New
It is a vendor’s responsibility, when transmitting its
quotation electronically, to ensure the delivery of its
quotation to the proper place at the proper time. Team
Housing Solutions, B-414105, Feb. 10, 2017, 2017 CPD ¶ 55
at 4. Moreover, as a general matter, we have found that
language in an RFQ requesting quotations by a certain date
does not establish a firm closing date for receipt of
quotations, absent a late submission provision expressly
providing that quotations must be received by that date to
be considered. M.Braun, Inc., B-298935.2, May 21, 2007,
2007 CPD ¶ 96 at 3. On the other hand, where, as here, the
RFQ contains the FAR provision 52.212-1(f), which
expressly limits the agency’s consideration of quotations
that are received late, a procuring agency may not accept
a late quotation that is not submitted in accordance with
that FAR provision. Peers Health, B-413557.3, Mar. 16,
2017, 2017 CPD ¶ 93 at 3.
Here, we find unobjectionable the agency’s decision not to
consider VS Aviation’s quotation. The record ultimately
supports the protester’s contention that it attempted to
submit its quotation to the contracting officer, prior to
the submission deadline, as attachments to two emails. See
Comments, attach. 2, Decl. of VS Aviation Director, at 1.
The first email was 21 megabytes (MB), and the other that
was 24 MB. Id. The Air Force explains that the size limit
for incoming emails is 10 MB, and consequently, each of VS
Aviation’s emails was “blocked due to its size.” COS at 1.
As such, the record confirms that neither the contracting
officer nor the contract specialist received VS Aviation’s
quotation in their email mailboxes prior to when
quotations were due at 12:00 p.m. EDT on May 18. Rather,
the first time the agency received a quotation from VS
Aviation was on June 26, more than a month after the
submission deadline and more than a week after the award
was made. See id. Consequently, because the quotation was
received well after the time for the receipt of
quotations, the agency’s decision not to consider the late
quotation is unobjectionable. See Peers Health, supra.
As highlighted above, the RFQ incorporated the standard
“Instruction to Offerors--Commercial Items” FAR provision,
which expressly limits the agency’s consideration of a
late submission. See FAR provision 52.212-1(f). Where, as
here, the RFQ contains a late submission provision that
quotations must be received by a stated deadline to be
considered, quotations cannot be considered if received
after the deadline. See Turner Consulting Group, Inc.,
B-400421, Oct. 29, 2008, 2008 CPD ¶ 198 at 3-4 (finding
agency’s decision not to consider protester’s late
quotation proper where RFQ provided that quotations
received after the exact time specified for receipt of
quotations would not be considered); cf. Data Integrators,
Inc., B-310928, Jan. 31, 2008, 2008 CPD ¶ 27 at 2
(sustaining protest where agency awarded to late quotation
despite solicitation provision that any quotation
“received . . . after the exact time specified for receipt
will not be considered”); M.Braun, Inc., supra, at 4
(sustaining protest where agency considered late quotation
despite the RFQ’s incorporation of FAR provision
52.212-1(f)).
We also highlight, for the record, that in order for the
agency to properly accept a late quotation pursuant to FAR
provision 52.212-1(f)(2)(i), the quotation must be
received before award, and its acceptance must be found to
not unduly delay competition. Here, as noted, the
protester’s quotation was not received until after the
evaluation of the other quotations and more than a week
after award. As such, the Air Force was under no
obligation to consider the late quotation. See Blue
Glacier Mgmt. Group, Inc., B‑412897, June 30, 2016, 2016
CPD ¶ 177 at 5; see also Comspace Corp., B-274037, Nov.
14, 1996, 96-2 CPD ¶ 186 at 2 (noting that in certain
situations, an agency is not precluded from considering a
quotation received after the announced due date provided
that no substantial activity has transpired in evaluating
quotations, and the other firms submitting quotations
would not be prejudiced).
In sum, because VS Aviation’s quotation was not received
at the email addresses designated in the solicitation by
the RFQ’s closing time, and in light of the applicability
of FAR provision 52.212-1(f), we find unobjectionable the
agency’s decision not to consider VS Aviation’s late
quotation. While the government may lose the benefit of
more advantageous terms included in a late submission,
such as may be the case here, protecting the integrity of
the competitive procurement process by ensuring fair and
equal treatment among competitors outweighs the possible
advantage to be gained by considering a late submission in
a single procurement. Zebra Techs. Int’l, LLC, B‑296158,
June 24, 2005, 2005 CPD ¶ 122 at 3. (VS
Aviation Services, LLC B-416538: Oct 3, 2018)
National Beef argues that DeCA improperly rejected its
proposals as late. The protester does not dispute that the
packages containing its proposals were delivered to the
agency by UPS after the solicitation deadline, but raises
two arguments for why its proposals should be considered
timely: (1) the proposals should be considered under the
custody of the government based on the time the UPS driver
entered the government installation, and (2) government
processes at Fort Lee were interrupted in a manner that
made it impossible to deliver the proposals by the
solicitation deadline. The protester also argues that
because award has not been made, accepting the protester's
late proposals would not unduly delay the procurement or
prejudice any other offeror. For the reasons discussed
below, we find no basis to sustain the protest.
The RFPs incorporated by reference FAR provision 52.212-1,
which includes the following relevant terms regarding late
proposal submissions:
(f) Late submissions, modifications, revisions, and
withdrawals of offers.
* * * * *
(2)(i) Any offer, modification, revision, or withdrawal
of an offer received at the Government office designated
in the solicitation after the exact time specified for
receipt of offers is "late" and will not be considered
unless it is received before award is made, the
Contracting Officer determines that accepting the late
offer would not unduly delay the acquisition; and-
* * * * *
(B) There is acceptable evidence to establish that it
was received at the Government installation designated
for receipt of offers and was under the Government's
control prior to the time set for receipt of offers;
* * * * *
(3) Acceptable evidence to establish the time of receipt
at the Government installation includes the time/date
stamp of that installation on the offer wrapper, other
documentary evidence of receipt maintained by the
installation, or oral testimony or statements of
Government personnel.
(4) If an emergency or unanticipated event interrupts
normal Government processes so that offers cannot be
received at the Government office designated for receipt
of offers by the exact time specified in the
solicitation, and urgent Government requirements
preclude amendment of the solicitation or other notice
of an extension of the closing date, the time specified
for receipt of offers will be deemed to be extended to
the same time of day specified in the solicitation on
the first work day on which normal Government processes
resume.
FAR provision 52.212-1 (emphasis added); see RFP-0005 at
77; RFP-0002 at 84.
As our Office has explained, it is an offeror's
responsibility to deliver its proposal to the proper place
at the proper time. FAR provision 52.212-1(f)(1);
Washingtonian Coach Corp., B-413809, Dec. 28, 2016, 2016
CPD ¶ 378 at 4. Moreover, in addressing protests
challenging an agency's rejection of late bids or
proposals, we have noted that delays in gaining access to
government facilities are not unusual and should be
expected. U.S. Aerospace, Inc., B-403464, B-403464.2, Oct.
6, 2010, 2010 CPD ¶ 225 at 11 n.17 (citing Econ, Inc.,
B-222577, July 28, 1986, 86-2 CPD ¶ 119 at 4; National
Blower & Sheet Metal Co., Inc., B-194895, Oct. 3, 1979,
79-2 CPD ¶ 240 at 4). Although the rule may seem harsh, it
alleviates confusion, ensures equal treatment of all
offerors, and prevents one offeror from obtaining a
competitive advantage that may accrue where an offeror is
permitted to submit a proposal later than the deadline set
for all competitors. See Inland Serv. Corp., Inc.,
B-252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
Our Office has also explained that a late hand-carried
offer may be considered for award if the government's
misdirection or improper action was the paramount cause of
the late delivery and consideration of the offer would not
compromise the integrity of the competitive process. See,
e.g., ALJUCAR, LLC, B-401148, June 8, 2009, 2009 CPD ¶ 124
at 3; Palomar Grading & Paving, Inc., B-274885, Jan. 10,
1997, 97-1 CPD ¶ 16 at 3. Nonetheless, even in cases where
the late receipt may have been caused, in part, by
erroneous government action, a late proposal should not be
considered if the offeror significantly contributed to the
late receipt by not doing all it could or should have done
to fulfill its responsibility. See ALJUCAR, LLC, supra;
Palomar Grading & Paving, Inc., supra.
Government Control of the Proposals
National Beef argues that an exception to the late
proposal rule applies here because the UPS driver carrying
its proposals entered Fort Lee prior to the solicitation
deadline. The record does not establish, however, that the
government had control of the proposals prior to the
deadline.
As discussed above, the FAR states that a proposal
received at the place designated for receipt of proposals
may be accepted after a solicitation deadline, provided "[t]here
is acceptable evidence to establish that it was received
at the Government installation designated for receipt of
offers and was under the Government's control prior to the
time set for receipt of offers." FAR provision
52.212-1(f)(2)(i)(B). As our Office has explained, the
exception applies where the proposal has been accepted by
government personal, thereby putting it under government
control. B&S Transport, Inc., B-404648.3, Apr. 8, 2011,
2011 CPD ¶ 84 at 4.
Here, National Beef contends that the UPS delivery truck
arrived at Fort Lee sometime around 9:30 a.m. on November
15. Protest, exh. E, Letter from National Beef to
Contracting Officer, Nov. 21, 2017, at 1. The protester,
however, provides no evidence that the agency took custody
of the proposals prior to the 3:00 p.m. deadline. Instead,
National Beef contends that its proposals should be
accepted as timely because the protester "relinquished
control of its proposals when it delivered them to UPS,"
that the UPS truck entered Fort Lee prior to 3:00 p.m.,
and that the entry of the truck onto Fort Lee constituted
government receipt and control of the proposals.
Protester's Comments at 1-2, 11-12.
The protester misstates the applicable standard for
receipt and control of a proposal under FAR provision
52.212-1(f). Even if there was evidence that established
the time the UPS truck entered Fort Lee, and even if the
entirety of Fort Lee is considered the government
installation for purposes of FAR provision 52.212-1(f)(2)(i)(B),
there is no evidence that the government took control of
the proposals prior to 3:27 p.m. Protest, exh. D-1, UPS
Tracking Slip (RFP-0002); exh. D-2, UPS Tracking Slip
(RFP-0005). As our Office has explained, a hand-delivered
proposal must be physically relinquished to government
control by the offeror or its agent; interaction between
the offeror or its agent and the agency's security
personnel, or mere access to the installation does not
establish government control over the proposal. See B&S
Transport, Inc., supra; Immediate Sys. Resources, Inc.,
B-292856, Dec. 9, 2003, 2003 CPD ¶ 227 at 4. On this
record, we find no basis to conclude that the government
had control of National Beef's proposals prior to the 3:00
p.m. deadline, and therefore find no basis to sustain the
protest.
Interruption of Normal Government Processes
Next, National Beef argues that, even if the proposals
were not in government custody prior to the deadline, an
interruption of "normal Government processes" precluded
delivery, which required the agency to extend the time for
receipt of proposals. The record does not establish,
however, whether delivery of the protester's proposals was
actually delayed or that the government was responsible
for any such potential delay.
As discussed above, FAR provision 52.212-1(f)(4) states
that if an "emergency or unanticipated event interrupts
normal Government processes so that offers cannot be
received at the Government office designated for receipt
of offers by the exact time specified in the
solicitation," and government requirements do not allow
for amendment of the solicitation or notice to offerors,
the deadline for receipt of proposals must be extended to
the same time the following day. Where the government
office designated for receipt of proposals is open for
business and able to accept receipt of proposals, we will
not conclude that normal government processes are
interrupted. See CFS-INC, JV, B-401809.2, Mar. 31, 2010,
2010 CPD ¶ 85, at 2-3; Hunter Contracting Co., B-402575,
Mar. 31, 2010, 2010 CPD ¶ 93 at 2-3. Instead, a protester
must provide evidence establishing that there was an
interruption and that it resulted in the protester's
inability to deliver its proposal. See id.
In a letter submitted after the solicitation closing date,
National Beef stated to DeCA that "[o]ur discussions with
UPS indicate that the proposal[s] arrived at the Ft. Lee
entrance gate around 9:30 a.m. on November 15, 2017 before
passing through Military Police inspection." Protest, exh.
E, Letter from National Beef to Contracting Officer, Nov.
21, 2017, at 1. The protester, however, does not explain
who provided the information, e.g., the UPS truck driver
or some other UPS representative. Moreover, the protester
does not provide any statements from UPS or any other
information from UPS aside from the tracking information.
This tracking information shows the following relevant
entries for November 15: (1) at 8:36 a.m., "Out For
Delivery Today," (2) at 3:27 p.m., "Delivered," and (3)
also at 3:27 p.m., "A required security check has delayed
delivery." Protest, exh. D-1, UPS Tracking Slip
(RFP-0002); exh. D-2, UPS Tracking Slip (RFP-0005).
Although National Beef contends that security and/or
construction activities near the Shop Gate delayed access
by the UPS truck to the base, the protester does not
provide any information that could possibly explain a
delay from 9:30 a.m. until 3:27 p.m., nor is there any
evidence that the UPS driver was actually delayed at Fort
Lee for 6 hours. In this regard, aside from the
protester's unsupported statement that UPS arrived at the
Fort Lee gate at 9:30 a.m., the protester does not
specifically state when or how many times UPS attempted
delivery of the proposals. With regard to the notation in
the UPS tracking information regarding a delay associated
with a security check, the tracking information entry for
this event is 3:27 p.m., the same time as the delivery.
Id. The tracking information, however, does not establish
when the delay occurred or the length of the delay. Thus,
even if there was a delay associated with security or
construction, the protester has not provided adequate
information to establish that there was an interruption of
normal government processes in a manner that precluded
submission of proposals.
In sum, National Beef does not establish that there were
emergency or unanticipated events that precluded delivery
of its proposals. See U.S. Aerospace, Inc., supra. In
contrast, the agency states that the office for receipt of
proposals was open during regular business hours on
November 15, through the time for receipt of proposals
specified in the solicitation. Memorandum of Law at 15.
The agency also states that any construction occurring on
November 15 did not affect traffic at the Shop Gate. See
AR, Tab 27, Decl. of Lead Security Officer, Dec. 21, 2017,
at 2-3; Supp. Documents, Tab 08a, Contractor Quality
Control Report, Nov. 15, 2017, at 1. On this record, we
find no basis to conclude that there was an interruption
of normal government processes that prevented the
protester from delivering its proposal, and therefore find
no basis to sustain the protest. (National
Beef Packing Co. LLC B-415754, B-415773: Feb 16, 2018)
Extension for Submission of BAE’s Final Revised
Quotation (FRQ)
As a preliminary matter, PWC contends that DHS should have
rejected BAE’s FRQ as late because it was submitted 30
minutes after the 12:00 p.m., September 18, deadline. PWC
Comments at 6‑10; see AR, Tab 19, BAE Discussions Letter,
at 1. At issue here, BAE contacted [Department of Homeland
Security] DHS shortly before FRQs were due to request a
30‑minute extension (until 12:30 p.m.) because BAE was
having “outages” at its offices. See AR, Tab 34, Contract
Specialist (CS) Email to Contracting Officer (CO), Sept.
18, 2017, at 10. The contracting officer granted the
extension because neither the solicitation nor the request
for FRQs stated that late submissions would not be
considered, and because the solicitation was an RFQ, not a
request for proposals (RFP). Id., CO Email to CS, Sept.
18, 2017, at 10; CS Email to BAE., Sept. 18, 2017, at 11;
CO Statement (COS) at 9; MOL at 11 n.5, citing Gartner
Inc., B‑408933.2; B‑408933.3, Feb. 12, 2014, 2014 CPD ¶ 67
at 2 (“It is well established that the standard for late
proposals does not generally apply to requests for
quotations.”).
PWC acknowledges the RFQ exception to the late proposal
rule, but contends that the strict lateness rule should
apply in the context of a task order competition
conducted, as here, under FAR subpart 16.5, regardless of
the solicitation type. PWC Comments at 6. In this respect,
PWC points out that the Federal Acquisition Streamlining
Act of 1994 (FASA) and the FAR stipulate that IDIQ
contractors be given a fair opportunity to be considered
for task and delivery orders, which, according to PWC,
necessarily “require[s] a significantly greater level of
procedural rigor” than task order competitions conducted
under FAR subpart 8.4, Federal Supply Schedules (FSS), or
FAR part 13, Simplified Acquisition Procedures. Id. at
6‑8, citing 41 U.S.C. 4106(c) and FAR subpart 16.5. PWC
maintains that DHS afforded an unequal advantage and
preferential treatment to BAE by granting the vendor an
extension to submit its FRQ, and thereby deprived PWC of
it right to a fair opportunity and fair consideration of
its quotation. Id. at 7. These assertions lack merit.
The standard for late proposals is based on whether a
solicitation seeks an offer that can be accepted by the
government. See Team Housing Sols., B‑414106, Feb. 10,
2017, 2017 CPD ¶ 55 at 5. An RFQ, unlike an RFP or
invitation for bids, does not seek offers that can be
accepted by the government to form a contract. Rather, the
government’s purchase order represents the offer that the
vendor may accept through performance or by a formal
acceptance document. DataVault Corp., B‑248664, Sept. 10,
1992, 92-2 CPD ¶ 166 at 2. It follows that language in an
RFQ (or, in this case, the contracting officer’s request
for FRQs) requesting quotations by a certain date cannot
be construed as establishing a firm closing date for
receipt of quotations, absent a late quotation provision
expressly providing that quotations must be received by
that date to be considered. Instruments & Controls Serv.
Co., B-222122, June 30, 1986, 86‑2 CPD ¶ 16 at 3. Agencies
should thus consider any quotations received prior to
source selection if no substantial activity has transpired
in evaluating quotations and other vendors would not be
prejudiced. Id.
We find no reason here to depart from the RFQ exception to
the late proposal rule. Although PWC is correct that IDIQ
contractors must be given a fair opportunity to submit a
quotation under a FAR subpart 16.5 task order competition,
neither FASA nor the FAR, in our view, requires the
application of a strict lateness rule in the circumstances
presented here. Moreover, PWC cannot possibly show that it
was prejudiced, where nothing in the record here indicates
that any evaluation activities occurred during the half
hour extension granted to BAE. We thus find that PWC has
not shown that it was unreasonable or inconsistent with
federal procurement laws and regulations for DHS to grant
BAE a 30‑minute extension to submit its FRQ. See KPMG
Consulting LLP, B‑290716, B‑290716.2, Sept. 23, 2002, 2002
CPD ¶ 196 at 11 (denying protest that agency should have
rejected a late proposal modification, notwithstanding the
protester’s arguments that the competition more closely
resembled a negotiated procurement than a “simple FSS
buy.”). (PricewaterhouseCoopers
Public Sector, LLP B-415504,B-415504.2: Jan 18, 2018)
ManTech asserts that the Air Force should be required to
consider its proposal because the proposal was timely sent
to the agency’s designated e-mail box, and ManTech
received confirmation from its Outlook delivery system
that it had been received. ManTech notes in this regard
that it reviewed the tracking record for the first sent
e-mail which indicates that the Cisco IronPort system
opened a Simple Mail Transfer Protocol (SMTP) connection
with the recipient at 13:28:47 (1:28 p.m. EDT), and
received the SMPT remote response at 13:31:52 (1:31 p.m.
EDT), three minutes later. Protest at 6; Decl. of ManTech
Director of Network Services, at 1. According to ManTech,
during these three minutes, the recipient’s server had the
ability to deliver or reject the transmittal. Id. ManTech
asserts that since it did not receive a bounce back
indicating that the e-mail containing the proposal had
been rejected, it must have been accepted by the agency’s
e-mail exchange server. Id. ManTech concludes that the Air
Force should be required to consider ManTech’s proposal
since it made it beyond the initial point of entry to the
government’s infrastructure.
In response, the Air Force reports that ManTech’s proposal
was never received in the CSIACTAT@us.af.mil mailbox, the
mailbox designated in the RFTOP [Request for Task Order
Proposals] for the receipt of proposals. Request for
Dismissal at 2. The Air Force explains that when an e-mail
is sent to any recipient that is at an organization that
is part of the Department of Defense, it is first scanned
by the enterprise e-mail security gateway (EEMSG) for
malicious content. Decl. of EEMSG Program Manager at 1.
EEMSG delivers the e-mail to the recipient’s e-mail
exchange server if no malicious content is found. Id. The
recipient’s e-mail exchange server then performs
additional scans based on the specific policies of the
recipient organization. Id. at 2. The recipient’s server
can block, quarantine, drop, or deliver the e-mail to the
recipient’s e-mail box. Id. The Air Force reports that the
e-mails sent by ManTech were received by the EEMSG system,
which scanned them and attempted to deliver them to the
specified Air Force e-mail address. Agency E-mail, Aug.
23, 2017 (10:44 a.m.); Decl. of EEMSG Program Manager at
1. However, based on the content, they were rejected by
the Air Force server. Id. ManTech did not receive a bounce
back because the EEMSG inbound system cannot initiate a
connection to the internet. Decl. of EEMSG Program Manager
at 1.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time. Tele-Consultants,
Inc., B-414135, Feb. 27, 2017, 2017 CPD ¶ 132 at 5.
Moreover, the protester has the burden of showing that it
timely delivered its proposal to the agency at the
specified address. See Latvian Connection Trading & Constr.,
LLC, B-402410, Feb. 25, 2010, 2010 CPD ¶ 58 at 3;
Lakeshore Engineering Services, B-401434, July 24, 2009,
2009 CPD ¶ 155 at 4. An agency is not required to consider
a proposal where there is no evidence that the proposal
was “actually received.” Tele-Consultants, Inc., supra.
Here, ManTech has demonstrated that it timely sent its
proposal to the agency, and that it reached the EEMSG
server. However, the RFTOP stated that proposals were to
be submitted electronically via e-mail to the contract
specialist, at CSIACTAT@us.af.mil. RFTOP, amend. 2, at 1.
ManTech has failed to establish that its proposal was
actually delivered to the agency’s designated e-mail prior
to the time set for the receipt of proposals, and thus,
has failed to meet its burden of showing that its proposal
was timely delivered to the agency. Accordingly, the
agency could not consider the proposal.[4]
Tele-Consultants, Inc., supra. (ManTech
Advanced Systems International, Inc. B-414985: Oct 20,
2017)
Ghazanfar contends that DLA failed to consider its
timely-submitted proposal and that the agency failed to
respond to its request as to the status of the proposal.
Protest at 1. In support of its position, Ghazanfar
provided copies of its March 13 and April 10 e-mails to
the contracting officer and contract specialist. Id.,
attach., Ghazanfar E-mails. Ghazanfar also provided
declarations from its deputy chief executive officer (CEO)
and information technology (IT) officer, as well as a
screenshot demonstrating that the e-mail transmitting the
proposal had been sent to the appropriate DLA officials.
Comments, attachs., Deputy CEO Decl. and IT Officer Decl.
DLA states that it did not receive Ghazanfar's proposal or
its April 10 e-mail retransmitting the proposal.
Memorandum of Law (MOL) at 5. The agency states that it
searched the e-mail inboxes and junk e-mail folders of the
contracting officer and the contract specialist and found
no e-mails from Ghazanfar for the dates the protester
asserts that it sent e-mails. AR, Tab 5, Contracting
Officer Decl., at 1-2; Tab 6, Contract Specialist Decl.,
at 1. The agency also states that its IT specialist
searched the mailboxes as well as the correlating message
tracing logs, but found no evidence of e-mails from
Ghazanfar for the relevant dates. AR, Tab 7, DLA IT
Specialist Decl. at 1.
It is an offeror's responsibility to deliver its proposal
to the proper place at the proper time. FAR § 15.208; DJW
Consulting, LLC, B-408846.3, Dec. 18, 2013, 2014 CPD ¶ 77
at 3. The protester has the burden of showing that it
timely delivered its proposal to the agency. Latvian
Connection Trading & Constr., LLC, B-402410, Feb. 25,
2010, 2010 CPD ¶ 58 at 3.
The record shows that Ghazanfar has failed to establish
that its proposal was actually delivered to and therefore
received by DLA. Although the protester has provided
evidence that it sent its proposal to the agency in a
timely manner and that a copy of the March 13 transmittal
e-mail was received internally at Ghazanfar, this evidence
does not demonstrate that DLA in fact received the
proposal.
The agency states that it has conducted a search of the
contracting officer's and contract specialist's e-mail
inboxes and junk mail boxes, as well as a search of its
message tracing logs, but has found no evidence of the
e-mails in question. See MOL at 5; AR, Tab 7, DLA IT
Specialist, at 1. Although neither Ghazanfar nor DLA have
been able to explain what happened to the e-mails
containing Ghazanfar's proposal, on the basis of the
record here, we conclude that the protester has failed to
satisfy its burden of showing that it timely delivered its
proposal to the agency. Latvian Connection Trading &
Constr., LLC, supra. (Ghazanfar
Neft Gas LTD B-414636: Jul 21, 2017)
Western Star challenges its exclusion from the
competition. The protester asserts:
A timely bid package was submitted.
That the [agency’s] system is not so reasonably
configured that the [agency] did not in this instance
receive the package until several hours after it was
sent should not prejudice the Protester. The [agency]
knew or should have known of potential flaws in its
email receiving system or the internet in general and
cautioned prospective bidders to check in some manner to
confirm receipt.
Protest at 4. The protester concludes
that it is “guilty of no fault,” and that “it is
completely unfair and unreasonable to reject its bid
because of factors beyond its control.” Id. at 4‑5.
In response, the agency explained in its report that its
Information Assurance Manager had conducted an
investigation of the emails in question. According to the
agency,
The investigation documents that each
of the four (4) emails were delayed by the Protester’s
email providers prior to receipt at the initial point of
entry to the Government’s infrastructure. This
investigation definitively proves that the delay was not
the fault or responsibility of the Government, which has
no control over commercial providers used by the
Protester.
AR at 4.
In its comments on the agency report, the protester
disputed the agency’s findings, contending that its
service provider had informed it that immediately upon
receiving the email messages, the service provider had
sent the messages to the agency’s “servers.” The protester
further explained that the servers were “not accessible,”
and that an error message “indicated a problem involving a
cueing error with [the agency’s] system which was
unrelated to any technical failure or delay caused by
Protestor or its service provider.” In support of its
position, the protester furnished a copy of a mail log
from its service provider. Comments at 1-2.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time. FAR §
52.212-1(f)(1); Washington Coach Corp., B-413809, Dec. 28,
2016, 2016 CPD ¶ 378 at 4; Lakeshore Eng’g Servs.,
B-401434, July 24, 2009, 2009 CPD ¶ 155 at 4. Proposals
that are received in the designated government office
after the exact time specified are “late,” and generally
may not be considered. While the rule may seem harsh, it
alleviates confusion, ensures equal treatment of all
offerors, and prevents one offeror from obtaining a
competitive advantage that may accrue where an offeror is
permitted to submit a proposal later than the deadline set
for all competitors. See Inland Serv. Corp., Inc.,
B-252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
The FAR also requires an offeror, when transmitting its
proposal electronically, to ensure the proposal’s timely
delivery by transmitting the proposal sufficiently in
advance of the time set for receipt of proposals to allow
for timely receipt by the agency. Specifically, FAR §
52.212-1(f)(2)(i)(A) provides that a late proposal,
received before award may be accepted if it was
“transmitted through an electronic commerce method
authorized by the solicitation,” and it was “received at
the initial point of entry to the Government
infrastructure” not later than 5:00 p.m. one working day
before proposals were due. Washington Coach Corp., supra,
at 4.
Here, Western Star concedes, and the record indicates,
that its electronically transmitted proposal was not
received by the agency by the time designated for the
receipt of proposals. Protest at 4; AR at 2. While the
protester and the agency differ with regard to which party
bears responsibility for the failure of the protester’s
proposal to reach the agency’s initial point of entry for
the agency’s servers prior to the deadline, see Protest at
4-5; AR at 4, we need not resolve this issue. We have
repeatedly found that it is an offeror’s responsibility to
ensure that an electronically submitted proposal is
received by--not just submitted to--the appropriate agency
email address prior to the time set for closing. See,
e.g., Washington Coach Corp., supra, at 4; Latvian
Connection Trading and Construction, LLC, B-402410, Feb.
25, 2010, 2010 CPD ¶ 58 at 2; Lakeshore Eng’g Servs.,
supra, at 4. There is no dispute that the protester’s
proposal was not transmitted electronically by 5:00 p.m.
the day before proposals were due, and was not received at
the agency’s servers until after the deadline for receipt
of proposals. Accordingly, we conclude that the protester
has failed to satisfy its burden of showing that it timely
delivered its proposal to the agency. (Western
Star Hospital Authority, Inc. B-414216.2: May 18,
2017)
TCI challenges the rejection of its proposal from
consideration. Although TCI acknowledges that it “did not
receive the expected notice from [the SeaPort-e portal]
that its proposal was submitted,” TCI asserts nonetheless
that its proposal was timely submitted. Protest at 4. TCI
also argues that even if its proposal was late, its
proposal should have been viewed as subject to “the
government control” exception of the Federal Acquisition
Regulation (FAR) § 15.208. Protest at 5. Both of TCI’s
arguments contend that “the archival lock on proposal
files is thus acceptable evidence to establish that [its
proposal] was received at the [g]overnment installation
designated for receipt of proposals, [i.e., the SeaPort-e
portal,] and was under the [g]overnment’s control prior to
the time set for receipt of proposals.” Protest at 5.
The agency responds that because TCI never engaged the
“Submit Signed Proposal” button, TCI did not submit a
signed final proposal, either prior to the submission
deadline or thereafter. Legal Memorandum at 5. In
addition, the agency explains that it is only when an
offeror engages the “Submit Signed Proposal” button that a
proposal is uploaded to the government side of the portal
and becomes a signed legally binding submission. As a
result, the Navy contends that TCI’s proposal was not
received at the government installation and was not under
the government’s control at the time of closing. Id. at
7-8. Further, the agency contends that since TCI did not
engage the “Submit Signed Proposal” button, it cannot know
whether TCI intended to be legally bound by its proposal.
Id. at 11.
In its comments on the agency report, TCI challenges the
significance of engaging the “Submit Signed Proposal”
button, arguing that its failure to egage the button was
irrelevant because, at the time of closing, its proposal
was uploaded to the correct government location, and
thereby in the government’s control, as evidenced by TCI’s
inability to further modify the proposal. Comments at 5-6.
We disagree.
Based on the undisputed facts in the record, we conclude
that TCI never actually submitted its proposal. Here, the
electronic submission of a legally binding offer was not
completed until an offeror engaged the portal’s “Submit
Signed Proposal” button, and accepted an agreement to
legally bind the company to its submission by the closing
time of 2:00 p.m. Eastern Time. RFP, Amend. 1, at 1; AR,
Exh. 2, Clause H.5 of SeaPort-e Multiple Award Contract,
at 3; AR, Exh. 1, SeaPort Guide, at 24. Additionally, the
portal does not allow a vendor to engage the “Submit
Signed Proposal” button after the time set for closing--as
TCI apparently tried here.
TCI does not dispute that it attempted to engage the
“Submit Signed Proposal” button after 2:00 p.m. Eastern
Time, and acknowledges that it did not receive notice from
the portal that its proposal was submitted. See Protest at
4. Instead, the protester received an “event closed”
notice stating that TCI did not complete the final
submission process. Finally, the record shows that neither
TCI nor the portal administrator reported technical issues
that would have prevented TCI from submitting its proposal
prior to the closing time. Accordingly, because TCI failed
to “hit the [s]ubmit button” prior to closing--an action
necessary to legally bind the offeror and to submit the
proposal--we conclude that TCI’s proposal was never
submitted.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time. DJW Consulting,
LLC, B-408846.3, Dec. 18, 2013, 2014 CPD ¶ 77 at 3. In
addition, an agency is not required to consider a proposal
where, as here, there is no evidence that the proposal was
“actually received.” See Federal Acquisition Servs. Team,
LLC, B-410466, December 31, 2014, 2015 CPD ¶ 20 at 4.
