Unbalanced Pricing
CRJV contends that WHS relied on a defective IGE in
determining that CRJV’s proposed prices were unbalanced.
Supp. Protest at 11. The protester argues that four of the
seven labor rates upon which WHS based its IGE for the
contract manager position were associated with labor
categories that were not comparable to the RFP with
respect to position description, educational requirements,
and/or experience requirements. Id. at 2. For example, the
agency used the labor rate for a contract administrator
position, which CRJV contends requires only 10 years of
contract administration experience compared to the 20
years of construction-related, engineering or architecture
work experience required under the RFP. Id. at 3. CRJV
also contends that an additional labor rate that WHS used
in developing its IGE is not reflected in the Federal
Supply Schedule contract that the agency identified as the
source for the labor rate. Id. at 5. CRJV asserts that
because of these errors and similar ones with respect to
the project manager 3 and 4 positions, the agency’s
determination that CRJV’s prices are unbalanced is
unreasonable. Id. at 11. CRJV also generally objects to
the agency’s comparison of CRJV’s prices to those of other
offerors. Supp. Protest at 12.
WHS asserts that it reasonably determined that CRJV’s
prices for the contract manager, project manager 3, and
project manager 4 positions were unbalanced. Memorandum of
Law (MOL) at 11. The agency states that the validity of
its IGE as a basis for evaluating prices was proven by the
fact that the IGE was consistent with the labor rates
submitted by all the offerors, with the exception of
CRJV’s prices for the three positions. Id. at 26, 28. WHS
also states that it compared CRJV’s labor rates with the
other offerors’ rates in addition to the IGE and
identified the three labor rates in question as outliers.
Id. at 28.
Unbalanced pricing exists when, despite an acceptable
total evaluated price, the price of one or more contract
line items is significantly overstated or understated as
indicated by the application of cost or price analysis
techniques. FAR § 15.404-1(g)(1). The FAR identifies
examples of price analysis techniques to include
comparison of proposed prices received in response to the
solicitation and comparison with IGEs. Id. §
15.404‑1(b)(2).
Although the agency has provided no explanation or
rationalization for the errors CRJV identified with
respect to the IGE, we nonetheless conclude that the
agency reasonably determined that CRJV’s prices for the
contract manager, project manager 3, and project manager 4
positions are unbalanced. The record shows that WHS
compared CRJV’s prices with those of other offerors, and
found that the proposed labor rate for CRJV’s contract
manager was significantly higher, whereas the proposed
labor rates for CRJV’s project managers 3 and 4 were
significantly lower. See AR, Tab 9, Price Analysis
Memorandum, at 17. As noted above, the FAR explicitly
provides for comparing offerors’ prices as an acceptable
price analysis technique. FAR § 15.404‑1(b)(2). See
Strategic Resources, Inc., B‑406841.2, Nov. 27, 2012, 2012
CPD ¶ 346 at 11 (agency’s price realism analysis was
reasonable, despite flawed IGE, because the agency also
used other price analysis techniques); Academy Facilities
Mgmt.--Advisory Op., B‑401094.3, May 21, 2009, 2009 CPD ¶
139 at 14 (finding unnecessary to address challenge to IGE
where the agency also compared offerors’ prices to each
other in conducting price realism analysis). Furthermore,
CRJV has not demonstrated any impropriety in WHS’s
comparison of its prices to those of other offerors.
Accordingly, we deny this protest ground.
Unbalanced Pricing Risk
CRJV also challenges the agency’s analysis of the risks
posed by the protester’s unbalanced pricing. Protest at
10-11. CRJV argues that the agency’s conclusion that
CRJV’s higher labor rate for the contract manager
increases the risk that the agency will pay unreasonably
high prices during contract performance is unreasonable,
given Markon’s $15 million higher price. Protest at 11. In
this regard, CRJV contends that the solicitation
guaranteed a minimum level of effort for each labor
category and WHS advised offerors that an estimated 40
task orders were issued over the last five years. CRJV
Comments at 4, 11. The protester further contends that, as
a result, the agency’s concern that only the contract
manager position would be utilized and give rise to an
unreasonably high price for the government is
unreasonable. Id. CRJV also argues that the agency’s
conclusion that CRJV will not propose individuals for the
project manager 3 and 4 positions, leading to the
government issuing a unilateral task order to CRJV, is
unsupported. Protest at 10.
WHS asserts that it conducted its unbalanced pricing
analysis in accordance with the FAR. WHS states that FAR §
15.404-1(g) requires the government to consider both the
risk that award of the contract will result in paying
unreasonably high prices for contract performance and
performance risk. MOL at 24. WHS explains that the only
task order guaranteed under the contract is for the
contract manager, and that the other labor rates do not
offset CRJV’s overstated contract manager labor rate. 2nd
Supp. MOL at 2, 10; AR, Tab 10, Source Selection Decision
Memorandum, at 32. The contract manager task order is
issued at the beginning of each contract year, and is paid
by the government regardless of the task orders that
follow, if any. 2nd Supp. MOL at 9. Therefore, WHS argues
that CRJV’s contract manager labor rate is a guaranteed
cost to the government and thus is not comparable to the
$15 million difference in CRJV’s and Markon’s evaluated
prices, which are a ‟fiction” created for evaluation
purposes. Id. at 9‑10.
Additionally, WHS states that the understated prices for
CRJV’s project manager 3 and 4 positions pose multiple
risks to contract performance. Under the terms of the RFP,
if the contract were awarded to CRJV, CRJV’s labor rates
would be incorporated into the contract and used for task
orders issued under the contract. Id. at 11. WHS explains
that, because CRJV’s labor rates for the project manager 3
and 4 positions are below the market rates, the contractor
would have difficulty retaining existing personnel and/or
hiring qualified personnel at those labor rates. Id. at
13; AR, Tab 10, Source Selection Decision Memorandum, at
33. Thus, CRJV is at risk of high turnover for those
positions, which could jeopardize contract performance
where WHS is operating under a ‟no mission failure
policy.” 2nd Supp. MOL at 12-13; AR, Tab 10, Source
Selection Decision Memorandum, at 35. Alternatively, CRJV
would have to pay market rates to retain or hire personnel
and take a loss. 2nd Supp. MOL at 13.
Additionally, WHS explains that CRJV may try to utilize
project manager 1 and 2 personnel--who are qualified to
perform ‟basic to mid-level work”--in place of project
manager 3 and 4 personnel, who are qualified to perform
the most complex task orders. Id.; AR, Tab 10, Source
Selection Decision Memorandum, at 35-36. WHS states that
any attempt to utilize these less qualified personnel for
tasks more appropriate for project manager 3 and 4
personnel poses a risk to contract performance. 2nd Supp.
MOL at 13-14; AR, Tab 10, Source Selection Decision
Memorandum, at 35‑36. Finally, WHS explains that if CRJV
were unwilling to propose project manager 3 and 4
personnel for task orders or to reach agreement with the
agency to staff a task order, the agency would have to
either issue a unilateral task order or procure the work
outside CRJV’s contract. 2nd Supp. MOL at 11, 14; AR, Tab
10, Source Selection Decision Memorandum, at 36. If WHS
were to issue a unilateral task order to CRJV, the agency
would be at risk of a later claim by CRJV or that the firm
would abandon the work. 2nd Supp. MOL at 11-12.
Contracting officers may evaluate unbalanced pricing to
determine if it increases performance risk and could
result in the payment of unreasonably high prices. FAR §
15.404-1(g)(1). Where unbalancing is detected, the
contracting officer must then consider the risk posed,
including the risk of paying an unreasonable price, and
must consider whether to reject the offer if the risk is
unreasonable. Id. § 15.404-1(g)(2)-(3). While both
understated and overstated prices are relevant to the
question of whether unbalanced pricing exists, the primary
risk to be assessed in an unbalanced pricing context is
the risk posed by overstatement of prices. Crown Point
Sys., B-413940, B‑413940.2, Jan. 11, 2017, 2017 CPD ¶ 19
at 5. Our Office will review for reasonableness both an
agency’s determination as to whether an offeror’s prices
are unbalanced, and an agency’s determination as to
whether an offeror’s unbalanced prices pose an
unacceptable risk to the government. Gulf Master Gen.
Trading, LLC, B‑407941.2, July 15, 2013, 2013 CPD ¶ 210 at
5.
On this record, we have no basis to question the
reasonableness of WHS’s conclusion that CRJV’s unbalanced
pricing posed significant risks to the government. With
respect to the overstated labor rates for the contract
manager position, the agency reasonably found that CRJV’s
proposed prices might not actually result in the
lowest-priced proposal, given that the only guaranteed
task order is the initial task order for the contract
manager, which would run for the duration of each contract
year. See Gulf Master Gen. Trading, LLC, supra (agency
reasonably determined protester’s unbalanced pricing
presented risk to government if option years not
exercised); cf. Kellie W. Tipton Constr. Co., B‑281331.3,
Mar. 22, 1999, 99-1 CPD ¶ 73 at 6 (agency reasonably
determined awardee’s apparently high labor rates remained
lower than protester’s over the first nine delivery
orders). Moreover, as discussed above, the record shows
that the agency reasonably considered the risks posed by
CRJV’s understated labor rates for the project manager 3
and 4 positions. The protester’s disagreement with the
agency’s judgment does not provide a basis to sustain the
protest. (Crawford
RealStreet Joint Venture B-415193.2, B-415193.3: Apr
2, 2018)
Price Realism Evaluation
Next, AbacusSecure protests that the agency failed to
perform an appropriate price realism analysis as part of
its source selection process. Among other things,
AbacusSecure asserts that the agency was required to
assess the realism of the awardee’s labor rates, arguing
that they were “too low to recruit the incumbent
workforce.” Supp. Protest, Sept. 1, 2017, at 24.
The agency responds that its price evaluation was
consistent with the terms of the solicitation.
