 2007) (pdf)
DRS maintains that the agency engaged in unequal discussions,
specifically, that it was given more exacting questions and was
required to provide far more detail in its responses than Onan.
In effect, DRS is arguing that it was given a greater level of
detail in its discussions than was given to Onan. We fail to see
how providing more detailed discussions to DRS was improper or
prejudicial to DRS. Discussions need not be identical; rather,
discussions are to be tailored to each offeror’s proposal.
Federal Acquisition Regulation sect. 15.306(d)(1), (e)(1);
PharmChem, Inc., B-291725.3 et al., July 22, 2003, 2003 CPD para.
148 at 6. We find no impropriety here. DRS also asserts
that its discussions were misleading. As noted, the agency
relaxed the solicitation’s requirements relating to the fuel
efficiency standards for the generator sets. The agency advised
both offerors of its intention to relax the specifications, and
requested comments relating to the revisions, by e-mail dated
October 18, 2006. AR, exh. 30. DRS commented by letter dated
October 23, stating that, in its view, the changes were
unnecessary because it could meet the original, more stringent,
standards. AR, exh. 31. Notwithstanding DRS’s position, the
agency revised the specifications on November 1. AR, exh. 32.
Thereafter, by letter of November 2, DRS requested that the Army
engage in discussions relating to the deficiencies identified in
its original phase II and III proposal. In response, the agency
provided DRS with two rounds of discussion questions, first by
letter dated November 3, and subsequently by letter dated
January 16, 2007. In both letters, the agency provided DRS with
detailed questions that had been developed by the evaluators
after their review of DRS’s initial proposal, including
questions relating to DRS’s ability to meet the original, more
stringent, fuel efficiency standards. (Engineered
Electric Company d/b/a/ DRS Fermont, B-295126.5; B-295126.6,
December 7, 2007) (pdf)
Discussions, when conducted, must be meaningful, that is, they
may not be misleading and must identify proposal deficiencies
and significant weaknesses that could reasonably be addressed in
a manner to materially enhance the offeror’s potential for
receiving award. PAI Corp., B‑298349, Aug. 18, 2006, 2006 CPD
para. 124 at 8. However, agencies are not required to “spoon
feed” an offeror during discussions; they need only lead
offerors into the areas of their proposal that require
amplification. LaBarge Elecs., B‑266210, Feb. 9, 1996, 96-1 CPD
para. 58 at 6. The discussions here were unobjectionable.
As noted above, the discussion letter specifically advised Blane
that its delivery plan was difficult to read and follow. In this
regard, Blane’s initial delivery plan consisted of a chart
containing various item descriptions (down the left hand side of
the chart), amounts (throughout the chart, including various
blank spaces), and country names (down the right hand side of
the chart), formatted in such a manner that the columns
contained no headings--thus making it unclear to what the
columns referred--and the rows contained amounts that were not
clearly on the same line, making it unclear which amount
referred to which item description.[2] Since the nature of the
agency’s difficulty with the chart was, simply, that it was
difficult to read and follow, the discussion letter was
sufficient to lead Blane into the area of its proposal that
required improvement or further clarification. Blane asserts
that the agency should have reviewed its entire proposal,
including the quantities contained in a “transportation matrix,”
and then brought any discrepancies to its attention during
discussions. Protester’s Comments at 3. However, while the
protester may believe that it would have been better able to
address the deficiencies in its delivery plan if the agency had
approached discussions as it suggests, the agency was not
required to do so; again, the agency was only required to lead
the protester into the area of concern. Moreover, given the lack
of clarity in the chart, and the agency’s resultant inability to
determine precisely what Blane intended, we think the agency was
not in a position to provide more information in its discussion
letter; certainly, it was not required to provide more detailed
questions based on its speculation as to what Blane may have
intended. (Blane International
Group, Inc., B-310329, December 13, 2007) (pdf)
Cornell next argues that, because the agency had “serious
concerns about the location offered by Cornell from the time
that the site visit was performed,” Comments at 7, the agency
was required by the FAR to raise those concerns in discussions.
When discussions are held they must at least address
deficiencies and significant weaknesses in the proposals. FAR
sect. 15.306(d)(3). However, the agency is not required to
discuss every area where a proposal could be improved, and the
scope and extent of discussions is a matter within the
contracting officer’s discretion. Id. In this regard, we review
the adequacy of discussions to ensure that agencies point out
weaknesses that, unless corrected, would prevent an offeror from
having a reasonable chance of award. Brown & Root, Inc. and
Perini Corp., a joint venture, B-270505.2, B-270505.3, Sept. 12,
1996, 96-2 CPD para. 143 at 6. As discussed above, the
record demonstrates that Cornell’s site location was never
considered to be a significant weakness or deficiency, and never
prevented Cornell from having a reasonable chance for award.
Nowhere in the SSEB working papers, the SSEB consensus papers,
the technical/management evaluation memorandum, or the SSD was
the weakness of Cornell’s site location characterized as
significant or as a deficiency. [2] Further, Cornell’s proposed
site location was found to meet the requirements of the
solicitation at every stage of the evaluation. Because there is
no evidence to suggest that Cornell’s site location ever kept
its proposal from being rated acceptable under the site location
or technical/management factor, or otherwise prevented Cornell
from having a reasonable chance of receiving award, the agency
was not required to raise the issue in discussions. See Northrop
Grumman Info. Tech. Inc., B-290080 et. al., June 10, 2002, 2002
CPD para. 136 at 6; Brown & Root, Inc. and Perini Corp., a joint
venture, supra. (Cornell
Companies, Inc., B-310548, December 3, 2007) (pdf)
We recognize, as
PADCO points out, that the TEC did in fact describe the level of
effort feature of its proposal as a “weakness.” Contrary to
PADCO’s argument, however, discussions are not inadequate simply
because a weakness, which was not addressed during discussions,
subsequently becomes a determinative factor in choosing between
two closely ranked proposals, as was the case here. See, e.g.,
Gracon Corp., B-293009 et al., Jan. 14, 2004, 2004 CPD para. 58
at 3; Hines Chicago Inv., LLC, B‑292984, Dec. 17, 2003, 2004 CPD
para. 5 at 3-4. Further, regarding PADCO’s contention that the
weakness must have been significant because its final ratings
were decreased, the agency reports, and the record confirms,
that this weakness was not viewed by the agency as significant.