Based on these facts, we have no basis to challenge the
agency’s decision that it had not received, and could not
consider, TCI’s draft proposal. (Tele-Consultants,
Inc. B-414135: Feb 27, 2017)
WCC asserts that its proposal was properly and timely
submitted and the agency erred in not evaluating and
considering its proposal. WCC argues that the
documentation that it submitted showing that its proposal
was sent by email and the return path of that email, shows
that the agency received the email before proposals were
due. Protest at 2-3. The protester also maintains that it
followed all of the instructions for the submission of
proposals in the solicitation, and that the solicitation
made no mention of the size limit of its email system. Id.
at 2; Comments at 1.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time. FAR §
52.212-1(f)(1); see International Code Council, B-409146,
Jan. 8, 2014, 2014 CPD ¶ 26 at 3; see M.Braun, Inc.,
B-298935.2, May 21, 2007, 2007 CPD ¶ 96 at 4; see
Lakeshore Eng’g Servs., B-401434, July 24, 2009, 2009 CPD
¶ 155 at 4. Proposals that are received in the designated
government office after the exact time specified are
“late,” and generally may be considered only if received
before award and the circumstances satisfy the specific
requirements set forth in FAR §15.208(b)(1). While the
rule may seem harsh, it alleviates confusion, ensures
equal treatment of all offerors, and prevents one offeror
from obtaining a competitive advantage that may accrue
where an offeror is permitted to submit a proposal later
than the deadline set for all competitors. See Inland Serv.
Corp., Inc., B‑252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at
3.
We view it as an offeror’s responsibility, when
transmitting its proposal electronically, to ensure the
proposal’s timely delivery by transmitting the proposal
sufficiently in advance of the time set for receipt of
proposals to allow for timely receipt by the agency. As
stated above, and referenced in the solicitation, FAR §
52.212-1(f)(2)(i)(A) provides that a late proposal,
received before award may be accepted if it was
“transmitted through an electronic commerce method
authorized by the solicitation,” and it was “received at
the initial point of entry to the Government
infrastructure” not later than 5:00 p.m. one working day
before proposals were due.
We note that in this instance the agency received four
timely proposals. While it is true that the solicitation
did not include a size limit for electronic submissions,
nevertheless, it is an offeror’s responsibility to ensure
that an electronically submitted proposal is received
by--not just submitted to—the appropriate agency email
address prior to the time set for closing. See Lakeshore
Eng’g Servs., supra at 4.
In sum, since WCC’s electronically transmitted proposal
was not received by the contracting officer or contract
specialist, at the time designated for the receipt of
proposals, it is a late proposal. Further, since it was
not received at the initial point of entry by 5:00 p.m.
the day before proposals were due, the late proposal
cannot be accepted. FAR § 52.212-1(f)(2)(i)(A); Sea Box,
Inc. B-291056, Oct. 31, 2002, 2002 CPD 181 at 4; Assoc.
Fabricators & Constructors, Inc., B-405872, Dec. 14, 2011,
2011 CPD ¶ 279 at 4. (Washingtonian
Coach Corporation B-413809: Dec 28, 2016)
Blue Glacier asserts that its quotation was properly and
timely submitted, and that the agency erred in not
evaluating and considering its quotation. The protester
maintains that the failure of Blue Glacier’s email
quotation to arrive at the email address specified in the
solicitation was due to problems with the agency’s email
system. Blue Glacier also contends that the agency should
consider its late quotation under the “government control”
exception. Protest at 8; Comments at 5. For the reasons
set forth below, we find no basis to sustain the protest.
It is the vendor’s responsibility, when transmitting its
quotation electronically, to ensure the delivery of its
quotation to the proper place at the proper time. Advanced
Decisions Vectors, Inc., B-412307, Jan. 11, 2016, 2016 CPD
¶ 18 at 5. Quotations that are received in the designated
government office after the exact time specified are
“late,” and generally may not be considered for award.
While this rule may seem harsh in some circumstances, it
alleviates confusion, ensures equal treatment of all
vendors, and prevents one vendor from obtaining a
competitive advantage that may accrue where a vendor is
permitted to submit a quotation later than the deadline
set for the competition. C2G Ltd. Co., B-411131, May 12,
2015, 2015 CPD ¶ 157 at 4.
Here, we find that Blue Glacier has failed to establish
that its quotation was submitted to and received by the
agency at the email address specified in the solicitation
prior to the due date for receipt of quotations. The RFQ
unequivocally required that quotations be submitted to the
email address specified in the RFQ. RFQ, amend. No. 1, at
12. The record is clear that the contract specialist did
not receive Blue Glacier’s quotation on November 9. AR,
Tab 3, Affidavit of Contract Specialist (Apr. 25, 2016),
at 4. It also reflects that the contract specialist did
not receive a notification advising that any emails had
been quarantined. Id. Blue Glacier does not argue, and the
record contains no evidence showing, that the protester
attempted to confirm receipt of its emailed quotation.
Rather, the protester’s efforts to establish that its
quotation was timely received by the agency did not begin
until more than three months after quotations were due.
Id. at 3. As discussed above, by that point, however, the
agency’s search for information regarding the protester’s
November 9 email transmission did not yield any results
because the agency’s email hygiene log is only retained
for 30 days. AR, Tab 4, Decl. of OCC’s Deputy Chief
Information Officer (Apr. 25, 2016), at 3. Accordingly,
although the Treasury Fiscal Services network indicates
that an email from Blue Glacier was sent to OCC’s external
server on November 9, where it appears that it may have
been blocked by the OCC’s email filtering system, the
record does not clearly establish what Blue Glacier
communication the agency’s email filtering system blocked.
Thus, the primary evidence establishing that Blue Glacier
properly submitted its quotation is the protester’s copy
of an email, with two attachments, purportedly sent to the
contract specialist on November 9, that appears to be a
quotation in response to the RFQ. This copy, however, does
not demonstrate that a quotation from the protester was
received by the agency in a manner consistent with the
solicitation. See International Garment Processors,
B-299674 et al., July 17, 2007, 2007 CPD ¶ 130 at 7
(finding reasonable agency’s rejection of revised
quotation where protester only demonstrated that quotation
was transmitted, but not that it was actually timely
received by the agency). Rather, as discussed above, the
record reflects that the first time the contract
specialist affirmatively received Blue Glacier’s quotation
was on February 26, following the protester’s inquiry as
to the status of the procurement. AR, Tab 3, Affidavit of
Contract Specialist (Apr. 25, 2016), at 4. A submission on
this date, however, clearly did not meet the
solicitation’s deadline.
Blue Glacier next argues, citing FAR clause
52.212-1(f)(2)(i)(B), that the agency should consider its
quotation because, even if it did not arrive at the
specified email address prior to the specified time, it
was “under the Government’s control” prior to the time set
for receipt of quotations. The protester points out that
it submitted its quotation more than three hours before
the deadline specified in the solicitation, and contends
that its quotation was in the government’s control as soon
as it entered the Treasury Fiscal Services network.
Our Office has held that in determining whether a
quotation was “under the Government’s control” prior to
the time set for receipt of quotations, a vendor must have
relinquished custody of the quotation to the government so
as to preclude any possibility that the vendor could
alter, revise or otherwise modify its quotation after
other vendors’ competing quotations have been submitted.
See Johnson Controls Gov’t Sys., LLC, B-411862.2, Nov. 24,
2015, 2015 CPD ¶ 357 at 4. Here, as discussed above,
because Blue Glacier did not seek prompt confirmation of
the agency’s receipt of its quotation, Blue Glacier’s
November 9 email was automatically deleted from the
agency’s system after 30 days. Accordingly, the agency has
no way to confirm the contents of the Blue Glacier email
that entered the Treasury Fiscal Services network on
November 9; that is, it has no way to confirm that the
November 9 email included a quotation identical to the
quotation furnished by the protester on February 26.
Whether the protester actually altered its quotation is
not the issue; rather, the issue is whether, under the
circumstances, there is any possibility that the protester
could have altered its quotation. This requirement
precludes any possibility that a vendor could alter,
revise or otherwise modify its quotation after other
vendors’ competing quotations have been submitted. Id. at
4-5. Because Blue Glacier was not precluded from altering
its quotation here, the government control exception is
inapplicable in this instance.
We also note that in order for the agency to properly
accept a late proposal pursuant to FAR clause
52.212-1(f)(2)(i), the quotation must be received before
award, and its acceptance must be found to not unduly
delay competition. Here, the record reflects that when the
contracting officer received Blue Glacier’s quotation at
the end of February, she decided that, because OCC was in
the final phase of decision‑making with regard to its
evaluation, and had adequate competition, it was not in
the best interest of the agency to include Blue Glacier’s
quotation in the competition because it would unduly delay
the competition. COS at 4. The protester does not
challenge the agency’s determination in this regard.
Accordingly, because the contracting officer found that
accepting the late quotation would unduly delay the
acquisition, none of the late proposal exceptions
specified under FAR clause 52.212‑1(f)(2)(i) apply.
Finally, Blue Glacier argues that the late submission of
its quotation arose due to a “systemic failure” of the
agency’s email system, and therefore, the agency should
consider its quotation. Protest at 9; Comments at 6.
Our Office has recognized a limited exception to the rule
that negligent loss of proposal/quotation information does
not entitle the offeror/vendor to relief. This exception
generally applies where the loss was not an isolated act
of negligence, but rather arises out of a systematic
failure in the agency’s procedures that typically results
in multiple or repetitive instances of lost information.
Project Res., Inc., B‑297968, Mar. 31, 2006, 2006 CPD ¶ 58
at 2. Here, the record reflects that, on November 9, five
vendors successfully submitted timely quotations, and one
vendor successfully submitted a late quotation, to the
designated OCC email inbox. AR, Tab 3, Decl. of Contract
Specialist (Apr. 25, 2016), at 2. Although the protester
contends that the vendor with the late-submitted quotation
submitted an earlier email that was also blocked by the
agency’s spam filter, this assertion is not supported by
the record. COS at 3 (stating that the vendor’s initial
email transmission was never received by the agency, and
that it was unclear why the vendor then decided to
resubmit its quotation as two separate emails).
Accordingly, even if, as the agency IT staff surmise, Blue
Glacier’s email quotation was blocked by the agency’s
anti-phishing filter, we fail to find that this reflects
systematic failure of the agency’s email system; rather,
it reflects the proper functioning of the system to block
emails that are suspect. The record also reflects that the
agency conducted an investigation of its email system and
found that no issues exist with external email providers.
AR, Tab 4, Affidavit of OCC’s Deputy Chief Information
Officer (Apr. 25, 2016), at 1-3.
The protest is denied. (Blue
Glacier Management Group, Inc. B-412897: Jun 30, 2016)
(pdf)
ADV asserts that its quotation was properly and timely
submitted, and the agency erred in not evaluating and
considering the quotation. In this regard, the protester
represents that its quotation was emailed to the contract
specialist at the email address identified in the RFQ five
minutes prior to the 10:00 a.m. deadline. In support, ADV
provided for the protest record a copy of the email it
purportedly sent to the contract specialist. Protest at 2;
exh. A, ADV Email to Contract Specialist, Sept. 8, 2015
(9:55 a.m.), at 1. In addition, the protester argues that
its quotation should have been considered because it also
was timely uploaded to the GSA e‑Buy portal. As evidence
of its e-Buy submission, ADV submitted for the record a
copy of a text message and an email from the e-Buy system
confirming that the quotation had been received. Protest
at 2-3; exh. C, Text Message Confirmation, at 1; exh. D,
Email Confirmation, at 1.
The agency maintains that it did not receive a quotation
from ADV prior to the submission deadline, and, as a
result, ADV’s quotation was properly not considered during
the procurement. As evidence, subsequent to ADV’s protest,
the contract specialist and several other DHS personnel
associated with the procurement provided for the protest
record all emails (sent and received) related to the
solicitation for the 24‑hour period surrounding the RFQ’s
closing time. CO Statement at 4; see AR, Tab C‑1 ‑‑ C-84,
Emails of Sept. 8 and 9 Relating to RFQ. In addition, a
DHS information technology (IT) team conducted a similar
search for emails related to the procurement. CO Statement
at 4. The agency points out that none of the emails
identified and produced included correspondence from ADV;
in this regard, the vendor’s quotation purportedly sent to
the contract specialist was not discovered during the
email search. See id.; AR at 10.
The agency further explains that DHS relies on an
“extensive” series of email security services that sit
between the DHS headquarters email servers and the
internet. Supp. AR at 1; AR, Tab F‑1, Revised DHS Incident
Response Manager Statement, at 2. Some of these security
services--what DHS refers to as the Edge--include
anti-virus, spam, and spyware interdiction that scrutinize
“many millions of inbound messages daily” prior to the
emails moving forward to the DHS email servers. Id. In
this respect, the Edge prevents spam and other malicious
emails from ever reaching the DHS email servers and purges
these potentially contaminated emails. Id. The agency
reports that an “exhaustive” search of the Edge
spreadsheet logs revealed what the DHS IT team referred to
as an “artifact” that showed the “tracking of an email”
from ADV addressed to the contract specialist. Supp. AR at
1. That is, the logs showed that an email from ADV may
have reached the Edge level of IT security on September 8;
however, no email from ADV passed through the Edge
firewall to the DHS email servers. AR, Tab F-1, Revised
DHS Incident Response Manager Statement, at 3. Moreover,
because DHS purges potentially malicious emails within a
week, by the time ADV filed its protest and the IT team
conducted its search, the Edge no longer included a copy
of any actual email from ADV. Id. at 2.
DHS also explains that no one at the agency reports
receiving any notification from the GSA e-Buy system
alerting the agency of the submission of a quotation for
this procurement. In any event, the agency asserts more
generally that to the extent ADV submitted its quotation
directly to the e-Buy system, such submission was counter
to the express language in the RFQ memorandum and, thus,
the quotation was properly not considered. In sum, the
agency maintains that it properly excluded ADV’s quotation
from consideration because the contract specialist did not
receive the quotation and any submission through the e-Buy
system was contrary to the terms of the solicitation.
As an initial matter, we agree with the agency that
whether ADV timely uploaded its quotation to the GSA e-Buy
portal--and it appears that the vendor did--is of no
consequence here. In this regard, it is the responsibility
of each vendor to deliver its quotation to the proper
place at the proper time. See Zebra Techs. Int’l, LLC,
B‑296158, June 24, 2005, 2005 CPD ¶ 122 at 3. Here, the
RFQ unequivocally required that quotations be submitted to
the contract specialist at the email address identified in
the RFQ memorandum. RFQ Memorandum at 1. Indeed, in three
separate paragraphs the agency warned that quotations had
to be submitted directly to the contract specialist by the
deadline and that quotations not received “in the manner
specified” in the memorandum would not be considered. Id.
Significantly, the RFQ did not provide for alternate
quotation submission procedures via the e-Buy portal.
Simply put, contrary to the protester’s suggestion
otherwise, e‑Buy was not the “Government installation
designated for receipt of offers.” See FAR clause
52.212-1(f)(2)(i)(B). Thus, that the protester apparently
submitted its quotation directly to the e-Buy system
imparted no obligation on the agency to consider the
quotation given that the e-Buy portal was not the proper
location for electronic submissions.
Further, the contract specialist explained that while she
relied on the e-Buy system to publish the RFQ, she did not
otherwise interface with the system. Contract Specialist’s
Statement at 1. In this regard, she reports--and the
record does not evidence otherwise--that she did not
access the e-Buy system to check for quotations;
quotations were “received, evaluated, and awarded” outside
of e-Buy. Id. In fact, the record does not show that any
agency personnel had knowledge that ADV’s quotation was
uploaded to e-Buy, accessed e-Buy to receive or review
quotations, or ever received ADV’s quotation via the e-Buy
system. The contract specialist further maintains that the
text message that ADV received from the e-Buy system that
referenced the contract specialist’s email address “did
not result from any input from my actual email address.”
Id. On this record, we decline to accept that the agency
erred when it did not consider the protester’s quotation
that was uploaded to the e-Buy portal. Cf. AECOM Tech.
Servs., Inc., B‑411862, Nov. 12, 2015, 2015 CPD ¶ 353 at 5
(finding that where protester uploaded its proposal to the
wrong electronic location, the agency nevertheless should
have considered and evaluated the proposal where the
agency knew that the proposal had been submitted to the
wrong location, the agency received the proposal prior to
the submission deadline, and there was no burden on the
agency or harm in accepting the proposal).
Next, we address ADV’s purported September 8 email to the
contract specialist. Here, the record is clear that the
contract specialist did not receive ADV’s quotation on
September 8. As discussed above, the agency’s search for
emails between the protester and certain DHS officials did
not yield any results. While it appears that the Edge
security service may have prevented an email from ADV from
reaching the DHS email servers, the record does not
clearly establish what ADV communication the Edge actually
blocked; the spreadsheet logs do not include a copy of the
correspondence to verify the submission of ADV’s
quotation.
Thus, the primary evidence establishing that ADV properly
submitted its quotation is the protester’s copy of an
email purportedly sent to the contract specialist on
September 8 with an attachment that appears to be a
quotation in response to the RFQ. This copy, however, does
not demonstrate that a quotation from the protester was
received by the agency in a manner consistent with the
solicitation. See International Garment Processors,
B‑299674 et al., July 17, 2007, 2007 CPD ¶ 130 at 7
(finding reasonable agency’s rejection of revised
quotation where protester only demonstrated that quotation
was transmitted, but not that it was actually timely
received by the agency). Indeed, the record reflects that
the first time the contract specialist affirmatively
received ADV’s quotation was on October 5, following the
protester’s inquiry as to the status of the procurement.
See AR, Tab B‑8, Test Message from ADV to Contract
Specialist, at 1. Under these circumstances, we find no
basis to sustain the protest.
Lastly, to the extent that the protester contends that the
agency should consider the quotation that it attached to
its October 5 correspondence with the contract specialist,
its contention is without merit. Where, as here, the RFQ
contains a late submission provision that quotations must
be received by a stated deadline to be considered,
quotations cannot be considered if received after the
deadline. See Turner Consulting Group, Inc., B‑400421,
Oct. 29, 2008, 2008 CPD ¶ 198 at 3 (finding agency’s
decision not to consider protester’s late quotation proper
where RFQ provided that quotations received after the
exact time specified for receipt of quotations would not
be considered); see also, e.g., Data Integrators, Inc.,
B‑310928, Jan. 31, 2008, 2008 CPD ¶ 27 at 2 (finding
agency’s consideration of late quotation improper where
the solicitation incorporated a late quotation provision
expressly providing that any quotation “received . . .
after the exact time specified for receipt will not be
considered”); M.Braun, Inc., B‑298935.2, May 21, 2007,
2007 CPD ¶ 96 at 4 (sustaining protest where agency
considered late quotation despite provision in RFQ--FAR
clause 52.212-1(f)--that generally precluded agency’s
consideration of a late submission).
Here, we find no basis to recommend that the agency
consider ADV’s quotation. In this regard, the RFQ
contained strict requirements for the submission of
quotations, including a firm deadline for quotations to be
considered. As discussed above, the first time the
contract specialist was in receipt of ADV’s quotation was
on October 5, well after the submission deadline. Thus,
because ADV’s quotation was not received prior to the
RFQ’s firm deadline, we see no legal basis to require the
agency to consider the late quotation. See Turner
Consulting Group, Inc., supra.
In sum, the record shows that the agency never received
ADV’s quotation prior to the submission deadline, the
vendor failed to seek timely confirmation from DHS with
respect to its submission, and the first time the agency
affirmatively received the quotation was nearly a month
after the RFQ closed and almost two weeks after the task
order was issued. Under these circumstances, we find
reasonable the agency’s decision not to consider ADV’s
quotation.
The protest is denied. (Advanced
Decisions Vectors, Inc. B-412307: Jan 11, 2016)
(pdf)
The agency used a proposal submission web portal known as
FedConnect. RFP, Amendment No. 3, at 81. FedConnect is a
centralized web portal where vendors seeking to conduct
business with the federal government can search for
contract opportunities. Vendors also can submit
solicitation responses directly through the FedConnect
system. As explained in the FedConnect tutorial, and as
relevant here, the FedConnect system has two distinct
communication features, a “response center” for submitting
proposals in response to solicitations, and a “message
center,” for asking questions related to a solicitation.
Proposals were due by May 13, 2015.
The record shows that, rather than submitting its proposal
to the response center, AECOM submitted its proposal to
the message center on May 12, 2015, one day before
proposals were due. Further, the record shows that,
shortly after the protester submitted its proposal to the
message center, also on May 12, the agency’s contract
specialist noticed AECOM’s error. He sent a message back
to AECOM’s designated employee advising AECOM as follows:
“In accordance with Section L.9.d of the solicitation,
proposals must be submitted through the FedConnect
Responses web portal, not the Message Center, to be
accepted.” Agency Report (AR), exh. B-2, Contract
Specialist Message to AECOM. The protester apparently did
not check the FedConnect message center after submitting
its proposal, and therefore never received the contract
specialist’s message regarding the proper submission of
its proposal before the deadline for submitting proposals
had passed. Thereafter, on July 27, the agency sent AECOM
a letter advising the firm that its proposal was rejected
because it had not been submitted properly to the
FedConnect web portal in accordance with the instructions
in the solicitation. AR, exh. B-3, AECOM Proposal
Rejection Letter.
The protester concedes that it was its own error that led
to its proposal not being properly submitted. However,
AECOM maintains that the agency should nonetheless
consider its proposal because it was timely submitted to
the agency, and the agency was contemporaneously aware of
the fact that it had been submitted. AECOM maintains that
accepting its proposal will not be prejudicial to the
other offerors because AECOM gained no competitive
advantage from submitting its proposal to the message
center rather than the response center. In this latter
connection, AECOM points out that it relinquished control
of its proposal, so it was never afforded an opportunity
to revise it after it was submitted. The protester
therefore argues that the agency should waive the
submission of its proposal to the message center rather
than to the response center as a minor informality.
In support of its position, AECOM directs our attention to
our decision in Abt, Assocs., Inc., B-226063, May 14,
1987, 87-1 CPD ¶ 513. In that case, the solicitation
required the simultaneous submission of proposals to two
locations, and the protester timely submitted its proposal
to one, but not both, locations. Our Office concluded that
acceptance of the proposal would be unobjectionable
because Abt had timely delivered its complete proposal to
the agency, such that it could be evaluated and, upon
acceptance, would form a binding contract. We also
concluded that none of the other offerors were prejudiced
by acceptance of the Abt offer because Abt’s proposal had
been timely and completely submitted to the agency.
The agency responds that it properly rejected AECOM’s
proposal because the firm failed to follow the directions
for its submission. The agency also states that the
protester is attempting to shift responsibility for the
final delivery of AECOM’s proposal to its contract
specialist, and that “moving” AECOM’s proposal to the
appropriate location within the agency’s acquisition
computing environment (known as STRIPES) imposes an
administrative burden on the agency. According to the
agency, the integrity of the system and the principle of
fundamental fairness would be harmed if the agency
accepted the AECOM proposal because it is due solely to
AECOM’s negligence that the proposal was not properly
submitted. Finally, as to the question of prejudice, the
agency states as follows:
Contrary to Protester’s assertion
(Protest, AR Tab E.1 at 7 of 20), competitive prejudice
to the other offerors would occur as there would be
increased competition for the number of awards. When
many firms are vying for a few awards (the "target"
established by the RFP was just 12 awards (AR Tab A.4 at
91 of 97)[)], increasing the number of proposals
received will arguably decrease another firm’s chance at
one of those contracts.
Agency Report at 9.
Our standard in cases such as this is longstanding, and
succinctly stated in Abt Assocs., Inc., supra at 2:
It is generally true, as AID [the
Agency for International Development] states, that the
government may impose conditions on offerors to the
extent those conditions reflect the actual and
reasonable needs of the agency. Bids and proposals that
deviate from solicitation requirements, however, need
not be rejected in every instance. When the deviation
involves a matter of form rather than of substance, or
when the government’s needs will be satisfied by
acceptance of a deviating offer and other offerors would
not be unfairly prejudiced by the acceptance, such an
offer can be accepted.
Here, we agree with the agency that
AECOM is directly and solely responsible for the improper
delivery of its proposal to the message center rather than
to the response center. That said, there is no question
that the agency was in possession of the complete AECOM
proposal before the deadline for proposal submission; that
the proposal was out of AECOM’s control and therefore
could not have been altered or revised after the deadline
for proposal submission had passed; and that the agency
had actual knowledge of having received AECOM’s proposal,
albeit in a different electronic “location” than the
location specified in the solicitation for delivery of the
proposal.
In this latter connection, we recently had occasion to
consider a case virtually identical to the present case,
and also involving DOE’s use of the FedConnect web portal.
As in this case, the protester there delivered its
proposal to the web portal’s message center rather than
its response center; the difference in the two cases is
that in the earlier case the agency was unaware that the
proposal had been submitted to the message center.
Instead, the agency only discovered the protester’s
proposal several months after it had been submitted. We
concluded as follows:
However, Onsite’s use of the message
center rather than the response center was not simply a
matter of form or a minor issue--it prevented the agency
from actually receiving Onsite’s proposal. We see no
flaw in the agency’s failure to waive the improper
submission of the protester’s proposal where the agency
had no knowledge of the proposal’s existence due to an
error committed by the protester itself.
Onsite OHS, B-406449, May 30, 2012,
2012 CPD ¶ 178 at 3 n.2.
Here, in contrast, the record shows that the agency timely
and contemporaneously had actual knowledge that AECOM had
submitted its proposal. This is demonstrated by the
message from the contract specialist to AECOM on May 12,
the day before the proposal submission deadline.
We also are not persuaded by the agency’s suggestion that
it imposes an undue administrative burden on it to accept
AECOM’s proposal. While we agree with the agency that
AECOM is entirely at fault for the improper delivery of
its proposal, we think the administrative burden imposed
on the agency in accepting the AECOM proposal is not
significant.
This result does not harm the integrity of the procurement
system or violate the principle of fundamental fairness;
AECOM submitted its proposal to the agency in a timely
manner and was afforded no advantage over any other
offeror when it submitted its proposal in one of the
portal’s electronic “locations” rather than another. Once
again, while we agree that AECOM is at fault for its
error, the error is, in the final analysis, a harmless
one.
As a final matter, as noted, the agency suggests that the
other offerors will suffer competitive harm because they
will be forced to compete with AECOM if the agency accepts
the protester’s proposal. We note that the RFP here
contemplates the award of multiple IDIQ contracts.
Although the agency argues that the RFP establishes a
“target” for the number of contracts the agency intends to
award, there is nothing preventing the agency from making
more awards in the event it concludes that an additional
proposal--either one from AECOM or one from another
offeror--offers a value to the government that merits the
award of an additional contract. In effect, the agency is
arguing that acceptance of the AECOM proposal will result
in more robust competition. Inasmuch as competition is the
bedrock objective of the federal acquisition system, DOE’s
acceptance of AECOM’s proposal as timely will enhance
competition.
In sum, where, as here, the record shows that a complete
copy of a proposal was submitted to--and contemporaneously
received by--the cognizant contracting personnel before
the deadline for proposal submission; where the cognizant
contracting personnel actually and contemporaneously were
aware of having received it; where there is no significant
administrative burden imposed on the agency by virtue of
accepting the proposal; and where there is no harm in
accepting the proposal, either to the integrity of the
procurement system, or to the principle of fundamental
fairness, the agency should accept the proposal. See Abt
Assocs., Inc., supra; cf. Onsite OHS, supra. We therefore
conclude based on the particular facts presented here that
acceptance of the AECOM proposal is unobjectionable. In
the final analysis, AECOM was afforded no advantage over
other offerors in the submission of its proposal by virtue
of the fact that it delivered it to the message center
rather than to the response center, and acceptance of the
AECOM proposal will result in enhanced, rather than
diminished, competition. We therefore sustain AECOM’s
protest.
In light of the foregoing, we recommend that the agency
accept AECOM’s proposal and evaluate it along with the
other proposals received; however, we do not recommend
that AECOM be reimbursed the costs associated with filing
and pursuing its protest. As noted, AECOM concedes that it
was responsible for creating the problem. We therefore
conclude that it would not be appropriate to recommend
reimbursement of its protest costs here. (AECOM
Technical Services, Inc. B-411862: Nov 12, 2015)
(pdf)
Northstar challenges the agency’s rejection of its
proposal as late. The protester primarily contends that
since the protester’s submission allegedly provided more
favorable terms than its initially submitted phase II
proposal, the agency was required to accept it pursuant to
Federal Acquisition Regulation (FAR) § 15.208(b)(2).
Protest at 2.
As set forth in FAR § 15.208, offerors are responsible for
submitting proposals, revisions, and modifications to the
proper place at the proper time. Late submissions of
proposals, revisions, and modifications may not be
considered, except, as is pertinent here, where the late
submission is received before award, and is a late
modification of an otherwise successful proposal that
makes its terms more favorable to the government. FAR §
15.208(a)-(b)(2); See Seven Seas Eng’g & Land Surveying,
B-294424.2, Nov. 19, 2004, 2004 CPD ¶ 236 at 4. An
“otherwise successful proposal” is one that is already in
line for a contract award regardless of the late
modification. See Philips Healthcare Informatics,
B-405382.2 et al., May 14, 2012, 2012 CPD ¶ 220 at 7; see
also RMS Indus., B-245539, Dec. 9, 1991, 91-2 CPD ¶ 528 at
3.
Here, Northstar’s second phase II proposal submission
cannot be considered a modification to an “otherwise
successful proposal” since, as established above, the
agency had nullified all the initial phase II proposals
due to the solicitation changes associated with the
issuance of amendment 17. Amend. No. 20, Q&A Nos. 26, 91,
214, and 216. In this regard, the agency expressly advised
offerors that they remained on equal standing at what
amounted to a restart of the phase II competition. Amend.
No. 20, Q&A No. 26 (explaining that “[p]reviously
submitted proposals will not influence the evaluation
process”). As a consequence, at the time of the second
phase II submissions, the agency had not evaluated
proposals and had not identified any otherwise successful
offerors. See Team Systems Int’l, LLC, B‑410420, Dec. 19,
2014, 2014 CPD ¶ 378 at 3; LATG, Inc., B‑409679.2, July
31, 2014, 2014 CPD ¶ 226 at 3‑4; The Sandi Group, Inc.,
B‑401218, June 5, 2009, 2009 CPD ¶ 123 at 3‑4.
Accordingly, the protester has not provided any basis to
question the reasonableness of the agency’s rejection of
its phase II proposal as late.
The protest is denied. (Northstar
Location Services LLC B-409722.10: May 8, 2015)
(pdf)
C2G argues that the reverse auction system “must have
malfunctioned when it failed to accept C2G’s revised
prices, submitted with one second remaining in the bidding
period, and failed to then extend the bidding period for
an additional three minutes.” Protest at 5-6. For the
reasons that follow, we deny the protest.
It is an offeror’s responsibility, when transmitting its
proposal electronically, to ensure the proposal’s timely
delivery by transmitting the proposal sufficiently in
advance of the time set for receipt of proposals to allow
for timely receipt by the agency. Alalamiah Tech. Grp.,
B-402707.2, June 29, 2010, 2010 CPD ¶ 148 at 3. Proposals
that are received in the designated government office
after the exact time specified are “late,” and generally
may not be considered for award. While this rule may seem
harsh in some circumstances, it alleviates confusion,
ensures equal treatment of all offerors, and prevents one
offeror from obtaining a competitive advantage that may
accrue where an offeror is permitted to submit a proposal
later than the deadline set for all competitors. Id.
In determining whether a proposal was submitted late, we
consider all relevant evidence in the record, including
statements by parties on behalf of the protester and the
agency, to ascertain whether a preponderance of the
evidence shows that the proposal was at the designated
location for receipt prior to the time set for closing.
Caddell Constr. Co., Inc., B-280405, Aug. 24, 1998, 98-2
CPD ¶ 50 at 6. In negotiated procurements, we have held
that, unless it is shown to be unreasonable, the
contracting official’s declaration that a procurement is
closed is determinative. U.S. Aerospace, Inc., B-403464,
B-403464.2, Oct. 6, 2010, 2010 CPD ¶ 225 at 9; Caddell
Constr. Co., Inc., supra, at 8.
Here, we find that C2G has failed to establish that its
revised bid was submitted to and received by DLA prior to
the closing time for the reverse auction, or that the
reverse auction system otherwise malfunctioned. As stated
above, it is an offeror’s responsibility to ensure that an
electronically submitted proposal is received by--not just
submitted to--an agency prior to the time set for closing.