Specifically, the agency points out that the solicitation
expressly put offerors on notice that price would be
evaluated without evaluating separate cost elements, see
FAR § 15.404-1(b), and further, that the solicitation did
not require submission of labor rates for the contract
line item numbers (CLINs) that constituted over 90 percent
of both offerors’ total evaluated prices. RFP at 1,912-33;
Memorandum of Law, Oct. 16, 2017, at 17. The agency
further states that it considered the offerors’ total
proposed prices as compared to one another, found that
there was an 8.6 percent price difference between the two
offerors’ prices, and concluded on the basis of this
comparison that AFDS’s price was not unrealistically low.
AR, Tab 44, Price Analysis Memorandum, at 18,489‑91.
In general, there is no requirement that a price realism
analysis be performed when award of a fixed-price contract
is contemplated; this is because a fixed-price contract
places the risk and responsibility for contract costs and
ensuing profit or loss on the contractor. Star Contract
Servs., LLC, B-409424, Apr. 23, 2014, 2014 CPD ¶ 133;
Phoebe Putney Mem’l Hosp., B‑311385, June 19, 2008, 2008
CPD ¶ 128 at 2. Nonetheless, a solicitation for a
fixed‑price contract may, as here, provide for a price
realism analysis to assess the offerors’ understanding of
the solicitation requirements and potential risks. PHP
Healthcare Corp., B‑251933, May 13, 1993, 93-1 CPD ¶ 381
at 5. The FAR provides a number of price analysis
techniques that may be used to determine whether prices
are reasonable and realistic, specifically including a
comparison of proposed prices. FAR § 15.404-1(b)(2); see
also General Dynamics--Ordnance & Tactical Systems,
B‑401658, B‑401658.2, Oct. 26, 2009, 2009 CPD ¶ 217 at 3;
Burns and Roe Servs. Corp., B‑296355, July 27, 2005, 2005
CPD ¶ 150 at 7. Finally, the nature and extent of a price
realism analysis ultimately are matters within the
exercise of the agency’s discretion, and our review of
such an evaluation is limited to determining whether it
was reasonable and consistent with the terms of the
solicitation. Northrop Grumman Info. Tech., Inc., et al.,
B‑295526 et al., Mar. 16, 2005, 2005 CPD ¶ 45 at 19.
Here, as discussed above, the solicitation specifically
stated that the agency would perform a price analysis “in
accordance with FAR § 15.404-1(b)”--which provides for
evaluation of price “without evaluating its separate cost
elements.” RFP at 1,907; FAR § 15.404-1(b). Accordingly,
AbacusSecure’s assertion that the agency was obligated to
evaluate the realism of individual cost elements,
including labor rates, is contrary to the express terms of
the solicitation. As also discussed above, the record
further establishes that the agency recognized that the
offerors’ prices were lower than the government’s
estimate, but noted that there was only an 8.6 percent
price difference between them and concluded, based on the
existence of adequate price competition, that neither
offeror’s price was unreasonably low. On this record, we
find no basis to question the reasonableness of the
agency’s price realism analysis, and AbacusSecure’s
protest challenging that aspect of the procurement is
denied. (AbacusSecure, LLC
B-415175, B-415175.2, B-415175.3, B-415175.4: Dec 6, 2017)
Price Evaluation
CPS contends that the agency’s price evaluation failed to
consider the risk associated with CTPI’s low and
unbalanced pricing. Specifically, CPS notes, based on its
independent analysis of pricing, that for a significant
number of items, CTPI’s pricing was dramatically lower
than CPS’s, and was lower than the other two offerors’
prices. CPS also notes that, for a smaller number of
items, CTPI’s prices were dramatically higher than those
of CPS and the other two offerors. Protester’s Comments on
the Agency Report at 1-2. According to CPS, this
demonstrates that CTPI’s pricing was unbalanced because it
contained both significantly understated and overstated
pricing, and that the agency failed to reasonably assess
the risk to the government posed by CTPI’s unbalanced
pricing. Id. at 3. In response, the agency notes that,
consistent with the terms of the solicitation, it assessed
CTPI’s proposal for unbalanced pricing based on random
sampling. The agency explains that, when it analyzed the
random samples, it found that the vast majority of CTPI’s
sampled prices were reasonable based on comparisons to
other offerors or market prices. Agency Report at 5.
In reviewing protests of an agency’s evaluation and source
selection decision, our Office will not reevaluate
proposals; rather, we review the record to determine
whether the evaluation and source selection decision are
reasonable and consistent with the solicitation’s
evaluation criteria, and applicable procurement laws and
regulations. M&S Farms, Inc., B-290599, Sept. 5, 2002,
2002 CPD ¶ 174 at 6. In this case, we find CPS’s
contention that the agency’s price evaluation and risk
assessment were unreasonable to be without merit.
As an initial matter, to the extent CPS’s argument can be
understood to suggest that the agency should have assessed
the risk that CTPI’s low prices posed to the agency, CPS
is describing a price realism analysis, which was not
contemplated by the solicitation, and is therefore without
merit. A price realism evaluation, which involves an
assessment of whether a price is too low, is conducted for
the purpose of assessing a vendor’s understanding of the
contract requirements or to assess the risk inherent in a
vendor’s proposal or quote. Ball Aerospace & Techs. Corp.,
B‑402148, Jan. 25, 2010, 2010 CPD ¶ 37 at 8. In order to
conduct a price realism analysis, an agency must provide
for such an analysis in the solicitation, and in this case
the RFP did not provide for such an assessment. See Ball
Aerospace & Techs. Corp., supra, at 8. Therefore, had the
agency performed a price realism analysis, it would have
been improper.
Alternatively, to the extent CPS’s argument can also be
understood as suggesting that the agency’s unbalanced
pricing analysis was unreasonable, that argument is also
without merit, because the agency’s analysis is
well-supported by the record and consistent with the terms
of the solicitation. Instead, CPS relies on its own
reevaluation of CTPI’s pricing using a methodology that is
inconsistent with the methodology established by the terms
of the solicitation.
With respect to unbalanced pricing generally, the Federal
Acquisition Regulation (FAR) requires that contracting
officers analyze offers with separately-priced line items
or subline items, to detect unbalancing. FAR §
15.404-1(g)(2). Where unbalancing is detected, the
contracting officer must then consider the risk posed,
including the risk of paying an unreasonable price, and
must consider whether to reject the offer if the risk is
unreasonable. See FAR § 15.404-1(g)(2)-(3). While both
understated and overstated prices are relevant to the
question of whether unbalanced pricing exists, the primary
risk to be assessed in an unbalanced pricing context is
the risk posed by overstatement of prices because low
prices (even below-cost prices) are not improper and do
not themselves establish (or create the risk inherent in)
unbalanced pricing. See AIS Engineering, Inc., B-410246,
B‑410246.2, Nov. 21, 2014, 2015 CPD ¶ 5 at 3.
Here, the RFP provided that unbalanced pricing would be
assessed based on random sampling, not a direct analysis
of all prices. RFP at 37. In this regard, the agency’s
application of random sampling and the conclusions drawn
from that sampling appear both reasonable and consistent
with the methodology set forth in the solicitation. The
agency provided a detailed description of its methods and
results as well as significant underlying documentation,
which support the reasonableness of the evaluation. See
Business Clearance Memorandum at 17-22 and Price Analysis
at 73-167.
As described above, the record reflects that with respect
to both potentially overstated and understated prices, the
agency found, with a high level of confidence, that a
majority of CTPI’s quoted prices were likely to be
reasonable. Agency Report at 5. The agency estimated that
between 0.6% and 1.4% of the 1,441 ELIN prices that CTPI
quoted were overstated. Id. at 5-6. Similarly, the agency
estimated that between 5.9% and 20.4% of the 1,441 ELIN
prices that CTPI quoted were understated. Id. While the
agency’s estimates show that a significant minority of
CTPI’s prices may, in fact, be understated, as noted
above, the primary risk to be assessed in an unbalanced
pricing context is the risk posed by overstatement of
prices. In this case, the agency estimated that only a
very small percentage of CTPI’s prices were likely to be
overstated. As a result, the agency reasonably concluded
that the risk posed by potential unbalanced pricing was
not significant, and that awarding to CTPI would not
result in the agency paying unreasonably high prices. See
Id. at 7, and Business Clearance Memorandum at 17-19.
CPS argues that the agency’s unbalanced pricing evaluation
was flawed because it failed to take into account the
magnitude of the price differences for various categories
of items identified by CPS. Protester’s Comments on the
Agency Report at 1-3. We are unpersuaded by CPS’s
argument, because it focuses on prices other than those
identified by the agency as part of its random sampling,
and is, in effect, a request that our Office reevaluate
the awardee’s proposal on a basis other than that
described in the RFP. We decline to do so, and deny this
protest ground.
Supply Chain Risk Management Factor
CPS argues that, in light of several original equipment
manufacturer (OEM) letters expressing concern about CTPI’s
pricing and status as an authorized reseller, the agency’s
assessment of CTPI’s technical proposal was unreasonable
with respect to the supply chain risk management factor.
Supplemental Protest at 5. According to CPS, the OEM
letters demonstrate that CTPI will not be capable of
obtaining goods through authorized channels and that the
Navy did not reasonably assess the risk posed by CTPI’s
proposal of introducing gray market or counterfeit goods
into the Navy’s supply chain. Id. at 5-6. This protest
ground is untimely.
On October 14, Brocade, an original equipment manufacturer
(OEM) of certain items to be supplied under the contract,
contacted CPS and, according to CPS, expressed concern
about CTPI’s pricing and status as an authorized reseller
of its products. Affadavit of CPS President at 2.
Approximately 10 days later, on October 24, CPS began
contacting other OEMs to determine if they had similar
concerns about CTPI. Id. at 1. On October 26, CPS states
that it received e-mails from three other OEMs expressing
concern either about CTPI’s pricing or CTPI’s status as an
authorized reseller of their products. Affadavit of CPS
President at 2-3.
On November 4, a representative of Brocade sent an e-mail
to the Navy expressing concern about CTPI’s pricing and
forwarded a copy to CPS, and CPS shared this e‑mail with
several other OEM representatives who had privately
expressed concerns to CPS. CPS Response to GAO Request for
Answers of December 12, 2016. Representatives from three
other OEMs also sent e-mails of concern to the Navy on
November 4, 6, and 8, respectively, expressing concerns
about CTPI’s pricing, and in some cases suggesting that
CTPI was not an authorized reseller of their products.