At PADCO’s debriefing, USAID expressly stated that it did not
consider the above weakness to be significant. Consistent with
this statement, the evaluation documents show that none of the
evaluation comments characterize PADCO’s distribution of its
level of effort as a “significant weakness,” a term the agency
had used to describe other weaknesses it identified in its
evaluation. See, e.g., AR, Tab 55, Competitive Range
Determination, at 9 (discussing a “significant weakness” in the
initial proposal submitted by The Services Group). While the
distribution of PADCO’s level of effort presented a “risk,” as
indicated by the TEC, there is nothing to suggest that it
created an unacceptable level of risk or “appreciably” increased
the risk of PADCO’s proposal. See FAR sect. 15.001 (defining a
“weakness” as “a flaw . . . that increases the risk of
unsuccessful contract performance” and a “significant weakness”
as “a flaw that appreciably increases the risk of unsuccessful
contract performance”). Ultimately, under both the management
and staffing plan subfactor and the overall technical approach
factor, PADCO’s proposal received a rating of “acceptable,”
which, as noted above, was defined by the RFP as a proposal
which meets all solicitation requirements, is “complete” and
“comprehensive,” and exemplifies an understanding of the tasks
required. RFP at M-2. (Planning And
Development Collaborative International, B-299041, January
24, 2007) (pdf)
It is a fundamental precept of negotiated procurements that
discussions, when conducted, must be meaningful; that is,
discussions must identify deficiencies and significant
weaknesses in each offeror’s proposal that could reasonably be
addressed so as to materially enhance the offeror’s potential
for receiving award. PAI Corp., B‑298349, Aug. 18, 2006, 2006
CPD para. 124 at 8; Spherix, Inc., B-294572, B-294572.2, Dec. 1,
2004, 2005 CPD para. 3 at 13. An agency fails to conduct
meaningful discussions where it fails to apprise an offeror that
its prices were viewed as unreasonably high. Price Waterhouse,
B-220049, Jan. 16, 1986, 86-1 CPD para. 54 at 6-7. Further, an
agency may not mislead an offeror--through the framing of a
discussion question or a response to a question--into responding
in a manner that does not address the agency’s concerns;
misinform the offeror concerning a problem with its proposal; or
misinform the offeror about the government’s requirements. Metro
Mach. Corp., B‑281872 et al., Apr. 22, 1999, 99-1 CPD para. 101
at 6. In conducting exchanges with offerors, agency personnel
also may not “engage in conduct that . . . favors one offeror
over another,” FAR sect. 15.306(e)(1); in particular, agencies
may not engage in what amounts to disparate treatment of the
competing offerors. Front Line Apparel Group, B-295989, June 1,
2005, 2005 CPD para. 116 at 3-4. Here, in the discussions
questions issued to NGI and Multimax (as well as to other
offerors such as BAE) questioning the proposed rates for
particular labor categories as significantly overstated, the
agency advised as follows: “Your proposed labor rates are
significantly higher than the Independent Government Cost
Estimate (IGCE) rates for the following labor categories . . . .
The offeror should consider revising the price proposal. If you
do not revise the identified rates, please provide an
explanation for the basis of the rate.” See IFN1 to
NGI no. 51, Nov. 3, 2005; IFN to NGI no. 298, Jan. 6, 2006; IFN
to BAE no. 50, Nov. 3, 2005; IFN to BAE no. 297, Jan. 6, 2006;
IFN to Multimax no. 49, Nov. 11, 2006. Thus, there was no
reference in the IFNs to the agency’s reliance on the
two-standard-deviation calculation, but instead only to the
proposed labor rate being “significantly higher than” the IGCE
as the basis for the IFN. The Army’s price discussions with NGI
and Multimax (as well as with BAE) were inadequate because, due
to the agency’s reliance on the two-standard-deviation formula
to identify “outlier” rates--and the broad range of acceptable
prices resulting from the formula--it failed to bring to the
protesters’ attention numerous rates that reasonably should have
been considered significantly overstated. In this regard, the
record shows that proposed rates that were not questioned in the
IFNs could actually exceed the IGCE rates by a greater
percentage than the rates that were identified. Thus, for
example, although NGI’s rate for [REDACTED] at the contractor
site was [REDACTED] percent higher than the IGCE rate, this rate
was not identified in an IFN because it was within the wide
range of acceptable prices established under the formula. At the
same time, although NGI’s proposed rate for [REDACTED] at the
contractor site was only [REDACTED] percent higher than the IGCE
rate, because it fell outside the range established by the
two-standard-deviation test, NGI was advised that its rate was
“significantly higher” than the IGCE. There simply is no
reasonable basis for bringing the former rate to the offeror’s
attention, but not the latter. The above example is not an
isolated one. NGI calculates that [REDACTED] of its proposed
labor rates that were not identified during price discussions
were similar to this example--they exceeded the corresponding
IGCE rate by a higher percentage than one or more of the rates
identified in its price IFNs. NGI notes further that [REDACTED]
of its unquestioned rates exceeded the IGCE rates by a greater
percentage than did some rates that were questioned in other
offerors’ IFNs. Likewise, the record indicates that Multimax was
not advised that its proposed rates for a significant number of
labor categories were higher than the corresponding IGCE rates,
despite the fact that these proposed rates deviated from the
IGCE by a greater percentage than rates that were identified in
discussions with Multimax or other offerors. Multimax calculates
that [REDACTED] of its unquestioned rates (only [REDACTED] of
its rates were identified in IFNs) exceeded the IGCE rates by a
greater percentage than the rates that were questioned in other
offerors’ IFNs (during initial price discussions). We conclude
that not only were offerors not adequately advised of all of
their significantly overstated rates, but the agency’s failure
to identify the additional rates actually misled the offerors
into believing that those rates did not require further
adjustment. In these circumstances, we conclude that the agency
failed to conduct meaningful discussions with the protesters.