It is undisputed that an offeror had to complete three
steps in order to successfully place a bid during the
reverse auction. It is also undisputed that the protester
did not complete the second of the three required steps
until there was only two seconds left in the reverse
auction. Even assuming that the system generated the
prompt for C2G to “place” its bid and the protester was
able to click the prompt--all within the span of two
seconds--there is no evidence that the revised bid was
timely received by DLA.
DLA’s agent, Procurex, represented that C2G’s revised
bid--allegedly submitted with one second left in the
auction--was not received prior to the closing time.
Procurex Results for Reverse Auction at 2; Decl. of DLA
Procurement Analyst at 4. The protester has submitted no
evidence that the bid, which was “placed” (the third step
in the three-step process) with one second left in the
reverse auction, was actually received by the reverse
auction system (i.e., successfully placed). In this
regard, the protester represents that it contacted
Procurex’s owner and quality assurance lead. C2G
represents that the Procurex official stated that there is
a lag time of a few seconds to fifteen seconds between
when a bidder clicks the “place bid” button/link and the
time when the system processes the bid because the system
needs time to process the information inputted by the
bidder and due to external factors, such as internet
connections and bidders’ computer systems. Decl. of C2G
COO at 1-2. We find this explanation to be consistent with
common knowledge and experience that some delay is to be
expected when data is transmitted across the internet and
must be processed by a receiving database. It also is
consistent with the fact that offerors took between 5 and
15 seconds to successfully place their bids after
previewing them during the reverse auction. Therefore, we
find no basis to challenge the reasonableness of DLA’s
determination that C2G’s proposal was not received before
the reverse auction’s closing time.
C2G also argues that DLA was required to disclose to
offerors the potential lag time between the placing of a
bid and when the system could process the data. See
Response to Request for Dismissal (Feb. 25, 2015) at 5. We
disagree. As noted above, we think the potential delay
between entering data, transmitting the data across the
internet, and the receiving system processing the data is
readily apparent from common experience using the
internet. Furthermore, an agency is not required to
apprise offerors of every conceivable risk or obstacle
they could face in submitting their proposals. Rather, as
stated above, it is incumbent on an offeror to submit its
proposal in a prompt and efficient manner to ensure timely
delivery to, and receipt by, an agency. In this regard, we
also note that the agency invited offerors to participate
in a mock auction using the same system that was used for
the actual reverse auction. The activity log for the mock
auction similarly shows that offerors took several seconds
between previewing and successfully placing their bids.
See Procurex Results for Mock Auction at 1-2. Offerors
therefore were afforded the opportunity to utilize the
system that would be used in the reverse auction, and
could, and should, have addressed any concerns regarding
apparent lag times between previewing and successfully
placing bids with DLA prior to the actual reverse auction.
The protest is denied. (C2G
Ltd. Company B-411131: May 12, 2015) (pdf)
FAST asserts that its proposal was improperly rejected
since it was submitted more than four hours prior to the
closing time for receipt of proposals. FAST also contends
that its transmission email was only 17.929 MB in size,
less than the solicitation’s 20 MB limit, and thus should
have been accepted by the agency. In addition, FAST
asserts that proposal emails from other offerors may also
have been improperly rejected.
The agency, relying on DISA’s records, responds that
FAST’s email with proposal totaled 24.84 MB and the other
offeror’s email totaled 21.39 MB, and thus “at the time
[they] entered the Government computer system,” both were
over the 20 MB limit set forth in the RFP. COS at 6; Supp.
AR, Dec. 3, 2014, at 8.
As an initial matter, the record clearly indicates that no
proposal was received by SOCOM from FAST. It is an
offeror’s responsibility to deliver its proposal to the
proper place at the proper time. Federal Acquisition
Regulation (FAR) § 15.208; Lakeshore Eng’g Servs.,
B‑401434, July 24, 2009, 2009 CPD ¶ 155 at 4. Here, as
noted, the record indicates that FAST’s proposal was
rejected (“bounced”) by the agency’s server; was never
received at the agency email address designated for
receipt of proposals; and can not be retrieved from the
agency’s servers. We have consistently declined to require
an agency to consider a proposal where, as here, there is
no evidence that the proposal was “actually received.”
See, e.g., DJW Consulting, LLC, B-408846.3, Dec. 18, 2013,
2014 CPD ¶ 77 at 4 (search of servers did not identify
transmittal email); Latvian Connection Trading and Constr.,
LLC, B-402410, Feb. 25, 2010, 2010 CPD ¶ 58 at 3 (thorough
searches of agency’s email system “did not result in any
finding of the protester’s proposal”); International
Garment Processors, B-299674, et al., July 17, 2007, 2007
CPD ¶ 130 at 7 (check of facsimile machines provided no
evidence submission was actually received at the
designated location). We decline to do so here.
Moreover, we need not resolve the dispute between FAST and
the agency about whether the FAST submission was under
20MB. Although DISA disputes FAST’s contention, FAST
received an “undeliverable” bounce back message more than
four hours prior to the closing time. Other offerors
successfully responded to messages indicating their
submissions were undeliverable by modifying their
submissions and resending them; FAST could have done so as
well.
FAST further asserts that the agency’s rejection of its
proposal resulted from a systemic failure of the agency’s
systems, as evidenced by the agency’s rejection of not
only its proposal, but also at least one other proposal as
oversized when in fact they were not. In this regard, FAST
notes that we have sustained protests where the protester
demonstrated that the agency’s systems suffered a
“systemic failure” that violated an agency’s obligation to
have procedures in place to reasonably safeguard proposals
or quotations actually received and to give them fair
consideration. See, e.g., S.D.M. Supply, Inc., B‑271492,
June 26, 1996, 96‑1 CPD ¶ 288 at 4-5; East West Research,
Inc., B‑239565, B-239566, Aug. 21, 1990, 90‑2 CPD ¶ 147,
aff’d, Defense Logistics Agency--Recon., B-239565.2,
B‑239566.2, Mar. 19, 1991, 91-1 CPD ¶ 298. A finding that
a proposal or quotation was not received due to a
“systemic failure,” however, requires more than “the
occasional negligent loss” of a proposal or quotation. See
East West Research, supra, at 4. For example, in S.D.M.
Supply, Inc., supra, a systemic failure was found when the
electronic contracting system in use at that time
malfunctioned, resulting in all quotations submitted
through the system not being received by the agency. Id.
at 4‑5. Further, the agency in that case conceded that
similar failures had occurred for other solicitations
issued by the agency. Id. at 4. Similarly, in East West
Research, Inc., supra, the agency lost two quotations from
the same offeror within less than one week, with “no
explanation” for the losses. Id. at 4-5.
Such circumstances are not present here. Rather, the
agency successfully received 15 proposals, in 32 total
emails containing proposal information. COS at 2; Supp.
AR, Dec. 3, 2014, at 8. The record also shows that three
proposals initially were rejected by the SOCOM server on
September 15 for exceeding the size limit, but two of the
proposals were successfully resubmitted by means of
smaller emails. Supp. AR, Dec. 3, 2012, at 2-4. Only FAST
made no attempt to resubmit its proposal prior to closing.
Id. at 7-8. Thus, even if there were problems with respect
to the agency server’s implementation of the email size
limitation, those problems did not amount to a “systemic
failure.” All offerors that diligently pursued submission
of their proposals were eventually successful, and the
agency received 15 timely proposals.
The protest is denied. (Federal
Acquisition Services Team, LLC B-410466: Dec 31, 2014)
(pdf)
TSI challenges the agency’s rejection of its proposal
revision. The protester contends that the agency was
required to accept the revision because the changes it
made to its proposal are covered by the authority found at
FAR § 15.208(b)(2). In this regard, TSI asserts that it
submitted an otherwise successful offer, as demonstrated
by the agency’s decision to open negotiations with the
company, and that the revisions it made to its proposal
make its offer more favorable to the government.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time and late delivery
generally requires rejection of the proposal. FAR §
15.208(a); PMTech, Inc., B-291082, Oct. 11, 2002, 2002 CPD
¶ 172 at 3. Proposals that are received in the designated
government office after the exact time specified are late,
and generally may not be considered for award unless the
exceptions outlined in FAR § 15.208(b) apply. U.S.
Aerospace, Inc., B-403464, B‑403464.2, Oct. 6, 2010, 2010
CPD ¶ 225 at 10-11; PM Tech, Inc., supra. While the rule
may seem harsh, it alleviates confusion, ensures equal
treatment of all offerors, and prevents one offeror from
obtaining a competitive advantage that may accrue where an
offeror is permitted to submit a proposal later than the
common deadline set for all competitors. NCI Information
Sys., Inc., B-405745, Dec. 14, 2011, 2011 CPD ¶ 280 at 5;
U.S. Aerospace, Inc., supra; Inland Serv. Corp., Inc.,
B-252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
TSI maintains that under FAR § 15.208(b)(2), the agency
was required to accept its late proposal submission
because TSI submitted a late modification of an otherwise
successful proposal that makes its terms more favorable to
the Government. In this regard, the protester views its
untimely proposal revisions as a modification to its
“otherwise successful” initial proposal.
Based upon our review of the record, we conclude that the
protester has not demonstrated that it submitted an
otherwise successful proposal; thus, the exception to the
late proposal rule, proffered by TSI, is not applicable
here. In this regard, our Office has held that an
otherwise successful proposal is one that would result in
the award of the contract to the offeror regardless of the
late modification. Seven Seas Eng’g & Land Surveying,
B-294424.2, Nov. 19, 2004, 2004 CPD ¶ 236 at 4. As
described above, the RFP terms made clear that only those
offers that were rated acceptable under all three
non-price evaluation factors could be eligible for award.
RFP at 20, 32. TSI’s initial offer was rated unacceptable
under all three of the RFP’s non-price evaluation factors.
AR, Tab 5, Competitive Range Determination, at 3. In
accordance with the terms of the solicitation, the agency
could not have awarded TSI a contract; thus, the
protester’s initial proposal was not an otherwise
successful proposal. Accordingly, the agency reasonably
rejected TSI’s revised proposal as late.
The protest is denied. (Team
Systems International, LLC, B-410420: Dec 19, 2014)
(pdf)
Mr. Scott’s proposal was sent by USPS Priority Mail
Express (1-day service) from Colorado Springs at 5:02 p.m.
local time on July 29. CO Statement at 2. The CO states
that MSC’s mailroom at the Washington Navy Yard received
Mr. Scott’s proposal on July 31, at 11:00 a.m. AR, Tab 2,
Mailroom Log, at 109. When the CO received the package, he
noted that affixed to it was a label which indicated that
the package had been received by JBAB at 2:09 p.m. on July
30.[3] Id. 107. Because the proposal was not received at
the MSC mailroom by 2:00 p.m. on July 30, as required by
the solicitation, the CO rejected Mr. Scott’s proposal as
late. The agency notified Mr. Scott of the rejection of
his proposal by email on August 1. AR, Tab 3, Letter from
MSC to Mr. Scott (Aug. 1, 2014), at 152-153. This protest
to our Office followed.
Mr. Scott argues that his proposal was received at the
JBAB mail facility before the time set for the receipt of
proposals and that the proposal was therefore under the
agency’s control; for these reasons, the protester
contends that its proposal should have been considered
timely received by the agency. The protester also notes
that the Navy maintained a chain of custody of his offer
from its receipt at the JBAB facility to its receipt at
the MSC facility. The protester further contends that the
agency’s failure to adequately warn offerors that internal
Navy procedures could cause significantly greater delays
to mailed offers constitutes misdirection on the part of
the agency. Protester’s Comments at 15. The protester
states that the agency “sabotage[d]” mailed proposals in
this regard.[4] Id.
It is an offeror’s responsibility to deliver its proposal
to the place designated in the solicitation by the time
specified, and late receipt generally requires rejection
of the proposal. Federal Acquisition Regulation (FAR) §
15.208(a); O.S. Sys., Inc., B‑292827, Nov. 17, 2003, 2003
CPD ¶ 211 at 3; Integrated Support Sys. Inc., B‑283137.2,
Sept. 10, 1999, 99-2 CPD ¶ 51 at 2. As our Office has
held, a proposal that was received late may be considered
if the late receipt was caused by mishandling at the
government installation. Russo & Sons, Inc., B-280948,
Dec. 11, 1998, 98-2 CPD ¶ 141 at 3.
Even assuming Mr. Scott’s proposal arrived at the JBAB
facility prior to the solicitation’s closing time, we find
no basis to sustain the protest. Our Office has clearly
held that receipt of a bid or proposal at a mailroom or
other receiving area does not constitute receipt at the
location specified in the RFP, provided the agency has
established reasonable procedures to ensure that mailed
bids or proposals are routed from the mailroom to the
location designated in a solicitation for receipt. See
CCSC, Inc., B‑404802.3, July 18, 2011, 2011 CPD ¶ 187 at
6; General Power Eng’g Assocs., Inc., B‑292170, May 28,
2003, 2003 CPD ¶ 109 at 3; Inland Marine Indus. Inc.,
B‑233117, Feb. 16, 1989, 89-1 CPD ¶ 165 at 3; Fishermen’s
Boat Shop, Inc., B‑223366, Oct. 3, 1986, 86-2 CPD ¶
389.[5] An offeror must allow sufficient time for the
proposal to pass through any intermediate stops and reach
the designated office on time. Systems for Bus., B‑224409,
Aug. 6, 1986, 86-2 CPD ¶ 164 at 3. On this record, we find
no basis to conclude that the Navy improperly rejected Mr.
Scott’s proposal.
Mr. Scott also contends that the Navy’s CO is responsible
for this late filing because the CO did not quickly send
the engineering drawings requested in Mr. Scott’s July 25
agency-level protest. Protester’s Comments at 17.
Specifically, Mr. Scott argues that the CO sent the
engineering drawings to at least three of his competitors
by July 7, but did not provide him the drawings until July
28. Id.
In our view, the protester cannot shift responsibility for
its late filing to the agency. The record shows that Mr.
Scott filed his agency-level protest on July 25, and was
provided documents three days later. In addition, the
protester requested additional time to submit his
proposal, and the agency granted the protester’s request
by issuing RFP amendment No. 5, which extended the
proposal due date by one day. As also discussed above, the
solicitation clearly advised offerors that there was the
potential for “unpredictable and lengthy routing delays”
in the delivery of mailed proposals to the agency. RFP at
75. To the extent that the protester believed that he did
not have sufficient time in which to prepare his proposal
after the issuance of amendment No. 5, he was required to
protest the lack of time prior to the July 30 closing
time. Bid Protest Regulations, 4 C.F.R. ¶ 21.5(a)(1)
(2014).
The protest is denied. (Brian
X. Scott, B-410195: Nov 7, 2014) (pdf)
LATG challenges the agency’s rejection of its proposal.
LATG does not dispute that it filed its [proposal
revisions] PRs after 5:00 p.m. on March 27. Rather, LATG
argues that even if its PRs were late, the agency should
have considered its initial proposal because the PRs were
not mandatory, and the changes LATG made were merely
“enhancements” and “explanations” not meant to change or
replace LATG’s initial proposal. Protest at 2; Comments at
1-2.
It is an offeror’s responsibility to deliver its proposal
to the proper place at the proper time and late delivery
generally requires rejection of the proposal. FAR §
15.208; PMTech, Inc., B-291082, Oct. 11, 2002, 2002 CPD ¶
172 at 2. Similarly, it is an offeror’s responsibility,
when transmitting its proposal electronically, to ensure
the proposal’s timely delivery by transmitting the
proposal sufficiently in advance of the time set for
receipt of proposals to allow for timely receipt by the
agency. Associated Fabricators & Constructors, Inc.,
B-405872, Dec. 14, 2011, 2011 CPD ¶ 279 at 3. Proposals
that are received in the designated government office
after the exact time specified are late, and generally may
not be considered for award. U.S. Aerospace, Inc.,
B-403464, B-403464.2, Oct. 6, 2010, 2010 CPD ¶ 225 at 10.
While the rule may seem harsh, it alleviates confusion,
ensures equal treatment of all offerors, and prevents one
offeror from obtaining a competitive advantage that may
accrue where an offeror is permitted to submit a proposal
later than the common deadline set for all competitors.
NCI Information Sys., Inc., B-405745, Dec. 14, 2011, 2011
CPD ¶ 280 at 5; U.S. Aerospace, Inc., supra; Inland Serv.
Corp., Inc., B-252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at
3.
With respect to the submission of PRs, the agency held
discussions with LATG, and informed LATG that it could
“alter” or “explain” “those aspects of [its] proposal
identified” in discussions “to materially enhance” the
“proposal’s potential for award.” AR, Tab K, Agency E-Mail
to LATG, March 21, 2014. Our review of the record
indicates that LATG’s PRs consisted of 45 pages, including
a four percent reduction in price. AR, Tabs M and N,
LATG’s PRs. On this record, we believe that the agency
reasonably found that LATG’s submission of the PRs
demonstrated LATG’s intent to modify its initial proposal,
and thereby eliminated LATG’s initial proposal (without
the revisions) from further consideration. See Integrated
Bus. Solutions, Inc., B-292239, July 9, 2003, 2003 CPD ¶
122 at 4; Touchstone Textiles, Inc., B-272230.4, Sept. 5,
1996, 96-2 CPD ¶ 107 at 2.[2]
Alternatively, LATG asserts that its late PRs constituted
late modifications of an otherwise successful proposal
that make its terms more favorable to the government, and
are therefore properly acceptable under FAR §§
15.208-2(b)(2) and 52.215-1. Comments at 2. This assertion
is equally without merit. It is well-settled that the term
“otherwise successful proposal” restricts this exception
to permit the government’s acceptance of a late
modification offering more favorable terms only from the
offeror already in line for the contract award.
Environmental Tectonics Corp., B-225474, Feb. 17, 1987,
87-1 CPD ¶ 175 at 4; see The Sandi Group, Inc., B‑401218,
June 5, 2009, 2009 CPD ¶ 123 at 3; Phyllis M. Chestang,
B‑298394.3, Nov. 20, 2006, 2006 CPD ¶ 176 at 5 n.3. Thus,
an offeror cannot avail itself of the late proposal
submission provision where the agency has not already
identified an otherwise successful offeror. Global
Analytic Info. Tech. Servs., Inc., B-298840.2, Feb. 6,
2007, 2007 CPD ¶ 57 at 5-6.
Here, the record establishes that no award decision has
been made. CO Statement at 2. Accordingly, the exception
set forth in both FAR §§ 15.208-2(b)(2) and
52.215-1(c)(3)(ii) is inapplicable. (LATG,
Inc., B-409679.2: Jul 31, 2014) (pdf)
Detailed instructions for
the submission of proposals were provided, stating, as
relevant here, that offerors were required to submit their
proposals through the agency’s online SeaPort-e portal.
RFP at 103.
(sections
deleted)
ICI
challenges the rejection of its proposal, arguing that the
agency’s position is based on an overly rigid
interpretation of the RFP’s proposal submission
instructions and a strained reading of the undisputed
facts. ICI argues, citing our decision in Tishman Constr.
Corp., B‑292097, May 29, 2003, 2003 CPD ¶ 94, that the
Navy should not have considered the submission of its
revised proposal as being late. The crux of ICI’s position
is that its final revised proposal was not late, given
that ICI requested and was granted leave to submit its
proposal by email, which it did well before the closing
time for receipt of proposal revisions. ICI further states
that it timely resubmitted its final revised proposal
through the e-portal when instructed to do so by amendment
6.
The Navy responds that the contracting specialist’s
acceptance of ICI’s revised proposal by email was invalid
“because the [contract specialist] had mistakenly assumed,
based on ICI’s submission of the [final proposal revision]
via email, that [ICI] had experienced technical
difficulties or that ICI was unable to access or use the
SeaPort-e system to upload ICI[’s] [final proposal
revision].” AR at 5. The agency suggests that the contract
specialist was misled by ICI, because ICI did not
demonstrate that the firm had difficulty in submitting its
revised proposal through the portal. AR at 8. The Navy
also argues that because ICI did not submit its proposal
to the “Government installation designated for receipt of
proposals,” that is, through the SeaPort-e portal, the
proposal was late, although received by the agency prior
to the closing time for submission of revised proposals.
Generally, a proposal received after the time set for
receipt may not be considered for award. In this regard,
“[o]fferors are responsible for submitting proposals, and
any revisions, and modifications, so as to reach the
Government office designated in the solicitation by the
time specified . . . .” Federal Acquisition Regulation §
15.208(a). The late proposal rule alleviates confusion,
ensures equal treatment of offerors, and prevents one
offeror from obtaining a competitive advantage as a result
of being permitted to submit a proposal later than the
deadline set for all competitors. Inland Serv. Corp.,
Inc., B‑252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
Although there is much disagreement in the record about
such things as whether technical difficulties prevented
ICI from uploading its proposal through the portal and
whether the contract specialist was misled with respect to
authorizing ICI’s submission of its proposal by email, we
need not resolve these disagreements. As relevant and
dispositive here, the record shows that the Navy
installation designated for receipt of proposals was in
receipt of ICI’s revised proposal by the closing time for
receipt of revised proposals. In this regard, the record
establishes the following facts: (1) the RFP provided an
alternative means for submitting proposals when there were
difficulties with the portal; (2) several offerors
(including ICI and BECTech), and the agency itself,
encountered technical difficulties with the portal; (3)
ICI requested and received permission to submit its
proposal by email and did so before the closing time for
receipt of proposals; and (4) the Navy amended the RFP to
allow re-submission of revised proposals, and both ICI and
BECTech submitted revised proposals through the portal by
the amended closing time.
We agree with ICI that our decision in Tishman Constr.
Corp., supra, is applicable here. In that case, we found
that the procuring agency improperly rejected the
protester’s proposal as late. The solicitation in Tishman
required the submission of both paper and electronic
versions of proposals. Although the agency timely received
the electronic version of the protester’s proposal, the
paper version was not received until after the time set
for receipt of proposals. Because the agency had received
a timely, complete copy of the electronic version of the
protester’s proposal, we found the agency’s rejection of
the proposal to be unreasonable. We affirmed, as we do
here, that the policy underlying the late proposal rule is
to ensure fair and equal competition and avoid confusion.
Although the Navy argues that accepting ICI’s proposal
“without evidence that [ICI] even attempted to upload its
proposal . . . would have put the other offerors at a
competitive disadvantage,” AR at 11, the agency does not
explain or show how other offerors would be disadvantaged,
nor do we see any such possibility here.
The protest is sustained. (ICI
Services, Inc., B-409231.2: Apr 23, 2014) (pdf)
DJW argues that the Air
Force unreasonably rejected its proposal. First, the protester contends that,
contrary to the agency assertion, it submitted an OCI plan. Second, DJW argues
that the agency should have provided the protester an opportunity to address its
failure to propose prices that complied with the applicable Service Contract Act
wage determination. For the reasons discussed below, we conclude that the Air
Force reasonably rejected DJW’s proposal based on its failure to submit an OCI
plan; we therefore need not address the protester’s
challenge to the agency’s rejection of its proposal for
failing to demonstrate compliance with the applicable
Service Contract Act wage determination.
It is an offeror’s responsibility to deliver its proposal to the proper place at
the proper time. FAR § 15.208; Lakeshore Eng’g Servs., B-401434, July 24, 2009,
2009 CPD ¶ 155 at 4. We have found an agency’s rejection of a proposal is
reasonable where, notwithstanding a protester’s claim that it emailed its
proposal to the agency, the record does not show that the proposal was actually
received. See Latvian Connection Trading and Constr., LLC, B-402410, Feb. 25,
2010, 2010 CPD ¶ 58 at 3.
As discussed above, the RFP required offerors to provide OCI plans in advance of
their proposals. RFP at 68. The agency states, and the protester does not
dispute, that submission of an OCI plan was a material requirement of the
solicitation. See AR at 4; Contracting Officer’s Statement at 8-10.
DJW states that its representative submitted the protester’s OCI plan via email
on May 31 to the two contracting officers responsible for the solicitation.
Affidavit of DJW Representative (Nov. 1, 2013) at 2. The protester states that
this individual requested an automated confirmation of delivery of that email
through “our company email system.” Id. The DJW representative received the
following response through the company’s email system: “Delivery to these
recipients or group is complete, but no delivery notification was sent by the
destination server.” Protester’s Comments, attach. 1, Receipt for email delivery
(May 31, 2013).
DJW contends that the delivery receipt demonstrates it timely delivered its OCI
plan. Although the documentation provided by the protester states that “no
delivery notification was sent by the destination server,” id., the protester
speculates that problems with the agency’s mail servers could have resulted in
the failure to provide receipt confirmation. Affidavit DJW Representative (Nov.
1, 2013) at 3.
We find that the circumstances here do not provide a basis to sustain the
protest. Although the protester provided an automated notice from its own email
system concerning the transmission of its OCI plan, the notice, on its face,
does not demonstrate that the proposal was received by the agency. See
Protester’s Comments, attach. 1, Receipt for email delivery (May 31, 2013).
Moreover, the Air Force states that, in response to the protest, it conducted a
search of the server that supports the email accounts for the two contracting
officers to see if either had received an email from DJW’s representative on May
31. Email from Agency Technical Representative to Agency Counsel (Nov. 4, 2013).
This search did not identify an email from DJW during the relevant time frame,
nor did the search identify any email concerning DJW’s OCI plan.[3] Id. The
agency also submitted statements from the two contracting officers explaining
that their email and file records were searched for DJW’s OCI plan, but that the
document was not found. Contracting Officer’s Statement at 12; Decl. of Second
Contracting Officer (Oct. 31, 2013). Under the circumstances here, where the
agency represents that it has made reasonable efforts to search its email system
for a particular email, and states that the message was not received, and where
the protester does not provide any basis to question the agency’s
representations, we find no basis to sustain the protest. See Latvian Connection
Trading and Constr., LLC, supra.
In the alternative DJW argues that the Air Force should have contacted the
protester to inquire about the missing OCI plan. As discussed above, however,
the RFP advised that the agency intended to make award without discussions, and
the agency did not conduct discussions with the offerors. An agency is not
required to provide an opportunity for discussions or clarifications under such
circumstances. See Kiewit Louisiana Co., B-403736, Oct. 14, 2010, 2010 CPD ¶ 243
at 3; Satellite Servs., Inc., B-295866, B-295866.2, Apr. 20, 2005, 2005 CPD ¶ 84
at 2 n.2. To the extent DJW contends that the agency should have provided the
protester an opportunity to submit its missing OCI plan, this argument provides
no basis to sustain the protest.
The protest is denied. (DJW Consulting, LLC,
B-408846.3: Dec 18, 2013) (pdf)
MOWA-Barlovento protests that the Corps unreasonably excluded the firm from the
competitive range, which prevented MOWA-Barlovento from submitting a revised
proposal. See Protest at 12. The protester also complains that the agency failed
to provide prompt notice of the exclusion of the firm’s proposal from the
competitive range, which denied the protester certain procedural safeguards to
which it argues it was entitled.
The Corps states that it did not exclude MOWA-Barlovento’s proposal from the
competitive range. Instead, the Corps explains that it concluded that
MOWA-Barlovento was electing to remove itself from the competition by failing to
timely submit a response to the discussion letter and to acknowledge a material
solicitation amendment. The Corps also states that it could not consider
anything the protester submitted after it failed to timely respond to the first
round of discussions, since any submission after March 27 would be late. AR at
4-5, citing Federal Acquisition Regulation (FAR) § 15.208(b)(1).
The protester argues that amendment 6 is not material, arguing that it would not
have changed its proposal in response to the amendment and that a change in the
period in which the optional item could be exercised is inconsequential because
this “amounts to only a 20 day increase for a bid item representing ½ of 1% of
the total bid price.” See Protester’s Response to Agency Request for Dismissal,
exhib. B, President’s Affidavit. MOWA-Barlovento also argues that the FAR late
proposal rules do not apply to proposal revisions in response to an agency’s
discussions. See Protester’s Response to Intervenor’s Supp. Comments, at 2.
First, we disagree with the protester that amendment 6 was not material.
Generally, an amendment is material where it imposes legal obligations on the
contractor that were not contained in the original solicitation. Skyline ULTD,
Inc., B297800.3, Aug. 22, 2006, 2006 ¶ 128 at 3. In this regard, changing the
time within which an option can be exercised changes the rights of the parties
and is therefore material. See, e.g., Peckham Vocational Indus., Inc., B‑257100,
Aug. 26, 1994, 94-2 CPD ¶ 81 at 4-5.
We also do not agree with MOWA-Barlovento’s apparent belief that the agency was
required, under the circumstances presented here, to allow the protester to
submit a late response to the discussions letter and amendment. While the
protester, and even our Office, would have preferred a more forthcoming response
from the agency in answer to the protester’s April 8 and April 25 inquiries,
those responses would not have changed the fact that MOWA-Barlovento failed to
respond to the discussion letter or to acknowledge the solicitation amendment by
March 27. Since the record here unequivocally establishes that the agency was
not the cause of MOWA-Barlovento’s failure to timely respond to the agency’s
discussions and to acknowledge a material amendment, we cannot say that the
agency has violated any procurement law or regulation by applying the language
of a cut-off date stated in the discussions letter. (MOWA
Barlovento, LLC-JV, B-408445: Sep 12, 2013) (pdf)
ICC
contends that its quotation was timely submitted, arguing that amendment 1 of
the RFQ effectively changed the time for receipt of quotations to 4:30 p.m.,
eastern time, because the amendment extending the date for solicitation
responses did not state a time for receipt of quotations. In this regard, ICC
states that FAR clause 52.212-1(f)(1) provides that where no time for receipt of
quotations is stated in the solicitation, the time for receipt of quotations is
4:30 p.m., local time. ICC also contends that, in any event, HUD waived the 3
p.m. time for receipt of quotations because the agency’s contract specialist
informed ICC that HUD would accept ICC’s quotation if received at any time on
July 26.
Generally, late quotations may be considered up to the time of issuance of the
order, because an RFQ, unlike a request for proposals (or an invitation for
bids), does not seek offers that can be accepted by the government to form a
contract. Rather, the government’s purchase order represents an offer that the
vendor may accept through performance or by a formal acceptance document. See
M.Braun, Inc., B-298935.2, May 21, 2007, 2007 CPD ¶ 96 at 3. Where, as here
however, an RFQ contains a late quotations clause--such as, FAR clause
52.212-1(f)--the agency’s consideration of late quotations is limited. Id.
ICC does not contend that the RFQ allowed HUD to consider late quotations.
Rather, ICC’s complaint reflects its belief that, because the agency’s extension
of the closing date did not restate the time for receipt of quotations, the
solicitation in effect did not state a time for submission of quotations. There
is no merit to this argument. We have previously found that where an amendment
changes only the date for receipt of quotations or proposals, the time
established for receipt is unchanged. See Sandler-Innocenzi, B-218322, 85-1 CPD
¶ 353 at 2; Pacific Coast Welding & Machine, Inc., B-205874, Jan. 15, 1982, 82-1
CPD ¶ 36 at 3-4. Here, the RFQ as issued established the hour and date for
receipt of quotations as 3 p.m., eastern time, on July 23, 2013. Although
amendment 1 changed the date for receipt of quotations to July 26, it did not
change the time. Accordingly, the amended time for receipt of quotations was 3
p.m., eastern time, July 26, and ICC’s quotation that was received after that
time was late.
We also find no merit to ICC’s contention that HUD waived the date and time for
receipt of quotations because the contract specialist allegedly agreed to accept
ICC’s quotation. We have repeatedly held that oral advice that would have the
effect of altering the written terms of a solicitation, does not operate to
amend a solicitation or otherwise legally bind the agency. See e.g., Noble
Supply & Logistics, B-404731, Mar. 4, 2011, 2011 CPD ¶ 67 at 3; Systems 4, Inc.,
B-270543, Dec. 21, 1995, 95-2 CPD ¶ 281 at 2. (International
Code Council, B-409146, Jan 8, 2014) (pdf)
RDT argues
that its proposal was delivered before the time set for submission, and contends
that the agency’s rejection was improper because of the actions of the mailroom
clerk. Specifically, the protester contends that the clerk accepted the proposal
before the time for acceptance of proposals had passed and then delayed in
putting a date/time stamp on the proposal. The protester contends that
regardless of the time indicated on the receipt, RDT’s proposal was possessed
by, and under the control of, the agency for several minutes prior to the
proposal submission deadline.