Affadavit of CPS President at 2-3. On November 14, CPS
filed a supplemental protest alleging that the agency’s
assessment of CTPI’s proposal under the supply chain risk
management technical evaluation factor was unreasonable in
light of the OEM letters. Supplemental Protest at 5.
With respect to timeliness, CPS alleges that its
supplemental protest is timely because it only
definitively learned of the OEMs’ concerns when they sent
their letters of concern to the Navy on November 4, 6, and
8. Supplemental Protest at 1. CPS suggests that the e-mail
it received from Brocade on October 14 was not sufficient
notice of the issue, as Brocade products, alone, only
represent a small portion of the total cost of the
contract. Protester’s Response to Request for Dismissal at
2-3. CPS suggests that a protest founded on that basis
alone would have been dismissed as speculative or legally
insufficient. Id. CPS, notes, however that the products
from all 5 OEMs discussed in its supplemental protest
taken together represented approximately 60% of the value
of the contract, which provided a firmer basis for
protest. Id.
Our Bid Protest Regulations require a detailed statement
of the legal and factual grounds of a protest, and CPS is
correct that we will not generally entertain protests
grounded on speculation or rumor. See Ervin and
Associates, Inc., B-278850, Mar. 23, 1998, 98-1 CPD ¶ 89
at 5. However, where a protester files supplemental
protest grounds, each new ground must independently
satisfy the timeliness requirements of our Bid Protest
Regulations, which do not contemplate the piecemeal
presentation or development of protest issues. FR
Countermeasures, Inc., B-295375, Feb. 10, 2005, 2005 CPD ¶
52 at 9. In general, protests other than protests of
defects in a solicitation, must be filed within 10 days of
when the protester knew or should have known the basis for
protest. Additionally, a protester has an affirmative
obligation to diligently pursue information providing the
basis for the protest, Automated Med. Prods. Corp.,
B-275835, Feb. 3, 1997, 97-1 CPD ¶ 52 at 2-3, and a
protester’s failure to utilize the most expeditious
information-gathering approach may constitute a failure to
meet its obligation in this regard. See, e.g., United
International Investigative Services, Inc., B-286327, Oct.
25, 2000, 2000 CPD ¶ 173 at 3. CPS’s supplemental protest
does not meet this standard.
CPS concedes that it received several additional contacts
from other OEMs expressing concerns prior to November 4.
Specifically, in addition to the e-mail from Brocade on
October 14, CPS indicates it received e-mails from three
different OEMs on October 26 expressing concerns, either
about CTPI’s pricing or CTPI’s status as an authorized
reseller. Affadavit of CPS President at 2-3. While several
of these OEMs ultimately did not contact the Navy with
their concerns, the fact that four separate OEMs expressed
concern to CPS should have alerted CPS to the factual
basis of this protest ground by October 26, at the latest.
Therefore we conclude that CPS knew or should have known
this basis of protest by October 26, and the protest
ground was untimely because it was filed 19 days later on
November 14.
Additionally, we note that CPS failed to diligently pursue
this basis of protest prior to October 26. The protester
learned of the award to CTPI on September 21, and received
a debriefing on October 3. At that point, CPS knew the
identity of the awardee and that its price was (in the
aggregate) much lower than its own pricing. CPS filed its
protest with our Office on October 7. On October 14, a
Brocade representative contacted CPS to alert CPS to the
precise issues that form the basis of CPS’s supplemental
protest, albeit only with respect to a small portion of
the total contract value. Affadavit of CPS President at 2.
However, according to CPS’s own account, it made no
further inquiries with any other OEMs until after October
24, over a month after award and several weeks after CPS’s
initial protest with our office was filed. Id. With
respect to establishing key facts supporting this basis of
its protest, reaching out to the OEMs immediately
following award, or, at the latest, immediately after
Brocade contacted CPS expressing concern, would clearly
have been the most expeditious avenue of inquiry. On these
facts, we find that this protest ground was not diligently
pursued and is untimely. As a result, we dismiss it. See,
e.g., Thomas May Constr. Co., B-255683, Mar. 23, 1994,
94-1 CPD ¶ 210 (delay in pursuing available information
about awardee until three weeks after bid opening not
diligent pursuit); Bannum, Inc., B-408838, Dec. 11, 2013,
2013 CPD ¶ 288 at 5; MILVETS Systems Tech., Inc.,
B-411721.2, B-411721.3, Jan. 14, 2016, 2016 CPD ¶ 42 at 8
(protester challenging an award on one ground should
diligently pursue information which may reveal additional
grounds of protest). (Crown
Point Systems B-413940,B-413940.2: Jan 11, 2017)
MTCE poses two challenges to the agency’s price evaluation
of Portus Services, first arguing that the price for the
container stuffing commodity rate was “significantly
underbid,” and that the agency failed to evaluate whether
the price quoted for the stuffing commodity rate was
reasonable or might have contributed to unbalanced
pricing. Comments at 18. The agency argues that it
properly determined that Portus Services’ pricing was
fair, reasonable, and balanced. COSF at 63-64.
The RFP stated that the agency will review the prices
proposed to determine if unbalanced pricing exists
pursuant to FAR § 15.404-1(g) and whether the price is
fair and reasonable pursuant to FAR § 15.404-1(b)(2). RFP,
Amend. 0001, at 8, 11. Price reasonableness is an
assessment of whether a price is unreasonably high, while
price realism is an assessment of whether a price is too
low. See, e.g., The Matthews Group, Inc. t/a TMG Constr.
Corp., B-408003.3, B‑408004.3, Mar. 21, 2014, 2014 CPD ¶
104 at 8. The RFP did not provide for a review of price
realism. Here, the awardee is the lowest-priced offeror,
and the protester’s allegation that the awardee’s price is
too low provides no basis on which to find error in the
agency’s price reasonableness analysis.
Unbalanced pricing exists where the prices of one or more
line items are significantly overstated or understated,
despite an acceptable total evaluated price (typically
achieved through underpricing of one or more other line
items). General Dynamics--Ordnance & Tactical Sys.,
B‑401658, B-401658.2, Oct. 26, 2009, 2009 CPD ¶ 217 at 5.
To prevail on an allegation of unbalanced pricing, a
protester must show that one or more prices in the
allegedly unbalanced proposal are overstated; that is, it
is insufficient for a protester to show simply that some
line item prices in the proposal are understated. See
Academy Facilities Mgmt.--Advisory Opinion, B‑401094.3,
May 21, 2009, 2009 CPD ¶ 139 at 15. This is so because low
prices (even below-cost prices) are not improper and do
not themselves establish (or create the risk inherent in)
unbalanced pricing. Id. Here, the protester only argues
that the awardee “significantly underbid its stuffing
commodity rate” since the rate proposed was lower than the
protester’s proposed rate. Comments at 18. There is thus
no merit to the protester’s claim that the awardee’s price
may be unbalanced, where the support for that assertion is
that one price out of many has been understated, but there
is no allegation or showing that one or more prices are
overstated. (Marine
Terminals Corporation-East, Inc. B-410698.9: Aug 4,
2016)
Al-Tahouna and Wadi Al-Sajaa argue that the contracting
officer erred in finding their bids to be unbalanced. Wadi
Al-Sajaa contends that the solicitation did not provide
for bids to be rejected for unbalanced pricing. Wadi Al-Sajaa
Protest at 2. Al-Tahouna argues that its bid continues to
provide the highest value to the government based on
scenarios in which the government sells 25, 50, 75, and
100 percent of the maximum quantity. Al-Tahouna Protest at
4. Al-Tahouna also asserts that it could provide a bank
guarantee for the price of purchasing the maximum quantity
indicated by the solicitation. Id. at 4-5.
Neither the Competition in Contracting Act of 1984 (CICA)
nor the Federal Acquisition Regulation (FAR) apply to
sales of government property. Where, as here, CICA and the
FAR do not apply to procurements that are otherwise within
our jurisdiction, we review the record to determine if the
agency’s actions were reasonable and consistent with any
statutes or regulations that do apply. See, e.g., Open
Spirit, LLC, B-410428, B-410428.2, Dec. 15, 2014, 2014 CPD
¶ 373 at 6; Great S. Bay Marina, Inc., B-293649, May 3,
2004, 2004 CPD ¶ 108 at 2-3. Moreover, although the FAR is
not applicable to sales contracts, our Office, where
appropriate, will refer to it for guidance in reviewing
protests involving sales contracts. See Alamo Aircraft
Supply, Inc.; Merchants World Surplus Enters., Inc.;
Associated Aircraft Mfg. & Sales, Inc.; Blazer Surplus;
Dixie Air Parts Supply, Inc., B-278215.4, Mar. 11, 1998,
98-1 CPD ¶ 76 at 5 n.5.
DLA contends that rejecting unbalanced bids is encompassed
within the broad authority to reject bids granted under
the terms of the IFB. DLA states that the IFB advised
bidders that the contracting officer had the discretion to
reject any and all bids, including bids under which a
bidder would take unfair advantage of the government or
other bidders. AR Legal Memorandum at 6-7.
An agency is required to evaluate proposals in accordance
with the terms of the solicitation. See Systems Research &
Applications Corp., B-407224.3, Dec. 17, 2012, 2012 CPD ¶
352 at 7. In evaluating offerors’ proposals, an agency may
properly consider specific, albeit not expressly
identified, matters that are logically encompassed by or
related to the stated evaluation factors. ITT Electronic
Sys. Radar, Reconnaissance & Acoustic Sys., B-405608, Dec.
5, 2011, 2012 CPD ¶ 7 at 10.
The IFB here stated that “The Government reserves the
right to reject any or all bids, including bids under
which a Bidder would take unfair advantage of the
Government or other Bidders . . . when in the best
interest of the Government.” AR, Tab 4, Sale by Reference,
at 4. As discussed below, an offer properly may be
rejected if the contracting officer determines that the
lack of balance in the bid or offer poses an unacceptable
risk to the government. FAR § 15.404-1(g)(3); L. W.