(Multimax, Inc.; NCI
Information Systems, Inc.; BAE Systems, B-298249.6, B-298249.7,
B-298249.8, B-298249.9, B-298249.10,October 24, 2006) (pdf)
————————————————
1 Items for negotiation (IFN)
Where
contracting agencies conduct discussions with offerors whose
proposals are within the competitive range, the discussions must
be meaningful. Professional Servs. Group, Inc., B-274289.2, Dec.
19, 1996, 97-1 CPD para. 54 at 3. Discussions cannot be
meaningful if an offeror is not advised of the weaknesses,
deficiencies, or excesses in its proposal that must be addressed
in order for the offeror to be in line for award. Mechanical
Contractors, S.A., B-277916.2, Mar. 4, 1998, 98-1 CPD para. 68
at 4. Here, we think that the agency’s failure to raise its
concerns regarding the achievability of ALF’s proposed delivery
schedule constituted a failure to conduct meaningful discussions
because the protester might well have been determined to be in
line for award if it had been able to validate its proposed
schedule. Further, we do not think that the agency was relieved
of its obligation to conduct discussions due to the circumstance
that it did not learn of the information giving rise to its
concerns until after discussions had concluded. If, after
discussions are completed, the agency identifies concerns
pertaining to the proposal as it was prior to discussions that
would have had to be raised if they had been identified before
discussions were held, the agency is required to reopen
discussions in order to raise the concerns with the offerors.
See DevTech Sys., Inc., B-284860.2, Dec. 20, 2000, 2001 CPD para.
11 at 4. The key fact is that the concerns (while identified
after discussions have been closed) relate to the proposal as it
was prior to discussions. Id. (Al Long
Ford, B-297807, April 12, 2006) (pdf)
IAP also
complains that the Navy improperly failed to inform IAP that its
proposed price was too high. In this regard, IAP notes that its
proposed price was substantially higher than both the government
estimate (by 34 percent) and EJB’s price (by 21 percent) for the
definite-quantity elements of the RFP, and 39 percent higher
than EJB’s price for the ID/IQ elements. Where an
offeror’s price is high in comparison to competitors’ prices or
the government estimate, the agency may, but is not required to,
address the matter during discussions. Grove Resource Solutions,
Inc., B-296228, B-296228.2, July 1, 2005, 2005 CPD para. 133 at
5 n.5. Thus, if an offeror’s price is not so high as to be
unreasonable and unacceptable for contract award, the agency
reasonably may conduct discussions without advising the offeror
that its prices are not competitive. Id.; cf. Creative Info.
Tech., Inc., B-293073.10, Mar. 16, 2005, 2005 CPD para. 110 at 7
(price nearly 7 times the government estimate and 4.6 and 9
times competitors’ prices is unreasonable on its face). Here,
the agency determined that IAP’s overall price was reasonable
for the work to be performed and for what IAP proposed, SSB
Report at 19, and the price difference, even as calculated by
IAP, is not of a magnitude that suggests that IAP’s price was
unreasonable on its face. See Grove Resource Solutions, Inc.,
supra (agency not required to discuss protester’s high price
where awardee’s price was about 40 percent lower). Under these
circumstances, the Navy was not required to raise the matter of
IAP’s higher price during discussions. (IAP
World Services, Inc., B-297084, November 1, 2005) (pdf)
We find that the record does not establish a reasonable basis
for the agency’s assessment of a significant weakness with
respect to Cogent’s proposed scanner. First, as the record shows
and the Army now admits (see Agency’s Hearing Comments at
13-14), the evaluators failed to recognize that Cogent had
proposed a different scanner in its revised proposals to satisfy
the solicitation requirements--this failure itself renders
unreasonable the agency’s evaluation judgment concerning
Cogent’s proposed scanner. Despite the error, the Army’s
evaluator nevertheless asserted that the weakness was based upon
Cogent’s failure to explain how it could offer a compliant
scanner when the firm had asserted in its initial proposal and
earlier protest that no such scanner existed. TR at 122-24.
However, even assuming this latter evaluation judgment was
reasonable, the Army failed to provide Cogent with meaningful
discussions with respect to this scanner. The FAR requires at a
minimum that contracting officers discuss with each firm being
considered for award “deficiencies, significant weaknesses, and
adverse past performance information to which the offeror has
not yet had an opportunity to respond.” FAR sect. 15.306(d)(3).
Here, the Army twice provided Cogent with written discussions
after it proposed the Epson Perfection 4870 scanner as a
compliant product, but never identified its concern that Cogent
had not explained how it was now able to offer a compliant
product, even though the evaluators regarded this as a
significant weakness. In short, we find no reasonable basis in
the record for the agency’s judgment that Cogent’s proposed
scanner was a significant proposal weakness. We also find that,
in any event, the Army failed to conduct meaningful discussions
with Cogent with respect to this aspect of the agency’s
evaluation. (Cogent Systems, Inc.,
B-295990.4; B-295990.5, October 6, 2005) (pdf)
When contracting agencies conduct discussions with offerors in
the competitive range, such discussions must be meaningful.