It is an offeror’s responsibility to deliver its proposal to the place
designated in the solicitation by the time specified, and late receipt generally
requires rejection of the proposal. FAR § 15.208(a); O.S. Sys., Inc., B-292827,
Nov. 17, 2003, 2003 CPD ¶ 211 at 3; Integrated Support Sys. Inc., B-283137.2,
Sept. 10, 1999, 99-2 CPD ¶ 51 at 2. Unless a preponderance of the evidence
demonstrates that the proposal was at the designated location for receipt prior
to the time set for closing, the proposal may not be considered for award. See
Med-National, Inc., B-277430, Sept. 8, 1997, 97-2 CPD ¶ 67 at 3. A late
hand-carried proposal may be considered for award, however, if improper
government action was the paramount cause of the late delivery and consideration
of the proposal would not compromise the integrity of the competitive
procurement process. Caddell Constr. Co., Inc., B-280405, Aug. 24, 1998, 98-2
CPD ¶ 50 at 6. Improper government action in this context is affirmative action
that makes it impossible for the offeror to deliver the proposal on time. Id.
For example, our Office has held that a late hand-carried offer may be
considered for award if the government’s misdirection or improper action was the
paramount cause of the late delivery and consideration of the offer would not
compromise the integrity of the competitive process. See Palomar Grading &
Paving, Inc., B-274885, Jan. 10, 1997, 97-1 CPD ¶ 16 at 3. A late proposal may
also be accepted if it is found to have been received at the designated
government installation and was under the agency’s control at the time set for
receipt of proposal. Id. at 3. Nonetheless, even in cases where the late receipt
may have been caused, in part, by erroneous government action, a late proposal
should not be considered if the offeror significantly contributed to the late
receipt by not doing all it could or should have done to fulfill its
responsibility to deliver a hand-carried proposal to the specified place by the
specified time. ALJUCAR, LLC, B-401148, June 8, 2009, 2009 CPD ¶ 124 at 3; O.S.
Sys., Inc., supra.
Here, both the mailroom clerk’s story and RDT’s story were corroborated in part
by the mailroom supervisor. On the day in question, the supervisor explains that
she was taking a break from 1:45 to 2:10 p.m. in her car in the parking lot
adjoining the Corps of Engineers building. AR, Tab 4, Decl. of Mailroom
Supervisor (Sept. 26, 2013), at 2. The supervisor states that she saw a car
driven by a man she did not know enter the parking lot and circle around looking
for parking; she did not see him park the car. Id. The supervisor then saw the
same man, this time with a box, at the mailroom door, which was promptly opened
by the clerk. Id. The supervisor states that she then saw “the same man leave
the facility a very short time later--not more than a minute or two--after he
entered the building.” Id. at 2. The supervisor explains that she paid close
attention to the man as he entered and exited the mailroom because she was aware
that proposals were due that afternoon. Id.
As discussed above, there is no dispute in this record that the agency gave the
protester a stamped and handwritten receipt showing that RTD’s proposal was
received at 2:03 p.m. Protest, exh. B, Receipt (2:03 p.m., Aug. 13, 2013). The
protester does not dispute the accuracy of the time stamp. Instead the protester
contends that its representative entered the mailroom at “approximately 1:58
p.m.” and handed the proposal to the mail clerk. Decl. of RDT Representative
(Aug. 30, 2013), at 2. The declaration of RDT’s representative does not,
however, explain the basis for his statement regarding the time that he entered
the building; for example, he does not state whether this time was based on his
own clock or the clock in the mailroom. See id. As our Office has held, the time
maintained by an agency for receiving bids or proposals is determinative, unless
that time standard is found to be unreasonable under the circumstances. See U.S.
Aerospace, Inc., B-403464, B-403464.2, Oct. 6, 2010, 2010 CPD ¶ 225 at 9.
In addition, the clerk states that, according to the clock in the mailroom,
RDT’s representative did not enter the mailroom until after 2:00 p.m. AR, Tab 6,
Decl. of Mailroom Clerk (Sept. 26, 2013), at 1. We also note that the statements
provided by the mailroom clerk and the mailroom supervisor are consistent. See
id. at 1-2; AR, Tab 4, Decl. of Mailroom Supervisor (Sept. 26, 2013), at 2. In
the absence of any basis to question the agency’s statements about when the
protester arrived--i.e., after 2 p.m.--we conclude that the preponderance of the
evidence does not support the protester’s contention that the agency mishandled
its proposal. See Med- National, Inc., supra; Caddell Constr. Co., Inc., supra.
We also find that the protester’s attempt to make the delivery only a couple of
minutes before the time deadline was the paramount cause of the lateness.[2] RDT
simply did not allow sufficient time to fulfill its responsibility to deliver
its proposal by the proper time. See Wyatt & Assocs., B-243349, July 1, 1991,
91-2 CPD ¶ 5 at 2-3. In short, RDT assumed a risk in allowing so little time for
delivery of its proposal here. Einhorn Yaffe Prescott, B-259552, Mar. 20, 1995,
95-1 CPD ¶ 153 at 4. In these circumstances where the protester did not act
reasonably to fulfill its obligation to deliver its proposal on time, we find no
basis to question the agency’s decision to reject the proposal as late. (RDT-Semper
Tek JV, LLC B-408811, Dec 9, 2013) (pdf)
On July 9,
the contract specialist, who had been out of the Office on July 8, returned to
work and began to open the e-mailed proposals. She opened the e-mail message
identified by the protester as e-mail 1 of 2, printed the attachment, and sent
the protester an e-mail response acknowledging that the message had been
received. The contract specialist also opened the protester’s second e-mail
message, but found no attachments. The contract specialist did not acknowledge
this e-mail message.
The contract specialist proceeded to contact the contracting officer to see
whether he had received the attachment to the second e-mail. The contracting
officer, who had also been out of the office on July 8 and who had not opened
either of JVDB’s e-mail transmissions prior to being contacted by the contract
specialist, opened both of the protester’s e-mails and verified that while the
first e-mail included an attachment, the second e-mail did not.
The contract specialist then contacted the office’s computer service provider to
determine whether there had been any issues with the system on July 8 that might
have prevented the delivery of e-mail attachments. On July 10, the computer
services provider responded that there had been no issues on the date in
question.
Also on July 10, the contract specialist and the contracting officer received a
third e-mail message from JVDB, which indicated that the protester had received
acknowledgment of its first e-mail only, and thus was resending the second
message. This third e-mail message included the protester’s price proposal,
joint venture documents, and line item schedule as attachments. Because this
message was received after the specified closing time, the contracting officer
considered it to be untimely.
On July 11, the contracting officer notified JVDB that its proposal had been
rejected as incomplete. On July 15, the protester filed an agency-level protest,
in which it speculated that the Navy’s e-mail system had stripped the
attachments from its message. The protester argued that if this were the case,
the agency should consider the proposal. In the alternative, JVDB argued that
when the contracting office received its second e-mail without the referenced
attachments, the agency was on notice of a problem with the transmission and
should have followed up with the protester. In JVDB’s view, since the agency
failed to alert JVDB of the problem, the agency should consider its price
proposal.
In response to the agency-level protest, the contract specialist again contacted
the office’s computer services provider, which examined its logs. The logs
showed that two e-mail messages had been received from the protester on July 8,
the first of which included an attachment and the second of which did not. The
logs identified the status of each message as “Legitimate,” meaning that they
were delivered without alteration. In this connection, the Deputy Director of
the Theater Network Operation Support Europe explained that if an attachment is
stripped from an e-mail message, the word “Blocked” appears in the log instead
of the word “Legitimate,” and a reply is triggered and sent to the sender
informing him/her that the attachment has been removed. Declaration of the
Deputy Director, Aug. 5, 2013; Exh. C to Agency-level protest decision. The
Deputy Director further reported that no computer network or system errors
affecting the receipt and delivery of e-mail were recorded on July 8 between 8
a.m. and 4 p.m.
By decision of August 14, the Navy denied JVDB’s agency-level protest, noting
that there was no evidence that the Navy’s e-mail servers had stripped the
attachments from the second e-mail. The agency further noted that its personnel
had not been required to open the protester’s e-mails until after the submittal
deadline had passed.
JVDB protested to our Office on August 26. The protester does not dispute the
agency’s findings regarding the absence of computer or system errors, which
could have affected the agency’s receipt of JVDB’s price proposal. Rather, JVDB
simply argues that it was unreasonable for agency personnel not to have reviewed
its e-mails--and notified it of the missing attachments--on July 8.
The protester’s argument is without merit. As an initial matter, the protester
bore the burden of ensuring the timely receipt of its proposal, not the agency,
and where JVDB’s proposal was received late, it could not be considered except
under limited circumstances specifically set forth in the Federal Acquisition
Regulation (FAR), none of which apply in this case. See FAR § 52.215-1(c)(3). To
the extent the protester suggests that the lateness of its proposal should be
excused because the agency’s procedures for receipt of proposals were deficient,
we disagree. JVDB has cited no law, regulation, or decision by this office--nor
are we aware of any--in support of the proposition that agency personnel have a
duty to review e-mailed offers for completeness prior to the proposal closing
date and to notify offerors of any missing sections. Ultimately, the primary
cause of JVDB’s late proposal submission was the protester’s failure to attach
its price proposal when it e-mailed its proposal to the agency, not the agency’s
failure to alert the protester to this error on the date proposals were due. See
Turner Consulting Group, Inc., B-400421, Oct. 29, 2008, 2008 CPD ¶ 198 at 4.
(JV Derichebourg-BMAR & Associates, LLC, B-408777,
Nov 20, 2013) (pdf)
Late
Proposal
Philips first protests that McKesson’s proposal was ineligible for award because
McKesson’s final proposal revision (FPR) was not submitted by the date and time
set for receipt of FPRs. Supp. Protest at 4-5. We agree.
The record here establishes that the deadline for submission of FPRs was noon on
December 2, 2011. Agency Request for McKesson Final Proposal, at 1. The record
further establishes that the agency did not receive McKesson’s FPR until 1:04 pm
on December 2. Second Supp. AR at 2. In transmitting its FPR, McKesson stated
that it “struggled . . . to get this attachment [containing a portion of its FPR]
to send properly.” First Supp. AR, Tab C, Agency E-mail correspondence with
McKesson, at 2. The agency acknowledges that McKesson did not submit its FPR
until after the established deadline, stating that “[a] problem with the email
address, due to an uncommon spelling of the contracting officer’s name resulted
in [McKesson’s proposal] not being received before Noon.” Second Supp. AR at 2.
It is an offeror’s responsibility to deliver its proposal to the proper place at
the proper time and late delivery generally requires rejection of the proposal.
FAR § 15.208; PMTech, Inc., B-291082, Oct. 11, 2002, 2002 CPD ¶ 172 at 2.
Similarly, it is an offeror’s responsibility, when transmitting its proposal
electronically, to ensure the proposal’s timely delivery by transmitting the
proposal sufficiently in advance of the time set for receipt of proposals to
allow for timely receipt by the agency. Associated Fabricators & Constructors,
Inc., B-405872, Dec. 14, 2011, 2011 CPD ¶ 279 at 3. Proposals that are received
in the designated government office after the exact time specified are late, and
generally may not be considered for award. U.S. Aerospace, Inc., B-403464,
B-403464.2, Oct. 6, 2010, 2010 CPD ¶ 225 at 10. While the rule may seem harsh,
it alleviates confusion, ensures equal treatment of all offerors, and prevents
one offeror from obtaining a competitive advantage that may accrue where an
offeror is permitted to submit a proposal later than the common deadline set for
all competitors. NCI Information Sys., Inc., B-405745, Dec. 14, 2011, 2011 CPD ¶
280 at 5; U.S. Aerospace, Inc., supra; Inland Serv. Corp., Inc., B-252947.4,
Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
The agency contends that it was entitled to accept McKesson’s late proposal
because the language of Federal Acquisition Regulation (FAR) § 52.212-1(f)(2)(i)
“allows late offers to be considered if they are received before award and would
not unduly delay award.” Second Supp. AR at 2; Second Supp. CO Statement at 1.
The agency also argues that its acceptance of McKesson’s late proposal was
permissible under FAR § 52.212-1(f)(2)(ii), which allows the agency to accept a
late modification of an “otherwise successful proposal” that makes its terms
more favorable to the government.
The agency is mistaken with regard to both assertions. With regard to the
agency’s first argument, FAR § 52.212-1(f)(2) states in its entirety:
(2)(i) Any offer, modification, revision, or withdrawal of
an offer received at the Government office designated in the solicitation
after the exact time specified for receipt of offers is “late” and will not be
considered unless it is received before award is made, the Contracting Officer
determines that accepting the late offer would not unduly delay the
acquisition; and—
(A) If it was transmitted through an electronic commerce
method authorized by the solicitation, it was received at the initial point
of entry to the Government infrastructure not later than 5:00 p.m. one
working day prior to the date specified for receipt of offers; or
(B) There is acceptable evidence to establish that it was
received at the Government installation designated for receipt of offers and
was under the Government’s control prior to the time set for receipt of
offers; or
(C) If this solicitation is a request for proposals, it was the only
proposal received.
(ii) However, a late modification of an otherwise
successful offer, that makes its terms more favorable to the Government, will
be considered at any time it is received and may be accepted.
FAR § 52.212-1(f)(2) (emphasis added).
In short, FAR § 52.212-1(f)(2)(i) provides that, in order for the agency to
properly accept a late proposal pursuant to this provision, the proposal must be
received before award, its acceptance will not unduly delay the acquisition, and
one of the alternatives listed in subsections (A), (B), or (C) must apply. Here,
the agency has not asserted that any of the alternatives in subsections (A),
(B), or (C) apply, and our review of the record confirms that none is
applicable. Accordingly, the agency’s acceptance of McKesson’s late proposal
does not fall under the exceptions specified in FAR § 52.212-1(f)(2)(i).
Next, the agency’s assertion that McKesson’s late FPR constituted a late
modification of an otherwise successful proposal that makes its terms more
favorable to the government, and is therefore properly acceptable pursuant to
FAR § 52.212-1(f)(2)(ii), is equally without merit. This exception applies only
to an “otherwise successful proposal.” The Sandi Group, Inc., B-401218, June 5,
2009, 2009 CPD ¶ 123 at 3. It is well-settled that the term “otherwise
successful” restricts this exception to permit the government’s acceptance of a
late modification offering more favorable terms only from the offeror already in
line for the contract award. Environmental Tectonics Corp., B-225474, Feb. 17,
1987, 87-1 CPD ¶ 175 at 4; see The Sandi Group, Inc., supra; Phyllis M. Chestang,
B-298394.3, Nov. 20, 2006, 2006 CPD ¶ 176 at 5 n.3. Thus, an offeror cannot
avail itself of the late proposal submission provision where the agency has not
already identified an “otherwise successful offeror.” Global Analytic Info.
Tech. Servs., Inc., B-298840.2, Feb. 6, 2007, 2007 CPD ¶ 57 at 5-6.
Here, the record establishes that, prior to the agency’s review of FPRs, the
agency had not identified any offeror as being in line for award. To the
contrary, even after receipt of FPRs, the source selection authority stated that
there was “no clear-cut choice.” AR, Tab 2, SSDD, at 7. Accordingly, the
exception set forth in FAR § 52.212-1(f)(2)(ii) is inapplicable, and there was
no basis for the agency to accept McKesson’s late proposal.
We sustain the protest on this basis. (Philips
Healthcare Informatics, B-405382.2, B-405382.3, B-405382.4, May 14, 2012)
(pdf)
NCI contends
that Harris was ineligible for award because Harris’s FPR was not submitted by
the date and time set for receipt of FPRs. Comments at 9-13. Specifically, NCI
argues that the agency set the due date for FPRs as the close of business on
August 31, and because the contracting officer’s notice did not provide a
specific time for “close of business,” the language of FAR § 52.215-1(c)(3) and
the solicitation dictate that the time for receipt of FPRs was 4:30 p.m.
Protester’s Comments at 9.
The agency contends that a specific time--close of business--was provided in the
contracting officer’s memorandum, and therefore the FAR clause (which provides
that 4:30 p.m. is the closing time if no time is specified) does not apply here.
Citing a decision by the General Services Board of Contract Appeals (GSBCA) from
1987, the agency argues that “close of business” means that proposals would be
received on the specified date at “any time prior to when the office closed for
the day . . . so long as an employee remained in the office during that
employee’s regularly scheduled duty hours.” Federal Sys. Group, Inc., GSBCA No.
9240-P, 88-1 BCA ¶ 20334. The agency argues that since the contracting officer’s
flextime hours are from 7:00 a.m. to 5:00 p.m. on Wednesdays (the day FPRs were
due), close of business that day was 5:00 p.m. The agency also argues that GAO
implicitly adopted the Federal Systems Group rule in 120 Church Street
Assoc.--Recon., B-232139.4, May 23, 1989, 89-1 CPD ¶ 490, in which GAO
distinguished the facts of that case from the facts of Federal Systems Group,
holding that where agency employees do not work flextime schedules and there is
an agency order establishing an agency-wide closing time, the time specified in
the order controls.
Under negotiated procurements, the FAR provides generally that a proposal or
revision received after the time set for receipt shall not be considered. FAR §
15.208(b)(1). Our Office has long held that the late proposal rule alleviates
confusion, ensures equal treatment of offerors, and prevents one offeror from
obtaining a competitive advantage as a result of being permitted to submit a
proposal later than the deadline set for all competitors. Sunrise Medical HHG,
Inc., B-310230, Dec. 12, 2007, 2008 CPD ¶ 7 at 8; Tishman Constr. Corp.,
B-292097, May 29, 2003, 2003 CPD ¶ 94 at 3. FAR § 52.215-1(c)(3)(i) states that
if no time for submission is specified in the solicitation, the time for receipt
is 4:30 p.m., local time. In 120 Church Street Assoc.--Recon., supra, our Office
stated that this FAR provision establishes 4:30 p.m. local time “as the close of
business where the solicitation does not state a specific time for receipt of
proposals.” Id. at 3.
Here, we find that the agency’s reference (in its request for FPRs) to the
“close of business” did not state a specific time for receipt of proposals. We
decline to adopt the Federal Systems Group rule that where an agency has no
established time for the close of business and allows its employees to work
flextime schedules, close of business means any time so long as an employee
remains in the office during his or her duty hours. Adoption of such a rule
would result in confusion and a lack of uniformity, where, as here, employees
work different schedules on different days.
Where, as in 120 Church Street, the agency has established official working
hours, then “close of business” means the end of the official day. Where, as
here, an agency does not have official working hours, then pursuant to FAR §
52.215-1(c)(3)(i), 4:30 p.m. local time is considered to be the close of
business where the solicitation does not state a specific time for receipt of
proposals. In this way, the exact date and time for submission of proposals will
be easily ascertainable to all potential offerors.
The contracting officer’s e-mail, which was sent only to Harris, cannot be
considered an amendment to the solicitation’s due date, and we have held that an
offeror acts unreasonably when it relies on the informal advice of a contracting
officer rather than following the solicitation’s instructions. See Noble Supply
& Logistics, B-404731, Mar. 4, 2011, 2011 CPD ¶ 67 at 3 (offeror acted
unreasonably where it relied on contracting officer’s oral permission to submit
proposal after stated closing time); Radva Corp., B-219595, July 26, 1985, 85-2
CPD ¶ 101 at 2 (“even if the contracting officer had told [the offeror] that its
late proposal would be accepted, the contracting officer in fact lacked the
authority to accept the late proposal”); see also Diamond Aircraft Industries,
Inc., B-289309, Feb. 4, 2002, 2002 CPD ¶ 35 (holding that informal advice sent
via e-mail to only one offeror could not amend the solicitation, and offerors
who rely on such informal advice do so at their own risk).
While application of the late proposal rules may sometimes seem harsh, the rules
are aimed at ensuring equal treatment of all offerors, and promoting confidence
in the competitive system, thereby protecting the integrity of the procurement
process--goals that are of greater importance than the possible advantage gained
by considering a late proposal in a single procurement. U.S. Aerospace, Inc.,
B-403464, B-403464.2, Oct. 6, 2010, 2010 CPD ¶ 225 at 10 n.16. The rationale
underlying strict application of the late proposal rules is to prevent even the
slightest possibility of any offeror gaining an unfair competitive advantage by
being able to make material changes in its offer after the cutoff date and time.
Computer Sciences Corp., B-190632, Aug. 4, 1978, 78-2 CPD ¶ 85.
The awardee here submitted its FPR after the time set for receipt, and the
agency should have rejected it as late. We therefore sustain the protest.
NCI Information Systems, Inc., B-405745, December
14, 2011. (pdf)
AFC does not
dispute that the FPI official designated for receipt of proposals was located in
the eastern time zone. Nor does AFC dispute that its proposal was first received
by FPI after 2:00 pm eastern time on September 23. The protester nevertheless
contends that its proposal was not late and should not have been rejected as
untimely because it met the RFP requirements, as AFC understood them. In support
of its position AFC argues that: (1) it first sent its proposal by 2:00 pm
central time; and (2) it believed the closing time was 2:00 pm central time
because contract performance was to occur in the central time zone. The
protester also essentially maintains that the timeliness of its proposal should
be measured by when AFC submitted its proposal, rather than when the designated
contracting official received it. We disagree.
It
is an offeror’s responsibility to deliver its proposal to the proper place at
the proper time. FAR § 15.208(a) (offerors are responsible for submitting
proposals so as to reach the designated government office by the specified
time); PMTech, Inc., B-291082, Oct. 11, 2002, 2002 CPD ¶ 172 at 2; Integrated
Support Sys. inc, B-283137.2, Sept. 10, 1999, 99-2 CPD ¶ 51 at 2. Similarly, it
is an offeror’s responsibility, when transmitting its proposal electronically,
to ensure the proposal’s timely delivery by transmitting the proposal
sufficiently in advance of the time set for receipt of proposals to allow for
timely receipt by the agency. PMTech, Inc., supra. Proposals that are received
in the designated government office after the exact time specified are “late,”
and generally may not be considered for award.3 While the rule may seem harsh,
it alleviates confusion, ensures equal treatment of all offerors, and prevents
one offeror from obtaining a competitive advantage that may accrue where an
offeror is permitted to submit a proposal later than the common deadline set for
all competitors. Inland Serv. Corp., Inc.
, B-252947.4, Nov. 4, 1993, 93-2 CPD ¶ 266 at 3.
Here, the RFP established a closing date and time of
2:00 pm eastern time on September 23. The solicitation also informed prospective
offerors in unambiguous terms that the controlling event was the agency’s
receipt--as opposed to an offeror’s submission--of proposals by the due date and
time. However, the record reflects that the FPI contracting officer did not
receive AFC’s proposal until 4:21 pm eastern time, well after both 2:00 pm
eastern time and 2:00 pm central time. In sum, the fact that AFC believed that
it had sent its proposal in advance of the designated closing time is not
determinative of the proposal’s timeliness.
Lastly, although AFC does not dispute that the RFP twice
expressly stated that the time for receipt of proposals was 2:00 pm eastern
time, AFC argues that the language on the Standard Form 1449 (“OFFER DUE
DT/LOCAL TIME, 9/23/2011 2:00 PM”) was ambiguous. Comments, Oct. 18, 2011, at
1-2. To the extent there was any ambiguity in the RFP regarding the closing
time, we find that AFC was required to protest this apparent solicitation defect
prior to the time for receipt of initial proposals. 4 C.F.R. § 21.2(a)(1)
(2011); see Sea Box, Inc. , B-401523, B-401523.2, Sept. 25, 2009, 2009 CPD ¶ 190
at 4 (conflict regarding solicitation closing date constituted a patent
ambiguity that was readily apparent prior to the time set for receipt of
submissions).
In sum, since AFC’s electronically transmitted proposal
was not received until 4:21 pm eastern time, after the time set for receipt of
proposals, it is a late proposal. Further, since it was not received at the
initial point of entry by 5:00 pm the day before proposals were due, the late
proposal cannot be accepted. FAR § 52.212-1(f)(2)(i)(A); Sea Box, Inc.,
B-291056, supra
, at 4. (Associated Fabricators & Constructors,
Inc., B-405872, December 14, 2011) (pdf)
ERC asserts
that the agency should not have rejected its proposal as late because the late
delivery of its proposal was caused by not allowing ERC to self deliver its
proposal with its own employee. ERC contends that other offerors were permitted
to have their own employees or agents (as distinguished from third-party
commercial carriers) hand deliver their proposals, yet ERC was not given the
same opportunity to ensure that its proposal was timely delivered.
It is an offeror's responsibility to deliver its proposal
to the proper place by the proper time, and late delivery generally requires
rejection of the proposal. Federal Acquisition Regulation sect. 15.208; The
Staubach Co., B-276486, May 19, 1997, 97-1 CPD para. 190 at 3. A proposal
delivered to an agency by a commercial carrier is considered to be hand-carried
and, if it arrives late, can only be considered for award if it is shown that
some government impropriety during or after receipt by the government was the
sole or paramount cause of the late arrival at the designated place. On-Site
Envt'l, Inc.; WRS Infrastructure & Env't., Inc., B-294057, B-294057.2, July 29,
2004, 2004 CPD para. 138 at 3. Improper government action in this context is
affirmative action that makes it impossible for the offeror to deliver the
proposal on time. Caddell Constr., Co., Inc., B-280405, Aug. 24, 1998, 98-2 CPD
para. 50 at 6. Nevertheless, even in cases where the late receipt may have been
caused, in part, by erroneous government action, a late proposal should not be
considered if the offeror significantly contributed to the late receipt by not
acting reasonably in fulfilling its responsibility to deliver a hand-carried
proposal to the proper place by the proper time. O.S. Sys., Inc., B-292827, Nov.
17, 2003, 2003 CPD para. 211 at 3.
ERC argues that it was treated unequally and prejudiced by the Air Force's
instructions to mail, rather than self deliver, its proposal to the contracting
officer at the address designated in the RFP. However, the record evidences that
ERC did not follow this advice, but chose to have its proposal delivered by a
commercial carrier. As indicated above, this is considered to be hand delivery
of a proposal by an agent of the offeror. On-Site Envt'l, Inc.; WRS
Infrastructure & Env't., Inc., supra.
Even conceding that the agency may have caused ERC to use a commercial carrier
rather than self delivering the proposal by its own employees or agents, the
record evidences that the delivery driver contributed significantly to the late
delivery of the proposal. In this regard, ERC admits that the delivery driver
arrived at the gate to Hanscom in sufficient time to deliver the proposal to the
proper place at the proper time, but chose not to enter the base at that time to
avoid waiting in a long line. It is apparent that this was the paramount cause
that ERC's proposal was delivered late, not improper government action.
Accordingly, we conclude that the Air Force properly rejected ERC's proposal as
late. (ERC Inc., B-405563, November 18,
2011) (pdf)
CCSC's
current protest argues that the firm followed the delivery directions in the RFP
which permitted the use of FedEx but did not make offerors aware of the
existence of either the [consolidated remote delivery site] CRDS or the
attendant screening delay. CCSC argues that following the RFP directions was the
paramount cause of the late delivery of the firm's proposal. Protester's
Comments at 3, 13. CCSC emphasizes that its proposal was addressed as specified
in the RFP, submitted to FedEx for delivery by 8:30 a.m. on December 14, and
that FedEx sought permission from the contracting officer to complete the
delivery before the closing time. Protest at 2; Protester's Comments at 4. Thus,
CCSC argues, its actions would have resulted in timely delivery of the proposal
at issue except that the [United States Customs and Border Protection] CBP
procedures allegedly made that impossible. Protester's Comments at 19.
The CBP responds that RFP proposal submission instructions
were "appropriate" and were not the primary cause of CCSC's late proposal. AR at
1. The CBP argues that it did not mishandle the proposal or make delivery
impossible. AR at 7. Instead, the agency maintains that CCSC should have
expected security delays due to package screening, and thus it should not have
delayed shipping the proposal until after 6 p.m. on December 13, the night
before it was due. AR at 8.
It is an offeror's responsibility to deliver its proposal
to the proper place at the proper time, and late delivery generally requires
rejection of the proposal. Federal Acquisition Regulation (FAR) sect. 15.208;
O.S. Sys., Inc., B-292827, Nov. 17, 2003, 2003 CPD para. 211 at 3. A proposal
delivered to an agency by FedEx or other commercial carrier is considered to be
hand-carried and, if it arrives late, can be considered if it is shown that some
government impropriety during or after receipt at the government installation
was the sole or paramount cause of the late arrival at the designated place.
Chappy Corp., B-252757, July 20, 1993, 93-2 CPD para. 44 at 3. Improper
government action in this context is affirmative action that makes it impossible
for the offeror to deliver the proposal on time. Lani Eko & Co., CPAs, PLLC,
B-404863, June 6, 2011, 2011 CPD para. 118 at 3.
To establish that government mishandling was the sole or
paramount cause of the late receipt of a proposal, an offeror must first
establish that it did not significantly contribute to the late delivery by not
allowing enough time to permit a timely submission. Wyatt & Assocs., B‑243349,
July 1, 1991, 91‑2 CPD para. 5 at 2-3. Even in cases where the late receipt may
have been caused, in part, by erroneous government action, a late proposal
should not be considered if the offeror significantly contributed to the late
receipt by not doing all it could or should have done to fulfill its
responsibility to deliver a hand-carried proposal to the specified place by the
specified time. ALJUCAR, LLC, B-401148, June 8, 2009, 2009 CPD para. 124 at 3;
O.S. Sys., Inc., supra., at 3.
Offerors are responsible for allowing a reasonable time for
proposals to be delivered from the point of receipt to the location designated
for receipt of offers; failure to do so, resulting in late arrival at the
designated location, cannot be attributed to governmental mishandling. CSLA,
Inc., B-255177, Jan. 10, 1994, 94‑1 CPD para. 63 at 2-3. Furthermore, delays in
gaining access to a government building are not unusual and should be expected.
Bergen Expo Sys., Inc.; Techniarts Eng'g, B‑236970; B-236970.2, Dec. 11, 1989,
89-2 CPD para. 540 at 3; see also ALJUCAR, LLC, supra., at 4 (proposal properly
rejected as late when delivered after closing time although courier arrived at
security gate 8 minutes before closing time); Kesser Int'l, B-296294, June 30,
2005, 2005 CPD para. 127 at 2 (proposal properly rejected as late when delivered
after closing time although courier was delayed 20 minutes at security
checkpoint); Wyatt & Assocs., B-243349, July 1, 1991, 91-2 CPD para. 5 at 3
(proposal properly rejected as late when delivered after closing although
courier arrived at security desk 10 minutes before closing time). Therefore, an
offeror that does not submit a proposal sufficiently in advance of the closing
time runs the risk that the agency's reasonable internal delivery procedures
will not get the proposal to the proper location by the required time. Bay
Shipbuilding Corp., B‑240301, Oct. 30, 1990, 91‑1 CPD para. 161 at 3 (bid sent
overnight was properly rejected as late when it arrived late at bid opening
room, even though delivered to agency mailroom 6 hours before bid opening time);
see also CSLA, Inc., supra., at 3; cf. Power Connector, Inc., B‑256362, June 15,
1994, 94-1 CPD para. 369 at 4 (agency reasonably considered late bid where
mishandling by agency mailroom caused late arrival at bid opening room).
The record here provides several significant facts
demonstrating that CCSC was, in large part, responsible for its proposal
arriving late. First, the protester did not bring its proposal to FedEx until
after 6 p.m. on the day before it was due, and CCSC has not shown that it was
impossible for it to have sent its proposal earlier to allow for potential
security screening. Second, CCSC placed no identification on the packaging
identifying that a proposal was inside, and there is no evidence that the FedEx
representative identified to the agency that the company was attempting to
deliver a proposal when the representative called the contracting officer on the
morning of delivery. Third, the protester should have expected delays due to
security screening, particularly considering that the proposal was being
submitted to DHS, an agency involved in national security that would be expected
to have tight security. Finally, the RFP did not warrant that delivery by FedEx
or any other express courier would actually reach the contracting officer on the
day of delivery. On these facts, we cannot conclude that the agency's conduct
was the paramount cause of the late receipt of CCSC's proposal.