Matteson, Inc., infra at 3. In our view, the risk to the
government posed by an unbalanced bid, where the risk is
unacceptably high, is reasonably related to the concept of
fairness and the best interests of the government.
Therefore, we conclude that the IFB’s language encompasses
the rejection of unbalanced bids where the bid poses an
unacceptable risk to the government.
DLA explains that it concluded that Al-Tahouna’s and Wadi
Al-Sajaa’s bids were unbalanced based on a comparison with
the five highest bids and historical information. DLA
states that both firms bid significantly higher than the
average bids of their five nearest competitors for the
plastics and rubber residue in line item 2, and
significantly lower on the other five line items. For
example, the protesters bid $11.00 and $10.55 per pound
for item 2, respectively, compared with an average of
$0.70 per pound for the remaining top five
bidders--amounting to more than 15 times higher. Al-Tahouna
and Wadi Al-Sajaa bid $0.001 and $0.002 per pound for
scrap tires in item 1, compared to an average bid $0.42
per pound by the top five bidders--or 420 and 210 times
lower. AR Legal Memorandum at 8. DLA also states that,
with respect to item 2, historical data from the sale of
plastics and rubber residue in Kuwait showed that bids
ranged from $0.010 to $0.317 per pound, compared to the
protesters’ bids of $11.00 and $10.55 per pound.[3] See
id. at 8 n.6.
DLA states that the unbalanced bids of Al-Tahouna and Wadi
Al-Sajaa put the government at risk in two ways. First,
there is a risk that a contractor who receives award based
on an unbalanced bid would terminate the contract because
it was unable to continue paying the high prices for item
2. As a result, the government would likely permit the
contractor to continue to buy and remove the lower-priced
scrap materials until another contractor could perform.
Id. at 10-12. Second, DLA states that the government would
be at risk of not receiving the overall highest price from
the protesters’ unbalanced bids if the percentages
allocated to each line item varied by even 10 percentage
points from the percentages that formed the basis for the
evaluated price. Id. at 9-10, 12. DLA explains that it has
a limited history of selling scrap materials in Qatar, and
therefore based its estimates on its experience with scrap
sales in Kuwait.
Section 14.404-2(g) of the FAR provides that “[a]ny bid
may be rejected if the prices for any line items or
subline items are materially unbalanced (see
15.404-1(g)).” FAR § 14.404‑2(g). Section § 15.404-1(g)(1)
of the FAR provides that unbalanced pricing exists when,
despite an acceptable total evaluated price, the price of
one or more contract line items is significantly
overstated or understated, as indicated by the application
of cost or price analysis techniques. While unbalanced
pricing may increase risk to the government, agencies are
not required to reject an offer solely because it is
unbalanced. L. W. Matteson, Inc., B-290224, May 28, 2002,
2002 CPD ¶ 89 at 3. An offer properly may be rejected if
the contracting officer determines that the lack of
balance in the bid or offer poses an unacceptable risk to
the government. FAR § 15.404-1(g)(3); L. W. Matteson,
Inc., supra at 3. Our Office will review for
reasonableness both an agency’s determination as to
whether an offeror’s prices are unbalanced, and an
agency’s determination as to whether an offeror’s
unbalanced prices pose an unacceptable risk to the
government. Semont Travel, Inc., B-291179, Nov. 20, 2002,
2002 CPD ¶ 200 at 3; L. W. Matteson, Inc., supra, at 4;
Enco Dredging, B-284107, Feb. 22, 2000, 2000 CPD ¶ 44 at
6.
The record shows that, with respect to item 2, plastics
and rubber residue, the protesters’ bids were more than 15
times higher than the average bids of the next five
highest bidders. With respect to the remaining line items,
the protesters’ bids were significantly lower than average
bids of the next five highest bidders, and either equal to
or lower than the lowest bids from other bidders. See AR,
Tab 3, Bid Abstract. As noted above, unbalanced pricing
exists when, despite an acceptable total evaluated price,
the price of one or more contract line items is
significantly overstated or understated. FAR §
15.404-1(g)(1). Given the disparity between the two firms’
bids and the average of the nearest five bids, DLA
reasonably concluded that Al-Tahouna’s and Wadi Al-Sajaa’s
bids for line item 2 were significantly overstated in
comparison to competitors’ bid and therefore unbalanced.
(Al-Tahouna Al-Ahliah General
Trading & Contracting Company, WLL; Wadi Al-Sajaa Scrap &
Metal Waste Trading Company, LLC; Royal Bridge
International General Trading & Contracting Company, WLL
B-412769, B-412769.2, B-412769.3: May 9, 2016) (pdf)
Ultimate Concrete challenges the Army’s determination that
Fortis’ original bid was not materially unbalanced. The
Army found that Fortis’ original bid was not materially
unbalanced and did not warrant rejection as non-responsive
because, although it was mathematically unbalanced with
the optional access road line item (CLIN 0007) being
disproportionately high, it was likely that the NTP for
CLIN 0007 would be delayed--or potentially never
issued--due to ongoing condemnation proceedings, thus
reducing the likelihood of any risk of an advance payment
to Fortis. See AR, Tab 16, Contracting Officer’s Memo. to
the PARC (Sept. 17, 2015), at 1; Tab 23, Contracting
Officer’s Letter (Sept. 28, 2015), at 1. We conclude that
the agency reasonably found that Fortis’ bid was not
materially unbalanced; for this reason, we find no basis
to conclude that award to Fortis was improper.
As addressed above, “[t]he Government may reject a bid as
nonresponsive if the prices bid are materially unbalanced
between line items or subline items.” FAR clause
52.214-19(d). A bid is materially unbalanced if it is
based on prices significantly less than cost for some work
and prices which are significantly overstated in relation
to cost for other work. Id.; RonsonsSDVOSB P&L JV-1,
B‑410605, Jan. 6, 2015, 2015 CPD ¶ 1 at 4. While
unbalanced pricing may increase risk to the government,
agencies are not required to reject a bid solely because
it is mathematically unbalanced. InfoZen, Inc., B-411530,
B-411530.2, Aug. 12, 2015, 2015 CPD ¶ 270 at 7. Rather,
where the contracting officer receives an unbalanced bid,
the contracting officer is required to consider the risks
to the government associated with the unbalanced pricing
in making the award decision, and whether a contract will
result in unreasonably high prices for contract
performance. Id.; EncoDredging, B-284107, Feb. 22, 2000,
2000 CPD ¶ 44 at 5. Our Office will review for
reasonableness both the agency’s determination as to
whether a bidder’s prices are unbalanced, and an agency’s
determination as to whether a bidder’s unbalanced prices
pose an unacceptable risk to the government. Ronsons
SDVOSB P&L JV-1, supra.
Based on the above standards, we find no basis to sustain
the protest. First, Ultimate Concrete argues that the
awardee’s bid was so mathematically unbalanced that it
should have been rejected as non-responsive on that basis
alone. Protester’s Comments (Nov. 23, 2015) at 27-29. As
set forth above, however, an agency is not required to
reject a bid merely because it is mathematically
unbalanced. Rather, the agency must reasonably consider
any attendant risks associated with the unbalanced
pricing. InfoZen, Inc., supra. Thus, the protester’s
contention that the mathematical imbalance of Fortis’
original bid, standing alone, was sufficient to warrant
rejection of the bid is without merit.
Next, Ultimate Concrete argues that the awardee improperly
front-loaded its bid, creating an unreasonable risk of
advance payment, where it overbid the price for the
optional access road line item (CLIN 0007), which the
protester argues will logically be completed first.
Protester’s Comments (Nov. 23, 2015) at 32‑33, 36‑38. As
an initial matter, we note that FAR § 14.404-2(g) states
that “any bid may be rejected if the prices for any line
items or subline items are materially unbalanced (see
15.404‑1(g)).” The current version of FAR § 15.404-1(g),
postdating the 1997 FAR part 15 rewrite, no longer
provides for rejection of unbalanced bids where acceptance
would be tantamount to an advance payment, and instead
requires the agency to perform a risk analysis. See FAR;
Part 15 Rewrite; Contracting by Negotiation & Competitive
Range Determination, 62 Fed. Reg. 51224, 51225 (Sept. 30,
1997); Gulf Master Gen. Trading, LLC, B-407941.2, July 15,
2013, 2013 CPD ¶ 210 at 6 n.2; JND Thomas Co., Inc.,
B-402240, Jan. 28, 2010, 2010 CPD ¶ 40 at 3 n.2. Thus, a
bid may not automatically be rejected merely because it
presents some risk of an advance payment; rather, the
government must conduct a reasonable assessment of the
potential risks.
In any event, the Army here reasonably determined that the
risk of an advance payment to Fortis was minimal. Ultimate
Concrete’s advance payment theory is predicated on its
belief that the optional access road work covered by CLIN
0007 will need to be performed prior to the base or
optional fence replacement work. See Protest (Oct. 5,
2015) at 11-13. The agency, however, reasonably concluded
that this scenario was unlikely. The IFB and associated
pre-bid questions and answers indicate that, although the
Army contemplated awarding the base and optional fence
replacement line items (CLINs 0001 and 0004) and optional
access road line item (CLIN 0007) simultaneously, each
CLIN would be subject to different NTPs, which might not
be issued simultaneously. IFB at 4; id., amend. No. 0004,
at 2; AR, Tab 6, Pre-Bid Inquiry Contractor Report, at 1.
Furthermore, the Army, both prior to award and in response
to the protest, articulated that the NTP for CLIN 0007 may
be delayed--or never even issued--due to ongoing
condemnation proceedings. AR, Tab 15A, Email from
Contracting Specialist (Sept. 15, 2015), at 1; COSF (Nov.
9, 2015) at 9 n.1. Based on these facts, the Army
determined that the risk that the government would be
subject to making an unreasonable advance payment to
Fortis based on the award and completion of the optional
access road CLIN prior to the base work was doubtful. See
AR, Tab 16, Contracting Officer’s Memo. to the PARC (Sept.
17, 2015), at 1; Tab 23, Contracting Officer’s Letter
(Sept. 28, 2015), at 1. On this record, we find that the
Army reasonably evaluated the potential risk of advance
payment as part of its unbalanced pricing analysis.