Kaneohe Gen. Servs., Inc., B-293097.2, Feb. 2, 2004, 2004 CPD
paragraph 50 at 3. In order for discussions to be meaningful,
agencies must advise an offeror of weaknesses, excesses, or
deficiencies in its proposal, correction of which would be
necessary for the offeror to have a reasonable chance of being
selected for award. In this regard, the actual content and
extent of discussions are matters of judgment primarily for
determination by the agency involved, and we generally limit our
review of the agency's judgments to a determination of whether
they are reasonable. J.G. Van Dyke & Assocs. , B-248981,
B-248981.2, Oct. 14, 1992, 92-2 CPD paragraph 245 at 4.
Specifically, with regard to the adequacy of discussions of
price, an agency generally does not have an obligation to tell
an offeror that its price is high, relative to other offers,
unless the government believes the price is unreasonable. State
Mgmt. Servs., Inc.; Madison Servs., Inc., B-255528.6 et al. ,
Jan. 18, 1995, 95-1 CPD paragraph 25 at 5-6; Marwais Steel Co.,
B-254242.2, B-254242.3, May 3, 1994, 94-1 CPD paragraph 291 at
6. The issue here is whether the Army's discussions with CITI
were meaningful where the Army advised CITI merely that its
total price appeared "overstated," given the unique
circumstances of this case--specifically, the extraordinary
disparity between CITI's proposed level of effort and price as
compared to the government estimate as well as the level of
effort and prices of the other offerors in the competitive
range. We conclude that they were not. In addressing this issue,
we recognize that it is within the agency's discretion to decide
whether to inform an offeror that its price is considered too
high and to reveal the results of the analysis supporting that
conclusion or to indicate to all offerors the cost or price that
the government's price analysis, market research, and other
reviews have identified as reasonable. See FAR 15.306(e). The
question is whether the agency's judgment in this instance was
reasonable. While an agency is not required to "spoon-feed" an
offeror during discussions as to each and every item that could
be revised to improve its proposal, see ITT Fed. Sys. Int'l
Corp. , B-285176.4, B-285176.5, Jan. 9, 2001, 2001 CPD paragraph
45 at 6, agencies must impart sufficient information to afford
offerors a fair and reasonable opportunity to identify and
correct deficiencies, excesses or mistakes in their proposals.
Matrix Int'l Logistics, Inc. , B-272388.2, Dec. 9, 1996, 97-2
CPD paragraph 89 at 9. In this case, we conclude that CITI could
not be reasonably expected to have understood the true nature
and magnitude of the agency's concern with its proposal based
upon the information provided by the Army during its discussions
with CITI, thus rendering those discussions essentially
meaningless. (Creative
Information Technology, Inc., B-293073.10, March 16, 2005) (pdf)
In order for discussions to be meaningful, agencies must, at a
minimum, point out to competing firms deficiencies, significant
weaknesses, and adverse past performance information to which
the firm has not previously had an opportunity to respond. FAR
15.306(d)(3). The FAR also encourages contracting officers to
discuss other aspects of a firm's proposal that could, in the
opinion of the contracting officer, be altered or explained to
enhance materially the proposal's potential for award. Id.
Discussions must be meaningful, equitable and not misleading;
discussions cannot be meaningful unless a firm is led into those
weaknesses, excesses or deficiencies that must be addressed in
order for it to have a reasonable chance for award. TDS, Inc.,
supra, at 6-7. LMC asserts that the agency identified 11
weaknesses in its proposal that were based on language from the
earlier, pre-corrective action, version of its proposal. LMC
maintains that the agency was required to discuss these 11
weaknesses with the firm pursuant to our decision in DevTech
Sys., Inc. , B-284860.2, Dec. 20, 2000, 2001 CPD 11 in which we
held that, where an agency identifies new weaknesses in a
proposal during a reevaluation of that proposal in an
acquisition where discussions have previously occurred, it is
required to discuss those new weaknesses with the offeror. The
agency responds that, with respect to 6 of the 11 alleged
weaknesses arising from proposal language that predated the
current FPRs, the agency did not assign a weakness to the LMC
proposal during its evaluation, and thus was not required to
raise the matter in discussions. Agency Legal Memorandum, Sept.
30, 2004, at 11833. While the agency is correct that the six
weaknesses to which LMC refers were not identified as weaknesses
in the technical evaluation report on LMC's proposal, all six
are specifically identified in the agency's final evaluation and
tradeoff analysis report as weaknesses and as bases for
distinguishing between the LMC and EDS proposals. AR, exh. 116,
atviix,xiv. Given that they ultimately were listed in the best
value analysis--they related to 6 of the agency's 10 identified
best value items--and that they contributed in some manner to
the proposal's receiving an overall marginal/high risk rating,
we do not think the fact that they were captured in the best
value determination, rather than the technical evaluation
report, provided a basis for concluding that these issues were
not significant weaknesses. Further, while it is not clear how
significant they were, given that they played a large part in
the best value determination--and therefore presumably were
among the most important reasons for downgrading LMC's
proposal--absent some clear showing by the agency that they were
not significant, since they were based on information in LMC's
original proposal, and the agency had not previously discussed
the issues with LMC, it was obliged to do so. DevTech Sys., Inc.
, supra , at 4-5. (Lockheed Martin
Simulation, Training & Support, B-292836.8; B-292836.9;
B-292836.10, November 24, 2004) (pdf)
We do not agree with CHS that the agency's referring to staffing
and labor hours interchangeably was misleading. Rather, we think
the agency's references to "labor hours for full time employees"
(oral discussions) and the adequacy of CHS's proposed EAP staff
(written discussions) both reasonably could be interpreted in
only one way: the agency was concerned that CHS had not proposed
enough staff to perform adequately. The agency's questions were
adequate to bring this concern to CHS's attention, and therefore
were meaningful. (Comprehensive
Health Services, Inc., B-294608, December 1, 2004) (pdf)
As described above, the SSET identified Spherix's marketing
approach, including a lack of projected growth, to be a
"significant weakness." See AR, Supplemental Documents, Source
Selection Briefing Slides, at 2985. Spherix's approach to the
marketing plan requirement was not discussed with the protester,
and therefore we conclude that the agency failed to conduct
meaningful discussions with the firm in this respect. We also
find that the agency did not conduct meaningful discussions with
Spherix with respect to its proposed quality control plan, which
was also determined to be a significant weakness. The RFP
provided for the evaluation of offerors' draft comprehensive
quality control plan "to include a Performance Work Summary (PRS)
with Standards, Acceptable Quality Level (AQL), and Incentives."