CCSC argues that the rerouting of its proposal to Maryland is akin to the
situation addressed by our decision in Dale Woods, B-209459, Apr. 13, 1983, 83-1
CPD para. 396. In that decision, we determined that an agency improperly changed
the location for the submission of bids without adequately informing prospective
bidders. Although all other bidders noticed a sign specifying the new location,
the protester arrived only 20 minutes before the closing time, and it did not
notice the signs. Our Office concluded that the agency had not satisfied its
duty to establish reasonable procedures for the timely receipt of bids when it
changed the delivery location without adequate notice, and we therefore
sustained the protest. Id. at 3, 5. CCSC argues that the CBP's actions were
similar. Protest at 11. We disagree.
Unlike in Dale Woods, the CBP here did not change the
location for submission of proposals, but rather only required deliveries to be
screened off-site prior to delivery to the specified location in the RFP. Mail
screening is common in government facilities, and should have been expected in
an agency such as DHS. Accordingly, our decision in Dale Woods is
distinguishable and is not persuasive here.
CCSC also argues that our decision in Hospital Klean of
Texas, Inc., B‑295836, B‑295836.2, Apr. 18, 2005, 2005 CPD para. 185, provides
support for its protest. In that case, we held that an agency properly
considered proposals that were due on a Saturday, but were not delivered by
FedEx until Monday, because the agency had not provided adequate means for the
FedEx courier to obtain entry into the building on Saturday. Protest at 12. CCSC
argues that the CBP similarly failed to provide a means for FedEx to deliver to
the specified address for receipt of proposals here.
However, unlike the situation in Hospital Klean where the
delivery courier encountered a locked door preventing his entry, CCSC has not
shown that it was physically impossible for its proposal to reach the
contracting officer at the designated location by the closing time set forth in
the RFP. Rather, the delivery of CCSC's proposal was delayed for security
screening, which CCSC should have expected. By not allowing sufficient time for
screening at the CRDS, CCSC bears the responsibility for its late proposal.
In sum, the CCSC has not shown that the RFP's failure to
describe the agency's mail screening policy was the primary cause of the late
proposal submission.
Instead, as described above, the protester failed to take
reasonable steps to ensure timely delivery. (CCSC,
Inc., B-404802.3, July 18, 2011) (pdf)
SGS asserts
that the agency's rejection of its FPR due to the late
submission of its subcontractor was improper because, according
to SGS, "even without [DELETED] revised business proposal
spreadsheets, SGS's proposal was complete." Protester's Comments
at 3. We agree.
Offerors are responsible for submitting proposals, and any
modifications to them, so as to reach the government office
designated in the solicitation by the time specified in the
solicitation. Federal Acquisition Regulation (FAR) sect.
15.208(a). Proposals, and modifications to them, that are
received in the designated government office after the exact
time specified are "late," and will be considered only if
received before award, and if the circumstances meet the
specific requirements of the provision at FAR sect. 52.215-1.
FAR sect. 15.208(b). Portions of proposals that are submitted
late may not be considered by the agency, and if the proposal is
unacceptable as timely submitted, it should be rejected as late.
See Inland Serv. Corp., Inc., B-252947.4, Nov. 4, 1993, 93-2 CPD
para. 266 at 4 (proposal was late and not acceptable where the
technical proposal was received on time but the price proposal
was late); Panasonic Comms. & Sys. Co., B-239917, Oct. 10, 1990,
90-2 CPD para. 279 (initial proposal was properly rejected
because it did not contain a significant required bid sample).
On the other hand, a proposal which does not provide all items
required by the solicitation may not be automatically rejected
if the proposal information received by the deadline is
sufficient to constitute an acceptable proposal. See Wetlands
Research Assocs., Inc., B-246342, Mar. 2, 1992, 92-1 CPD para.
251 at 5, n.7.
SGS contends that its proposal was acceptable, even without
[DELETED] revised business proposal spreadsheets. According to
SGS, [DELETED] was a minor subcontractor included for the
purpose of adding [DELETED] under one of the least important
non-cost evaluation factors. [DELETED] proposal included a total
of [DELETED] FTEs and was [DELETED] percent of SGS's total cost.
Protester's Comments at 21.
According to SGS, the changes to [DELETED] proposal were
reflected in SGS's Business FPR. For example, in response to
discussion questions indicating that [DELETED] may have
[DELETED] proposed FTEs/hours for its [DELETED] position, SGS's
FPR showed that the [DELETED] position had been [DELETED].
Protest, exh. 7, Discussion Response, at 9-11; Protester's
Comments, exh. 1, SGS Bus. FPR, vol. 1, Task Order 1, at I-6;
exh. 2, SGS Bus. FPR, vol. I, Task Order 2, at I-8. Moreover,
SGS's FPR business spreadsheet for each task order reflects the
number of FTEs, number of hours, and the total costs for each
labor category (there was only [DELETED]) proposed by [DELETED].
Protester's Comments, exh. 3, SGS FPR Task Order 1 Business
Spreadsheet; exh. 4, SGS FPR Task Order 2 Business Spreadsheet.
Here, the record reflects that the agency did not consider
whether SGS's FPR was acceptable without [DELETED] revised
business proposal spreadsheets. AR, Tab J-1, CMS Letter to SGS
(Mar. 9, 2011); Tab J-2, CMS Letter to SGS (Mar. 17, 2011)
("given the plain language in the solicitation, I believe it
remains appropriate to treat the entire proposal as late when
any part, no matter how small, was late."). However, as
discussed above, SGS asserts that its FPR was complete and
acceptable because it contained all of [DELETED] costs.
Our review confirms SGS's assertion that the information
included in [DELETED] revised business spreadsheet was reflected
in SGS's business proposal. Thus, [DELETED] submission could
appropriately be viewed as backup supporting material for SGS's
proposed costs. In addition, we note again that the [DELETED]
submission at issue here represents approximately [DELETED]
percent of SGS's total costs--and [DELETED] FTEs. In
circumstances like these, where an agency finds that an
offeror's proposed costs on a cost reimbursement contract are
not reasonably supported, an agency, as part of the cost realism
analysis, can adjust the proposed costs to account for this lack
of supporting information. See Magellan Health Servs., B-298912,
Jan. 5, 2007, 2007 CPD para. 81 at 13-14; Earl Indus., LLC,
B-309996, B-309996.4, Nov. 5, 2007, 2007 CPD para. 203 at 8‑9;
Metro Mach. Corp., B-295744, B-295744.2, Apr. 21, 2005, 2005 CPD
para. 112 at 10; General Offshore Corp.--Riedel Co., A Joint
Venture, B-271144.2, B‑271144.3, July 2, 1996, 96-2 CPD para. 42
at 11.
In sum, we conclude that the agency improperly rejected SGS's
entire FPR as late without considering whether the proposal was
acceptable without the subcontractor's revised business
proposal, and we sustain the protest on this basis. (SafeGuard
Services, LLC, B-404910, June 28, 2011) (pdf)
Lani Eko contends that its representative arrived at the Jemal
Building with its proposal package prior to the closing time on
March 2, and that the agency improperly refused to accept its
proposal. In support of its position, the protester relies on
its representative's timing of events, and maintains that
consistent with the language of the solicitation, the firm's
representative was "in line" at the loading dock prior to 3 p.m.
As such, the agency improperly determined that its proposal was
late. Protester's Comments at 1-2. We disagree.
It is an offeror's responsibility to deliver its proposal to the
place designated in the solicitation by the time specified, and
late receipt generally requires rejection of the proposal.
Federal Acquisition Regulation (FAR) sect. 15.208(a); O.S. Sys.,
Inc., B‑292827, Nov. 17, 2003, 2003 CPD para. 211 at 3;
Integrated Support Sys. Inc., B‑283137.2, Sept. 10, 1999, 99-2
CPD para. 51 at 2. Unless a preponderance of the evidence
demonstrates that the proposal was at the designated location
for receipt prior to the time set for closing, the proposal may
not be considered for award. See Med‑National, Inc., B-277430,
Sep. 8, 1997, 97-2 CPD para. 67 at 3. A late hand-carried
proposal may be considered for award, however, if improper
government action was the paramount cause of the late delivery
and consideration of the proposal would not compromise the
integrity of the competitive procurement process. Caddell Constr.
Co., Inc., B-280405, Aug. 24, 1998, 98-2 CPD para. 50 at 6.
Improper government action in this context is affirmative action
that makes it impossible for the offeror to deliver the proposal
on time. Id. Even in cases where the late receipt may have been
caused, in part, by erroneous government action, a late proposal
should not be considered if the offeror significantly
contributed to the late receipt by not doing all it could or
should have done to fulfill its responsibility to deliver a
hand-carried proposal to the specified place by the specified
time. ALJUCAR, LLC, B-401148, June 8, 2009, 2009 CPD para. 124
at 3; O.S. Sys., Inc., supra. We find no basis to conclude that
Lani Eko timely delivered its proposal or that improper
government action was the paramount cause for the late
submission of its proposal.
The agency reports that on March 2, three contract specialists
were present at various times throughout the day at the loading
dock in the Jemal Building to receive proposal packages. At
approximately 2:58 p.m., one of the contract specialists
declares that she began processing a hand-carried proposal
package from another vendor which she completed just after 3
p.m. Agency Report (AR) exh. 28, Decl. of Contract Specialist A,
Apr. 19, 2011; see also, exh. 29, Decl. of Contract Specialist
B, Apr. 19, 2011 at 2. According to this individual, at 3:01
p.m., after acknowledging that the closing time had passed, a
third contract specialist stepped out of the door to the loading
dock. The second contract specialist declares that no offerors
were waiting at the security desk at 3 p.m. AR, exh. 29, Decl.
of Contract Specialist B, Apr. 19, 2011, at 1. When the security
desk phone registered 3:01 p.m., the contract specialists
concluded that the submission deadline had passed, and the third
contract specialist went to the top of the loading dock stairs
to inform all offerors that the submission deadline had expired.
Id. The third contract specialist, who in fact engaged Lani
Eko's representative outside the loading dock, declares that no
offerors were waiting inside or outside of the loading dock at
3:01 p.m. (he verified the time via his wristwatch, cell phone
and security guard desk phone), and that approximately six
offerors, including Lani Eko's representative, approached the
loading dock door with their proposals as he was standing there.
AR, exh. 27, Decl. of Contract Specialist C, Apr. 19, 2011, at
2. After approximately a minute of conversation, the offerors
asked which clock he was using and the third contract specialist
indicated "the guard desk clock," which verified the time as
3:02 p.m. Id. Because the offerors arrived after the closing
time and were considered late, the contracting specialist
refused to accept their proposals. Id.
We conclude that the protester has failed to demonstrate by a
preponderance of evidence that it arrived at the place
designated for delivery of proposals by the 3 p.m. deadline
established by the RFP. In this regard, the protester offers no
evidence, other than the declaration of its own representative,
to support its assertion that it had arrived at the Jemal
loading dock area by 3 p.m. Moreover, the protester's assertion
of timely delivery is based solely on the time that its
representative observed on her personal cell phone. This is not
the relevant time, however, since the official time maintained
by the agency is controlling absent a showing that it was
unreasonable. See U.S. Aerospace, Inc., B‑403464, B-403464.2,
Oct. 6, 2010, 2010 CPD para. 225 at 9. With regard to the
official time, the protester's representative reports having
observed a time of 3:02 p.m. after being informed that its
proposal was late. This is consistent with the declarations
submitted by the agency, which represent that an agency
representative was waiting at the loading dock door at 3:01, the
protester arrived just after 3:01 p.m., and that, after a
conversation of approximately 1 minute, he showed her the
official time, which then was 3:02. On this record, we find
nothing unreasonable in the agency's determination that Lani
Eko's proposal was delivered late.
The protester also contends that its delivery was frustrated by
the agency's use of a security guard phone clock to determine
the closing time. Protest at 2. Lani Eko argues that use of this
device was unreasonable since there was a "1-2 minute
discrepancy maintained on that device versus on various cell
phones." Id. at 2. This argument is without merit. As noted
above, we have held that the time maintained by the agency
official responsible for receiving bids or proposals is
determinative, unless it is shown to be unreasonable under the
circumstances. U.S. Aerospace, Inc., B‑403464, B-403464.2,
supra. Here, there was nothing inherently unreasonable with the
agency's use of a security guard desk phone clock to determine
the solicitation's closing time. Notwithstanding the protester's
suggestion to the contrary, there simply is no requirement for
the time maintained by the agency to be synchronized with the
protester's personal cell phone, or any other cell phone.
Moreover, it is apparent that the paramount cause of Lani Eko's
late delivery of its proposal stemmed from the fact that Lani
Eko's representative arrived at the Jemal Building, according to
her own version of events, with approximately 1 minute to spare.
By allowing herself so narrow a margin of time, Lani Eko's
representative assumed the risk that any number of events might
intervene to prevent the timely submission of the proposal. See
Pat Mathis Constr. Co, Inc., B-248979, Oct. 9, 1992, 92-2 CPD
para. 236 at 4. Accordingly, we have no basis on which to object
to the agency's actions. (Lani
Eko & Company, CPAs, B-404863, PLLC, June 6, 2011) (pdf)
B&S contends that DLA should accept its proposals because the
agency was the primary cause of the late filing, and because the
courier was under the control of the agency at the time he
arrived at the VPC. We find no merit to these arguments.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time; proposals that are received
after the exact time specified are "late" and must generally be
rejected. Federal Acquisition Regulation (FAR) sect.
52.212-1(f); O.S. Sys., Inc., B-292827, Nov. 17, 2003, 2003 CPD
para. 211 at 3; Integrated Support Sys. Inc., B-283137.2, Sept.
10, 1999, 99-2 CPD para. 51 at 2. The late proposal rules
include limited exceptions under which late proposals may be
considered. Our Office has held that a late hand-carried offer
may be considered for award if the government's misdirection or
improper action was the paramount cause of the late delivery and
consideration of the offer would not compromise the integrity of
the competitive process. See U.S. Aerospace, Inc., B-403464,
B-403464.2, Oct. 6, 2010, 2010 CPD para. 225 at 11; ALJUCAR,
LLC, B-401148, June 8, 2009, 2009 CPD para. 124 at 3. A late
proposal may also be accepted if it is found to have been
received at the designated government installation and was under
the agency's control at the time set for receipt of proposals.
FAR sect. 52.212-1(f)(1)(B); U.S. Aerospace, Inc., supra, at 12.
Nonetheless, even in cases where the late receipt may have been
caused, in part, by erroneous government action, a late proposal
should not be considered if the offeror significantly
contributed to the late receipt by not doing all it could or
should have done to fulfill its responsibility. See U.S.
Aerospace, Inc., supra; ALJUCAR, LLC, supra.
Here, we conclude that the protester's actions were the
paramount cause for the late delivery. As discussed above, the
RFPs stated that if an offeror intended to hand deliver its
proposal, the offeror must provide notice to DLA a day in
advance of delivery in order to be sponsored and be entered into
the VNS. RFP, encl. 6, at 3; RFP, Q&A No. 8. The RFPs further
advised offerors that visitors would be required to check in at
the VPC, and that any delays encountered at the VPC would not be
a basis for accepting a late proposal. RFP, Q&A No. 8.
Despite the instructions and warnings in the RFPs, the record
shows that B&S's courier was not entered into the VNS system
prior to his arrival, nor did the courier have the appropriate
contact information to obtain a sponsor for entry into the VNS.
Moreover, the courier arrived at the VPC less than 10 minutes
before the proposal receipt deadline. On this record, we
conclude that the protester's actions, rather than the agency's
actions, were the paramount cause of the late receipt. See
ALJUCAR, LLC, supra, at 4 (a protester contributes significantly
to a delay where it fails to provide sufficient time for
delivery at a secure government facility).
To the extent that B&S contends that DLA's actions were the
paramount cause of the late delivery, we disagree. First, the
protester argues that the agency was responsible for the late
filing because the acquisition specialist directed the
protester's courier to the wrong building. As discussed above,
the agency does not dispute that the courier was initially
directed to Building 21, instead of Building 20. See AR at 3.
However, the videotape shows that the courier did not leave the
VPC until 1:03 p.m. On this record, we think it is clear that
the courier would not have made a timely delivery of the
proposals, even if he had been directed to the correct building.
Next, B&S contends that personnel at the VPC directed the
courier to call "a person who had nothing to do with the
matter," thus resulting in delay in the courier's departure from
the VPC. Protester's Comments at 3. As discussed above, however,
the call to the DLA Small Business Office was suggested by the
security officer because the courier was unable to provide the
appropriate contact information. Moreover, as discussed above,
the RFPs instructed offerors to contact DLA the day before an
attempted delivery in order to enter couriers into the VNS, and
warned that any delays encountered at the VPC were the
responsibility of the offeror. We do not think that the security
officer's suggestion to call the Small Business Office was the
paramount cause of the delay.
Finally, the protester argues that the courier was under the
control of the government as of the time the courier arrived at
the VPC, and thus the proposals should have been deemed as
timely received. In determining whether a late-submitted
proposal was "under the Government's control" prior to the time
set for receipt of proposals, our Office has held that an
offeror must, at a minimum, have relinquished physical custody
of the proposal. See U.S. Aerospace, Inc., supra; ALJUCAR, LLC,
supra. This requirement is an obvious necessity in order to
preclude any potential that an offeror could alter, revise, or
otherwise modify its proposal after other offerors' competing
proposals have been submitted. B&S's argument misapprehends the
legal standard: the issue is not whether the courier was under
the control of the government personnel, but instead whether the
proposal had been accepted by government personal, thereby
putting it under government control. The record here shows that
the courier did not relinquish control of the proposals until
his arrival at Building 20 at 1:20 p.m. CO's Memorandum Re: Late
Bids, Jan. 24, 2011, at 3. For this reason, as well as those
stated above, we find no merit the protester's arguments.
The protest is denied. (B&S
Transport, Inc., B-404648.3, April 8, 2011) (pdf)
The RFP set the closing date for receipt of proposals as 4:30
p.m. on December 22, 2010. The protester explains that on
December 21, it delivered its proposal package to UPS to be
shipped using "Next Day" service, but that when it checked on
the status of the delivery the following morning, UPS advised it
that severe weather would delay delivery of the package to the
23rd. According to Noble, it then located a UPS store in Minot,
North Dakota and spoke with an employee of the store, who
advised it that he would be able to print, package, and deliver
a copy of the proposal to the base prior to the 4:30 p.m.
closing time.
Before implementing this alternative plan for delivering its
proposal, however, the protester contacted the contracting
officer and explained its situation. According to Noble, the
contracting officer advised that she understood the protester's
problem and stated "that if the proposal was delivered on
December 23, it would still be evaluated." Protest at 5. Based
on this advice, the protester elected not to implement its
alternative plan for proposal delivery. UPS delivered the
proposal to Minot AFB at 11:05 a.m. on December 23.
By letter of January 3, the contracting officer notified Noble
that its proposal had been received after the specified closing
time and would not be considered. On January 13, Noble protested
to our Office.
The protester argues that its proposal was not late because the
contracting officer orally amended the RFP on December 22 to
extend the closing date to December 23. In the alternative,
Noble argues that even if its proposal was late, the agency
should have considered it, because the late delivery was the
result of incorrect information furnished by the contracting
officer.
The protester's first argument is without merit. While it is
true that a contracting officer may provide oral notice of a
solicitation amendment "when time is of the essence," see
Federal Acquisition Regulation (FAR) sect. 15.206(f), Noble has
not alleged that the contracting officer ever in fact advised
Noble that she would "amend" the solicitation to extend the
closing date until December 23. Rather, Noble essentially argues
that it understood the contracting officer's oral assurance that
its proposal would be evaluated even if submitted on the 23rd as
implying that the RFP would be amended since there would not
otherwise have been any basis for the contracting officer to
consider its proposal. However, absent an unambiguous statement
from the contracting officer conveying her intent to amend the
closing date for all offerors, Noble could not reasonably
disregard the solicitation's express closing date and instead
rely on an implied understanding of the contracting officer's
oral assurances, which were otherwise inconsistent with the
terms of the RFP. We have repeatedly held that oral advice that
would have the effect of altering the written terms of a
solicitation, even from the contracting officer, does not
operate to amend a solicitation or otherwise legally bind the
agency, ESCO Marine, Inc., B‑401438, Sept. 4, 2009, 2009 CPD
para. 234 at 8, and that an offeror relies on such oral advice
at its own risk. TRS Research, B-274845, Jan. 7, 1997, 97-1 CPD
para. 6 at 3.
Turning then to Noble's second argument, while it is an
offeror's responsibility to deliver its proposal to the proper
place at the proper time, and late delivery generally requires
rejection of the proposal, see FAR sect. 15.208, O.S. Sys.,
Inc., B-292827, Nov. 17, 2003, 2003 CPD para. 211 at 3, a
hand-carried proposal that arrives late may be considered if
improper government action was the paramount cause of the late
submission and consideration of the proposal would not
compromise the integrity of the competitive procurement process.
Hospital Klean of Texas, Inc., B-295836, B‑295836.2, Apr. 18,
2005, 2005 CPD para. 185 at 4-5.
The protester argues that it was the incorrect information
furnished by the contracting officer regarding the acceptability
of submitting its proposal a day after the specified closing
date that led it to forego its alternative approach to
delivering the proposal by the December 22 deadline, and that
improper government action was thus the paramount cause for the
late submission. We disagree. Even assuming that the contracting
officer did incorrectly advise the protester regarding the
acceptability of delivery on the 23rd, this misinformation did
not prevent the protester from delivering its proposal on time,
and thus was not the paramount cause of the late submission;
rather, it was the protester's decision to rely on the
contracting officer's erroneous oral advice, which was at
Noble's own peril as explained above, and thereby forego its
alternative approach to delivering its proposal that resulted in
the proposal being received late. Because the agency's actions
were not the paramount cause for the late receipt of Noble's
proposal, the agency properly rejected it as late. (Noble
Supply and Logistics, B-404731, March 4, 2011) (pdf)
Metters protests that its proposal should not have been rejected
as late, arguing that a complete copy of its proposal (with the
paper versions of the subcontractors' proposals) was submitted
to the agency before 3 p.m. Metters contends that, to the extent
that its proposal was considered late because it did not submit
its subcontractors' proposals on CDs until after 3 p.m., the RFP
was ambiguous as to what format must be used for the submission
of the subcontractors' proposals. Protest at 9.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time, and late delivery generally
requires rejection of a proposal. Slates Roofing Corp.,
B-286052, Nov. 8, 2000, 2000 CPD para.182 at 4. The late
proposal rule alleviates confusion, ensures equal treatment of
offerors, and prevents one offeror from obtaining a competitive
advantage as a result of being permitted to submit a proposal
later than the deadline set for all competitors. Inland Serv.
Corp., Inc., B‑252947.4, Nov. 4, 1993, 93-2 CPD para. 266 at 3;
Phelps-Stokes Fund, B-194347, May 21, 1979, 79-1 CPD para. 366
at 5-6.
Here, the record shows that the agency did not receive a
complete proposal in the correct format from Metters until after
the closing time specified in the solicitation, and therefore
its proposal was late.[3] Although Metters notes the agency had
received all but the subcontractors' proposals by the 3 p.m.
closing time, offerors were required to submit their complete
proposal to the agency by the closing time, and timely delivery
of part of a proposal does not constitute the timely submission
of the proposal. See Inland Serv. Corp., Inc., supra, at 3-4.
We do not agree that the protester's late submission of a
complete proposal was caused by some ambiguity in the RFP.[4] A
solicitation ambiguity exists where two or more reasonable
interpretations of the terms of the solicitation are possible.
Ashe Facility Servs., Inc., B-292218.3; B-292218.4, Mar. 31,
2004, 2004 CPD para. 80 at 10. Here, the RFP stated that:
If any of the work under the cost reimbursable CLIN will be
subcontracted for $650,000 or more, the subcontractor(s) shall
prepare and submit a cost breakdown and cost proposal. If the
subcontractor(s) considers the data to be company proprietary,
the cost proposal shall be submitted directly to the
Contracting Officer with a concurrent redacted copy and
notification to the offeror.
RFP, Proposal Submission Instructions, at 12. This provision
simply informed offerors that they would be required to submit
separate proposals for their major subcontractors under the cost
reimbursement CLIN, and did not address what form those
proposals must take. Rather, the proposals' format was addressed
elsewhere in the RFP's proposal preparation instructions, where
offerors were instructed that they must submit their proposals
on CDs, that paper copies were not permitted, and that
submission of proposals by email or facsimile was not
authorized.[5] See id. at 1.
In short, we find that the RFP required that subcontractors'
proposals, like the offerors' own proposals, be submitted on
CDs. Because Metters did not deliver its subcontractors'
proposals on CDs to the agency until after the specified closing
time, its proposal was late.
Metters also argues that its late proposal should have been
considered by the agency under Federal Acquisition Regulation
(FAR) sect. 15.208(b)(1)(ii), which provides an exception for
late proposals where there is evidence establishing that the
late proposal was received at the government installation
designated for receipt and was under the control of the agency
prior to the time set for receipt of proposals.Even assuming the
application of this provision to the task order competition
here, Metters failed to deliver a complete proposal in the
correct format into the agency's control prior to the closing
time for receipt of proposals. Thus, this exception to the late
proposal rule does not provide a basis for considering the
protester's proposal.
Metters also argues that, because the contract specialist
informed its subcontractor that it could submit its proposal
after the specified closing time, this effectively waived the
RFP's proposal submission time. The Army disputes that its
contract specialist informed Metters that the agency would
consider the subcontractor's proposal submitted after the
closing time for receipt of proposal. We need not resolve this
conflict because the contract specialist does not have the
authority to amend the solicitation or waive the deadline for
proposal submission. See Heath Constr., Inc., B-403417, Sept. 1,
2010, 2010 CPD para. 202. Moreover, such a waiver or amendment
of the closing time for receipt of proposal for only one offeror
would be wholly inconsistent with the purpose of the late
proposal rule, which is intended to assure fair and equal
treatment of offerors. (Metters,
Incorporated, B-403629, November 10, 2010) (pdf)
Agency Determination that Proposal was Not Timely Submitted
USAI first protests that its proposal was, in fact, delivered by
2 p.m. on July 9. In this regard, USAI offers no evidence to
support its assertion other than its messenger's representations
regarding the timing of events prior to proposal submission, and
the messenger's conclusion that "the proposal was submitted by 2
p.m." Statement of USAI Messenger at 2. Rather, USAI notes that
the [contracting officer's representative] COR relied on his
wrist watch in determining that the proposal was late and argues
that the evidence the agency considered, including the COR's
wrist watch, is inadequate to establish the time of receipt,
arguing, among other things, that the agency has failed to
present a "standard metered timestamp showing the exact
Coordinated Universal Time ('UTC') of actual receipt of the
bid." Comments at 1 (italics in original). USAI asserts that the
agency's determination was unreasonable because the agency has
not demonstrated that the COR's wrist watch reflected the "exact
[time], accurate or synchronized to UTC." Id. at 2. Thus, USAI
maintains that "the purported time shown on the watch is not
legally trustworthy, cannot establish the exact time of receipt,
and is not admissible to support the determination that the bid
was late." Id. We disagree.
This Office has repeatedly held that the declaration of the
agency official responsible for receiving bids or proposals is
determinative with regard to the time a bid or proposal is
received, absent a showing that the agency official's
declaration was unreasonable. See, e.g., Pat Mathis Constr. Co.,
Inc., B-248979, Oct. 9, 1992, 92-2 CPD para. 236 at 3; Robert R.
Nathan Assocs., Inc., B-230707, June 28, 1988, 88-1 CPD para.
615 at 2-3; Chattanooga Office Supply Co., B-228062, Sept. 3,
1987, 87-2 CPD para. 221 at 2.
Here, as discussed above, the agency COR specifically concluded
that USAI's proposal was not received until 2:05 p.m., advised
USAI's messenger of that determination, and provided the
messenger written notification reflecting the 2:05 p.m. receipt.
USAI's messenger did not dispute the accuracy of the COR's
determination at that time. Further, as noted above, the record
contains an email from another USAI representative to agency
personnel stating that "Messenger with Bid is lost" and
providing the messenger's name and cell phone number; the face
of that email states that it was sent at 1:58 p.m. AR, Tab 8,
Email from USAI representative to Agency, July 9, 2010, at 1.
Consistent with the time reflected on the USAI email, the COR's
cell phone records show that the first call he placed to the
messenger was made at 1:59 p.m. AR, Tab 12, Verizon Wireless
Record. Thereafter, the COR drove to the messenger's location,
spoke with him, directed the messenger to follow him (the COR)
back to the building 570 parking lot, and drove to that lot--at
which point the messenger handed the proposal to the COR.
Statement of USAI Messenger at 2-3. On this record, we find
nothing unreasonable in the agency's determination that the
proposal was received after the 2 p.m. deadline. USAI's protest
to the contrary is denied.
Alleged Government Delay and Misdirection
As noted above, USAI's messenger complains that he was delayed
in entering the AFB and asserts that he was provided directions
by the Wright-Patterson guard to 1755 Eleventh Street, building
570, which he followed, but that, upon turning onto Eleventh
Street, "the road dead ended into a building." Statement of USAI
Messenger at 2. Additionally, USAI complains that maps provided
by the agency in response to USAI's protest are "incorrect
and/or outdated." USAI Opposition to Dismissal at 2. USAI states
that currently available photographic maps of Wright-Patterson
AFB reflect a "missing section of Eleventh Street, which has
been . . . removed since the Air Force maps [provided in
response to the protest] were drawn," further noting that USAI's
photographic maps indicate that another building has been "built
over the missing section of Eleventh Street." Id. Accordingly,
USAI asserts that:
[T]he paramount cause of delay
here is the fact that the street address listed on the RFP
does not exist (or, incredibly, the address still exists, even
though the street no longer does), and that the Air Force maps
of Area B are wrong. . . . [T]he pertinent section of Eleventh
Street was removed years ago; a new building was built where
the road used to be, and the street now dead ends more than a
block before Building 570.[] It is impossible to find
[building 570] without already knowing where it is.
. . . . .
The time that [USAI's] messenger
arrived on base is not the determining factor here. [USAI's]
messenger could have arrived minutes--or hours--earlier, and
he still never would have found the building until Air Force
personnel either provided accurate directions or took him
there. Comments at 7.
It is an offeror's responsibility
to deliver its proposal to the proper place at the proper time;
proposals that are received after the exact time specified are
"late" and must generally be rejected. Federal Acquisition
Regulation (FAR) sect. 15.208(a); O.S. Sys., Inc., B-292827,
Nov. 17, 2003, 2003 CPD para. 211 at 3; Integrated Support Sys.
Inc., B-283137.2, Sept. 10, 1999, 99-2 CPD para. 51 at 2. The
late proposal rules include limited exceptions under which late
proposals may be considered. Specifically, this Office has held
that a late hand-carried offer may be considered for award if
the government's misdirection or improper action was the
paramount cause of the late delivery and consideration of the
offer would not compromise the integrity of the competitive
process. See, e.g., ALJUCAR, LLC, B-401148, June 8, 2009, 2009
CPD para. 124 at 3; Palomar Grading & Paving, Inc., B‑274885,
Jan. 10, 1997, 97-1 CPD para. 16 at 3; AABLE Tank Servs., Inc.,
B‑273010, Nov. 12, 1996, 96-2 CPD para. 180 at 3; Select Inc.,
B‑245820, Jan. 3, 1992, 92-1 CPD para. 22 at 4. Nonetheless,
even in cases where the late receipt may have been caused, in
part, by erroneous government action, a late proposal should not
be considered if the offeror significantly contributed to the
late receipt by not doing all it could or should have done to
fulfill its responsibility. See ALJUCAR, LLC, supra; O.S. Sys.,
Inc., supra; Palomar Grading & Paving, Inc., supra.