Alternatively, Ultimate Concrete argues that, if the
optional access road contract line item is not performed
first, the Army unreasonably failed to consider the
performance risks associated with Fortis’ underbidding of
the base and optional fence replacement line items (CLINs
0001 and 0004). Protester’s Comments (Nov. 23, 2015) at
33-34. We find, however, that the protester’s arguments
that the agency failed to reasonably evaluate the
potential risk associated with Fortis’ underbidding of the
base and optional fence replacement line items (CLINs 0001
and 0004) in the event that the optional access road line
item (CLIN 0007) is not performed are irrelevant to the
Army’s unbalanced pricing analysis. The concern with
unbalanced pricing is that the government will ultimately
pay unreasonably high prices. FAR §§ 14.408-2,
15.404-1(g); Burney & Burney Constr. Co., Inc.,
B‑292458.2, Mar. 19, 2004, 2004 CPD ¶ 49 at 2 n.1; HSG
Philipp Holzmann Technischer Serv. GmbH, B-289607, Mar.
22, 2002, 2002 CPD ¶ 67 at 6. Vendors are not prohibited
from submitting below-cost quotes on fixed-price
contracts, and the ability of a vendor to perform at the
price offered is an issue of contractor responsibility,
not unbalanced pricing. JCMCS, B-409407, Apr. 8, 2014,
2014 CPD ¶ 125 at 2; Semont Travel, Inc., B‑291179, Nov.
20, 2002, 2002 CPD ¶ 200 at 5; Atlantic Maint., Inc.,
B-239621.2, June 1, 1990, 90-1 CPD ¶ 523 at 1-2.
Therefore, we find no basis to sustain Ultimate Concrete’s
objection that the Army failed to consider the risk
associated with Fortis bidding a price too low to perform
the base and optional fence replacement CLINs as part of
its unbalanced pricing analysis.
(Ultimate
Concrete, L.L.C. B-412255, B-412255.2: Jan 13, 2016)
(pdf)
Although competition for a task order under a
multiple-award contract is generally governed by Part 16
of the Federal Acquisition Regulation (FAR), the concept
of unbalanced pricing used by the RFP here is defined in
FAR Part 15, which we therefore apply by analogy. See AIS
Eng’g, Inc., B‑410246, B-410246.2, Nov. 21, 2014, 2015 CPD
¶ 5 at 3 (unbalancing analysis applied to task order
evaluation); Triumvirate Envtl., Inc., B-406809, Sept. 5,
2012, 2012 CPD ¶ 244 at 5 n.3 (unbalancing analysis
applied by analogy to competition for blanket purchase
agreement under FAR subpart 8.4). Unbalanced pricing
exists when, despite an acceptable total evaluated price,
the price of one or more contract line items is
significantly over or understated as indicated by the
application of cost or price analysis techniques. FAR §
15.404‑1(g)(1). The areas where the risk of unbalanced
pricing is greatest include pricing where base quantities
and option quantities are separate line items, or where
the evaluated price is the aggregate of estimated
quantities to be ordered under separate line items of an
indefinite-delivery contract. FAR §
15.404‑1(g)(1)(ii)-(iii). Therefore, a contracting officer
“shall analyze” offers with separately-priced line items
or subline items, to detect unbalancing. FAR §
15.404-1(g)(2). Where unbalancing is detected, the
contracting officer must then consider the risk posed,
including the risk of paying an unreasonable price, and
must consider whether to reject the offer if the risk is
unreasonable. FAR § 15.404‑1(g)(2)-(3).
To prevail on an allegation of unbalanced pricing, a
protester must first show that one or more prices are
overstated. AIS Eng’g, Inc., supra, at 3. Even then, while
unbalanced pricing may increase risk to the government, an
agency is not required to reject an offer solely because
it is unbalanced. Ronsons SDVOSB P&L JV-1, B‑410605, Jan.
6, 2015, 2015 CPD ¶ 1 at 4. Rather, the contracting
officer is required to consider the risks to the
government associated with the unbalanced pricing in
making the award decision, and whether a contract will
result in unreasonably high prices for contract
performance. Id. Our Office will review for reasonableness
both the agency’s determination as to whether an offeror’s
prices are unbalanced, and an agency’s determination as to
whether an offeror’s unbalanced prices pose an
unacceptable risk to the government. Id.
Even then, our Office will not sustain a protest unless
the protester demonstrates a reasonable possibility that
it was prejudiced by the agency’s actions, that is, unless
the protester demonstrates that, but for the agency’s
actions, it would have had a substantial chance of
receiving the award. McDonald Bradley, B-270126, Feb. 8,
1996, 96-1 CPD ¶ 54 at 3; see Statistica, Inc. v.
Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996). Where
an agency overlooks unbalanced pricing, and thus fails to
consider the risk it poses, we will not sustain the
protest if no material risk to the government from this
unbalancing is apparent from the record, because the
agency’s error has not prejudiced the protester. Citywide
Managing Servs. of Port Washington, Inc., B-281287.12,
B-281287.13, Nov. 15, 2000, 2001 CPD ¶ 6 at 8. Moreover,
if the risk posed by unbalanced pricing is that the agency
will not obtain the lower pricing--for example, due to the
potential that the agency’s requirement may change, or
requirements may be deleted--but the record provides no
basis to conclude that such changes are likely, the risk
is merely speculative and does not provide a basis to
sustain the protest. Id. at 9.
In its protest, while InfoZen argues extensively that the
awardee’s price is unbalanced, it has not shown that the
VA faces a significant risk of failing to obtain the
benefit of Smartronix’s lower pricing offered in the later
years of the contract. Rather, InfoZen only speculates
that it is possible that the VA will not exercise options
for the later contract years. Protester’s Supplemental
Comments at 3. Other than this brief speculation, however,
InfoZen provides no facts to show that it is likely that
the VA’s needs will change such that the agency will not
need these services for much or all of the term of the
contract. Absent such evidence that the risk of
Smartronix’s unbalanced pricing was significant, we cannot
find that InfoZen has been prejudiced. Accordingly, we
deny this ground of protest. (InfoZen,
Inc. B-411530, B-411530.2: Aug 12, 2015) (pdf)
WW Contractors challenges the agency’s determination that
its price proposal was unbalanced and unrealistic. The
firm argues that, even if there was an error in its price
proposal, based on the total contract price, including
overhead and profit, its proposal “was very viable.”
Comments at 7.
(sentences deleted)
As noted above, the
RFP stated that an offer might be rejected as
non-responsive if it was materially unbalanced as to
prices for the initial and option periods, explaining that
"an offer is unbalanced when it is based on prices which
are significantly less than cost for some work, and prices
which are significantly overstated for other work." RFP at
13. Thus, under the RFP’s terms, to find a price
unbalanced, the agency had to find both an understatement
of price in some respect and an overstatement of price in
another. The record does not support a finding that the
protester’s price is unbalanced. See Ronsons SDVOSB P&L
JV-1, B-410605, Jan. 6, 2015, 2015 CPD ¶ 1 at 4.
The agency explains its decision to reject WW Contractor’s
proposal as follows:
The Contracting
Officer was concerned about WW’s pricing because even
though WW’s overall price was not unreasonable, WW’s
option years prices for the [CLIN] work as compared to
its base price for the [CLIN] work and the option year
prices for the [CLIN] work from all of the other
offerors were significantly understated. She was
concerned that there were significant risks to the
Government of WW’s nonperformance or poor performance
due to WW’s unbalanced pricing if it were to be awarded
the Contract, and she determined that these risks were
unacceptable.
Agency Legal
Memorandum and Contracting Officer’s Statement (Agency
Memorandum) at 7.
While the [Source Selection Decision Document] SSDD bears
out the concern that WW Contractors’ price for this one
particular CLIN for each of the option years was
significantly understated, it does not show a concern on
the part of the agency that the protester’s low price for
this one CLIN was accompanied by a commensurately high
price in another portion of the firm’s price proposal.
Moreover, it is not apparent from WW Contractor’s price
proposal that the significantly understated price for this
one CLIN was accompanied by significant overstatement of
prices elsewhere in the firm’s proposal. See generally AR,
exh. 2, WW Contractor’s Proposal. Thus, the record does
not evidence that the protester’s price proposal was
unbalanced.
However, the [source selection authority] SSA also
articulated a concern that the protester’s price was
unrealistically low with respect to this particular CLIN,
and that there was risk of nonperformance or poor
performance owing to the protester’s low price. See AR,
exh. 6, SSDD, at 48. Where a solicitation contemplates the
award of a fixed-price contract, an agency may provide in
the solicitation for the use of a price realism analysis
for the purpose of measuring an offeror’s understanding of
the requirements. IBM Corp., B-299504, B-299504.2, June 4,
2007, 2008 CPD ¶ 64 at 10-11. Price realism may also be
used by the agency to evaluate whether an offeror can
realistically perform its technical solution at the fixed
price proposed in order to assess the risk inherent in an
offeror’s proposed approach. DynCorp Int’l LLC,
B-407762.3, June 7, 2013, 2013 CPD ¶ 160 at 8-9; Triad
Int’l Maint. Corp., B‑408374, Sept. 5, 2013, 2013 CPD ¶
208 at 8. The RFP here provided for such an analysis. RFP
at 447.
As noted above, GSA’s analysis of WW Contractor’s price
proposal showed that the relevant CLIN accounted for
approximately three percent of the firm’s monthly cost of
performance during the option years. AR, exh. 6, SSDD at
48. The agency found this amount unrealistically low in
comparison to the median cost of 12.9 percent for each of
the other offerors. Id. The unredacted report provided to
our Office for review confirms the agency’s analysis in
this regard. Further, a review of the prices submitted by
other offerors, as well as historical price data
considered by the agency, shows that the CLIN represented
a substantial portion of the total scope of work, and that
the protester significantly understated, by an order of
magnitude, the relevant CLIN price for the option years.
While the protester argues that there was little risk to
the government even if it mistakenly submitted a low price
for the relevant CLIN because the overall contract would
have remained profitable, such an assertion is not
apparent from the firm’s proposal. Protester’s Supp.