RFP M, at 333. Spherix's initial proposal described its proposed
quality control plan, see AR, Tab103, Spherix Initial Proposal,
at 2139-214, which the SSET evaluated to be a weakness, stating
that Spherix's "overall quality control plan . . . is not a
complete approach . . . Vendor must amplify a more thorough
approach to quality control ensuring that [DELETED] are
addressed." See AR, Supplemental Documents, Final SSET
Evaluation Worksheets for Spherix, at 2997. The SSET also
evaluated Spherix's proposed approach to the PRS and AQL
requirements to be weaknesses. Id. In its discussions with
Spherix, the agency addressed only the firm's proposed approach
to the PRS and AQL requirements, and Spherix's proposal
revisions sufficiently addressed those aspects of its proposal
such that the agency no longer identified them as proposal
weaknesses. Id. The agency did not otherwise address Spherix's
quality control plan during discussions. Id. In its final
evaluation, the SSET noted that Spherix had not changed its
proposal with respect to its proposed quality control plan, and
stated that discussions were not conducted on this weakness
because Spherix "had a plan[; the] plan was simply weak." Id.
Ultimately, this aspect of Spherix's proposal was identified by
the SSET identified to be a "significant weakness." See AR,
Supplemental Documents, Source Selection Briefing Slides,
at2985. We therefore find that the agency failed to conduct
meaningful discussions with Spherix with respect to its proposed
quality control plan. We also find that Spherix did not receive
meaningful discussions with respect to its proposed transition
period staffing, which was evaluated as a part of the proposed
project implementation plan under the management approach
factor. See RFP M, at 333. Spherix's response to this
requirement was evaluated as a weakness, because the SSET found
that Spherix did not provide detailed information; SSET did not
conduct discussions on the matter with Spherix because it
concluded that Spherix's proposal "spoke to staffing but weak in
identification." See AR, Supplemental Documents, Final SSET
Consensus Evaluation Worksheets for Spherix, at 2999. This
aspect of Spherix's proposal, which was identified by the SSET
as a "significant weakness," see AR, Supplemental Documents,
Source Selection Briefing Slides, at2985, also should have been
raised with Spherix during discussions, but was not. (Spherix,
Inc., B-294572; B-294572.2, December 1, 2004) (pdf)
PDMG asserts that the agency improperly failed to conduct
adequate discussions for the Area 5 and 6 awards and, as a
result, treated offerors unequally. Specifically, PDMG maintains
that, after the initial rounds of discussions--during which the
agency asked PDMG about its experience as it related to
performing the RFP's mortgagee compliance requirements--the
agency continued to have a concern in the area, but did not
again raise it with PDMG. The protester contrasts this with the
agency's actions in conducting discussions with SAAM; in both
the first and second rounds of discussions, the agency pointed
out to SAAM that its prices for certain line items appeared low.
PDMG asserts that the agency's repeated discussions with SAAM in
the area of price, compared to the single round of technical
discussions with PDMG covering the agency's experience concern,
evidence disparate treatment. This argument is without merit.
PDMG's proposals received good ratings in the area of experience
following the agency's discussions in the area. AR, exhs. 9 at
80, 10 at 57. Agencies are not required to discuss every element
of a technically acceptable proposal that receives less than the
maximum possible score, nor are they required to afford an
offeror multiple opportunities to cure a weakness remaining in a
proposal that previously was the subject of discussions. Bioqual,
Inc. , B-259732.2., B259732.3, May 15, 1995, 95-1 CPD 243 at 45.
In any case, the record shows that the two firms were given the
same opportunity to revise their proposals as to both technical
matters and price during the first round of discussions, AR,
exhs. 5, 6, 7, 8, and that revisions for both firms were limited
to the pricing proposals during the second round. Id. Thus,
contrary to PDMG's assertion, both firms received virtually
identical discussions, albeit in different proposal areas
depending on the particulars of their offers. (Portfolio
Disposition Management Group, LLC, B-293105.7, November 12,
2004) (pdf)
Chapman also argues that HUD misled it into believing that its
responses to the discussion questions had satisfied HUD's
concerns. Specifically, Chapman asserts that, during each round
of discussions, HUD required Chapman to address only those
issues currently raised and informed it that all prior issues
had been resolved. Chapman's assertions are belied by the
record. While HUD's discussion letters included the statement
Your written responses to the written negotiations/ discussions
should address only the areas set forth above. . . . (emphasis
in original), the letters nowhere stated that prior issues had
been resolved, and (other than the initial letter, which did not
request FPRs) specifically advised that offerors may address any
area in their FPR. Discussion Letters dated Apr. 27, 2004, May
21, 2004, and June 8, 2004. (Chapman
Law Firm, LPA, B-293105.6, B-293105.10, B-293105.12,
November 15, 2004) (pdf)
NIH's discussions with Cygnus did not comply with the
requirement that discussions be meaningful. As noted above, in
explaining why THG's proposal was superior to Cygnus's proposal
such that, notwithstanding the significantly lower cost of
Cygnus's proposal, THG's proposal represented the best value to
the government, the source selection authority cited a number of
weaknesses in Cygnus's proposal (as well as strengths in THG's
proposal). NIH, however, failed to raise several of these
weaknesses during the discussions with Cygnus. Thus, the agency
failed to advise Cygnus that the agency viewed as a major
weakness (under the single most important technical evaluation
subcriterion) the evaluated limited [DELETED]; had assigned a
weakness to Cygnus's proposal on the basis that [DELETED]; and
had concluded that Cygnus, although displaying an understanding
of the scope of work, had not presented a [DELETED]. At the
least, in conducting discussions with Cygnus, the agency was
required to discuss the first of these concerns, since the
agency indisputably viewed it as major weakness. Moreover, while
NIH did raise other matters of concern during discussions, the
record indicates that the agency misled the protester as to the
results of those discussions, advising Cygnus that it had
successfully addressed the agency's concerns when this in fact
does not appear to have been the case. In this regard, NIH
advised Cygnus during discussions of its concern that the
proposed leader of Cygnus's team of meeting planners would
[DELETED]. Further, NIH viewed Cygnus's failure to furnish
samples of its graphics designers' work to be a major weakness,
and the agency therefore requested that Cygnus submit such
samples. NIH Discussions Letter to Cygnus, Oct.9, 2002. In
response, Cygnus sought to explain its rationale for the
specified level of effort for [DELETED]. In addition, Cygnus
furnished [DELETED]. Cygnus Discussions Response, Oct. 24, 2002.