Here, USAI has not demonstrated
that the alleged government misdirection and/or delays
associated with its messenger's entry at gate 19B was the
paramount cause of the late delivery of USAI's proposal. To the
contrary, the record indicates that, even accepting USAI's
assertions that the gate guard provided inaccurate directions
which delayed the submission of USAI's proposal, USAI's own
actions significantly contributed to the late submission of its
proposal. As discussed above, it was USAI's decision to attempt
entry to Wright-Patterson AFB, a secure military facility, at
gate 19B--a gate designated for admission of personnel with
military credentials--rather than at gate 1B--the entrance at
which visitors without military credentials were directed to
arrive. In addition to its decision to attempt entry at a gate
not designated for use by non-military visitors, USAI's
messenger arrived at the entrance gate with less than an hour
remaining before proposals were due, did not obtain advance
approval for entry, and failed to previously ascertain the
location of, and directions to, the building designated for
proposal submission. On this record, we conclude that USAI's own
actions were significant contributing factors to the late
receipt of its proposal, and we reject USAI's assertion that any
delay in obtaining admission through gate 19B and/or the gate
guard's alleged misdirection was the paramount cause of the late
proposal submission. USAI's protest that the agency was required
to accept its proposal because of the government's actions is
denied.
Agency Control of the Proposal
Finally, USAI protests that USAI's proposal was "under Air Force
control" prior to the 2 p.m. closing time. Protest at 2. In this
regard, USAI refers to FAR sect. 52.215‑1(c)(3), which was
incorporated into the solicitation and addresses the late
submission of proposals. In pertinent part, FAR sect.
52.215-1(c)(3) states:
(ii)(A) Any proposal,
modification, or revision received at the Government office
designated in the solicitation after the exact time specified
for receipt of offers is "late" and will not be considered
unless it is received before award is made, the Contracting
Officer determines that accepting the late offer would not
unduly delay the acquisition; and—
. . . . .
(2) There is acceptable evidence
to establish that it was received at the Government
installation designated for receipt of offers and was under
the Government's control prior to the time set for receipt of
offers; or
(3) It is the only proposal received. FAR sect.
52.215-1(c)(3).
In determining whether a
late-submitted proposal was "under the Government's control"
prior to the time set for receipt of proposals, it is clear that
an offeror must, at a minimum, have relinquished physical
custody of the proposal. See, e.g., ALJUCAR, LLC, supra; Einhorn
Yaffe Prescott, B-259552, Mar. 20, 1995, 95-2 CPD para. 153; see
also Shirlington Limousine & Transp., Inc. v. United States, 77
Fed. Cl. 157 (2007). This requirement is an obvious necessity in
order to preclude any potential that an offeror could alter,
revise, or otherwise modify its proposal after other offerors'
competing proposals have been submitted.
Here, as discussed above, USAI's messenger did not relinquish
physical custody of its proposal until it handed the proposal to
the COR in the parking lot outside of building 570. As also
discussed above, the agency reasonably determined that such
transfer of physical custody did not occur until after the 2
p.m. proposal submission deadline. Accordingly, the prerequisite
for consideration of a late proposal contained in FAR sect.
52.215-1(c)(3)(ii)(A)(2)--that is, that the proposal "was under
the Government's control prior to the time set for receipt of
offers"--has not been met, and USAI's assertion that the agency
was required to consider USAI's proposal on the basis of that
FAR provision is without merit. (U.S.
Aerospace, Inc., B-403464, B-403464.2, October 6, 2010)
(pdf)
ATG does not dispute that its proposal was received by DRMS
after 10:00 a.m. local time on April 28. The protester
nevertheless contends that its proposal was not late and should
not have been rejected because ATG met the RFP requirements, as
the offeror understood them, by electronically transmitting its
proposal by 10:00 a.m. local time. In support of its position,
ATG points to the language of the RFP amendments that stated the
time to "submit"--which ATG interprets as "send"--proposals was
10:00 a.m. local time. We disagree.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time. FAR sect. 15.208(a) (offerors
are responsible for submitting proposals so as to reach the
designated government office by the specified time); PMTech,
Inc., B-291082, Oct. 11, 2002, 2002 CPD para. 172 at 3;
Integrated Support Sys. inc, B-283137.2, Sept. 10, 1999, 99-2
CPD para. 51 at 2. Similarly, we view it as an offeror's
responsibility, when transmitting its proposal electronically,
to ensure the proposal's timely delivery by transmitting the
proposal sufficiently in advance of the time set for receipt of
proposals to allow for timely receipt by the agency. PMTech,
Inc., supra, at 3-4. Proposals that are received in the
designated government office after the exact time specified are
"late," and generally may not be considered for award. While
this rule may seem harsh in some circumstances, it alleviates
confusion, ensures equal treatment of all offerors, and prevents
one offeror from obtaining a competitive advantage that may
accrue where an offeror is permitted to submit a proposal later
than the deadline set for all competitors. Inland Serv. Corp.,
Inc., B-252947.4, Nov. 4, 1993, 93-2 CPD para. 266 at 3.
Here, the RFP provisions established that offerors' proposals
were to be received by the designated agency contracting
official by April 28 at 10:00 a.m. local time. The email by
which DRMS distributed the RFP likewise informed prospective
offerors that the defining event was the agency's
receipt--rather than an offeror's submission--of proposals by
the due date and time. Moreover, to the extent ATG is now
alleging that the solicitation as amended was ambiguous about
whether the established time was for the submission of
proposals, as opposed to the receipt of proposals, ATG was
required to protest this apparent solicitation defect prior to
the next closing time for receipt of proposals following their
incorporation. 4 C.F.R. sect. 21.2(a)(1) (2010); see Sea Box,
Inc., B-401523, B-401523.2, Sept. 25, 2009, 2009 CPD para. 190
at 3-4 (conflict regarding solicitation closing date constituted
a patent ambiguity that was readily apparent prior to the time
set for receipt of submissions). Having failed to seek
clarification or file a protest before the closing time of the
RFP, ATG may not now assert that its understanding of the
solicitation requirements regarding the submission of proposals
is controlling. See id. at 4; Kellogg Brown & Root, Inc.,
B-291769, B-291769.2, Mar. 24, 2003, 2003 CPD para. 96 at 8-9.
ATG also argues that the timing of the actual delivery of its
proposal was beyond its control--that the 11-minute transmission
times were due to Internet delays and the large files that made
up each of its three emails. The protester notes that it is
operating in Kuwait City where it has had emails take hours, if
not almost all day, to arrive at their destinations. ATG
Response to DRMS Dismissal Request, June 11, 2010, at 3.
In our view, the record shows that the primary cause of ATG's
late delivery of its electronic proposal was that the offeror
delayed attempting to transmit its proposal until shortly before
the time set for the receipt of proposals; as noted above, two
parts of its proposal were sent 8 minutes and 3 minutes before
10:00 a.m., respectively, and the third was sent at 10:00 a.m.
An offeror's responsibility to deliver its proposal to the
proper place at the proper time includes allowing a reasonable
amount of time for the delivery of the proposal. PMTech, Inc.,
supra. Here, we conclude that ATG did not act reasonably in
waiting to transmit its electronic proposal until minutes before
the time set for receipt of proposals, especially when the
offeror was apparently aware of the potentially long email
delivery times common to its location. We think an offeror
accepts the risk of late receipt and rejection of a proposal
where it delays transmitting its proposal until the last few
minutes before the time set for receipt of proposals. Id.
In sum, since ATG's electronically transmitted proposal was not
received in full until 10:11 a.m. (after the time set for
receipt of proposals), it is a late proposal; since it was not
received at the initial point of entry by 5:00 p.m. the day
before proposals were due, the late proposal cannot be accepted.
See Sea Box, Inc., B-291056, supra. (Alalamiah
Technology Group, B-402707.2, June 29, 2010) (pdf)
Due to major winter storms in the Washington D.C. area on
February 5 and 6 and again on February 9 and 10, federal
agencies in the Washington D.C. area were closed from Monday,
February 8 through Thursday, February 11. On February 9, several
offerors, including CFS, attempted to hand deliver their
proposals to the Triangle Service Center in Washington, D.C.,
but could not because the agency was closed. On Friday, February
12, federal agencies in Washington D.C. reopened, but Federal
employees were allowed to arrive for work up to 2 hours later
than they would normally arrive, and employees who could not
report for work were allowed to take unscheduled leave. OPM
Federal Government Archived Operating Status in the Washington,
D.C. Area (Feb. 11, 2010).
On February 12, when GSA reopened, the contracting officer
determined that under FAR sect. 52.212-1(f)(4)--the provision
included in the RFP--the due date for receipt of proposals was
extended from February 9 at 2 p.m. to February 12, at 2 p.m.,
"because GSA was open for business and ready to accept bids well
before 2 p.m. on February 12, 2010." Contracting Officer's
Statement at 2. Multiple proposals were submitted by the
February 12 closing time. The protester submitted its proposal
on February 12, at 2:24 p.m, and it was rejected as late. This
protest followed.
CFS contends that the due date for proposals should have been
extended until 2 p.m. on Tuesday, February 16, because this was
the first day that normal government processes resumed.
Therefore, the protester argues that the contracting officer
determination to reject CFS's proposal as late was in error. The
protester essentially contends that "normal government
processes" could not be said to have resumed on a day when the
federal agency was operating under a 2-hour delayed
arrival/unscheduled leave policy.
We agree with the agency that normal Government processes
resumed on February 12. The agency states it "went on with the
pursuit of its normal business following a morning that
permitted Federal employees some additional time to safely
commute to work" and was able to accept proposals at 2 p.m.
Agency Report at 6. Contrary to the protester's allegations, the
fact that Federal employees were allowed to delay arrival or
take unscheduled leave does not mean that the Government had not
resumed its normal processes. In fact, procedures of the Office
of Personnel Management recognize that situations that allow for
delayed arrival or unscheduled leave are different from the
situations where the "Federal agencies are closed." OPM
Washington, D.C. Area Dismissal or Closure Procedures (Nov.
2009) at 11.
We therefore find that the agency reasonably rejected CFS's
proposal as late because it was received after 2 p.m. on "the
first work day on which normal Government processes resume[d]."
(CFS-INC, JV, B-401809.2, March
31, 2010) (pdf)
The RFP, as amended, required offerors to submit proposals to
the CBP's Arlington, Virginia office by 3 p.m. (eastern time),
Friday, February 12, 2010. Hunter mailed its proposal from
Tucson, Arizona on February 10 via the United States Postal
Service's "Next Day Noon Express." Due to severe inclement
weather in the Washington D.C. area, airplane flights were
cancelled and federal agencies were closed February 8-11. On
Friday, February 12, federal agencies reopened, but were
operating on a "delayed arrival/unscheduled leave" policy.
Hunter's proposal was delivered to the CBP on the morning of
Tuesday, February 16--the next business day following February
12. The agency rejected Hunter's proposal as late, and this
protest followed.
The protester argues that, given the inclement weather and
resulting closures, the CBP should have accepted its proposal
under Federal Acquisition Regulation (FAR) sect. 15.208(d). This
section provides that
[i]f an emergency or unanticipated event interrupts normal
Government processes so that proposals cannot be received at the
Government office designated for receipt of proposals by the
exact time specified in the solicitation, and urgent Government
requirements preclude amendment of the solicitation closing
date, the time specified for receipt of proposals will be deemed
to be extended to the same time of day specified in the
solicitation on the first work day on which normal Government
processes resume.
Hunter argues that, consistent with this FAR provision, its
proposal was timely submitted because CBP received the proposal
prior to 3 p.m. on the first work day that normal government
processes resumed.
We agree with the agency that FAR sect. 15.208(d) does not apply
to the circumstances here. The CBP concluded that normal
government operations resumed on February 12 because the
government was open that entire day. Since the government was
open on February 12, the earlier closures that Hunter cites did
not prevent the CBP from receiving proposals "by the exact time
specified in the solicitation." FAR sect. 15.208(d). Indeed, the
record shows that the CBP had an individual in place to receive
proposals beginning at 8 a.m. on February 12, and CBP received a
number of proposals prior to the 3 p.m. closing time. Motion to
Dismiss at 2. While Hunter points to the "delayed
arrival/unscheduled leave" policy to show that government
processes were interrupted on February 12, the relaxed arrival
and leave policy did not mean the government had not resumed
normal operations, and, in fact, had no bearing on the agency's
ability to receive proposals by the specified closing time.
Because Hunter did not timely deliver its proposal to the CBP,
the proposal was late and properly rejected. See FAR sect.
52.215-1(c)(3); PMTech, Inc., B‑291082, Oct. 11, 2002, 2002 CPD
para. 172 at 3 ("It is an offeror's responsibility to deliver
its proposal to the proper place at the proper time.") (Hunter
Contracting Company, B-402575, March 31, 2010) (pdf)
Latvian Connection asserts that
contrary to the agency's records, it timely submitted its
proposal by e-mail on November 12 at 1:19 a.m. Protest at 4. In
support of this assertion, the protester states that its "'sent'
e-mail folder confirms the transmission of [Latvian
Connection's] proposal," and that it "continued to utilize
(without incident) the same e-mail address in its post-proposal
submission communications" with the agency. Id. The protest also
includes the declaration of Latvian Connection's Chief Executive
Officer (CEO), which states that he transmitted the proposal as
an attachment to an e-mail "at '1:19 [a.m.]' on 'Thursday,
November 12, 2009,'" and that his e-mail records do not "in any
way suggest[] that the e-mail and attachments were rejected as
undeliverable or otherwise not sent." Protest, exh. 6,
Declaration, at 1. The protester asserts that the agency's
actions in awarding the contract to any other offeror were
unreasonable because, in the protester's view, "[t]he evidence
of [Latvian Connection's] timely submission of its lower-priced
proposal to the address specified in the RFP is clear,
cumulative and undisputed." Protest at 6.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time. Federal Acquisition Regulation
sect. 15.208; Lakeshore Eng'g Servs., B‑401434, July 24, 2009,
2009 CPD para. 155 at 4. Although the protester has submitted
certain evidence, including the declaration of its CEO, in
support of its assertion that it timely sent its proposal to the
agency, there is no evidence establishing that the proposal was
actually received by the agency. In this regard, the agency
states that in response to Latvian Connection's initial
inquiries and protest, searches of the agency's e-mails were
performed on five different occasions by four different
individuals, including the contracting officer, the cognizant
senior systems administrator, and the cognizant information
management officer, and that these searches did not result in
any finding of the protester's proposal. Contracting Officer's
Statement at 2.
On the basis of the record here, we conclude that the protester
has failed to satisfy its burden of showing that it timely
delivered its proposal to the agency. Lakeshore Eng'g Servs.,
supra; International Garment Processors, B-299674 et al., July
17, 2007, 2007 CPD para. 130 at 7. Accordingly, we have no basis
on which to object to the agency's actions. (Latvian
Connection Trading and Construction, B-402410, LLC, February
25, 2010) (pdf)
The protester contends that it timely submitted part 10 of its
cost/price proposal via e-mail and that its delivery receipt
proves that the agency received the e-mail prior to the
submission due date. In support of its argument, Lakeshore's
network administrator submitted a statement that, to the best of
his knowledge, the protester's e-mail server was fully
functional and operational on May 8, and was capable of sending
and receiving e-mail. Protester's Comments, exh. E. The network
administrator also confirms that it was Lakeshore's server that
generated the delivery status notification, which the protester
refers to as a "delivery receipt." Id. The network administrator
states that to the best of his knowledge, Lakeshore's May 8
e-mail was delivered to the agency. Id. Therefore, the protester
believes that the agency improperly excluded its proposal from
the competitive range.
The Navy argues that the protester has shown only that it timely
sent part 10 of its proposal, not that the proposal was timely
delivered. The Navy contends that it never received the
protester's May 8 e-mail. AR, Tab 3, CO's Statement at 3. The
agency states that its e-mail system was properly functioning on
May 8, and that other incoming e-mails were received in the
e-mail box immediately prior to and shortly after the time that
protester sent its proposal. AR, Tab 4 at 1; Tab 5 at 1.
Therefore, the Navy concludes that the protester failed to
timely deliver the proposal in accordance with the terms of the
solicitation and FAR sect. 52.215-1.
The Navy's Information Technology (IT) Specialist has submitted
a statement explaining that the delivery receipt submitted by
the protester is only a relay message, as opposed to a delivery
message. According to the IT Specialist, relay messages indicate
that an e-mail message was relayed or sent from the sending
server (i.e., Lakeshore's server). AR, Tab 7. Thus, the IT
Specialist states that the message generated by Lakeshore's
server merely confirmed that the e‑mail had been sent or relayed
by Landmark's server, but it does not indicate whether the
e-mail was received by the NMCI server. Id. Accordingly, the
Navy argues that Lakeshore has failed to show timely delivery of
part 10 of its cost/price proposal.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time. FAR sect. 52.215-1(c)(3);
PMTech, Inc., B-291082, Oct. 11, 2002, 2002 CPD para. 172 at 3.
While the protester has shown that it timely sent part 10 of the
proposal, there is no evidence that it was received by the
agency prior to the due date for proposal submissions. As
explained above, protester's "delivery receipt," which was sent
by the protester's own e-mail server, confirms only that the
message was successfully relayed from Lakeshore's system. It
does not confirm that the proposal arrived at the agency's
e-mail system.
Because there is no evidence that part 10 of the protester's
cost/price proposal was successfully delivered to the agency's
e-mail box prior to the due date for receipt of proposals, the
protester has failed to satisfy its burden of showing that it
timely delivered its proposal to the agency. Accordingly, we
conclude that the agency reasonably excluded the protester's
proposal from the competitive range. (Lakeshore
Engineering Services, B-401434, July 24, 2009) (pdf)
TSG argues that the agency did not have any reasonable grounds
to eliminate TSG from the competition prior to evaluation of
offers. TSG asserts that the agency was required to consider its
late modification pursuant to the RFP provision stating that "a
late modification of an otherwise successful proposal that makes
its terms more favorable to the government will be considered at
any time it is received and may be accepted." RFP at L-2. TSG
also contends that at the time it was eliminated from the
competition, the agency had not selected an awardee and that TSG,
like all other offerors at that point in the procurement, was
"in line for award" when it submitted its modification to the
agency.
TSG's argument is without merit. Under negotiated procurements,
the FAR provides generally that a proposal received after the
time set for receipt shall not be considered. FAR sect.
15.208(b)(1). Our Office has long held that the late proposal
rule alleviates confusion, ensures equal treatment of offerors
and prevents one offeror from obtaining a competitive advantage
as result of being permitted to submit a proposal later than the
deadline set for all competitors. Tishman Constr. Corp.,
B-292097, May 29, 2003, 2003 CPD para. 94 at 3. The FAR provides
a limited exception for receipt of late proposals that are
submitted by the "otherwise successful offeror" and which
provide more favorable terms. This exception to the general
"late is late" rule is intended to allow the government to
receive the benefit of a more advantageous proposal from the
offeror who has been selected for award, without offending the
general rule that offerors must be treated equally.
As an initial matter, we disagree with TSG's assertion that the
limited exception for receipt of late proposals applies here. An
"otherwise successful proposal" is one that would result in the
award of the contract to the offeror regardless of the late
modification; generally, this means that the government may
accept a favorable late modification only from the offeror
already in line for award. Seven Seas Eng'g & Land Surveying,
B-294424.2, Nov. 19, 2004, 2004 CPD para. 236 at 4. This
exception is not available for every proposal submitted.
Furthermore, an offeror cannot make itself the "otherwise
successful offeror" by submitting a late proposal modification;
instead the offeror must already be the offeror in line for
award prior to the time the late proposal modification is
submitted. Phyllis M. Chestang, B-298394.3, Nov. 20, 2006, 2006
CPD para. 176 at 5 n.3. In this regard, an offeror cannot avail
itself of the late proposal submission provision where the
agency has not already identified an "otherwise successful
offeror." Global Analytic Info. Tech. Servs., Inc., B-298840.2,
Feb. 6, 2007, 2007 CPD para. 57 5-6.
Here, the agency had only begun
its evaluation of proposals when it was advised by TSG that its
project manager was no longer available to perform the contract,
or to attend the scheduled oral presentation. Without this
individual TSG's proposal was deficient, and TSG can not be
viewed as, the "otherwise successful offeror." On this record,
we conclude that the agency's determination not to accept TSG's
late proposal modification was entirely consistent with the RFP
and reasonable under these circumstances.
TSG also argues that the agency's cancellation of its oral
presentation and elimination of its proposal from the
competition were unreasonable. Where a protester challenges an
agency's evaluation of a proposal's technical acceptability, our
review is limited to considering whether the evaluation is
reasonable and consistent with the terms of the RFP and
applicable procurement statutes and regulations. National Shower
Express, Inc.; Rickaby Fire Support, B-293970, B‑292970.2, Jul.
15, 2004, 2004 CPD para. 140 at 4-5.
TSG's argument that the agency's decision to reject its proposal
was unreasonable is primarily based on its contention that the
agency improperly refused to accept its late modification. TSG
does not argue that the agency should have evaluated its
proposal as originally submitted. In any event, the record shows
that once TSG advised the contracting officer that the
individual it proposed as its project manager was no longer
available, TSG's proposal did not meet the RFP requirement that
the proposal identify at a minimum, the key individual
responsible for the overall contract, and a letter of commitment
for that key person. Under these circumstances, we cannot say
that the rejection of TSG's proposal was unreasonable or
violated the terms of the RFP.
As a final matter, we recognize that the protester and the
agency disagree about whether TSG was attempting to identify for
the first time a new key position, director of operations, when
TSG advised the agency that it needed to substitute a new
project manager. Compare Initial Protest at 5 n.1 (TSG says it
was not identifying this individual as one of its key personnel)
with Agency Memorandum of Law at 7 n.8 (the agency concluded
that by submitting a new resume, a letter of commitment and a
request that its director of operations attend the oral
presentation, which was only to be attended by key personnel,
TSG was identifying a new key position). While TSG may not have
intended to identify its new director of operations as a key
employee, its actions, at a minimum, created an ambiguity about
the extent to which TSG was seeking to modify its proposal weeks
after the proposal submission date. We see nothing unreasonable
about the agency’s decision not to allow either of these
modifications. (The Sandi Group,
Inc., B-401218, June 5, 2009) (pdf)
The protester states that two principals of ALJUCAR arrived at
the security checkpoint at 1:52 p.m. to deliver the firm's
proposal to building 421 before the scheduled 2 p.m. closing;
the protester estimates that it is a 3-5 minute drive to the
building from the checkpoint. The protester states there was a
delay at the checkpoint, however, because a security guard there
determined that one of the protester's representatives did not
have adequate identification. According to the protester, the
guard would not allow the individual to remain at the security
checkpoint or walk unescorted to the base exit at Gate 4;
rather, the individual was to be driven back to the nearby exit.
At that point, the protester states, one of its representatives
called the contracting officer from the security checkpoint to
notify him of the matter, and the contracting officer informed
him that the contracting specialist would come to the security
checkpoint to receive the firm's proposal. ALJUCAR does not
state what time it was when its representative gave its proposal
to the contracting specialist at the security checkpoint. The
contracting specialist, on the other hand, reports that it was
after 2 p.m. when she received the contracting officer's request
to leave building 421 to drive to the security checkpoint to
receive the proposal. After the firm's proposal was loaded in
the contracting specialist's car, she apparently spent several
minutes speaking to one of the protester's representatives, then
she returned to building 421 where the proposal was logged in as
delivered at 2:29 p.m., 29 minutes after the scheduled closing
time.
By letter of January 5, 2009, the agency informed ALJUCAR that,
since the firm's proposal had not been under government control
prior to the time set for the receipt of proposals, it was
rejected as late. On January 7, ALJUCAR filed an agency-level
protest asserting that the security guard's improper decision
not to allow one of ALJUCAR's representative to either walk to
the base exit unescorted or remain at the security checkpoint
while the other representative delivered the proposal made it
impossible for the firm to deliver its proposal on time. The
agency denied the protest on February 23, finding that the
protester's allegation of improper government action was not
adequately supported and concluding that, since the contracting
specialist reported she did not receive the proposal from the
protester at the security checkpoint until after 2 p.m., the
proposal (logged in as delivered at 2:29 p.m.) was late. This
protest followed.
It is an offeror's responsibility to deliver its proposal to the
proper place at the proper time, and late delivery generally
requires rejection of the proposal. Integrated Support Sys. inc,
B-283137.2, Sept. 10, 1999, 99-2 CPD para. 51 at 2. However, a
hand-carried proposal that arrives late may be considered if
improper government action was the paramount cause for the late
submission, and where consideration of the proposal would not
compromise the integrity of the competitive process; improper
government action in this context is affirmative action that
makes it impossible for the offeror to deliver the proposal on
time. Id. Nonetheless, even in cases where the late receipt may
have been caused, in part, by erroneous government action, a
late proposal should not be considered if the offeror
significantly contributed to the late receipt by not acting
reasonably in fulfilling its responsibility to deliver a
hand-carried proposal to the proper place by the proper time.
See O.S. Sys., Inc., B‑292827, Nov. 17, 2003, 2003 CPD para. 211
at 3.
Our review of the record here shows no evidence that the ALJUCAR
proposal was in fact received by the agency prior to the 2 p.m.
closing time. The contracting specialist reports arriving after
2 p.m. to retrieve the proposal. While the protester states it
was on the telephone with the contracting officer minutes before
closing, it has not shown that the proposal was under government
control prior to 2 p.m. Rather, the protester argues that the
sole cause of the proposal's untimely receipt was the delay
caused by the guard at the security checkpoint. ALJUCAR contends
that the guard's failure to allow the firm's representative who
lacked adequate identification to either wait at the checkpoint
or leave the checkpoint, unescorted, to exit the base was
improper government action. ALJUCAR disagrees with the agency's
position that the guard's action was appropriate under the
agency's general security policies regarding access and movement
controls at a secure facility such as the Space Center. As the
agency points out, however, even if the guard acted in error, we
cannot conclude that his action was the sole or paramount cause
of the proposal being received late, since the representatives
of the protester--which had the primary responsibility for
delivering its proposal on time--significantly contributed to
the lateness of the proposal.
Despite numerous RFP instructions emphasizing the offeror's
responsibility for timely submission, including that the offeror
should anticipate it taking up to an hour to complete the
required security screening for proposal submissions, the
protester's representatives arrived on the base only 8 minutes
before closing. ALJUCAR simply did not allow sufficient time to
fulfill its responsibility to deliver its proposal by the proper
time. See Wyatt and Assocs., B‑243349, July 1, 1991, 91-2 CPD
para. 5 at 2-3. Given the RFP warnings and the secure nature of
the NASA installation, the protester should have reasonably
anticipated delay in gaining access to the facility. See, e.g.,
Einhorn Yaffee Prescott, B‑259552, Mar. 20, 1995, 95-1 CPD para.
153 at 4. In short, ALJUCAR assumed a risk in allowing so little
time for delivery of its proposal here. Id. In these
circumstances, where the protester did not act reasonably to
fulfill its obligation to deliver its proposal on time, we find
no basis to question the agency's decision to reject the
proposal as late. (ALJUCAR, LLC,
B-401148, June 8, 2009) (pdf)
Rehal objects in its protest to our Office that its proposal was
"mislaid following delivery and consequently was not evaluated,"
arguing that it was "clearly stated under Amendment 0001 to the
Solicitation that all required documentation required to be
submitted" could be delivered to Camp Arifjan. In this regard,
Rehal complains that the proposal delivery instructions were
very complicated and misleading.
We do not agree with Rehal that amendment 1 changed the RFP
delivery instructions that required offerors to submit their
technical and price proposals to two different locations.
Rather, reading the relevant question and answer included in
amendment 1 within the context of the RFQ as a whole, the
solicitation informed offerors that they were still required to
submit one copy of their technical proposal and all of the
copies of their price proposals to the Army Sustainment Command
at Rock Island.[2] In this regard, the RFP, as amended,
continued to inform offerors that receipt of proposals by the
Army Sustainment Command at Rock Island, the only location that
was designated to receive both the technical and cost proposals,
would determine whether offerors' proposals were timely
submitted.
Here, it is undisputed that the protester did not deliver its
technical and price proposals to the Army Sustainment Command at
Rock Island, as directed by the RFP, for the purpose of
establishing the timeliness of the proposal. It is an offeror's
responsibility to deliver its proposal to the proper place by
the proper time. Shirlington Limousine & Transp., Inc.,
B-299241.2, Mar. 30, 2007, 2007 CPD para. 68 at 2. Because Rehal
did not submit its proposal in accordance with the solicitation
instructions, we find reasonable the Army's rejection of Rehal's
proposal.
With respect to Rehal's complaint that the RFP's proposal
instructions were complex and that it was misled by the
solicitation's instructions, even were we to accept Rehal's
arguments, these arguments, at best, would establish a patent
ambiguity, i.e., one that is obvious from the face of the
solicitation. Offerors have an affirmative obligation to seek
clarification prior to the first due date for submission of
proposals following introduction of an ambiguity into a
solicitation. See Bid Protest Regulations, 4 C.F.R. 21.2(a)(1)
(2008). Protests of a patent solicitation ambiguity that are not
filed before the time set for receipt of initial proposals are
untimely and will not be considered by our Office. See Kellogg
Brown & Root, Inc., B-291769, B‑291769.2, Mar. 24, 2003, 2003
CPD para. 96; Bank of Am. , B-287608, B-287608.2, July 26, 2001,
2001 CPD para. 137 at 10. The requirement that protests of
patent ambiguities be filed prior to time set for receipt of
initial proposals is intended to facilitate clarification of
legitimate questions prior to preparation of submissions. Since
Rehal sought no such clarification of this matter prior to
responding to the solicitation, its complaints about being
misled by the solicitation instructions are untimely. (Rehal
International Transportation, B-401090, April 7, 2009) (pdf)
With respect to the first issue, we find that HUD correctly
concluded that Urban Title’s FPR was late. As explained above,
both of Urban Title’s attempts to submit its FPR were received
after the time specified by the agency for receipt of FPRs.
Although Urban Title objects that the agency has provided no
explanation of the anomaly that resulted in the apparent delay
of the protester’s first e-mail for 5 weeks, the protester does
not dispute that it occurred, and the contracting specialist has
provided the facts in a sworn declaration to our Office.
HUD argues that the only exception for a late proposal revision
received by electronic means is found in FAR sect.
52.215-1(c)(3)(ii)(A), which could only apply if Urban Title’s
electronic submission had reached the “initial point of entry to
the Government infrastructure” by 5 p.m. a day before the due
date. HUD points out that Urban Title confirms that its FPR
submissions were sent on the due date (not a day early), and
thus the exception is unavailable.
Urban Title argues HUD elected to limit offerors to submitting
FPRs only by e-mail, and that by doing so, HUD was obliged to
ensure that its e-mail system was reasonably reliable. In Urban
Title’s view, the facts here suggest that HUD failed in meeting
that duty.
In our view, the protester’s argument is foreclosed by the
specific treatment of the issue in FAR sect. 52.215-1(c)(3)(ii)(A).
See Sea Box, Inc., B-291056, Oct. 31, 2002, 2002 CPD para. 181
at 3 (other exception necessarily applies only to proposals not
delivered by electronic means). Moreover, any objection to HUD’s
decision to specify that FPRs be submitted by e-mail is an
allegation of a patent solicitation defect,[3] which is
therefore untimely when raised for the first time now, after
award.[4] 4 C.F.R. sect. 21.2(a)(1) (2008). Accordingly, Urban
Title’s protest to the treatment of its FPR as late is denied.
(Urban Title, LLC, B-311437.3,
January 7, 2009) (pdf)
Sector One asserts that it sent its proposal by express mail to
the address in the RFP for hand-delivery or courier. The
protester has provided the USPS Express Mail label from the
package indicating that it had the correct hand-carried address
provided by the RFP and that USPS made two attempts to deliver
the package, one of which was after the date and time for
submission of proposals. The protester argues that express mail
is delivered by courier and that someone at the agency marked
“refused” in the employee signature box.
It is the responsibility of each firm to deliver its proposal to
the proper place at the proper time, and late delivery generally
requires rejection of the submission. Sencland CDC Enters.,
B-252796, B-252797, July 19, 1993, 93-2 CPD para. 36 at 3. Where
late receipt results from the failure of a vendor to reasonably
fulfill its responsibility for ensuring timely delivery to the
specified location, the late offer may not be considered. Aztec
Dev. Co., B-256905, July 28, 1994, 94-2 CPD para. 48 at 3. An
offer that arrives late may only be considered if it is shown
that the paramount reason for late receipt was improper
government action, and where consideration of the proposal would
not compromise the integrity of the competitive procurement
process. Caddell Constr. Co., Inc., B-280405, Aug. 24, 1998,
98-2 CPD para. 50 at 6. Improper government action in this
context is affirmative action that makes it impossible for the
offeror to deliver the proposal on time. Id.