Comments at 4; see generally AR, exh. 2, WW Contractor’s
Proposal. Moreover, this argument does not address the
risk that WW Contractors lacked understanding of the scope
of work contemplated by this CLIN; a valid concern when
conducting a price realism analysis. See IBM Corp., supra,
at 10-11. Based on the record, we have no basis to
question the SSA’s concern that there were significant
risks to the agency of nonperformance or poor performance
by WW Contractors due to the firm’s price proposal, or to
find the rejection of the proposal on this basis
unreasonable. (WW
Contractors, Inc. B-410825: Feb 26, 2015) (pdf)
Under FAR clause 52.214-19(d), “[t]he Government may reject a
bid as nonresponsive if the prices bid are materially unbalanced
between line items or subline items.” A bid is materially
unbalanced if it is based on prices significantly less than cost
for some work and prices which are significantly overstated in
relation to cost for other work. Id.; MCI Constructors, Inc.,
B-274347, B‑274347.2, Dec. 3, 1996, 96-2 CPD ¶ 210 at 5. While
unbalanced pricing may increase risk to the government, agencies
are not required to reject an offer solely because it is
unbalanced. W.B. Constr. & Sons, Inc., B-405818, B-405818.2,
Jan. 4, 2012, 2012 CPD ¶ 17 at 6. Rather, where the contracting
officer receives an unbalanced bid or offer, the contracting
officer is required to consider the risks to the government
associated with the unbalanced pricing in making the award
decision, and whether a contract will result in unreasonably
high prices for contract performance. Id.; Enco Dredging,
B-284107, Feb. 22, 2000, 2000 CPD ¶ 44 at 5. Our Office will
review for reasonableness both the agency’s determination as to
whether an offeror’s prices are unbalanced, and an agency’s
determination as to whether an offeror’s unbalanced prices pose
an unacceptable risk to the government. W.B. Constr. & Sons,
Inc., supra, at 6; Enco Dredging, supra, at 6.
The record here shows that, even if the awardee’s bid for CLIN
0005 was materially understated, Glen/Mar’s proposed pricing for
the base scope of work was not materially overstated. The eight
bids received by the agency for the base scope of work ranged
from the protester’s low bid of $1,287,500 to a high bid of
$2,065,000; the awardee’s bid for the base scope of work,
$1,544,779, was the second lowest. See, AR, Tab 10, Abstract of
Bids, ¶ 9. Therefore, the agency reasonably determined that
Glen/Mar’s bid for the base scope of work was not materially
overstated based on the competitive bids received. See, e.g.,
AR, Tab 11, CO’s Determination of Responsibility and Price
Reasonableness, at 6; FAR clause 52.214‑19(d) (providing that
unbalanced pricing exists only when there are both significantly
below cost and overstated line items).
In any event, even if we found Glen/Mar’s bid to be materially
unbalanced, the Corps reasonably concluded that acceptance of
the bid did not create an unacceptable risk to the government.
Here, the optional requirements are reasonably certain to exist
and there is a reasonable expectation that funds will be
available to permit exercise of the options. Prior to issuing
the IFB, the CO determined that it was in the best interest of
the government to include option CLINs in the evaluation for
award because, although the full requirement could not be funded
at the time of the IFB’s issuance, the need for the optional
work was verified and had been budgeted for in the future. AR,
Tab 5, CO’s Determination to Include Options, ¶ 1.a. In light of
the verified need and budgeting for the work, the agency
concluded that there was a “reasonable likelihood that the
option CLINs will be exercised.” Id. ¶ 1.d. In the time since
the award of the base work, the agency represented that it has
obtained the funds necessary to award optional CLINs 0005 and
0007. See CO’s Statement at 9. Thus, the record does not
demonstrate a reasonable basis to doubt that the acceptance of
Glen/Mar’s bid will result in the lowest overall cost to the
government. (Ronsons SDVOSB P&L
JV-1, B-410605: Jan 6, 2015 (pdf)
Gulf Master
argues that the agency unreasonably rejected its proposal as
unbalanced where its pricing reflects its underlying cost
structure, which differs from that of the incumbent, ASCS. Id.
As discussed below, the protester’s arguments are misplaced and
without merit.
As a general matter, unbalanced pricing may increase risk to the
government and can result in payment of unreasonably high
prices. FAR § 15.404-1(g); Semont Travel, Inc., B-291179, Nov.
20, 2002, 2002 CPD ¶ 200 at 3. Unbalanced pricing exists where,
despite a proposal’s low overall price, individual line item
prices are either understated or overstated, as indicated by the
application of cost or price analysis techniques. FAR §
15.404-1(g); Semont Travel, Inc., supra. The risks of unbalanced
pricing can occur in several contexts, to include instances
where a solicitation establishes base quantities and option
quantities as separate line items, as in this case. FAR §
15.404-1(g)(1). Where the level of service for each period is
essentially the same, a large price differential between the
base and option periods, or between one option period and
another, is prima facie evidence of unbalancing. See, e.g.,
Technology Services International, Inc., B-278050, Nov. 25,
1997, 97-2 CPD ¶ 152 at 2.
Agencies are not, however, required to reject an offer solely
because it is unbalanced. FAR § 15.404-1(g)(3). Rather, where an
unbalanced offer is received, the contracting officer is
required to consider the risks to the government associated with
the unbalanced pricing in making the award decision, including
the risk that the unbalancing will result in unreasonably high
prices for contract performance. FAR § 15.404-1(g)(2). An offer
may be properly rejected if the contracting officer determines
that the lack of balanced pricing poses an unacceptable risk to
the government. Id.; L. W. Matteson, Inc., B-290224, May 28,
2002, 2002 CPD ¶ 89 at 3. Our Office will review for
reasonableness both an agency's determination as to whether an
offeror's prices are unbalanced, and an agency's determination
as to whether an offeror's unbalanced prices pose an
unacceptable risk to the government. See L. W. Matteson, Inc.,
supra, at 4; Gemmo Impianti SpA, B-290427, Aug. 9, 2002, 2002
CPD ¶ 146 at 2 n.1.
As noted above, Gulf Master contends that its pricing is not in
fact unbalanced since it reasonably reflects its actual costs.
In this regard, the protester explains that its relatively high
base year prices are a result of start-up costs not incurred by
the incumbent--ASCS. Protester’s Comments at 4-9. Likewise, Gulf
Master explains that it uses the proceeds from the sale of
vehicles after the second option year of the contract to reduce
the prices it charges the government in the final two years of
the contract. Id. at 9. Although ASCS disputes the rationale
underlying Gulf Master’s claims regarding its costs, we need not
resolve these issues. As discussed below, the Agency was not
required to consider the protester’s actual costs in conducting
its unbalanced pricing analysis.
Unbalanced pricing is determined “by the application of cost or
price analysis techniques.” FAR § 15.404-1(g)(1) (emphasis
added). Accordingly, the type of analysis used--cost or
price--is within the agency’s discretion. In this instance, the
Air Force used several price analysis techniques identified in
the FAR to assess Gulf Master’s prices for balance.
Specifically, the agency compared the protester’s proposed
pricing to the prices of other vendors and the IGE, and
considered the year-to-year pricing change of CLINs within the
protester’s proposal for essentially the same services. See FAR
§ 15.404-1(b); cf. HMR Tech, LLC, B-295968, B-295968.2, May 19,
2005, 2005 CPD ¶ 101 (explaining that “The [FAR] provides a
number of price analysis techniques that may be used to
determine whether prices are reasonable and realistic, including
comparison of the prices received with each other; comparison of
previously proposed prices for the same or similar items;
comparison with the independent government estimate; and
analysis of pricing information provided by the offeror.”).
Because a price analysis, by its nature, does not involve a
consideration of the separate cost elements and proposed profit
underlying a proposed price, see FAR § 15.404-1(b), information
about the protester’s actual costs were not relevant
considerations.
The protester’s contention that prices should not be found
unbalanced if an offeror has legitimate cost-based reasons to
justify higher prices earlier in contract performance appears to
be based on older decisions by this Office, issued when the
FAR’s guidance regarding unbalanced pricing was materially
different. For example, in its comments on the agency’s report,
the protester cites our decision in Eastex Maritime, Inc.,
B-256164, May 19, 1994, 94-1 CPD ¶ 340, which indicated that the
“determinative question in assessing mathematical unbalancing is
whether the pricing structure is reasonably related to the
actual costs to be incurred in each year of the contract.”
Protester’s Comments at 4. This decision, however, was issued at
a time when the FAR suggested a cost-based unbalancing analysis.
In relevant part, the FAR indicated a price “is mathematically
unbalanced if it is based on prices which are significantly less
than cost for some contract line items and significantly
overstated in relation to cost for others.” FAR § 15.814(b) (FAC
90-44) Dec. 31, 1996 (emphasis added). This language, however,
was removed from the FAR’s section on unbalanced pricing in
1997. See Part 15 Rewrite, 62 FR 51224, 51243 (Sept. 30, 1997).
Further, we have no basis to question the reasonableness of the
agency’s conclusion that Gulf Master’s pricing was unbalanced.
The FAR provides that prices are unbalanced if they are
“significantly over or understated.” FAR § 15.404-1(g)(1). In
order for prices to be considered over or understated, they must
necessarily be compared to some relevant baseline. As discussed
above, the Air Force found that Gulf Master’s base year prices
were significantly overstated when compared to the prices of the
other offerors and the IGE. AR, Exh. 17, Unbalanced Pricing
Report, at 1-5. Likewise, Gulf Master’s prices for each of the
20 vehicle types were significantly higher in the base year than
its prices for the same types of vehicles in the last two years
of the contract. Id. at 10-11. As previously indicated, where
the level of service for each period is essentially the same, as
was the case under this solicitation, a large price differential
between the base and option periods, or between one option
period and another, is prima facie evidence of unbalancing.
We also have no basis to question the reasonableness of the Air
Force’s conclusion that the protester’s unbalanced pricing posed
an unacceptable risk to the government. The Air Force found that
the next-lowest-priced offeror, which offered [deleted], had a
lower price than Gulf Master through the second to last month of
the final option year. AR, Exh. 21, Risk Analysis Report, at 2.