NIH also requested and received from Cygnus additional
information regarding, and verification of, several elements of
Cygnus's proposed costs, and the agency specifically negotiated
[DELETED]. See , e.g. , NIH Discussion Letters to Cygnus, Oct.9,
2002, Dec. 2, 2002, and Jan. 28, 2003. NIH did not find Cygnus's
response with respect to the team [DELETED] to be satisfactory,
and, according to the agency, it [DELETED]. Further, as noted
above, the agency considered the costs negotiated with Cygnus to
be [DELETED]. Nevertheless, notwithstanding its continuing
concerns with Cygnus's proposal, the agency advised Cygnus in
the March 26 request for an FPR that as a result of the oral
discussions with it, "in which we negotiated cost issues
concerning your proposal," including the [DELETED], a "total
estimated cost of[DELETED] . . . is considered to be fair and
reasonable." NIH Request to Cygnus for FPR, Mar. 26, 2003. NIH
further advised Cygnus on March 27 that "[d]iscussions
concerning Cygnus Corporation's proposal have concluded... . It
is understood that these discussions have resulted in agreement
of all technical and cost issues raised during negotiations."
NIH Request to Cygnus for FPR, Mar. 27, 2003. Likewise, when the
agency afforded Cygnus and the other offerors on April30 an
opportunity to submit a second FPR, it advised Cygnus in its
letter that "discussions held on March 26, 2003, resulted in
agreement of all technical and cost issues raised during
negotiations." NIH Request to Cygnus for FPR, Apr. 30, 2003. (Cygnus
Corporation, Inc., B-292649.3; B-292649.4, December 30,
2003) (pdf)
Here, ASUS admits that, “[d]uring discussions . . . the Navy
expressed concerns about [the subcontractor’s] size and its
capability to perform the subcontracted work if it were to
experience rapid growth as a result of this project.” ASUS
Comments at 7. However, ASUS notes that, in response to these
expressed concerns, it provided financial records regarding the
subcontractor’s viability, a corporate guarantee from ASUS’s
parent company, and an explanation of the subcontractor’s plans
to hire the workers from the existing government workforce
necessary to operate the wastewater systems. ASUS argues that
the agency’s apparent “acceptance” of the information and
“failure to point out any continuing perceived weaknesses” was
misleading and denied ASUS the opportunity to revise it
proposal. Id. at 8. We disagree. Nothing in the record
suggests that the agency misled ASUS regarding its concerns.
ASUS has pointed to no affirmative statements by the Navy
indicating that the agency viewed the concerns it had raised
regarding the proposed subcontractor as having been resolved.
Further, since the agency was not required to reiterate concerns
that were not alleviated after reviewing the protester’s
response to the initial discussions, OMV Med., Inc. , supra ,
the mere fact that the Navy remained silent after the
protester’s response could not reasonably be understood here as
an indication that the agency found ASUS’s response to be
satisfactory. (American States
Utilities Services, Inc., B-291307.3, June 30, 2004) (pdf)
Here, as discussed above, despite Lockheed’s inclusion in its
initial proposal of “contractor-specific” savings, including the
savings associated with the [deleted], the agency declined
during discussions to indicate in any way that such savings
would be excluded from the agency’s calculation of AUPC.[13] The
agency asserts that Lockheed should have known that
“contractor-specific” savings would be excluded from the
agency’s AUPC calculation due to the RFP’s statements that an
“independent Government estimate” of AUPC would be conducted and
that various estimating tools would be used to “either validate
contractors’ cost estimates or to develop Government cost
estimates.” RFP § M.3.1.1.1. We disagree. Neither the language
of the solicitation, nor the information provided by the agency
during discussions, reasonably placed the offerors on notice
that “contractor-specific” savings would have no effect on the
agency’s calculation of AUPC. Although we agree that, if the
agency actually intends to compete the follow-on production
contract, there is nothing inherently unreasonable in evaluating
only “design-specific” costs,[14] the offerors were not clearly
advised of this. As noted above, the RFP stated that the agency
would evaluate the AUPC of “the offeror’s proposed munition” and
that such evaluation would be based on an assessment of “the
bidders’ production cost estimates.” RFP § M.3.1.1.1. Further,
the agency clearly knew, or should have known, that Lockheed’s
initially proposed AUPC was based on “contractor-specific”
costs, including the costs associated with the proposed
[deleted]; yet the agency failed to advise Lockheed during
discussions that such costs would be replaced with “industry
rates” in calculating the evaluated AUPC. Consistent with the
terms of the solicitation, and the information provided during
discussions, Lockheed reasonably believed that it could reduce
its evaluated AUPC by increasing its proposed
“contractor-specific” savings. On this record, the agency failed
to conduct meaningful discussions because it failed to advise
Lockheed that “contractor-specific” savings would not be
reflected in the agency’s calculation of AUPC. (Lockheed
Martin Corporation, B-293679; B-293679.2; B-293679.3, May
27, 2004) (pdf)
USF does not protest the evaluation of its proposed price.