As an initial matter, the agency denies receiving or rejecting
the Sector One proposal submission that was the subject of the
alleged delivery attempt by the USPS carrier. As explained
above, since USPS does not deliver mail to the building where
the Office of Acquisition is located, the RFP contained a P.O.
box for mailed proposals, and allowed for hand-carried proposals
provided delivery was coordinated with the contracting officer.
By its own admission, the protester did not follow the
instructions in the RFP for submission of its proposal in that
it made no arrangements with the contracting officer for
hand-carried delivery.
In our view, the evidence submitted by the protester does not
establish that the agency actually received the protester’s
submission or that there was an attempt to deliver the proposals
to the agency before the closing time established in the
solicitation. As explained above, the record here, at best, only
demonstrates that the USPS carrier attempted to deliver the
protester’s submission to some DOS location and does not
specifically demonstrate whether anyone at DOS refused to accept
delivery. The record shows that the paramount reason for the
nonreceipt of the protester’s submission is the protester’s
failure to follow the solicitation instructions to either mail
its proposal to the designated P.O. box number or make the
proper arrangements for hand-carried delivery. In short, there
is nothing in the record showing that any affirmative government
action deprived the protester of the ability to make a proper
delivery of its proposal. (Sector
One Security Solution, B-400728, December 10, 2008) (pdf)
Late Quote: The RFQ contemplated the award of an
order to a General Services Administration Federal Supply
Schedule vendor in accordance with Federal Acquisition
Regulation (FAR) Subpart 8.4. The RFQ required that vendors
submit their quotations electronically to the contract
specialist and the contracting officer by 12 p.m. on Monday,
July 21, 2008; email addresses were provided for both agency
recipients. Vendors were cautioned that they were responsible
for ensuring that quotations were received by the agency at the
specified date and time, and that “[q]uotes received after the
exact time specified for receipt of quotes shall not be
considered.” RFQ sect. L.2.
Turner states that on Sunday, July 20 at 10:12 p.m. (the evening
before the due date for receipt of quotations), its vice
president (VP) transmitted the firm’s quotation, consisting of
an e-mail with five attached files in Adobe portable document
format (pdf), to the contract specialist and contracting officer
at the email addresses specified in the RFQ. Turner also
transmitted copies of this email to two other, non‑agency
recipients, one of whom automatically forwarded his email to a
government email account that is sponsored by the Office of
Management and Budget (OMB) for his work on another project.
This addressee received the email and all its attachments at his
OMB mailbox a few minutes after Turner’s transmission. Protest
at 7.
Turner states that, after sending its quotation to these four
recipients, the firm sent a second email to the contract
specialist and contracting officer, informing them that Turner
had submitted its quotation. Turner did not receive any messages
from its email system, informing the firm of errors or problems
with the delivery of these emails. After transmitting these
emails, Turner’s VP called the contract specialist and left a
telephone voicemail message requesting confirmation that the
agency had received Turner’s quotation. Turner did not receive
any response to this voicemail request.
On Monday, July 21, at 10:05 a.m., Turner again called the
contract specialist and left a second voicemail message seeking
confirmation of the receipt of its quotation; one minute later,
Turner left a similar message with the contracting officer. The
contract specialist states that she arrived in her office at
8:10 a.m. but was in another building from 9:30 a.m. until 11:35
a.m. She also states that she received an “unintelligible
[voicemail] message” at 10:16 p.m., on Sunday night, and
Turner’s 10:05 a.m. Monday voicemail message. She states that
after hearing the latter message at 11:35 a.m. on Monday, she
searched her email for Turner’s quotation, but did not find it.
She did, however, see Turner’s second email (which had no
attachments) stating that Turner had submitted its proposal. The
contract specialist states that she was still trying to locate
Turner’s quotation at 12:25 p.m., after the closing time for
receipt of quotations, when Turner’s VP called her, and she
informed him that the agency had not received the firm’s
quotation. Agency Report, Declaration of Contract Specialist, at
2.
Turner immediately re-sent the email with the five attached pdf
files, comprising its quotation, which the agency again did not
receive. The contract specialist suggested that Turner separate
the attachments and send the quotation in multiple emails.
Turner did so, and four of the five attachments were
successfully delivered to the contract specialist’s email
account. Turner eventually converted the remaining pdf file to a
Microsoft Word document, which Turner successfully transmitted
to the contract specialist. Id.
Two other firms successfully transmitted quotations to the
agency by the noon deadline for receipt of quotations.
The contract specialist contacted the agency’s Office of the
Chief Information Officer and requested assistance in
investigating the situation, asking whether there was any way to
determine whether the agency’s server had rejected Turner’s
email with its attachments. After being told that a search of
the office’s records had detected no problems in the agency’s
server and that there was no record of having received the
email, even at the outermost point of entry in the agency’s
system, the contracting officer rejected Turner’s quotation as
late. This protest followed.
Turner does not dispute that its quotation was received late;
rather, the crux of Turner’s protest is that some unspecified
error in the agency’s internet system prevented the timely
delivery of Turner’s quotation. Turner maintains that, because
its email to the agency was simultaneously and successfully
transmitted to the two other non-agency recipients, the
paramount cause of its quotation not reaching the designated
agency email accounts must be something in the agency’s email
system or server, such as, Turner speculates, an arbitrary
blocking of pdf files or other arbitrary fault in the agency’s
system.
DOE does not dispute that Turner attempted to send its quotation
by email before the noon deadline, or that Turner took
reasonable steps to confirm its delivery. Rather, the agency
argues that there is no evidence that Turner’s email ever
reached its server and that, since other offerors successfully
submitted pdf files, the problem most likely was caused by some
technical “glitch” in one of Turner’s pdf files. In this regard,
the agency notes that when, after the closing date for receipt
of quotations, Turner separately transmitted its attachments,
all but one of the attachments was successfully transmitted.
That one attachment had to be converted to a different format to
be successfully delivered to the agency. Legal Memorandum at 4.
FAR provisions in Parts 14 and 15, governing the late
delivery of bids and proposals, generally do not apply to the
late delivery of a quotation. However, where as here the RFQ
contains a late submission provision that quotations must be
received by a stated deadline to be considered, quotations
cannot be considered if received after the deadline. See Data
Integrators, Inc., B-310928, Jan. 31, 2008, 2008 CPD para. 27 at
2. (emphasis added by Wifcon.com)
Here, there is no question that Turner’s quotation was not
received by the agency by the time required for submission of
quotations. Although Turner contends that something in DOE’s
internet system prevented the timely receipt of Turner’s
quotation, there is no evidence in the record to support this
contention. Rather, DOE states that its investigation found no
problems with the agency’s servers that would prevent the timely
receipt of quotations, and that the agency timely received other
emailed quotations which included pdf files, see Contracting
Officer’s Statement at 3, which lends support to this view.
Moreover, Turner’s late delivery of its quotation could not be
completed until after the protester had changed the format of
one of its email attachments, which also lends support to the
agency’s view that Turner’s inability to timely deliver its
quotation to the agency was more likely the result of a
corrupted file. We recognize that Turner disputes that its
attachments were corrupted and that it continues to contend that
it timely transmitted its quotation to DOE; this, however, does
not demonstrate that DOE timely received the firm’s quotation or
was responsible for Turner’s inability to timely deliver its
quotation to the agency. In short, given that there is no
evidence in the record to show actual timely receipt of the
Turner’s quotation, we have no basis to find unreasonable the
agency’s rejection of the quotation as late. See
International Garment Processors, B-299674; B-299743;
B‑299746, July 17, 2007, 2007 CPD para. 130 at 7. (Turner
Consulting Group, Inc., B-400421, October 29, 2008) (pdf)
On August 5, 2008, the Navy posted the RFQ on the FedBizOpps
website. The RFQ specified a closing date and time of 2 p.m.,
August 21. The RFQ contained instructions for submission of
quotations, including the notice that “[e]lectronic bids may be
submitted to the following email address: roicc_chpt_ktr_bids@navy.mil
by the time stated on the [standard form] 18.” RFQ at 7. The
electronic version of the RFQ included a blue, underlined
hyperlink for the email address. With the cursor placed over the
hyperlink for the email address, it appears as
roicc_chpt_ktr_bids@navy.mil, clearly showing the underscoring
of the otherwise blank spaces between characters. The agency
received one quotation, from Mid-Atlantic Crane, which received
the award on September 3.
On September 5, PHC contacted the agency to ask about this
procurement and was told that the agency had not received a
quotation from PHC and that award had been made to another
vendor. PHC maintained that it had sent its quotation by email
on August 21, at 11:52 a.m., to the following address:
roiccchptktrbids@navy.mil, eliminating the spaces created by the
underscoring in the email address as set out in the RFQ. That
same day, PHC submitted its quotation directly to the
contracting officer, as well as information to show the August
21 submission of its quotation. Upon review of the information
provided by PHC, the contracting officer determined that PHC’s
quotation had not been received because it was sent to the wrong
email address. Because the agency first received PHC’s quotation
on September 5, after award already had been made, the agency
did not consider PHC’s quotation further.
The protester does not dispute that its quotation was received
late and after award. Rather, the protester argues that the
circumstances surrounding the late receipt of its quotation
compel the agency to consider it. In this regard, the protester
argues that the error in the email address it used was the
result of the unclear manner in which the address was set out in
the RFQ. Moreover, the protester asserts that the email address
it used must exist because the protester received a notice of
receipt of its email, similar to notices of receipt that it has
received in response to other email submissions that were known
to have been properly received.
We have long held that the requirement to obtain competition to
the maximum extent practicable means that language requesting
quotations by a certain date cannot be construed as establishing
a firm closing date for the receipt of quotations absent a
provision--which was not present here--expressly providing that
quotations must be received by that date to be considered.
Instruments & Controls Serv. Co., B-222122, June 30, 1986, 86-2
CPD para. 16 at 3. Instead, agencies should consider any
quotations received prior to source selection if no substantial
activity has transpired in evaluating quotations and other
vendors would not be prejudiced. Id. See also KPMG Consulting
LLP, B-290716, B-290716.2, Sept. 23, 2002, 2002 CPD para. 196 at
11. Here, where the agency had already made an award prior to
its receipt of the protester’s quotation, we see no reason to
object to the agency’s refusal to consider that quotation. John
Blood, B-274624, Dec. 19, 1996, 96-2 CPD para. 233 at 2.
The protester’s argument that the email address used by the
agency for receipt of quotations was “complicated and
error-prone,” Comments at 2, and that if the address had been
clear the protester would not have made the entry error, does
not compel a different result. As noted above, the email
address, with the underscoring, was clearly visible in the
electronic version of the RFQ once the cursor was placed over
the address. To the extent the underscoring was not apparent to
PHC, PHC nevertheless failed to act reasonably in the electronic
submission of its quotation, which directly resulted in the
agency not timely receiving its quotation. Without first raising
the issue with the agency, PHC simply assumed that what it
perceived as blank spaces between the characters in the agency’s
email address were unintended and immaterial--as noted above,
the email address used by PHC for the submission of its
quotation simply eliminated the underscored spaces. It was
unreasonable for PHC to make this assumption and thereby modify
the email address designated in the RFQ for the submission of
quotations. Given PHC’s own actions, we have no basis to
conclude that the agency acted unreasonably by rejecting PHC’s
late quotation. (Piedmont Hoist
& Crane, B-400563, October 8, 2008) (pdf)
The protester is
one of three offerors whose proposals were included in the most
recent competitive range created by the agency. At issue is the
mode of transmission permitted by the RFP. As a general matter,
offerors may use any transmission method authorized by the
solicitation. Federal Acquisition Regulation (FAR) sect.
15.208(a). The solicitation nowhere authorized the use of
electronic methods of submission for the original proposal and
contemplated the use of facsimile submissions only for revisions
of offers. RFP at 2. The RFP did clearly contemplate submission
in paper form. See id. (listing the mailing address for offers
and instructions for hand delivery, including delivery by
courier).
The record shows that throughout this competition the agency has
made no objection to the submission by e-mail of proposal
revisions by the protester and at least one other offeror. On
May 13, 2008, DSCP transmitted amendment 7 to Labatt as an
attachment to an e-mail that instructed Labatt to “review, sign,
and return this amendment along with your proposal no later than
20 May 2008.” Protest, Exh. 9. The attached amendment specified
a deadline of 2:00 p.m. Eastern Standard Time (EST), May 20.
Amendment 7 increased the guaranteed minimum and maximum order
quantities by over 20 percent and made several changes to the
solicitation which directly addressed Labatt’s previous protest.
The other two offerors submitted proposals by the 2:00 p.m.
deadline; Labatt transmitted its proposal at 4:27 p.m. On May
22, the agency informed the protester that its proposal was
transmitted by e-mail, which was not an authorized transmission
method, and that it was submitted late. This protest followed.
Labatt does not contest that it failed to meet the 2:00 p.m.
solicitation deadline. Rather, Labatt argues that, because the
e-mail transmitting the amendment was created after the
amendment and did not bear the 2:00 p.m. deadline, Labatt
reasonably understood the deadline to be 4:30 p.m. In support of
its position, Labatt relies on FAR sect. 52.212-1(f)(1)
(incorporated into the RFP here), which provides that “[i]f no
time is specified in the solicitation, the time for receipt is
4:30 p.m., local time, . . . on the date that offers or
revisions are due.” The protester met that deadline, and thus
its proposal was not late, Labatt argues. We disagree. The FAR
clause quoted above also stated that “[o]fferors are responsible
for submitting offers, and any modifications, revisions, or
withdrawals, so as to reach the Government office designated in
the solicitation by the time specified in the solicitation.”
Solicitation at 75. The “time specified in the solicitation,”
specifically, amendment 7, was 2:00 p.m., irrespective of what
the transmittal e-mail said, and the protester failed to meet
that deadline.
The protester argues that, assuming all of the offerors made
submissions via e-mail, which, as noted above, was not a
transmission method permitted by the solicitation, the agency
was required to reject all of the proposals. We disagree. Even
where an agency clearly should have amended a solicitation or
otherwise apprised offerors that it had effectively waived a
requirement, our Office will not sustain a protest unless the
protester demonstrates a reasonable possibility that it was
prejudiced by the agency’s actions. 4-D Neuroimaging,
B-286155.2; B-286155.3, Oct. 10, 2001, 2001 CPD para. 183 at
9-10. Here, the agency allowed each of the offerors to submit
proposals by e-mail, which was not a method permitted by the
solicitation; the protester, in fact, benefited from the
agency’s decision to relax the transmission method. The
protester has not shown how it was harmed by the agency’s
acceptance of the offerors' submissions by e-mail. (Labatt
Food Service, Inc., B-310939.6, August 18, 2008) (pdf)
Acceptance of the
late quotation was improper. GPO is correct that
solicitation language setting a certain date and time for
submission of quotations generally does not establish a firm
deadline for receipt of quotations. However, where the
solicitation contains a late submission provision expressly
providing that quotations must be received by the stated
deadline in order to be considered, quotations cannot be
considered if received after the deadline. See M.Braun, Inc.,
B‑298935.2, May 21, 2007, 2007 CPD para. 96; DataVault Corp.,
B-248664, Sept. 10, 1992, 92-2 CPD para. 166 at 2; Instruments &
Controls Serv. Co., supra. Here, the solicitation stated that
“GPO Contract Terms (GPO Pub. 310.2, effective December 1, 1987
(Rev. 6-01)) applies.” AR, Tab B. The referenced GPO contract
terms, in section 7(a) under “Solicitation Provisions,” included
a late submission provision providing that any bid “received …
after the exact time specified for receipt will not be
considered” (except under specified exceptions not applicable
here). This is precisely the type of provision that we have held
precludes an agency from accepting a quotation submitted after
the stated deadline. Although section 7 refers to “bids,” it is
clear from GPO’s incorporation of this provision in the
solicitation that it was intended to apply to the quotations
received here. We conclude that, since TDC’s quotation was
received after the deadline set forth in the solicitation, it
could not be accepted; issuance of the purchase order to TDC
therefore was improper. See M.Braun, Inc., supra. On December
13, 2007, GPO advised us by letter that it had determined
“continued performance under the purchase order issued for the
Quotation Request at issue to be in the best interests of the
Government.” Where, as here, an agency determines that it is in
the best interest of the government to proceed with performance
in the face of a protest to our Office, and we sustain the
protest, we are required by the Competition in Contracting Act
of 1984, 31 U.S.C. sect. 3554(b)(2) (2000), to make our
recommendation for corrective action without regard to any cost
or disruption from terminating the contract, or recompeting or
reissuing the solicitation. Department of the Navy--Modification
of Remedy, B-274944.4, July 15, 1997, 97-2 CPD para. 16 at 2-4.
Ordinarily, therefore, we would recommend that GPO cancel the
purchase order issued to TDC and issue an order to Data
Integrators based on its lowest-priced, timely quotation. See,
e.g., e-LYNXX Corp., B-292761, Dec. 3, 2003, 2003 CPD para. 219
at 9-10 (agency directed to conduct new source selection
decision and cancel order if necessary). Here, however,
shipment was required by December 31, 2007, and we have been
advised by GPO that delivery has been completed. Under these
circumstances, we cannot recommend that GPO cancel TDC’s
purchase order and issue a new order to Data Integrators, since
there is no substantial part of the purchase order remaining to
be performed. See Information Ventures, Inc., B-293518,
B-293518.2, Mar. 29, 2004, 2004 CPD para. 76 at 5 (GAO cannot
recommend disturbing award where contract for educational
services was largely completed); International Data Sys., Inc.,
B‑277385, Oct. 8, 1997, 97-2 CPD para. 96 at 5 (corrective
action not available when contract for personal computers fully
performed). Accordingly, we recommend that Data Integrators be
reimbursed its costs of quotation preparation and of filing and
pursuing the protest, including reasonable attorneys’ fees. Bid
Protest Regulations, 4 C.F.R. sect. 21.8(d)(1), (2) (2007). Data
Integrators should submit its certified claim for costs,
detailing the time expended and costs incurred, directly to GPO
within 60 days after the receipt of this decision. (emphasis
added) (Data Integrators, Inc.,
B-310928, January 31, 2008) (pdf)
Northwest first argues that the agency should accept and
evaluate its submissions because, in the protester’s view, the
USPS records show that delivery was attempted prior to the
closing time, but could not be completed. Thus, the protester
contends that the agency must have failed to make proper
arrangements to receive submissions. The protester also argues
that since its submissions were not proposals, but merely A-E
Qualifications Statements--the evaluation of which are used only
to qualify potential vendors for inclusion on a list for
issuance of task orders at future dates--acceptance and
evaluation of its submissions despite their late receipt causes
no harm to other offerors. It is the responsibility of
each firm to deliver its proposal (or here A-E Qualifications
Statements) to the proper place at the proper time, and late
delivery generally requires rejection of the submission.
Sencland CDC Enters., B-252796, B-252797, July 19, 1993, 93-2
CPD para. 36 at 3. Where late receipt results from the failure
of a vendor to reasonably fulfill its responsibility for
ensuring timely delivery to the specified location, the late
offer may not be considered. Axtec Dev.Co., B-256905, July 28,
1994, 94-2 CPD para. 48 at 3. An offer that arrives late may
only be considered if it is shown that the paramount reason for
late receipt was improper government action, and where
consideration of the proposal would not compromise the integrity
of the competitive procurement process. Caddell Constr. Co.,
Inc., B-280405, Aug. 24, 1998 , 98-2 CPD para. 50 at 6. Improper
government action in this context is affirmative action that
made it impossible for the offeror to deliver the proposal on
time. Id. As an initial matter, the agency denies
receiving or rejecting the Northwest submission package that was
the subject of the alleged delivery attempt by the USPS carrier.
Instead, NPS explains that it followed its standard procedure
for receipt and acceptance of proposals on December 22, 2006. In
this regard, since the designated installation is a secured
facility manned by security personnel on a 24-hour basis,
deliveries entering the building lobby are stopped at the
security desk, while the guard calls the NPS mailroom to advise
that a package had arrived, and needs to be retrieved. CO’s
Statement at 3. If mailroom personnel are not available, the
practice is for building security personnel to call the
contracting and general services offices directly. Moreover, the
agency provided a declaration from the security guard who
covered the post on the date and time in question, and the guard
states that no notice of an attempted delivery was left by the
USPS on that date, and that there were no delivery problems that
day. Declaration of Security Guard, Apr. 11, 2007 . In addition
the CO states that several other proposals were hand-carried to
the agency on December 22, and that, in each case, security
personnel called to advise that a package had arrived. Upon
receipt of these calls, the CO personally greeted individuals
seeking to deliver the submissions and took possession of the
submissions in the building lobby. Finally, the CO explains that
both mailroom and security personnel were aware that the CO was
receiving proposals that day. In our view, the evidence
submitted by the protester does not establish that the agency
actually received the protester’s submissions or that there was
ever an attempt to deliver the submissions to the NPS facility
before the closing time established in the solicitation. As
explained above, the record here, at best, only demonstrates
that the USPS carrier attempted to deliver the protester’s
submissions somewhere in Oakland at 11:22 a.m. on December 22.
There is also no evidence that the NPS failed to make proper
arrangements for deliveries, or in any way mishandled the
submissions. Instead, numerous other proposals were received
throughout the day, and the security guard on duty has submitted
a sworn statement explaining that there were no delivery
problems that day. Under these circumstances, we think the
agency properly refused to accept the protester’s submissions
when they were subsequently delivered by FEDEX.
Alternatively, Northwest asserts that since the submissions here
were only Qualifications Statements, and not proposals, no harm
will result from the agency evaluating its untimely submissions.
For the reasons below, we disagree. The FedBizOpps notice
specifically stated a date and time for delivery of these
submissions and warned vendors that late responses would be
handled in accordance with FAR sect. 15.208. We have recognized
that even when the submissions at issue are not proposals, the
late submission rules alleviate confusion, ensure equal
treatment of all competitors, and prevent one firm from
obtaining any unfair competitive advantage that might accrue
where only one firm is permitted additional time to prepare its
submissions for evaluation by the agency. See Zebra Techs.
Int’l, LLC, B-296158, June 24, 2005, 2005 CPD para. 122 at 3.
(agency reasonably declined to waive a late submission of past
performance information--requested by the solicitation prior to
quotes, and by a date certain--because waiving the clear
submission deadline for the protester would effectively confer a
competitive advantage not provided to other offerors). While the
government may lose the benefit of more advantageous terms
included in a late submission, protecting the integrity of the
competitive procurement process by ensuring fair and equal
treatment among competitors is of greater importance than the
possible advantage to be gained by considering a late submission
in a single procurement. Id. Lastly, the protester
maintains that it is a veteran-owned emerging small business and
may suffer material harm if it is denied the opportunity to be
considered as a potential provider of such services. While we
recognize that denying the protester an opportunity to
participate in these procurements may have an adverse affect on
the protester, acceptance of the protester’s untimely
submissions is unfair to other vendors who timely submitted
responses and inconsistent with protecting the integrity of the
procurement system. (Northwest
Heritage Consultants, B-299547, May 10, 2007) (pdf)
It is an offeror’s responsibility to deliver its proposal to the
proper place by the proper time, and late delivery generally
requires rejection of the proposal. Federal Acquisition
Regulation (FAR) sect. 15.208; The Staubach Co., B-276486, May
19, 1997, 97-1 CPD para. 190 at 3. However, a hand-carried
proposal that arrives late may be considered if improper
government action was the paramount cause for the late
submission, and where consideration of the proposal would not
compromise the integrity of the competitive procurement process.
Caddell Constr. Co., Inc., B-280405, Aug. 24, 1998, 98-2 CPD
para. 50 at 6. Improper government action in this context is
affirmative action that makes it impossible for the offeror to
deliver the proposal on time. Id. Here, as explained below, we
find no basis to conclude that improper government action caused
the late submission of Shirlington’s proposal. The record
shows that once the inconsistency in the delivery addresses
listed in the original RFP was brought to the agency’s
attention, the agency issued an amendment clarifying where
proposals were to be delivered. Thus, there simply is no support
for the protester’s assertion that the agency’s failure “to
provide sufficiently clear delivery instructions,” Comments at
3, caused Shirlington to submit its bid late. The protester
argues that its past pattern of dealing with the agency, which
made it unique among the offerors, led it to conclude that the
proper delivery address was the bid room at 7th and D Streets.
Whatever the protester may have done to satisfy proposal
delivery requirements in prior procurements does not excuse the
protester from its burden to ensure timely delivery of its
proposal at the location specified in the solicitation. See
Schmid & Kalhert GmBH & Co. KG, B‑233467, Feb. 13, 1989, 89-1
CPD para. 148 at 3. In short, there is nothing in the record
showing that any affirmative government action deprived the
protester of the ability to make proper delivery of its
proposal. The protester also asserts that the agency treated
offerors unfairly because DHS employees “may have provided more
explicit instructions to other offerors without sharing this
information with Shirlington.” Comments at 3. As explained
above, two offerors received minimal assistance with directions
to the proposal delivery locations after calling the contract
specialist on the proposal due date. That a contracting official
or other agency employee, in response to an inquiry from a
prospective offeror, provides that offeror with directions to
the proposal delivery location does not form a valid basis of
protest. See Aztec Dev. Co., B-256905, July 28, 1994, 94-2 CPD
para. 48 at 4 (noting that courier could have called the
contracting officer for additional directions to the delivery
location). The protester, of course, could have availed itself
of the same opportunity to obtain directions. The
protester asserts, alternatively, that its proposal was received
and under the government’s control prior to the submission
deadline so that an exception to the rule that late proposals
must be rejected applies. In this regard, FAR sect. 15.208(b)(1)
states that any proposal that
is received at the designated Government office after the
exact time specified for receipt of proposals is “late” and
will not be considered unless it is received before award is
made, the contracting officer determines that accepting the
late proposal would not unduly delay the acquisition; and—
* * * * *
(ii) There is acceptable evidence to establish that it was
received at the Government installation designated for receipt
of proposals and was under the Government’s control prior to
the time set for receipt of proposals . . . .
This exception may apply, if all other conditions are also met,
when a proposal is late but at the office designated for receipt
of proposals, and under the government’s control, before the
time set for receipt of proposals. See States Roofing Corp.,
B-286052, Nov. 8, 2000, 2000 CPD para. 182 at 4-5. This
exception clearly does not apply here given that the proposal
was not, in fact, at any time delivered to “the designated
Government office,” i.e., the address listed in amendment 3 of
the RFP; in fact, it was delivered to an entirely different
location. (Shirlington
Limousine & Transportation, Inc., B-299241.2, March 30,
2007) (pdf)
Omega asserts that the agency was required to consider its late
FPR pursuant to a solicitation provision stating that “a late
modification of an otherwise successful proposal that makes its
terms more favorable to the government will be considered at any
time it is received and may be accepted.” RFP sect. L-1
(incorporating Federal Acquisition Regulation (FAR) sect.
52.215-1). Omega maintains that its proposal was the only
acceptable one--and thus was the “otherwise successful proposal”
prior to the request for second FPRs--because it was the only
one that offered the required OEM warranties; based on
discussions it had with component manufacturers, Omega believes
GDC4S’s proposal could not have included the required OEM
warranties.
Omega’s argument is without merit. An “otherwise successful
proposal” is one that would result in the award of the contract
to the offeror regardless of the late modification; generally,
this means that the government may accept a favorable late
modification only from the offeror already in line for award.
Seven Seas Eng’g & Land Surveying, B‑294424.2, Nov. 19, 2004,
2004 CPD para. 236 at 4; Robotic Sys. Tech., B‑271760, May 14,
1996, 96-1 CPD para. 229 at 3. The record shows that Omega’s
proposal would not have been in line for award prior to the late
modification. In this regard, the agency informed Omega in its
August 17 discussions (prior to the second FPR) that its price
proposal was “unreasonably high, relative to the other offerors,
and is potentially non‑competitive.” Agency Report (AR), exh.
16. Since the agency found that pricing changes were necessary
in order for Omega’s proposed price to be deemed reasonable, and
required offerors to respond to the amended solicitation, its
proposal was not the “otherwise successful proposal,” and there
thus was no basis for the agency to accept its late FPR. (Omega
Systems, Inc., B-298767, November 6, 2006) (pdf)
On August 23, 2006, Symetrics transmitted its FPR electronically
to the contracting officer’s e-mail address. At 2:58 p.m., the
president of Symetrics phoned the contracting officer to notify
her that Symetrics had submitted its FPR. Protest, Symetrics’
President’s Affidavit. The contracting officer received the
e-mail while on the phone with Symetrics’ president and told him
that it was received at 3:01 p.m, according to her computer. The
e‑mail, according to the contracting officer’s computer, showed
the e-mail message forwarding the FPR was sent at 2:54 p.m.
Agency Report, attach. 2, Declaration of Contracting Officer.
Symetrics’ computer mail server records evidence that at
14:55:42 p.m. Symetrics commenced transmission, at 14:55:44 p.m.
the intended recipient was identified and located, at 14:58:30
p.m. Symetrics’ transmission to the destination was identified
as complete, and finally at 14:58:31 p.m. Symetrics’ mail server
returned the following message: “SMTP session successful.”
Protest, exh. B, Affidavit of Information Technology Specialist
Contracted by Symetrics; attach. The Government’s e-mail
relay report showed Symetrics’ FPR was accepted at the server at
Wright-Patterson Air Force Base, Ohio at 2:57:41 p.m. and
delivered to the contracting officer’s e-mail box at 3:01:00
p.m., and that the process was completed at 3:01:00 p.m. Agency
Supplemental Report, Declaration of Computer System Analyst;
Agency Report, attach. 2A, E-mail Relay Report. Symetrics argues
that the rejection of its FPR was unreasonable because it was
within the control of the government by the deadline for receipt
of FPRs. However, a late proposal revision submitted
electronically may only be accepted if one of the exceptions
contained in FAR sect. 52.215-1(c)(3) is applicable. See Sea
Box, Inc, B‑291056, Oct. 31, 2002, 2002 CPD para. 181.
Under the first exception to FAR sect. 52.215-1(c)(3), a late
proposal submitted via electronic means is late, unless
accepting the late offer would not unduly delay the acquisition,
and it was received at the initial point of entry to the
Government infrastructure not later than 5 p.m. 1 working day
prior to the date specified for receipt of proposals. FAR sect.
52.215-1(c)(3)(ii)(A)(1). This exception does not apply, as
Symetrics FPR was not submitted by 5 p.m. on August 22, 2006.