Thus, the Air Force reasonably found that Gulf Master’s proposal
might not actually result in the lowest cost if any of the
option years were not exercised, or if the contract was
terminated before the end of the final option year. Id. Further,
the agency found that the difference in prices between ASCS and
Gulf Master was such that if the contract did not continue
beyond the second option year, it would pay substantially more
under Gulf Master’s pricing than under ASCS’s pricing. Id. at
1-2. This substantial price disparity supports the
reasonableness of the Air Force’s conclusion that Gulf Master’s
unbalanced pricing posed an unacceptable risk that it would pay
unreasonably high prices for contract performance if some of the
options were not exercised. Id.; see DGS Contract Services,
Inc., B-250306, Jan. 15, 1993, 93-1 CPD ¶ 49 at 3 (denying
protest that agency improperly rejected bid under unbalanced
pricing analysis when it did not become low until the eleventh
month of the last option year).
Finally, Gulf Master argues that the Agency’s preference for a
[deleted] structure, which the protester contends only the
incumbent can propose, is unreasonable and constitutes an
irrational preference for one business model over another.
Protester’s Comments to Intervenor’s Response, at 8. To the
contrary, it was entirely rational for the agency to avoid an
unacceptable level of risk that it will pay more than the market
value of the services it receives. As discussed above, FAR
15.404-1(g) provides the mechanism by which an agency can avoid
such risks.
While Gulf Master contends its pricing structure is a “sound and
logical way” for it to offer lower prices to the government, the
company’s pricing structure also posed risks to the government
that the Air Force reasonably concluded were unacceptable.
(Gulf Master General Trading, LLC,
B-407941.2, Jul 15, 2013) (pdf)
The protester
also argues that the agency’s price evaluation was flawed
because it failed to recognize that some of the awardees’
proposed labor rates were unbalanced. In this regard, ABSG
argues that “[s]ome of the offerors used reasonable/projected
rates for key [labor categories] . . . while significantly
understating rates for other [labor categories].” Protester’s
Comments at 7. In support of its unbalanced pricing argument,
ABSG claims that one offeror proposed “reasonable” rates for
labor categories with “low hour estimates” and “unreasonably
low” rates for labor categories with “high hour estimates.” Id.
There is no merit to this aspect of the protest. First,
unbalanced pricing exists where the prices of one or more items
are significantly overstated, despite an acceptable total
evaluated price (typically achieved through under pricing one or
more of the other line items). General Dynamics--Ordnance &
Tactical Sys., B-401658, B-401658.2, Oct. 26, 2009, 2009 CPD ¶
217 at 5. ABSG has not alleged that any of the awardees’ labor
rates were “significantly overstated.” Rather, the protester
merely asserts that the rates were either “understated” or
“reasonable.” Low prices are not improper and do not themselves
establish (or create the risk inherent in) unbalanced pricing.
Id.
Second, the record does not support ABSG’s assertion that one
awardee proposed unbalanced labor rates depending on whether the
labor hour estimates for a particular labor category were high
or low. The example cited by ABSG concerns labor rates for the
program manager and project manager labor categories, both of
which had the same number of estimated hours (19,200). To the
extent the protester is actually arguing that the labor hour
estimates for these categories were inaccurate--that the hours
themselves were over or understated as compared to the hours the
agency would actually order under the contract--ABSG did not
challenge the solicitation’s estimated hours. Where a
solicitation for the award of an ID/IQ contract provides
estimated quantities (in this case hours) for individual items
to be used in calculating a total price, and the estimated
quantities used go unchallenged, there is no basis for our
office to find a risk that the agency will pay unreasonably high
prices, a necessary aspect of an unbalanced pricing argument.
See Cherokee Painting LLC, B-311020.3, Jan. 14, 2009, 2009 CPD ¶
18 at 3. (ABSG Consulting, Inc.,
B-404863.7, Jun 26, 2013) (pdf)
Triumvirate first
asserts that the agency’s price analysis was unreasonable and
incorrect as a matter of law. In this regard, the agency
concluded that certain of Triumvirate’s line item prices were
“impossibly low” and showed that Triumvirate “appeared to using
their historical usage knowledge to give unbalanced pricing.”
SSDD at 7.
As a general matter, unbalanced pricing exists when, despite an
acceptable total evaluated price, the price of one or more
contract line items is significantly overstated or understated.
See, e.g., FAR § 15.404-1(g)(1); Citywide Managing Servs. of
Port Washington,Inc., B-281287.12, B-281287.13, Nov. 15, 2000,
2001 CPD ¶ 6 at 7. Unbalanced pricing may increase risk to the
government, but agencies cannot reject an offer solely because
it is unbalanced. In this regard, low prices (even below-cost
prices), are not improper and do not establish (or create the
risk inherent in) unbalanced pricing. General Dynamics--Ordnance
& Tactical Systems, B-401658, B-401658.2, Oct. 26, 2009, 2009
CPD ¶ 217 at 5; Diversified Capital, Inc., B-293105.4,
B-293105.8, Nov. 12, 2004, 2004 CPD ¶ 242 at 2 n.1; Islandwide
Landscaping, Inc., B-293018, Dec. 24, 2003, 2004 CPD ¶ 9 at 3.
Thus, where an unbalanced offer is received, the agency is
required to consider the risks to the government associated with
the unbalanced pricing in making the award decision, including
the risk that the unbalancing will result in unreasonably high
prices for contract performance. FAR § 15.404-1(g)(2); Cherokee
Painting LLC, B-311020.3, Jan. 14, 2009, 2009 CPD ¶ 18 at 3. Our
Office will review for reasonableness both an agency’s
determination whether a firm’s prices are unbalanced, and an
agency’s determination as to whether a firm’s unbalanced prices
pose an unacceptable risk. Semont Travel, Inc., B-291179, Nov.
20, 2002, 2002 CPD ¶ 200 at 3.
According to the agency, in the evaluation of Triumvirate’s
price quotation, the VA evaluators found numerous line items
priced at $5, which they believed were understated and indicated
that Triumvirate was “engaging in unbalanced pricing as they
understood what line items could be priced lower based on
historical usage.” CO Statement at 2. However, in this case, the
RFQ set forth estimated quantities on which vendors based their
prices, and the agency has not indicated that these estimates
are incorrect. Thus, there is no basis to conclude that any
unbalanced pricing, to the extent it exists, will result in the
government actually paying higher prices. See Accumark, Inc.,
B-310814, Feb. 13, 2008, 2008 CPD ¶ 68 at 4 (explaining that if
estimates for task order contract are reasonably accurate, then
evidence of mathematical unbalancing generally does not present
a risk that the government will pay higher prices).
Further, in explaining to our Office his determination that
there was unbalanced pricing, the CO engaged in a post hoc
review of Triumvirate’s rates, procedures, and performance under
prior task orders for hazardous waste removal as the incumbent
contractor to justify the agency’s concerns regarding
Triumvirate’s pricing. For example, in response to the protest,
the CO alleged that invoices from prior task orders indicated
that Triumvirate “will send two chemists when a chemist and
technician will suffice,” “will charge for travel time to and
from the site,” and will “spend an extraordinary amount of time
on each site.” CO Statement at 3. Based on these considerations,
the CO concluded that Clean Harbors’ quotation will save
significant amounts of money (despite its higher evaluated
price), and that Triumvirate may utilize “higher priced labor
categories and travel time to offset reduced line item pricing.”
Id.
In his explanation, the CO does not provide any documentation
suggesting that Triumvirate’s prices for particular line items,
such as the rates for chemists, were overstated. In this regard,
it is not apparent how the agency could conclude that any
particular line item prices were overstated, where the record
reflects that the agency conducted its price reasonableness
evaluation on a line item basis, and found Triumvirate’s pricing
to be “reasonable, as their line item pricing was less than that
of their GSA schedule pricing.” SSDD at 7. Rather, the CO’s post
hoc analysis here is apparently premised on the presumption that
Triumvirate may perform inefficiently, thereby resulting in
higher pricing. This presumption, which is not suggested in the
contemporaneous record, has no basis in Triumvirate’s pricing
per se. Instead, the presumption is based on past performance
concerns that are not contained in the contemporaneous
evaluation record, and which appear to be inconsistent with
Triumvirate’s rating of “low” risk under the past performance
factor.
Moreover, the agency’s post hoc concerns do not reasonably
support a finding that Triumvirate’s pricing presented an
unreasonable risk to the government. In this regard, there is no
basis to conclude that estimates contained in the solicitation
are inaccurate or that the BPA is subject to the type of
manipulation presumed by the agency. As acknowledged by the CO,
because the BPA merely establishes the unit prices for the
schedule items to be ordered on a task basis, when the
government requests quotes for future BPA orders, the agency
will be in a position to specifically consider, before placing
any order, whether the selected BPA holder will be using an
appropriate level of effort and labor mix to perform the
required work. CO Statement at 4.
In sum, we find that the CO failed to reasonably identify any
risk to the government inherent in Triumvirate's quotation of
multiple $5 line items. It is also apparent that Triumvirate was
prejudiced, where the SSDD in this procurement included a
negative inference against Triumvirate’s price quotation, noting
that Triumvirate’s pricing was “unbalanced.” Accordingly, we
conclude that the agency’s price analysis was unreasonable, and
sustain the protest on that basis. (Triumvirate
Environmental, Inc., B-406809, Sep 5, 2012) (pdf)
Unbalanced
pricing exists where the prices of one or more line items are
significantly overstated, despite an acceptable total evaluated
price (typically achieved through underpricing of one or more
other line items). See Federal Acquisition Regulation (FAR)
sect. 15.404‑1(g)(1); Legacy Mgmt. Solutions, LLC, B‑299981.2,
B-299981.4, Oct. 10, 2007, 2007 CPD para. 197 at 5; Triple H
Servs., B-298248, B-298248.2, Aug. 1, 2006, 2006 CPD para. 115
at 2.