Rather, USF maintains that the agency failed to engage in
meaningful discussions with it by failing to provide adequate
notice that its price exceeded the government estimate, and by
failing to adequately discuss the implications of its “all or
none” proposal. With respect to the former point, the record
shows that the agency did apprise USF in the second negotiation
message that its proposed price exceeded the government
estimate. USF maintains, however, that when it thereafter
submitted pricing that continued to exceed the government
estimate, the agency was required to again raise the matter with
the firm. With respect to the latter point, the record shows
that, in its request for FPRs, the agency asked USF to clarify
whether its offer was still “all or none.” AR, exh. 12, at 1.
USF maintains that the agency was required to apprise it of the
fact that unbundling the proposal could have made it eligible
for award of the wastewater system. We have no basis to object
to the adequacy of discussions here. Discussions are legally
adequate where offerors are advised of the weaknesses, excesses
and deficiencies in their proposals. Professional Performance
Dev. Group, Inc., B‑279561.2 et al., July 6, 1998, 99-2 CPD ¶ 29
at 5. While discussions should be as specific as practicable,
there is no requirement that they be all-encompassing or
extremely specific in describing the agency's concerns; rather,
the legal requirement is that they generally lead offerors into
the areas of their proposals that require amplification or
correction, without being misleading. Id. Where an agency has
advised an offeror of an area of concern, there is no legal
requirement that it raise the issue again in a subsequent round
of discussions, even where the issue continues to be of concern
to the agency. Id. at 5 n.3. (USFilter
Operating Services, Inc., B-293215, February 10, 2004) (pdf)
An agency is not required to afford offerors all encompassing
discussions, or to discuss every aspect of a proposal that
receives lower than the maximum score, and is not required to
advise an offeror of a minor weakness that is not considered
significant, even where the weakness subsequently becomes a
determinative factor in choosing between two closely ranked
proposals. Northrop Grumman Info. Tech., Inc., B‑290080 et al.,
June 10, 2002, 2002 CPD ¶ 136 at 6. Here, none of the identified
weaknesses prevented AO’s proposal from being considered fully
acceptable or otherwise from having a reasonable chance of
receiving the award. Rather, the weaknesses merely resulted in
AO’s proposal being rated good rather than excellent under the
factors in question, and the award ultimately was made to AMTEC,
not because AO’s proposal was deficient, but because AMTEC’s was
superior. Development Alternatives, Inc., B-279920, Aug. 6,
1998, 98-2 CPD ¶ 54 at 7. Under these circumstances, the agency
was not required to discuss these weaknesses with AO. (American
Ordnance, LLC, B-292847; B-292847.2; B-292847.3, December 5,
2003) (pdf)
Although discussions must address at least deficiencies and
significant weaknesses identified in proposals, the scope and
extent of discussions are largely a matter of the contracting
officer’s judgment. In this regard, we review the adequacy of
discussions to ensure that agencies point out weaknesses that,
unless corrected, would prevent an offeror from having a
reasonable chance for award. For discussions to be meaningful,
they must lead offerors into the areas of their proposals
requiring amplification or revision. The Communities Group,
B‑283147, Oct. 12, 1999, 99-2 CPD ¶ 101 at 4. The agency
provided MacB with meaningful discussions. Specifically, it
issued several evaluation notices (EN), two of which requested
clarification of MacB’s plans to use incumbent personnel. The
first sought clarification of the “commitment of individuals
listed as key technical personnel . . . and . . . who they
propose to fill key . . . positions if incumbents are not
interested.” AR 14 at 1. A second EN sought clarification of an
apparent contradiction in MacB’s proposal relating to its plan
to offer the right of first refusal to incumbent personnel while
at the same time proposing to have 30 percent of the effort
staffed by subcontractor personnel. Id. While these ENs did not
specifically refer to “risk,” they clearly were sufficient to
communicate the agency’s concerns about MacB’s ability to
successfully acquire the incumbent workforce, upon which the
moderate risk rating ultimately was based. This satisfied the
requirement for meaningful discussions in this area. (MacAulay-Brown,
Inc., B-292515; B-292515.2, September 30, 2003) (pdf)
The agency's initial evaluation under this sub-criterion
downgraded M&S Farms' proposal for not identifying what each
individual would do, and downgraded Carr's proposal to the same
degree because its resumes did not list references. Agency
Report, Tab 7, Initial Rating Sheets for M&S Farms'
Proposal, at 51, 109; Tab 8, Initial Rating Sheets for Carr's
Proposal, at 22, 51. Discussions with M&S Farms did not
include a question regarding this sub-criterion, or otherwise
identify the concern for which M&S Farms' proposal was
downgraded, Agency Report, Tab 11, Discussions with M&S
Farms, but discussions with Carr did include a question that
disclosed the agency's concern under this sub-criterion. Agency
Report, Tab 12, Discussions with Carr (Feb. 14, 2002), at 2.