Our Office has previously determined that the second exception,
FAR sect. 52.215‑1(c)(3)(ii)(A)(2), which allows for
consideration of proposals received at the Government
installation designated for receipt of offers and under the
Government's control prior to the time set for receipt of
offers, is not applicable to electronic proposals. Sea Box, Inc,
supra, at 3. Although not expressly stated in the regulation, we
found that the second exception necessarily applies only to
proposals delivered by other than electronic means. This is so
because if the Government considered a late electronic proposal
under the second exception, regardless of whether it was
received by 5 p.m. the previous working day, the first exception
would effectively be rendered meaningless. Id. Since Symetric’s
FPR was not received in the e-mail mailbox of the contracting
officer until 3:01:00 p.m., which was validated by the
Government’s e-mail relay report, the late proposal cannot be
accepted. Id. (Symetrics Industries,
LLC, B-298759, October 16, 2006) (pdf)
The protest is without merit because there is no evidence of
mishandling or any other improper agency action. USAID’s
Director of Mail Management denies receiving or rejecting the
Castle proposal package, and reports that the contractor’s
mailroom supervisor and mailroom staff also deny handling the
package. Director’s Affidavit, paras. 7-8. In this regard, there
is no marking on the returned package to indicate it was handled
by USAID’s mailroom. Further, as noted by the Director, USAID
mailroom procedures do not include handwritten notations for
returns but, rather, involve the use of a special “return to
sender” label (Id. at para. 6) which, we note, does not appear
on the photocopy of the returned package’s label. Further, the
package’s tracking information and the returned label both
indicate that the package was refused at zip code 20460, which
is assigned to the Environmental Protection Agency (EPA),
another tenant in the Ronald Reagan Building with its own
mailroom. Since, aside from the protester’s speculation, there
is no evidence that USAID mishandled the proposal package or
contributed in any way to the failed delivery attempt, the
agency’s subsequent refusal to accept the late proposal was
proper. We find that the record supports the alternative
explanation--suggested by the agency--that Castle’s mislabeling
of the proposal package may have caused the failed delivery. In
this regard, the Reagan Building, where USAID is located, is the
second largest federal building in the country, and is shared by
three other federal agencies and more than 50 private
businesses. There are five separate mailrooms and zip codes for
the building--one for each federal agency and one for the
private businesses. USAID’s zip code--as stated in the RFP--is
20523 and its mailroom is located on the 13½ Street side of the
building, while the private business tenants share the 20004 zip
code--the zip code on Castle’s mailing label--and have their
mailroom on the Pennsylvania Avenue side. According to USAID’s
Director, the mail for each federal agency is delivered by USPS
directly to the particular agency’s mailroom. Given the zip code
on Castle’s proposal package and the absence of the agency’s
name, it appears that USPS may have attempted delivery to the
mailroom for the private business tenants, rather than to
USAID’s mailroom. The Director explains that, when USAID mail is
misdirected to other agencies in the building, those agencies’
staff “will sometimes bring pieces of misdirected mail to our
attention--provided, of course, that the address on the letter
or package makes clear that it is intended for receipt by USAID.”
Id., paras. 3-5. The Director further states that, in his
experience, it is uncommon for USAID mail to be misdirected to
the private business tenants, and even less common for those
firms to alert USAID staff when it does happen. Id. at para. 5.
Thus, while it appears that Castle’s proposal package arrived at
the proper street address--1300 Pennsylvania Avenue--it also
appears that Castle’s failure to use the correct zip code and
agency name may have prevented delivery of its proposal. Castle
asserts that we should find “government mishandling” based on
the “malfunctioning” Click-N-Ship® program, and USPS’s failure
to deliver its Express Mail package by the guaranteed time and
taking 7 days to return the package to Castle. Supplemental
Comments at 5. None of these matters constitute government
mishandling. First, we view the alleged Click-N-Ship® problems
as a failure on the protester’s part, not the government’s,
since the protester chose to use the Click-N-Ship® program to
print its mailing label. Castle was responsible for choosing a
means of addressing its proposal package--such as simply
handwriting all necessary information on an Express Mail
envelope and having the postage affixed at the nearest post
office--that would result in the package being correctly
addressed. Further, any delay connected with USPS’s handling of
the Express Mail delivery is not considered to be mishandling by
the government; the word “government” in the context of proposal
mishandling refers to the procuring agency, not USPS, and the
mishandling must occur after the proposal is received at the
government installation. California State Univ., Fullerton,
B-243040.2, May 9, 1991, 91-1 CPD para. 452 at 2. (The
Castle Group, B-297853, March 21, 2006) (pdf)
We find the agency’s action was the paramount cause for the late
delivery of the proposal revision on Monday, May 17. In this
regard, the agency extended closing to Saturday, May 15, but
failed to establish adequate procedures to ensure that
reasonable attempts to deliver hand‑carried proposals prior to
closing would be received at the place designated for delivery.
Specifically, Saturday was not a normal business day for the
agency and the doors to the agency were locked. The agency did
not post instructions outside the locked door stating that
agency personnel would be present to receive deliveries, or how
to contact them. Therefore, when a courier attempted to enter
the locked doors and received no response from within, it was
reasonable for the courier to assume that delivery at that
address on Saturday was not possible. While the record shows
that Saturday delivery was possible at other times on that day
(as evidenced by the single proposal that the agency did receive
on that day), delivery was impossible at the time Federal
Express attempted to deliver Integrity’s proposal revision (as
evidenced by the note left on the locked door by Federal
Express), and the circumstances of the locked door and lack of
posted instructions regarding delivery of proposals did not
create a reasonable basis upon which the courier should have
concluded that delivery would be possible later that day. But
for the agency’s action here, Integrity’s hand-carried proposal
revision would have been delivered prior to the required closing
date, and we therefore conclude that the agency’s action was the
paramount cause of the late delivery. See Palomar Grading &
Paving, Inc., B‑274885, Jan. 10, 1997, 97‑1 CPD para. 16 at 3-4
(agency’s incorrect delivery instructions was the reason for a
failed timely hand-carried delivery of bid and the paramount
cause of late delivery); Richards Painting Co., B‑232678, Jan.
25, 1989, 89‑1 CPD para. 76 at 2-4 (agency failure to staff room
designated for receipt of bids up to the exact time specified
for bid opening was the paramount cause of late delivery); Sun
Int’l, B‑208146, Jan. 24, 1983, 83‑1 CPD para. 78 at 2-4 (agency
failure to apply reasonable procedure for accepting delivery of
bids on weekends was the paramount cause of late bid delivery);
cf. Bergen Expo Sys., Inc.; Techniarts Eng’g, B‑236970,
B‑236970.2, Dec. 11, 1989, 89-2 CPD para. 540 at 2-3 (where
courier failed to wait a reasonable time for agency personnel to
respond to security guard’s call and courier did not attempt
re-delivery later that same business day, agency’s
action--restricting access and delay in responding to call--was
not the paramount cause of late delivery). We also find that
consideration of the late proposal revision did not compromise
the integrity of the competitive procurement process. The
proposals were not publicly opened and Integrity’s proposal
remained in the possession of Federal Express during the time
between the attempted delivery on Saturday and the actual
delivery by that carrier the following Monday; therefore, there
is no evidence that Integrity had an opportunity to alter its
submission after closing. See Palomar Grading & Paving, Inc.,
supra, at 4; Sun Int’l, supra, at 4. (Hospital
Klean of Texas, Inc., B-295836; B-295836.2, April 18, 2005)
(pdf)
An offer
is late if its does not arrive in the office designated in the
solicitation by the time specified in the solicitation. Sencland
CDC Enters., B-252796, B-252797, July 19, 1993, 93-2 CPD
paragraph 36 at 3. An offer that arrives late may only be
considered if it is shown that the paramount reason for late
receipt was improper government action, and where consideration
of the proposal would not compromise the integrity of the
competitive procurement process. Caddell Constr. Co., Inc. ,
B-280405, Aug. 24, 1998, 98-2 CPD paragraph 50 at 6. Here, FedEx
records provide the only evidence that the FedEx truck was
stopped at a random security checkpoint on the base; the agency
maintains it has no record of such a stop. Agency Report (AR),
Tab 16. However, even assuming there was a security stop, this
would not necessarily constitute improper government action,
since a 20 minute security delay on a military base is not on
its face unreasonable. Rather, we think this is a situation
where an offeror should reasonably anticipate such a delay. We
have recognized that delays in gaining access to government
facilities are not unusual and should not be unexpected. See ,
e.g., Einhorn Yaffee Prescott , B-259552, Mar. 20, 1995, 95-1
CPD paragraph 153 at 3. In any case, we do not view the
government's actions here as the paramount cause of the late
receipt of Kesser's proposal. In this regard, the alleged
security delay took place at approximately 11:40 a.m. Thus, the
courier still had 2 hours to timely deliver the package once he
was allowed to proceed. The courier explained to the CO that,
after he was stopped by the military police, he continued to
follow his usual route until he received a call from his
dispatcher, instructing him to deliver to Building 6 before
making his scheduled stop at Building 4. AR, Tab 11. He then
proceeded to deliver Kesser's package at that time. Given these
circumstances, the paramount cause for the package's late
delivery was the courier's decision to continue on his normal
route after the alleged security delay--rather than deliver
Kesser's proposal at that time--and not the government's
actions. (Kesser International,
B-296294, June 30, 2005) (pdf)
The record here provides no basis to question the reasonableness
of the rejection of Zebra's quotation for failure to timely
submit its past performance information. First, since the RFQ's
late quotation provision expressly applied to the past
performance submission, it is clear that the agency's rejection
of Zebra's quotation for failing to meet the closing time
specified for that submission falls squarely within the terms of
the solicitation. Moreover, the protester has not shown that its
failure to meet the mandatory past performance submission
deadline was only a minor informality that must be waived, as
Zebra argues, as a matter of form over substance. Rather, our
review of the record confirms the reasonableness of the agency's
position that the RFQ's deadline for the past performance
submissions was material to the agency's actual needs, and thus,
was not merely a matter of form. This is evident, for example,
from the repeated emphasis given in the RFQ (as well as its
cover letter, and several answers to vendor questions published
by the agency) to the agency's need to prevent any delay in the
procurement from the substantial past performance evaluation
efforts that were anticipated under the RFQ, including the
management and review of the multitude of past performance
reference questionnaires for each of the many vendors expected
under each of the multiple award groups. (Zebra
Technologies International, LLC, B-296158, June 24, 2005) (pdf)
Seven Seas submitted its reply to CECOM's IFNs on July 27, after
the required date for its reply; Seven Seas also acknowledged
amendment 2 at the same time. The record shows that the
protester's IFN responses would have revised the firm's proposal
in a number of regards. Comments, attach. H. CECOM did not
consider the protesters late response to the IFNs or its late
acknowledgment of amendment 2. In the absence of a timely
response to the IFNs, CECOM concluded that Seven Seas proposal
was technically unacceptable based upon deficiencies and
weaknesses identified in all three technical subfactors, and
based upon the missing past performance information. AR, Tab K,
Letter from CECOM to Seven Seas (Aug. 2, 2004). CECOM rejected
Seven Seas proposal, and this protest followed. Seven Seas
acknowledges that its reply to the agency's IFNs was late, but
protests that the contracting officer should have considered the
protesters late response. Seven Seas argues, citing Federal
Acquisition Regulation (FAR) 15.307, that the contracting
officer is required to establish a common cut-off date for only
the receipt of final proposal revisions, and that, because the
IFNs did not request the firm's final proposal revisions, the
contracting officer had latitude to relax time constraints for
the submission of proposal revisions before the final revision.
Comments at 4-6. On this basis, Seven Seas contends that the
contracting officer could waive the late submission of the firms
proposal revisions as a minor informality under FAR14.405. Seven
Seas does not contend that its late response to the IFNs was due
to any action or inaction by the agency. We disagree with Seven
Seas apparent belief that the contracting officer was required
to consider the protester's late IFN responses or was required
to waive the protesters late proposal revisions. Although it is
true that FAR 15.307(b) provides for a common cut-off date only
for receipt of final proposal revisions, this does not mean that
an offeror is permitted to submit other proposal revisions (not
the final proposal revision) after the time specified by an
agency. FAR 15.208 provides in this regard that offerors are
responsible for submitting proposals, revisions, and
modifications to the proper place at the proper time and that
late submissions of proposals, revisions, and modifications may
not be considered, except, as is pertinent here, where the late
submission is received before award, and is a late modification
of an otherwise successful proposal that makes its terms more
favorable to the government. An otherwise successful proposal is
one that would result in the award of the contract to the
offeror regardless of the late modification. RMS Indus.,
B-245539, Dec. 9, 1991, 91-2 CPD 528 at 3. Here, Seven Seas
initial proposal was not technically acceptable and therefore
could not be considered an otherwise successful proposal. In the
absence of any action by the agency causing the protester's late
response to the IFNs, we conclude that the contracting officer
did not act unreasonably in rejecting Seven Seas late IFNs
responses. (Seven Seas Engineering &
Land Surveying, B-294424.2, November 19, 2004) (pdf)
It is well established that the standard for late proposals does
not generally apply to requests for quotations. An RFQ, unlike a
request for proposals (or an invitation for bids), does not seek
offers that can be accepted by the government to form a
contract. Rather, the government's purchase order represents the
offer that the vendor may accept through performance or by a
formal acceptance document. DataVault Corp., B-248664, Sept. 10,
1992, 92-2 CPD 166 at 2. It follows that language in an RFQ
requesting quotations by a certain date cannot be construed as
establishing a firm closing date for receipt of quotations,
absent a late quotation provision expressly providing that
quotations must be received by that date to be considered.
Instruments & Controls Serv. Co. , B-222122, June 30, 1986, 86-2
CPD 16 at 3. An agency may consider late quotations or quotation
modifications, so long as the award process has not begun and
other offerors would not be prejudiced. KPMG Consulting LLP ,
B-290716, Sept. 23, 2002, 2002 CPD 196 at 11. Here, AMC
considered AFMOs submission substituting that firm for Tactical
Gear Now. AMCs action was consistent with the RFQ, which did not
contain a late quotation provision. Further, the substitution of
AFMO for Tactical Gear Now was received on May 28, only 2 days
after the closing time on May 26, and apparently before start of
the selection process. Since there is no apparent basis to find
that any competitor was prejudiced by the agencys acceptance of
the substitution of AFMO for Tactical Gear Now, we find that AMC
acted properly when it accepted AFMOs late modification of the
quotation. (Armed Forces Merchandise
Outlet, Inc., B-294281, October 12, 2004) (pdf)
The FedEx courier arrived at the DOT building with InfoGroup's
package (and, apparently, numerous other packages) at around
9:30 a.m. on Friday, August 13. Security personnel x-rayed and
date-stamped the package, and the courier then signed in at 9:37
and proceeded into the building to deliver the packages,
unescorted, to individual rooms. While at the building,
according to the courier, he attempted to telephone the
contracting officer at the number on InfoGroup's proposal
package to find out the room number to which the package should
be delivered, but there was no answer. Letter from FedEx to
Protester, Sept. 9, 2004. Before leaving the building at 2:30
p.m., the courier placed a second call to the contracting
officer; again, however, there was no answer. The courier
therefore left the building and returned to the FedEx office
with the package. FedEx telephoned the agency again on the
afternoon of Tuesday, August 17, and learned the room number at
that time. The proposal package finally was delivered on August
18 at 12:11 p.m. Since this was well after the August 16 closing
time, the agency rejected the proposal as late. The protest is
without merit. There is no evidence of improper agency action.
The RFP clearly set forth the precise location for delivery of
proposals, and InfoGroup's courier arrived at the proper address
and was permitted access to the building for purposes of
delivering packages. While the protester points to the agency's
failure to escort the courier or to be available to provide
information to the courier, the agency was not required to
perform these functions. Rather, the agency fulfilled its
responsibility by providing the protester with complete delivery
information, including the room number, and then providing the
protester's courier with access to the building for purposes of
delivering the proposal. The fact that the agency did not
proceed in accordance with InfoGroup's understanding regarding
DOT building policy is not improper agency action; the RFP did
not state that couriers would be escorted to the designated
room, and there simply was no basis for the protester to plan
the delivery of its proposal using that assumption. InfoGroup,
on the other hand, did not reasonably fulfill its responsibility
for ensuring timely delivery. The solicitation informed offerors
that proposals were to be received in room 5301. InfoGroup
failed to list the room number on the proposal package and this,
as the record shows, led to the courier's inability to deliver
the package. In this regard, as noted above, FedEx states in a
September 9 letter sent to the protester in connection with this
protest that the courier was unable to deliver the proposal
package on August 13 due to the absence of a room number on the
package. We note that this explanation is consistent with the
courier's attempts to contact the contracting officer while he
was in the DOT building on August 13. (InfoGroup
Inc., B-294610, September 30, 2004) (pdf)
The dispositive question here is when Immediate’s president
relinquished control of its proposal. Even if we agree with the
protester that Immediate’s BAFO was properly logged in by the
guard at 2 p.m., Immediate’s president retained control of the
proposal after the guard signed for the package, because the
president (not the guard) delivered the proposal to the
contracting specialist. We do not agree with the protester that
the brief exchange between the guard and Immediate’s president
qualifies as relinquishment of control. See J.C.N. Constr. Co.,
Inc., B-250815, Feb. 23, 1993, 93-1 CPD ¶ 166 at 3. Since
Immediate’s president did not relinquish control of the BAFO
until 2:14 p.m., after the time set for the receipt of BAFOs, to
the contract specialist, its BAFO was properly rejected as late.
(Immediate Systems Resources, Inc.,
B-292856, December 9, 2003) (pdf)
In the context of negotiated procurements, such as the one at
issue here, there is, of course, no bid opening and thus no
requirement that a government official announce when the time
for receipt of submissions has arrived. However, just as we
believe that it would have been reasonable for a government
official, had this been a sealed bid acquisition, to announce
bid opening at any point between 14:00:00 and 14:00:59, we
believe that the RFP’s reference to a closing time of 14:00
hours could reasonably be interpreted either as requiring that
proposals be received by 14:00:00, or as requiring that they be
received by 14:00:59. To the extent that is viewed as an
ambiguity in the solicitation, it was one that was obvious from
the face of the RFP, and we have repeatedly held that an offeror
who chooses to compete under a patently ambiguous solicitation
does so at its peril and cannot later complain when the agency
proceeds in a manner inconsistent with one of the possible
interpretations. Wackenhut Servs., Inc., B‑276012.2, Sept. 1,
1998, 98‑2 CPD ¶ 75 at 5. The protester contends that the
fact that the RFP referenced the closing time for receipt of the
part 1 proposals as “14:00:00” indicates that the agency
intended the reference to “1400 hours” in the instructions for
receipt of part 2 proposals to be interpreted as 14:00:00. This
argument is not persuasive. It could be argued equally
reasonably that the agency’s dropping of the zeroes in the
seconds place in the time specified for receipt of part 2
proposals signified that it did not intend that reference to be
interpreted as 14:00:00. Accordingly, if the record establishes
that Gray’s proposal was received prior to 14:01:00, we think
that the agency need not have rejected it as late. Turning
then to our second question, we think that the record here
establishes that Gray’s proposal was received by the agency
prior to 14:01:00. A proposal is received at the time that the
offeror relinquishes control of it to the government. See Weeks
Marine, Inc., B-292758, Oct. 16, 2003, 2003 CPD ¶ __; Carothers
Constr., Inc., B-235910, Oct. 11, 1989, 89-2 CPD ¶ 338 at 4.
Gray’s messenger relinquished control of Gray’s proposal package
to the designated contracting official by placing it on her desk
in her presence, which, according to the contracting official’s
uncontroverted statement, occurred prior to the time/date stamp
clock turning to 14:01. The fact that the contracting official
may not have picked up the package prior to 14:01 is irrelevant
since an individual may gain effective control over an item
without actually taking it into his or her hands. The case cited
by the protester for the proposition that an offeror does not
relinquish control of its proposal by placing it on a desk in
the opening room, George W. Kane, Inc., B-245382.2, Feb. 4,
1992, 92-1 CPD ¶ 143, is distinguishable from the case at hand.
In the Kane case, no government official was present at the desk
at the time the bidder placed its bid on it; thus, placing the
bid on the desk did not transfer it to the control of an
appropriate government official. (The
Haskell Company, B-292756, November 19, 2003) (pdf)
Improper government action in this context is affirmative action
that makes it impossible for the offeror to deliver the proposal
on time. Id. Nevertheless, even in cases where the late receipt
may have been caused, in part, by erroneous government action, a
late proposal should not be considered if the offeror
significantly contributed to the late receipt by not acting
reasonably in fulfilling its responsibility to deliver a
hand-carried proposal to the proper place by the proper time.
Integrated Support Sys., Inc., B-283137.2, Sept. 10. 1999, 99-2
CPD ¶ 51 at 2. Here, as explained below, we find no basis to
conclude that improper government action was the paramount cause
for the late submission of O.S.’s proposal. Even conceding that
USSOCOM may have complicated delivery of hand-carried proposals
by not including more explicit instructions in the RFP and by
designating a location with restricted access for receipt of
proposals, the record evidences that the delivery driver
contributed significantly to the late delivery of the proposal.
Indeed, the record indicates that the main reason that the
proposal was received late was because the delivery driver was
unfamiliar with the exact address on MacDill AFB, and decided to
make another delivery first and then to attempt to find the
filing location unaided, rather than seeking advice concerning
the address and location of the contracting officer immediately
upon entering the facility. It was only after this effort proved
unsuccessful that the delivery driver attempt to contact the
contracting officer (just prior to 2 p.m.), and to seek the
assistance of other personnel, including those in the mailroom
at the designated address.[3] The delivery driver ultimately was
able to deliver the proposal to the contracting officer, albeit
30 minutes after the designated time for receipt of proposals,
which evidences that the delivery driver could have delivered
the proposal to the proper place at the proper time if he had
more prudently utilized his time upon entering the facility.
Thus, we find that the delivery driver significantly contributed
to the late receipt of O.S.’s proposal, and that improper
government action was not the paramount cause of its late
receipt. (O.S. Systems, Inc.,
B-292827, November 17, 2003) (pdf)
As a general matter, offerors may use any transmission method
authorized by the solicitation. Federal Acquisition Regulation
(FAR) § 15.208(a). Here, the RFP incorporated by reference FAR §
52.215-1, which provides in pertinent part as follows:
"Unless other methods (e.g., electronic commerce or facsimile)
are permitted in the solicitation, proposals and modifications
to proposals shall be submitted in paper media . . . ."
FAR § 52.215-1(c)(1). The solicitation nowhere authorized the
use of electronic methods of submission, and in fact clearly
contemplated submission in paper form. See RFP § A2 (listing the
mailing address for offers and instructions for hand delivery).
Accordingly, since the RFP did not authorize submission of
offers by e-mail or other electronic methods, NSF properly
rejected IBS's electronically submitted FPR. See Environmental
Control Div., Inc., B-255181, Feb. 16, 1994, 94-1 CPD ¶ 115 at 4
(facsimile best and final offer (BAFO) was properly rejected
where RFP did not provide authorization for facsimile
submissions); G.D. Searle & Co., B-247077, Apr. 30, 1992, 92-1
CPD ¶ 406 at 3. In any event, even if the RFP had
authorized electronic submission of offers, the record shows
that at the submission deadline--10:30 a.m., March 13--NSF's
server had received only the technical portion of IBS's
proposal. Two minutes after the deadline, NSF's server received
the remaining cost portion.[1] Proposals received after the
exact time specified for receipt of proposals are late and will
not be considered by the government unless the exceptions
outlined in FAR § 15.208(b)(1) apply. PMTech, Inc., B-291082,
Oct. 11, 2002, 2002 CPD ¶ 172 at 2. Nothing in the record
suggests that those exceptions apply here. Thus, NSF was under
no obligation to consider the submission it received at 10:30
a.m. because that submission was missing a material portion.
Cyber Digital, Inc., B-270107, Jan. 24, 1996, 96-1 CPD ¶ 20 at
4. (Integrated Business Solutions,
Inc., B-292239, July 9, 2003)
We have always viewed the underlying policy for application of
the late proposal rules as ensuring fair and equal competition
and avoiding confusion. See, e.g., Phelps-Stokes Fund, B‑194347,
May 21, 1979, 79-1 CPD ¶ 366 at 5 (prior to Abt); see also
PMTech, Inc., B‑291082, Oct. 11, 2002, 2002 CPD ¶ 172 at 3.
Given that HHS had received, by means specifically authorized by
the RFP, a complete copy of Tishman's proposal prior to the time
set for receipt of proposals, we fail to see how the late
proposal rule or policy would be violated by consideration of
Tishman's proposal. HHS argues that consideration of
Tishman's proposal would reflect an unequal treatment of those
offerors that were able to timely submit both an electronic and
paper version of its proposals. HHS neglects, however, to
consider that such “unequal treatment,” as asserted by the
agency here, is not material nor does it present any possibility
that Tishman could obtain competitive advantage over other
offerors, given that it undeniably submitted a proposal by the
closing time. Rather, as we found in Abt, the protester's
failure to timely deliver more than one complete copy of its
proposal is nothing more than a minor informality. Moreover,
contrary to HHS's suggestion, since no one denies that Tishman's
electronic proposal was timely submitted and was identical to
its paper proposal, there is nothing that indicates any possible
confusion. (Tishman Construction
Corporation, B-292097, May 29, 2003)
It is the contracting agency's right to determine when the
negotiation and offer stage of a procurement is finished, and an
offeror has no legal right to insist that negotiations be
reopened after final proposal revisions have been submitted.
Independent Bus. Servs. Inc., B-235569.3, Nov. 2, 1989, 89-2 CPD
¶ 413 at 3. The record shows that more than 2 months after
submission of final proposal revisions Dismas requested a site
change on the basis that its proposed site was unavailable and
had been sold to another party. Nothing in the record suggests
that the agency acted unreasonably or in a way inconsistent with
the solicitation in deciding not to accept Dismas's proposal
revision. A late proposal modification may be accepted
only if the late modification makes the terms of an otherwise
successful proposal more favorable to the government.
Environmental Tectonics Corp., B-225474, Feb. 17, 1987, 87-1 CPD
¶ 175 at 4. Here, notwithstanding the statement in the agency
report that Dismas was “apparently in line for award,” there is
nothing in the contemporaneous evaluation record showing that
the agency had concluded that the Dismas revised proposal was
the “otherwise successful” proposal. Since, as the agency report
to our Office indicates, a recommendation concerning Dismas “was
being reviewed,” it is not clear from the record which offeror
was actually in line for award based on revised proposals. The
documents referred to by the agency in its report do not
identify any “otherwise successful” proposal. Agency Report, Tab
9B. More importantly, at the time Dismas requested the site
change, its revised proposal was no longer acceptable because
its proposed facility was no longer available. Thus, under these
circumstances, the RFP provision cited by Dismas does not
provide a basis to accept Dismas's request for a site change.
(Dismas Charities,
Inc. , B-291868, April 23, 2003) (pdf)
Here, the RFQ's call for “technical proposals” due on the next
business day may well have been objectionable in other
circumstances. In the context of the unique facts of this case,
however, we do not find the agency's actions to be
objectionable. During a telephonic hearing that our Office
conducted, Warden admitted that it could have timely prepared
and submitted the requested technical proposal; instead,
according to the protester, the critical issue was the medium of
submission, not its ability to prepare a technical proposal in
the limited time. Warden apparently believed that it could
prepare and submit its proposal by the deadline, if the agency
would accept e-mail submission. Warden was unwilling, however,
to fax its proposal (as the contracting officer suggested)
because it was concerned that even if transmission began before
1 p.m., the last faxed page might not be received by 1 p.m.
Warden did not raise this concern about facsimile transmission
with the SBA during the September 30 telephone calls, and
concedes that it probably could have faxed the proposal before 1
p.m., although it would have been close to that deadline.
Furthermore, the contracting officer stated during the
telephonic hearing that she would have stood by her offer to
accept the facsimile of Warden's submission. Warden's company
personnel nevertheless decided to file a protest instead. In
other words, Warden could have made a timely submission to the
contracting agency, but instead chose not to. (Warden Associates, Inc., B-291440;
B-291440.2, December 27, 2002)
Sea Box does not dispute that its proposal could not be accepted under the first
exception, FAR § 52.215-1(3)(ii)(A)(1), since it was not transmitted by 5:00 p.m. the
working day before the due date. See PMTech, Inc., B-291082, Oct. 11, 2002, 2002
CPD ¶ __ at 2-3 (electronic proposal transmitted 13 minutes prior to deadline for
submitting proposals properly rejected). Sea Box argues, however, that its proposal
nevertheless could be accepted under the second exception, FAR §
52.215-1(3)(ii)(A)(2). While the second exception may be
broad enough to encompass situations involving electronic
commerce delivery methods, we do not read the regulation as
providing two alternative means for determining whether a late
electronically transmitted proposal may be accepted. The first
exception applies, by its express terms, to situations where a
proposal has been submitted by an electronic commerce method,
and unqualifiedly permits such a late proposal to be considered
for award only if it was received at the initial point of entry
to the government infrastructure no later than 5:00 p.m. the
preceding working day. Although not expressly stated in the
regulation, we think the second exception necessarily applies
only to proposals delivered by other than electronic means. This
is so because, under the protester's alternative interpretation,
late electronically transmitted proposals could be considered
for award under the second exception whether or not they were
received at the initial point of entry by the preceding working
day; this would essentially render the first exception a
nullity. Since the first exception expressly applies to
electronically transmitted proposals, there is no reason to
assume that such a result was intended. Moreover, such an
interpretation would be inconsistent with the fundamental
principle that statutes and regulations must be read and
interpreted as a whole, thereby giving effect to all provisions.
See Waste Mgmt. of North Am., B-225551, B-225553, Apr. 24, 1987,
87-1 CPD P: 435 at 5. We conclude that the two exceptions are
complementary, each addressing the circumstance of a late
proposal, depending upon the method of proposal submission.
Since Sea Box's electronically transmitted proposal was received
at the specified e-mail destination after the time set for
receipt of proposals, it is a late proposal; since it was not
received at the initial point of entry by 5:00 p.m. the day
before proposals were due, the late proposal cannot be
considered for award. (Sea
Box, Inc., B-291056, October 31, 2002) (pdf)
We
view it as an offeror's responsibility, when transmitting its
proposal electronically, to ensure the proposal's timely
delivery by transmitting the proposal sufficiently in advance of
the time set for receipt of proposals to allow for timely
receipt by the agency. In our view, the record shows that
the primary cause of PMT's late delivery of its electronic
proposal was that PMT delayed attempting to transmit its
proposal until only 13 minutes before the time set for the
receipt of proposals. An offeror's responsibility to
deliver its proposal to the proper place at the proper time
includes allowing a reasonable amount of time for the delivery
of the proposal. Thus, we have found that where an offeror
delayed transmitting a lengthy facsimile best and final offer
until 10 minutes prior to the closing deadline, and the agency
otherwise had reasonable facsimile submission procedures in
place, the late receipt of the offeror's facsimile transmission
was the fault of the offeror and not the government. See
Brookfield Dev., Inc. et al., B-255944, Apr. 21, 1994,
94-1 CPD ¶ 273 at 3; see also Cyber Digital,
Inc., supra, at 4 (late receipt of facsimile
transmission of best and final offer was offeror's fault where
offeror waited until 30 minutes before the closing time to
request an extension, which was denied, and thereafter
transmitted the proposal). (PMTech,
Inc., B-291082, October 11, 2002) (pdf)
We do not think the agency was
required to anticipate that faxing would make the intended due
date unclear such that potential offerors could be misled.[3]
We note in this regard that agencies are not guarantors that
solicitation documents will be received by offerors in every
instance--the risk of nonreceipt rests with offerors. Chem-Fab
Corp., B-277795, Oct. 27, 1997, 97-2 CPD ¶ 120. It follows,
we think, that agencies are not guarantors that information sent
by fax will be accurately printed by an offeror's fax machine.
We conclude that the agency properly rejected Centro's offer as
late. (Centro
Management, Inc., B-287107, March 9, 2001)
The timeliness of SRC's proposal
turns solely on the sequence of two events--the contracting
officer's time-stamping of the sheet of paper at 4:01, and the
protester's arrival in Suite 100. If SRC arrived prior to the
time-stamping, its proposal was timely submitted, since the
contracting officer used the time-stamping to signify that the
closing time had passed; [4] if the protester's delivery of its
proposal occurred after the sheet of paper was time-stamped, it
was late. The most probative evidence of the sequence of these
events is the statement of the daughter, who undisputedly was
actually in Suite 100 during the entire time in question, and
was the only person who saw both the contracting officer
time-stamp the piece of paper at 4:01, and SRC deliver its
proposal. As noted, the daughter states that she observed the
contracting officer and chief return from the porch and
time-stamp the sheet of paper, and that it was not until after
this happened, and the agency officials left Suite 100, that she
observed SRC's representative enter with the firm's proposal.
(States
Roofing Corporation, B-286052, November 8, 2000)
Here, the contracting officer
denies that the agency received the protester's quote, and the
protester's facsimile transmission report is inadequate, by
itself, to establish receipt by the agency. This is so because
our Office does not regard a transmission record within the
protester's control, such as this one, to be definitive evidence
of transmission, since such a record can be created or altered
to support a protester's contention. (W&W
Logistics, B-283998, December 30, 1999)
Agency reasonably rejected
protester's hand-delivered proposal as late where the protester
significantly contributed to the late receipt of the proposal by
failing to allow sufficient time for timely delivery of the
proposal. (Integrated
Support Systems inc, B-283137.2, September 10, 1999)
|