Here, JND has produced no definitive evidence that CJW's prices
are significantly overstated. While higher than the IGE and
JND's prices, CJW's price for line item No. 3 is lower than that
of bidder Furby Construction Co., Inc. and its line item No. 9
price is lower than that of bidder Cutting Edge Concrete
Services, Inc. See Reece Contracting, Inc., B‑285666, Aug. 21,
2000, 2000 CPD para. 135 at 4 (prices not overstated where they
fall within range of government estimate and other bids).
Similarly, JND has not shown that CJW's $.01 prices for line
item Nos. 4 and 10 are understated. In this regard, the agency
accepted CJW's explanation that its lower prices were based on
its intent to cover its costs through sale of salvaged material.
Agency Report (AR) at 5. Below-cost prices on fixed-price
contracts are not prohibited, see Reece Contracting, Inc.,
supra, at 2 n.1, and whether a bidder can perform at its bid
price is a matter of bidder responsibility, which is not
reviewable by our Office absent circumstances not present here.
See Bid Protest Regulations 4 C.F.R. sect. 21.5(c) (2009);
Ventura Petroleum Servs., Inc., B‑281278, Jan. 21, 1999, 99-1
CPD para. 15 at 6.
In any case, even where a firm's pricing is found to be
unbalanced, an agency need not reject the bid if, after
conducting a risk analysis, it determines that award will not
result in the government's paying an unreasonably high price for
contract performance or otherwise present an unacceptable level
of risk to the government. See FAR sect.15.404-1(g)(2), (3).
The record shows that the agency conducted a risk assessment,
considering information from CJW, its prior experience with the
bidder, and the anticipated order of work. For example, in
response to the agency's inquiries, CJW confirmed its bid and
its intent to perform all work in accordance with the IFB's
specifications. Engineer's Memorandum para. 4. In connection
with its $.01 prices for line item Nos. 4 and 10, CJW explained
that it had a buyer for at least 177,000 CY of material (the
amount identified in the IFB as salvageable and a cost benefit
to bidders); that profit from the sale would cover its cost of
re-handling the material; and that, even if it failed to sell
all of the material, CJW expected that sale of a certain
percentage would produce profits sufficient to cover re-handling
of the remaining material. Id. As to other work, CJW had a
history of good performance on a number of projects with another
Corps district office, including a 2005 dredging job where CJW
demonstrated its knowledge of the sediment market by
successfully marketing all of the excavated sand. Id. para. 7.
While the IFB did not specify the order of work, the agency's
analysis showed that the contractor would have to excavate pond
Nos. 4-7 (line item No. 3) in order to provide the necessary
capacity to "store" the dredge material to be pumped from the
lake (line item No. 9), and thus would have to re‑handle
virtually all of the dry excavated material (line item No. 4)
prior to dredging. AR at 7. Further, payment for dredging (line
item No. 9) would not be made in a lump sum but, rather, would
be based on the percentage of dredging completed, and the agency
anticipated that a portion of the dredged material would have to
be re-handled (line item 10) prior to completion of the dredging
process. Engineer Declaration paras. 4, 6. At the time dredging
is complete, the agency estimates that various aspects of the
work--worth more than $1 million--will remain to be completed
and paid for, including final excavation of pond Nos. 4-7, final
levee construction, and riprap/crushed rock placement. Id. para.
7.
Based on its consideration of the above information, the agency
concluded that CJW's bid did not pose a significant risk of
non-performance or the payment of unreasonably high prices.
Contracting Officer's Statement paras. 17-18; AR at 8. In our
view, the agency's conclusion was reasonable, since CJW's plan
to offset the cost of re-handling excavated and dredged material
represented a plausible explanation for its low prices; its
conclusion was based on prior experience with CJW in which the
firm had successfully performed contracts involving the sale of
salvage material; and the expected order of work will
effectively prevent payment for all of the allegedly overstated
line items prior to performance of much of the understated items
and will include other contract line items providing incentive
to continue performance. (JND
Thomas Company, Inc., B-402240, January 28, 2010) (pdf)
Noting that Wind
River submitted significantly higher prices (than Cherokee’s) on
4 CLINs and significantly lower prices on 18, Cherokee asserts
that Wind River’s proposed CLIN pricing is unbalanced, Protest
at 3-8, and poses “a risk to Tinker Air Force Base which could
cost the government additional funds during the life of this
contract.” Protester’s Comments at 2. Cherokee concludes that
Wind River’s proposal should have been rejected.
Unbalanced pricing exists where, despite a proposal’s low
overall price, individual line item prices are either
understated or overstated. Federal Acquisition Regulation (FAR)
sect. 15.404-1(g); Semont Travel, Inc., B-291179, Nov. 20, 2002,
2002 CPD para. 200 at 3. While unbalanced pricing may increase
risk to the government, agencies are not required to reject an
offer solely because it is unbalanced. FAR sect. 15.404-1(g)(1).
Rather, where an unbalanced offer is received, the contracting
officer is required to consider the risks to the government
associated with the unbalanced pricing in making the award
decision, including the risk that the unbalancing will result in
unreasonably high prices for contract performance. FAR sect.
15.404-1(g)(2). In the context of an ID/IQ contract, as here, a
key consideration is the accuracy of the government’s quantity
estimates; if the estimates are reasonably accurate, then
evidence of mathematical unbalancing generally does not present
a risk that the government will pay unreasonably high prices for
contract performance. Accumark, Inc., B-310814, Feb. 13, 2008,
2008 CPD para. 68, at 4.
Cherokee does not challenge the accuracy of the agency’s
estimated quantities. Moreover, we find nothing in the record to
suggest that the agency was concerned about the accuracy of its
estimated quantities. Where a protester does not challenge the
estimated quantities used in the calculation of total item
prices, there is no basis in the record for us to find a risk
that the agency will pay unreasonably high prices for the items;
it follows that, in such cases, there is no basis for us to
object to mathematically unbalanced pricing. See Accumark, Inc.,
supra, at 4.
In any event, even if the estimates were in question, as noted
above, the agency conducted a risk assessment and determined
that the risk associated with Wind River’s pricing strategy was
acceptable. In this regard, the CO analyzed the risk in two
ways: by cost comparisons with recent delivery orders and by
total maximum cost. AR, Tab 1, Memorandum of Law, at 8.
Specifically, the CO compared each CLIN price with the
corresponding IGE price and then conducted an analysis of five
recent delivery orders under the current contract, which showed
that Wind River’s prices would result in a lower cost than the
IGE on four of the five. AR, Tab 12, Final Price Competition
Memorandum, at 15 (not released to the protester). The CO also
assessed the maximum possible liability to the Air Force by
comparing the maximum cost under each IGE price with the maximum
cost under each of Wind River’s CLIN prices. AR, Tab 1,
Memorandum of Law, at 8. Other than asserting generally that
Wind River’s pricing may pose a risk to the agency, Cherokee
does not challenge this risk assessment, and we find no basis
for questioning it. Thus, to the extent that Wind River’s
pricing may be viewed as unbalanced, the agency has satisfied
the FAR requirement by reasonably determining that the risks of
any unbalancing were not significant enough to render its offer
unacceptable. (Cherokee Painting LLC,
B-311020.3, January 14, 2009) (pdf)
PEMCO's prices were not unbalanced, since any overstatement of
its CLIN 0001 price was not significant. PEMCO's CLIN 0001 price
was only 23 percent higher than the government's estimate; this
is not an amount significant enough to require that the offer be
considered unbalanced. Cf. Baxter Healthcare Corp.; Abbott
Labs.--Recon. , B253455.3, B253455.4, May 10, 1994, 941 CPD 301
at 4, n.2 (base year price 44 percent above option year prices
did not constitute impermissible frontloading). In any case, the
agency fully discussed the CLIN 0001 pricing with PEMCO, and
ultimately determined that it was reasonable; this satisfied the
agency's obligation to ensure that the pricing did not pose an
unacceptable risk. See PharmChem, Inc. , B-291725.3 et al., July
22, 2003, 2003 CPD 148 at 8. (Diversified
Capital, Inc., B-293105.4; B-293105.8, November 12, 2004) (pdf)
There is no basis for concluding
that STL’s pricing is unbalanced. PharmChem does
not identify any specific prices that it believes are
significantly overstated and the
record does not indicate that any of STL’s prices are
overstated. In this latter regard,
for example, in the base year, STL’s line item prices exceed the
government estimate
under only 4 of 13 line items. Further, while STL’s proposal of
$0.00 for [deleted]
labor categories could be considered “understated,” such labor
rate proposals alone
do not establish that a bid is unbalanced. See SMC Info. Sys.,
B-224466, Oct. 31,
1986, 86-2 CPD ¶ 505 at 5. In any case, even if STL’s labor rate
pricing evidenced
unbalancing, it is clear that the agency considered the risk
involved; it specifically
inquired about STL’s $0.00 labor rate pricing, and had no
concern that these rates
would result in a higher contract price. Source Selection
Decision at 6-7. (PharmChem, Inc., B-291725.3;
B-291725.4; B-291725.5, July 22, 2003) (pdf)
While the agency here analyzed the unbalancing in terms of an "advance payment," that term
does not appear in the discussion of unbalanced pricing in the revised Part
15 of the FAR, which applies to solicitations issued after January 1, 1998,
such as the subject IFB. We believe, however, that the agency's analysis
remains valid when couched in terms of the risk that IBI's pricing poses to
the government. (Industrial
Builders, Inc., B-283749, December 29, 1999)
The Navy was satisfied, based on
Phillips's response and Phillips's extensive experience
performing housing maintenance contracts, that the rationale
behind Phillips's pricing was sound, and that Phillips was aware
of the risks involved in that strategy. The Navy also concluded
from Phillips's explanation that its pricing was fair and
reasonable. ARLS at 7. While Red River disagrees with the Navy's
conclusions, in our view, the Navy could reasonably conclude
that Phillips's pricing represented a legitimate business
judgement that did not pose an unacceptable risk to the
government, and that it would not pay an unreasonably high price
for performance. Accordingly, the Navy was not required to
reject Phillips's proposal. (Red
River Service Corporation, B-282634; B-282634.2, July 15,
1999) |