Carr then provided the requested references and the agency
increased Carr's score to the maximum points available under the
sub-criterion, which accounts for the majority of the difference
in technical scores between these proposals. Agency Report, Tab
14, Carr's Response to Discussions, at 34; Tab 17, Revised
Rating Sheets for Carr's Proposal, at 3. The agency thus treated
the offerors unequally on this point, with the awardee receiving
a prejudicial competitive advantage as a result. (M&S
Farms, Inc., B-290599, September 5, 2002) (pdf)
However,
as the agency points out, this was just one of several noted
weaknesses in Northrop's approach to performing the contract,
with no indication that it was considered significant. COR at
23-24. This being the case, and since there is no evidence that
the weakness prevented the proposal from being rated acceptable
under the systems management/program management subfactor, or
otherwise prevented Northrop from having a reasonable chance of
receiving the award, the agency was not required to discuss this
issue with Northrop. See Brown & Root, Inc. and Perini
Corp., a joint venture, supra. (Northrop
Grumman Information Technology, Inc., B-290080; B-290080.2;
B-290080.3, June 10, 2002) (pdf)
While agencies generally are
required to conduct meaningful discussions by leading offerors
into the areas of their proposals requiring amplification, this
does not mean that an agency must "spoon-feed" an
offeror as to each and every item that could be revised or
otherwise addressed to improve its proposal. LaBarge Elecs.,
B-266210, Feb. 9, 1996, 96-1 CPD para. 58 at 6. (DeLeon
Technical Services, Inc.; TekStar, Inc., B-288811;
B-288811.2; B-288811.3, December 12, 2001)
Where agency knew or should have
known that the protester interpreted the solicitation as
limiting technical proposals to 100 pages, discussions with the
protester were not meaningful when the agency did not advise
protester that the solicitation permitted 200 page proposals,
declined to advise the protester of the agency's repeatedly
expressed concerns that the protester's proposal lacked detail,
and advised the protester there were no technical weaknesses in
its proposal. (Bank
of America, B-287608; B-287608.2, July 26, 2001)
Under Federal Acquisition
Regulation (FAR) § 15.306(e)(3), "the [CO] may inform an
offeror that its price is considered by the Government to be too
high, or too low, and reveal the results of the analysis
supporting that conclusion." This language clearly gives
the CO discretion to inform the offeror that its price is too
high, but does not require that the CO do so, especially where,
as here, the agency does not consider the price a significant
weakness or deficiency that the offeror could alter or explain
to enhance the proposal's potential for award. National
Projects, Inc., B-283887, Jan. 19, 2000, 2000 CPD
¶ 16 at 5; see also KBM Group, Inc.,
B-281919, B-281919.2, May 3, 1999, 99-1 CPD ¶ 118 at 8-9
(agency did not mislead protester during discussions, even
though award was ultimately made based on price and agency did
not inform protester that its price was higher than awardee's
price, where agency did not believe that protester's price was
too high for the approach taken). (SOS Interpreting,
Ltd., B-287477.2, May 16, 2001)
The agency's discussions with
IRRI specifically identified the individual CLINs for which the
agency considered IRRI's proposed prices too low, which
constituted half of the CLINs, as well as that IRRI's overall
price was too low. It then afforded IRRI an unrestricted
opportunity to submit final proposal revisions. The record thus
shows that the Air Force conducted meaningful discussions on the
issue. (International Resources Recovery,
Inc., B-287160, March 30, 2001)
We will not find that an agency
improperly failed to advise an offeror of a weakness reasonably
viewed during the evaluation as minor merely because, as the
competition played out, the weakness could have been a
determinative factor in choosing between two closely ranked
proposals. Brown & Root, Inc. and Perini Corp., a joint
venture, B-270505.2, B-270505.3, Sept. 12, 1996, 96-2 CPD para.
143 at 6. (Millar Elevator Service
Company, B-284870.4, December 27, 2000)
This case highlights the
challenge that an agency may face when, for whatever reason, it
reevaluates initial proposals after discussions are complete. If
during the reevaluation of proposals the agency identifies
concerns that would have had to be raised had they been
identified before discussions were held, the agency is required
to reopen discussions in order to raise the concerns with the
offerors. Mechanical Contractors, S.A., supra, at 5-6; CitiWest
Properties, Inc., supra, at 5. The key fact is that the concerns
(while identified relatively late) relate to the proposals as
they were prior to discussions. (DevTech
Systems, Inc., B-284860.2, December 20, 2000)
Contracting agencies are not
obligated to afford all-encompassing discussions that
"spoon-feed" an offeror each item that must be
addressed to improve a proposal; agencies are only required to
lead offerors into the areas of their proposals considered
deficient and requiring amplification. (SDS International,
B-285821, September 21, 2000)
Contracting agencies are not
obligated to afford all-encompassing discussions that
"spoon-feed" an offeror each item that must be
addressed to improve a proposal; agency reasonably led protester
into the areas of its proposal with shortcomings that warranted
amplification or clarification. (Arctic Slope World Services,
Inc., B-284481; B-284481.2, April 27, 2000)
Allegation that discussions with
protester were not meaningful is sustained where the record
shows that the evaluators were concerned over the protester's
pricing methodology and the source selection official shared
that concern, but the protester was not afforded an opportunity
during discussions to explain its pricing strategy. (ACS
Government Solutions Group, Inc., B-282098; B-282098.2;
B-282098.3, June 2, 1999)
For discussions to be
meaningful, they must lead offerors into the areas of their
proposals requiring amplification or revision; the agency is not
required to "spoon-feed" an offeror as to each and
every item that could be revised so as to improve its proposal,
however. Du and Assocs., Inc., supra, at 7-8; Applied Cos.,
B-279811, July 24, 1998, 98-2 CPD para. 52 at 8. (LB&B Associates,
Inc., B-281706, March 24, 1999)
Protest that discussions were
not meaningful because agency failed to point out excesses in
protester's technical proposal is denied where claimed
beneficial features in fact were not excesses, but rather (1)
were considered by the agency to be desirable, (2) were simply
protester's approach to complying with the solicitation
requirements, or (3) did not render the proposal unacceptable,
result in a significant reduction in score, or result in an
unreasonable, grossly excessive price. (Consolidated Engineering Services,
Inc, B-279565.5, March 19, 1999)
Written discussion questions
generated by a contracting agency should reasonably apprise
offerors of the areas that the agency considers deficient such
that the offerors will understand the agency's concerns. (Stratus Systems,
Inc., B-281645, February 24, 1999)
|